What can we learn from the
Hoover Dam project that
influenced modern project
management?
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT VOL.32(2014) P.256-264
YOUNG HOON KWAK, JOHN WALEWSKI, DANA SLEEPER AND HESSAM SADATSAFAVI
102034550 簡翊真
102034611 董咨均
Index
 Introduce
 Video
 Abstract
 Background
 History of the Hoover Dam project by project phases
 Hoover Dam Project challenges and innovative
management
 Lessons learned from comparing megaproject
framework by the Department of Energy (DOE)
 Conclusion
Introduction
 Location: Clark County/ Arizona, US
 Duration: 1931 ~ 1936 (2 yrs earlier)
 Life cost: 112 person
 Cost: $ 833 million with inflation
 Length: 379m, Height: 221.4m, Width: 200m
 Company: Six Companies, Inc.
 Purpose: control floods, provide irrigation water and
produce hydroelectric power for Nevada, Arizona, and
California.
Introduction
Why Hoover Dam is so special?
Reason1 - Breakthrough
• Never built such large dam before
• Techniques were unproven
Reason2 – Time limit
• Get fund if not on time
• Built the road on canyon before start
Video
 One is from the history aspect
 One is from the construction aspect
Abstract
 This paper examines project and program management
practices applied to the building of the Hoover Dam,
and discusses how these factors contributed to the
establishment and evolution of modern project
management principles, tools, and techniques.
Background
The greatest engineering and construction projects
In the Great Depression
 Completed in 1936
 Two years ahead of schedule and under
budget
History of the Hoover Dam project
by project phases
Conceptual
phase
Planning,
execution
and
construction
phase
Close out
phase
History of the Hoover Dam project
by project phases
 Colorado River Compact
 In Black Canyon
 dividing generated electricity
Fourth version of the Boulder
Canyon Project Act
1920 1928
12190419
History of the Hoover Dam project
by project phases
Frank T. Crowe
 Work on the foundation
 Technical and productivity innovations
 Electric lighting
 Aerial tramways
Planning, execution and construction phase
1931
General Superintendent
30192919
History of the Hoover Dam project
by project phases  The dam and power house were
turned over to the Interior
Department in February 1936,
26 months ahead of schedule
and $15 million under budget.
 Six Companies, Inc. was also
able to overcome many obstacles
in the construction of the dam
and secure a profit of $13 million.
Close out phase
1936
35193419
Hoover Dam Project challenges
and innovative management
Human
resources
Innovative
project
management
There are various issues, including organizational, managerial,
planning, and implemental challenges, obstacles, solutions,
and suggestions related to the Hoover Dam project.
Strategic
value
creation
 Economical and managerial challenges
 Ensuring the profitability of the project
 Determining the hydroelectric power rate
 Dividing the water and power to seven Basin states
 Supporting the construction activities
 Safety and health issues
Hoover Dam Project challenges
and innovative management Strategic
value
creation
 Government relations
 Hoover Dam project was one of the first examples
of a partnership between public and private sectors
 Joint ventures
 Foremost among innovative managerial solutions
was the employment of a joint venture involving
eight different firms, organized into six partners.
Hoover Dam Project challenges
and innovative management Strategic
value
creation
 Innovative resources allocations
 Unbalanced bid
 Technological innovations
 Overhead cableway
 Jumbo Drill
 Concrete mixing plant
Innovative
project
management
Hoover Dam Project challenges
and innovative management
 Human Resources
 Managing workers relations
 Pushing workers on output
 Taking a non-negotiation stance with unions
 providing healthcare
Special medical dispensaries
 lack of safety programs
Human
resources
Hoover Dam Project challenges
and innovative management
Lessons learned from comparing megaproject
framework by the Department of Energy (DOE)
Method
 Frame Work developed by the Department of Energy (DOE)
Four Major phases:
 Key factors that were common to large construction projects delivered
successfully from the standpoint of cost, schedule, and scope.
Purpose
 Checklist can be used in different types of projects as a benchmark
against generally accepted characteristics of successful project.
Preconcepti
on
Conception Execution Closeout
 Clear define everything (1/6)
 Project Champion (2/6)
 Relationship (3/6)
 Leadership (4/6)
 Contract (5/6)
 Government (6/6)
Condition cited as essential to success by
DOE & Hoover Dam project
Clear define everything (1/6)
DOE
1. Project sponsors know what
they need and afford.
2. Has a purpose and benefits
are clearly defined.
Hoover Dam
1. All the essential need understood
by both public and private
agencies.
2. All revenue were divided long
before the operation of the dam.
Project Champion (2/6)
DOE
Has one project champion
whose position and behavior
can benefits the project.
Hoover Dam
Agency maintain a close relationship
with parties, state and labors.
For instance:
• Address conflicts between public
against private interests and states
benefits.
• Deal with the strike problem.
• Secure adequately annual funds.
Relationship (3/6)
DOE
Open communications, mutual
trust, and close coordination are
maintained between
owner/users and project.
Hoover Dam
Government (Parties, Federal..)
Bureau of Reclamation
Contractor of the project
( Six Companies, resident
construction engineer…)r
Project manager (4/6)
DOE
1. Experienced project
manager
2. Project builder, possesses
the requisite technical,
managerial, and
communications skills, and
is brought into the project
early.
Hoover Dam
1. Interior secretary : addressing
financial and political considerations
of the project
2. Commissioner of the Bureau
of Reclamation : playing the role
of project champion .
3. Resident construction
engineer : strengthen the chain of
command between site superintendent
and company's senior management.
Contract (5/6)
DOE
1. Contract incentives are clear
and unambiguous,
appropriate to the
performance objectives.
2. Adequately compensate the
contractor for the use of
resources, risks.
Hoover Dam
1. Construction phase is divided into
major sub-phase and deadline
were set for each one of them.
2. Penalty for each delay
For instance:
• The deadline for diversion of the
Colorado River was set as October
1st, 1933. Had to pay $3000 for
each day passing this deadline.
Government(6/6)
DOE
The half life of the political
sponsors that decided to
proceed with the project
exceeds the half life of the
project.
Hoover Dam
Mainly support by federal
government from the initiation to the
final.
Conclusion
 Project need to satisfying legislative requirements as the
result of which challenges can overcome by the parties
involved.
 Both Bureau of Reclamation and Six Companies, Inc. at the
field level and the executive level.
 Ensuring the construction are review board which
minimized rework and delay during construction.
 Establishing a clear chain of command in the owner and
contractor.
 Securing adequate annual funding and relevant legislative
and regulatory facilities.
Thank for your attention.
Thank for your attention.

Mais conteúdo relacionado

Mais procurados

Nucor Case Analysis
Nucor Case AnalysisNucor Case Analysis
Nucor Case AnalysisBskwarski87
 
Case analysis boeing 787
Case analysis boeing 787Case analysis boeing 787
Case analysis boeing 787Ashish Michael
 
Haier: Taking a chinese company global in 2011
Haier: Taking a chinese company global in 2011Haier: Taking a chinese company global in 2011
Haier: Taking a chinese company global in 2011Ilaria Fiore
 
Hewlett packard company Hewlett Packard Company Deskjet Printer Supply Chain
Hewlett packard company Hewlett Packard Company Deskjet Printer Supply ChainHewlett packard company Hewlett Packard Company Deskjet Printer Supply Chain
Hewlett packard company Hewlett Packard Company Deskjet Printer Supply Chainaliyudhi_h
 
The Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
The Walt Disney Company and Pixar Inc.: To Acquire or Not to AcquireThe Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
The Walt Disney Company and Pixar Inc.: To Acquire or Not to AcquireEric Moon
 
Toyota Operations Case Study
Toyota Operations Case Study Toyota Operations Case Study
Toyota Operations Case Study Martin Massiah
 
Donner case study om
Donner case study   omDonner case study   om
Donner case study omPratik Patel
 
Case study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of WebvanCase study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of WebvanRutvik Bapat
 
Apple INC.: Managing a Global Supply Chain
Apple INC.: Managing a Global Supply ChainApple INC.: Managing a Global Supply Chain
Apple INC.: Managing a Global Supply ChainAyesha Majid
 
The Toyota Way (Toyota Production System) [Operations Management]
The Toyota Way (Toyota Production System) [Operations Management]The Toyota Way (Toyota Production System) [Operations Management]
The Toyota Way (Toyota Production System) [Operations Management]Arjun Parekh
 
Medisys Corp - Case Presentation
Medisys Corp - Case Presentation Medisys Corp - Case Presentation
Medisys Corp - Case Presentation Abhirup Rudra
 
Ford motor final presentation
Ford motor final presentationFord motor final presentation
Ford motor final presentationadithya_msridhar
 
IDEO Product Development Presentation Team 4_Final
IDEO Product Development Presentation Team 4_FinalIDEO Product Development Presentation Team 4_Final
IDEO Product Development Presentation Team 4_FinalKaren He
 
Case study of Competitive advantage at Dell Inc
Case study of  Competitive advantage at Dell IncCase study of  Competitive advantage at Dell Inc
Case study of Competitive advantage at Dell IncMehvish Rehman
 

Mais procurados (20)

Dore Dore case study
Dore Dore case studyDore Dore case study
Dore Dore case study
 
MediSys Corp- Case Study
MediSys Corp- Case Study MediSys Corp- Case Study
MediSys Corp- Case Study
 
Nucor Case Analysis
Nucor Case AnalysisNucor Case Analysis
Nucor Case Analysis
 
Case analysis boeing 787
Case analysis boeing 787Case analysis boeing 787
Case analysis boeing 787
 
Matching Dell
Matching DellMatching Dell
Matching Dell
 
Haier: Taking a chinese company global in 2011
Haier: Taking a chinese company global in 2011Haier: Taking a chinese company global in 2011
Haier: Taking a chinese company global in 2011
 
Hewlett packard company Hewlett Packard Company Deskjet Printer Supply Chain
Hewlett packard company Hewlett Packard Company Deskjet Printer Supply ChainHewlett packard company Hewlett Packard Company Deskjet Printer Supply Chain
Hewlett packard company Hewlett Packard Company Deskjet Printer Supply Chain
 
The Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
The Walt Disney Company and Pixar Inc.: To Acquire or Not to AcquireThe Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
The Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
 
Toyota Operations Case Study
Toyota Operations Case Study Toyota Operations Case Study
Toyota Operations Case Study
 
Donner case study om
Donner case study   omDonner case study   om
Donner case study om
 
Terracog gps
Terracog gpsTerracog gps
Terracog gps
 
Case study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of WebvanCase study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of Webvan
 
Hp case study
Hp case studyHp case study
Hp case study
 
Apple INC.: Managing a Global Supply Chain
Apple INC.: Managing a Global Supply ChainApple INC.: Managing a Global Supply Chain
Apple INC.: Managing a Global Supply Chain
 
The Toyota Way (Toyota Production System) [Operations Management]
The Toyota Way (Toyota Production System) [Operations Management]The Toyota Way (Toyota Production System) [Operations Management]
The Toyota Way (Toyota Production System) [Operations Management]
 
Xerox & Fuji Xerox
Xerox & Fuji XeroxXerox & Fuji Xerox
Xerox & Fuji Xerox
 
Medisys Corp - Case Presentation
Medisys Corp - Case Presentation Medisys Corp - Case Presentation
Medisys Corp - Case Presentation
 
Ford motor final presentation
Ford motor final presentationFord motor final presentation
Ford motor final presentation
 
IDEO Product Development Presentation Team 4_Final
IDEO Product Development Presentation Team 4_FinalIDEO Product Development Presentation Team 4_Final
IDEO Product Development Presentation Team 4_Final
 
Case study of Competitive advantage at Dell Inc
Case study of  Competitive advantage at Dell IncCase study of  Competitive advantage at Dell Inc
Case study of Competitive advantage at Dell Inc
 

Destaque

Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentLengkengs
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vicmrs_murphy_ncssm
 
Note for Hoover Dam
Note for Hoover DamNote for Hoover Dam
Note for Hoover DamLengkengs
 
Hoover dam bypass_bridge2
Hoover dam bypass_bridge2Hoover dam bypass_bridge2
Hoover dam bypass_bridge2George Martin
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridgeBismillah Arif
 
TEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONSTEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONSA Y V CHENULU
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentLengkengs
 
Herbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumHerbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumAidan Brady
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homeworkmrzislion
 
The hoover dam 3
The hoover dam 3The hoover dam 3
The hoover dam 3l yingling
 
Grace Cathedral - San Francisco California
Grace Cathedral  - San Francisco CaliforniaGrace Cathedral  - San Francisco California
Grace Cathedral - San Francisco CaliforniaSteven Cantler
 
Hoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaHoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaSteven Cantler
 
4M Presentation - E-learning platform
4M Presentation - E-learning platform4M Presentation - E-learning platform
4M Presentation - E-learning platformProxicon Ltd
 
Ppt on tehri dam by shubham dobhal
Ppt on tehri dam by shubham dobhalPpt on tehri dam by shubham dobhal
Ppt on tehri dam by shubham dobhalShubham Dobhal
 

Destaque (20)

Hoover dam
Hoover damHoover dam
Hoover dam
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vic
 
Note for Hoover Dam
Note for Hoover DamNote for Hoover Dam
Note for Hoover Dam
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
 
HOOVER DAM DOC
HOOVER DAM DOCHOOVER DAM DOC
HOOVER DAM DOC
 
Hoover dam bypass_bridge2
Hoover dam bypass_bridge2Hoover dam bypass_bridge2
Hoover dam bypass_bridge2
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridge
 
Hoover Dam by John Howard
Hoover Dam by John HowardHoover Dam by John Howard
Hoover Dam by John Howard
 
TEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONSTEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONS
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
 
Herbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumHerbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-Museum
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homework
 
Hoover
HooverHoover
Hoover
 
Women
WomenWomen
Women
 
The hoover dam 3
The hoover dam 3The hoover dam 3
The hoover dam 3
 
Grace Cathedral - San Francisco California
Grace Cathedral  - San Francisco CaliforniaGrace Cathedral  - San Francisco California
Grace Cathedral - San Francisco California
 
Hoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaHoover Dam - Arizona & Nevada
Hoover Dam - Arizona & Nevada
 
4M Presentation - E-learning platform
4M Presentation - E-learning platform4M Presentation - E-learning platform
4M Presentation - E-learning platform
 
Ppt on tehri dam by shubham dobhal
Ppt on tehri dam by shubham dobhalPpt on tehri dam by shubham dobhal
Ppt on tehri dam by shubham dobhal
 

Semelhante a What can we learn from the hoover dam

Nuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKeeNuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKeedignagni
 
State senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperState senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperpeggydrouet
 
Improving Megaproject Performance (2011)
Improving Megaproject Performance (2011)Improving Megaproject Performance (2011)
Improving Megaproject Performance (2011)Michael Filippich
 
Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docxcravennichole326
 
Project Management
Project ManagementProject Management
Project ManagementAnton Orlov
 
LEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docxLEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docxcroysierkathey
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxcravennichole326
 
The Channel Tunnel
The Channel TunnelThe Channel Tunnel
The Channel TunnelPriya Raj
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfAdina Levin
 
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_RegionPresentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_RegionKevin Lovell, PMP
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfMartinsAras
 
Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...
Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...
Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...Association for Project Management
 
Derek Dhonau resume
Derek Dhonau resumeDerek Dhonau resume
Derek Dhonau resumeDerek Dhonau
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Nicholas Phelan
 
Project Complexity (Case study)
Project Complexity (Case study)Project Complexity (Case study)
Project Complexity (Case study)Sunny Mahajan
 
Civil10
Civil10Civil10
Civil10saihem
 
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...Adam Berry
 
DSD-Kampala 2023 Modelling in support of decision making - Russell
DSD-Kampala 2023 Modelling in support of decision making - RussellDSD-Kampala 2023 Modelling in support of decision making - Russell
DSD-Kampala 2023 Modelling in support of decision making - RussellDeltares
 

Semelhante a What can we learn from the hoover dam (20)

Nuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKeeNuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKee
 
State senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperState senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaper
 
Improving Megaproject Performance (2011)
Improving Megaproject Performance (2011)Improving Megaproject Performance (2011)
Improving Megaproject Performance (2011)
 
Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docx
 
Project Management
Project ManagementProject Management
Project Management
 
LEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docxLEADERSHIP ROLES With a project of this magnitude, it .docx
LEADERSHIP ROLES With a project of this magnitude, it .docx
 
projects
projectsprojects
projects
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
 
The Channel Tunnel
The Channel TunnelThe Channel Tunnel
The Channel Tunnel
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdf
 
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_RegionPresentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdf
 
Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...
Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...
Conflict management with lessons from history by Mark Kozak-Holland, 18 Oct 2...
 
Derek Dhonau resume
Derek Dhonau resumeDerek Dhonau resume
Derek Dhonau resume
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
 
Eschenburg Resume 1
Eschenburg  Resume 1Eschenburg  Resume 1
Eschenburg Resume 1
 
Project Complexity (Case study)
Project Complexity (Case study)Project Complexity (Case study)
Project Complexity (Case study)
 
Civil10
Civil10Civil10
Civil10
 
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
Multifunctional Stormwater Projects - An Innovative Technical Design and Part...
 
DSD-Kampala 2023 Modelling in support of decision making - Russell
DSD-Kampala 2023 Modelling in support of decision making - RussellDSD-Kampala 2023 Modelling in support of decision making - Russell
DSD-Kampala 2023 Modelling in support of decision making - Russell
 

Último

Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...lizamodels9
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdftbatkhuu1
 

Último (20)

Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdf
 

What can we learn from the hoover dam

  • 1. What can we learn from the Hoover Dam project that influenced modern project management? INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT VOL.32(2014) P.256-264 YOUNG HOON KWAK, JOHN WALEWSKI, DANA SLEEPER AND HESSAM SADATSAFAVI 102034550 簡翊真 102034611 董咨均
  • 2. Index  Introduce  Video  Abstract  Background  History of the Hoover Dam project by project phases  Hoover Dam Project challenges and innovative management  Lessons learned from comparing megaproject framework by the Department of Energy (DOE)  Conclusion
  • 3. Introduction  Location: Clark County/ Arizona, US  Duration: 1931 ~ 1936 (2 yrs earlier)  Life cost: 112 person  Cost: $ 833 million with inflation  Length: 379m, Height: 221.4m, Width: 200m  Company: Six Companies, Inc.  Purpose: control floods, provide irrigation water and produce hydroelectric power for Nevada, Arizona, and California.
  • 4. Introduction Why Hoover Dam is so special? Reason1 - Breakthrough • Never built such large dam before • Techniques were unproven Reason2 – Time limit • Get fund if not on time • Built the road on canyon before start
  • 5. Video  One is from the history aspect  One is from the construction aspect
  • 6. Abstract  This paper examines project and program management practices applied to the building of the Hoover Dam, and discusses how these factors contributed to the establishment and evolution of modern project management principles, tools, and techniques.
  • 7. Background The greatest engineering and construction projects In the Great Depression  Completed in 1936  Two years ahead of schedule and under budget
  • 8. History of the Hoover Dam project by project phases Conceptual phase Planning, execution and construction phase Close out phase
  • 9. History of the Hoover Dam project by project phases  Colorado River Compact  In Black Canyon  dividing generated electricity Fourth version of the Boulder Canyon Project Act 1920 1928 12190419
  • 10. History of the Hoover Dam project by project phases Frank T. Crowe  Work on the foundation  Technical and productivity innovations  Electric lighting  Aerial tramways Planning, execution and construction phase 1931 General Superintendent 30192919
  • 11. History of the Hoover Dam project by project phases  The dam and power house were turned over to the Interior Department in February 1936, 26 months ahead of schedule and $15 million under budget.  Six Companies, Inc. was also able to overcome many obstacles in the construction of the dam and secure a profit of $13 million. Close out phase 1936 35193419
  • 12. Hoover Dam Project challenges and innovative management Human resources Innovative project management There are various issues, including organizational, managerial, planning, and implemental challenges, obstacles, solutions, and suggestions related to the Hoover Dam project. Strategic value creation
  • 13.  Economical and managerial challenges  Ensuring the profitability of the project  Determining the hydroelectric power rate  Dividing the water and power to seven Basin states  Supporting the construction activities  Safety and health issues Hoover Dam Project challenges and innovative management Strategic value creation
  • 14.  Government relations  Hoover Dam project was one of the first examples of a partnership between public and private sectors  Joint ventures  Foremost among innovative managerial solutions was the employment of a joint venture involving eight different firms, organized into six partners. Hoover Dam Project challenges and innovative management Strategic value creation
  • 15.  Innovative resources allocations  Unbalanced bid  Technological innovations  Overhead cableway  Jumbo Drill  Concrete mixing plant Innovative project management Hoover Dam Project challenges and innovative management
  • 16.  Human Resources  Managing workers relations  Pushing workers on output  Taking a non-negotiation stance with unions  providing healthcare Special medical dispensaries  lack of safety programs Human resources Hoover Dam Project challenges and innovative management
  • 17. Lessons learned from comparing megaproject framework by the Department of Energy (DOE) Method  Frame Work developed by the Department of Energy (DOE) Four Major phases:  Key factors that were common to large construction projects delivered successfully from the standpoint of cost, schedule, and scope. Purpose  Checklist can be used in different types of projects as a benchmark against generally accepted characteristics of successful project. Preconcepti on Conception Execution Closeout
  • 18.  Clear define everything (1/6)  Project Champion (2/6)  Relationship (3/6)  Leadership (4/6)  Contract (5/6)  Government (6/6) Condition cited as essential to success by DOE & Hoover Dam project
  • 19. Clear define everything (1/6) DOE 1. Project sponsors know what they need and afford. 2. Has a purpose and benefits are clearly defined. Hoover Dam 1. All the essential need understood by both public and private agencies. 2. All revenue were divided long before the operation of the dam.
  • 20. Project Champion (2/6) DOE Has one project champion whose position and behavior can benefits the project. Hoover Dam Agency maintain a close relationship with parties, state and labors. For instance: • Address conflicts between public against private interests and states benefits. • Deal with the strike problem. • Secure adequately annual funds.
  • 21. Relationship (3/6) DOE Open communications, mutual trust, and close coordination are maintained between owner/users and project. Hoover Dam Government (Parties, Federal..) Bureau of Reclamation Contractor of the project ( Six Companies, resident construction engineer…)r
  • 22. Project manager (4/6) DOE 1. Experienced project manager 2. Project builder, possesses the requisite technical, managerial, and communications skills, and is brought into the project early. Hoover Dam 1. Interior secretary : addressing financial and political considerations of the project 2. Commissioner of the Bureau of Reclamation : playing the role of project champion . 3. Resident construction engineer : strengthen the chain of command between site superintendent and company's senior management.
  • 23. Contract (5/6) DOE 1. Contract incentives are clear and unambiguous, appropriate to the performance objectives. 2. Adequately compensate the contractor for the use of resources, risks. Hoover Dam 1. Construction phase is divided into major sub-phase and deadline were set for each one of them. 2. Penalty for each delay For instance: • The deadline for diversion of the Colorado River was set as October 1st, 1933. Had to pay $3000 for each day passing this deadline.
  • 24. Government(6/6) DOE The half life of the political sponsors that decided to proceed with the project exceeds the half life of the project. Hoover Dam Mainly support by federal government from the initiation to the final.
  • 25. Conclusion  Project need to satisfying legislative requirements as the result of which challenges can overcome by the parties involved.  Both Bureau of Reclamation and Six Companies, Inc. at the field level and the executive level.  Ensuring the construction are review board which minimized rework and delay during construction.  Establishing a clear chain of command in the owner and contractor.  Securing adequate annual funding and relevant legislative and regulatory facilities.
  • 26. Thank for your attention.
  • 27. Thank for your attention.