<Insert Picture Here>
Concepts and Best Practices for the Risk Register in Primavera Risk
Analysis
Matt Candela
Senior Technical Support Engineer
3
The following is intended to outline our general product
direction. It is intended for information purposes only,
and may not be incorporated into any contract. It is
not a commitment to deliver any material, code, or
functionality, and should not be relied upon in making
purchasing decisions.
The development, release, and timing of any features
or functionality described for Oracle’s products remains
at the sole discretion of Oracle.
4
Agenda
• Demo of primary Risk Register functionality in Primavera
Risk Analysis (PRA)
• Detailed look at functionality
• Other options and considerations
• Overview of risk functionality in P6 R8
5
• Uncertainty is inherent to a task.
– Example: digging a trench is scheduled for 10 days. It may only
take 8, or could take up to 12.
• Risks are events that may or may not occur and could
affect a task.
– Example: there is a 5% chance of flooding, which could delay
the digging of the trench by 5 to 8 days.
Risk vs. Uncertainty
6
• Risk scoring
– Thresholds, scoring criteria
• Create risks and assign to tasks
– Qualitative, quantitative probabilities and impacts
– Risk scores generated
• Mitigation
– Post-mitigated probabilities, impacts and risk scores
• Build impacted risk plans
Primary Risk Register Functionality
7
Risk Scoring
• Scores are calculated using Probability and Impact
Scoring Diagram
• Determined by intersection of the probability and impact
8
Qualitative and Quantitative Risks
• Risks have both qualitative and quantitative values
– Quantitative used in impacted risk plan
– Qualitative used to determine risk scores
• Qualitative risks: quantitative values from thresholds
– For probability, low and high are averaged
– For impacts, low is min and high is max
• Quantitative risks: qualitative values determined by
average of min, max, and most likely impacts
9
Qualitative Risks - Example
• Risk HAZ is assigned a high schedule impact
• High schedule threshold is defined as 20 to 40 days in
the risk scoring options
10
Qualitative Risks - Example
• Risk is assigned to a task on Quantitative tab
• Schedule impact is min 20 days and max 40
11
Quantitative Risks - Example
• Risk ACC is quantified and assigned to task 3
• Cost impact is min $50,000 and max $100,000, average
is $75,000
12
Quantitative Risks - Example
• $75,000 is within medium cost threshold
• Qualitative cost impact is medium
13
Qualitative and Quantitative Risks Assigned to
Multiple Tasks
• Qualitative: impacts spread across the tasks, per
following Risk Register options:
– “Spread the risk duration across multiple impacts”
– “Spread the risk costs across multiple impacts”
• Quantitative: impact averages will be summed to
determine qualitative value
14
Mitigation
• Mitigation Response of Avoid, Transfer, or Reduce
allows for post-mitigation values and score.
• Title and Total Cost optional for simple mitigation plan
15
Mitigation - Detailed Actions
• Qualitative tab > Mitigation tab > Use Detailed Actions
• Multiple mitigation actions with additional fields available
16
Mitigation - Detailed Actions
• Total Cost calculated as sum of details actions costs
– Excluding actions set to Rejected
• Post-mitigated values taken from an action
– Rejected actions are not considered
– Action with latest finish date is used
– Tie goes to action with the lowest score
17
• Mitigation Response set to Accept: any other response
allows for mitigation
• Use Detailed Actions is selected: post-mitigated values
taken from an action
• Risk is quantified: post-mitigated values must be set on
Quantitative tab
Post-Mitigated Options Grayed Out
18
Building an Impacted Plan
• (Task ID):B is the original task with no risk impact
– Duration and duration uncertainty of the original task
19
Building an Impacted Plan
• (Task ID):(Risk ID) is the risk event
– Task existence for probability, duration uncertainty for schedule
impact, resource uncertainty (ZCRI) for cost impact
– Zero remaining duration
20
Building an Impacted Plan
• (Task ID) is the summary for base task and risk event
– Logic from original task
– Resource assignments from original task, unless “Cost Impacts
include duration costs” is selected in Risk Register options
21
Correlation
• Available on Risk View tab when a risk is assigned to
multiple tasks
• Impact Ranges 90% correlation, Event Existence 100%
22
Link in Series
• Available on Task View tab when a task has multiple
risks assigned
• When unchecked, risks are in parallel
23
Link in Series - Example 1
• Risks are linked in series
• Cumulative effect, both impact schedule
24
Link in Series - Example 2
• Risks are not linked in series, occur in parallel
• Only longest duration affects schedule
25
Assigning a Risk to a Summary Task
• Risk will impact sub task with latest finish date
• Potential for confusion over which task risk will impact
and/or unexpected impact
26
Assigning a Risk to a Hammock Task
• Crash may occur or impacts may be incorrect
• Ability to do so has been removed in version 8.7.0029
27
Other Considerations and FAQs
• Opportunity on task near Data Date
– Opportunities work by pulling back start date, impact may be
incorrect
• What do risk start and finish dates affect?
– Proximity, exposure plan
• Is there a way to quickly assign a risk to a large number
of tasks?
– Filter on Risk View tab or use “Impacted Task ID(s)” column:
IDs separated by comma, no space
28
• Web only
• Risk scoring
– Thresholds, scoring criteria
• Create risks and assign to tasks
– Qualitative probabilities and impacts
– Risk scores generated
• Mitigation
– Post-mitigated probabilities, impacts and risk scores
Primary P6 R8 Risk Functionality
29
Primary P6 R8 Functionality
Define risk scoring under “Administer…Enterprise Data”
30
Primary P6 R8 Functionality
Select “Risks” on Projects View to create and assign risks
31
Primary P6 R8 Functionality
Use “Response Plans” tab for mitigation
32
Importing a Project from P6 R8 into PRA
• Requires Primavera Risk Analysis 8.7.0029 or later
• Requires Web Services Utility with appropriate settings
– See “Using Web Services to connect” in PRA help
• Run Connection Wizard in PRA
• Use “File…Primavera…Import Primavera P6 Project”
from PRA, no option from P6 R8 Web
• Risks only included in single project import
33
34

Mais conteúdo relacionado

Mais procurados

Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...p6academy
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisIntaver Insititute
 
Qualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisQualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisAlin Veronika
 
Qualitative risk analysis
Qualitative risk analysisQualitative risk analysis
Qualitative risk analysissonali talkar
 
Decision and risk analysis
Decision and risk analysisDecision and risk analysis
Decision and risk analysisIndra Biswakarma
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo
 
Risk Management
Risk ManagementRisk Management
Risk Managementrajuinstru
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisIntaver Insititute
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction IndustryIntaver Insititute
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Liana Underwood
 
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Association for Project Management
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectIntaver Insititute
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisProject Controls Expo
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear ProjectsIntaver Insititute
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Risk Management in Sprint Environment
Risk Management in Sprint EnvironmentRisk Management in Sprint Environment
Risk Management in Sprint EnvironmentMike Wienold
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Intaver Insititute
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesIntaver Insititute
 

Mais procurados (20)

Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Qualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisQualitative & Quantitative Analysis
Qualitative & Quantitative Analysis
 
Qualitative risk analysis
Qualitative risk analysisQualitative risk analysis
Qualitative risk analysis
 
Decision and risk analysis
Decision and risk analysisDecision and risk analysis
Decision and risk analysis
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
 
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Risk Management in Sprint Environment
Risk Management in Sprint EnvironmentRisk Management in Sprint Environment
Risk Management in Sprint Environment
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 

Semelhante a Best Practices for Risk Register in Primavera Risk Analysis (PRA

Project risk management
Project risk managementProject risk management
Project risk managementDewang Agrawal
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Risk management
Risk managementRisk management
Risk managementtumetr1
 
Risk Management
Risk ManagementRisk Management
Risk ManagementSaqib Raza
 
Project Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt nProject Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt nKevin117905
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.pptKareemRasmy1
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfMUST
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptYasirShaikh34
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 
Project risk management
Project risk managementProject risk management
Project risk managementBarnatuCoffee
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENTNeenu Babu
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfdddddddddddddddddddddddddddddddddddddddddddddddSPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfdddddddddddddddddddddddddddddddddddddddddddddddShepherdChidambaeh
 

Semelhante a Best Practices for Risk Register in Primavera Risk Analysis (PRA (20)

Project risk management
Project risk managementProject risk management
Project risk management
 
Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015
 
Project Risk management
Project Risk management Project Risk management
Project Risk management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Risk management
Risk managementRisk management
Risk management
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt nProject Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt n
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Session 18 -2 PMP 4th edition
Session 18 -2  PMP 4th editionSession 18 -2  PMP 4th edition
Session 18 -2 PMP 4th edition
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
Project risk management
Project risk managementProject risk management
Project risk management
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfdddddddddddddddddddddddddddddddddddddddddddddddSPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
 

Último

Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 

Último (20)

Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 

Best Practices for Risk Register in Primavera Risk Analysis (PRA

  • 1. 1
  • 2. <Insert Picture Here> Concepts and Best Practices for the Risk Register in Primavera Risk Analysis Matt Candela Senior Technical Support Engineer
  • 3. 3 The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.
  • 4. 4 Agenda • Demo of primary Risk Register functionality in Primavera Risk Analysis (PRA) • Detailed look at functionality • Other options and considerations • Overview of risk functionality in P6 R8
  • 5. 5 • Uncertainty is inherent to a task. – Example: digging a trench is scheduled for 10 days. It may only take 8, or could take up to 12. • Risks are events that may or may not occur and could affect a task. – Example: there is a 5% chance of flooding, which could delay the digging of the trench by 5 to 8 days. Risk vs. Uncertainty
  • 6. 6 • Risk scoring – Thresholds, scoring criteria • Create risks and assign to tasks – Qualitative, quantitative probabilities and impacts – Risk scores generated • Mitigation – Post-mitigated probabilities, impacts and risk scores • Build impacted risk plans Primary Risk Register Functionality
  • 7. 7 Risk Scoring • Scores are calculated using Probability and Impact Scoring Diagram • Determined by intersection of the probability and impact
  • 8. 8 Qualitative and Quantitative Risks • Risks have both qualitative and quantitative values – Quantitative used in impacted risk plan – Qualitative used to determine risk scores • Qualitative risks: quantitative values from thresholds – For probability, low and high are averaged – For impacts, low is min and high is max • Quantitative risks: qualitative values determined by average of min, max, and most likely impacts
  • 9. 9 Qualitative Risks - Example • Risk HAZ is assigned a high schedule impact • High schedule threshold is defined as 20 to 40 days in the risk scoring options
  • 10. 10 Qualitative Risks - Example • Risk is assigned to a task on Quantitative tab • Schedule impact is min 20 days and max 40
  • 11. 11 Quantitative Risks - Example • Risk ACC is quantified and assigned to task 3 • Cost impact is min $50,000 and max $100,000, average is $75,000
  • 12. 12 Quantitative Risks - Example • $75,000 is within medium cost threshold • Qualitative cost impact is medium
  • 13. 13 Qualitative and Quantitative Risks Assigned to Multiple Tasks • Qualitative: impacts spread across the tasks, per following Risk Register options: – “Spread the risk duration across multiple impacts” – “Spread the risk costs across multiple impacts” • Quantitative: impact averages will be summed to determine qualitative value
  • 14. 14 Mitigation • Mitigation Response of Avoid, Transfer, or Reduce allows for post-mitigation values and score. • Title and Total Cost optional for simple mitigation plan
  • 15. 15 Mitigation - Detailed Actions • Qualitative tab > Mitigation tab > Use Detailed Actions • Multiple mitigation actions with additional fields available
  • 16. 16 Mitigation - Detailed Actions • Total Cost calculated as sum of details actions costs – Excluding actions set to Rejected • Post-mitigated values taken from an action – Rejected actions are not considered – Action with latest finish date is used – Tie goes to action with the lowest score
  • 17. 17 • Mitigation Response set to Accept: any other response allows for mitigation • Use Detailed Actions is selected: post-mitigated values taken from an action • Risk is quantified: post-mitigated values must be set on Quantitative tab Post-Mitigated Options Grayed Out
  • 18. 18 Building an Impacted Plan • (Task ID):B is the original task with no risk impact – Duration and duration uncertainty of the original task
  • 19. 19 Building an Impacted Plan • (Task ID):(Risk ID) is the risk event – Task existence for probability, duration uncertainty for schedule impact, resource uncertainty (ZCRI) for cost impact – Zero remaining duration
  • 20. 20 Building an Impacted Plan • (Task ID) is the summary for base task and risk event – Logic from original task – Resource assignments from original task, unless “Cost Impacts include duration costs” is selected in Risk Register options
  • 21. 21 Correlation • Available on Risk View tab when a risk is assigned to multiple tasks • Impact Ranges 90% correlation, Event Existence 100%
  • 22. 22 Link in Series • Available on Task View tab when a task has multiple risks assigned • When unchecked, risks are in parallel
  • 23. 23 Link in Series - Example 1 • Risks are linked in series • Cumulative effect, both impact schedule
  • 24. 24 Link in Series - Example 2 • Risks are not linked in series, occur in parallel • Only longest duration affects schedule
  • 25. 25 Assigning a Risk to a Summary Task • Risk will impact sub task with latest finish date • Potential for confusion over which task risk will impact and/or unexpected impact
  • 26. 26 Assigning a Risk to a Hammock Task • Crash may occur or impacts may be incorrect • Ability to do so has been removed in version 8.7.0029
  • 27. 27 Other Considerations and FAQs • Opportunity on task near Data Date – Opportunities work by pulling back start date, impact may be incorrect • What do risk start and finish dates affect? – Proximity, exposure plan • Is there a way to quickly assign a risk to a large number of tasks? – Filter on Risk View tab or use “Impacted Task ID(s)” column: IDs separated by comma, no space
  • 28. 28 • Web only • Risk scoring – Thresholds, scoring criteria • Create risks and assign to tasks – Qualitative probabilities and impacts – Risk scores generated • Mitigation – Post-mitigated probabilities, impacts and risk scores Primary P6 R8 Risk Functionality
  • 29. 29 Primary P6 R8 Functionality Define risk scoring under “Administer…Enterprise Data”
  • 30. 30 Primary P6 R8 Functionality Select “Risks” on Projects View to create and assign risks
  • 31. 31 Primary P6 R8 Functionality Use “Response Plans” tab for mitigation
  • 32. 32 Importing a Project from P6 R8 into PRA • Requires Primavera Risk Analysis 8.7.0029 or later • Requires Web Services Utility with appropriate settings – See “Using Web Services to connect” in PRA help • Run Connection Wizard in PRA • Use “File…Primavera…Import Primavera P6 Project” from PRA, no option from P6 R8 Web • Risks only included in single project import
  • 33. 33
  • 34. 34