Six Sigma DMAIC Project




                                       GE Medical Systems




                               Project Leader/Green Belt: Steve Kosloske
                                      Project Leader Title: SDL, CGB
                                      Project Start Date: March 6, 2003

Master Black Belt: Steven Bonacorsi
Six Sigma in Action
                                                                            Sun Monitor Costs


Customer Profile – GEMS Engineering – 3 Sites in Milwaukee Area
                                                                      Process Capability – Before
Business Problem & Impact
Standard Engineering workstations pricing continues at the
same high level yearly. Sun has moved to more standard                Z bench (ST) = - 3.0
parts, allowing substitution of high cost Sun parts for less-lostly   Avg. Cost = $1000
3rd party products, which can save GEMS thousands per year.

Measure & Analyze
Data Collection: Average cost for a standard Sun 21” monitor
is $1000 for all open leases in 2000-2002.
Root Causes: Single source of monitors (Sun).
                                                                       Process Capability – After

Improve & Control
Bid replacements monitors to 3rd party companies, test
replacement monitors to meet/exceed user requirements, and            Z bench (ST) = 6
get end-user sign off on new monitors.                                Avg. Cost = $509


Results/Benefits
Direct savings of $509 per workstation order, no extra costs to
customer if monitor fails during lease period.


                  A Customer Direct Savings of US$385K in 2003!

More Related Content

More from Kevin Egan

Qaa paul nelson
Qaa   paul nelsonQaa   paul nelson
Qaa paul nelson
Kevin Egan
 

More from Kevin Egan (11)

Gillette Six Sigma Case Study
Gillette Six Sigma Case StudyGillette Six Sigma Case Study
Gillette Six Sigma Case Study
 
Image Update Six Sigma Case Study
Image Update Six Sigma Case StudyImage Update Six Sigma Case Study
Image Update Six Sigma Case Study
 
Operating System Six Sigma Case Study
Operating System Six Sigma Case StudyOperating System Six Sigma Case Study
Operating System Six Sigma Case Study
 
Pc Shipping Improvement Six Sigma Case Study
Pc Shipping Improvement Six Sigma Case StudyPc Shipping Improvement Six Sigma Case Study
Pc Shipping Improvement Six Sigma Case Study
 
Serrver Imaging Six Sigma Case Study
Serrver Imaging Six Sigma Case StudySerrver Imaging Six Sigma Case Study
Serrver Imaging Six Sigma Case Study
 
Sms Integration Six Sigma Case Study
Sms Integration Six Sigma Case StudySms Integration Six Sigma Case Study
Sms Integration Six Sigma Case Study
 
Ticket Accuracy Six Sigma Case Study
Ticket Accuracy   Six Sigma Case StudyTicket Accuracy   Six Sigma Case Study
Ticket Accuracy Six Sigma Case Study
 
Qaa paul nelson
Qaa   paul nelsonQaa   paul nelson
Qaa paul nelson
 
Pharma iq mediakit1
Pharma iq mediakit1Pharma iq mediakit1
Pharma iq mediakit1
 
Jack Welch Speak - PEXN
Jack Welch Speak - PEXNJack Welch Speak - PEXN
Jack Welch Speak - PEXN
 
ISLSS Offerings
ISLSS OfferingsISLSS Offerings
ISLSS Offerings
 

Monitor Costs Six Sigma Case Study

  • 1. Six Sigma DMAIC Project GE Medical Systems Project Leader/Green Belt: Steve Kosloske Project Leader Title: SDL, CGB Project Start Date: March 6, 2003 Master Black Belt: Steven Bonacorsi
  • 2. Six Sigma in Action Sun Monitor Costs Customer Profile – GEMS Engineering – 3 Sites in Milwaukee Area Process Capability – Before Business Problem & Impact Standard Engineering workstations pricing continues at the same high level yearly. Sun has moved to more standard Z bench (ST) = - 3.0 parts, allowing substitution of high cost Sun parts for less-lostly Avg. Cost = $1000 3rd party products, which can save GEMS thousands per year. Measure & Analyze Data Collection: Average cost for a standard Sun 21” monitor is $1000 for all open leases in 2000-2002. Root Causes: Single source of monitors (Sun). Process Capability – After Improve & Control Bid replacements monitors to 3rd party companies, test replacement monitors to meet/exceed user requirements, and Z bench (ST) = 6 get end-user sign off on new monitors. Avg. Cost = $509 Results/Benefits Direct savings of $509 per workstation order, no extra costs to customer if monitor fails during lease period. A Customer Direct Savings of US$385K in 2003!