SlideShare uma empresa Scribd logo
1 de 53
Baixar para ler offline
BUILDING COMMISSIONING:

   The Value of Commissioning




         CaGBC Building Advisor Program
         October, 2012
         John Kokko, P.Eng., CCP, LEED AP
         jkokko@enermodal.com
         519-743-8777 x2424
LEARNING OBJECTIVES

 What is building
  commissioning
 What are the steps required by

  LEED
 Why is it important

 What results can we expect
NEW BUILDING CX

LEED Credits


EAp1 – Fundamental Cx (Prerequisite)
   Deals mainly with construction and getting the building operating before
    hand-over


EAc3 - Enhanced Cx (Credit)
   Deals with design and post occupancy operation
WHAT IS NEW BUILD COMMISSIONING
Definition:
       To bring a new project or facility on line
?
?
?
Hands over a
    building that gives the
    owner what he paid for.
NAME FROM SHIP BUILDING

   A commissioned ship is one deemed ready for service.
   Must pass several milestones.
   Equipment is installed and tested, problems are identified and
    corrected, and staff are extensively trained.
   A commissioned ship is one whose materials, systems, and staff have
    successfully completed a thorough quality assurance process.
   Commissioned ship is one ready to sail safely and reliably
VISION OF COMMISSIONING
      Take the owner’s needs and wants
      ►   Ensure requirements properly articulated
      Through the minds of the consultants
      ►   Ensure designs properly reflect OPR
      Through the hands of suppliers and contractors
      ►   Ensure building is properly built
      Deliver a properly performing building
      ►   Ensure all systems operate as intended
BUILDING Cx = QC FOR CARS?
       Similar to a QC
       process for cars
       Note similarities in:
       Work area
       Tools
       Assembly
       techniques
       Workers’
       responsibilities
WHY IS COMMISSIONING NEEDED
   Don’t the design and construction teams already
    do this?
   Everyone wants to do a good job.
   But two constrains:
     1.   Scope included with fees
     2.   Knowledge of the state-of-the-art
   Low price generally gets the job
   Designers responsible for code
   Site review for conformance to
    drawings and specs
   Not performance beyond obvious
    faults and complaints after the fact
UP-TO-DATE KNOWLEDGE
 Innovation moving extremely fast
 Innovative equipment and

  systems are relatively unfamiliar
  to designers, contractors,
  operators and even
  manufacturers agents
 Energy efficiency, integrated

  systems, imported design
  concepts and computerization
  have multiplied levels of
  complexity
WHAT IS INNOVATION
    MULTIPLE MARRIED TECHNOLOGIES
ADDED COMPLICATIONS
   Radiant heating
   Radiant cooling
   Condensing boiler
   Water-side economizer
   Building automation systems
INNOVATION INCREASING EXPONENTIALLY

      Direct and indirect evaporative cooling
      Optimum start
      Cascading PID loops
      Stratified thermal storage
      Daylighting control
      LON and BACnet
      Integration
             And on and on and on ….
CONVENTIONAL COMMISSIONING


• Start-up and basic check out of equipment
• Testing, Adjusting and Balancing (TAB)
• Begins after systems in and ready for
  start-up
• Verify individual components function as
  components
• Performed by installing contractor or
  manufacturers rep
TOTAL COMMISSIONING (LEED™)

A systematic quality assurance program
Starts at concept design and concludes at end of
  warranty
Includes all phases concept design, detailed design,
  construction, start-up, 1 year operation
Commissioning verifies energy performance and
  comfort maintenance
TOTAL COMMISSIONING (LEED™)

 Includes reviews
 through all stages

 Includes participation

 of consultants, trades,

  O&M staff
 Includes detailed reviews

 design, shop draw, install

 Expanded installation

 verification and start-up checks

 O&M documentation more centralized

 Whole system performance vs. component checks
COMMISSIONING COMPARISON
TOTAL COMMISSIONING              TRADITIONAL COMMISSIONING
Concept Design Reviews           No Cx. Consultant self-checks.
Detailed Design Reviews          No Cx. Consultant self-checks.
Shop Drawing Reviews             No Cx. Dwgs & specs met only.
Site Installation Verification   No Cx. Dwgs & specs met only.
Equipment Start-Up Verification Contractor or Manufacturer only. No
                                  systems interoperability
Balancing Verification           No Cx. Contractor self-checks.
Functional Performance Test      No Cx. Contractor self-checks.
Documentation and Operator       No Cx. Contractor self-checks.
  Training                         Owner verifies acceptability.
Trending and Seasonal FPT        Contractor seldom returns
Warranty and Occupant            No Cx. Respond to complaints only.
              concerns
VALUE OF Cx
     Largest study to date
     Mills, LBNL July 2009

     http://cx.lbl.gov/2009-assessment.html

     643 buildings, 26 US states

     561 existing and 82 new buildings

     37 Cx firms

     99 M ft2, $2.2 B construct

     90.4 M ft2 existing, 8.8 M ft2 new construction

     $43 M Cx costs
NEW BUILDING Cx MEDIANS

        Cx cost, $1.16/ft2 or 0.4% of overall construct cost
        ($290/ft2) (Range $0.60 - $2.15)
        Number of deficiencies identified, 3,528
        (about 1/3 of projects reported deficiencies)
        Energy savings 13% (Range 9% - 29%)
       Payback time, 4.2 years (Range 1.7 to 11.4 yrs)
AREAS OF BENEFIT
         Construction Cost Savings
             Equipment downsizing and trade-offs
         Energy Savings - $0.05 to $0.45/ft2
         Peak demand reductions
         Maintenance and replacement costs reduced
         Increased productivity and reduced liability
                 Indoor environmental quality maintenance
         Carbon emissions reductions
COMMISSIONING PROCESS OVERVIEW
LEED Cx OUTLINE
Design and Construction Phases   EAp1 – Fundamental Cx                 EAc3 – Enhanced Cx

Design                           Owner documents OPR                   Before 50% CD Owner designates
                                                                       CxA
Construction Documents           Designers incorporate Cx specs into   CxA presents Cx Plan
                                 Construction Docs
50% CD                                                                 CxA conducts 50% design review

Post Contract Award              Owner designates CxA                  CxA reviews shop drawings
                                 CxA presents Cx Plan
Installation                     CxA performs/oversees installation
                                 verification
Start-up                         CxA performs/oversees functional
                                 testing
                                                                       CxA reviews O&M Manuals
                                                                       CxA oversees staff training
Substantial Completion           CxA prepares Draft Final Report       CxA prepares Systems Manual

Post Construction                CxA performs/oversees defered
                                 testing
Occupancy                        CxA delivers Final Report             CxA provides Warranty and
                                                                       occupant concerns review
OWNER & DESIGN TEAM DOCUMENTATION
     Owners Project Requirements (OPR)
     ►   Owner and User requirements
     ►   Environmental sustainability goals
     ►   Energy efficiency goals
     ►   Indoor environmental quality requirements
     ►   Equipment and systems expectations
     ►   Building occupant & O&M personnel requirements


     Basis of Design (BoD)
     ►   Primary design assumptions
     ►   Standards
     ►   Narrative descriptions
Cx DURING DESIGN
    Work with design team to define measurable energy and
    indoor environmental quality goals
    Discuss alternatives to traditional design solutions
    Provide support for unfamiliar technologies
    Review to verify design meets objectives and technologies
    properly implemented
    Review to verify equipment specified meets goals and
    objectives
COMMON DESIGN ISSUES

 No design target for energy use
 Lighting power density not identified

 No heat recovery

 Condensing boilers not considered

 Variable speed pumps and fans

     ECM motors not incorporated
 20°F rather than 40°F design

     temp drop design used
 Undersized piping and

  ductwork
Cx PLAN

   Overview of Cx Process
   List of equipment and systems to be Cx

   Cx Team and responsibilities

   Management, Communication and Reporting Overview

   Cx Process Overview (Outline above)

   List of deliverables

   Milestones
Cx MEMBERS & RESPONSIBILITIES
        COMMISSIONING AGENT
         Owner’s rep leading commissioning
         Reviews and produces most paperwork
         Directs testing

         Ensures LEED™ requirements are met

        OWNER
         Provide support as required to ensure Cx
          proceeds smoothly
         FM Staff?

        Consultants
         Provide documentation as required for review
         Attend commissioning meetings as required
Cx MEMBERS & RESPONSIBILITIES

   GENERAL CONTRACTOR
   ►   Ensures contractors meet commissioning
       requirements
   M&E CONTRACTORS
   ► Completes start-up, installation verification lists
   ► Operates equipment for Performance Testing
   ► Produces O&M manuals, Provides owner training

   CONTROLS CONTRACTOR
   ► Operate controls for Performance Testing, produce
     O&M materials for controls
Cx SPECIFICATIONS

         Contractor responsibilities
         Submittal review process

         Meetings

         IVC process

         Start-up process

         Balancing reviews

         FPT process

         O&M manuals requirements

         Training requirements

         Warranty review
Cx DURING CONSTRUCTION


        Verify equipment installed per drawings and
        specs, manuf’rs requirements and proper
        industry practice and standards
        Verify equipment is, set-up, adjusted,
        balanced, controlled and operated to provide
        expected comfort and energy performance
        Provide owner complete systems O&M docs
        Provide owner’s operating personnel
        adequate training to understand, operate and
        maintain equipment
COMMON INSTALLATION ISSUES


 Coils piped backward
 Maintenance access not

  provided
 Pumps with shaft oriented

  improperly
 Thermostats located adjacent

  to heating/cooling diffusers
 Insulation missing

 Sensors improperly located
COMMON FUNCTIONAL TESTING ISSUES

 Controls functions not
  matching sequence
 VFDs do not modulate

 Outdoor damper minimum

  position
 Control valve action reversed
TRAINING TOPICS

      General purpose of system
      Use of O&M manuals

      Operation of systems under all conditions

      Interaction with other systems

      Adjustments and optimization for efficiency

      Health and safety

      Special maintenance and replacement resources

      Occupant interaction

      Controls training
SYSTEMS MANUAL

     Final BoD
     System single line diagrams

     As-Built sequences, set-points, etc.

     System operating instructions

     Maintenance schedule

     Retesting schedule
Cx AFTER OCCUPANCY


     Follow trends on BAS to ensure ongoing operation
     Completion of deficiencies remaining after
     construction
     Follow-up on warranty issues arising
     Follow up on occupant concerns during warranty
     and first year occupancy
     Verify that issues are cleaned up by the end of
     warranty
FINAL REPORT


      OPR
      Design and shops review summary

      Cx specifications

      IVC results

      FPT results

      O&M evaluation

      Value achieved through Cx

      Outstanding issues
MULTI-FUNTION AHU

DESIGN ISSUES
     Dehumidifying only
      outdoor air reduces size of
      equipment and increases
      efficiency of equipment
     Using heat recovery to
      reduce load on cooling coil
     Using indirect evaporative
      cooler to increase HX eff’y
      humidity carried outdoors
MULTI-FUNCTION AHU

   INSTALLATION ISSUES
   No radiation shield on sensor by flame
   No maintenance access to some
    sensors
   Installation of single point sensor
    where averaging required
   Reset button set tight and vibration
    causing unit to cut out
   Overloads not set properly
BOILERS

DESIGN ISSUES
  No check valves would
  required both boilers operate in
  parallel
  Independent controllers would
  not have been coordinated
  Primary only loop with DHW
  would have required
  continuous minimum 160F
BOILER

INSTALLATION ISSUES
   Water treatment eliminated by
    aluminum boiler manufacturer. But
    piping not protected
    OA reset not programmed
    because tech believed it would not
    save energy
    Control sensor located in single
    boiler supply rather than common
    header
RETIREMENT RESIDENCE



HVAC SYSTEM

   Ground loop coupled distributed heat pumps with
    supplemental gas-fired heating.
   One AHU with heat recovery and HP htg/clg for fresh air
    distribution to corridors and common areas
   One AHU with WLHP htg/clg for Kitchen
   Individual HRVs for ventilation and WLHPs for htg/clg in
    each room
RETIREMENT HOME
DESIGN ISSUES

   Heat injection before rather
    than after ground loop
        Moved to eliminate boiler
    heating ground
   HX between building loop and
    ground loop removed
        Reduced capital cost and
    increased efficiency
RETIREMENT HOME Cont’d

    Dedicated DHW heaters
     simplified boiler loop controls,
     allowed summer shutdown
     and allowed primary loop OA
     reset and condensing
    Cascading different
     temperature loops ensured
     cold return water temps
    40°F temp rise drop reduced
     pipe and pump sizing
AIR HANDLER
 SHOP DRAWING REVIEW FINDINGS
 1. 3 re-submittals of heat wheel shop drawings required
    before a workable defrost strategy provided.
 2. Shop drawing coil performance based on water while
    system will used propylene glycol.
 3. Coils have greater air-side and water-side pressure
    drops than specified.
 4. Controls sequences were carbon copy of engineer’s
    general wording rather than converting to specifics that
    can be programmed.
     Heat wheel, heating coil and cooling coils shall be
      sequenced to provide energy efficient operation
SERVICES and REPAIR BUILDING




 HVAC SYSTEM
  Ground Source Heat Pump
  Radiant floor heating

  Dedicated outdoor air ventilation with heat recovery

  Supplemental fan coils for cooling
SERVICE and REPAIR BUILDING

HVAC System
SMALL SERVICES BUILDING


Functional Testing
 System relied on heat pump circulator but never
  programmed to operate when heat pump off
 PID loops needed tuning to provide stable operation

 Radiant floor valve found with wire not connected leaving

  valve open and space overheating
SERVICE AND REPAIR BUILDING CASE STUDY
FUNCTIONAL TEST
        Storage room hot, office cool. Found crossed floor loops. Office
        t’stat controlling floor heat in storage room. Loops not labelled
       Heat pump constantly tripping. Supplier blamed system but did not
        measure any parameters. Cx measurements showed water flows
        ok. Heat pump diagnostics finally found faulty TX valve and low
        refrigerant.
       Controls are probably the single most important item in ensuring
        successful system operation for comfort and energy savings.
         CC programmed system heating water temps lower than
          specified because this works better
         Improperly programmed 24 hr moving average outdoor temp
          caused the system to flip-flop between heating and cooling
REAL PERFORMANCE
What is the energy use of typical buildings?
              800

              700

              600
     Annual
     Energy   500

              400
    ekWh/m2
              300

              200

              100

                0                                                     All data (except GoG) from 
                                                                      NRCan Survey (CIBEUS, 2000).
                    All Bldgs  C&I Accom  Offices    Offices    GoG
                      (ON)       (ON)      (ON)      (CAN)
RETIREMENT RESIDENCE A
Actual Performance
               300



               250
      Annual
      Energy
               200
     ekWh/m2

               150



               100



               50              Simulated                                              Floor Area = 5348 m2

                               Actual

                0
                     Dec '04 (SL)       Nov '05 (SL)   Nov '05 (CBIP)   Jul '06 (Review) Apr '07 to Mar '08
RETIREMENT RESIDENCE B
Actual Performance

              250




              200
     Annual
     Energy

    ekWh/m2   150




              100




              50                                                         Floor Area = 11702 m2

                         Simulated
                         Actual
               0
                     Aug '04 (SL)    Feb '06 (CBIP)   Aug '06 (Review)    Aug '07 to Feb '08
LABORATORY BUILDING
Actual Performance
               500
                             Simulated
                             Actual
               400
      Annual
      Energy

     ekWh/m2   300



               200



               100


                                                                                           Floor Area = 9350 m2
                0
                     Aug '04 (SL)     Aug '06 (CBIP)   Feb '07 (Review)   Dec '07 to Feb '08    Mar to May '08
COMPARISON

                   Actual energy use compared to typical buildings
         800

         700

         600
Annual
         500
Energy

ekWh/m2 400

         300

         200

         100

           0
               All Bldgs  C&I Accom  Offices    Offices    GoG     VA
                                                                 Building     SSJ
                                                                            Building    KPHQ
                                                                                       Building    TRCA
                                                                                                  Building
                 (ON)       (ON)      (ON)      (CAN)               A          B          C          D
MMM Group Limited
100 Commerce Valley Drive West
Thornhill, ON Canada L3T 0A1
t: 905.882.1100 | f: 905.882.0055
e: mmm@mmm.ca

Mais conteúdo relacionado

Mais procurados

Innovative building materials
Innovative building materialsInnovative building materials
Innovative building materialsiindhu567
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean ConstructionVedzen Consultants
 
Green Building Materials
Green Building MaterialsGreen Building Materials
Green Building MaterialsPulkit Shukla
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT Nischay N Gowda
 
Embodied Energy In Building Construction
Embodied Energy In Building ConstructionEmbodied Energy In Building Construction
Embodied Energy In Building ConstructionSandeep Jaiswal
 
Green buildings & Materials
Green buildings & MaterialsGreen buildings & Materials
Green buildings & MaterialsVijay325
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingAnkit Patel
 
Under water concreting
Under water concretingUnder water concreting
Under water concretingAgnesh Shetty
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergiesAnkit Patel
 
green building concept
green building conceptgreen building concept
green building conceptAVDHUT PALANDE
 

Mais procurados (20)

Green building rating system
Green building rating systemGreen building rating system
Green building rating system
 
Innovative building materials
Innovative building materialsInnovative building materials
Innovative building materials
 
IGBC
IGBCIGBC
IGBC
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean Construction
 
Leed
Leed Leed
Leed
 
Green buildings
Green buildingsGreen buildings
Green buildings
 
cracks repairing
 cracks repairing  cracks repairing
cracks repairing
 
Green Building Materials
Green Building MaterialsGreen Building Materials
Green Building Materials
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT
 
Embodied Energy In Building Construction
Embodied Energy In Building ConstructionEmbodied Energy In Building Construction
Embodied Energy In Building Construction
 
Green rating systems
Green rating systemsGreen rating systems
Green rating systems
 
Green buildings & Materials
Green buildings & MaterialsGreen buildings & Materials
Green buildings & Materials
 
BREEAM
BREEAMBREEAM
BREEAM
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergies
 
green building concept
green building conceptgreen building concept
green building concept
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Green building ppt
Green building pptGreen building ppt
Green building ppt
 

Semelhante a The Value of Building Commissioning

Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioningjeff_ranson
 
BDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Engineering
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioningluigiseta
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guidelineMahmoud Ezz
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Nicholas Chazapis
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Nicholas Chazapis
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Processd_mackay
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Dr. Mohamed A. El-Reedy
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdcAvi Grigorescu
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
Design & Development in the Airship Industry
Design & Development in the Airship IndustryDesign & Development in the Airship Industry
Design & Development in the Airship IndustryLen Jones
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 
Doing more with less
Doing more with lessDoing more with less
Doing more with lessmnico
 

Semelhante a The Value of Building Commissioning (20)

Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioning
 
BDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Leed Commissioning Presentation
BDC Leed Commissioning Presentation
 
BDC LEED Cx Preso
BDC LEED Cx PresoBDC LEED Cx Preso
BDC LEED Cx Preso
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioning
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.
 
Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.Chazapis Systems Commissioning Lessons.
Chazapis Systems Commissioning Lessons.
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
EA credit 3
EA credit 3EA credit 3
EA credit 3
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template
 
REEP[1]
REEP[1]REEP[1]
REEP[1]
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
Design & Development in the Airship Industry
Design & Development in the Airship IndustryDesign & Development in the Airship Industry
Design & Development in the Airship Industry
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
Thanzeel CV
Thanzeel CVThanzeel CV
Thanzeel CV
 
Integrative Design Working With Your Mep
Integrative Design Working With Your MepIntegrative Design Working With Your Mep
Integrative Design Working With Your Mep
 
Doing more with less
Doing more with lessDoing more with less
Doing more with less
 
Resume Acc
Resume AccResume Acc
Resume Acc
 

Mais de Toronto 2030 District

GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationGBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationToronto 2030 District
 
GBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & CitiesGBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & CitiesToronto 2030 District
 
GBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the CrosshairsGBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the CrosshairsToronto 2030 District
 
GBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient DesignGBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient DesignToronto 2030 District
 
GBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient CitiesGBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient CitiesToronto 2030 District
 
Closing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel SkogClosing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel SkogToronto 2030 District
 
Re-Energizing Our Cities: From District to Specific - Integral Group
Re-Energizing Our Cities:  From District to Specific - Integral GroupRe-Energizing Our Cities:  From District to Specific - Integral Group
Re-Energizing Our Cities: From District to Specific - Integral GroupToronto 2030 District
 
Sustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta PerssonSustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta PerssonToronto 2030 District
 
Ampersand: A Sustainable Community - Robert Smith
Ampersand:  A Sustainable Community - Robert SmithAmpersand:  A Sustainable Community - Robert Smith
Ampersand: A Sustainable Community - Robert SmithToronto 2030 District
 
An Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow FarabakhshAn Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow FarabakhshToronto 2030 District
 
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...Toronto 2030 District
 
Update on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design ProgramUpdate on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design ProgramToronto 2030 District
 
Toronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy EfficiencyToronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy EfficiencyToronto 2030 District
 
The Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building CodeThe Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building CodeToronto 2030 District
 
Low-Impact Development from the Developer Perspective
Low-Impact Development from the Developer PerspectiveLow-Impact Development from the Developer Perspective
Low-Impact Development from the Developer PerspectiveToronto 2030 District
 
Low-Impact Development Case Study Examples
Low-Impact Development Case Study ExamplesLow-Impact Development Case Study Examples
Low-Impact Development Case Study ExamplesToronto 2030 District
 

Mais de Toronto 2030 District (20)

GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationGBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
 
GBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & CitiesGBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & Cities
 
GBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the CrosshairsGBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the Crosshairs
 
GBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient DesignGBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient Design
 
GBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient CitiesGBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient Cities
 
Closing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel SkogClosing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel Skog
 
Re-Energizing Our Cities: From District to Specific - Integral Group
Re-Energizing Our Cities:  From District to Specific - Integral GroupRe-Energizing Our Cities:  From District to Specific - Integral Group
Re-Energizing Our Cities: From District to Specific - Integral Group
 
Sustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta PerssonSustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta Persson
 
Ampersand: A Sustainable Community - Robert Smith
Ampersand:  A Sustainable Community - Robert SmithAmpersand:  A Sustainable Community - Robert Smith
Ampersand: A Sustainable Community - Robert Smith
 
An Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow FarabakhshAn Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
 
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...
 
B bach energy efficiency in obc2012
B bach energy efficiency in obc2012B bach energy efficiency in obc2012
B bach energy efficiency in obc2012
 
Update on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design ProgramUpdate on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design Program
 
Toronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy EfficiencyToronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy Efficiency
 
The Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building CodeThe Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building Code
 
Stormwater Compliance
Stormwater ComplianceStormwater Compliance
Stormwater Compliance
 
SB-10: The Envelope Ultimatum
SB-10: The Envelope UltimatumSB-10: The Envelope Ultimatum
SB-10: The Envelope Ultimatum
 
National Energy Code for Buildings
National Energy Code for BuildingsNational Energy Code for Buildings
National Energy Code for Buildings
 
Low-Impact Development from the Developer Perspective
Low-Impact Development from the Developer PerspectiveLow-Impact Development from the Developer Perspective
Low-Impact Development from the Developer Perspective
 
Low-Impact Development Case Study Examples
Low-Impact Development Case Study ExamplesLow-Impact Development Case Study Examples
Low-Impact Development Case Study Examples
 

Último

Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girlsssuser7cb4ff
 
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Yantram Animation Studio Corporation
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10uasjlagroup
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in designnooreen17
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,Aginakm1
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024CristobalHeraud
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Servicejennyeacort
 
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...Rishabh Aryan
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证nhjeo1gg
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryrioverosanniejoy
 
Iconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing servicesIconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing servicesIconic global solution
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一D SSS
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 

Último (20)

Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girls
 
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in design
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
 
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industry
 
Iconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing servicesIconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing services
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 

The Value of Building Commissioning

  • 1. BUILDING COMMISSIONING: The Value of Commissioning CaGBC Building Advisor Program October, 2012 John Kokko, P.Eng., CCP, LEED AP jkokko@enermodal.com 519-743-8777 x2424
  • 2. LEARNING OBJECTIVES  What is building commissioning  What are the steps required by LEED  Why is it important  What results can we expect
  • 3. NEW BUILDING CX LEED Credits EAp1 – Fundamental Cx (Prerequisite)  Deals mainly with construction and getting the building operating before hand-over EAc3 - Enhanced Cx (Credit)  Deals with design and post occupancy operation
  • 4. WHAT IS NEW BUILD COMMISSIONING Definition: To bring a new project or facility on line ? ? ? Hands over a building that gives the owner what he paid for.
  • 5. NAME FROM SHIP BUILDING  A commissioned ship is one deemed ready for service.  Must pass several milestones.  Equipment is installed and tested, problems are identified and corrected, and staff are extensively trained.  A commissioned ship is one whose materials, systems, and staff have successfully completed a thorough quality assurance process.  Commissioned ship is one ready to sail safely and reliably
  • 6. VISION OF COMMISSIONING Take the owner’s needs and wants ► Ensure requirements properly articulated Through the minds of the consultants ► Ensure designs properly reflect OPR Through the hands of suppliers and contractors ► Ensure building is properly built Deliver a properly performing building ► Ensure all systems operate as intended
  • 7. BUILDING Cx = QC FOR CARS?  Similar to a QC process for cars  Note similarities in:  Work area  Tools  Assembly techniques  Workers’ responsibilities
  • 8. WHY IS COMMISSIONING NEEDED  Don’t the design and construction teams already do this?  Everyone wants to do a good job.  But two constrains: 1. Scope included with fees 2. Knowledge of the state-of-the-art  Low price generally gets the job  Designers responsible for code  Site review for conformance to drawings and specs  Not performance beyond obvious faults and complaints after the fact
  • 9. UP-TO-DATE KNOWLEDGE  Innovation moving extremely fast  Innovative equipment and systems are relatively unfamiliar to designers, contractors, operators and even manufacturers agents  Energy efficiency, integrated systems, imported design concepts and computerization have multiplied levels of complexity
  • 10. WHAT IS INNOVATION MULTIPLE MARRIED TECHNOLOGIES
  • 11. ADDED COMPLICATIONS  Radiant heating  Radiant cooling  Condensing boiler  Water-side economizer  Building automation systems
  • 12. INNOVATION INCREASING EXPONENTIALLY Direct and indirect evaporative cooling Optimum start Cascading PID loops Stratified thermal storage Daylighting control LON and BACnet Integration And on and on and on ….
  • 13. CONVENTIONAL COMMISSIONING • Start-up and basic check out of equipment • Testing, Adjusting and Balancing (TAB) • Begins after systems in and ready for start-up • Verify individual components function as components • Performed by installing contractor or manufacturers rep
  • 14. TOTAL COMMISSIONING (LEED™) A systematic quality assurance program Starts at concept design and concludes at end of warranty Includes all phases concept design, detailed design, construction, start-up, 1 year operation Commissioning verifies energy performance and comfort maintenance
  • 15. TOTAL COMMISSIONING (LEED™)  Includes reviews  through all stages  Includes participation  of consultants, trades, O&M staff  Includes detailed reviews  design, shop draw, install  Expanded installation  verification and start-up checks  O&M documentation more centralized  Whole system performance vs. component checks
  • 16. COMMISSIONING COMPARISON TOTAL COMMISSIONING TRADITIONAL COMMISSIONING Concept Design Reviews No Cx. Consultant self-checks. Detailed Design Reviews No Cx. Consultant self-checks. Shop Drawing Reviews No Cx. Dwgs & specs met only. Site Installation Verification No Cx. Dwgs & specs met only. Equipment Start-Up Verification Contractor or Manufacturer only. No systems interoperability Balancing Verification No Cx. Contractor self-checks. Functional Performance Test No Cx. Contractor self-checks. Documentation and Operator No Cx. Contractor self-checks. Training Owner verifies acceptability. Trending and Seasonal FPT Contractor seldom returns Warranty and Occupant No Cx. Respond to complaints only. concerns
  • 17. VALUE OF Cx  Largest study to date  Mills, LBNL July 2009  http://cx.lbl.gov/2009-assessment.html  643 buildings, 26 US states  561 existing and 82 new buildings  37 Cx firms  99 M ft2, $2.2 B construct  90.4 M ft2 existing, 8.8 M ft2 new construction  $43 M Cx costs
  • 18. NEW BUILDING Cx MEDIANS  Cx cost, $1.16/ft2 or 0.4% of overall construct cost ($290/ft2) (Range $0.60 - $2.15)  Number of deficiencies identified, 3,528 (about 1/3 of projects reported deficiencies)  Energy savings 13% (Range 9% - 29%)  Payback time, 4.2 years (Range 1.7 to 11.4 yrs)
  • 19. AREAS OF BENEFIT  Construction Cost Savings  Equipment downsizing and trade-offs  Energy Savings - $0.05 to $0.45/ft2  Peak demand reductions  Maintenance and replacement costs reduced  Increased productivity and reduced liability  Indoor environmental quality maintenance  Carbon emissions reductions
  • 21. LEED Cx OUTLINE Design and Construction Phases EAp1 – Fundamental Cx EAc3 – Enhanced Cx Design Owner documents OPR Before 50% CD Owner designates CxA Construction Documents Designers incorporate Cx specs into CxA presents Cx Plan Construction Docs 50% CD CxA conducts 50% design review Post Contract Award Owner designates CxA CxA reviews shop drawings CxA presents Cx Plan Installation CxA performs/oversees installation verification Start-up CxA performs/oversees functional testing CxA reviews O&M Manuals CxA oversees staff training Substantial Completion CxA prepares Draft Final Report CxA prepares Systems Manual Post Construction CxA performs/oversees defered testing Occupancy CxA delivers Final Report CxA provides Warranty and occupant concerns review
  • 22. OWNER & DESIGN TEAM DOCUMENTATION Owners Project Requirements (OPR) ► Owner and User requirements ► Environmental sustainability goals ► Energy efficiency goals ► Indoor environmental quality requirements ► Equipment and systems expectations ► Building occupant & O&M personnel requirements Basis of Design (BoD) ► Primary design assumptions ► Standards ► Narrative descriptions
  • 23. Cx DURING DESIGN  Work with design team to define measurable energy and indoor environmental quality goals  Discuss alternatives to traditional design solutions  Provide support for unfamiliar technologies  Review to verify design meets objectives and technologies properly implemented  Review to verify equipment specified meets goals and objectives
  • 24. COMMON DESIGN ISSUES  No design target for energy use  Lighting power density not identified  No heat recovery  Condensing boilers not considered  Variable speed pumps and fans ECM motors not incorporated  20°F rather than 40°F design temp drop design used  Undersized piping and ductwork
  • 25. Cx PLAN  Overview of Cx Process  List of equipment and systems to be Cx  Cx Team and responsibilities  Management, Communication and Reporting Overview  Cx Process Overview (Outline above)  List of deliverables  Milestones
  • 26. Cx MEMBERS & RESPONSIBILITIES COMMISSIONING AGENT  Owner’s rep leading commissioning  Reviews and produces most paperwork  Directs testing  Ensures LEED™ requirements are met OWNER  Provide support as required to ensure Cx proceeds smoothly  FM Staff? Consultants  Provide documentation as required for review  Attend commissioning meetings as required
  • 27. Cx MEMBERS & RESPONSIBILITIES GENERAL CONTRACTOR ► Ensures contractors meet commissioning requirements M&E CONTRACTORS ► Completes start-up, installation verification lists ► Operates equipment for Performance Testing ► Produces O&M manuals, Provides owner training CONTROLS CONTRACTOR ► Operate controls for Performance Testing, produce O&M materials for controls
  • 28. Cx SPECIFICATIONS  Contractor responsibilities  Submittal review process  Meetings  IVC process  Start-up process  Balancing reviews  FPT process  O&M manuals requirements  Training requirements  Warranty review
  • 29. Cx DURING CONSTRUCTION  Verify equipment installed per drawings and specs, manuf’rs requirements and proper industry practice and standards  Verify equipment is, set-up, adjusted, balanced, controlled and operated to provide expected comfort and energy performance  Provide owner complete systems O&M docs  Provide owner’s operating personnel adequate training to understand, operate and maintain equipment
  • 30. COMMON INSTALLATION ISSUES  Coils piped backward  Maintenance access not provided  Pumps with shaft oriented improperly  Thermostats located adjacent to heating/cooling diffusers  Insulation missing  Sensors improperly located
  • 31. COMMON FUNCTIONAL TESTING ISSUES  Controls functions not matching sequence  VFDs do not modulate  Outdoor damper minimum position  Control valve action reversed
  • 32. TRAINING TOPICS  General purpose of system  Use of O&M manuals  Operation of systems under all conditions  Interaction with other systems  Adjustments and optimization for efficiency  Health and safety  Special maintenance and replacement resources  Occupant interaction  Controls training
  • 33. SYSTEMS MANUAL  Final BoD  System single line diagrams  As-Built sequences, set-points, etc.  System operating instructions  Maintenance schedule  Retesting schedule
  • 34. Cx AFTER OCCUPANCY  Follow trends on BAS to ensure ongoing operation  Completion of deficiencies remaining after construction  Follow-up on warranty issues arising  Follow up on occupant concerns during warranty and first year occupancy  Verify that issues are cleaned up by the end of warranty
  • 35. FINAL REPORT  OPR  Design and shops review summary  Cx specifications  IVC results  FPT results  O&M evaluation  Value achieved through Cx  Outstanding issues
  • 36. MULTI-FUNTION AHU DESIGN ISSUES  Dehumidifying only outdoor air reduces size of equipment and increases efficiency of equipment  Using heat recovery to reduce load on cooling coil  Using indirect evaporative cooler to increase HX eff’y humidity carried outdoors
  • 37. MULTI-FUNCTION AHU  INSTALLATION ISSUES  No radiation shield on sensor by flame  No maintenance access to some sensors  Installation of single point sensor where averaging required  Reset button set tight and vibration causing unit to cut out  Overloads not set properly
  • 38. BOILERS DESIGN ISSUES  No check valves would required both boilers operate in parallel  Independent controllers would not have been coordinated  Primary only loop with DHW would have required continuous minimum 160F
  • 39. BOILER INSTALLATION ISSUES  Water treatment eliminated by aluminum boiler manufacturer. But piping not protected  OA reset not programmed because tech believed it would not save energy  Control sensor located in single boiler supply rather than common header
  • 40. RETIREMENT RESIDENCE HVAC SYSTEM  Ground loop coupled distributed heat pumps with supplemental gas-fired heating.  One AHU with heat recovery and HP htg/clg for fresh air distribution to corridors and common areas  One AHU with WLHP htg/clg for Kitchen  Individual HRVs for ventilation and WLHPs for htg/clg in each room
  • 41. RETIREMENT HOME DESIGN ISSUES  Heat injection before rather than after ground loop  Moved to eliminate boiler heating ground  HX between building loop and ground loop removed  Reduced capital cost and increased efficiency
  • 42. RETIREMENT HOME Cont’d  Dedicated DHW heaters simplified boiler loop controls, allowed summer shutdown and allowed primary loop OA reset and condensing  Cascading different temperature loops ensured cold return water temps  40°F temp rise drop reduced pipe and pump sizing
  • 43. AIR HANDLER SHOP DRAWING REVIEW FINDINGS 1. 3 re-submittals of heat wheel shop drawings required before a workable defrost strategy provided. 2. Shop drawing coil performance based on water while system will used propylene glycol. 3. Coils have greater air-side and water-side pressure drops than specified. 4. Controls sequences were carbon copy of engineer’s general wording rather than converting to specifics that can be programmed.  Heat wheel, heating coil and cooling coils shall be sequenced to provide energy efficient operation
  • 44. SERVICES and REPAIR BUILDING HVAC SYSTEM  Ground Source Heat Pump  Radiant floor heating  Dedicated outdoor air ventilation with heat recovery  Supplemental fan coils for cooling
  • 45. SERVICE and REPAIR BUILDING HVAC System
  • 46. SMALL SERVICES BUILDING Functional Testing  System relied on heat pump circulator but never programmed to operate when heat pump off  PID loops needed tuning to provide stable operation  Radiant floor valve found with wire not connected leaving valve open and space overheating
  • 47. SERVICE AND REPAIR BUILDING CASE STUDY FUNCTIONAL TEST  Storage room hot, office cool. Found crossed floor loops. Office t’stat controlling floor heat in storage room. Loops not labelled  Heat pump constantly tripping. Supplier blamed system but did not measure any parameters. Cx measurements showed water flows ok. Heat pump diagnostics finally found faulty TX valve and low refrigerant.  Controls are probably the single most important item in ensuring successful system operation for comfort and energy savings.  CC programmed system heating water temps lower than specified because this works better  Improperly programmed 24 hr moving average outdoor temp caused the system to flip-flop between heating and cooling
  • 48. REAL PERFORMANCE What is the energy use of typical buildings? 800 700 600 Annual Energy 500 400 ekWh/m2 300 200 100 0 All data (except GoG) from  NRCan Survey (CIBEUS, 2000). All Bldgs  C&I Accom  Offices  Offices  GoG (ON) (ON) (ON) (CAN)
  • 49. RETIREMENT RESIDENCE A Actual Performance 300 250 Annual Energy 200 ekWh/m2 150 100 50 Simulated Floor Area = 5348 m2 Actual 0 Dec '04 (SL) Nov '05 (SL) Nov '05 (CBIP) Jul '06 (Review) Apr '07 to Mar '08
  • 50. RETIREMENT RESIDENCE B Actual Performance 250 200 Annual Energy ekWh/m2 150 100 50 Floor Area = 11702 m2 Simulated Actual 0 Aug '04 (SL) Feb '06 (CBIP) Aug '06 (Review) Aug '07 to Feb '08
  • 51. LABORATORY BUILDING Actual Performance 500 Simulated Actual 400 Annual Energy ekWh/m2 300 200 100 Floor Area = 9350 m2 0 Aug '04 (SL) Aug '06 (CBIP) Feb '07 (Review) Dec '07 to Feb '08 Mar to May '08
  • 52. COMPARISON Actual energy use compared to typical buildings 800 700 600 Annual 500 Energy ekWh/m2 400 300 200 100 0 All Bldgs  C&I Accom  Offices  Offices  GoG VA Building SSJ Building KPHQ Building TRCA Building (ON) (ON) (ON) (CAN) A B C D
  • 53. MMM Group Limited 100 Commerce Valley Drive West Thornhill, ON Canada L3T 0A1 t: 905.882.1100 | f: 905.882.0055 e: mmm@mmm.ca