  Network analysis is the general name given to
  certain specific techniques which can be used
  for the planning, management and control of
  projects.
 Use of nodes and arrows:-

Arrows  An arrow leads from tail to head
  directionally
       Indicate ACTIVITY, a time consuming effort that is
        required to perform a part of the work.
•   NODE:-
    A  node is represented by a circle
    - Indicate EVENT, a point in time where one or
      more activities start and/or finish.
•   Activity:-
    –   A task or a certain amount of work required in the
        project
    –   Requires time to complete
    –   Represented by an arrow
•   Dummy Activity:-
    – Indicates only precedence relationships
    – Does not require any time of effort.
   Event:-
       Signals the beginning or ending of an activity
       Designates a point in time
       Represented by a circle (node)
   Network:-
       Shows the sequential relationships among
        activities using nodes and arrows
   Activity-on-node (AON):-
    nodes represent activities, and arrows show precedence
      relationships
   Activity-on-arrow (AOA):-
    arrows represent activities and nodes are events for points
      in time
SITUATIONS IN NETWORK DIAGRAM:-
             B
                         A must finish before either B or C
             C           can start.
    A
                 C       Both A and B must finish before C
    B                    can start.
    A        C            Both A and B must finish before
                         either of C or D can start.
    B        D


                         A must finish before B can start
         B
A                        both A and C must finish before
        Dummy            D can start.

    C                D
 illustration of network analysis of a minor
  redesign of a product and its associated
  packaging.
The key question is: How long will it take to
complete this project ?
   Path
       A connected sequence of activities leading from the
        starting event to the ending event
   Critical Path
       The longest path (time); determines the project
        duration
   Critical Activities
       All of the activities that make up the critical path.
Forward Pass:-
   Earliest Start Time (ES)
     earliest time an activity can start
     ES = maximum EF of immediate predecessors


   Earliest finish time (EF)
     earliest time an activity can finish
     earliest start time plus activity time
                            EF= ES+t
Backward Pass:-
   Latest Start Time (LS)
    Latest time an activity can start without delaying critical
      path time
      LS= LF - t
   Latest finish time (LF)
    latest time an activity can be completed without
       delaying critical path time
    LS = minimum LS of immediate predecessors
   Draw the CPM network
   Analyze the paths through the network
   Determine the float for each activity
     Compute the activity’s float
                float = LS - ES = LF - EF
     Float is the maximum amount of time that this
      activity can be delay in its completion before it
      becomes a critical activity, i.e., delays completion of
      the project
   Find the critical path is that the sequence of activities
    and events where there is no “slack” i.e.. Zero slack
     Longest path through a network
   Find the project duration is minimum project
   CPM Network:-
                            f, 15


                              g, 17              h, 9
       a, 6
                                      i, 6


              b, 8

                             d, 13       j, 12


                     c, 5
                            e, 9
   ES and EF Times:-
                            f, 15

                              g, 17              h, 9
      a, 6
      0 6                             i, 6

             b, 8
           0 8                           j, 12
                            d, 13


       0     5      c, 5
                           e, 9
   ES and EF Times:-
                                         6     21
                                             f, 15


                                                  g, 17                   h, 9
            a, 6
                                     6       23
        0        6                                             i, 6


                     b, 8
                 0        8                   d, 13               j, 12

                                         8        21
                              c, 5
             0        5
                                             e, 9

                                                    5     14
   ES and EF Times:-
                                          6   21
                                    f, 15
                                                                         21 30
       0     6
                                      g, 17                               h, 9
      a, 6
                               6     23
                                                          i, 6
                    0      8                            23 29
             b, 8

                                     d, 13 8       21            j, 12

                                                                         21 33
                    c, 5
       0     5
                                   e, 9
                                                         Project’s EF = 33
                                          5   14
   LS and LF Times:-
                                              6    21
                                              0     0
                                  f, 15                                21 30
          0     6                                                      24 33
          0     0
                                    g, 17                              h, 9
         a, 6
                              6     23
                                                             i, 6 23 29
                              0      0                            27 33
                 0     8
                 0     0
                b, 8                               8    21     j, 12
                                  d, 13
                                                   0     0
                                                                       21 33
                       c, 5                                            21 33
     0     5
     0     0                  e, 9

                                          5       14
                                          0        0
   LS and LF Times:-
                                            6 21
                                           18 24
                                                                    21 30
                                   f, 15
         0      6                                                   24 33
         4     10
                              6 23 g, 17                           h, 9
        a, 6                                          23 29
                             10 27
                                                      27 33 i, 6

                 0     8
                 0     8      8   21
               b, 8           8   21                       j, 12
                                           d, 13
                                                                   21 33
    0    5
                      c, 5                                         21 33
    7   12
                                  e, 9
                                               5 14
                                              12 21
FLOAT:-
                                                 6     21
                                        03
                                                 9     24
                                              f, 15                              21 30
                                                                             3
                                                                                 24 33
                 0 6
        3
                 4 10                       g, 17                                h, 9
                a, 6                     6 23
                                     04
                                        10 27
                                                                    23 29 i, 6
                                                                4
                          0      8                                  27 33
                  0                      8      21
                          0      8   0
                      b, 8               8      21
                                                      d, 13              j, 12

                                                                                     21 33
                                                                                 0
            0     5           c, 5                                                   21 33
    7
            7    12                      e, 9            5 14
                                                 7
                                                        12 21
   Critical Path:-
                              f, 15


                                  g, 17                h, 9
      a, 6
                                                i, 6



             b, 8
                                      d, 13   j, 12


                    c, 5
                           e, 9
   PERT is based on the assumption that an activity’s
    duration follows a probability distribution instead
    of being a single value
   Three time estimates are required to compute the
    parameters of an activity’s duration distribution:
     pessimistic time (tp ) - the time the activity
      would take if things did not go well
     most likely time (tm ) - the consensus best
      estimate of the activity’s duration
     optimistic time (to ) - the time the activity would
      take if things did go well
       te = a+4m+b
                6
   Draw the network.
   Analyze the paths through the network and find
    the critical path.
   The length of the critical path is the mean of the
    project duration probability distribution which is
    assumed to be normal
   The standard deviation of the project duration
    probability distribution is computed by adding
    the variances of the critical activities (all of the
    activities that make up the critical path) and
    taking the square root of that sum
   Probability computations can now be made using
    the normal distribution table.
Determine probability that project is completed
 within specified time
Z=   x-



   where   = tp = project mean time
      = project standard mean time
    x = (proposed ) specified time
Probability




       Z




= tp       x             Time
   Useful at many stages of project management
   Mathematically simple
   Give critical path and slack time
   Provide project documentation
   Useful in monitoring costs
•   How long will the entire project take to be
    completed? What are the risks involved?
•   Which are the critical activities or tasks in the
    project which could delay the entire project if they
    were not completed on time?
•   Is the project on schedule, behind schedule or
    ahead of schedule?
•   If the project has to be finished earlier than
    planned, what is the best way to do this at the least
    cost?
   Parallel paths-identifying a single path is difficult
    when there are parallel paths with similar duration.
   Time consuming-critics note that it takes too much
    time to identify all activities and inter-relate them to
    get multiple projects paths.
   First time projects-CPM is not suitable if projects
    cannot be broken down into discrete activities with
    known completion times.
PRESENTED BY:-
BHUPENDRA SINGH SHEKHAWAT
ANKIT VINOD AGARWAL

Mais conteúdo relacionado

Mais procurados

Project management
Project managementProject management
Project managementJay Raval
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalJude Iheanacho
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniquesTata Dinyuy
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
Introduction to monitoring and evaluation Ungaluk Program 2015
Introduction to monitoring and evaluation Ungaluk Program 2015Introduction to monitoring and evaluation Ungaluk Program 2015
Introduction to monitoring and evaluation Ungaluk Program 2015Martin Comeau
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementWaleed Elnaggar
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt chartsVARSHA RUSTAGI
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 

Mais procurados (20)

Project management
Project managementProject management
Project management
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project Management
Project ManagementProject Management
Project Management
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Project planning
Project planning Project planning
Project planning
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Introduction to monitoring and evaluation Ungaluk Program 2015
Introduction to monitoring and evaluation Ungaluk Program 2015Introduction to monitoring and evaluation Ungaluk Program 2015
Introduction to monitoring and evaluation Ungaluk Program 2015
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 

Semelhante a Project Management PERT and CPM

Semelhante a Project Management PERT and CPM (8)

Day 6 graphing review
Day 6 graphing reviewDay 6 graphing review
Day 6 graphing review
 
Algo 23 MSTP
Algo 23 MSTPAlgo 23 MSTP
Algo 23 MSTP
 
Critical Path Examples
Critical Path ExamplesCritical Path Examples
Critical Path Examples
 
Img 0002
Img 0002Img 0002
Img 0002
 
Double patterning (4/20 update)
Double patterning (4/20 update)Double patterning (4/20 update)
Double patterning (4/20 update)
 
Greedy embedding problem
Greedy embedding problemGreedy embedding problem
Greedy embedding problem
 
Minimum spanning Tree
Minimum spanning TreeMinimum spanning Tree
Minimum spanning Tree
 
Cpm & network diagrams
Cpm & network diagramsCpm & network diagrams
Cpm & network diagrams
 

Mais de Institute of Rural Management (10)

Opec Organization of Petroleum Exporting Countries
Opec Organization of Petroleum Exporting CountriesOpec Organization of Petroleum Exporting Countries
Opec Organization of Petroleum Exporting Countries
 
Talent management
Talent managementTalent management
Talent management
 
Economic System
Economic SystemEconomic System
Economic System
 
Business cycle
Business cycleBusiness cycle
Business cycle
 
3 c's 4 p's of Management
3 c's 4 p's of Management3 c's 4 p's of Management
3 c's 4 p's of Management
 
MBO and MBE
MBO and MBEMBO and MBE
MBO and MBE
 
Personality and emotions ppt marks.
Personality and emotions ppt marks.Personality and emotions ppt marks.
Personality and emotions ppt marks.
 
Research process and sampling
Research process and samplingResearch process and sampling
Research process and sampling
 
Supply
SupplySupply
Supply
 
Planning
PlanningPlanning
Planning
 

Último

Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 

Último (20)

Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 

Project Management PERT and CPM

  • 1.
  • 2.  Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects.  Use of nodes and arrows:- Arrows  An arrow leads from tail to head directionally  Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work.
  • 3. NODE:- A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. • Activity:- – A task or a certain amount of work required in the project – Requires time to complete – Represented by an arrow • Dummy Activity:- – Indicates only precedence relationships – Does not require any time of effort.
  • 4. Event:-  Signals the beginning or ending of an activity  Designates a point in time  Represented by a circle (node)  Network:-  Shows the sequential relationships among activities using nodes and arrows  Activity-on-node (AON):- nodes represent activities, and arrows show precedence relationships  Activity-on-arrow (AOA):- arrows represent activities and nodes are events for points in time
  • 5. SITUATIONS IN NETWORK DIAGRAM:- B A must finish before either B or C C can start. A C Both A and B must finish before C B can start. A C Both A and B must finish before either of C or D can start. B D A must finish before B can start B A both A and C must finish before Dummy D can start. C D
  • 6.  illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
  • 7.
  • 8.
  • 9. Path  A connected sequence of activities leading from the starting event to the ending event  Critical Path  The longest path (time); determines the project duration  Critical Activities  All of the activities that make up the critical path.
  • 10. Forward Pass:-  Earliest Start Time (ES)  earliest time an activity can start  ES = maximum EF of immediate predecessors  Earliest finish time (EF)  earliest time an activity can finish  earliest start time plus activity time EF= ES+t
  • 11. Backward Pass:-  Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t  Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors
  • 12. Draw the CPM network  Analyze the paths through the network  Determine the float for each activity  Compute the activity’s float float = LS - ES = LF - EF  Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project  Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack  Longest path through a network  Find the project duration is minimum project
  • 13. CPM Network:- f, 15 g, 17 h, 9 a, 6 i, 6 b, 8 d, 13 j, 12 c, 5 e, 9
  • 14. ES and EF Times:- f, 15 g, 17 h, 9 a, 6 0 6 i, 6 b, 8 0 8 j, 12 d, 13 0 5 c, 5 e, 9
  • 15. ES and EF Times:- 6 21 f, 15 g, 17 h, 9 a, 6 6 23 0 6 i, 6 b, 8 0 8 d, 13 j, 12 8 21 c, 5 0 5 e, 9 5 14
  • 16. ES and EF Times:- 6 21 f, 15 21 30 0 6 g, 17 h, 9 a, 6 6 23 i, 6 0 8 23 29 b, 8 d, 13 8 21 j, 12 21 33 c, 5 0 5 e, 9 Project’s EF = 33 5 14
  • 17. LS and LF Times:- 6 21 0 0 f, 15 21 30 0 6 24 33 0 0 g, 17 h, 9 a, 6 6 23 i, 6 23 29 0 0 27 33 0 8 0 0 b, 8 8 21 j, 12 d, 13 0 0 21 33 c, 5 21 33 0 5 0 0 e, 9 5 14 0 0
  • 18. LS and LF Times:- 6 21 18 24 21 30 f, 15 0 6 24 33 4 10 6 23 g, 17 h, 9 a, 6 23 29 10 27 27 33 i, 6 0 8 0 8 8 21 b, 8 8 21 j, 12 d, 13 21 33 0 5 c, 5 21 33 7 12 e, 9 5 14 12 21
  • 19. FLOAT:- 6 21  03 9 24 f, 15 21 30 3 24 33 0 6 3 4 10 g, 17 h, 9 a, 6 6 23 04 10 27 23 29 i, 6 4 0 8 27 33 0 8 21 0 8 0 b, 8 8 21 d, 13 j, 12 21 33 0 0 5 c, 5 21 33 7 7 12 e, 9 5 14 7 12 21
  • 20. Critical Path:- f, 15 g, 17 h, 9 a, 6 i, 6 b, 8 d, 13 j, 12 c, 5 e, 9
  • 21. PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value  Three time estimates are required to compute the parameters of an activity’s duration distribution:  pessimistic time (tp ) - the time the activity would take if things did not go well  most likely time (tm ) - the consensus best estimate of the activity’s duration  optimistic time (to ) - the time the activity would take if things did go well te = a+4m+b 6
  • 22. Draw the network.  Analyze the paths through the network and find the critical path.  The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal  The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum  Probability computations can now be made using the normal distribution table.
  • 23. Determine probability that project is completed within specified time Z= x-  where = tp = project mean time  = project standard mean time  x = (proposed ) specified time
  • 24. Probability Z = tp x Time
  • 25. Useful at many stages of project management  Mathematically simple  Give critical path and slack time  Provide project documentation  Useful in monitoring costs
  • 26. How long will the entire project take to be completed? What are the risks involved? • Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? • Is the project on schedule, behind schedule or ahead of schedule? • If the project has to be finished earlier than planned, what is the best way to do this at the least cost?
  • 27. Parallel paths-identifying a single path is difficult when there are parallel paths with similar duration.  Time consuming-critics note that it takes too much time to identify all activities and inter-relate them to get multiple projects paths.  First time projects-CPM is not suitable if projects cannot be broken down into discrete activities with known completion times.
  • 28. PRESENTED BY:- BHUPENDRA SINGH SHEKHAWAT ANKIT VINOD AGARWAL