SlideShare a Scribd company logo
1 of 82
TRANSPORTATION
(SPECIALLY STRUCTURED LINEAR PROGRAMS)
                SUBMITTED BY:

              Transportation 1

                 Escober, Mark
           de la Cruz, Edghan Bryan

              Transportation 2

               Kali, Norhasim
              Lagasca, Michelle
              Ronidel, Roderick
TRANSPORTATION AND ASSIGNMENT PROBLEM

   Transportation problem is concerned with selecting routes in a
    product – distribution networks among manufacturing plants to
    distribution warehouse or among regional warehouses to local
    distribution outlets.

   Assignment problem involves assigning employees to tasks,
    salesperson to towns, contract to bidders or jobs to plants.
TRANSPORTATION METHOD
The Transportation Problem:
(demand equals supply)

   Let us consider the case of the Bulacan Gravel Company , which has received
    a contract to supply gravel for three road projects located in the towns of
    Marilao, Bocaue and Balagtas. Construction engineers have estimated the
    amount of gravel which be needed at three construction projects:




                                                 Weekly Requirement
             Project       Location                 Truckloads
                A           Marilao                      72
                B           Bocaue                       102
                C          Balagtas                      41
     Total                                               215
The Transportation Problem:
(demand equals supply)
    The Bulacan Gravel Company has three gravel plants located in the towns of San
    Rafael, San Ildefonso and San Miguel. The gravel required for the construction
    projects can be supplied by these three plants. Bulacan’s chief dispatcher has
    calculated the amounts of gravel which can be supplied by each plant:

                                                       Amount Available/Week
        Plant                   Location                     Truckloads
          W                    San Rafael                       56
          X                   San Ildefonso                     82
          Y                    San Miguel                       77
                  Total                                         215



   The company has computed the delivery costs from each plant to each project site.

                  Cost per Truckload
        From              To project A        To project B        To project C
       Plant W                P4                  P8                      P8
        Plant X               16                  24                      16
        Plant Y                8                  16                      24
Gravel plants, road construction projects and transportation costs for Bulacan Gravel
Company

                                                   P4        Plant W (San Rafael)
                 Project A                                    56 loads available
                  (Marilao)
             72 loads required



                                                        P8
                                                                         P16
                                       Project B
                                       (Bocaue)                        P24 Plant X ( San Ildefonso)
                                       102 loads                                    82 loads available
                                        required
                 P8
                                                                P8
                                                                                    P16
                             P16

                                                                   Project C
              Plant Y (San Miguel)            P24                  (Balagtas)
               77 loads available                                   41 loads
                                                                    required
   The objective is to minimize the total transportation cost:


           4WA + 8WB + 8WC + 16XA + 24XB + 16XC + 8YA + 16YB + 24YC


   There are three “origin constraints” which say that Bulacan cannot ship out
    more gravel than they have:

                      WA + WB + WC < 56: Plant W
                      XA + XB + XC < 82 : Plant X
                      YA + YB + YC < 77: Plant Y


   There are three “destination constraints”, which say that each project must
    receive the gravel it requires:

                      WA + XA + YA > 72: Project A
                      WB + XB + YB > 102: Project B
                      WC +XC + YC >    41:Project C
     Using it all together, we get the final linear programming model:

minimize


    4WA + 8WB + 8WC + 16XA + 24XB + 16XC + 8YA + 16YB + 24YC

subject to
  WA +     WB +   WC                                                        < 56: Plant W
                           XA +     XB +     XC                             < 82: Plant X
                                                      YA +    YB +       YC < 77: Plant Y
     WA                +   XA                     +   YA                    > 72: Project A
                                                                            >
           WB                   +   XB                   +    YB            102: Project B
                  WC                     +   XC                  +       YC > 41: Project C
                                                           All Variables    > 0
STEP 1: Set up the transportation table

STEP 2: Develop an initial solution

STEP 3: Test the solution for improvement

STEP 4: Develop the improved solution
C

                                           Plant
           To   Project Project Project
    From                                  Capacit
                   A       B       C
                                             y
     Plant
                                            56
      W

A   Plant X                   E             82        B

    Plant Y                                 77

    Project                                     215
    Requireme     72     102      41      215
       nts




                           D
To                                                  Plant
            Project A      Project B       Project C
From                                                      Capacity
            WA         4   WB          8    WC        8
Plant W                                                         56
             X1             X2              X3
                       1               2              1
            XA             XB              XC
 Plant X               6               4              6         82
             X4             X5             X6
                                       1              2
            YA         8   YB              YC
 Plant Y                               6              4         77
             X7             X8              X9
 Project
                  72             102             41              215
Requirem                                                  215
  ents
1   WA        4       2


         +
         -
         X1       3
To                                                Plant
            Project A     Project B       Project C
From                                                    Capacity
            WA        4   WB          8    WC       8
Plant W                                                       56
            56
                      1               2             1
            XA            XB              XC
 Plant X              6               4             6         82
            16             66
                                      1             2
            YA        8   YB              YC
 Plant Y                              6             4         77
                           36             41
 Project
                 72             102            41              215
Requirem                                                215
  ents
From           To              Quantity,

Plant        Project        truckloads/week

 W             A                  56

 X             A                  16

 X             B                  66

 Y             B                  36

 Y             C                  41

                                 215




  Used Squares = Total Rim Requirements – 1
                5=6-1
   Total Cost of the Initial Solution


             Source - destination Quantity       Unit      Total
                Combination      Shipped x Cost =          Cost
                     WA             56       P      4       224.00
                     XA             16             16       256.00
                     XB             66             24     1,584.00
                     YB             36             16       576.00
                     YC             41         24           984.00
                           Total Transporation
            Cost                                        P 3,624.00



   Is this the best solution?
   Choose the unused square to be evaluated

   Beginning with the selected unused square, traced a closed path
    (moving horizontally and vertically only)

   Assign plus (+) and minus (-) signs alternately at each corner square of
    the closed path

   Determine the net change in costs as a result of the changes made in
    tracing the path

   Repeat the above steps until an improvement index has been
    determined for each unused squares
To                                                Plant
            Project A     Project B       Project C
From                                                    Capacity
            WA        4   WB          8    WC       8
Plant W                                                       56
            56 _                  +
                      1               2             1
            XA            XB              XC
 Plant X              6               4             6         82
            16 +           66     _
                                      1             2
            YA        8   YB              YC
 Plant Y                              6             4         77
                           36             41
 Project
                 72             102            41              215
Requirem                                                215
  ents
Addition to cost: From plant W to project B    P 8
                  From plant X to project A     16     P24

Reduction to cost: From plant W to project A   P 4
                   From plant X to project B    24      28
                                                       -P4

 Improvement index for square WB = WB – WA + XA – XB
                               = P8 - P4 + P16 - P24
                             WB = -P4
Improvement index for WC = WC – WA + XA – XB + YB – YC
                         = P8 – 4P + P16 -P24 + P16 - P 24
                      WC = - P 12
Improvement index for XC= XC – XB + YB – YC
                        = P16 - P24 + P16 - P24
                      XC = -P16
Improvement index for YA = YA - XA + XB – YB
                         = P8 - P16 + P24 - P16
                       YA = P 0
To                                                 Plant
            Project A     Project B       Project C
From                                                     Capacity
            WA        4   WB          8    WC        8
Plant W                                                        56
            56            -4               -12
                      1               2              1
            XA            XB              XC
 Plant X              6               4              6         82
            16             66             -16
                                      1              2
            YA        8   YB              YC
 Plant Y                              6              4         77
            0              36             41
 Project
                 72             102             41              215
Requirem                                                 215
  ents
24                16

XB            XC
                   `
6
     _
6                  +


         16                24
YB            YC


3                      4
     +             _
6                      1
XB            XC
66 - 41        0 + 41
                        `

          2                 4
          5                 1

 YB           YC
36 + 41       41 - 41


          7
          7                 0
To                                                Plant
            Project A     Project B       Project C
From                                                    Capacity
            WA        4   WB          8    WC       8
Plant W                                                       56
            56
                      1               2             1
            XA            XB              XC
 Plant X              6               4             6         82
            16             25             41
                                      1             2
            YA        8   YB              YC
 Plant Y                              6         n   4         77
                           77
 Project
                 72             102            41              215
Requirem                                                215
  ents
Shipping     Quantity        Unit       Total
Assignments   Shipped     x   Cost   =   Cost
    WA               56       P4         P224
    XA               16       16          256
    XB               25       24          600
    XC               41       16          656
    YB               77       16         1,232
                                         P 2,968
Unused              Closed               Computation of
Squares              path              Improvement Index
  WB      + WB - WA + XA - XB     +    8 - 4 + 16 - 24 = - 4
  WC      + WC - WA + XA - XC     +    8 - 4 + 16 - 16 = + 4
  YA      + YA   - XA + XB - YB   +    8 - 16 + 24 - 16 = 0
  YC      + YC   - XC + XB - YB   +   24 - 16 + 24 -16 = + 16
WA              WB
56 - 25          0 + 25
                          `

            3                 2
            1                 5

 XA             XB
16 + 25 =       25 - 25


            4
            1                 0
To                                                Plant
            Project A     Project B       Project C
From                                                    Capacity
            WA        4   WB          8    WC       8
Plant W                                                       56
            31            25
                      1               2             1
            XA            XB              XC
 Plant X              6               4             6         82
            41                            41
                                      1             2
            YA        8   YB              YC
 Plant Y                              6         n   4         77
                           77
 Project
                 72             102            41              215
Requirem                                                215
  ents
Shipping     Quantity       Unit        Total

Assignments   Shipped    x   Cost   =    Cost

    WA          31           P4          P124

    WB          25             8          200

    XA          41           16           656

    XC          41           16           656

    YB          77           16          1,232

                                        P 2,868
Unused             Closed                   Computation of
Squares             path                 Improvement Index
  WC      +WC - WA + XA - XC      +8 – 4 + 16 – 16 = + 4
  XB      +XB - WB + WA - XA      +24 – 8 + 4 – 16 = + 4
  YA      +YA - WA + WB – YB      +8 – 4 + 8 – 16 = - 4
            YC - YB + WB - WA +
  YC      + XA - XC               +    24 – 16 + 8 – 4 + 16 – 16 = + 12
To                                                Plant
            Project A     Project B       Project C
From                                                    Capacity
            WA        4   WB          8    WC       8
Plant W                                                       56
                          56
                      1               2             1
            XA            XB              XC
 Plant X              6               4             6         82
            41                            41
                                      1             2
            YA        8   YB              YC
 Plant Y                              6         n   4         77
            31             46
 Project
                 72             102            41              215
Requirem                                                215
  ents
Unused                Closed                       Computation of
Squares                 path                    Improvement Index
  WA      +WA – YA + YB - WB             +4 – 8 + 16 – 8 = + 4
  WC      +WC – XC + XA – YA + YB - WB   +8 – 16 + 16 – 8 + 16 – 8 = + 8
  XB      +XB – YB + YA - XA             +24 – 16 + 8 – 16 = 0
  YC      +YC – XC + XA - YA             +24 – 16 + 16 – 8 = +16
Shipping     Quantity         Unit            Total

Assignments   Shipped     x    Cost    =       Cost

    WB          56              P8             P448

    XA          41               16             656

    XC          41              16              656

    YA          31                8             248

    YB          46              16              736

                  Total Transportation Cost   P 2,744
R i = value assigned to row i

K = value assigned to row j
   j




C i j = cost in square ij ( the square at the intersection
             of row i and column j
Kj                 K1
Ri                                    K2            K3
                                                              Plant
                 To   Project    Project       Project
                                                             Capacit
          From           A          B             C
                                                                y
                       WA    4   WB        8   WC        8
R1        Plant W       5
                                                                   56
                        6
                             1             2             1
                      XA         XB        4    XC       6
R2        Plant X      1
                             6
                                 6                                 82
                       6         6
                                           1             2
                       YA    8   YB        6   YC
R3        Plant Y                3             4
                                                         4         77
                                 6             1
          Project                                                   215
          Requirem      72           102            41
                                                             215
            ents
R1   + K1       To solve the five equations, then we proceed as follows. If R1 = 0, then
         =4
R2   + K1               R1+ K1= 4                   R2 + K2 = 24
         = 16
R2   +K  = 24           0 + K1 = 4                  12 + K2 = 24
        2
R3   +K  = 16           K1 = 4                      K2 = 12
     + 2                                                                        R3 + K3 = 24
R3    K3 = 24                                                                   4 + K3 = 24
                                                                                K3 = 20
                        R2 + K1 = 16                 R3 + K2 = 16
                        R2 + 4 = 16                  R3 + 12 = 16
                        R2 = 12                      R3 = 4
Kj                K1 = 4        K2 = 12           K3 = 20
Ri
                     To                                               Plant
                          Project       Project        Project
                                                                     Capacit
              From           A             B              C
                                                                        y
                           WA       4   WB         8   WC        8
R1 = 0                                                                     56
              Plant W       5
                            6
                                    1              2             1
R2 =12                    XA        6   XB         4    XC       6
              Plant X      1            6                                  82
                           6            6
                                                   1             2
 R3 = 4                    YA       8   YB         6   YC        4
              Plant Y                   3              4                   77
                                        6              1
              Project                                                       215
              Requirem      72              102             41
                                                                     215
                ents
Unused   C   ij –   Ri – Kj   Improvement
Square                           Index
  12     C12 - R1 – K2            -4
         8 – 0 – 12
  13      C13 - R1 - K3           -12
          8 – 0 - 20
  23      C23 – R2 - K3           -16
         16 – 12 - 20
 31      C31 – R3 – K1            0
          8–4-4
   Traced a close path for the cell having the largest negative
    improvement index

   Placed plus and minus signs at alternative corners of the path
    beginning with a plus sign at the unused square.

   The smallest stone in a negative position on the close path
    indicates the quantity that can be assigned to the unused
    square.

   Finally, the improvement indices for the new solution are
    calculated.
Kj                K1         K2               K3
Ri
                  To                                           Plant
                       Project    Project       Project
                                                              Capacit
           From           A          B             C
                                                                 y
                        WA    4   WB        8   WC        8
R1                                                                  56
           Plant W       5
                         6
                              1             2             1
R2                     XA     6   XB        4   XC        6
           Plant X      1         2             4                   82
                        6         5             1
                                            1             2
 R3                     YA    8   YB        6   YC        4
           Plant Y                7                                 77
                                  7
           Project                                                   215
           Requirem      72           102            41
                                                              215
             ents
Stone square 11:    Stone square 22:
       R1+ K1= 4        R2 + K2 = 24
       0 + K1 = 4        12 + K2 = 24   Stone Square 32:
           K1 = 4         K2 = 12       R3 + K2 = 16
                                        R3 + 12 = 16
Stone square 21:    Stone square 23:    R3 = 4
       R2+ K1= 16       R2 + K3 = 16
       R2+ 4 = 16       12 + K3 = 16
       R2 = 12           K3 = 4
Unused   C   ij –   Ri – Kj   Improvement
Square                           Index

  12     C12 - R1 – K2            -4
          8 – 0 - 12

  13     C13 - R1 – K3            +4
          8–0-4
  31     C31 – R3 – K1             0
          8–4-4

  33     C33 – R3 – K3            +16
         24 – 4 - 4
Kj                K1 = 4        K2 = 8           K3 = 4
Ri
                     To                                                 Plant
                          Project       Project       Project
                                                                       Capacit
              From           A             B             C
                                                                          y
                           WA       4   WB        8   WC           8
R1 = 0                                                                       56
              Plant W       3                2
                            1                5
                                    1             2                1
R2 =12                    XA        6   XB        4   XC           6
              Plant X      4                          4                      82
                           1                          1
                                                  1                2
 R3 = 8                    YA       8   YB        6   YC           4
              Plant Y                   7                                    77
                                        7
              Project                                                         215
              Requirem      72              102            41
                                                                       215
                ents
Unused   C   ij –   Ri – Kj   Improvement
Square                           Index

  13     C13 - R1 – K3            +4
          8–0-4

  22     C22 – R2 – K2            +4
         24 – 12 - 8

  31     C31 – R3 – K1            -4
          8–8-4

  33     C33 – R3 – K3            +12
         24 – 8 - 4
Kj                K1         K2               K3
Ri
                  To                                           Plant
                       Project    Project       Project
                                                              Capacit
           From           A          B             C
                                                                 y
                        WA    4   WB        8   WC        8
R1                                                                  56
           Plant W                     5
                                       6
                              1             2             1
R2                     XA     6   XB        4   XC        6
           Plant X      4                       4                   82
                        1                       1
                                            1             2
 R3                     YA    8   YB        6   YC        4
           Plant Y      3         4                                 77
                        1         6
           Project                                                   215
           Requirem      72           102            41
                                                              215
             ents
Stone square 12:     Stone square 23:
       R1+ K2= 8                         Stone Square 32:
                         R2 + K3 = 16
       0 + K2 = 8                        R3 + K2 = 16
                          16 + K3 = 16
           K2 = 8                        8 + K2 = 16
                           K3 = 0
                                         K2 = 8
Stone square 21:     Stone square 31:
       R2+ K1= 16        R3 + K1 = 8
       R2 + 0 = 16       R3 + 0 = 8
       R2 = 16            R3 = 8
Unused   C          Ri – Kj   Improvement
Is this the Optimal Solution?   Square
                                             ij –
                                                                 Index

                                  11     C11 - R1 – K1            +4
                                          4–0-0

                                  13     C13 – R1 – K3            +8
                                          8–0-0

                                  22     C22 – R2 – K2             0
                                         24 – 16 - 8

                                  33     C33 – R3 – K3            +16
                                         24 – 8 - 0
1. For each solution, compute the R and K values for the table

2. Calculate the improvement indices for all unused squares

3. Select the unused square with the most negative index

4. Trace the closed path for the unused square having the most negative
     index.

5. Develop an improved solution

6. Repeat steps 1 to 5 until an optimal solution has been found.
  Demand Less than Supply
Considering the original Bulacan Gravel Company problem, suppose that
   plant W has a capacity of 76 truckloads for week rather than 56. The
   company would be able to supply 235 truckloads per week. However,
   the project requirements remain the same .
Plant
       To   Project       Project           Project       Dummy
                                                                       Capacit
From           A             B                 C            D
                                                                          y
              WA     4        WB        8             8            0
Plant W                                     WC                           76
               7               4
               2
                      1                 2             1
             XA       6       XB        4    XC       6            0
Plant X                       8                                          82
                              2
                                        1             2
              YA      8       YB        6   YC        4
                                                                   0
Plant Y                       1             4             2                  77
                              6             1             0
Project                                                                      235
Requirem       72                 102            41           20
                                                                       235
  ents

        Total Cost:
        72 x P4 = P 288
         4 x P8 = 32
        82 x P24= 1,968
        16 x P16 = 256
        41 x P24 = 984
        20x P0 =        0
                    P 3,528
Plant
       To   Project       Project           Project       Dummy
                                                                       Capacit
From           A             B                 C            D
                                                                          y
              WA     4        WB        8             8            0
Plant W                                     WC                           76
                              7
                              6
                      1                 2             1
             XA       6       XB        4    XC       6            0
Plant X                       2              4            2              82
                              1              1            0
                                        1             2
              YA      8       YB        6   YC        4
                                                                   0
Plant Y       7                                                              77
                               5
              2
Project                                                                      235
Requirem       72                 102            41           20
                                                                       235
  ents

        Total Cost:
        76 x P8 = P 608
        21 x P24= 504
        41 x P16= 656
        20 x P0 =      0
        72 x P8 = 576
        5x P16 =      80
                    P 2,424
   Demand Greater than Supply
   Assume that project A will require 10 additional truckloads per week
    and that project C estimates additional requirements of 20 truckloads.
    The total project requirements now would be equal to 245 truckloads,
    as opposed to the 215 available from the plants.



                                                                Total Cost:
                                                                56 x P4 = P224
                                                                26 x P16= 416
                                                                56 x P24= 1,344
                                                                46 x P16= 736
                                                                31 x P24= 744
                                                                30 x P 0=     0
                                                                          P 3,464
Total Cost:

56 x P 8 = P 448
21 x P16 = 336
61 x P16 = 976
61 x P 8 = 488
16 x P 16 = 256
30 x P 0 =      0
            P 2,504
   There maybe an excessive number of stone squares in a solution; the
    number of stone squares is greater than the number of rim
    requirements minus 1.

   There may be an insufficient number of stone squares in a solution.
    DEGENERACY IN ESTABLISHING AN INITIAL SOLUTION


           To                                              Plant
                Project A     Project B     Project C
    From                                                  Capacity
                WA        4   WB        8    WC       8
    Plant W                                                     55
                35            20
                          1             2             1
                XA            XB            XC
    Plant X               6             4             6         25
                16            25
                                        1             2
                YA        8   YB            YC
    Plant Y                             6             4         35
                                            35
 Project
                     35            45            35              115
Requirem                                                  115
  ents
To                                              Plant
            Project A     Project B     Project C
From                                                  Capacity
            WA        4   WB        8    WC       8
Plant W                                                     55
            35            20
                      1             2             1
            XA            XB            XC
 Plant X              6             4             6         25
            16            25            0
                                    1             2
            YA        8   YB            YC
 Plant Y                            6             4         35
                                        35
 Project
                 35            45            35              115
Requirem                                              115
  ents
To                                     Plant
                    A         B          C
From                                             Capacity
                        9          8         5
   W                                                   25

                        6          8         4
       X                                               35

                        7          6         9
       Y                                               40

 Project
                   30         25        45              100
Requirem                                         100
  ents
           TRANSPORTATION TABLE FOR SUPER FERRY SHIPPING
Shipping    Quantity    x   Unit   = Total
Assignments   Shipped         Cost     Cost

    WC          25             5          P125
    WX          15             6           90
    WC          20             4           80

    YA          15             7           105
    YB          25             6           150
              Total Transportation Cost   P550
Shipping    Quantity   x   Unit     = Total
    Assignments   Shipped        Cost       Cost

        WA           25           9          P225

        XA            5           6           30

        XB           25           8          200
        XC            5           4          20

        YC           40           9           360
              Total Transportation Cost      P835
0
Shipping     Quantity   X   Unit   =    Total
    Assignments    Shipped        Cost        Cost

        WA            15           9          P135

        WC            10           5            50

        XC            35           4           140

        YA            15           7           105
        YB            25           6           150
                  Total Transportation Cost   P580
0
Opportunity Costs for the first allocation


    Row W
    Row X




      First Allocation using the VAM (Vogel Approximation Method)




0
 Opportunity costs for the
        Second allocation




                Second Allocation
               Using the VAM

0
 Opportunity costs for the
        Third allocation




           Second Allocation
          Using the VAM


0
•THE ASSIGNMENT PROBLEM
•THE ASSIGNMENT PROBLEM
   The Meycauayan Machine Shop does custom metalworking for a
    number of local plants. Meycauayan currently has three jobs to be done
    (let us symbolize them A, B and C). Meycauayan also has three
    machines on which to do the work (X, Y, and Z).
   Anyone of the jobs can be processed completely on any of the
    machines. Furthermore, the cost of processing any job on any machine
    is known. The assignment of jobs to machine must be on one-to-one
    basis; that is, each job must be assigned exclusively to one and only
    one machine. T jobs to the objective is to assign the jobs to the
    machines so as to minimize the cost.

                                  Machine                 Total
             Job         X           Y           Z

              A          P25        P31         P35         91

              B          15          20         24          59

              C          22          19         17          58

            Total        62          70         76         208
STEP 1: Determine the opportunity- cost table
    Column X            Column Y          Column Z

    25-15=10            31-19 = 12       35 – 17 = 18        Step 1; part a
    15-15 =0            20 – 19 = 1      24 – 17 = 7

    22-15 = 7           19 – 19 = 0      17 – 17 = 0

                                                Job     X           Y         Z

                 Computations                  A       10         12         18

                                                B       0           1         7

                                                C       7           0         0
Step 1; part b                  Computations:
                                                    X           Y             Z

                                      Row A   10 – 10 = 0   12 – 10 = 2   18 – 10 = 8

                                      Row B    0–0=0         1–0=1         7–0=7

                                      Row C    7–0=7         0–0=0         0–0=0




    STEP 2: Determine whether an optimal assignment can be made




                                     Line 1


               Line 2



0
STEP 3: Revise the total opportunity-cost table




                                                        Computations:
                                                           0       2–1=1   8–1=7     a) Subtract
                                                                                     lowest number
                                                           0       1–1=0   7 – 1 = 6 from all uncovered
                                                                                     number
                                                 7+1=      8           0       0        Line 1

                       b) Add same smallest number to
                                                         Line 2
                       numbers lying at the intersection
                       of two lines



      Job       X     Y          Z               revised opportunity
                                                 cost table
       A        0     1          7

       B        0     0          6      Line 2

       C        8     0          0      Line 3

             Line 1


0
Total Cost:

    Assignment    Cost
    A to X        P25
    B to Y         20
    C to Z         17
                  P62




0
•MAXIMIZATION PROBLEMS
TRANSPORTATION FOR MAXIMIZATION PROBLEMS
       Juan dela Cruz is Marketing Vice President with the Malolos Company. Malolos is
        planning to expand its sales of computer software into new towns – Angat, Norzagaray,
        and Baliuag. It has been determined that 20, 15 , and 30 salespersons will be required
        to service each of the three areas, respectively. The company recently hired 65 new
        salespersons to cover these areas, and based on their experience and prior sales
        performance, the new hires have been classified as Type A, B, or C salesperson.
        Depending upon the regions to which each of the three types are assigned, Malolos
        estimates the following annual revenues per salesperson:


                                                         Annual Revenues
               Type       Number of
                         Salespersons      Angat        Norzagaray           Baliuag
                           available

                A             24          P100,000       120,000             130,000

                B             27             90,000      106,000             126,000

                C             14             84,000       98,000             120,000

       Dave wishes to determine how many salespersons of each type to assign to the three
        regions so that total annual revenues will be maximized.




0
 evaluation of unused squares




0
 evaluation of unused squares




0
Salesper   Territor   Numbe     Annual
    son Type      y          r     Revenue
                          Assign
                            ed
       A        Angat       9      P900, 000

       A       Norzaga      15     1,800,000
                 ray

       B        Angat       11      990,000

       B       Baliuag      16     2,016,000

       C       Baliuag      14     1,680,000
                                   P7,386,000


0
STEP 1: Select the highest and second-highest revenue
    alternatives from among those not already allocated. The
    difference between these two revenues will be the
    opportunity cost for the row or column.

    STEP 2: Scan these opportunity-cost figures and identify the
    row or columns with the largest opportunity cost.

    STEP 3: Allocate as many units as possible to this row or
    column in the square with the greatest revenue.




0
ASSIGNMENT FOR METHOD OF
    MAXIMIZATION PROBLEMS
    Josefa Santos manages the Aves Car Rental Agency. This year, she
    plans to purchase five new automobiles to replace five older
    vehicles. The older vehicles are to be sold at auction. Josefa has
    solicited bid from five individuals, each of whom wishes to purchase
    only one vehicle but has agreed to make a sealed bid on each of
    the five. The bids are as follows:
                                        Automobile
     Buyer       Ford     Honda      Kia      Mitsubishi       Toyota

     Amalia     P 3,000   P 2,500   P 3,300   P 2,600        P 3,100

      Berto      3,500     3,000     2,800    2,800           3,300

     Carlos      2,800     2,900     3,900    2,300           3,600

     Dolores     3,300     3,100     3,400    2,900           3,500

    Edgardo      2,800     3,500     3,600    2,900           3,000




0
•REGRET VALUES FOR AUTOMOBILE
                                            Automobile
     Buyer      Ford    Honda         Kia        Mitsubishi    Toyota

    Amalia      500      1000         600             300          500

     Berto       0       500       1100              100       300

     Carlos     700      600           0             600           0

    Dolores     200      400          500             0        100

    Edgardo     700          0        300             0        600


              •OPTIMAL ASSIGNMENT OF BID AWARDS
                                            Automobile
    Buyer      Ford    Honda     Kia           Mitsubishi     Toyota

    Amalia     200      700      200             0            100

     Berto      0       500      1000           100           200

    Carlos     800      700       0             700            0

    Dolores    200      400      400             0            0

    Edgardo    700       0       200             0            500
0
•OPTIMAL SOLUTION TO Aves CAR RENTAL AGENCY
                          Buyer                Bid Accepted              Bid
                                                                        Price
                          Amalia                 Mitsubishi            P 2,600

                           Berto                    Ford                3,500

                          Carlos                     Kia                3,900

                          Dolores                  Toyota               3,500

                         Edgardo                   Honda                3,500
                                                                      P 17,000




    Reference: Quantitative Approaches to Management, 8th edition; Richard I. Levin, et. al

0
Thank You

More Related Content

What's hot

General Ledger and Financial Reporting System (GLFRS)
General Ledger and Financial Reporting System (GLFRS)General Ledger and Financial Reporting System (GLFRS)
General Ledger and Financial Reporting System (GLFRS)Osareme Erhomosele
 
Decision Theory
Decision TheoryDecision Theory
Decision Theorykzoe1996
 
Philippine Government Budgetary Processes
 Philippine Government Budgetary Processes Philippine Government Budgetary Processes
Philippine Government Budgetary ProcessesChristine Liz Jimenea
 
200844797 rsh-qam11-tif-01-doc
200844797 rsh-qam11-tif-01-doc200844797 rsh-qam11-tif-01-doc
200844797 rsh-qam11-tif-01-docFiras Husseini
 
352735344 rsh-qam11-tif-10-doc
352735344 rsh-qam11-tif-10-doc352735344 rsh-qam11-tif-10-doc
352735344 rsh-qam11-tif-10-docFiras Husseini
 
Ap cash-cash-equivalents-q
Ap cash-cash-equivalents-qAp cash-cash-equivalents-q
Ap cash-cash-equivalents-qdodinadyosa
 
Linear programming 1
Linear programming 1Linear programming 1
Linear programming 1Rezaul Karim
 
transportation and assignment models
transportation and assignment modelstransportation and assignment models
transportation and assignment modelsAnne Lee
 
Challenges Encountered and Insights of the Bureau of Fire Protection Personne...
Challenges Encountered and Insights of the Bureau of Fire Protection Personne...Challenges Encountered and Insights of the Bureau of Fire Protection Personne...
Challenges Encountered and Insights of the Bureau of Fire Protection Personne...Associate Professor in VSB Coimbatore
 
352735322 rsh-qam11-tif-03-doc
352735322 rsh-qam11-tif-03-doc352735322 rsh-qam11-tif-03-doc
352735322 rsh-qam11-tif-03-docFiras Husseini
 

What's hot (20)

Rsh qam11 ch10 ge
Rsh qam11 ch10 geRsh qam11 ch10 ge
Rsh qam11 ch10 ge
 
General Ledger and Financial Reporting System (GLFRS)
General Ledger and Financial Reporting System (GLFRS)General Ledger and Financial Reporting System (GLFRS)
General Ledger and Financial Reporting System (GLFRS)
 
Decision Theory
Decision TheoryDecision Theory
Decision Theory
 
Installment Sales Method (Income Taxation
Installment Sales Method (Income TaxationInstallment Sales Method (Income Taxation
Installment Sales Method (Income Taxation
 
5. advance topics in lp
5. advance topics in lp5. advance topics in lp
5. advance topics in lp
 
Philippine Government Budgetary Processes
 Philippine Government Budgetary Processes Philippine Government Budgetary Processes
Philippine Government Budgetary Processes
 
200844797 rsh-qam11-tif-01-doc
200844797 rsh-qam11-tif-01-doc200844797 rsh-qam11-tif-01-doc
200844797 rsh-qam11-tif-01-doc
 
352735344 rsh-qam11-tif-10-doc
352735344 rsh-qam11-tif-10-doc352735344 rsh-qam11-tif-10-doc
352735344 rsh-qam11-tif-10-doc
 
Ap cash-cash-equivalents-q
Ap cash-cash-equivalents-qAp cash-cash-equivalents-q
Ap cash-cash-equivalents-q
 
Rsh qam11 ch09 ge
Rsh qam11 ch09 geRsh qam11 ch09 ge
Rsh qam11 ch09 ge
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Linear programming 1
Linear programming 1Linear programming 1
Linear programming 1
 
transportation and assignment models
transportation and assignment modelstransportation and assignment models
transportation and assignment models
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Decision theory Problems
Decision theory ProblemsDecision theory Problems
Decision theory Problems
 
Challenges Encountered and Insights of the Bureau of Fire Protection Personne...
Challenges Encountered and Insights of the Bureau of Fire Protection Personne...Challenges Encountered and Insights of the Bureau of Fire Protection Personne...
Challenges Encountered and Insights of the Bureau of Fire Protection Personne...
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
352735322 rsh-qam11-tif-03-doc
352735322 rsh-qam11-tif-03-doc352735322 rsh-qam11-tif-03-doc
352735322 rsh-qam11-tif-03-doc
 
5. transportation problems
5. transportation problems5. transportation problems
5. transportation problems
 

Viewers also liked

Decision science
Decision scienceDecision science
Decision scienceIkram Vora
 
Studying hidden drivers of decision making through implicit research technolo...
Studying hidden drivers of decision making through implicit research technolo...Studying hidden drivers of decision making through implicit research technolo...
Studying hidden drivers of decision making through implicit research technolo...Merlien Institute
 
Zonas. cuadro resumen
Zonas. cuadro resumenZonas. cuadro resumen
Zonas. cuadro resumenEnrique Pena
 
Managerial Decision Making - MANAGEMENT PROCESS
Managerial Decision Making - MANAGEMENT PROCESSManagerial Decision Making - MANAGEMENT PROCESS
Managerial Decision Making - MANAGEMENT PROCESSRamasubramanian H (HRS)
 
Basic Concepts Of Economics
Basic  Concepts Of  EconomicsBasic  Concepts Of  Economics
Basic Concepts Of EconomicsGenny Nazal
 
Psicologia Del Consumidor
Psicologia Del ConsumidorPsicologia Del Consumidor
Psicologia Del Consumidorpsandrea
 
Los 52 mejores libros para emprendedores
Los 52 mejores libros para emprendedoresLos 52 mejores libros para emprendedores
Los 52 mejores libros para emprendedoresjosejcerpa
 
Introduction to economics
Introduction to economicsIntroduction to economics
Introduction to economicsMichael Noel
 

Viewers also liked (9)

Decision science
Decision scienceDecision science
Decision science
 
Studying hidden drivers of decision making through implicit research technolo...
Studying hidden drivers of decision making through implicit research technolo...Studying hidden drivers of decision making through implicit research technolo...
Studying hidden drivers of decision making through implicit research technolo...
 
Zonas. cuadro resumen
Zonas. cuadro resumenZonas. cuadro resumen
Zonas. cuadro resumen
 
Managerial Decision Making - MANAGEMENT PROCESS
Managerial Decision Making - MANAGEMENT PROCESSManagerial Decision Making - MANAGEMENT PROCESS
Managerial Decision Making - MANAGEMENT PROCESS
 
11-Management Science
11-Management Science11-Management Science
11-Management Science
 
Basic Concepts Of Economics
Basic  Concepts Of  EconomicsBasic  Concepts Of  Economics
Basic Concepts Of Economics
 
Psicologia Del Consumidor
Psicologia Del ConsumidorPsicologia Del Consumidor
Psicologia Del Consumidor
 
Los 52 mejores libros para emprendedores
Los 52 mejores libros para emprendedoresLos 52 mejores libros para emprendedores
Los 52 mejores libros para emprendedores
 
Introduction to economics
Introduction to economicsIntroduction to economics
Introduction to economics
 

Recently uploaded

a presentation for foreigners about how to travel in Germany.
a presentation for foreigners about how to travel in Germany.a presentation for foreigners about how to travel in Germany.
a presentation for foreigners about how to travel in Germany.moritzmieg
 
It’s Time Get Refresh Travel Around The World
It’s Time Get Refresh Travel Around The WorldIt’s Time Get Refresh Travel Around The World
It’s Time Get Refresh Travel Around The WorldParagliding Billing Bir
 
question 2: airplane vocabulary presentation
question 2: airplane vocabulary presentationquestion 2: airplane vocabulary presentation
question 2: airplane vocabulary presentationcaminantesdaauga
 
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)Mazie Garcia
 
Phil....National-Capital-Region-NCR.pptx
Phil....National-Capital-Region-NCR.pptxPhil....National-Capital-Region-NCR.pptx
Phil....National-Capital-Region-NCR.pptxDitasDelaCruz
 
How Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersHow Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersMakena Coast Charters
 
Paragliding Billing Bir at Himachal Pardesh
Paragliding Billing Bir at Himachal PardeshParagliding Billing Bir at Himachal Pardesh
Paragliding Billing Bir at Himachal PardeshParagliding Billing Bir
 
Where to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdWhere to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdusmanghaniwixpatriot
 
Revolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI UpdateRevolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI Updatejoymorrison10
 
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)Escort Service
 
Authentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptxAuthentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptxGregory DeShields
 
Inspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodInspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodKasia Chojecki
 
Sicily Holidays Guide Book: Unveiling the Treasures of Italy's Jewel
Sicily Holidays Guide Book: Unveiling the Treasures of Italy's JewelSicily Holidays Guide Book: Unveiling the Treasures of Italy's Jewel
Sicily Holidays Guide Book: Unveiling the Treasures of Italy's JewelTime for Sicily
 

Recently uploaded (15)

a presentation for foreigners about how to travel in Germany.
a presentation for foreigners about how to travel in Germany.a presentation for foreigners about how to travel in Germany.
a presentation for foreigners about how to travel in Germany.
 
It’s Time Get Refresh Travel Around The World
It’s Time Get Refresh Travel Around The WorldIt’s Time Get Refresh Travel Around The World
It’s Time Get Refresh Travel Around The World
 
question 2: airplane vocabulary presentation
question 2: airplane vocabulary presentationquestion 2: airplane vocabulary presentation
question 2: airplane vocabulary presentation
 
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
 
Phil....National-Capital-Region-NCR.pptx
Phil....National-Capital-Region-NCR.pptxPhil....National-Capital-Region-NCR.pptx
Phil....National-Capital-Region-NCR.pptx
 
How Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersHow Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s Waters
 
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
 
Paragliding Billing Bir at Himachal Pardesh
Paragliding Billing Bir at Himachal PardeshParagliding Billing Bir at Himachal Pardesh
Paragliding Billing Bir at Himachal Pardesh
 
Where to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdWhere to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasd
 
Revolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI UpdateRevolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI Update
 
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
 
Authentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptxAuthentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptx
 
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
 
Inspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodInspirational Quotes About Italy and Food
Inspirational Quotes About Italy and Food
 
Sicily Holidays Guide Book: Unveiling the Treasures of Italy's Jewel
Sicily Holidays Guide Book: Unveiling the Treasures of Italy's JewelSicily Holidays Guide Book: Unveiling the Treasures of Italy's Jewel
Sicily Holidays Guide Book: Unveiling the Treasures of Italy's Jewel
 

Final powerpoint decision science

  • 1. TRANSPORTATION (SPECIALLY STRUCTURED LINEAR PROGRAMS) SUBMITTED BY: Transportation 1 Escober, Mark de la Cruz, Edghan Bryan Transportation 2 Kali, Norhasim Lagasca, Michelle Ronidel, Roderick
  • 2. TRANSPORTATION AND ASSIGNMENT PROBLEM  Transportation problem is concerned with selecting routes in a product – distribution networks among manufacturing plants to distribution warehouse or among regional warehouses to local distribution outlets.  Assignment problem involves assigning employees to tasks, salesperson to towns, contract to bidders or jobs to plants.
  • 4. The Transportation Problem: (demand equals supply)  Let us consider the case of the Bulacan Gravel Company , which has received a contract to supply gravel for three road projects located in the towns of Marilao, Bocaue and Balagtas. Construction engineers have estimated the amount of gravel which be needed at three construction projects: Weekly Requirement Project Location Truckloads A Marilao 72 B Bocaue 102 C Balagtas 41 Total 215
  • 5. The Transportation Problem: (demand equals supply)  The Bulacan Gravel Company has three gravel plants located in the towns of San Rafael, San Ildefonso and San Miguel. The gravel required for the construction projects can be supplied by these three plants. Bulacan’s chief dispatcher has calculated the amounts of gravel which can be supplied by each plant: Amount Available/Week Plant Location Truckloads W San Rafael 56 X San Ildefonso 82 Y San Miguel 77 Total 215  The company has computed the delivery costs from each plant to each project site. Cost per Truckload From To project A To project B To project C Plant W P4 P8 P8 Plant X 16 24 16 Plant Y 8 16 24
  • 6. Gravel plants, road construction projects and transportation costs for Bulacan Gravel Company P4 Plant W (San Rafael) Project A 56 loads available (Marilao) 72 loads required P8 P16 Project B (Bocaue) P24 Plant X ( San Ildefonso) 102 loads 82 loads available required P8 P8 P16 P16 Project C Plant Y (San Miguel) P24 (Balagtas) 77 loads available 41 loads required
  • 7. The objective is to minimize the total transportation cost: 4WA + 8WB + 8WC + 16XA + 24XB + 16XC + 8YA + 16YB + 24YC  There are three “origin constraints” which say that Bulacan cannot ship out more gravel than they have: WA + WB + WC < 56: Plant W XA + XB + XC < 82 : Plant X YA + YB + YC < 77: Plant Y  There are three “destination constraints”, which say that each project must receive the gravel it requires: WA + XA + YA > 72: Project A WB + XB + YB > 102: Project B WC +XC + YC > 41:Project C
  • 8. Using it all together, we get the final linear programming model: minimize 4WA + 8WB + 8WC + 16XA + 24XB + 16XC + 8YA + 16YB + 24YC subject to WA + WB + WC < 56: Plant W XA + XB + XC < 82: Plant X YA + YB + YC < 77: Plant Y WA + XA + YA > 72: Project A > WB + XB + YB 102: Project B WC + XC + YC > 41: Project C All Variables > 0
  • 9. STEP 1: Set up the transportation table STEP 2: Develop an initial solution STEP 3: Test the solution for improvement STEP 4: Develop the improved solution
  • 10. C Plant To Project Project Project From Capacit A B C y Plant 56 W A Plant X E 82 B Plant Y 77 Project 215 Requireme 72 102 41 215 nts D
  • 11. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 X1 X2 X3 1 2 1 XA XB XC Plant X 6 4 6 82 X4 X5 X6 1 2 YA 8 YB YC Plant Y 6 4 77 X7 X8 X9 Project 72 102 41 215 Requirem 215 ents
  • 12. 1 WA 4 2 + - X1 3
  • 13. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 56 1 2 1 XA XB XC Plant X 6 4 6 82 16 66 1 2 YA 8 YB YC Plant Y 6 4 77 36 41 Project 72 102 41 215 Requirem 215 ents
  • 14. From To Quantity, Plant Project truckloads/week W A 56 X A 16 X B 66 Y B 36 Y C 41 215 Used Squares = Total Rim Requirements – 1 5=6-1
  • 15. Total Cost of the Initial Solution Source - destination Quantity Unit Total Combination Shipped x Cost = Cost WA 56 P 4 224.00 XA 16 16 256.00 XB 66 24 1,584.00 YB 36 16 576.00 YC 41 24 984.00 Total Transporation Cost P 3,624.00  Is this the best solution?
  • 16. Choose the unused square to be evaluated  Beginning with the selected unused square, traced a closed path (moving horizontally and vertically only)  Assign plus (+) and minus (-) signs alternately at each corner square of the closed path  Determine the net change in costs as a result of the changes made in tracing the path  Repeat the above steps until an improvement index has been determined for each unused squares
  • 17. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 56 _ + 1 2 1 XA XB XC Plant X 6 4 6 82 16 + 66 _ 1 2 YA 8 YB YC Plant Y 6 4 77 36 41 Project 72 102 41 215 Requirem 215 ents
  • 18. Addition to cost: From plant W to project B P 8 From plant X to project A 16 P24 Reduction to cost: From plant W to project A P 4 From plant X to project B 24 28 -P4 Improvement index for square WB = WB – WA + XA – XB = P8 - P4 + P16 - P24 WB = -P4
  • 19. Improvement index for WC = WC – WA + XA – XB + YB – YC = P8 – 4P + P16 -P24 + P16 - P 24 WC = - P 12
  • 20. Improvement index for XC= XC – XB + YB – YC = P16 - P24 + P16 - P24 XC = -P16
  • 21. Improvement index for YA = YA - XA + XB – YB = P8 - P16 + P24 - P16 YA = P 0
  • 22. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 56 -4 -12 1 2 1 XA XB XC Plant X 6 4 6 82 16 66 -16 1 2 YA 8 YB YC Plant Y 6 4 77 0 36 41 Project 72 102 41 215 Requirem 215 ents
  • 23. 24 16 XB XC ` 6 _ 6 + 16 24 YB YC 3 4 + _ 6 1
  • 24. XB XC 66 - 41 0 + 41 ` 2 4 5 1 YB YC 36 + 41 41 - 41 7 7 0
  • 25. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 56 1 2 1 XA XB XC Plant X 6 4 6 82 16 25 41 1 2 YA 8 YB YC Plant Y 6 n 4 77 77 Project 72 102 41 215 Requirem 215 ents
  • 26. Shipping Quantity Unit Total Assignments Shipped x Cost = Cost WA 56 P4 P224 XA 16 16 256 XB 25 24 600 XC 41 16 656 YB 77 16 1,232 P 2,968
  • 27. Unused Closed Computation of Squares path Improvement Index WB + WB - WA + XA - XB + 8 - 4 + 16 - 24 = - 4 WC + WC - WA + XA - XC + 8 - 4 + 16 - 16 = + 4 YA + YA - XA + XB - YB + 8 - 16 + 24 - 16 = 0 YC + YC - XC + XB - YB + 24 - 16 + 24 -16 = + 16
  • 28. WA WB 56 - 25 0 + 25 ` 3 2 1 5 XA XB 16 + 25 = 25 - 25 4 1 0
  • 29. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 31 25 1 2 1 XA XB XC Plant X 6 4 6 82 41 41 1 2 YA 8 YB YC Plant Y 6 n 4 77 77 Project 72 102 41 215 Requirem 215 ents
  • 30. Shipping Quantity Unit Total Assignments Shipped x Cost = Cost WA 31 P4 P124 WB 25 8 200 XA 41 16 656 XC 41 16 656 YB 77 16 1,232 P 2,868
  • 31. Unused Closed Computation of Squares path Improvement Index WC +WC - WA + XA - XC +8 – 4 + 16 – 16 = + 4 XB +XB - WB + WA - XA +24 – 8 + 4 – 16 = + 4 YA +YA - WA + WB – YB +8 – 4 + 8 – 16 = - 4 YC - YB + WB - WA + YC + XA - XC + 24 – 16 + 8 – 4 + 16 – 16 = + 12
  • 32. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 56 56 1 2 1 XA XB XC Plant X 6 4 6 82 41 41 1 2 YA 8 YB YC Plant Y 6 n 4 77 31 46 Project 72 102 41 215 Requirem 215 ents
  • 33. Unused Closed Computation of Squares path Improvement Index WA +WA – YA + YB - WB +4 – 8 + 16 – 8 = + 4 WC +WC – XC + XA – YA + YB - WB +8 – 16 + 16 – 8 + 16 – 8 = + 8 XB +XB – YB + YA - XA +24 – 16 + 8 – 16 = 0 YC +YC – XC + XA - YA +24 – 16 + 16 – 8 = +16
  • 34. Shipping Quantity Unit Total Assignments Shipped x Cost = Cost WB 56 P8 P448 XA 41 16 656 XC 41 16 656 YA 31 8 248 YB 46 16 736 Total Transportation Cost P 2,744
  • 35.
  • 36.
  • 37. R i = value assigned to row i K = value assigned to row j j C i j = cost in square ij ( the square at the intersection of row i and column j
  • 38. Kj K1 Ri K2 K3 Plant To Project Project Project Capacit From A B C y WA 4 WB 8 WC 8 R1 Plant W 5 56 6 1 2 1 XA XB 4 XC 6 R2 Plant X 1 6 6 82 6 6 1 2 YA 8 YB 6 YC R3 Plant Y 3 4 4 77 6 1 Project 215 Requirem 72 102 41 215 ents
  • 39. R1 + K1 To solve the five equations, then we proceed as follows. If R1 = 0, then =4 R2 + K1 R1+ K1= 4 R2 + K2 = 24 = 16 R2 +K = 24 0 + K1 = 4 12 + K2 = 24 2 R3 +K = 16 K1 = 4 K2 = 12 + 2 R3 + K3 = 24 R3 K3 = 24 4 + K3 = 24 K3 = 20 R2 + K1 = 16 R3 + K2 = 16 R2 + 4 = 16 R3 + 12 = 16 R2 = 12 R3 = 4
  • 40. Kj K1 = 4 K2 = 12 K3 = 20 Ri To Plant Project Project Project Capacit From A B C y WA 4 WB 8 WC 8 R1 = 0 56 Plant W 5 6 1 2 1 R2 =12 XA 6 XB 4 XC 6 Plant X 1 6 82 6 6 1 2 R3 = 4 YA 8 YB 6 YC 4 Plant Y 3 4 77 6 1 Project 215 Requirem 72 102 41 215 ents
  • 41. Unused C ij – Ri – Kj Improvement Square Index 12 C12 - R1 – K2 -4 8 – 0 – 12 13 C13 - R1 - K3 -12 8 – 0 - 20 23 C23 – R2 - K3 -16 16 – 12 - 20 31 C31 – R3 – K1 0 8–4-4
  • 42. Traced a close path for the cell having the largest negative improvement index  Placed plus and minus signs at alternative corners of the path beginning with a plus sign at the unused square.  The smallest stone in a negative position on the close path indicates the quantity that can be assigned to the unused square.  Finally, the improvement indices for the new solution are calculated.
  • 43. Kj K1 K2 K3 Ri To Plant Project Project Project Capacit From A B C y WA 4 WB 8 WC 8 R1 56 Plant W 5 6 1 2 1 R2 XA 6 XB 4 XC 6 Plant X 1 2 4 82 6 5 1 1 2 R3 YA 8 YB 6 YC 4 Plant Y 7 77 7 Project 215 Requirem 72 102 41 215 ents
  • 44. Stone square 11: Stone square 22: R1+ K1= 4 R2 + K2 = 24 0 + K1 = 4 12 + K2 = 24 Stone Square 32: K1 = 4 K2 = 12 R3 + K2 = 16 R3 + 12 = 16 Stone square 21: Stone square 23: R3 = 4 R2+ K1= 16 R2 + K3 = 16 R2+ 4 = 16 12 + K3 = 16 R2 = 12 K3 = 4
  • 45. Unused C ij – Ri – Kj Improvement Square Index 12 C12 - R1 – K2 -4 8 – 0 - 12 13 C13 - R1 – K3 +4 8–0-4 31 C31 – R3 – K1 0 8–4-4 33 C33 – R3 – K3 +16 24 – 4 - 4
  • 46. Kj K1 = 4 K2 = 8 K3 = 4 Ri To Plant Project Project Project Capacit From A B C y WA 4 WB 8 WC 8 R1 = 0 56 Plant W 3 2 1 5 1 2 1 R2 =12 XA 6 XB 4 XC 6 Plant X 4 4 82 1 1 1 2 R3 = 8 YA 8 YB 6 YC 4 Plant Y 7 77 7 Project 215 Requirem 72 102 41 215 ents
  • 47. Unused C ij – Ri – Kj Improvement Square Index 13 C13 - R1 – K3 +4 8–0-4 22 C22 – R2 – K2 +4 24 – 12 - 8 31 C31 – R3 – K1 -4 8–8-4 33 C33 – R3 – K3 +12 24 – 8 - 4
  • 48. Kj K1 K2 K3 Ri To Plant Project Project Project Capacit From A B C y WA 4 WB 8 WC 8 R1 56 Plant W 5 6 1 2 1 R2 XA 6 XB 4 XC 6 Plant X 4 4 82 1 1 1 2 R3 YA 8 YB 6 YC 4 Plant Y 3 4 77 1 6 Project 215 Requirem 72 102 41 215 ents
  • 49. Stone square 12: Stone square 23: R1+ K2= 8 Stone Square 32: R2 + K3 = 16 0 + K2 = 8 R3 + K2 = 16 16 + K3 = 16 K2 = 8 8 + K2 = 16 K3 = 0 K2 = 8 Stone square 21: Stone square 31: R2+ K1= 16 R3 + K1 = 8 R2 + 0 = 16 R3 + 0 = 8 R2 = 16 R3 = 8
  • 50. Unused C Ri – Kj Improvement Is this the Optimal Solution? Square ij – Index 11 C11 - R1 – K1 +4 4–0-0 13 C13 – R1 – K3 +8 8–0-0 22 C22 – R2 – K2 0 24 – 16 - 8 33 C33 – R3 – K3 +16 24 – 8 - 0
  • 51. 1. For each solution, compute the R and K values for the table 2. Calculate the improvement indices for all unused squares 3. Select the unused square with the most negative index 4. Trace the closed path for the unused square having the most negative index. 5. Develop an improved solution 6. Repeat steps 1 to 5 until an optimal solution has been found.
  • 52.  Demand Less than Supply Considering the original Bulacan Gravel Company problem, suppose that plant W has a capacity of 76 truckloads for week rather than 56. The company would be able to supply 235 truckloads per week. However, the project requirements remain the same .
  • 53. Plant To Project Project Project Dummy Capacit From A B C D y WA 4 WB 8 8 0 Plant W WC 76 7 4 2 1 2 1 XA 6 XB 4 XC 6 0 Plant X 8 82 2 1 2 YA 8 YB 6 YC 4 0 Plant Y 1 4 2 77 6 1 0 Project 235 Requirem 72 102 41 20 235 ents Total Cost: 72 x P4 = P 288 4 x P8 = 32 82 x P24= 1,968 16 x P16 = 256 41 x P24 = 984 20x P0 = 0 P 3,528
  • 54. Plant To Project Project Project Dummy Capacit From A B C D y WA 4 WB 8 8 0 Plant W WC 76 7 6 1 2 1 XA 6 XB 4 XC 6 0 Plant X 2 4 2 82 1 1 0 1 2 YA 8 YB 6 YC 4 0 Plant Y 7 77 5 2 Project 235 Requirem 72 102 41 20 235 ents Total Cost: 76 x P8 = P 608 21 x P24= 504 41 x P16= 656 20 x P0 = 0 72 x P8 = 576 5x P16 = 80 P 2,424
  • 55. Demand Greater than Supply  Assume that project A will require 10 additional truckloads per week and that project C estimates additional requirements of 20 truckloads. The total project requirements now would be equal to 245 truckloads, as opposed to the 215 available from the plants. Total Cost: 56 x P4 = P224 26 x P16= 416 56 x P24= 1,344 46 x P16= 736 31 x P24= 744 30 x P 0= 0 P 3,464
  • 56. Total Cost: 56 x P 8 = P 448 21 x P16 = 336 61 x P16 = 976 61 x P 8 = 488 16 x P 16 = 256 30 x P 0 = 0 P 2,504
  • 57. There maybe an excessive number of stone squares in a solution; the number of stone squares is greater than the number of rim requirements minus 1.  There may be an insufficient number of stone squares in a solution.
  • 58. DEGENERACY IN ESTABLISHING AN INITIAL SOLUTION To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 55 35 20 1 2 1 XA XB XC Plant X 6 4 6 25 16 25 1 2 YA 8 YB YC Plant Y 6 4 35 35 Project 35 45 35 115 Requirem 115 ents
  • 59. To Plant Project A Project B Project C From Capacity WA 4 WB 8 WC 8 Plant W 55 35 20 1 2 1 XA XB XC Plant X 6 4 6 25 16 25 0 1 2 YA 8 YB YC Plant Y 6 4 35 35 Project 35 45 35 115 Requirem 115 ents
  • 60. To Plant A B C From Capacity 9 8 5 W 25 6 8 4 X 35 7 6 9 Y 40 Project 30 25 45 100 Requirem 100 ents TRANSPORTATION TABLE FOR SUPER FERRY SHIPPING
  • 61. Shipping Quantity x Unit = Total Assignments Shipped Cost Cost WC 25 5 P125 WX 15 6 90 WC 20 4 80 YA 15 7 105 YB 25 6 150 Total Transportation Cost P550
  • 62. Shipping Quantity x Unit = Total Assignments Shipped Cost Cost WA 25 9 P225 XA 5 6 30 XB 25 8 200 XC 5 4 20 YC 40 9 360 Total Transportation Cost P835 0
  • 63. Shipping Quantity X Unit = Total Assignments Shipped Cost Cost WA 15 9 P135 WC 10 5 50 XC 35 4 140 YA 15 7 105 YB 25 6 150 Total Transportation Cost P580 0
  • 64. Opportunity Costs for the first allocation Row W Row X First Allocation using the VAM (Vogel Approximation Method) 0
  • 65.  Opportunity costs for the Second allocation  Second Allocation Using the VAM 0
  • 66.  Opportunity costs for the Third allocation  Second Allocation Using the VAM 0
  • 68. •THE ASSIGNMENT PROBLEM  The Meycauayan Machine Shop does custom metalworking for a number of local plants. Meycauayan currently has three jobs to be done (let us symbolize them A, B and C). Meycauayan also has three machines on which to do the work (X, Y, and Z).  Anyone of the jobs can be processed completely on any of the machines. Furthermore, the cost of processing any job on any machine is known. The assignment of jobs to machine must be on one-to-one basis; that is, each job must be assigned exclusively to one and only one machine. T jobs to the objective is to assign the jobs to the machines so as to minimize the cost. Machine Total Job X Y Z A P25 P31 P35 91 B 15 20 24 59 C 22 19 17 58 Total 62 70 76 208
  • 69. STEP 1: Determine the opportunity- cost table Column X Column Y Column Z 25-15=10 31-19 = 12 35 – 17 = 18 Step 1; part a 15-15 =0 20 – 19 = 1 24 – 17 = 7 22-15 = 7 19 – 19 = 0 17 – 17 = 0 Job X Y Z  Computations A 10 12 18 B 0 1 7 C 7 0 0
  • 70. Step 1; part b Computations: X Y Z Row A 10 – 10 = 0 12 – 10 = 2 18 – 10 = 8 Row B 0–0=0 1–0=1 7–0=7 Row C 7–0=7 0–0=0 0–0=0 STEP 2: Determine whether an optimal assignment can be made Line 1 Line 2 0
  • 71. STEP 3: Revise the total opportunity-cost table Computations: 0 2–1=1 8–1=7 a) Subtract lowest number 0 1–1=0 7 – 1 = 6 from all uncovered number 7+1= 8 0 0 Line 1 b) Add same smallest number to Line 2 numbers lying at the intersection of two lines Job X Y Z revised opportunity cost table A 0 1 7 B 0 0 6 Line 2 C 8 0 0 Line 3 Line 1 0
  • 72. Total Cost: Assignment Cost A to X P25 B to Y 20 C to Z 17 P62 0
  • 74. TRANSPORTATION FOR MAXIMIZATION PROBLEMS  Juan dela Cruz is Marketing Vice President with the Malolos Company. Malolos is planning to expand its sales of computer software into new towns – Angat, Norzagaray, and Baliuag. It has been determined that 20, 15 , and 30 salespersons will be required to service each of the three areas, respectively. The company recently hired 65 new salespersons to cover these areas, and based on their experience and prior sales performance, the new hires have been classified as Type A, B, or C salesperson. Depending upon the regions to which each of the three types are assigned, Malolos estimates the following annual revenues per salesperson: Annual Revenues Type Number of Salespersons Angat Norzagaray Baliuag available A 24 P100,000 120,000 130,000 B 27 90,000 106,000 126,000 C 14 84,000 98,000 120,000  Dave wishes to determine how many salespersons of each type to assign to the three regions so that total annual revenues will be maximized. 0
  • 75.  evaluation of unused squares 0
  • 76.  evaluation of unused squares 0
  • 77. Salesper Territor Numbe Annual son Type y r Revenue Assign ed A Angat 9 P900, 000 A Norzaga 15 1,800,000 ray B Angat 11 990,000 B Baliuag 16 2,016,000 C Baliuag 14 1,680,000 P7,386,000 0
  • 78. STEP 1: Select the highest and second-highest revenue alternatives from among those not already allocated. The difference between these two revenues will be the opportunity cost for the row or column. STEP 2: Scan these opportunity-cost figures and identify the row or columns with the largest opportunity cost. STEP 3: Allocate as many units as possible to this row or column in the square with the greatest revenue. 0
  • 79. ASSIGNMENT FOR METHOD OF MAXIMIZATION PROBLEMS Josefa Santos manages the Aves Car Rental Agency. This year, she plans to purchase five new automobiles to replace five older vehicles. The older vehicles are to be sold at auction. Josefa has solicited bid from five individuals, each of whom wishes to purchase only one vehicle but has agreed to make a sealed bid on each of the five. The bids are as follows: Automobile Buyer Ford Honda Kia Mitsubishi Toyota Amalia P 3,000 P 2,500 P 3,300 P 2,600 P 3,100 Berto 3,500 3,000 2,800 2,800 3,300 Carlos 2,800 2,900 3,900 2,300 3,600 Dolores 3,300 3,100 3,400 2,900 3,500 Edgardo 2,800 3,500 3,600 2,900 3,000 0
  • 80. •REGRET VALUES FOR AUTOMOBILE Automobile Buyer Ford Honda Kia Mitsubishi Toyota Amalia 500 1000 600 300 500 Berto 0 500 1100 100 300 Carlos 700 600 0 600 0 Dolores 200 400 500 0 100 Edgardo 700 0 300 0 600 •OPTIMAL ASSIGNMENT OF BID AWARDS Automobile Buyer Ford Honda Kia Mitsubishi Toyota Amalia 200 700 200 0 100 Berto 0 500 1000 100 200 Carlos 800 700 0 700 0 Dolores 200 400 400 0 0 Edgardo 700 0 200 0 500 0
  • 81. •OPTIMAL SOLUTION TO Aves CAR RENTAL AGENCY Buyer Bid Accepted Bid Price Amalia Mitsubishi P 2,600 Berto Ford 3,500 Carlos Kia 3,900 Dolores Toyota 3,500 Edgardo Honda 3,500 P 17,000 Reference: Quantitative Approaches to Management, 8th edition; Richard I. Levin, et. al 0