SlideShare uma empresa Scribd logo
1 de 107
Baixar para ler offline
Regional Convergence in PPP
        MENA PPP Projects Success
               Framework –
    Regional PPP Development Strategy

   3rd Annual ME PPP – Qatar, February 2012




Loay Ghazaleh – Advisor - B. Sc. Civil Eng. , MBA
                                                    1
Presentation Index

MENA PPP Scio - Economic Outlook

MENA PPP Initiatives / Early Successes


PPP Global Adaptation / Learning


PPP Options & Projets Structure


PPP Projets Success Framework

PPP Regional Deveopment Strategy

                                                          2
MENA PPP Socioeconomic Outlook
Balancing Factors or Another Europe in 5 Years !




                                                                          Cash Flow -
                                                     PPP Planning       Lifecycle Costs
                                                    – must comply         – needed for
                                                          to            repayments to
                                                   legislation, poli    prevent delays
                                                       cies and           due to cash
                                                      guidelines           shortages
                                                                  Budget /
                                                               Affordability -
                                                                   Project
                                                               commitments
                                                             framework to be
                                                              reflected in the
                                                                   budget

                                                                                          3
MENA Infrastructure Supply Side

• Relatively high infrastructure investment in recent years has succeeded in
  ensuring basic infrastructure access to the vast majority of MENA
  citizens, yet significant infrastructure investments are needs coupled with
  financial pressures on Government debts and budget deficits

• The connection rate to the electricity grid by households is around 90
  percent; access to acceptable water and sanitation services is above 70
  percent, however, connectivity for the most part utilizes old / inefficient
  systems and industrial connectivity is still way below needed capacity.

• The penetration of mobile telephony has reached the level witnessed in
  industrialized countries.

• Paved roads represent between 60 to 70 percent of the total road
  network.



                                                                                4
MENA Infrastructure Demand Forecast
•   There are some considerable challenges that MENA countries need to overcome in
    order to move the infrastructure agenda forward .
•   Good demand drivers exist like attractive investment alternatives, pension fund and
    insurance companies diversification into new asset class and poor historical Public
    output performance
•   The installed generation capacity of the electricity sector is estimated to be 20
    percent below the aggregate demand for electricity across countries in MENA.
•   The prevalence of highly subsidized electricity & water tariffs induces wasteful use
    of electricity& water therefore increasing pressures for expansion of electricity
    generation capacity.
•   Energy & Water subsidies cost the region the equivalent of 10 percent of its GDP in
    2006, whereas reducing these subsidies could raise the region GDP by 3 - 4 percent.
•   Urban congestion is growing and therefore increasing transaction costs for
    businesses or commuting times for workers (In Cairo, the average speed of vehicles
    is as low as 9 km/h )
•   It is estimated that the total economic and social cost of congestion is about 5
    percent of GDP. In Teheran, it is estimated that commuters spent around 4.5 million
    hours/day in traffic.
•   The quality and reliability of Infrastructure services are a real challenge which
    constrains competitiveness, regional economic activity and growth prospects
                                                                                           5
MENA Infrastructure Investment Forecast
•    Private investments in infrastructure in MENA have grown significantly since
     1994, but at a lower rate than in other regions.
•    MENA countries need to create 40 million new jobs in the next ten years to meet
     the fast growing labor force.
•    This will require sustaining the economic growth at around 7 percent per year in
     the next ten years which cannot be achieved without significant investments in
     infrastructure.
•    The annual volume of infrastructure projects financed in MENA is estimated to
     have grown from US$25 billion in 2007 to US$27 billion in 2008,before sharply
     declining by June 2009 to US$6 billion due the global financial crisis (Investments
     in PPP in the Middle East and North Africa almost tripled between 2000 and 2007)
•    Middle Income Countries in MENA will need to invest the equivalent of 9.2
     percent of their yearly GDP, in order to sustain their economic growth prospects.
     This represents a total investment effort between US$75 to 100 billion a year, of
     which 33 percent is earmarked for the maintenance of the existing stock of
     infrastructure.
•    The Arab world invests about $60 billion a year in infrastructure, but to sustain
     current growth rates, it needs about $100 billion annually.
•    To meet this $40 billion gap, a smart mix of public sector engagement in
     coordination with financing and expertise from the private sector is essential.
                                                                                           6
Opportunities in GCC Power, Utilities and
                 Infrastructure
• Long-standing problems like high unemployment, limited access to finance
  and weak regulatory frameworks are the forefronts in MENA Region.

• There are more live projects in the MENA region than anywhere else




•   Qatar are planning projects worth $20 billion over 5 years
•   Saudi Arabia is planning to spend $400 billion in the same period
•   Oman is budgeting $2.43 billion for capital investments in 2010
•   Abu Dhabi is spending $68 billion in public transport schemes alone
•   Oman projecting a total government spending of $10 billion for the
    construction industry in year 2012, an increase of 23 per cent over 2011.
                                                                                7
Opportunities in GCC
Transport Sector
•   The GCC Transport and Railways Conference held in Qatar, October, 2011
    (Sponsored by Qatar Railways Company (RAIL) in association with the General
    Secretariat of the GCC, the Federation of GCC Chambers, the Qatar Chamber of
    Commerce and Industry, and others)

•   Investments of more than US$ 200 Billion already allocated to the development of
    transport systems, with the rail networks and metro projects reaching US$ 100
    Billion.

•   The national GCC railway projects, a 2200 km network that will be carry
    passengers and goods at speeds of 200 km/h and 80-120 km/h, and will link the six
    Gulf countries at a total cost of more than US$ 15.4 billion. Commissioning of the
    entire network is expected by 2018 A.D.

•   It’s forecasted that GCC GDP to reach around US$ 2 trillion and a total population
    of around 53 million in the year 2020 A.D.

                                                                                         8
Opportunities in MENA Social Housing
• Affordable housing for the MENA region has an estimated shortfall of 3.5
  million units -JLL Consultancy – 2012.
• Saudi Arabia has the largest shortfall in the Gulf of 500,000 plus homes
  followed by 40,000 homes in Bahrain, 20,000 in the UAE and 15,000 in Oman .

• KSA Construction Housing Pipeline Projects valued at US$ 29 billion for 2012.
• Sharjah has a shortfall of 5,000 affordable homes. Sharjah ruler unveiled initiate
  in 2012 for affordable housing.
• Bahrain government signed early 2012 a record BD208m ($550m) with a local
  developer to build more than 4,000 affordable homes.

• Saudi Arabia needs 1.65 million new homes by 2015 (275,000 units a year). Total
  commitment is $130bn on social projects with $67bn allocated for 500,000 new
  homes and $400 billion for infrastructure projects.
• Bahrain forecasts the need for about 350,000 new residential units to be added
  to existing stock by 2030 with $1.1bn to be spent every year up to 2020, and
  then $242m annually up to 2030, (EDB report).
                                                                                 9
GCC PPP Activity Update (KFH 2010 report)
• With huge government surpluses, securing finance is not the overriding
  factor behind the PPP push in the GCC countries, rather, it is the goal to
  deliver projects more efficiently, grant the private sector a greater
  economic role and assist with the diversification of the local economy.

• Since 2010; over 50 PPP contracts were signed in the GCC region. These
  projects require investments of more than USD 60 billion.

• As of September 2010, the UAE had signed off an estimated USD20 billion
  worth of PPPs, with some USD7 billion accounted for by Abu Dhabi's utility
  sector.

• Kuwait government rolled out in mid-2010 through Partnerships Technical
  Bureau (PTB) – a PPP unit - PPP program comprising 32 projects and
  requiring investment of USD28 billion in various sectors -
  Transportation, real estate, healthcare, utility projects and recycling
  factories under B.O.T system with the largest being the estimated USD10
  billion Kuwait national rail scheme.
                                                                               10
PPP Pipeline Projects – GCC
Mar-10       KSA               Airport Cities PPP
Jul-10       KSA               Airport Cities PPP
Aug-10       KSA               High Speed Railway PPP
Sep-10       KSA - GCC         Railway Network PPP
Apr-10       KSA - Jeddah      Airport PPP
Aug-11       KSA - Mecca       Mass Rail Transit PPP
Apr-10       KSA - Medina      Airport PPP
Jul-10       KSA - Medina      Medina International Airport PPP

Aug-10       Kuwait            Metro Rail PPP
Sep-11       Kuwait            Recycling factories PPP / B.O.T

Sep-10       Oman              Railway Network PPP
Jul-11       Qatar - Doha      Metro PPP

Oct-10       UAE               Railway PPP
Dec-10       UAE               Union Railway PPP
Aug-10       UAE - Abu Dhabi   Mafraq-Ghweifat Highway PPP
Jul-11       UAE - Abu Dhabi   Airport PPP
Oct-10       UAE - Dubai       Water PPP                          11
PPP Pipeline Projects – Rest of MENA
Oct-10     Egypt                      Rod el-Farag Highway PPP
Sep-11     Egypt                      Egyptian Refining Company
Sep-11     Egypt                      Suez 650 MW Steam Thermal Plant
Sep-11     Egypt                      Taxi Replacement Scheme
Jul-10     Egypt - Alexandria         University Hospital PPP
Jul-11     Egypt - Alexandria         Hospital PPP
Feb-10     Egypt - Cairo              Wastewater treatment plant PPP
Jul-10     Egypt - Cairo-Alexandria   Cairo-Alexandria Freeway PPP

Sep-10     Jordan                     Rail Transit / Way PPP
Jul-10     Jordan - Amman             Light Rail PPP
Jul-10     Jordan - Amman             Ring Road Highway PPP
Sep-11     Morocco                    Railway Line
Sep-11     Morocco - Casablanca       Drinking Water Supply -Rabat
                                      Hasdrubal Oil and Gas Field
Sep-11     Tunisia                    Development
Sep-11     Tunisia                    Road Project VI                   12
MENA PPP Initiatives / Successes




                                   13
MENA PPP Environment

• There are some considerable challenges for MENA region in moving the
  infrastructure agenda forward.

• PPP investments in MENA region Countries have essentially been contractual
  rather than being based on a larger legislative framework.

• Some ministries in some countries have developed expertise in structuring a
  very specific PPP category like telecommunications, roads or sanitary / water.

• The procurement process, dispute resolution and regulation / tariff setting
  arrangements have generally been subject to a contractual arrangement rather
  than independent laws, regulations and regulators.




                                                                              14
GCC PPP Activity in the Last 10 Years
                    (Kuwait Finance House – KFH- 2010 report)
•   GCC PPP contracts during the last ten years amounted to USD 628 billion with over
    100 PPP-type agreements, of which half can be classified as management contracts.
•   In terms of PPP deals concluded, Saudi Arabia has the highest number at 45 with
    power and desalination's share of the PPP market was near 90 percent of the total
    spent.
•   Management contracts (Often seen as the first step towards privatizations) have
    been used extensively in used in regional seaport and airports projects.
•   The UAE and Saudi Arabia represent the largest markets for PPP especially IWPP
    (energy and water projects).
•   The first IPP in GCC (Al-Manah independent power project ) was signed in 1994 in
    Oman.
•   In 1998 Abu Dhabi successfully launched the restructuring of the Abu Dhabi utility
    sector and formed Abu Dhabi Water Electricity Authority (ADWEA) on BOO basis.
•   Oman re-launched its own utility privatization program in 1999 and was followed in
    2000 by Qatar and in 2003 by both Bahrain and Saudi Arabia.
•   In 2002, the region's first sewage treatment plant (STP) PPP was awarded at
    Sulaibiya in Kuwait (USD 400 million)
                                                                                         15
Regional Infrastructure Regulatory Forum -
                              December 2009

• Jordan’s Ministry of Planning and International Cooperation
  (MOPIC), and in collaboration with the Public-Private Partnerships
  Infrastructure Facility (PPIAF) and the International Finance Corporation
  (IFC) launched in Amman on December 7, 2009, the first Regional
  Conference on Infrastructure Reform and Regulation in the MENA region.

• The Conference adopted a final resolution to launch a process towards the
  establishment of the “Middle East and North Africa Infrastructure
  Regulatory Forum” of which the objectives will be to promote the
  cooperation among infrastructure regulators within and across countries
  in MENA.

• A working group was formed to work jointly with World Bank in bringing
  the process forward. The Membership of the Forum will be open to all
  relevant organizations responsible for regulation and that are based in the
  MENA states.


                                                                              16
Middle East and North Africa
        Infrastructure Regulatory Forum
• Cooperation among stakeholders , regulators dialogue and knowledge-
  sharing can serve to;

-   Accelerate reform progress,
-   Promote best practice and
-   Enhance the harmonization of infrastructure networks.
-   promote the adoption of common rules, norms and standards,

• A multi-sector regional Forum of infrastructure Regulation can serve as a
  valuable platform for

- Experience and information sharing across borders and sectors,
- Problem-solving, and the dissemination of best practices.
- Knowledge sharing center providing capacity building services

                                                                              17
Arab Financing Facility for Infrastructure (AFFI)
 World Bank Group & Islamic Development Bank Infrastructure Facility

  •   The World Bank Group (IFC), in cooperation with the Islamic Development Bank,
      set up a $1 billion facility (the public side of investments will be financed via an
      initial $200 million from the World Bank) to close the infrastructure gap in the
      Middle East and North Africa.

  •   This regional investment vehicle supports both conventional and Shariah-
      compliant investment in infrastructure which will attract untapped, alternative
      sources of financing.”

  •   The Facility focus is cross-border PPP infrastructure projects like electricity
      networks and rail, road and maritime networks and projects with regional impact
      like the plans for large-scale concentrated solar power production in Morocco to
      increase the regional integration and competitiveness.

  •   IFC supports cross-border projects that commercial banks would consider too risky
      without IFC’s involvement.

  •   World Bank lending to the MENA region for infrastructure, including electricity,
      transport and water, has exceeded $1 billion a year.
                                                                                             18
ADB (African Development Bank) Investment Update

North African Countries : Algeria, Egypt, Libya, Mauritania, Morocco, and Tunisia.

•   The Bank Group started operations in the North Africa sub region in 1968 – one
    year after the other sub regions.
•   Loan and grant approvals for the sub region totaled UA 1.47 billion in 2010, which
    is a rise of 40.0 % above the 2009 level of UA 1.05 billion. ( ADB uses UA units of
    accounts which is SDR and is nearly equivalent to 1.5 USD)
•   North Africa’s approvals represented 40 % of total Bank Group approvals, which
    makes it the main beneficiary sub region during the year.

The key projects approved for North Africa were:

•   Suez 650 MW Steam Cycle Thermal Power Plant in Egypt;
•   Increasing capacity on Tangiers–Marrakech Railway Line in Morocco;
•   Road Project VI in Tunisia;
•   Drinking Water Supply in the Rabat Casablanca in Morocco;
•   Egyptian Refining Company Project in Egypt;
•   National Program for Taxi Replacement Scheme in Egypt;
•   Oil and Gas Field Development Project in Tunisia;
•   Public Administration Reform Support Program, Phase IV in Morocco.
                                                                                      19
IFC-World Bank

 IFC is currently active in both projects financing and advisory services in the
  MENA region ( GCC countries are excluded from the financing)

 IFC mission is to foster sustainable economic growth in developing countries by
  financing private sector investment, mobilizing capital in the international financial
  markets, and providing advisory services to businesses and governments.

 IFC has expanded its advisory services to improve the business enabling
  environment and encourage public-private partnerships for the development of
  infrastructure.

 Reducing infrastructure bottlenecks—especially in transportation& power sector is
  a strategic priority for IFC to support the region’s sustained long term growth.




                                                                                      20
IFC-World Bank Advisory - 2010
EGYPT                        SAUDI ARABIA

• Cairo-Alexandria Freeway   • Airport cities
• Alexandria University      • Madinah International
  Hospitals                    Airport

JORDAN                       SYRIA
• Amman Ring-Road            • First Independent Power
• Amman Light Rail             Project

PAKISTAN                     YEMEN

• FAISALABAD ELECTRIC        • First Independent Power
  SUPPLY COMPANY (FESCO)       Project

                                                         21
MENA PPP Laws

• PPP draft law to be approved in Lebanon. - October 23, 2010

• Dubai´s PPP law will be approved in the first quarter of 2011- drafted by
  Roads and Transport Authority (TRA) but it is not specific to transport-
  January 13, 2011

• PPP law draft ready for private comments in Jordan (Privatization law was
  passed in Jordan in year 2000)- July 12, 2010

• PPP law for Egypt ( under process) - drafted by Finance Ministry's Public-
  Private Partnership (PPP) Central Unit - August 23, 2010

• In 2009 Kuwait announced its intention to pursue the private power
  route.


                                                                               22
MENA PPP Government Initiatives
Country        Sectors                                        Law                   PPP Unit
Jordan         water, airport, ring road, , airport           Privatization & PPP   Yes
Lebanon        Energy (IPP 435 MW)                            Privatization & PPP   Yes
Egypt          Rail, roads, water, STP, health, education     Privatization & PPP   Yes
Algeria        Rail, roads                                    Project wise Laws     ?
Tunisia        Solar, roads, oil & gas (production sharing) Project wise Laws       Yes
Morocco        Solar, railway, water transmission.            Project wise Laws     Yes
Bahrain        Energy (IPP),STP, waste treat. , housing       Mortgage - Housing    Yes
Qatar          Metro                                          Sector Laws           MoBaT
Kuwait         STP, metro, railway, recycling factories.      PPP                   PTB
UAE            Energy (IWPP), water taxi, airport             PPP                   RTA
Oman           Energy (IPP) STP, railway, housing             Mortgage - Housing    ?
Saudi Arabia   IWPP, STP, housing, airport Cities, GCC rail   Mortgage - Housing    ?
Yemen          IPP (400 MW)                                   Sector Law            ?
                                                                                          23
Jordan - Water Sector
• Since 1997, the Government continually issued strategy, policies and investment
  program:

   • 2002 – 2011 Sector Plan and Investment Program
   • Action Plan 2002 – 2006.
   • Water Utility Policy
   • Ground Water, Wastewater and Irrigation Policies
   • New Water Strategy for Jordan for Water Demand Management (WDM) and
     Public Private Partnership (PPP)
• Institutional responsibilities lies with Ministry of Water and Irrigation (MWI)

• Management Contract selected due to
    • Improvement of Services with Reduced Risks to Government
    • Results in Significant Improvement, in System Operation
    • Improvement of Organizational Reform of Operations
    • Good First Step Towards Significant PPP

                                                                                    24
Egypt – Full PPP Program
Egypt has led MENA Countries with 22 PPP Deals valued at $15.4bn achieving financial
closure between 1990 and 2007

Performance-based contracts under concession (affordability or a hybrid of both).
   • Output is specified by Line Ministries while input is by the private sector
   • Under the PPP contract the Government retains total strategic control
   • Adoption and localisation of international successful PPP models (UK based)
   • Supportive legislative environment , new legal framework for PPP projects
     (Draft under finalization for Submission to Cabinet and Parliament)

Standard PPP Contracts

   • Standardization of procurement documentation and procedures
   • Creation of regulatory bodies for post contract implementation
   • Establishing a PPP Central Unit at Ministry of Finance as well as Satellite Units.
   • PPP Pipeline Projects in Social Infrastructure (Education                     &Health
     Sectors), Wastewater Treatment Plants and Transportation Sector

                                                                                          25
PPP Global Adaptation / Learning




                                   26
Countries PPP Knowledge Sources




                                  27
HM Treasury References




                         28
WB PPP Knowledge Reference




                             29
International PPP Center of Excellence Initiative




                                                30
Neighboring Countries PPP Actions




                                    31
PPPs Evolutionary Phases
     START (Infancy)         Stage Two (Establishment)           Stage Three (Maturity)
•Introduce PPP concepts      •Introduce legislative         •Fully defined, comprehensive
for Public discussions       reform                         “system”
•Explore PPP models          •Publish policy and practice   •Legal impediments removed
                             guidelines
                                                            •PPP models refined and
  Stage One (Emerging)
                             •Establish dedicated PPP       replicated
•Define policy framework     unit/s
                                                            •Sophisticated risk allocation
•Test legal drafts           • Refine PPP delivery
                                                            •Committed, long-term deal flow
                             models
•Identify project pipeline
                                                            •Long-term political consensus
                             •Continue to foster local /
•Develop PPP concepts
                             int’l marketplace              •Use of full-range funding sources
•Apply lessons from                                         including pension funds and
                             •Expand project pipeline
earlier deals to other                                      private-equity
sectors                      •Extend to new sectors
                                                            •Well-trained civil service
•Start to build the local    •Leverage new sources of       applying lessons from PPP
marketplace                  funds                          experience

                                                                                             32
PPP Market Maturity Curve – UN Publications




                                              33
Governments & Institutions objectives in PPPs
 •   Fiscal objectives (defers the cost of capital investments, reduce apparent
     borrowing by government )
 •   Economic objectives:
      – expected efficiency gains
      – more reliable completion of projects on time and on budget
      – expected greater management skills / know how of private sector
 •   Political objectives
      – reduce role of the State / the Government
      – weaken influence of public sector trade unions

                   Fiscal Objectives            Economic Objectives          Political Objectives
                   Limits on government
     IMF           spending/borrowing
                                                Efficiency                   Develop global market

                   Limits on government
     EU            borrowing, debt (stability   Efficiency                   Develop internal market
                   pact)
                                                                             Reduce role of state, extend
     National      Limits on government         Efficiency, reduced public
                                                                             role of private sector,
     governments   borrowing                    spending
                                                                             weaken unions
     Local                                      Efficiency, reduced public
                   Reduce local taxes                                        ?
     governments                                spending
                                                                                                            34
35
PPP Program - Integrated Approach – Key Notes
 No perfect design for regulation and
  institutions

      Changing market condition needs to     Vision – Strong Political       Institutional
       be reflected in PPP framework by        Will Accepted By The
       modifying and updating regulatory                                  Framework – Building
       and institutional design                    Public / Users           Capacity, National
                                               (Empowered Public)                Policy
      Competition & transparency
       principles need to be kept

 Government’s proactive use of                             Viable / VFM PPP
  vision, policy & sustainability in market                 Projects Pipeline
  creation is important.
 Taxpayers / users engagement in PPP           Funding – Priority           Legal & Regulatory
  dialogue                                           Funding                Framework – Clear &
                                                                              Friendly Business
 Supporting local financing institutions /    Strategies, Building
                                                                           Environment To PPP’S .
  local development funds is key.             Local Financial Supply       Oversight Procedures -
                                               Side – Infrastructure      Transparency, Competiti
 In house skill within the government is
  of crucial importance to build                       Funds                   on, Monitoring
  capacity , to monitor and create PPP
  pipeline projects
                                                                                             36
POLICY AND LEGAL FRAMEWORKS & SUPPORT FUNCTIONS
   Comprehensive PPP Law – Investment , Funding & Technical (PPP Contract Type/s) and Legal Powers to
    contract out the services
   Dispute Resolution Mechanisms – Independent Chamber
   Open & Transparent Public Procurement / Tender Law
   Clearly Defined Gov. / PPP Unit Role in – Budgeting Allocation / Oversight , Progress Monitoring & PPP
    Projects Approvals and Contract Management – performance-linked payments/penalties.

   Sector & Scope of Sector Law – Ex. How to own a pipeline in a public road?
   Private / Public Land Acquisition Law
   Easements / Way leaves / Permits , etc
   PPP Implementation Structures – Technical Public / Private Interface Offices.

   Integration of PPP into Public Procurement w/ Multi Stage Financial & Scio-economic Appraisal
    Procedures (Rationale for use of PPP’s (Business Case) , Suitability & VFM Assessment) , Guidelines for
    PPP’s Pre-qualification , Tender And Bidder Selection.
   Standardized PPP Bidding Documents
   Unsolicited Bids Procedures.
   Standardized PPP Contracts / Asset (Facility) Type or PPP Model / Structure

   Information dissemination – data, networking, training
   Guidance – model contracts, tools, case studies
   Facilitating functions – political/advisory support, funding
                                                                                                         37
Criteria's & Performance for PPPs
Criteria for PPPs (PPP Project Test)
      Affordability for the Public Sector & Desired Gains
      Financially viable for the Private Sector
      Appropriate Risk and Reward Balance for Public and Private Sector
      Public Sector - value for money (VFM – True Cost) Verses traditional PSC

PPP Performance & Monitoring : World lessons
       National audit authorities need to be involved in assessing PPP VFM (UK NAO)
       Periodic reports for progress , learning and benchmarking are needed.
       Public and private sector may need to acquire new skills to commence a PPP
        program.
       Sufficient ‘deal flow’ is critical to justify the high transaction costs and to
        promote effective competition.
       Procurement programs need to be managed to minimize costs (e.g.
        standardized documentation) and maximize competition (e.g. timing of contract
        notices).
       National PPP Task Forces / PPP units can play key role in securing VFM in
        programs.
       Globally , cost and time performance in major infrastructure generally good,
        performance in IT & Social PPP sectors generally weak.
                                                                                   38
PPP Projects Value Drivers
           Less                   PPP Value Added Driver                                   More
                              PERFORMANCE-BASED PAYMENT MECHANISM:
                              Above-par performance should give higher
Unitary Fixed Payments        profitability, low performance should trigger       Performance Payments
                              penalties.
                              OUTPUT SPECIFICATIONS: Relates to the private
                              sector's ability to deliver the services at lower
Limited Incentive Contracts   costs, or to provide better quality at the same     Output Based Contracts
                              cost to the user.
                              INTELLIGENT RISK ALLOCATION: Risk to be
                              allocated to the party that is best to manage ,
Wrong Risks Allocation        mitigate or absorb it. Wrong risks allocation       Optimal Risk Allocation
                              reduces PPP value.
                              LIFECYCLE OPTIMIZATION: Integrating different
                              components and phases increases the                 More project phases in
Multiple Project Phases       performance over the PPP lifecycle and reduces
                              interface problems.
                                                                                  one hand
                              FORMAL CONTRACTING: Clear legal recourse in
Simple Contracts              case of disputes increases clarity and reduces      Complex Contracts
                              risk.
                              COMPETITION / FUNCTIONING MARKET:
                              Competition from adequate number of
Limited Competition           companies increases value-for-money. PPPs           More competition
                              without competition are inefficient.
                              PRIVATE FINANCING: Private financing results in
Public Financing              strong oversight from debt and equity providers     Private Financing
                              which increases project performance.

                                                                                                      39
UNECE Guidelines On Governance In PPPs
                                                                                 
Coherent PPP                                                   No! , You need a policy framework with
                    PPP pilot project will start the process
Policy                                                         direction, responsibilities and goals.
                                                               No! , capacity building within
Strong Enabling     PPP’s projects should focus on ring
                                                               Government & setting up institutions
Institutions        fencing
                                                               are needed.
                    PPP’s have prescriptive rules and tight    No! , Overall framework should be
Legal Framework
                    control                                    flexible.
Cooperative risk    PPP’s provide assets to governments at     No! , Governments must assume some
sharing             no risk and no cost                        risks and offer some subsidy.
Transparency in                                                No! , Competition allows selecting the
                    In PPP’s no tender required…
Partner selection                                              best fit (partner /project)
Putting people      In PPP’s its best to Keep people out:
                                                               No! , People need to be put first.
First               they do not understand the complexity
Sustainable         In PPP’s one have to choose between        No! , Project can make profit and still
Development         profit and social & environment …          achieve social and environmental goals.
                                                                                                      40
Key to Successful PPP’s
   Alignment of proposed projects to strategic plans and mandates.
   Vertical alignment in terms of national and also provincial priorities to enhance “buy in”.
   Proper groundwork at inception with regards to option analysis: clear VFM
   Attracting private investors .
   Appointing good transaction advisors: well rounded experience, no conflict of interest.
   Clear contract terms and conditions to avoid contract re-negotiation.
               PPP PRO’s                                       PPP CON’s
Competitive Process                          Complex Structures & Documents
Increased Transparency                       Time-Consuming to Arrange / Tender
Off Balance Sheet Consideration              Higher Borrowing Costs Than Public Financing
Private Sector Efficiencies and Innovation   No different than EPC Contracts
Commercial Risk Sharing                      Difficult to Resolve When In Default
Acceleration of Infrastructure Provision     Project Choice Important
Faster Implementation                        Skill Deficit for Administration
Reduced Whole Life Costs                     High Transaction Costs
Better Risk Allocation                       Structured Risks
Better Incentives to Perform                 Needs Legal Framework
Improved Quality Of Service                  Can be achieved at High Price
Generation of Additional Revenues            Collection Issues & Costs
Enhanced Public Management                   Public Perception and Political Reactions            41
PPP Units – A World Trend !
•   There are no single design of PPP unit, design to fit local the context
•   PPP unit is not a prerequisite nor a guarantee for successful PPP
•   PPP unit need to demonstrate leaderships and specialties


•   Most countries commence PPP programs in Transport, Energy, Water, Wastewater
    and later migrate to other sectors like – Health, Education, Energy, Water, Waste
    Treatment.
•   Rate of ‘migration’ to other sectors reflects both national priorities and existing
    legal frameworks.
•   Tendency for project to cascade from central to local government / municipalities.

•   Line ministries which have a long experience in traditional procurement may not
    want to cooperate with new agency

    MoF – Policy Formulation &                               Line ministries/ local Gov’t
    Fiscal / Budgetary Control                                Project Implementation




                                                                                        42
PPP Units Design Notes – Function Wise

• Design factors for PPP units include size and type of government (
  Federal / non Federal) , decentralizing from central government to local /
  state governments, where within government infrastructure delivery
  "sits" and the size and growth of the PPP program (measured as the ratio
  of PFI/PPP investment to the total investment in public services).
• It is highly desirable that the roles of PPP Policy Development
 (Institutional Fr amewor k and development of top line guidance like
 value for money) and PPP Pr ojects Appr ovals are not within the scope
 of the same PPP unit that serves as centre of best practice and expertise
 (Project Development) or coordination unit.
• To be effective, a PPP unit needs to be able to build up experience and
  retain institutional memory project and lessons leant wise. This can be a
  challenge of sitting within the public sector. In all cases the public sector
  needs to have experience of managing financial, legal and technical
  advisory roles if these functions are sourced out .

                                                                                  43
PPP Units Design Notes – Government System Wise
• In a Federal system (like India, Australia, UAE and USA), the
  relationship between Federal and State Units depends on the
  responsibilities of the different levels of government with the federal
  government role as Project Developer is less significant, however, the
  financing / guarantees role of the Federal still exists.
• In non federal, centralized system the role of the PPP unit needs to fit
  with the existing structures of government considering the extent to
  which levels of government / Line ministries have control over their own
  budgetary resources or have private finance units or are permitted to
  generate own revenues . At the early stage of PPP development, it is
  usual to start with a central PPP unit, however, as the program grows; the
  need to avoid excessive deficiencies stemming from centralization needs
  to be addressed.
• In Constitutional democracies with strong parliamentary processes, PPP
  units are preferably located in the Ministry of Finance to exercise fiscal
  and budgetary control with Ministry of Planning or Mega Projects being
  also other preferred locations.
                                                                               44
PPP Units Should Also Resolve Government Failures!

Government Failures                                     PPP Units Functions
Policy & Strategy
undefined , not clear                                   Marketing & Promotion
Poor Procurement            PPP Units functions         Policy Formulation &
Incentives                       need to
                                                        Coordination
                              accommodate
Poor information                                        Information and Guidance
                           Governments failures
dissemination                                           - Standardization
Poor Contract                                           Project Advise – Technical
Management                                              Assistance
Lack of Coordination
among stakeholders          PPP Units associated with   Project Development
                            Successful PPP Programs;
Lack of complex projects
skills & analysis                                       Funding Preparation
                           Partnership UK (PUK)
Poor Transaction                                        Contract Monitoring &
                           Partnership Victoria
Management & High Costs    South Africa PPP Unit        Control
Lack of Information                                     Approval Power
                                                                              45
Examples of Location & Roles of PPP Units
Policy Setting /    Monitoring /    Collaboration /   Investment
 Fiscal Control    Budget Control   Coordination      Promotion

  Ministry of        Ministry of       Ministry        Ministry of
  Finance /          Finance /      (Authority) of     Business &
 Treasury or        Treasury or       Planning /         Trade
Economic Unit      Economic Unit     Ministry of      , Ministry of
                                    Mega Projects       Industry
    PPP                PPP                PPP            PPP
    Unit               Unit               Unit           Unit




                                                                   46
Examples of Roles , Location & Funding of PPP Units
                       Victoria,                            Nether-
                                 BC, CA   Ireland   Italy              Philip.   SA     UK
                         Aus.                                lands
 Guidance                                                                         
 Project Advise                                                                  
 PPP Development                                                                      
 Funding Preparation                                                                  
 Monitoring                                                                         
 Approval Power                                                                       

                                                                      PV, Australia
  Inside the Government
                                                                      PBC, Canada
  (All are funded by the Government)
                                                                      UK Treasury Task Force
  Outside the government (Private)                                    PIMAC, Korea
  Public / Private (Generates Revenue - Advisory Services)            PUK, UK

Multitier PPP units exist in countries where project development , financing and
approvals are bundled together. Example in UK , the Treasury Task force ( located in
MoF is the approval authority) while PUK ( Partnership UK , a semi private unit) does
the Project Development in line with satellite units from line Ministries.           47
PPP Other Sources - International Law
 UNCITRAL – UN Commission for International Trade
  Law, website – http://www.uncitral.org.

• Significant work toward the harmonization of private
  international law.
• Numerous translations of documents
  (French, Spanish, Arabic, Chinese, and Russian).

 UNIDROIT – Int’l Institute for the Unification of Private
  Law , website – http://www.unidroit.org.

• Best-known accomplishment = UNIDROIT Principles of
  International Commercial Contracts.

                                                              48
PPP Other Sources - Arbitral Institutions
 Permanent Court of Arbitration –
 http://www.pca-cpa.org.
 Int’l Center for the Settlement of Investment Disputes –
 http://www.worldbank.org/icsid/.
 International Chamber of Commerce (ICC) –
 http://www.iccwbo.org/index_court.asp.
 London Court of International Arbitration (LCIA) –
 http://www.lcia-arbitration.com/lcia/lcia/index.htm.
 American Arbitration Association (AAA) –
 http://www.adr.org/index2.1.jsp.
 WWW Virtual Library Arbitration –
 http://www.interarb.com/vl/pages/.

                                                            49
PPP Options & Projets Structures

                                                 Toll Roads
                                                 Airports
                                                 Seaports, Water Transport
                                                 Rail ( Railway, monorails, etc)
                        Transportation           Underground Transport


                                               Electricity
                                               Gas
                                               Water
                      Regulated Utilities

                                                 Hospitals
                                                 Schools
                                                 Prisons
                                                 Social Housing
                      Social Infrastructure

                                                 Broadcast Networks
                                                 Mobile Telephony
                                                 Satellites Cables
                                                 Terrestrial / Submarine Cable
                       Communications

                                                                              50
Generic - Risk Scales & Durations for PPP’s
 •   Privatization & Divestiture (Highest Private risk)
 •   DBFO & BO Concession contract - Revenue or off- take - (25 -30 yrs)
 •   DBOT, BOT (25 yrs)
 •   Lease / Afterimage contracts (5 – 10 yrs)
 •   JV, Partnerships ( varies but has a life time with dissolving mechanisms)
 •   Sale & lease back (8 – 15 yrs)
 •   Operation & Management ( O&M) Contracts (3-5 yrs)
 •   Service Contracts (1- 3 yrs w/ renewals)
 •   Technical assistance – discrete tasks - (Lowest Private risk)




                                                                                 51
Comparisons ! – More Common PPP’s
                                  Aggregat Approx.                       Construction,                     Operational
              PPP     PPP                                 Operators                     Demand
  Scheme                           e Risk Duration                       Rehabilitation          Env. Risk & Technical
             Type   Examples                               Revenue                        Risk
                                  % ( + / -) Years                            Risk                             Risk
                                   Nearly             Service Sale (
Privatization Non                   100%              regulated) ,         Private, if
                  Telecomm.                  Lifetime                                    Private Private     Private
& Divestiture PPP                  Private            Facility / License    needed
                                     Risk             re-sale
      Full                                          User's charges (
                                                                                        Volume
Concessions                                         Direct or shadow
                                    90%                                                Caps and
   (BOO) /        Highways,                         payments) /
                                  Private /                                             / or Off Private /
    Design    PPP IPP, IWPP,                25 - 30 Based on               Private                             Private
                                    10%                                                 take by Public
Finance Build     Hospitals                         Performance
                                   Public                                                  the
  Operate                                           (Availability/
                                                                                         Public
   (DFBO)                                           Delivery)
                  STP's , Water
                  Production,
                                    70%
DBOT,BOOT,        Social                            User's charges /                     Joint
                                  Private /                                                      Private /
 BOT (turkey PPP Housing,                   20 - 25 Off take               Private      Public /               Private
                                    30%                                                           Public
  delivery)       Education                         Agreement                           Private
                                   Public
                  facilities,
                  Prisons,
   Lease /        Sewer,
                                    60%
 Afterimage       Transmission              5 - 10, w/ Fee based on     Public ( for the
                                  Private /                                                                   More on
   (not the   PPP lines.                     Renewal collected             needed        Private   Public
                                    40%                                                                      Private side
    same!)        Electricity               Provisions revenues           facilities)
                                   Public                                                                         52
  Contracts       Distribution
Comparisons ! – Less Common PPP’s
                                         Aggregate Approx.           Construction,                   Operational
                        PPP    PPP                         Operators                Demand
      Scheme                                Risk Duration            Rehabilitation        Env. Risk & Technical
                        Type Examples                      Revenue                   Risk
                                          % ( + / -) Years               Risk                            Risk
   JV , Partnerships                                Lifetime
                            Solar
  ( usually high tech                      Nearly      w/     User's charges /
                            Generation,
 with environmental     PPP               balanced dissolving Off take                   Joint             Joint     Joint       Joint
                            Waste to
impact or Production                    (50% / 50%) mechanis Agreement
                            Energy,
  sharing -oil & gas)                                  ms

                            Common in
                            Airlines,
  Sale / Lease back
                            Government 20% Private              Direct - Capital /
 Contracts ( Asset is                                                               Public ( for the
                        PPP Building ,   / 80%         8 - 15   Operational                               Public     Public    Negotiated
 leased back to the                                                                needed facilities)
                            Sports       Public                 Lease agreement
       Public)
                            venues



                                                                                                          Public,
   Operation &         Airports &        10% Private                                                     Minimum
                                                                Contractual                                        Private /    Private /
Management (O & M) PPP Seaports,           / 90%        3-5                              N/A              volume
                                                                (lump sum)                                          Public       Public
    Contracts          land fills          Public                                                       guarantees
                                                                                                         by Public

Service / Maintenance
 Contracts, Technical
                          The usual     Nearly                  Contractual / On
      Assistance      Non
                          outsourcing 100% Public       1-3     call / job card fee      N/A              Public     Public      Public
    (Government       PPP
                          PSC.           Risk                   ( Discrete Tasks)
Procurement - Design
    - Build or EPC)
                                                                                                                                    53
Comparisons ! - PPP Versus Privatizations
         Public-Private Partnerships                                                Privatizations / JV’s
Water, Wastewater Treatment, Electricity Generation              Telecommunications , Some Water Services

Hospitals , Hotels, Sports Venues                                Electricity generating , Transmission / Delivery Networks

Roads, Bridges, Rails                                            Production of Oil and Natural Resources (sharing)

Social Housing, Schools, Prisons ( Social infrastructure)        Poorly Managed Large Assets.

A new special purpose vehicle (SPV) is formed - Project           Existing state-owned assets are sold directly to a private sector
Company , owned by the private sector                             entity, often after an international / local tender

The SPV develops, finances and completes the
                                                                  Title to the assets is transferred to the private sector entity
infrastructure necessary to deliver the project

Full operational control is transferred to the public sector
                                                                  Private sector entity owns the assets and can dispose of them
at the end of the agreed “concessionary” period , while the
                                                                  after contractually imposed deadlines and benchmarks (lock in
title to the asset remains with the public sector in BOT
                                                                  period)
and most utilities


The SPV delivers the service and receives agreed-upon              Because the asset has been permanently transferred to the
compensation . Compensation to the private sector can be          private sector, the public sector benefits are gained through
in the form of tariffs paid by service users or directly by the   receiving the acquisition price, improved efficiency , tax and
government, or a combination                                      royalty payments



                                                                                                                                    54
Comparisons ! - Risk Areas of Private ,PPP & EPC
                Public Projects
                        Private Project      Public Private     Traditional EPC
                         Development       Partnership (PPP)     Procurement

                           No Public        Public side has     Public Side has
  Urban Planning           Influence        good influence       total Control


                           No Public        Public Side has     Public Side has
  Execution Speed          Influence        good Influence       total Control


                           No Public         Guarantees of        Contractor
  Guarantees               Influence        Private Investor      Guarantees


  Project Financing     Private Investor    Private Investor      Public Side



  Market Risks          Private Investor    Fair Risk Sharing     Public Side


  Economical Benefits    Benefit From         Sustainable        Sustainable
  - Public Side          Property Sale         Benefits           Benefits


                                                                                  55
Comparisons ! - Tax-Exempt Financing Versus
     PPP – Government Perspective
     Tax-Exempt Financing                             Public-Private Partnerships
• Strengths                                         Strengths
  –   Tax-exempt interest (deductable)                   Strength of private equity credits
  –   Tax credit                                         Addition of equity cushion
  –   Existing relationships with insurers               Market demand for infrastructure projects
  –   Retains operational control of assets              Transfer of operating risk
                                                         Ability to continue oversight
• Challenges
  –   Market access issues                          Challenges
  –   Future financial viability of bond insurers        Shift to executive oversight
  –   Full retention of operating risk                   Equity partners belief in future growth
  –   Revenue shortfalls, unprotected.                   Public policy implications/transfer of
                                                          revenue stream




                                                                                                    56
PPP Risks - The More Familiar
       Risk                         Type                                        Risk Mitigation
                     Environmental and safety
Environment and                                             EIA before and after, Both parties to agree on the
                     constraints defined in the
Safety Risks                                                Environmental impact.
                     Concession Agreement
                                                            Risk to be borne by Concessionaire. Acquisition of land
                                                            risk by Government before construction start. Tools;
                     Time delays & cost overrun risks,      - Fixed price turnkey contracts
Construction Risks
                     geotechnical risks                     -Warranties (bonds),
                                                            - Liquidated damages clauses.
                                                            -Clear input or output or performance specifications.
                                                            Tools include;
                                                            - Equipment Suppliers guarantees
                     Performance based risks,
Technical                                                   - Proven technologies
                     operating costs, management
Operation Risks                                             - Performance guarantees.
                     failure.
                                                            - Raw materials / feedstock agreements
                                                            - Public Authority involvement
Revenue Risk in       Minor risk in existing facilities     Often acceptable risk level is borne by Concessionaire
existing facilities / unless forecasts after                (adequate provision on tariff in Concession
infrastructure        improvements are exaggerated.         Agreement).
                                                            Often not possible for Concessionaire to bear all the
Revenue Risk in
                                                            risk. Tools include;
newly-built          Major risk in newly-built facilities
                                                            - Off take agreement
facilities /         like traffic volume, tariff setting.
                                                            - Caps ( floors / ceiling)
infrastructure                                                                                                    57
                                                            - Revenue build up period
PPP Risks - The Less Familiar
        Risk                          Type                                     Risk Mitigation

                    - Structure ( Debt / Equity)               - Optimal Equity 30 – 10%
                    - IRR / NPV                                - IRR (15 % -25%)
                    -Debt Service Cover Ratio                  - 1.5 ( can be as low as 1.1 with string off
Financing Risks     - Tax Status / Benefits                    take agreements)
                    - Others - Exchange Risks, Sovereign       - Translates into tax account treatment
                    Credit Ratings, etc.                       - Financial derivatives hedging.
                    - Refinancing                              - Syndication


Legal Risks         Regulatory framework, concession /         Experienced (high priced) Lawyers. Clear
                    sector laws.                               documents. International Arbitration set.


                    Compliance to contractual terms in a       Mitigation through Risk Guarantee (IBRD and
Political Risks /   Concession Agreement. [Currency            MIGA). Transferred Risk can be insured –
Government          Inconvertibility, Confiscation,            Political risk insurance. World Bank provides
Performance Risks   Expropriation, Nationalization, Civil      Partial Risk Guarantees. Remaining risks can
                    Strife, War, etc.]. Force majeure can be   be borne by Lenders.
                    included

                                                                                                              58
Risks Perspectives
                                                                 Access to PPP
 Development         Best Value for           Acceptable
                                                                   Contracts
    Speed               Money              Financial Return
                                                                    Pipeline
           Government                                   Concessionaire
          Incentives to                            Risk Mitigation
          Transfer Risk                               & Control
                      Access To              Minimize /         Access To
Payment Source
                   Private Capital         Re-use Capital         Revenue Stream




                   Risk           Risk        Risk         Risk
               Identification   Analysis   Allocation    Monitoring




                                                                              59
Understanding Political Economic Connection




                                              60
Political Risk Agencies - (Social-Political-Economic)            Financial Risk Agencies / Ratings
               BERI , PRS , Prince, ICRG                    S & P , Moody’s, Milken Index , Fitch IBCA
               Hybrid Risk Models / Rating Agencies - (Financial Focus and Political Causes)
  Economist (Magazine)        Chase Manhattan Bank               Euro money            Institutional Investor


            POLITICAL RISK FACTORS                             ECONOMIC & FINANCIAL RISKs
Ethnic Social Tensions                                   Domestic Economic Problems
Strife, Armed Insurrection                               International Economic Problems
Urbanization                                             Low Wages / Labor Cost / High Productivity
Decentralization                                         Good Infrastructure / Telecommunication
Bad Neighbors                                            Restricted Import / Export
Commodity Dependence                                     High Commodity Prices
International Trade Agreements                           Expedient FDI Screening / Approvals
Regional Trade Agreements                                Favorable Taxation / Tax Holiday
Corruption                                               Third Party Cost / Biding Cost
Staleness / Illegitimacy                                 Debt in Default / Rescheduled / Non Payment
Democracy /Opposition Tolerance                          Reasonable Gov. Bonds Risk Premium
Liberties / Unrestricted Internet                        Service Oriented / Competitive Market
Powerful Private Interests                               Limited Creditworthiness
State Owned Enterprises                                  Restrictions on Privatization
Competent Local Management Partners                      Access to Bank Finance
Foreign Control / Foreign Equity Ownership allowed       Liberal Labor Laws / Modest Termination Benefits
Non-Repatriation/Non-Payments                            Fiscal Monetary Expansion / Capital Flight
Creeping Appropriation                                   Exchange Controls/Convertibility
MIGA Membership / OPIC Insurance Available               Liquid / Transparent Stock Market
                                                                                                         61
Stable Regulation & Law Enforceability                   Access to Capital Markets
PPP Projets Success Framework




                                62
PPP Projects Success Framework – EPEC Adopted
 1.   Choice of Project - Only sustainable projects should be launched
 2.   Choice of Funding & Risk Sharing - Fit with Project structure
 3.   Choice of Procurement Procedure – In line with Project complexity
 4.   Choice of Financial Structure - Balancing spreads and risks
 5.   Whole Contract Life Management - Renegotiations to the benefit of all parties.



  The main driver of the PPP contract duration should remain technical (life-cycle
   and obsolescence considerations), rather than financial!
  The legal framework of PPP’s should remain flexible enough to meet the
   conditions of success.
  Guarantees should be given more systematically to private operators, in order to
   have the best possible use of public funds.
  Resorting to guarantees to secure private financing can expose the government to
   hidden and often higher costs than traditional public financing

                                                                                       63
1. Project Choice - Sustainable Projects
 Decision makers must choose the projects that are desirable from the socio-
  economic point of view and respond to real demand and needs. e.g.:

      Which will enable the economic development of a market or a region;
      Which will save time and increase safety, in the case of a road;
      Which will save lives, in the case of a hospital, etc.
 A desirable project means a high socio-economic IRR (Internal Rate of Return)

 A high socio-economic utility makes the payment of a tax or a toll politically more
  acceptable.
 Experience shows , if contracts do not meet the condition of a high socio-economic
  IRR, problems necessarily arise:

      Bankruptcy of operator (in case of traffic risk)
      Skyrocketing public debt (if large grants are needed)
      Political legitimacy problems with regards to final users and tax payers
      And in the end: reputation problems for all partners
                                                                                   64
PPP Projects According to Revenue
Users Pay (Termed as Concessions when users pay)
• Traditional BOT model
• Revenues collected from users usually by the private partner (e.g. tolls paid on a highway or
    bridge)
• Project is “off the Government budget” as revenues flow directly to private sector
• Used only where there are substantial revenues that can be directly charged to users
• It is estimated that about 10% of receipts relate to toll collecting (without automated systems).
Everybody Pay (Termed as PFI when the Public makes regular payments)
• Annuity scheme or availability model
• Revenue collected can be either from users directly to private partner or may stay with
    government and Government opts to make regular payments for making the service available
    (availability / shadow payments)
• Project is often “on the Government budget” as revenues flow through Government
• Can be used widely for services paid by known users, or for those paid through taxes or in
    countries where tolling is not socially acceptable.
• There is no expenditure for toll collecting

    General tendency to move from toll to availability based payments in road projects. Also
    Innovative use of payment mechanisms to focus on public sector objectives are becoming
    trend. Examples from the road sector ; User tolls – to pass costs to users; Availability
    payments – to reduce congestion; Accident rate premium – to improve safety.
                                                                                                  65
PPP Transactions – Economic Partnering
Highways (Concessions – BOO, BOT, BTO) & Rails (BTO)
• Direct tolled – i.e. users pay full cost or partial cost (Government Subsidy)
  – compete on costs – e.g. Malaysia, Australia.
• Shadow tolled – users don’t pay directly but all pay indirectly via tax & fuel
  surcharge etc – compete on subsidy amount – e.g. India
Airports /Sea Ports (usually Management Contracts)
• Long term management contracts that may include capital works – e.g.
  Australia, Srilanka, Cambodia, KSA, Jordan
• Government may agree to minimum thru-put and provides core custom &
  immigration functions
Water & Power -IPP, IWPP- (Concessions – BOO, BOOT)
• Government agree on minimum uptake (usually 80 -90% the rest sold in
  open market – e.g. Indonesia, Malaysia, GCC (IWPP)
  , Egypt, Jordan, Lebanon, Yemen.
• Government may agree to pass-thru cost on fuel.
Power -Solar (Concessions)
• Similar to power – e.g. Morocco, Tunisia                                    66
PPP Transactions – Environmental Partnering
 Landfills (usually outsourcing – O & M Contracts)
 •   Private Partner to takeover waste treatment and landfill management , may
     include methane extraction – e.g. Malaysia , Indonesia
 •   Governments agrees to management fees and
 •   Governments usually approves combustion power plant on site for internal use as
     well as sale to power grid
 Waste to Energy (recycling of solid waste / used tires) (usually JV’s)
 •   Reduces excessive gas emissions while stimulating private sector demand.
 •   Private Partner to takeover waste conversion to energy – e.g. Bahrain.
 •   Governments agrees on energy sale to power grid
 Sewerage Treatment Plants (STP) – ( usually BOO / BOT, transmissions usually BOOT)
 •   Population and business levels increase leading to increased waste generation
 •   Private Partner to takeover sewerage treatment
 •   Government agree on off take (usually distribution to farms is by the
     Government) – e.g. GCC ( Bahrain)



                                                                                     67
PPP Transactions – Social Partnering
Hospitals (usually DBOF) / Prisons (usually BOT)
• Private Partner to build the facility , manage it for a set time and operate
  noncore service like catering, parking etc
• Government provides the doctors, nurse ,wardens etc and operates the
  core services – e.g. Lesotho, Australia
Schools/ Sports Venue / Shopping Malls (usually DBOF)
• Private Partner bids on cost, design and facility management for a set time
  & run noncore services – e.g. Australia, Egypt.
• Government runs core services of teaching / tutoring or agrees to use the
  facility for an agreed period
Public / Government / Affordable housing (usually BOOT)
• Private Partner to build, lease and maintain for a set period – e.g.
  Malaysia, GCC ( KSA, Oman, Bahrain)
• Government agrees to minimum lease for a set period / off take and / or
  allows co-developments on site

                                                                                 68
PPPs and Value for Money (VFM)
    Achieving optimal allocation of risk is the most important factor in
     structuring a PPP
-    Does the private sector’s price for taking project risks represent good value for money?
-    Is the private sector’s return on capital appropriate to the level of risk being taken?

    Facilitating and making incentives on time and on project budget
     implementation:
       – No service / no pay.
       – Incentives to cost control.
    Optimization of capital & maintenance expenditure over project life.
    Innovation in design and financing structures.
    Improving management of operational risks.

                    Optimal risk allocation  reduced cost of risk
                    Reduced cost of risk  better Value for Money
     No presumption that PPP’s will always prove better Value for Money than
                   conventional Public Sector Contracts (PSC / EPC)
                                                                                                69
(VFM) Higher Than Forecasts Costs in EPC /PPPs
Evidence on construction projects from the UK’s National Audit Office

                                         Conventional procurement (PSC)   PPP procurement
   Cost overruns for the public sector                73%                      22%
   Delay in project delivery                          70%                      24%




                                                                                            70
71
2. Funding & Risk Sharing - Fit with Project

Funding translates into;
Who should bear the demand risk?
Who will pay for the infrastructure/service?
 Payment by users - when the principal source of revenue for the private
  operator is by users , the operator bears the demand risk.
 Payment by taxpayers (i.e. public budget) means that the demand risk is
  not transferred to the operator.
The choice of funding must be based on a trade-off between:
 The marginal cost of public funds collection.
 The willingness not to exclude users from the infrastructure
  (problem associated with the payment by users).
                                                                            72
PPP Major Funding Sources
                                                          Credit   Political
                                               Loan
                             Equity   Loans            Guarantees    Risk
                                            Guarantees
                                                       /Insurance Insurance
Sponsor                        
Private
  Commercial Banks                    
  Capital Markets                    
  Insurance Cos.                                         
  Private Equity Funds               
Public
Multilateral
  IBRD                                                     
  IFC                                        
  MIGA                                                               
OPIC                                                               
Development Banks
  (IADB, EIB, EBRD, CAF,
                                                                     
 BNDES, ASD, AFDB)
Export Credit Agencies
  (Ex-Im Bank-US,ECGD -

 UK,EDC - Canada, HERMES -                                         
 Germany, COFACE - France)
                                                                               73
Managing Fiscal Risks in PPP’s
•   PPP’s create fiscal obligations that are long term and binding future generations
    and tax payers.

•   Accurate design of PPP’s requires that the fiscal cost and risk of the major
    contractual obligations be identified, quantified and mitigated.

Direct, debt-like obligations
•   Availability payment for the use of facilities
•   For PPP hospitals, schools, prisons and a like, PPP deal also requires government to
    allocate funds for government doctors, nurses, and teachers, guards who will run
    the facilities built, maintained & operated by the private sector.
Explicit contingent obligations
•   Government guarantees to repay investors cost and agreed returns
•   Revenues and exchange rate guarantees.
•   Shadow payments for assets provided by private sector.
Implicit contingent obligations
•   Taking over private debt if developer becomes financially distressed
•   Implicit use guarantees in PPA – Power Purchase Agreements, off take agreements.
                                                                                        74
3. Procurement Choice – In line with Complexity

 Classical competitive bidding aiming at minimizing financial costs fits well with
  simple contracts, whereas negotiated procedures (e.g. through competitive
  dialogue / with a set of criteria’s) fit better with complex contracts

 In terms of incentives, complex contracts fit better with Cost Plus schemes and
  simple contracts fit better with fixed price regulation schemes.

 Procurement procedures should be adapted to the project type, in order to
  prevent opportunistic behavior, and should also favor strict prequalification and
  additional award criteria. Unsustainable offers should be legally excluded.
      Classical procurement procedures are not a guarantee for fair competition:
       bid rigging, first mover advantage (incumbent's renewal), etc.
      Renegotiation & opportunism costs need to be guarded against! ( for
       example, lengthy post negotiation can jeopardize the project)



                                                                                      75
PPP Procurement Process
 Planning process

   -   Planning requires time and money - worth the investment
   -   Fund supporting project development – needed.
   -   Cross sector dialogue including Treasury - required
   -   Check and balance – are key

 Market testing

   - Testing the interest of market is crucial
   - The market condition can impact risk sharing
   - Transparency should be kept

 Procurement method - Prioritization

   -   Solicited or unsolicited proposal
   -   Prequalification, 2 envelope bidding
   -   Award criteria (VFM , PPP Versus PSC )
   -   Time management
                                                                 76
Unsolicited Proposals in PPP
•   Can be useful in early stage of PPP program especially at local governments
    level , however, often the Public Sector then lacks the fiscal and knowledge
    capacity to analyze projects

•   Attract private sector investors ( Proponents) by giving initiatives and
    incentives

•   Priority set for proposals without asking government support

•   Genuine unsolicited proposals can wash out network effect of entrenched
    infrastructure development

•   More scrutiny is required , additional requirement for value for money tests
    are needed.

•   Competition is key , opportunity for counter proposals should be given thus
    providing level playing field

•   Common is some countries like Chile, Argentina, South Korea, South
    Africa< India, Italy and Malaysia

                                                                                   77
Steps in PPPs Procurement - PPP Project Life Cycle
  What are the steps?
Project Preparation –            Service Provider Selection      Contract Management -
Funding Approval                   – Technical RFP & Bid                Financial
1. Prioritise Key Project               4. Project Dev.              7. Final Negotiation
   Objectives
2. Agree Project Concept              Team, Gov ernance,           Signing contract, financial
3. Obtain Stakeholder Approval                                               close
                                    Timeline, execution plan

     1. Service Need                  5. Bid Preparation             8. Contract Mgmt.
   Output specifications              EOI/ Short listing, RFP      Construction, monitoring,
                                                                      Dispute settlement,
  2. Option Appraisal                         Bid Doc                communications and
   Report on EPC / PPP                       Approval                finally commissioning
      options, VFM

                                        6. Bid Evaluation             9. Renegotiations
    3. Business Case
                                    Preferred bidder selection         Due to changing
 Affordably/public interest                                              conditions

         Project/                             Project                   10. Turn Over
         Funding                            Finalization
                                                                      Upon expiry of the
         Approval                             Review
                                                                    concession agreement
                                                                                            78
4. Financial Structure Choice - Balancing
 The financial structure of a project is usually composed of loans (banks or
  bonds), shareholder loans, equity and grants.

 The continuing financial crisis has shown that there should be a systematic follow-up
  of the main events occurring during the life of a contract, in order to balance spreads
  and risks:

       During the crisis: spreads have skyrocketed - projects became unfeasible.
       In the crisis: spreads have gone back but not to normal levels. If spreads are too
        low, banks cannot pay for their risk.
 One should also take into account the asymmetry regarding the way public entities
  and private operators absorb risks. The allocation of risks must take into account this
  asymmetry. Grants and/or guarantees should be adjusted accordingly.

 Due to the financial crisis, loan maturity has been shortened. State support may be
  needed.



                                                                                             79
Risk Transfer                 PPP Stakeholders & Risk Transfer
                                   Host Government / Public Authority
                                   Legal /regulatory framework & support functions
     Advisors – Legal                                                                Contracting PPP
     , Technical &                                                                   Authority (is)
     Financial
     Equity Investors
                                            SPV / Project Company
     Arranging Bank                         (Borrower) .Made up of
                 Banks Syndicate            Project Sponsors -
                                            Equity Investors.

     Hedge Providers                    Input Contracts
     Currency & Interest                Guaranteed long
     Rate, Multilaterals, P             term supply
     olitical Risk Insurers             of inputs / feedstock            Off Taker
                                                                         Guaranteed revenue stream to project. Can
                                                                         be the Public Contracting Authority or MoF

      Equipment Supplier             Contractor(s) ,EPC                               O&M Contractor(s)
      Warranties & Supply            - Risk transfer –                 Interface      Pass down of penalties for
      Agents Agreements. Can         Turnkey Contract ,                Contract       availability payments
      be bundled in EPC              penalties , bonds.                               , performance, etc.

Risk Duration                       3 – 5 Years                       25 - 30 Years ( Risk by Project Company)
                                                                                                            80
Corporate & Project Finance




             Debt                                       100

 Project Financing provided
                              Mezzanine Funds Equity provided by
       by banks / IFIs                            sponsors     81
Structuring Project Finance




                              82
Project Long Term Financing
Project cash flows must be sufficient to service (interest and principal)
All risks to lenders must be eliminated
•   Construction ,Market ,Consumption ,Operating ,Inflation & Credit risk
•   Other risks as applicable –Refinancing, Interest rate, Exchange rate
Advantages
•   Enables high debt to equity ratio , Releases Investors equity
•   Enables equity risk sharing in projects
•   Funds can invest into SPV
•   Avoids refinancing risk
Disadvantages
•   More restrictions in use of funds
•   Restrictive covenants (debt service cover ratios etc)
•   More complex documentation (risk mitigation)
•   Less flexible administration (most changes require lenders' consent)


                                                                            83
5. Management – Allow Renegotiations
 All contingencies cannot be anticipated (changes in the legal environment, force
   majeure, innovation, changes in demand, environmental and technical constraints.

 Contract will necessarily evolve over time/be renegotiated. Renegotiation clauses
   , conditions of execution , adjustment should be specified in the contract.

 Renegotiation should be viewed to the advantages of 3 parties (Public
   entity, Users, Private operator). Fair and transparent renegotiation is the essence of
   the contract.

 Necessary conditions for a good management of the life of the contract:
       Fair behavior of both parties
       Technical skills
       Experience and capacity building
       Flexibility and adaptation to local customs
       The threat of sanction (must be credible) to enable self enforced good practices.
       Non written aspects of the contractual relationship (trust, reputation, etc.) are key
        elements for success.                                                              84
Typical PPP Project Administration & Risks
                                                 Political and
                                                Macroeconomic
                                                     Risks
                                                                                              Regulatory
                                                 Shareholders –                                 Risks
                                                 Equity Investors
          FX Risks and
                                                                                 Regulatory
        Refinancing Risks                        Shareholder’s                    Authority
                                                 Agreement
              Lead / Syndicate Banks                                     Guarantees
                 & Bond Holders                                            Concession          Granting PS
                                                    SPV -                  Agreement            Authority
      Operator -                                   Project
      Production        Operation &
                        Maintenance
                                                  Company                  Purchase / Off           Services
     Operator -         Agreement(s) (O&M)                                 Take Agreement          Purchaser /
      Delivery                                                                                      Off Taker


Performance
                   Interface     Construction                                            Regulatory and
                   Agreement     Contracts                  Supply / Feedstock            Performance
    Risks                                                   Agreement                         Risks
                     Construction
                     Contractor(s)                                      Raw Material /
                                                                          Feedstock
                                                                           Supplier
                     Completion
                       Risks                                                                                 85
PPP Example Structures




                         86
PPP Regional Strategy & Readiness



      Actions?



      Diagnosis?




                                    87
MENA PPP Investments Comparisons
                           PPI Data Base – Data Source


• The PPI (Private Participation in Infrastructure) database is a multi-donor-
  funded facility and is maintained by PPIAF (Public Private Partnership
  Advisory Facility).
• The database is the most sophisticated attempt so far to create a global
  database of PPI / PPP projects which helps to understand the pattern and
  scale of PPP deals in world regions.
• The PPI database does not cover social infrastructure / PFI-model PPPs. It
  does cover Energy (electricity and natural
  gas), Telecommunications, Transport
• (airports, seaports, railways, toll roads), and Water and Sewerage
  (treatment plants and utilities).
• The PPIAF PPI database identifies four types of project: Management and
  Lease contracts; Concessions, Greenfield projects, and Divestitures /
  Privatization. Divestitures (either full or partial) are not considered PPPs.

                                                                                  88
World Regions by Sector
                           (1990 – 2010 , Total Count & Investment – million USD)
                       Sector         Project Count                                                                                     Total Investment (US$ million)
                Telecom                    798                                                                                                     761,394
                Energy (Example Next)     1,952                                                                                                    548,279
                Transport                 1,291                                                                                                    275,597
                Water and sewerage         731                                                                                                      62,543
                Grand Total               4772                                                                                                    1,647,813
              1,800,000                                                                                                                      6,000
              1,600,000                                                                                                                      5,000
              1,400,000




                                                                                                                                    Number
              1,200,000                                                                                                                      4,000
Million USD




              1,000,000                                                                                                                      3,000
                800,000
                600,000                                                                                                                      2,000
                400,000                                                                                                                      1,000
                200,000
                      0                                                                                                                          0
                          Latin America …




                                                                                                                                                     Latin America …
                                                                          Europe and…




                                                                                                                                                                                                     Europe and…
                                            East Asia and…




                                                                                                                                                                       East Asia and…
                                                                                                       Middle East…




                                                                                                                                                                                                                                  Middle East…
                                                                                        Sub-Saharan…




                                                                                                                                                                                                                   Sub-Saharan…
                                                             South Asia




                                                                                                                                                                                        South Asia
                                                                                                                      Grand Total




                                                                                                                                                                                                                                                 Grand Total
                                                                                                                                                                                                                                                    89
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework
MENA Region PPP Development Strategy and Success Framework

Mais conteúdo relacionado

Mais procurados

Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012Ezzedin Tago
 
Preparing the Dragon for Flight
Preparing the Dragon for FlightPreparing the Dragon for Flight
Preparing the Dragon for FlightJohn Smith
 
Road ppt 14 12 15 final
Road ppt 14 12 15 finalRoad ppt 14 12 15 final
Road ppt 14 12 15 finalarpitgoel075
 
IRJET- Analysis of Affordable Urban Housing Projects of Bhopal
IRJET- Analysis of Affordable Urban Housing Projects of BhopalIRJET- Analysis of Affordable Urban Housing Projects of Bhopal
IRJET- Analysis of Affordable Urban Housing Projects of BhopalIRJET Journal
 
Trends and Overview of PPP in ASEAN
Trends and Overview of PPP in ASEANTrends and Overview of PPP in ASEAN
Trends and Overview of PPP in ASEANFauziah Zen
 
Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private PartnershipDeepti Mahajan
 
Artba p3 policy recommendations
Artba p3 policy recommendations Artba p3 policy recommendations
Artba p3 policy recommendations artba
 
Department of Transportation Fiscal Year 2012 Budget Highlights
Department of Transportation Fiscal Year 2012 Budget HighlightsDepartment of Transportation Fiscal Year 2012 Budget Highlights
Department of Transportation Fiscal Year 2012 Budget HighlightsPorts-To-Plains Blog
 
Chapter1 PPPs: An Overview
Chapter1   PPPs: An OverviewChapter1   PPPs: An Overview
Chapter1 PPPs: An OverviewGowri Sundaresan
 
Road, Railway & Port projects fall short of investment targets in 11th Plan
Road, Railway & Port projects fall short of investment targets in 11th PlanRoad, Railway & Port projects fall short of investment targets in 11th Plan
Road, Railway & Port projects fall short of investment targets in 11th PlanPierre Memheld
 
Target audience
Target audienceTarget audience
Target audienceBossGee
 
Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley Roger Bazeley, USA
 
Africa Green Corporation
Africa Green CorporationAfrica Green Corporation
Africa Green CorporationGrafic.guru
 
Other Publishers: Investment Opportunities in China's Growing Infrastructure ...
Other Publishers: Investment Opportunities in China's Growing Infrastructure ...Other Publishers: Investment Opportunities in China's Growing Infrastructure ...
Other Publishers: Investment Opportunities in China's Growing Infrastructure ...Excelsior Management Solutions, LLC
 
Introduction to competitive supplier dev prog(1)
Introduction to competitive supplier dev prog(1)Introduction to competitive supplier dev prog(1)
Introduction to competitive supplier dev prog(1)Dr Lendy Spires
 

Mais procurados (18)

Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012
 
Preparing the Dragon for Flight
Preparing the Dragon for FlightPreparing the Dragon for Flight
Preparing the Dragon for Flight
 
Road ppt 14 12 15 final
Road ppt 14 12 15 finalRoad ppt 14 12 15 final
Road ppt 14 12 15 final
 
IRJET- Analysis of Affordable Urban Housing Projects of Bhopal
IRJET- Analysis of Affordable Urban Housing Projects of BhopalIRJET- Analysis of Affordable Urban Housing Projects of Bhopal
IRJET- Analysis of Affordable Urban Housing Projects of Bhopal
 
Ppp in asean
Ppp in aseanPpp in asean
Ppp in asean
 
Trends and Overview of PPP in ASEAN
Trends and Overview of PPP in ASEANTrends and Overview of PPP in ASEAN
Trends and Overview of PPP in ASEAN
 
Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private Partnership
 
Artba p3 policy recommendations
Artba p3 policy recommendations Artba p3 policy recommendations
Artba p3 policy recommendations
 
IHA Congress 2011 - Global Workshop - Jasper Oduor
IHA Congress 2011 - Global Workshop - Jasper OduorIHA Congress 2011 - Global Workshop - Jasper Oduor
IHA Congress 2011 - Global Workshop - Jasper Oduor
 
FMOC Report
FMOC ReportFMOC Report
FMOC Report
 
Department of Transportation Fiscal Year 2012 Budget Highlights
Department of Transportation Fiscal Year 2012 Budget HighlightsDepartment of Transportation Fiscal Year 2012 Budget Highlights
Department of Transportation Fiscal Year 2012 Budget Highlights
 
Chapter1 PPPs: An Overview
Chapter1   PPPs: An OverviewChapter1   PPPs: An Overview
Chapter1 PPPs: An Overview
 
Road, Railway & Port projects fall short of investment targets in 11th Plan
Road, Railway & Port projects fall short of investment targets in 11th PlanRoad, Railway & Port projects fall short of investment targets in 11th Plan
Road, Railway & Port projects fall short of investment targets in 11th Plan
 
Target audience
Target audienceTarget audience
Target audience
 
Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley
 
Africa Green Corporation
Africa Green CorporationAfrica Green Corporation
Africa Green Corporation
 
Other Publishers: Investment Opportunities in China's Growing Infrastructure ...
Other Publishers: Investment Opportunities in China's Growing Infrastructure ...Other Publishers: Investment Opportunities in China's Growing Infrastructure ...
Other Publishers: Investment Opportunities in China's Growing Infrastructure ...
 
Introduction to competitive supplier dev prog(1)
Introduction to competitive supplier dev prog(1)Introduction to competitive supplier dev prog(1)
Introduction to competitive supplier dev prog(1)
 

Destaque

The Entrepreneurial (Risk-Taking) State
The Entrepreneurial (Risk-Taking) State The Entrepreneurial (Risk-Taking) State
The Entrepreneurial (Risk-Taking) State imec
 
Mariana Mazzucato: The Entrepeneurial State
Mariana Mazzucato: The Entrepeneurial StateMariana Mazzucato: The Entrepeneurial State
Mariana Mazzucato: The Entrepeneurial StateIKT-Norge
 
foss4g2009tokyo_Takasu_rtklib
foss4g2009tokyo_Takasu_rtklibfoss4g2009tokyo_Takasu_rtklib
foss4g2009tokyo_Takasu_rtklibOSgeo Japan
 
Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...
Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...
Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...ghoshk
 
Knowledge Management in Software Development
Knowledge Management in Software DevelopmentKnowledge Management in Software Development
Knowledge Management in Software DevelopmentKarsten Jahn
 
MIDDLE EAST INVESTMENT OPPORTUNITES FOR PRIVATE EQUITY
MIDDLE EAST  INVESTMENT OPPORTUNITES FOR PRIVATE EQUITYMIDDLE EAST  INVESTMENT OPPORTUNITES FOR PRIVATE EQUITY
MIDDLE EAST INVESTMENT OPPORTUNITES FOR PRIVATE EQUITYsanthoshkrish
 
Mena pharmaceuticals steps for successful model tph
Mena pharmaceuticals steps for successful model tphMena pharmaceuticals steps for successful model tph
Mena pharmaceuticals steps for successful model tphWesam Nehad
 
Kenya Pharmaceutical Regulatory Overview and Opportunities
Kenya Pharmaceutical Regulatory Overview and OpportunitiesKenya Pharmaceutical Regulatory Overview and Opportunities
Kenya Pharmaceutical Regulatory Overview and Opportunitiestoroiticham
 
Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...
Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...
Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...Karsten Jahn
 
African Pharmaceutical Sector: A Global Opportunity
African Pharmaceutical Sector: A Global OpportunityAfrican Pharmaceutical Sector: A Global Opportunity
African Pharmaceutical Sector: A Global OpportunityPharmaAfrica
 
Pharmaceutical challenges in Africa
Pharmaceutical challenges in AfricaPharmaceutical challenges in Africa
Pharmaceutical challenges in AfricaPharmaAfrica
 
East African Pharmaceutical Sector: Opportunities and Challenges
East African Pharmaceutical Sector: Opportunities and ChallengesEast African Pharmaceutical Sector: Opportunities and Challenges
East African Pharmaceutical Sector: Opportunities and ChallengesPharmaAfrica
 
Transforming Railway Infrastructure in Ghana through Public Private Partnersh...
Transforming Railway Infrastructure in Ghana through Public Private Partnersh...Transforming Railway Infrastructure in Ghana through Public Private Partnersh...
Transforming Railway Infrastructure in Ghana through Public Private Partnersh...jhmensah
 

Destaque (20)

PPP: North-South Railway System
PPP: North-South Railway System PPP: North-South Railway System
PPP: North-South Railway System
 
The Entrepreneurial (Risk-Taking) State
The Entrepreneurial (Risk-Taking) State The Entrepreneurial (Risk-Taking) State
The Entrepreneurial (Risk-Taking) State
 
Ahmed Serry CV
Ahmed Serry CVAhmed Serry CV
Ahmed Serry CV
 
Mariana Mazzucato: The Entrepeneurial State
Mariana Mazzucato: The Entrepeneurial StateMariana Mazzucato: The Entrepeneurial State
Mariana Mazzucato: The Entrepeneurial State
 
foss4g2009tokyo_Takasu_rtklib
foss4g2009tokyo_Takasu_rtklibfoss4g2009tokyo_Takasu_rtklib
foss4g2009tokyo_Takasu_rtklib
 
Supply chain management
Supply chain managementSupply chain management
Supply chain management
 
Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...
Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...
Ghosh Kingshuk (Pharmaceutical Market Trend Analysis In The Middle East &amp;...
 
Knowledge Management framework of Hansen, Earl and Alvesson
Knowledge Management framework of Hansen, Earl and AlvessonKnowledge Management framework of Hansen, Earl and Alvesson
Knowledge Management framework of Hansen, Earl and Alvesson
 
Kuwait PPP Transport Projects
Kuwait PPP Transport ProjectsKuwait PPP Transport Projects
Kuwait PPP Transport Projects
 
New Approaches to Knowledge Management (part 1)
New Approaches to Knowledge Management (part 1)New Approaches to Knowledge Management (part 1)
New Approaches to Knowledge Management (part 1)
 
Knowledge Management in Software Development
Knowledge Management in Software DevelopmentKnowledge Management in Software Development
Knowledge Management in Software Development
 
MIDDLE EAST INVESTMENT OPPORTUNITES FOR PRIVATE EQUITY
MIDDLE EAST  INVESTMENT OPPORTUNITES FOR PRIVATE EQUITYMIDDLE EAST  INVESTMENT OPPORTUNITES FOR PRIVATE EQUITY
MIDDLE EAST INVESTMENT OPPORTUNITES FOR PRIVATE EQUITY
 
Mena pharmaceuticals steps for successful model tph
Mena pharmaceuticals steps for successful model tphMena pharmaceuticals steps for successful model tph
Mena pharmaceuticals steps for successful model tph
 
Kenya Pharmaceutical Regulatory Overview and Opportunities
Kenya Pharmaceutical Regulatory Overview and OpportunitiesKenya Pharmaceutical Regulatory Overview and Opportunities
Kenya Pharmaceutical Regulatory Overview and Opportunities
 
Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...
Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...
Codified vs. Personalized – A Vertical Approach to the Dilemma of the Knowled...
 
Ppp train station
Ppp train stationPpp train station
Ppp train station
 
African Pharmaceutical Sector: A Global Opportunity
African Pharmaceutical Sector: A Global OpportunityAfrican Pharmaceutical Sector: A Global Opportunity
African Pharmaceutical Sector: A Global Opportunity
 
Pharmaceutical challenges in Africa
Pharmaceutical challenges in AfricaPharmaceutical challenges in Africa
Pharmaceutical challenges in Africa
 
East African Pharmaceutical Sector: Opportunities and Challenges
East African Pharmaceutical Sector: Opportunities and ChallengesEast African Pharmaceutical Sector: Opportunities and Challenges
East African Pharmaceutical Sector: Opportunities and Challenges
 
Transforming Railway Infrastructure in Ghana through Public Private Partnersh...
Transforming Railway Infrastructure in Ghana through Public Private Partnersh...Transforming Railway Infrastructure in Ghana through Public Private Partnersh...
Transforming Railway Infrastructure in Ghana through Public Private Partnersh...
 

Semelhante a MENA Region PPP Development Strategy and Success Framework

Getting public-private partnerships going: good practices from the MENA region
Getting public-private partnerships going: good practices from the MENA regionGetting public-private partnerships going: good practices from the MENA region
Getting public-private partnerships going: good practices from the MENA regionOECDglobal
 
Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010Parti Djibouti
 
PIDA Interconnecting, integrating and transforming a continent African Union
PIDA Interconnecting, integrating and transforming a continent African Union PIDA Interconnecting, integrating and transforming a continent African Union
PIDA Interconnecting, integrating and transforming a continent African Union Dr Lendy Spires
 
Role of Carbon Finance Support Instruments in Africa
Role of Carbon Finance Support Instruments in AfricaRole of Carbon Finance Support Instruments in Africa
Role of Carbon Finance Support Instruments in Africareetasharma201
 
GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013QNB Group
 
OSAA @OECD Side Event #FFD3 Concept Note
OSAA @OECD Side Event #FFD3 Concept NoteOSAA @OECD Side Event #FFD3 Concept Note
OSAA @OECD Side Event #FFD3 Concept NoteDr Lendy Spires
 
Municipal Finances in India and Alternative Sources of Municipal Finance
Municipal Finances in India and Alternative Sources of Municipal FinanceMunicipal Finances in India and Alternative Sources of Municipal Finance
Municipal Finances in India and Alternative Sources of Municipal FinanceRavikant Joshi
 
Public private partnerships - the case of lebanon first ppp - pierre el-hnoud
Public private partnerships - the case of lebanon first ppp - pierre el-hnoudPublic private partnerships - the case of lebanon first ppp - pierre el-hnoud
Public private partnerships - the case of lebanon first ppp - pierre el-hnoudPierre Hnoud
 
Emerging markets’ infrastructural sector — at a tipping point aranca special ...
Emerging markets’ infrastructural sector — at a tipping point aranca special ...Emerging markets’ infrastructural sector — at a tipping point aranca special ...
Emerging markets’ infrastructural sector — at a tipping point aranca special ...Aranca
 
Sectoral Infrastructure Development
Sectoral Infrastructure DevelopmentSectoral Infrastructure Development
Sectoral Infrastructure DevelopmentGAURAV. H .TANDON
 
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016Anindya Roychowdhury
 
Qnb group government spending will be significantly higher than budgeted in 2...
Qnb group government spending will be significantly higher than budgeted in 2...Qnb group government spending will be significantly higher than budgeted in 2...
Qnb group government spending will be significantly higher than budgeted in 2...QNB Group
 
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubrePresentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubreProColombia
 
slEconomics - Models for funding infrastructure in South Africa - Nov 2013
slEconomics  - Models for funding infrastructure in South Africa - Nov 2013slEconomics  - Models for funding infrastructure in South Africa - Nov 2013
slEconomics - Models for funding infrastructure in South Africa - Nov 2013Stephen Labson
 

Semelhante a MENA Region PPP Development Strategy and Success Framework (20)

3
33
3
 
Getting public-private partnerships going: good practices from the MENA region
Getting public-private partnerships going: good practices from the MENA regionGetting public-private partnerships going: good practices from the MENA region
Getting public-private partnerships going: good practices from the MENA region
 
PIDA Brief Financing
PIDA Brief FinancingPIDA Brief Financing
PIDA Brief Financing
 
Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010
 
Indian budget 2011 2012
Indian budget 2011 2012Indian budget 2011 2012
Indian budget 2011 2012
 
PIDA Interconnecting, integrating and transforming a continent African Union
PIDA Interconnecting, integrating and transforming a continent African Union PIDA Interconnecting, integrating and transforming a continent African Union
PIDA Interconnecting, integrating and transforming a continent African Union
 
Union budget fy12
Union budget fy12Union budget fy12
Union budget fy12
 
upload web RK B.O.T PROGRAM.pdf
upload web RK B.O.T PROGRAM.pdfupload web RK B.O.T PROGRAM.pdf
upload web RK B.O.T PROGRAM.pdf
 
Role of Carbon Finance Support Instruments in Africa
Role of Carbon Finance Support Instruments in AfricaRole of Carbon Finance Support Instruments in Africa
Role of Carbon Finance Support Instruments in Africa
 
GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013
 
OSAA @OECD Side Event #FFD3 Concept Note
OSAA @OECD Side Event #FFD3 Concept NoteOSAA @OECD Side Event #FFD3 Concept Note
OSAA @OECD Side Event #FFD3 Concept Note
 
Municipal Finances in India and Alternative Sources of Municipal Finance
Municipal Finances in India and Alternative Sources of Municipal FinanceMunicipal Finances in India and Alternative Sources of Municipal Finance
Municipal Finances in India and Alternative Sources of Municipal Finance
 
Public private partnerships - the case of lebanon first ppp - pierre el-hnoud
Public private partnerships - the case of lebanon first ppp - pierre el-hnoudPublic private partnerships - the case of lebanon first ppp - pierre el-hnoud
Public private partnerships - the case of lebanon first ppp - pierre el-hnoud
 
Budget Presentation
Budget PresentationBudget Presentation
Budget Presentation
 
Emerging markets’ infrastructural sector — at a tipping point aranca special ...
Emerging markets’ infrastructural sector — at a tipping point aranca special ...Emerging markets’ infrastructural sector — at a tipping point aranca special ...
Emerging markets’ infrastructural sector — at a tipping point aranca special ...
 
Sectoral Infrastructure Development
Sectoral Infrastructure DevelopmentSectoral Infrastructure Development
Sectoral Infrastructure Development
 
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
 
Qnb group government spending will be significantly higher than budgeted in 2...
Qnb group government spending will be significantly higher than budgeted in 2...Qnb group government spending will be significantly higher than budgeted in 2...
Qnb group government spending will be significantly higher than budgeted in 2...
 
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubrePresentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
 
slEconomics - Models for funding infrastructure in South Africa - Nov 2013
slEconomics  - Models for funding infrastructure in South Africa - Nov 2013slEconomics  - Models for funding infrastructure in South Africa - Nov 2013
slEconomics - Models for funding infrastructure in South Africa - Nov 2013
 

Mais de Loay Ghazaleh MBA, BSc Civil Eng.

Successfully Delivering PPP Tolled Bridges and Highway Projects
Successfully Delivering PPP Tolled Bridges and Highway ProjectsSuccessfully Delivering PPP Tolled Bridges and Highway Projects
Successfully Delivering PPP Tolled Bridges and Highway ProjectsLoay Ghazaleh MBA, BSc Civil Eng.
 
Modular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of HousingModular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of HousingLoay Ghazaleh MBA, BSc Civil Eng.
 
Developing Facilities Management in a Rapidly Changing Business Environment
Developing Facilities Management in a Rapidly Changing Business EnvironmentDeveloping Facilities Management in a Rapidly Changing Business Environment
Developing Facilities Management in a Rapidly Changing Business EnvironmentLoay Ghazaleh MBA, BSc Civil Eng.
 
Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...
Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...
Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...Loay Ghazaleh MBA, BSc Civil Eng.
 

Mais de Loay Ghazaleh MBA, BSc Civil Eng. (20)

Dubai sep. 2019 smart cities financing - loay ghazaleh
Dubai sep. 2019   smart cities financing - loay ghazalehDubai sep. 2019   smart cities financing - loay ghazaleh
Dubai sep. 2019 smart cities financing - loay ghazaleh
 
PPP in Modal Transport
PPP in Modal TransportPPP in Modal Transport
PPP in Modal Transport
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Privatization and Concessions (PPP) In Airports
Privatization and Concessions (PPP) In AirportsPrivatization and Concessions (PPP) In Airports
Privatization and Concessions (PPP) In Airports
 
Successfully Delivering PPP Tolled Bridges and Highway Projects
Successfully Delivering PPP Tolled Bridges and Highway ProjectsSuccessfully Delivering PPP Tolled Bridges and Highway Projects
Successfully Delivering PPP Tolled Bridges and Highway Projects
 
ITS in Bahrain
ITS in BahrainITS in Bahrain
ITS in Bahrain
 
Exploring Renewable Energy Technologies in MENA Region
Exploring Renewable Energy Technologies in MENA RegionExploring Renewable Energy Technologies in MENA Region
Exploring Renewable Energy Technologies in MENA Region
 
Modular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of HousingModular Construction Solution For Rapid Cost-effective Development Of Housing
Modular Construction Solution For Rapid Cost-effective Development Of Housing
 
Bridges Functionality and Aesthetics
Bridges Functionality and AestheticsBridges Functionality and Aesthetics
Bridges Functionality and Aesthetics
 
Developing Facilities Management in a Rapidly Changing Business Environment
Developing Facilities Management in a Rapidly Changing Business EnvironmentDeveloping Facilities Management in a Rapidly Changing Business Environment
Developing Facilities Management in a Rapidly Changing Business Environment
 
The Future of Passenger Railways
The Future of Passenger RailwaysThe Future of Passenger Railways
The Future of Passenger Railways
 
Energy From Waste Options
Energy From Waste OptionsEnergy From Waste Options
Energy From Waste Options
 
Today's Contracting - Contracts Risks and Disputes
Today's Contracting - Contracts Risks and Disputes Today's Contracting - Contracts Risks and Disputes
Today's Contracting - Contracts Risks and Disputes
 
Evolving ITS Solutions
Evolving ITS SolutionsEvolving ITS Solutions
Evolving ITS Solutions
 
Loay Ghazaleh Profile and Projects Portfolio - March 2018
Loay Ghazaleh Profile and Projects Portfolio - March 2018Loay Ghazaleh Profile and Projects Portfolio - March 2018
Loay Ghazaleh Profile and Projects Portfolio - March 2018
 
Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...
Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...
Monitoring and Control Technologies to Assess Climate Change and Rising Sea L...
 
Smart High Performanc Facades
Smart High Performanc FacadesSmart High Performanc Facades
Smart High Performanc Facades
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 

Último

Stock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfStock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfMichael Silva
 
2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptx2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptxHenry Tapper
 
Kempen ' UK DB Endgame Paper Apr 24 final3.pdf
Kempen ' UK DB Endgame Paper Apr 24 final3.pdfKempen ' UK DB Endgame Paper Apr 24 final3.pdf
Kempen ' UK DB Endgame Paper Apr 24 final3.pdfHenry Tapper
 
cost of capital questions financial management
cost of capital questions financial managementcost of capital questions financial management
cost of capital questions financial managementtanmayarora23
 
Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...Amil baba
 
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...Amil baba
 
NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...
NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...
NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...Amil baba
 
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...Amil baba
 
Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024Champak Jhagmag
 
Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024Devarsh Vakil
 
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptAnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptPriyankaSharma89719
 
Financial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptxFinancial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptxsimon978302
 
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Amil baba
 
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...Amil baba
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Commonwealth
 
Liquidity Decisions in Financial management
Liquidity Decisions in Financial managementLiquidity Decisions in Financial management
Liquidity Decisions in Financial managementshrutisingh143670
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGeckoCoinGecko
 
Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024Money Forward
 
The AES Investment Code - the go-to counsel for the most well-informed, wise...
The AES Investment Code -  the go-to counsel for the most well-informed, wise...The AES Investment Code -  the go-to counsel for the most well-informed, wise...
The AES Investment Code - the go-to counsel for the most well-informed, wise...AES International
 

Último (20)

Stock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfStock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdf
 
2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptx2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptx
 
Kempen ' UK DB Endgame Paper Apr 24 final3.pdf
Kempen ' UK DB Endgame Paper Apr 24 final3.pdfKempen ' UK DB Endgame Paper Apr 24 final3.pdf
Kempen ' UK DB Endgame Paper Apr 24 final3.pdf
 
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth AdvisorsQ1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
 
cost of capital questions financial management
cost of capital questions financial managementcost of capital questions financial management
cost of capital questions financial management
 
Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
Uae-NO1 Pakistani Amil Baba Real Amil baba In Pakistan Najoomi Baba in Pakist...
 
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
Uae-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Ra...
 
NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...
NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...
NO1 Certified Black Magic Removal in Uk kala jadu Specialist kala jadu for Lo...
 
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
 
Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024Unveiling Business Expansion Trends in 2024
Unveiling Business Expansion Trends in 2024
 
Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024Market Morning Updates for 16th April 2024
Market Morning Updates for 16th April 2024
 
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.pptAnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
AnyConv.com__FSS Advance Retail & Distribution - 15.06.17.ppt
 
Financial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptxFinancial Preparation for Millennia.pptx
Financial Preparation for Millennia.pptx
 
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
Uae-NO1 Kala Jadu specialist Expert in Pakistan kala ilam specialist Expert i...
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]
 
Liquidity Decisions in Financial management
Liquidity Decisions in Financial managementLiquidity Decisions in Financial management
Liquidity Decisions in Financial management
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko
 
Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024
 
The AES Investment Code - the go-to counsel for the most well-informed, wise...
The AES Investment Code -  the go-to counsel for the most well-informed, wise...The AES Investment Code -  the go-to counsel for the most well-informed, wise...
The AES Investment Code - the go-to counsel for the most well-informed, wise...
 

MENA Region PPP Development Strategy and Success Framework

  • 1. Regional Convergence in PPP MENA PPP Projects Success Framework – Regional PPP Development Strategy 3rd Annual ME PPP – Qatar, February 2012 Loay Ghazaleh – Advisor - B. Sc. Civil Eng. , MBA 1
  • 2. Presentation Index MENA PPP Scio - Economic Outlook MENA PPP Initiatives / Early Successes PPP Global Adaptation / Learning PPP Options & Projets Structure PPP Projets Success Framework PPP Regional Deveopment Strategy 2
  • 3. MENA PPP Socioeconomic Outlook Balancing Factors or Another Europe in 5 Years ! Cash Flow - PPP Planning Lifecycle Costs – must comply – needed for to repayments to legislation, poli prevent delays cies and due to cash guidelines shortages Budget / Affordability - Project commitments framework to be reflected in the budget 3
  • 4. MENA Infrastructure Supply Side • Relatively high infrastructure investment in recent years has succeeded in ensuring basic infrastructure access to the vast majority of MENA citizens, yet significant infrastructure investments are needs coupled with financial pressures on Government debts and budget deficits • The connection rate to the electricity grid by households is around 90 percent; access to acceptable water and sanitation services is above 70 percent, however, connectivity for the most part utilizes old / inefficient systems and industrial connectivity is still way below needed capacity. • The penetration of mobile telephony has reached the level witnessed in industrialized countries. • Paved roads represent between 60 to 70 percent of the total road network. 4
  • 5. MENA Infrastructure Demand Forecast • There are some considerable challenges that MENA countries need to overcome in order to move the infrastructure agenda forward . • Good demand drivers exist like attractive investment alternatives, pension fund and insurance companies diversification into new asset class and poor historical Public output performance • The installed generation capacity of the electricity sector is estimated to be 20 percent below the aggregate demand for electricity across countries in MENA. • The prevalence of highly subsidized electricity & water tariffs induces wasteful use of electricity& water therefore increasing pressures for expansion of electricity generation capacity. • Energy & Water subsidies cost the region the equivalent of 10 percent of its GDP in 2006, whereas reducing these subsidies could raise the region GDP by 3 - 4 percent. • Urban congestion is growing and therefore increasing transaction costs for businesses or commuting times for workers (In Cairo, the average speed of vehicles is as low as 9 km/h ) • It is estimated that the total economic and social cost of congestion is about 5 percent of GDP. In Teheran, it is estimated that commuters spent around 4.5 million hours/day in traffic. • The quality and reliability of Infrastructure services are a real challenge which constrains competitiveness, regional economic activity and growth prospects 5
  • 6. MENA Infrastructure Investment Forecast • Private investments in infrastructure in MENA have grown significantly since 1994, but at a lower rate than in other regions. • MENA countries need to create 40 million new jobs in the next ten years to meet the fast growing labor force. • This will require sustaining the economic growth at around 7 percent per year in the next ten years which cannot be achieved without significant investments in infrastructure. • The annual volume of infrastructure projects financed in MENA is estimated to have grown from US$25 billion in 2007 to US$27 billion in 2008,before sharply declining by June 2009 to US$6 billion due the global financial crisis (Investments in PPP in the Middle East and North Africa almost tripled between 2000 and 2007) • Middle Income Countries in MENA will need to invest the equivalent of 9.2 percent of their yearly GDP, in order to sustain their economic growth prospects. This represents a total investment effort between US$75 to 100 billion a year, of which 33 percent is earmarked for the maintenance of the existing stock of infrastructure. • The Arab world invests about $60 billion a year in infrastructure, but to sustain current growth rates, it needs about $100 billion annually. • To meet this $40 billion gap, a smart mix of public sector engagement in coordination with financing and expertise from the private sector is essential. 6
  • 7. Opportunities in GCC Power, Utilities and Infrastructure • Long-standing problems like high unemployment, limited access to finance and weak regulatory frameworks are the forefronts in MENA Region. • There are more live projects in the MENA region than anywhere else • Qatar are planning projects worth $20 billion over 5 years • Saudi Arabia is planning to spend $400 billion in the same period • Oman is budgeting $2.43 billion for capital investments in 2010 • Abu Dhabi is spending $68 billion in public transport schemes alone • Oman projecting a total government spending of $10 billion for the construction industry in year 2012, an increase of 23 per cent over 2011. 7
  • 8. Opportunities in GCC Transport Sector • The GCC Transport and Railways Conference held in Qatar, October, 2011 (Sponsored by Qatar Railways Company (RAIL) in association with the General Secretariat of the GCC, the Federation of GCC Chambers, the Qatar Chamber of Commerce and Industry, and others) • Investments of more than US$ 200 Billion already allocated to the development of transport systems, with the rail networks and metro projects reaching US$ 100 Billion. • The national GCC railway projects, a 2200 km network that will be carry passengers and goods at speeds of 200 km/h and 80-120 km/h, and will link the six Gulf countries at a total cost of more than US$ 15.4 billion. Commissioning of the entire network is expected by 2018 A.D. • It’s forecasted that GCC GDP to reach around US$ 2 trillion and a total population of around 53 million in the year 2020 A.D. 8
  • 9. Opportunities in MENA Social Housing • Affordable housing for the MENA region has an estimated shortfall of 3.5 million units -JLL Consultancy – 2012. • Saudi Arabia has the largest shortfall in the Gulf of 500,000 plus homes followed by 40,000 homes in Bahrain, 20,000 in the UAE and 15,000 in Oman . • KSA Construction Housing Pipeline Projects valued at US$ 29 billion for 2012. • Sharjah has a shortfall of 5,000 affordable homes. Sharjah ruler unveiled initiate in 2012 for affordable housing. • Bahrain government signed early 2012 a record BD208m ($550m) with a local developer to build more than 4,000 affordable homes. • Saudi Arabia needs 1.65 million new homes by 2015 (275,000 units a year). Total commitment is $130bn on social projects with $67bn allocated for 500,000 new homes and $400 billion for infrastructure projects. • Bahrain forecasts the need for about 350,000 new residential units to be added to existing stock by 2030 with $1.1bn to be spent every year up to 2020, and then $242m annually up to 2030, (EDB report). 9
  • 10. GCC PPP Activity Update (KFH 2010 report) • With huge government surpluses, securing finance is not the overriding factor behind the PPP push in the GCC countries, rather, it is the goal to deliver projects more efficiently, grant the private sector a greater economic role and assist with the diversification of the local economy. • Since 2010; over 50 PPP contracts were signed in the GCC region. These projects require investments of more than USD 60 billion. • As of September 2010, the UAE had signed off an estimated USD20 billion worth of PPPs, with some USD7 billion accounted for by Abu Dhabi's utility sector. • Kuwait government rolled out in mid-2010 through Partnerships Technical Bureau (PTB) – a PPP unit - PPP program comprising 32 projects and requiring investment of USD28 billion in various sectors - Transportation, real estate, healthcare, utility projects and recycling factories under B.O.T system with the largest being the estimated USD10 billion Kuwait national rail scheme. 10
  • 11. PPP Pipeline Projects – GCC Mar-10 KSA Airport Cities PPP Jul-10 KSA Airport Cities PPP Aug-10 KSA High Speed Railway PPP Sep-10 KSA - GCC Railway Network PPP Apr-10 KSA - Jeddah Airport PPP Aug-11 KSA - Mecca Mass Rail Transit PPP Apr-10 KSA - Medina Airport PPP Jul-10 KSA - Medina Medina International Airport PPP Aug-10 Kuwait Metro Rail PPP Sep-11 Kuwait Recycling factories PPP / B.O.T Sep-10 Oman Railway Network PPP Jul-11 Qatar - Doha Metro PPP Oct-10 UAE Railway PPP Dec-10 UAE Union Railway PPP Aug-10 UAE - Abu Dhabi Mafraq-Ghweifat Highway PPP Jul-11 UAE - Abu Dhabi Airport PPP Oct-10 UAE - Dubai Water PPP 11
  • 12. PPP Pipeline Projects – Rest of MENA Oct-10 Egypt Rod el-Farag Highway PPP Sep-11 Egypt Egyptian Refining Company Sep-11 Egypt Suez 650 MW Steam Thermal Plant Sep-11 Egypt Taxi Replacement Scheme Jul-10 Egypt - Alexandria University Hospital PPP Jul-11 Egypt - Alexandria Hospital PPP Feb-10 Egypt - Cairo Wastewater treatment plant PPP Jul-10 Egypt - Cairo-Alexandria Cairo-Alexandria Freeway PPP Sep-10 Jordan Rail Transit / Way PPP Jul-10 Jordan - Amman Light Rail PPP Jul-10 Jordan - Amman Ring Road Highway PPP Sep-11 Morocco Railway Line Sep-11 Morocco - Casablanca Drinking Water Supply -Rabat Hasdrubal Oil and Gas Field Sep-11 Tunisia Development Sep-11 Tunisia Road Project VI 12
  • 13. MENA PPP Initiatives / Successes 13
  • 14. MENA PPP Environment • There are some considerable challenges for MENA region in moving the infrastructure agenda forward. • PPP investments in MENA region Countries have essentially been contractual rather than being based on a larger legislative framework. • Some ministries in some countries have developed expertise in structuring a very specific PPP category like telecommunications, roads or sanitary / water. • The procurement process, dispute resolution and regulation / tariff setting arrangements have generally been subject to a contractual arrangement rather than independent laws, regulations and regulators. 14
  • 15. GCC PPP Activity in the Last 10 Years (Kuwait Finance House – KFH- 2010 report) • GCC PPP contracts during the last ten years amounted to USD 628 billion with over 100 PPP-type agreements, of which half can be classified as management contracts. • In terms of PPP deals concluded, Saudi Arabia has the highest number at 45 with power and desalination's share of the PPP market was near 90 percent of the total spent. • Management contracts (Often seen as the first step towards privatizations) have been used extensively in used in regional seaport and airports projects. • The UAE and Saudi Arabia represent the largest markets for PPP especially IWPP (energy and water projects). • The first IPP in GCC (Al-Manah independent power project ) was signed in 1994 in Oman. • In 1998 Abu Dhabi successfully launched the restructuring of the Abu Dhabi utility sector and formed Abu Dhabi Water Electricity Authority (ADWEA) on BOO basis. • Oman re-launched its own utility privatization program in 1999 and was followed in 2000 by Qatar and in 2003 by both Bahrain and Saudi Arabia. • In 2002, the region's first sewage treatment plant (STP) PPP was awarded at Sulaibiya in Kuwait (USD 400 million) 15
  • 16. Regional Infrastructure Regulatory Forum - December 2009 • Jordan’s Ministry of Planning and International Cooperation (MOPIC), and in collaboration with the Public-Private Partnerships Infrastructure Facility (PPIAF) and the International Finance Corporation (IFC) launched in Amman on December 7, 2009, the first Regional Conference on Infrastructure Reform and Regulation in the MENA region. • The Conference adopted a final resolution to launch a process towards the establishment of the “Middle East and North Africa Infrastructure Regulatory Forum” of which the objectives will be to promote the cooperation among infrastructure regulators within and across countries in MENA. • A working group was formed to work jointly with World Bank in bringing the process forward. The Membership of the Forum will be open to all relevant organizations responsible for regulation and that are based in the MENA states. 16
  • 17. Middle East and North Africa Infrastructure Regulatory Forum • Cooperation among stakeholders , regulators dialogue and knowledge- sharing can serve to; - Accelerate reform progress, - Promote best practice and - Enhance the harmonization of infrastructure networks. - promote the adoption of common rules, norms and standards, • A multi-sector regional Forum of infrastructure Regulation can serve as a valuable platform for - Experience and information sharing across borders and sectors, - Problem-solving, and the dissemination of best practices. - Knowledge sharing center providing capacity building services 17
  • 18. Arab Financing Facility for Infrastructure (AFFI) World Bank Group & Islamic Development Bank Infrastructure Facility • The World Bank Group (IFC), in cooperation with the Islamic Development Bank, set up a $1 billion facility (the public side of investments will be financed via an initial $200 million from the World Bank) to close the infrastructure gap in the Middle East and North Africa. • This regional investment vehicle supports both conventional and Shariah- compliant investment in infrastructure which will attract untapped, alternative sources of financing.” • The Facility focus is cross-border PPP infrastructure projects like electricity networks and rail, road and maritime networks and projects with regional impact like the plans for large-scale concentrated solar power production in Morocco to increase the regional integration and competitiveness. • IFC supports cross-border projects that commercial banks would consider too risky without IFC’s involvement. • World Bank lending to the MENA region for infrastructure, including electricity, transport and water, has exceeded $1 billion a year. 18
  • 19. ADB (African Development Bank) Investment Update North African Countries : Algeria, Egypt, Libya, Mauritania, Morocco, and Tunisia. • The Bank Group started operations in the North Africa sub region in 1968 – one year after the other sub regions. • Loan and grant approvals for the sub region totaled UA 1.47 billion in 2010, which is a rise of 40.0 % above the 2009 level of UA 1.05 billion. ( ADB uses UA units of accounts which is SDR and is nearly equivalent to 1.5 USD) • North Africa’s approvals represented 40 % of total Bank Group approvals, which makes it the main beneficiary sub region during the year. The key projects approved for North Africa were: • Suez 650 MW Steam Cycle Thermal Power Plant in Egypt; • Increasing capacity on Tangiers–Marrakech Railway Line in Morocco; • Road Project VI in Tunisia; • Drinking Water Supply in the Rabat Casablanca in Morocco; • Egyptian Refining Company Project in Egypt; • National Program for Taxi Replacement Scheme in Egypt; • Oil and Gas Field Development Project in Tunisia; • Public Administration Reform Support Program, Phase IV in Morocco. 19
  • 20. IFC-World Bank  IFC is currently active in both projects financing and advisory services in the MENA region ( GCC countries are excluded from the financing)  IFC mission is to foster sustainable economic growth in developing countries by financing private sector investment, mobilizing capital in the international financial markets, and providing advisory services to businesses and governments.  IFC has expanded its advisory services to improve the business enabling environment and encourage public-private partnerships for the development of infrastructure.  Reducing infrastructure bottlenecks—especially in transportation& power sector is a strategic priority for IFC to support the region’s sustained long term growth. 20
  • 21. IFC-World Bank Advisory - 2010 EGYPT SAUDI ARABIA • Cairo-Alexandria Freeway • Airport cities • Alexandria University • Madinah International Hospitals Airport JORDAN SYRIA • Amman Ring-Road • First Independent Power • Amman Light Rail Project PAKISTAN YEMEN • FAISALABAD ELECTRIC • First Independent Power SUPPLY COMPANY (FESCO) Project 21
  • 22. MENA PPP Laws • PPP draft law to be approved in Lebanon. - October 23, 2010 • Dubai´s PPP law will be approved in the first quarter of 2011- drafted by Roads and Transport Authority (TRA) but it is not specific to transport- January 13, 2011 • PPP law draft ready for private comments in Jordan (Privatization law was passed in Jordan in year 2000)- July 12, 2010 • PPP law for Egypt ( under process) - drafted by Finance Ministry's Public- Private Partnership (PPP) Central Unit - August 23, 2010 • In 2009 Kuwait announced its intention to pursue the private power route. 22
  • 23. MENA PPP Government Initiatives Country Sectors Law PPP Unit Jordan water, airport, ring road, , airport Privatization & PPP Yes Lebanon Energy (IPP 435 MW) Privatization & PPP Yes Egypt Rail, roads, water, STP, health, education Privatization & PPP Yes Algeria Rail, roads Project wise Laws ? Tunisia Solar, roads, oil & gas (production sharing) Project wise Laws Yes Morocco Solar, railway, water transmission. Project wise Laws Yes Bahrain Energy (IPP),STP, waste treat. , housing Mortgage - Housing Yes Qatar Metro Sector Laws MoBaT Kuwait STP, metro, railway, recycling factories. PPP PTB UAE Energy (IWPP), water taxi, airport PPP RTA Oman Energy (IPP) STP, railway, housing Mortgage - Housing ? Saudi Arabia IWPP, STP, housing, airport Cities, GCC rail Mortgage - Housing ? Yemen IPP (400 MW) Sector Law ? 23
  • 24. Jordan - Water Sector • Since 1997, the Government continually issued strategy, policies and investment program: • 2002 – 2011 Sector Plan and Investment Program • Action Plan 2002 – 2006. • Water Utility Policy • Ground Water, Wastewater and Irrigation Policies • New Water Strategy for Jordan for Water Demand Management (WDM) and Public Private Partnership (PPP) • Institutional responsibilities lies with Ministry of Water and Irrigation (MWI) • Management Contract selected due to • Improvement of Services with Reduced Risks to Government • Results in Significant Improvement, in System Operation • Improvement of Organizational Reform of Operations • Good First Step Towards Significant PPP 24
  • 25. Egypt – Full PPP Program Egypt has led MENA Countries with 22 PPP Deals valued at $15.4bn achieving financial closure between 1990 and 2007 Performance-based contracts under concession (affordability or a hybrid of both). • Output is specified by Line Ministries while input is by the private sector • Under the PPP contract the Government retains total strategic control • Adoption and localisation of international successful PPP models (UK based) • Supportive legislative environment , new legal framework for PPP projects (Draft under finalization for Submission to Cabinet and Parliament) Standard PPP Contracts • Standardization of procurement documentation and procedures • Creation of regulatory bodies for post contract implementation • Establishing a PPP Central Unit at Ministry of Finance as well as Satellite Units. • PPP Pipeline Projects in Social Infrastructure (Education &Health Sectors), Wastewater Treatment Plants and Transportation Sector 25
  • 26. PPP Global Adaptation / Learning 26
  • 29. WB PPP Knowledge Reference 29
  • 30. International PPP Center of Excellence Initiative 30
  • 32. PPPs Evolutionary Phases START (Infancy) Stage Two (Establishment) Stage Three (Maturity) •Introduce PPP concepts •Introduce legislative •Fully defined, comprehensive for Public discussions reform “system” •Explore PPP models •Publish policy and practice •Legal impediments removed guidelines •PPP models refined and Stage One (Emerging) •Establish dedicated PPP replicated •Define policy framework unit/s •Sophisticated risk allocation •Test legal drafts • Refine PPP delivery •Committed, long-term deal flow models •Identify project pipeline •Long-term political consensus •Continue to foster local / •Develop PPP concepts int’l marketplace •Use of full-range funding sources •Apply lessons from including pension funds and •Expand project pipeline earlier deals to other private-equity sectors •Extend to new sectors •Well-trained civil service •Start to build the local •Leverage new sources of applying lessons from PPP marketplace funds experience 32
  • 33. PPP Market Maturity Curve – UN Publications 33
  • 34. Governments & Institutions objectives in PPPs • Fiscal objectives (defers the cost of capital investments, reduce apparent borrowing by government ) • Economic objectives: – expected efficiency gains – more reliable completion of projects on time and on budget – expected greater management skills / know how of private sector • Political objectives – reduce role of the State / the Government – weaken influence of public sector trade unions Fiscal Objectives Economic Objectives Political Objectives Limits on government IMF spending/borrowing Efficiency Develop global market Limits on government EU borrowing, debt (stability Efficiency Develop internal market pact) Reduce role of state, extend National Limits on government Efficiency, reduced public role of private sector, governments borrowing spending weaken unions Local Efficiency, reduced public Reduce local taxes ? governments spending 34
  • 35. 35
  • 36. PPP Program - Integrated Approach – Key Notes  No perfect design for regulation and institutions  Changing market condition needs to Vision – Strong Political Institutional be reflected in PPP framework by Will Accepted By The modifying and updating regulatory Framework – Building and institutional design Public / Users Capacity, National (Empowered Public) Policy  Competition & transparency principles need to be kept  Government’s proactive use of Viable / VFM PPP vision, policy & sustainability in market Projects Pipeline creation is important.  Taxpayers / users engagement in PPP Funding – Priority Legal & Regulatory dialogue Funding Framework – Clear & Friendly Business  Supporting local financing institutions / Strategies, Building Environment To PPP’S . local development funds is key. Local Financial Supply Oversight Procedures - Side – Infrastructure Transparency, Competiti  In house skill within the government is of crucial importance to build Funds on, Monitoring capacity , to monitor and create PPP pipeline projects 36
  • 37. POLICY AND LEGAL FRAMEWORKS & SUPPORT FUNCTIONS  Comprehensive PPP Law – Investment , Funding & Technical (PPP Contract Type/s) and Legal Powers to contract out the services  Dispute Resolution Mechanisms – Independent Chamber  Open & Transparent Public Procurement / Tender Law  Clearly Defined Gov. / PPP Unit Role in – Budgeting Allocation / Oversight , Progress Monitoring & PPP Projects Approvals and Contract Management – performance-linked payments/penalties.  Sector & Scope of Sector Law – Ex. How to own a pipeline in a public road?  Private / Public Land Acquisition Law  Easements / Way leaves / Permits , etc  PPP Implementation Structures – Technical Public / Private Interface Offices.  Integration of PPP into Public Procurement w/ Multi Stage Financial & Scio-economic Appraisal Procedures (Rationale for use of PPP’s (Business Case) , Suitability & VFM Assessment) , Guidelines for PPP’s Pre-qualification , Tender And Bidder Selection.  Standardized PPP Bidding Documents  Unsolicited Bids Procedures.  Standardized PPP Contracts / Asset (Facility) Type or PPP Model / Structure  Information dissemination – data, networking, training  Guidance – model contracts, tools, case studies  Facilitating functions – political/advisory support, funding 37
  • 38. Criteria's & Performance for PPPs Criteria for PPPs (PPP Project Test)  Affordability for the Public Sector & Desired Gains  Financially viable for the Private Sector  Appropriate Risk and Reward Balance for Public and Private Sector  Public Sector - value for money (VFM – True Cost) Verses traditional PSC PPP Performance & Monitoring : World lessons  National audit authorities need to be involved in assessing PPP VFM (UK NAO)  Periodic reports for progress , learning and benchmarking are needed.  Public and private sector may need to acquire new skills to commence a PPP program.  Sufficient ‘deal flow’ is critical to justify the high transaction costs and to promote effective competition.  Procurement programs need to be managed to minimize costs (e.g. standardized documentation) and maximize competition (e.g. timing of contract notices).  National PPP Task Forces / PPP units can play key role in securing VFM in programs.  Globally , cost and time performance in major infrastructure generally good, performance in IT & Social PPP sectors generally weak. 38
  • 39. PPP Projects Value Drivers Less PPP Value Added Driver More PERFORMANCE-BASED PAYMENT MECHANISM: Above-par performance should give higher Unitary Fixed Payments profitability, low performance should trigger Performance Payments penalties. OUTPUT SPECIFICATIONS: Relates to the private sector's ability to deliver the services at lower Limited Incentive Contracts costs, or to provide better quality at the same Output Based Contracts cost to the user. INTELLIGENT RISK ALLOCATION: Risk to be allocated to the party that is best to manage , Wrong Risks Allocation mitigate or absorb it. Wrong risks allocation Optimal Risk Allocation reduces PPP value. LIFECYCLE OPTIMIZATION: Integrating different components and phases increases the More project phases in Multiple Project Phases performance over the PPP lifecycle and reduces interface problems. one hand FORMAL CONTRACTING: Clear legal recourse in Simple Contracts case of disputes increases clarity and reduces Complex Contracts risk. COMPETITION / FUNCTIONING MARKET: Competition from adequate number of Limited Competition companies increases value-for-money. PPPs More competition without competition are inefficient. PRIVATE FINANCING: Private financing results in Public Financing strong oversight from debt and equity providers Private Financing which increases project performance. 39
  • 40. UNECE Guidelines On Governance In PPPs   Coherent PPP No! , You need a policy framework with PPP pilot project will start the process Policy direction, responsibilities and goals. No! , capacity building within Strong Enabling PPP’s projects should focus on ring Government & setting up institutions Institutions fencing are needed. PPP’s have prescriptive rules and tight No! , Overall framework should be Legal Framework control flexible. Cooperative risk PPP’s provide assets to governments at No! , Governments must assume some sharing no risk and no cost risks and offer some subsidy. Transparency in No! , Competition allows selecting the In PPP’s no tender required… Partner selection best fit (partner /project) Putting people In PPP’s its best to Keep people out: No! , People need to be put first. First they do not understand the complexity Sustainable In PPP’s one have to choose between No! , Project can make profit and still Development profit and social & environment … achieve social and environmental goals. 40
  • 41. Key to Successful PPP’s  Alignment of proposed projects to strategic plans and mandates.  Vertical alignment in terms of national and also provincial priorities to enhance “buy in”.  Proper groundwork at inception with regards to option analysis: clear VFM  Attracting private investors .  Appointing good transaction advisors: well rounded experience, no conflict of interest.  Clear contract terms and conditions to avoid contract re-negotiation. PPP PRO’s PPP CON’s Competitive Process Complex Structures & Documents Increased Transparency Time-Consuming to Arrange / Tender Off Balance Sheet Consideration Higher Borrowing Costs Than Public Financing Private Sector Efficiencies and Innovation No different than EPC Contracts Commercial Risk Sharing Difficult to Resolve When In Default Acceleration of Infrastructure Provision Project Choice Important Faster Implementation Skill Deficit for Administration Reduced Whole Life Costs High Transaction Costs Better Risk Allocation Structured Risks Better Incentives to Perform Needs Legal Framework Improved Quality Of Service Can be achieved at High Price Generation of Additional Revenues Collection Issues & Costs Enhanced Public Management Public Perception and Political Reactions 41
  • 42. PPP Units – A World Trend ! • There are no single design of PPP unit, design to fit local the context • PPP unit is not a prerequisite nor a guarantee for successful PPP • PPP unit need to demonstrate leaderships and specialties • Most countries commence PPP programs in Transport, Energy, Water, Wastewater and later migrate to other sectors like – Health, Education, Energy, Water, Waste Treatment. • Rate of ‘migration’ to other sectors reflects both national priorities and existing legal frameworks. • Tendency for project to cascade from central to local government / municipalities. • Line ministries which have a long experience in traditional procurement may not want to cooperate with new agency MoF – Policy Formulation & Line ministries/ local Gov’t Fiscal / Budgetary Control Project Implementation 42
  • 43. PPP Units Design Notes – Function Wise • Design factors for PPP units include size and type of government ( Federal / non Federal) , decentralizing from central government to local / state governments, where within government infrastructure delivery "sits" and the size and growth of the PPP program (measured as the ratio of PFI/PPP investment to the total investment in public services). • It is highly desirable that the roles of PPP Policy Development (Institutional Fr amewor k and development of top line guidance like value for money) and PPP Pr ojects Appr ovals are not within the scope of the same PPP unit that serves as centre of best practice and expertise (Project Development) or coordination unit. • To be effective, a PPP unit needs to be able to build up experience and retain institutional memory project and lessons leant wise. This can be a challenge of sitting within the public sector. In all cases the public sector needs to have experience of managing financial, legal and technical advisory roles if these functions are sourced out . 43
  • 44. PPP Units Design Notes – Government System Wise • In a Federal system (like India, Australia, UAE and USA), the relationship between Federal and State Units depends on the responsibilities of the different levels of government with the federal government role as Project Developer is less significant, however, the financing / guarantees role of the Federal still exists. • In non federal, centralized system the role of the PPP unit needs to fit with the existing structures of government considering the extent to which levels of government / Line ministries have control over their own budgetary resources or have private finance units or are permitted to generate own revenues . At the early stage of PPP development, it is usual to start with a central PPP unit, however, as the program grows; the need to avoid excessive deficiencies stemming from centralization needs to be addressed. • In Constitutional democracies with strong parliamentary processes, PPP units are preferably located in the Ministry of Finance to exercise fiscal and budgetary control with Ministry of Planning or Mega Projects being also other preferred locations. 44
  • 45. PPP Units Should Also Resolve Government Failures! Government Failures PPP Units Functions Policy & Strategy undefined , not clear Marketing & Promotion Poor Procurement PPP Units functions Policy Formulation & Incentives need to Coordination accommodate Poor information Information and Guidance Governments failures dissemination - Standardization Poor Contract Project Advise – Technical Management Assistance Lack of Coordination among stakeholders PPP Units associated with Project Development Successful PPP Programs; Lack of complex projects skills & analysis Funding Preparation Partnership UK (PUK) Poor Transaction Contract Monitoring & Partnership Victoria Management & High Costs South Africa PPP Unit Control Lack of Information Approval Power 45
  • 46. Examples of Location & Roles of PPP Units Policy Setting / Monitoring / Collaboration / Investment Fiscal Control Budget Control Coordination Promotion Ministry of Ministry of Ministry Ministry of Finance / Finance / (Authority) of Business & Treasury or Treasury or Planning / Trade Economic Unit Economic Unit Ministry of , Ministry of Mega Projects Industry PPP PPP PPP PPP Unit Unit Unit Unit 46
  • 47. Examples of Roles , Location & Funding of PPP Units Victoria, Nether- BC, CA Ireland Italy Philip. SA UK Aus. lands Guidance        Project Advise         PPP Development    Funding Preparation    Monitoring      Approval Power    PV, Australia Inside the Government PBC, Canada (All are funded by the Government) UK Treasury Task Force Outside the government (Private) PIMAC, Korea Public / Private (Generates Revenue - Advisory Services) PUK, UK Multitier PPP units exist in countries where project development , financing and approvals are bundled together. Example in UK , the Treasury Task force ( located in MoF is the approval authority) while PUK ( Partnership UK , a semi private unit) does the Project Development in line with satellite units from line Ministries. 47
  • 48. PPP Other Sources - International Law  UNCITRAL – UN Commission for International Trade Law, website – http://www.uncitral.org. • Significant work toward the harmonization of private international law. • Numerous translations of documents (French, Spanish, Arabic, Chinese, and Russian).  UNIDROIT – Int’l Institute for the Unification of Private Law , website – http://www.unidroit.org. • Best-known accomplishment = UNIDROIT Principles of International Commercial Contracts. 48
  • 49. PPP Other Sources - Arbitral Institutions Permanent Court of Arbitration – http://www.pca-cpa.org. Int’l Center for the Settlement of Investment Disputes – http://www.worldbank.org/icsid/. International Chamber of Commerce (ICC) – http://www.iccwbo.org/index_court.asp. London Court of International Arbitration (LCIA) – http://www.lcia-arbitration.com/lcia/lcia/index.htm. American Arbitration Association (AAA) – http://www.adr.org/index2.1.jsp. WWW Virtual Library Arbitration – http://www.interarb.com/vl/pages/. 49
  • 50. PPP Options & Projets Structures  Toll Roads  Airports  Seaports, Water Transport  Rail ( Railway, monorails, etc) Transportation  Underground Transport  Electricity  Gas  Water Regulated Utilities  Hospitals  Schools  Prisons  Social Housing Social Infrastructure  Broadcast Networks  Mobile Telephony  Satellites Cables  Terrestrial / Submarine Cable Communications 50
  • 51. Generic - Risk Scales & Durations for PPP’s • Privatization & Divestiture (Highest Private risk) • DBFO & BO Concession contract - Revenue or off- take - (25 -30 yrs) • DBOT, BOT (25 yrs) • Lease / Afterimage contracts (5 – 10 yrs) • JV, Partnerships ( varies but has a life time with dissolving mechanisms) • Sale & lease back (8 – 15 yrs) • Operation & Management ( O&M) Contracts (3-5 yrs) • Service Contracts (1- 3 yrs w/ renewals) • Technical assistance – discrete tasks - (Lowest Private risk) 51
  • 52. Comparisons ! – More Common PPP’s Aggregat Approx. Construction, Operational PPP PPP Operators Demand Scheme e Risk Duration Rehabilitation Env. Risk & Technical Type Examples Revenue Risk % ( + / -) Years Risk Risk Nearly Service Sale ( Privatization Non 100% regulated) , Private, if Telecomm. Lifetime Private Private Private & Divestiture PPP Private Facility / License needed Risk re-sale Full User's charges ( Volume Concessions Direct or shadow 90% Caps and (BOO) / Highways, payments) / Private / / or Off Private / Design PPP IPP, IWPP, 25 - 30 Based on Private Private 10% take by Public Finance Build Hospitals Performance Public the Operate (Availability/ Public (DFBO) Delivery) STP's , Water Production, 70% DBOT,BOOT, Social User's charges / Joint Private / Private / BOT (turkey PPP Housing, 20 - 25 Off take Private Public / Private 30% Public delivery) Education Agreement Private Public facilities, Prisons, Lease / Sewer, 60% Afterimage Transmission 5 - 10, w/ Fee based on Public ( for the Private / More on (not the PPP lines. Renewal collected needed Private Public 40% Private side same!) Electricity Provisions revenues facilities) Public 52 Contracts Distribution
  • 53. Comparisons ! – Less Common PPP’s Aggregate Approx. Construction, Operational PPP PPP Operators Demand Scheme Risk Duration Rehabilitation Env. Risk & Technical Type Examples Revenue Risk % ( + / -) Years Risk Risk JV , Partnerships Lifetime Solar ( usually high tech Nearly w/ User's charges / Generation, with environmental PPP balanced dissolving Off take Joint Joint Joint Joint Waste to impact or Production (50% / 50%) mechanis Agreement Energy, sharing -oil & gas) ms Common in Airlines, Sale / Lease back Government 20% Private Direct - Capital / Contracts ( Asset is Public ( for the PPP Building , / 80% 8 - 15 Operational Public Public Negotiated leased back to the needed facilities) Sports Public Lease agreement Public) venues Public, Operation & Airports & 10% Private Minimum Contractual Private / Private / Management (O & M) PPP Seaports, / 90% 3-5 N/A volume (lump sum) Public Public Contracts land fills Public guarantees by Public Service / Maintenance Contracts, Technical The usual Nearly Contractual / On Assistance Non outsourcing 100% Public 1-3 call / job card fee N/A Public Public Public (Government PPP PSC. Risk ( Discrete Tasks) Procurement - Design - Build or EPC) 53
  • 54. Comparisons ! - PPP Versus Privatizations Public-Private Partnerships Privatizations / JV’s Water, Wastewater Treatment, Electricity Generation Telecommunications , Some Water Services Hospitals , Hotels, Sports Venues Electricity generating , Transmission / Delivery Networks Roads, Bridges, Rails Production of Oil and Natural Resources (sharing) Social Housing, Schools, Prisons ( Social infrastructure) Poorly Managed Large Assets. A new special purpose vehicle (SPV) is formed - Project Existing state-owned assets are sold directly to a private sector Company , owned by the private sector entity, often after an international / local tender The SPV develops, finances and completes the Title to the assets is transferred to the private sector entity infrastructure necessary to deliver the project Full operational control is transferred to the public sector Private sector entity owns the assets and can dispose of them at the end of the agreed “concessionary” period , while the after contractually imposed deadlines and benchmarks (lock in title to the asset remains with the public sector in BOT period) and most utilities The SPV delivers the service and receives agreed-upon Because the asset has been permanently transferred to the compensation . Compensation to the private sector can be private sector, the public sector benefits are gained through in the form of tariffs paid by service users or directly by the receiving the acquisition price, improved efficiency , tax and government, or a combination royalty payments 54
  • 55. Comparisons ! - Risk Areas of Private ,PPP & EPC Public Projects Private Project Public Private Traditional EPC Development Partnership (PPP) Procurement No Public Public side has Public Side has Urban Planning Influence good influence total Control No Public Public Side has Public Side has Execution Speed Influence good Influence total Control No Public Guarantees of Contractor Guarantees Influence Private Investor Guarantees Project Financing Private Investor Private Investor Public Side Market Risks Private Investor Fair Risk Sharing Public Side Economical Benefits Benefit From Sustainable Sustainable - Public Side Property Sale Benefits Benefits 55
  • 56. Comparisons ! - Tax-Exempt Financing Versus PPP – Government Perspective Tax-Exempt Financing Public-Private Partnerships • Strengths Strengths – Tax-exempt interest (deductable)  Strength of private equity credits – Tax credit  Addition of equity cushion – Existing relationships with insurers  Market demand for infrastructure projects – Retains operational control of assets  Transfer of operating risk  Ability to continue oversight • Challenges – Market access issues Challenges – Future financial viability of bond insurers  Shift to executive oversight – Full retention of operating risk  Equity partners belief in future growth – Revenue shortfalls, unprotected.  Public policy implications/transfer of revenue stream 56
  • 57. PPP Risks - The More Familiar Risk Type Risk Mitigation Environmental and safety Environment and EIA before and after, Both parties to agree on the constraints defined in the Safety Risks Environmental impact. Concession Agreement Risk to be borne by Concessionaire. Acquisition of land risk by Government before construction start. Tools; Time delays & cost overrun risks, - Fixed price turnkey contracts Construction Risks geotechnical risks -Warranties (bonds), - Liquidated damages clauses. -Clear input or output or performance specifications. Tools include; - Equipment Suppliers guarantees Performance based risks, Technical - Proven technologies operating costs, management Operation Risks - Performance guarantees. failure. - Raw materials / feedstock agreements - Public Authority involvement Revenue Risk in Minor risk in existing facilities Often acceptable risk level is borne by Concessionaire existing facilities / unless forecasts after (adequate provision on tariff in Concession infrastructure improvements are exaggerated. Agreement). Often not possible for Concessionaire to bear all the Revenue Risk in risk. Tools include; newly-built Major risk in newly-built facilities - Off take agreement facilities / like traffic volume, tariff setting. - Caps ( floors / ceiling) infrastructure 57 - Revenue build up period
  • 58. PPP Risks - The Less Familiar Risk Type Risk Mitigation - Structure ( Debt / Equity) - Optimal Equity 30 – 10% - IRR / NPV - IRR (15 % -25%) -Debt Service Cover Ratio - 1.5 ( can be as low as 1.1 with string off Financing Risks - Tax Status / Benefits take agreements) - Others - Exchange Risks, Sovereign - Translates into tax account treatment Credit Ratings, etc. - Financial derivatives hedging. - Refinancing - Syndication Legal Risks Regulatory framework, concession / Experienced (high priced) Lawyers. Clear sector laws. documents. International Arbitration set. Compliance to contractual terms in a Mitigation through Risk Guarantee (IBRD and Political Risks / Concession Agreement. [Currency MIGA). Transferred Risk can be insured – Government Inconvertibility, Confiscation, Political risk insurance. World Bank provides Performance Risks Expropriation, Nationalization, Civil Partial Risk Guarantees. Remaining risks can Strife, War, etc.]. Force majeure can be be borne by Lenders. included 58
  • 59. Risks Perspectives Access to PPP Development Best Value for Acceptable Contracts Speed Money Financial Return Pipeline Government Concessionaire Incentives to Risk Mitigation Transfer Risk & Control Access To Minimize / Access To Payment Source Private Capital Re-use Capital Revenue Stream Risk Risk Risk Risk Identification Analysis Allocation Monitoring 59
  • 61. Political Risk Agencies - (Social-Political-Economic) Financial Risk Agencies / Ratings BERI , PRS , Prince, ICRG S & P , Moody’s, Milken Index , Fitch IBCA Hybrid Risk Models / Rating Agencies - (Financial Focus and Political Causes) Economist (Magazine) Chase Manhattan Bank Euro money Institutional Investor POLITICAL RISK FACTORS ECONOMIC & FINANCIAL RISKs Ethnic Social Tensions Domestic Economic Problems Strife, Armed Insurrection International Economic Problems Urbanization Low Wages / Labor Cost / High Productivity Decentralization Good Infrastructure / Telecommunication Bad Neighbors Restricted Import / Export Commodity Dependence High Commodity Prices International Trade Agreements Expedient FDI Screening / Approvals Regional Trade Agreements Favorable Taxation / Tax Holiday Corruption Third Party Cost / Biding Cost Staleness / Illegitimacy Debt in Default / Rescheduled / Non Payment Democracy /Opposition Tolerance Reasonable Gov. Bonds Risk Premium Liberties / Unrestricted Internet Service Oriented / Competitive Market Powerful Private Interests Limited Creditworthiness State Owned Enterprises Restrictions on Privatization Competent Local Management Partners Access to Bank Finance Foreign Control / Foreign Equity Ownership allowed Liberal Labor Laws / Modest Termination Benefits Non-Repatriation/Non-Payments Fiscal Monetary Expansion / Capital Flight Creeping Appropriation Exchange Controls/Convertibility MIGA Membership / OPIC Insurance Available Liquid / Transparent Stock Market 61 Stable Regulation & Law Enforceability Access to Capital Markets
  • 62. PPP Projets Success Framework 62
  • 63. PPP Projects Success Framework – EPEC Adopted 1. Choice of Project - Only sustainable projects should be launched 2. Choice of Funding & Risk Sharing - Fit with Project structure 3. Choice of Procurement Procedure – In line with Project complexity 4. Choice of Financial Structure - Balancing spreads and risks 5. Whole Contract Life Management - Renegotiations to the benefit of all parties.  The main driver of the PPP contract duration should remain technical (life-cycle and obsolescence considerations), rather than financial!  The legal framework of PPP’s should remain flexible enough to meet the conditions of success.  Guarantees should be given more systematically to private operators, in order to have the best possible use of public funds.  Resorting to guarantees to secure private financing can expose the government to hidden and often higher costs than traditional public financing 63
  • 64. 1. Project Choice - Sustainable Projects  Decision makers must choose the projects that are desirable from the socio- economic point of view and respond to real demand and needs. e.g.:  Which will enable the economic development of a market or a region;  Which will save time and increase safety, in the case of a road;  Which will save lives, in the case of a hospital, etc.  A desirable project means a high socio-economic IRR (Internal Rate of Return)  A high socio-economic utility makes the payment of a tax or a toll politically more acceptable.  Experience shows , if contracts do not meet the condition of a high socio-economic IRR, problems necessarily arise:  Bankruptcy of operator (in case of traffic risk)  Skyrocketing public debt (if large grants are needed)  Political legitimacy problems with regards to final users and tax payers  And in the end: reputation problems for all partners 64
  • 65. PPP Projects According to Revenue Users Pay (Termed as Concessions when users pay) • Traditional BOT model • Revenues collected from users usually by the private partner (e.g. tolls paid on a highway or bridge) • Project is “off the Government budget” as revenues flow directly to private sector • Used only where there are substantial revenues that can be directly charged to users • It is estimated that about 10% of receipts relate to toll collecting (without automated systems). Everybody Pay (Termed as PFI when the Public makes regular payments) • Annuity scheme or availability model • Revenue collected can be either from users directly to private partner or may stay with government and Government opts to make regular payments for making the service available (availability / shadow payments) • Project is often “on the Government budget” as revenues flow through Government • Can be used widely for services paid by known users, or for those paid through taxes or in countries where tolling is not socially acceptable. • There is no expenditure for toll collecting General tendency to move from toll to availability based payments in road projects. Also Innovative use of payment mechanisms to focus on public sector objectives are becoming trend. Examples from the road sector ; User tolls – to pass costs to users; Availability payments – to reduce congestion; Accident rate premium – to improve safety. 65
  • 66. PPP Transactions – Economic Partnering Highways (Concessions – BOO, BOT, BTO) & Rails (BTO) • Direct tolled – i.e. users pay full cost or partial cost (Government Subsidy) – compete on costs – e.g. Malaysia, Australia. • Shadow tolled – users don’t pay directly but all pay indirectly via tax & fuel surcharge etc – compete on subsidy amount – e.g. India Airports /Sea Ports (usually Management Contracts) • Long term management contracts that may include capital works – e.g. Australia, Srilanka, Cambodia, KSA, Jordan • Government may agree to minimum thru-put and provides core custom & immigration functions Water & Power -IPP, IWPP- (Concessions – BOO, BOOT) • Government agree on minimum uptake (usually 80 -90% the rest sold in open market – e.g. Indonesia, Malaysia, GCC (IWPP) , Egypt, Jordan, Lebanon, Yemen. • Government may agree to pass-thru cost on fuel. Power -Solar (Concessions) • Similar to power – e.g. Morocco, Tunisia 66
  • 67. PPP Transactions – Environmental Partnering Landfills (usually outsourcing – O & M Contracts) • Private Partner to takeover waste treatment and landfill management , may include methane extraction – e.g. Malaysia , Indonesia • Governments agrees to management fees and • Governments usually approves combustion power plant on site for internal use as well as sale to power grid Waste to Energy (recycling of solid waste / used tires) (usually JV’s) • Reduces excessive gas emissions while stimulating private sector demand. • Private Partner to takeover waste conversion to energy – e.g. Bahrain. • Governments agrees on energy sale to power grid Sewerage Treatment Plants (STP) – ( usually BOO / BOT, transmissions usually BOOT) • Population and business levels increase leading to increased waste generation • Private Partner to takeover sewerage treatment • Government agree on off take (usually distribution to farms is by the Government) – e.g. GCC ( Bahrain) 67
  • 68. PPP Transactions – Social Partnering Hospitals (usually DBOF) / Prisons (usually BOT) • Private Partner to build the facility , manage it for a set time and operate noncore service like catering, parking etc • Government provides the doctors, nurse ,wardens etc and operates the core services – e.g. Lesotho, Australia Schools/ Sports Venue / Shopping Malls (usually DBOF) • Private Partner bids on cost, design and facility management for a set time & run noncore services – e.g. Australia, Egypt. • Government runs core services of teaching / tutoring or agrees to use the facility for an agreed period Public / Government / Affordable housing (usually BOOT) • Private Partner to build, lease and maintain for a set period – e.g. Malaysia, GCC ( KSA, Oman, Bahrain) • Government agrees to minimum lease for a set period / off take and / or allows co-developments on site 68
  • 69. PPPs and Value for Money (VFM)  Achieving optimal allocation of risk is the most important factor in structuring a PPP - Does the private sector’s price for taking project risks represent good value for money? - Is the private sector’s return on capital appropriate to the level of risk being taken?  Facilitating and making incentives on time and on project budget implementation: – No service / no pay. – Incentives to cost control.  Optimization of capital & maintenance expenditure over project life.  Innovation in design and financing structures.  Improving management of operational risks. Optimal risk allocation  reduced cost of risk Reduced cost of risk  better Value for Money No presumption that PPP’s will always prove better Value for Money than conventional Public Sector Contracts (PSC / EPC) 69
  • 70. (VFM) Higher Than Forecasts Costs in EPC /PPPs Evidence on construction projects from the UK’s National Audit Office Conventional procurement (PSC) PPP procurement Cost overruns for the public sector 73% 22% Delay in project delivery 70% 24% 70
  • 71. 71
  • 72. 2. Funding & Risk Sharing - Fit with Project Funding translates into; Who should bear the demand risk? Who will pay for the infrastructure/service?  Payment by users - when the principal source of revenue for the private operator is by users , the operator bears the demand risk.  Payment by taxpayers (i.e. public budget) means that the demand risk is not transferred to the operator. The choice of funding must be based on a trade-off between:  The marginal cost of public funds collection.  The willingness not to exclude users from the infrastructure (problem associated with the payment by users). 72
  • 73. PPP Major Funding Sources Credit Political Loan Equity Loans Guarantees Risk Guarantees /Insurance Insurance Sponsor  Private  Commercial Banks   Capital Markets    Insurance Cos.     Private Equity Funds   Public Multilateral  IBRD   IFC     MIGA  OPIC     Development Banks  (IADB, EIB, EBRD, CAF,   BNDES, ASD, AFDB) Export Credit Agencies  (Ex-Im Bank-US,ECGD - UK,EDC - Canada, HERMES -     Germany, COFACE - France) 73
  • 74. Managing Fiscal Risks in PPP’s • PPP’s create fiscal obligations that are long term and binding future generations and tax payers. • Accurate design of PPP’s requires that the fiscal cost and risk of the major contractual obligations be identified, quantified and mitigated. Direct, debt-like obligations • Availability payment for the use of facilities • For PPP hospitals, schools, prisons and a like, PPP deal also requires government to allocate funds for government doctors, nurses, and teachers, guards who will run the facilities built, maintained & operated by the private sector. Explicit contingent obligations • Government guarantees to repay investors cost and agreed returns • Revenues and exchange rate guarantees. • Shadow payments for assets provided by private sector. Implicit contingent obligations • Taking over private debt if developer becomes financially distressed • Implicit use guarantees in PPA – Power Purchase Agreements, off take agreements. 74
  • 75. 3. Procurement Choice – In line with Complexity  Classical competitive bidding aiming at minimizing financial costs fits well with simple contracts, whereas negotiated procedures (e.g. through competitive dialogue / with a set of criteria’s) fit better with complex contracts  In terms of incentives, complex contracts fit better with Cost Plus schemes and simple contracts fit better with fixed price regulation schemes.  Procurement procedures should be adapted to the project type, in order to prevent opportunistic behavior, and should also favor strict prequalification and additional award criteria. Unsustainable offers should be legally excluded.  Classical procurement procedures are not a guarantee for fair competition: bid rigging, first mover advantage (incumbent's renewal), etc.  Renegotiation & opportunism costs need to be guarded against! ( for example, lengthy post negotiation can jeopardize the project) 75
  • 76. PPP Procurement Process  Planning process - Planning requires time and money - worth the investment - Fund supporting project development – needed. - Cross sector dialogue including Treasury - required - Check and balance – are key  Market testing - Testing the interest of market is crucial - The market condition can impact risk sharing - Transparency should be kept  Procurement method - Prioritization - Solicited or unsolicited proposal - Prequalification, 2 envelope bidding - Award criteria (VFM , PPP Versus PSC ) - Time management 76
  • 77. Unsolicited Proposals in PPP • Can be useful in early stage of PPP program especially at local governments level , however, often the Public Sector then lacks the fiscal and knowledge capacity to analyze projects • Attract private sector investors ( Proponents) by giving initiatives and incentives • Priority set for proposals without asking government support • Genuine unsolicited proposals can wash out network effect of entrenched infrastructure development • More scrutiny is required , additional requirement for value for money tests are needed. • Competition is key , opportunity for counter proposals should be given thus providing level playing field • Common is some countries like Chile, Argentina, South Korea, South Africa< India, Italy and Malaysia 77
  • 78. Steps in PPPs Procurement - PPP Project Life Cycle What are the steps? Project Preparation – Service Provider Selection Contract Management - Funding Approval – Technical RFP & Bid Financial 1. Prioritise Key Project 4. Project Dev. 7. Final Negotiation Objectives 2. Agree Project Concept Team, Gov ernance, Signing contract, financial 3. Obtain Stakeholder Approval close Timeline, execution plan 1. Service Need 5. Bid Preparation 8. Contract Mgmt. Output specifications EOI/ Short listing, RFP Construction, monitoring, Dispute settlement, 2. Option Appraisal Bid Doc communications and Report on EPC / PPP Approval finally commissioning options, VFM 6. Bid Evaluation 9. Renegotiations 3. Business Case Preferred bidder selection Due to changing Affordably/public interest conditions Project/ Project 10. Turn Over Funding Finalization Upon expiry of the Approval Review concession agreement 78
  • 79. 4. Financial Structure Choice - Balancing  The financial structure of a project is usually composed of loans (banks or bonds), shareholder loans, equity and grants.  The continuing financial crisis has shown that there should be a systematic follow-up of the main events occurring during the life of a contract, in order to balance spreads and risks:  During the crisis: spreads have skyrocketed - projects became unfeasible.  In the crisis: spreads have gone back but not to normal levels. If spreads are too low, banks cannot pay for their risk.  One should also take into account the asymmetry regarding the way public entities and private operators absorb risks. The allocation of risks must take into account this asymmetry. Grants and/or guarantees should be adjusted accordingly.  Due to the financial crisis, loan maturity has been shortened. State support may be needed. 79
  • 80. Risk Transfer PPP Stakeholders & Risk Transfer Host Government / Public Authority Legal /regulatory framework & support functions Advisors – Legal Contracting PPP , Technical & Authority (is) Financial Equity Investors SPV / Project Company Arranging Bank (Borrower) .Made up of Banks Syndicate Project Sponsors - Equity Investors. Hedge Providers Input Contracts Currency & Interest Guaranteed long Rate, Multilaterals, P term supply olitical Risk Insurers of inputs / feedstock Off Taker Guaranteed revenue stream to project. Can be the Public Contracting Authority or MoF Equipment Supplier Contractor(s) ,EPC O&M Contractor(s) Warranties & Supply - Risk transfer – Interface Pass down of penalties for Agents Agreements. Can Turnkey Contract , Contract availability payments be bundled in EPC penalties , bonds. , performance, etc. Risk Duration 3 – 5 Years 25 - 30 Years ( Risk by Project Company) 80
  • 81. Corporate & Project Finance Debt 100 Project Financing provided Mezzanine Funds Equity provided by by banks / IFIs sponsors 81
  • 83. Project Long Term Financing Project cash flows must be sufficient to service (interest and principal) All risks to lenders must be eliminated • Construction ,Market ,Consumption ,Operating ,Inflation & Credit risk • Other risks as applicable –Refinancing, Interest rate, Exchange rate Advantages • Enables high debt to equity ratio , Releases Investors equity • Enables equity risk sharing in projects • Funds can invest into SPV • Avoids refinancing risk Disadvantages • More restrictions in use of funds • Restrictive covenants (debt service cover ratios etc) • More complex documentation (risk mitigation) • Less flexible administration (most changes require lenders' consent) 83
  • 84. 5. Management – Allow Renegotiations  All contingencies cannot be anticipated (changes in the legal environment, force majeure, innovation, changes in demand, environmental and technical constraints.  Contract will necessarily evolve over time/be renegotiated. Renegotiation clauses , conditions of execution , adjustment should be specified in the contract.  Renegotiation should be viewed to the advantages of 3 parties (Public entity, Users, Private operator). Fair and transparent renegotiation is the essence of the contract.  Necessary conditions for a good management of the life of the contract:  Fair behavior of both parties  Technical skills  Experience and capacity building  Flexibility and adaptation to local customs  The threat of sanction (must be credible) to enable self enforced good practices.  Non written aspects of the contractual relationship (trust, reputation, etc.) are key elements for success. 84
  • 85. Typical PPP Project Administration & Risks Political and Macroeconomic Risks Regulatory Shareholders – Risks Equity Investors FX Risks and Regulatory Refinancing Risks Shareholder’s Authority Agreement Lead / Syndicate Banks Guarantees & Bond Holders Concession Granting PS SPV - Agreement Authority Operator - Project Production Operation & Maintenance Company Purchase / Off Services Operator - Agreement(s) (O&M) Take Agreement Purchaser / Delivery Off Taker Performance Interface Construction Regulatory and Agreement Contracts Supply / Feedstock Performance Risks Agreement Risks Construction Contractor(s) Raw Material / Feedstock Supplier Completion Risks 85
  • 87. PPP Regional Strategy & Readiness Actions? Diagnosis? 87
  • 88. MENA PPP Investments Comparisons PPI Data Base – Data Source • The PPI (Private Participation in Infrastructure) database is a multi-donor- funded facility and is maintained by PPIAF (Public Private Partnership Advisory Facility). • The database is the most sophisticated attempt so far to create a global database of PPI / PPP projects which helps to understand the pattern and scale of PPP deals in world regions. • The PPI database does not cover social infrastructure / PFI-model PPPs. It does cover Energy (electricity and natural gas), Telecommunications, Transport • (airports, seaports, railways, toll roads), and Water and Sewerage (treatment plants and utilities). • The PPIAF PPI database identifies four types of project: Management and Lease contracts; Concessions, Greenfield projects, and Divestitures / Privatization. Divestitures (either full or partial) are not considered PPPs. 88
  • 89. World Regions by Sector (1990 – 2010 , Total Count & Investment – million USD) Sector Project Count Total Investment (US$ million) Telecom 798 761,394 Energy (Example Next) 1,952 548,279 Transport 1,291 275,597 Water and sewerage 731 62,543 Grand Total 4772 1,647,813 1,800,000 6,000 1,600,000 5,000 1,400,000 Number 1,200,000 4,000 Million USD 1,000,000 3,000 800,000 600,000 2,000 400,000 1,000 200,000 0 0 Latin America … Latin America … Europe and… Europe and… East Asia and… East Asia and… Middle East… Middle East… Sub-Saharan… Sub-Saharan… South Asia South Asia Grand Total Grand Total 89