1. BUILDING COMMISSIONING:
The Value of Commissioning
CaGBC Building Advisor Program
October, 2012
John Kokko, P.Eng., CCP, LEED AP
jkokko@enermodal.com
519-743-8777 x2424
2. LEARNING OBJECTIVES
What is building
commissioning
What are the steps required by
LEED
Why is it important
What results can we expect
3. NEW BUILDING CX
LEED Credits
EAp1 – Fundamental Cx (Prerequisite)
Deals mainly with construction and getting the building operating before
hand-over
EAc3 - Enhanced Cx (Credit)
Deals with design and post occupancy operation
4. WHAT IS NEW BUILD COMMISSIONING
Definition:
To bring a new project or facility on line
?
?
?
Hands over a
building that gives the
owner what he paid for.
5. NAME FROM SHIP BUILDING
A commissioned ship is one deemed ready for service.
Must pass several milestones.
Equipment is installed and tested, problems are identified and
corrected, and staff are extensively trained.
A commissioned ship is one whose materials, systems, and staff have
successfully completed a thorough quality assurance process.
Commissioned ship is one ready to sail safely and reliably
6. VISION OF COMMISSIONING
Take the owner’s needs and wants
► Ensure requirements properly articulated
Through the minds of the consultants
► Ensure designs properly reflect OPR
Through the hands of suppliers and contractors
► Ensure building is properly built
Deliver a properly performing building
► Ensure all systems operate as intended
7. BUILDING Cx = QC FOR CARS?
Similar to a QC
process for cars
Note similarities in:
Work area
Tools
Assembly
techniques
Workers’
responsibilities
8. WHY IS COMMISSIONING NEEDED
Don’t the design and construction teams already
do this?
Everyone wants to do a good job.
But two constrains:
1. Scope included with fees
2. Knowledge of the state-of-the-art
Low price generally gets the job
Designers responsible for code
Site review for conformance to
drawings and specs
Not performance beyond obvious
faults and complaints after the fact
9. UP-TO-DATE KNOWLEDGE
Innovation moving extremely fast
Innovative equipment and
systems are relatively unfamiliar
to designers, contractors,
operators and even
manufacturers agents
Energy efficiency, integrated
systems, imported design
concepts and computerization
have multiplied levels of
complexity
11. ADDED COMPLICATIONS
Radiant heating
Radiant cooling
Condensing boiler
Water-side economizer
Building automation systems
12. INNOVATION INCREASING EXPONENTIALLY
Direct and indirect evaporative cooling
Optimum start
Cascading PID loops
Stratified thermal storage
Daylighting control
LON and BACnet
Integration
And on and on and on ….
13. CONVENTIONAL COMMISSIONING
• Start-up and basic check out of equipment
• Testing, Adjusting and Balancing (TAB)
• Begins after systems in and ready for
start-up
• Verify individual components function as
components
• Performed by installing contractor or
manufacturers rep
14. TOTAL COMMISSIONING (LEED™)
A systematic quality assurance program
Starts at concept design and concludes at end of
warranty
Includes all phases concept design, detailed design,
construction, start-up, 1 year operation
Commissioning verifies energy performance and
comfort maintenance
15. TOTAL COMMISSIONING (LEED™)
Includes reviews
through all stages
Includes participation
of consultants, trades,
O&M staff
Includes detailed reviews
design, shop draw, install
Expanded installation
verification and start-up checks
O&M documentation more centralized
Whole system performance vs. component checks
16. COMMISSIONING COMPARISON
TOTAL COMMISSIONING TRADITIONAL COMMISSIONING
Concept Design Reviews No Cx. Consultant self-checks.
Detailed Design Reviews No Cx. Consultant self-checks.
Shop Drawing Reviews No Cx. Dwgs & specs met only.
Site Installation Verification No Cx. Dwgs & specs met only.
Equipment Start-Up Verification Contractor or Manufacturer only. No
systems interoperability
Balancing Verification No Cx. Contractor self-checks.
Functional Performance Test No Cx. Contractor self-checks.
Documentation and Operator No Cx. Contractor self-checks.
Training Owner verifies acceptability.
Trending and Seasonal FPT Contractor seldom returns
Warranty and Occupant No Cx. Respond to complaints only.
concerns
17. VALUE OF Cx
Largest study to date
Mills, LBNL July 2009
http://cx.lbl.gov/2009-assessment.html
643 buildings, 26 US states
561 existing and 82 new buildings
37 Cx firms
99 M ft2, $2.2 B construct
90.4 M ft2 existing, 8.8 M ft2 new construction
$43 M Cx costs
18. NEW BUILDING Cx MEDIANS
Cx cost, $1.16/ft2 or 0.4% of overall construct cost
($290/ft2) (Range $0.60 - $2.15)
Number of deficiencies identified, 3,528
(about 1/3 of projects reported deficiencies)
Energy savings 13% (Range 9% - 29%)
Payback time, 4.2 years (Range 1.7 to 11.4 yrs)
19. AREAS OF BENEFIT
Construction Cost Savings
Equipment downsizing and trade-offs
Energy Savings - $0.05 to $0.45/ft2
Peak demand reductions
Maintenance and replacement costs reduced
Increased productivity and reduced liability
Indoor environmental quality maintenance
Carbon emissions reductions
21. LEED Cx OUTLINE
Design and Construction Phases EAp1 – Fundamental Cx EAc3 – Enhanced Cx
Design Owner documents OPR Before 50% CD Owner designates
CxA
Construction Documents Designers incorporate Cx specs into CxA presents Cx Plan
Construction Docs
50% CD CxA conducts 50% design review
Post Contract Award Owner designates CxA CxA reviews shop drawings
CxA presents Cx Plan
Installation CxA performs/oversees installation
verification
Start-up CxA performs/oversees functional
testing
CxA reviews O&M Manuals
CxA oversees staff training
Substantial Completion CxA prepares Draft Final Report CxA prepares Systems Manual
Post Construction CxA performs/oversees defered
testing
Occupancy CxA delivers Final Report CxA provides Warranty and
occupant concerns review
22. OWNER & DESIGN TEAM DOCUMENTATION
Owners Project Requirements (OPR)
► Owner and User requirements
► Environmental sustainability goals
► Energy efficiency goals
► Indoor environmental quality requirements
► Equipment and systems expectations
► Building occupant & O&M personnel requirements
Basis of Design (BoD)
► Primary design assumptions
► Standards
► Narrative descriptions
23. Cx DURING DESIGN
Work with design team to define measurable energy and
indoor environmental quality goals
Discuss alternatives to traditional design solutions
Provide support for unfamiliar technologies
Review to verify design meets objectives and technologies
properly implemented
Review to verify equipment specified meets goals and
objectives
24. COMMON DESIGN ISSUES
No design target for energy use
Lighting power density not identified
No heat recovery
Condensing boilers not considered
Variable speed pumps and fans
ECM motors not incorporated
20°F rather than 40°F design
temp drop design used
Undersized piping and
ductwork
25. Cx PLAN
Overview of Cx Process
List of equipment and systems to be Cx
Cx Team and responsibilities
Management, Communication and Reporting Overview
Cx Process Overview (Outline above)
List of deliverables
Milestones
26. Cx MEMBERS & RESPONSIBILITIES
COMMISSIONING AGENT
Owner’s rep leading commissioning
Reviews and produces most paperwork
Directs testing
Ensures LEED™ requirements are met
OWNER
Provide support as required to ensure Cx
proceeds smoothly
FM Staff?
Consultants
Provide documentation as required for review
Attend commissioning meetings as required
27. Cx MEMBERS & RESPONSIBILITIES
GENERAL CONTRACTOR
► Ensures contractors meet commissioning
requirements
M&E CONTRACTORS
► Completes start-up, installation verification lists
► Operates equipment for Performance Testing
► Produces O&M manuals, Provides owner training
CONTROLS CONTRACTOR
► Operate controls for Performance Testing, produce
O&M materials for controls
28. Cx SPECIFICATIONS
Contractor responsibilities
Submittal review process
Meetings
IVC process
Start-up process
Balancing reviews
FPT process
O&M manuals requirements
Training requirements
Warranty review
29. Cx DURING CONSTRUCTION
Verify equipment installed per drawings and
specs, manuf’rs requirements and proper
industry practice and standards
Verify equipment is, set-up, adjusted,
balanced, controlled and operated to provide
expected comfort and energy performance
Provide owner complete systems O&M docs
Provide owner’s operating personnel
adequate training to understand, operate and
maintain equipment
30. COMMON INSTALLATION ISSUES
Coils piped backward
Maintenance access not
provided
Pumps with shaft oriented
improperly
Thermostats located adjacent
to heating/cooling diffusers
Insulation missing
Sensors improperly located
31. COMMON FUNCTIONAL TESTING ISSUES
Controls functions not
matching sequence
VFDs do not modulate
Outdoor damper minimum
position
Control valve action reversed
32. TRAINING TOPICS
General purpose of system
Use of O&M manuals
Operation of systems under all conditions
Interaction with other systems
Adjustments and optimization for efficiency
Health and safety
Special maintenance and replacement resources
Occupant interaction
Controls training
33. SYSTEMS MANUAL
Final BoD
System single line diagrams
As-Built sequences, set-points, etc.
System operating instructions
Maintenance schedule
Retesting schedule
34. Cx AFTER OCCUPANCY
Follow trends on BAS to ensure ongoing operation
Completion of deficiencies remaining after
construction
Follow-up on warranty issues arising
Follow up on occupant concerns during warranty
and first year occupancy
Verify that issues are cleaned up by the end of
warranty
35. FINAL REPORT
OPR
Design and shops review summary
Cx specifications
IVC results
FPT results
O&M evaluation
Value achieved through Cx
Outstanding issues
36. MULTI-FUNTION AHU
DESIGN ISSUES
Dehumidifying only
outdoor air reduces size of
equipment and increases
efficiency of equipment
Using heat recovery to
reduce load on cooling coil
Using indirect evaporative
cooler to increase HX eff’y
humidity carried outdoors
37. MULTI-FUNCTION AHU
INSTALLATION ISSUES
No radiation shield on sensor by flame
No maintenance access to some
sensors
Installation of single point sensor
where averaging required
Reset button set tight and vibration
causing unit to cut out
Overloads not set properly
38. BOILERS
DESIGN ISSUES
No check valves would
required both boilers operate in
parallel
Independent controllers would
not have been coordinated
Primary only loop with DHW
would have required
continuous minimum 160F
39. BOILER
INSTALLATION ISSUES
Water treatment eliminated by
aluminum boiler manufacturer. But
piping not protected
OA reset not programmed
because tech believed it would not
save energy
Control sensor located in single
boiler supply rather than common
header
40. RETIREMENT RESIDENCE
HVAC SYSTEM
Ground loop coupled distributed heat pumps with
supplemental gas-fired heating.
One AHU with heat recovery and HP htg/clg for fresh air
distribution to corridors and common areas
One AHU with WLHP htg/clg for Kitchen
Individual HRVs for ventilation and WLHPs for htg/clg in
each room
41. RETIREMENT HOME
DESIGN ISSUES
Heat injection before rather
than after ground loop
Moved to eliminate boiler
heating ground
HX between building loop and
ground loop removed
Reduced capital cost and
increased efficiency
42. RETIREMENT HOME Cont’d
Dedicated DHW heaters
simplified boiler loop controls,
allowed summer shutdown
and allowed primary loop OA
reset and condensing
Cascading different
temperature loops ensured
cold return water temps
40°F temp rise drop reduced
pipe and pump sizing
43. AIR HANDLER
SHOP DRAWING REVIEW FINDINGS
1. 3 re-submittals of heat wheel shop drawings required
before a workable defrost strategy provided.
2. Shop drawing coil performance based on water while
system will used propylene glycol.
3. Coils have greater air-side and water-side pressure
drops than specified.
4. Controls sequences were carbon copy of engineer’s
general wording rather than converting to specifics that
can be programmed.
Heat wheel, heating coil and cooling coils shall be
sequenced to provide energy efficient operation
44. SERVICES and REPAIR BUILDING
HVAC SYSTEM
Ground Source Heat Pump
Radiant floor heating
Dedicated outdoor air ventilation with heat recovery
Supplemental fan coils for cooling
46. SMALL SERVICES BUILDING
Functional Testing
System relied on heat pump circulator but never
programmed to operate when heat pump off
PID loops needed tuning to provide stable operation
Radiant floor valve found with wire not connected leaving
valve open and space overheating
47. SERVICE AND REPAIR BUILDING CASE STUDY
FUNCTIONAL TEST
Storage room hot, office cool. Found crossed floor loops. Office
t’stat controlling floor heat in storage room. Loops not labelled
Heat pump constantly tripping. Supplier blamed system but did not
measure any parameters. Cx measurements showed water flows
ok. Heat pump diagnostics finally found faulty TX valve and low
refrigerant.
Controls are probably the single most important item in ensuring
successful system operation for comfort and energy savings.
CC programmed system heating water temps lower than
specified because this works better
Improperly programmed 24 hr moving average outdoor temp
caused the system to flip-flop between heating and cooling
48. REAL PERFORMANCE
What is the energy use of typical buildings?
800
700
600
Annual
Energy 500
400
ekWh/m2
300
200
100
0 All data (except GoG) from
NRCan Survey (CIBEUS, 2000).
All Bldgs C&I Accom Offices Offices GoG
(ON) (ON) (ON) (CAN)
49. RETIREMENT RESIDENCE A
Actual Performance
300
250
Annual
Energy
200
ekWh/m2
150
100
50 Simulated Floor Area = 5348 m2
Actual
0
Dec '04 (SL) Nov '05 (SL) Nov '05 (CBIP) Jul '06 (Review) Apr '07 to Mar '08
50. RETIREMENT RESIDENCE B
Actual Performance
250
200
Annual
Energy
ekWh/m2 150
100
50 Floor Area = 11702 m2
Simulated
Actual
0
Aug '04 (SL) Feb '06 (CBIP) Aug '06 (Review) Aug '07 to Feb '08
51. LABORATORY BUILDING
Actual Performance
500
Simulated
Actual
400
Annual
Energy
ekWh/m2 300
200
100
Floor Area = 9350 m2
0
Aug '04 (SL) Aug '06 (CBIP) Feb '07 (Review) Dec '07 to Feb '08 Mar to May '08
52. COMPARISON
Actual energy use compared to typical buildings
800
700
600
Annual
500
Energy
ekWh/m2 400
300
200
100
0
All Bldgs C&I Accom Offices Offices GoG VA
Building SSJ
Building KPHQ
Building TRCA
Building
(ON) (ON) (ON) (CAN) A B C D
53. MMM Group Limited
100 Commerce Valley Drive West
Thornhill, ON Canada L3T 0A1
t: 905.882.1100 | f: 905.882.0055
e: mmm@mmm.ca