SlideShare uma empresa Scribd logo
1 de 67
Baixar para ler offline
Report No. IRL99440.01




     NETWORK
RELIABILITY AND FIRM
  POWER CAPACITY
     WORKSHOP

       HELD AT INDUSTRIAL RESEARCH LIMITED,
       GRACEFIELD, FRIDAY 16TH DECEMBER 2005



      ISSUES, NEEDS, CONCLUSIONS AND ACTION
                      POINTS




                  Prepared by: Dr. Iain Sanders,
             Sustainable Innovative Solutions Ltd.
                (for Industrial Research Limited)
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Table of Contents
1.     Introduction                                                            Page 3

         1.1 Summary                                                           Page 3

         1.2 Background                                                        Page 3

         1.3 What is Firm Power Capacity?                                      Page 4

         1.4 Why is Network Reliability an                                     Page 4
             Issue for New Zealand?

         1.5 Overview of the Rest of this Report                               Page 4

2.     Key Conclusions                                                         Page 5

3.     Action Points Raised                                                    Page 12

4.     Workshop Summary                                                        Page 15

5.     Supplementary Feedback from Participants                                Page 41

6.     Appendices                                                              Page 42

         6.1 Workshop Agenda                                                   Page 42

         6.2 List of Attendees                                                 Page 43

         6.3 Alternative Policy Frameworks for DG                              Page 45

         6.4 Capacity Metering for General Customers                           Page 59


Editorial Statement: We have attempted to faithfully report and draw
conclusions from the presentations and discussions at the workshop. Neither
Industrial Research Limited nor Sustainable Innovative Solutions Limited
necessarily endorse these findings.
Alister Gardiner, Industrial Research Limited.
Iain Sanders, Sustainable Innovative Solutions Limited.


Disclaimer: The Commerce Commission does not comment on policy
matters. The Commission has participated only to explain its approach to
assessing breaches of quality thresholds by electricity lines businesses where
caused by extreme events, and has not participated in discussions on nor
makes any comment in regard to other technical matters or industry design
matters.
Paolo Ryan, Manager, Network Performance Group.


                                                                                Page 2 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)



1. Introduction
1.1 Summary
On Friday December 16th, Industrial Research Limited held a workshop in
Gracefield, Lower Hutt, Wellington, on “Network Reliability Requirements” to
which electricity industry stakeholders contributed.

The purpose of this workshop was to provide an industry forum to discuss key
reliability issues facing network operators in relation to the growing interest in
connection of distributed generation plant.

The workshop presenters in order of appearance were:

• Alan Jenkins, Chief Executive, Electricity Networks Association
• Rodney Doyle, Chief Advisor, Network Performance Group, Commerce
  Commission
• Gareth Wilson, Manager of the Electricity Group, Ministry of Economic
  Development (MED)
• Robert Reilly, Senior Advisor Retail, Electricity Commission
• Duncan Head, Divisional Manager Business Development, Vector Networks
• Brent Noriss, Engineering Manager, The Lines Company
• Matt Todd, CEO, Eastland Networks Limited
• Robert Reilly (speaking on behalf of Roy Hemmingway, Chair, Electricity
  Commission
• Todd Mead, Generation Development Manager, MainPower
• Iain Sanders, CEO, Sustainable Innovative Solutions Limited (formerly of
  Industrial Research Limited)
• Alister Gardiner, Hydrogen and Distributed Energy Platform Manager,
  Industrial Research Limited

These presenters discussed regulations, policies, technical issues, business
development and research opportunities and challenges associated with
delivering firm power capacity in Distribution networks from conventional
network infrastructure assets (e.g. lines and poles and underground cables)
and alternatives options, including: load management, embedded distributed
generation and storage systems.


1.2 Background
Network reliability is essential to the safe and secure operation of New
Zealand’s electricity delivery infrastructure. Distributed generation adds a new
level of complexity for operating networks. This workshop explored some of
the needs for reliable firm power capacity in New Zealand’s electricity network
infrastructure. Reliability issues were examined from conventional network
delivery and alternative energy generation perspectives.

This workshop was the first in a series of two workshops. The second
workshop (to be held around the middle of 2006) will report on and
demonstrate models and techniques developed by Industrial Research for


                                                                              Page 3 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)



evaluating the impact of distributed energy resources on network reliability, to
providing a means for objective comparison of different distributed energy
resources against network capacity costs.


1.3 What is Firm Power Capacity?
Firm power capacity is defined as “the provision of power capacity when and
where it is required, with a high degree of certainty” (Industrial Research
Limited). This constitutes firm power capacity as described in this report and
as discussed during the workshop.


1.4 Why is Network Reliability an Issue for New Zealand?
Network reliability is affected by the age and cost of maintaining infrastructure
assets. Alternative energy supply options such as distributed energy
resources may in some circumstances provide more reliable and affordable
energy delivery solutions.

Ageing infrastructure assets can cost too much to maintain – there just isn’t
enough revenue generated from the service provided.

In other places, network delivery capacities are exceeded because growth in
peak demand cannot be met by existing infrastructure capacity.

Complimentary localized dispersed generation can address some of the
network reliability issues mentioned. This is only possible if affordable
distributed generation resources can match the network reliability
requirements of the energy demand needs they address.


1.5 Overview of the Rest of this Report
In the next section (2. Key Conclusions), a summary of the main conclusions
derived from the workshop are presented under appropriate headings that
best define the key points raised.

Following the “Key Conclusions”, is a section that presents a series of action
points (3. Action Points Raised) or recommendations towards helping to
address some of the issues identified as needing urgent attention.

After section three, there is a summary of the entire workshop (4. Workshop
Summary), outlining the main points raised, issues addressed and specific
needs identified by each speaker and the audience in the Q&A sessions
following each formal presentation.

The final section (5. Appendices), provides the workshop agenda (5.1), and a
list of attendees (5.2). A couple of appendices (5.3 and 5.4) describe in further
detail some of the conclusions from a technical, commercial and regulatory
perspective.




                                                                              Page 4 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)



2. Key Conclusions
The following conclusions were derived from the forum discussion and the
question and answer sessions held after each presentation.

These high level conclusions indicate concern about governance in the
industry affecting future reliability through an uncertain investment climate, of
which the future for distributed generation is only one component.

“Sustainable development” was frequently used in the workshop as the
primary need for the industry and government to address. No attempt is made
to define the meaning intended by participants, although network “reliability” is
clearly an important contributor to this concept.


Ref.     Key Conclusions


C1       Long-term needs not addressed by short-term political agendas.

         a. The energy industry of New Zealand is the economic engine critical
         to the nation’s survival and prosperity over the next 25 years.

         b. Therefore we need to do a lot more evaluation about what the way
         forward for the electricity supply sector ought to be.

         c. There are major concerns about the overall lack of integration and
         mismatch of issues in the energy sector regarding possible energy
         futures and mapping out a suitable path forward.

         d. The central generation electricity market model needs to be
         supported with reinforcement. We have a bureaucratic structure for
         energy policy in New Zealand that is: “confused and has a great deal
         of difficulty making decisions” (forum participant).

         e. Many reports are being written, submissions made, requests for
         information given etc., but no decisions are being made that address
         the issues and concerns raised.

         f. New Zealand needs an energy strategy to address mid- to long-term
         needs.




                                                                                Page 5 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Ref.     Key Conclusions


C2       Untapped potential for sustainable development due to
         fragmented markets.

         a. Sustainable development is possible if there is the political will to
         succeed, backed by a commitment to make the hard decisions and
         consistently pursue policies and directives critical to achieving this
         outcome.

         b. Sustainable development includes the significant adoption of
         distributed energy resources, energy efficient design and utilization,
         load management, and energy conservation in buildings, industrial
         processes etc.

         c. With respect to sustainable development, the question is: what is
         technically possible if we have the will to achieve it? What is technically
         possible within the timeframes required? Considering grid-
         interconnection guidelines, the Resource Management Act (RMA),
         Power Purchase Agreements (PPAs) etc.?

         d. Credibility is a key issue for policymakers to address if progress is
         going to be made. If it is desirable and doable, then why aren’t we
         making it happen? I.e. putting structures and policies and standards
         and regulations etc. in place that will facilitate the uptake and
         establishment of a more sustainable energy market in New Zealand for
         our long-term growth and prosperity?




                                                                                Page 6 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Ref.     Key Conclusions


C3       Many opportunities missed or lost due to lack of coordinated
         planning between Government and industry stakeholders.

         a. If barriers to investment in distributed energy resources were
         effectively reduced and removed, the New Zealand electricity industry
         could experience a transformation, through competition driving
         innovation, technology advances, business process and practice
         improvements, new product developments and practical contractual,
         regulatory and policy design.

         b. The electricity market only accounts for about 9% of New Zealand’s
         CO2 emissions. Farming is responsible for half the country’s
         emissions, and transport takes care of most of the rest. Industrial
         transformation would be possible if the electricity industry could help
         substantially to reduce farming and transport greenhouse gas
         emissions, by focusing on security of supply without increasing CO2
         emissions from the energy resources required to achieve it. How much
         more can the electricity grid be used to supply the energy demands
         that are currently being met by non-electrical thermal conversion
         processes? E.g. fuel substitution and methane gas conversion.

         c. Poorly thought out strategies for banning wood burning for
         environmental reasons is placing an increasing strain on already
         capacity-constrained peak loading of networks (and doesn’t account
         for peak generation fossil fuel CO2 emissions). Here we have
         disincentives for better load management and conservation of energy
         resources. How do we create incentives for more efficient and effective
         energy management and delivery solutions?

         d. There is a major lack of coordination between new generation
         planning and network infrastructure utilization for delivering it.
         Consequently, many new generation and network infrastructure
         investments are suboptimal. Long-term needs are not addressed
         through lack of coordinated optimal design of solutions because they
         involve competing electricity market stakeholders. Short-term vested
         financial interests take priority over long-term sustainable security of
         supply.

         e. There are great opportunities for New Zealand to implement
         sustainable renewable energy options, but it only takes one barrier e.g.
         the Resource Management Act to bring an entire project to a halt
         indefinitely.




                                                                                Page 7 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Ref.     Key Conclusions


C4       Short-term micro-management drives decision-making process
         because of distrust between Government and industry.

         a. How do we reconcile: assurance from Government to industry: for
         Government to implement consistent long-term policies that work,
         versus assurance from industry to Government: that industry will
         deliver solutions that work? Unless we are really clear about
         reconciling and balancing the need for the former with the need for the
         latter, we will not know what we can technically do if we have the will to
         achieve it.

         b. How do we build a market system that starts to account for and
         incorporate external costs and benefits as part of the total value
         equation; and, furthermore, Government must take responsibility for
         leading the sustainable development of New Zealand’s energy future.

         c. How well do we manage and utilize our energy resources, and how
         can we do it better? What do investors need for sustainable energy
         development to become a practical reality?




                                                                                Page 8 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Ref.     Key Conclusions


C5       Current decision-making framework is inadequate for developing
         a consensus amongst Government and industry stakeholders to
         take appropriate action to address sustainable development of
         the electricity sector.

         a. Government agencies want views and opinions of energy market /
         industry stakeholders to be expressed and presented with concrete
         evidence-based facts and case studies for proposals for making
         changes, taking action etc. It is evident that the existing processes
         used to collect this information are not achieving the desired results to
         address present Government needs.

         b. Proper discussion and consideration of individual submissions from
         members of the public and industrial organizations is not possible
         because Government agencies do not have the expertise or the
         resources to properly consider and assess all the options put forward.

         c. Submissions are not coordinated and expressed in such a way as to
         effectively address integrated industrial and public concerns of different
         electricity market shareholders: responses are fragmented and
         contradict one another – confusing the primary concerns and needs
         addressed from lesser secondary concerns and interests.

         d. Lack of coordination amongst various ministries and government
         agencies has made it difficult to move forward with a cohesive strategy
         for tackling current electricity market needs. There are no clearly
         defined boundaries or guidelines for linking the various responsibilities,
         interests and policy objectives of separate agencies and ministries into
         a unified cohesive framework or plan that links New Zealand’s
         sustainable economic growth and prosperity with its security of energy
         supply.

         e. Government needs policies that are: “long(-term), loud and legal”.




                                                                                Page 9 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Ref.     Key Conclusions


C6       Insufficient vision and uncoordinated focus, fragmented scientific
         and technological research, and inadequate human and financial
         resources are preventing significant economic benefits being
         derived from sustainable energy.

         a. “Think Global, Act Local”. New Zealand Inc. needs a clear vision:
         e.g. “New Zealand completely self-sustainable in energy resources by
         ____?”. If you provide a stable infrastructure environment that people
         are confident in remaining stable, reliable and dependable for a long
         period of time, with long-term hedge-type products with reliable
         investment and pricing indicators that people can start banking against,
         then the other stuff will follow. E.g. the Orion Networks pricing model
         for investing in distributed generation. The same thing is observed with
         transport infrastructure investments. We must have a stable long-term
         focus.

         b. Universities, Crown Research Institutes and other academic
         institutions need to work much more closely with industry to facilitate
         more effective commercialization of research, and ensure research
         funding / investments are relevant to developing and improving the
         industrial capabilities required to realize the market benefits possible.

         c. The group of shareholders using and benefiting from distributed and
         other sustainable energy resources do not necessarily represent the
         same group of investors needed to facilitate their adoption. This
         problem can be resolved if the distribution networks are given /
         possess the technical capability, the financial capacity, the cooperation
         and support of the public at large and local communities (beneficiaries
         / recipients of the services provided), and most importantly of all: the
         will and clout of the political establishment to support: business
         investment, R&D funding, long-term incentives, efficient and effective
         rules and regulations etc. to make it all work.

         d. In order to work out these issues, a research institute that addresses
         the technological, political, commercial and legal issues should be set
         up to facilitate and coordinate the reliable and useful adoption of
         sustainable distributed energy resources through the lines companies,
         and plot the smooth transition of New Zealand’s energy industry
         towards delivering a long-term sustainable, secure and competitively
         priced energy infrastructure that meets the needs of New Zealand Inc.
         for generations to come.




                                                                               Page 10 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Ref.     Key Conclusions


C7       Government needs to establish a Leadership Task Force of
         people who know how the whole electricity system works and
         how to effectively incorporate distributed energy resources for
         optimum operating efficiency, reliability and security of supply.

          a. Government policymaking for the electricity industry is a rudderless
         affair. There are too many disparate parties attempting to steer
         electricity policy in different directions. Lack of coordination is
         responsible for much confusion.

         b. There is significant overlap and hence confusion regarding the roles
         of different yet similar political / governmental agencies competing for
         influence and resources.

         c. Government and industry must take a more hands-on approach
         towards maintaining and developing New Zealand’s energy
         infrastructure and untapped energy resources – including new /
         improved load management strategies, smart metering and distributed
         renewable energy resources.

         d. Government and industry must take a more hands-on approach
         towards improving the reliability and security of delivering New
         Zealand’s energy requirements today and for future generations.

         e. Greater integration and proactive coordination of industrial and
         economic development policy with energy security policy and
         environmental protection policy required.




                                                                               Page 11 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




3. Action Points Raised
From the key conclusions (C1 to C7) and issues raised / specific needs
identified by participants, a list of action points are proposed. A1 to A4 are
derived from C1 to C7 and A5 to A6 have been drawn from the workshop
proceedings.

                                                                            Proposed
Ref. Issues                              Action Points
                                                                            Participation

A1      Support long-term                • Long-term contracts for          Energy
        planning.                        energy supply and demand           Minister;
                                         required.                          Electricity
        a. Long-term needs not                                              Commission;
        addressed by short-term          • Pricing arrangements             MED;
        political agendas. (C1)          should deliver long-term           Commerce
                                         contractual arrangements           Commission;
                                         that help new investors get        Energy Users;
                                         established and give               Generators;
                                         consumers who put a                Retailers;
                                         premium on security,               T&D
                                         contractual certainty.             Networks.


A2      Constructive stakeholder         • Views and opinions of            Energy
        cooperation.                     energy market / industry           Minister;
                                         stakeholders need to be            Electricity
                                         documented and presented to
        a. Untapped potential for                                           Commission;
                                         the MED, Electricity
        sustainable development          Commission, Commerce               MED; MfE;
        due to fragmented markets.       Commission and other               NZTE;
        (C2)                             Government ministries and          Climate
                                         agencies.                          Change
        b. Many opportunities                                               Office;
        missed or lost due to lack of    • Responses to Government          Office of the
        coordinated planning             Requests for Information           Parliamentary
        between Government and           (RFIs) should provide              Commissioner
        industry stakeholders. (C3)      concrete, evidence-based           for the
                                         information; and, specific
                                                                            Environment;
                                         proposals for making
        c. Short-term micro-             changes, taking action etc.        Commerce
        management drives                should be given where              Commission;
        decision-making process          possible.                          Energy Users;
        because of distrust between                                         Generators;
        Government and industry.         • Government needs to be           Retailers;
        (C4)                             informed by stakeholders           T&D
                                         about problems associated          Networks.
                                         with regulations and policies
                                         affecting the operation,
                                         efficiency and effectiveness of
                                         the electricity and energy
                                         markets.




                                                                               Page 12 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                            Proposed
Ref. Issues                             Action Points
                                                                            Participation


A3      Effective decision-             • Chains of command,                Energy
        making framework.               accountability and                  Minister;
                                        communication need to be            Electricity
        a. Current decision-making      improved within and amongst
                                                                            Commission;
        framework is inadequate         Government structures.
                                                                            MED;
        for developing a                                                    Commerce
                                        • A more robust, transparent
        consensus amongst               and technically-qualified           Commission;
        Government and industry         decision making process is          Energy Users;
        stakeholders to take            necessary.                          Generators;
        appropriate action to                                               Retailers;
        address sustainable             • Industrial stakeholders must      T&D
        development of the              be engaged collectively by          Networks.
        electricity sector. (C5)        Government in such a way that
                                        interaction amongst different
        b. Government needs to          organizations is supported and
        establish a Leadership          enhanced to achieve better
                                        results.
        Task Force of people who
        know how the whole              • Acquire timely information,
        electricity system works        and the management of that
        and how to effectively          information, with appropriate
        incorporate distributed         smart metering technology.
        energy resources for
        optimum operating               • Adopt Area and Time Specific
        efficiency, reliability and     Marginal Capacity [ATSMC]
        security of supply. (C7)        cost programmes.



A4      Concentrate resources to • Restructure R&D investment               Energy
        achieve a specific       so that it supports NZ Inc., and           Minister;
        outcome.                 a common long-term vision for              Electricity
                                        New Zealand’s sustainable           Commission;
        a. Insufficient vision and      economic growth and
                                                                            MED; MfE;
                                        prosperity.
        uncoordinated focus,                                                NZTE; R&D
        fragmented scientific and       • Create a guiding industrial-      organizations;
        technological research,         Governmental coalition with         Academia;
        and inadequate human            the resources needed to             Climate
        and financial resources are     achieve the vision developed.       Change
        preventing significant                                              Office;
        economic benefits being         • Empower broad-based action,       Parliamentary
        derived from sustainable        by getting rid of the obstacles     Commissioner
        energy. (C6)                    and structures that undermine       for Environ.;
                                        the vision created.
                                                                            Local govt.;
                                        • Encourage risk taking and         Chambers of
                                        innovation by visibly               Commerce;
                                        recognizing and rewarding the       Commerce
                                        organizations that make a           Commission;
                                        difference towards progressing      Energy Users;
                                        the vision’s outcomes for New       Generators;
                                        Zealand.                            Retailers;
                                                                            T&D Networks



                                                                               Page 13 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                            Proposed
Ref. Issues                             Action Points
                                                                            Participation

A5      Encourage greater               • Support the development           Energy
        diversity of supply and         of distributed energy               minister;
        demand to reduce risks.         resource portfolio business         Banks and
                                        investment tools and                other lending
        a. A well-structured,           models.                             institutions;
        diverse portfolio of                                                Business
        distributed energy (supply-     • Encourage banks and               investors and
        & demand-side) resources,       other lending institutions to       owners;
        that can balance                provide the equivalent of           R&D orgs.;
        fluctuating loads with          revolving home loan                 MfE; Climate
        fluctuating weather             accounts for distributed            Change
        patterns, is needed for         energy resource project             Office;
        long-term investment.           finance.                            Electricity
                                                                            Commission;
                                        • Support collaboration             MED; NZTE;
                                        between business / project          Generators;
                                        investors and load /                Retailers;
                                        renewable energy                    T&D
                                        forecasters to develop              Networks.
                                        acceptable & reliable
                                        financial risk management
                                        metrics.

                                        • Ensure coordination of
                                        energy investment signals
                                        with energy and capacity
                                        pricing signals, and energy
                                        and capacity usage.


A6      Ensure multi-stakeholder        • Government intervention is        Energy
        benefits derived from           required to reconcile               Minister;
        new energy investments          benefits derived from               Electricity
        cover their costs.              investing in energy supply-         Commission;
                                        and demand-side products,           MED; Project
        a. Economic and other           processes and services,             Investors;
        benefits derived from           with the costs borne by             Commerce
        investing in distributed        project investors. This             Commission;
        generation and demand           means energy and capacity           Energy Users;
        side management are not         benefits obtained by energy         Generators;
        readily realized by the         wholesalers, retailers, T&D         Retailers;
        project sponsor or system       networks, insurance firms           T&D
        operator.                       etc., recompense part of the        Networks.
                                        investor’s project capital
                                        and operating expenditure,
                                        as applicable, by law.




                                                                               Page 14 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




4. Workshop Summary

                                                                                                                       ISSUES          SPECIFIC
PRESENTER                                                 MAIN POINTS
                                                                                                                       RAISED           NEEDS


                   • Historically, the ‘Planning Division’ definition of ‘reliability’: enough plant and fuel        • Long-term      • Can the
                   available to meet 7% more than normal load in a winter where lake inflows had been                contracts for    industry
                   85% of the mean.                                                                                  energy supply    provide the
                                                                                                                     required.        reliability NZ
                   • Historically the ‘Electricity Division’ definition of ‘reliability’: based around maintaining                    needs?
                   frequency and voltage through a centrally coordinated generation and transmission                 • Pricing
Alan Jenkins       system operated to defined engineering standards.                                                 arrangements     • Who pays for
                                                                                                                     should give      R&D?
(Electricity       • The new market structure has created the view: ‘the market will provide’, overlooking           local
Networks           the need to plan ahead. Consequently, focus is on creating an environment for                     generation as    • Can CPI-X
Association)       competition to flourish, not on delivering reliability.                                           well as more     deliver an
                                                                                                                     remote           economically
Presentation:      • In the interests of creating a flat commercial playing field, NZ has tended to have a           generation       sustainable
                   transmission-centric system.                                                                      options a        network
What is Reliable                                                                                                     reasonable       infrastructure
Firm Power         • Transmission nodal pricing is one manifestation of possessing a transmission-centric            chance of        for NZ’s future
Capacity? Why      system.                                                                                           succeeding.      energy delivery
Do We Need it?                                                                                                                        reliability
                   • People don’t like building power stations near a local node, because even a relatively          • Pricing        requirements?
                   small volume of new generation there will mean that the price of power from remote                arrangements
                   competing stations plummets. The net result: no significant investment, either in plant or        should keep
                   long-term contracts.                                                                              old, back-up
                                                                                                                     power stations
                   • NZ’s deregulated electricity market is operationally-focused on generation and nodally-         in reserve for
                   driven by trans-mission.                                                                          when things go
                                                                                                                     wrong, or
                   • It is not clear how much customers are willing to pay for reliability, and who should pay       demand gets




                                                                                                                                                       Page 15 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




for what within the mix of customers.                                                        ahead of
                                                                                             supply.
• Between 1992 and 1998, network companies were very focused on supply security,
and providing two-thirds of the new capacity being built at that time. The state was no      • Pricing
longer carrying the responsibility for building power stations, and new stations were        arrangements
actually being built close to loads.                                                         should ensure
                                                                                             that the parties
• The Bradford reforms of 1998 brought an end to this era, heavily influenced by a belief    selling
that the networks’ involvement in generation was occurring because local monopolies          electricity are
were imprudently building generation capacity that the country didn’t need – leaving         selling a
local consumers to carry the cost through inflated lines charges.                            package that
                                                                                             includes
•The Bradford Electricity Reform Act of 1998 was driven by the belief that it would          defined,
‘ensure that costs and prices in the electricity industry are subjected to sustained         minimum
downward pressure”.                                                                          reliability levels.

• Since 1998: distribution and transmission prices have decreased by: 10%.                   • Pricing
                                                                                             arrangements
• Since 1998: energy wholesale prices have increased by: 45%.                                should give the
                                                                                             parties who are
• Since 1998: total energy retail prices have increased by: 18%.                             best equipped
                                                                                             to put
• As a result of the 1998 reforms: there is a ban on networks trading in energy hedges.      commercial
                                                                                             pressure on
• As a result of the 1998 reforms: there is a ban on exercising any sort of influence over   transporters
a generation subsidiary, which must be managed through its own officers, with its own        responsibility
board.                                                                                       for paying
                                                                                             transmission
• The Electricity Commission was established to address problems of:                         and
    - security of supply;                                                                    distribution.
    - transmission losses;
    - grid capacity constraints;                                                             • Pricing
    - no liquidity or transparency in forward wholesale electricity prices; and,             arrangements
    - limited competition emerging / occurring in generation and retail.                     should
                                                                                             incentivise
• If network companies were investing in generation it would help Government and the         consumers to




                                                                                                                   Page 16 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Electricity Commission achieve their objectives.                                               make a
                                                                                               contribution to
• After the 1992 crisis, electricity system operations were working around a hydro             reliability.
‘minizone’ (storage availability) to decide when, and if, back-up capacity is needed. Do
we need to revert to these centrally imposed security arrangements?                            • Pricing
                                                                                               arrangements
• There are not effective contingency plans in place to keep old, back-up plant available,     should deliver
as a consequence of constructing the electricity market in the mid-1990s around spot           long-term
nodal prices without any imposed longer term pricing arrangements such as loss of load         contractual
probability payments.                                                                          arrangements
                                                                                               that help new
• Existing network-level regulatory signals are very poor at dealing with supply reliability   investors get
problems. The Commerce Commission’s price control formula linking volumes                      established and
distributed and allowed income deters: a. energy conservation and b. uptake of                 give consumers
distributed generation options that take load off parts of their systems (source of            who put a
revenue).                                                                                      premium on
                                                                                               security
• Bad signals from the regulatory regime also disincentivise spending on research and          contractual
development. The CPI-X thresholds only allow R&D expenditure to come out of profits            certainty.
and under no circumstances be passed through to consumers.

• The annual minus-X adjustment erodes network profits and gives them the same
immediate, operational focus that dogs the wholesale electricity market.

• Does New Zealand need a major power crisis resulting in a substantial economic
recession to get reliability back firmly on the policy agenda?




                                                                                                                 Page 17 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                                 ISSUES           SPECIFIC
PRESENTER                                              MAIN POINTS
                                                                                                                 RAISED            NEEDS


                 • For Lines Companies to comply with Part 4a of the Commerce Act defining thresholds                            • If a subjective
                 for declaration of control of lines businesses: they must demonstrate no material                               process is used
                 deterioration in reliability                                                                                    to define an
                                                                                                                                 “extreme
                 • SAIDI/SAIFI thresholds screening mechanism – are used to identify breaches that may                           event”, why use
                 warrant further investigation.                                                                                  an objective
                                                                                                                                 mathematical
                 • Businesses may avoid post-breach inquiry if they demonstrate: Breach due to an                                process to
                 extreme event.                                                                                                  analyze it?
                                                                                                               • Views and
                 • What is an extreme event? Definition from the Assessment and Inquiry Guidelines:            opinions of       • The existing
Rodney Doyle
                 “Where one or a small number of rare but high impact events has a significant and             energy market /   process
                 material impact on a business’ reliability performance”.                                      industry          proposed for
(Commerce
                                                                                                               stakeholders to   handling
Commission)
                 • Difficult to use meteorological definitions of extreme events. Extreme weather limits are   be expressed      extreme events
                 location specific, open to argument, and Extreme events may not be meteorological.            and presented     cannot make
Presentation:
                                                                                                               to the            decisions fast
                 • Extreme events are self-defining. Key requirements for defining a measure                   Commerce          enough to
Extreme Events
                 to identify extreme events:                                                                   Commission.       address the
                                                                                                                                 needs raised.
                 Consistency – Applicable to all networks large or small, urban or rural.
                                                                                                                                 • Priority is to
                 Efficiency – Clear classification of normal and extreme data.                                                   encourage best
                                                                                                                                 practice in
                 Practicality – Should facilitate metric setting.                                                                outage
                                                                                                                                 mitigation,
                 Suitability – Should use readily available data.                                                                supply
                                                                                                                                 restoration and
                 Simplicity – Easy to understand and apply.                                                                      network design.




                                                                                                                                                Page 18 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                        There-fore
• Steps to identifying an extreme event:                                                                proposal aimed
                                                                                                        at improving
    1. Collect up to five years of historical outage data                                               existing
                                                                                                        practices more
    2. Calculate natural log of daily SAIDI figures.                                                    than providing
                                                                                                        an effective
    3. Calculate alpha (α) (mean of the log values).                                                    method for
                                                                                                        dealing with
    4. Calculate beta (β) (standard deviation of the log values).                                       real-time
                                                                                                        operational
    5. Formula for an extreme event day boundary:                                                       requirements.
                                                                                                        Focus is on
        e(α + 2.5 β).                                                                                   reducing
                                                                                                        problems and /
• If an extreme event is identified:                                                                    or improving
                                                                                                        responsiveness
        Exclude data for extreme event days from SAIDI records.                                         to current
                                                                                                        problems.
        Calculate average daily SAIDI of residual (last 5 years).
                                                                                                        • Extreme
        Substitute extreme event days SAIDI figures with average.                                       weather events
                                                                                                        are very difficult
        Calculate new annual SAIDI figure.                                                              to anticipate
                                                                                                        from historical
        Test if threshold is exceeded.                                                                  data, weather
                                                                                                        patterns and
        Decide on action.                                                                               the shear
                                                                                                        complexity of
• Need consistent reporting practices from lines businesses; Standardised reporting                     the statistical
information for those in breach; Issues in reporting of “Step” restoration type                         models (and
interruptions;                                                                                          hence their
Appropriate allocation of outage cause; Evidence of extreme events to be notified to                    reliability)
Commission a.s.a.p. to facilitate investigation and decision.                                           involved.

• The Commerce Commission recognise the geographic diversity;                                           • Conclusion:




                                                                                                                        Page 19 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




Distribution businesses should still identify best practice: outage mitigation,                        industry is very
supply restoration procedures, and network design; Aim of improving overall service                    nervous and
reliability.                                                                                           wants to be
                                                                                                       heard over the
                                                                                                       Commerce
                                                                                                       Commission’s
                                                                                                       proposed
                                                                                                       thresholds
                                                                                                       regime.




                                                                                                                     Page 20 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                               ISSUES       SPECIFIC
PRESENTER                                               MAIN POINTS
                                                                                                               RAISED        NEEDS


                    • Electricity Commission (EC) responsible primarily for:                                               • Wide range of
                                                                                                                           possible
                        -   overseeing electricity industry and markets.                                                   options and
                        -   ensuring dry-year reserve.                                                                     alternatives to
                        -   Conducting electricity efficiency programmes; and                                              transmission
                        -   regulating Transpower.                                                                         upgrade in the
                                                                                                                           Akld region
                    • Transpower proposes Grid Upgrade Plans (GUPs) to EC. Focus: 400kV Whakamaru-                         have been
                    Otahuhu transmission upgrade.                                                                          considered.
Robert Reilly
                                                                                                                           Options
(on behalf of Roy
                    • EC involved because:                                                                                 favoured
Hemmingway)
                                                                                                                           include:
                        -   Load in Auckland is growing.                                                                   building surplus
(Electricity
                        -   A solution needed to meet demand at peak times by about 2010.                                  capacity into
Commission)
                        -   Transpower requires EC approval to be able to pass costs of investment on to                   existing
                            its customers.                                                                                 proposed
Presentation:
                        -   EC must decide if Transpower’s proposal is best solution. Assessment includes                  solutions to
                            application of GIT.                                                                            address future
Alternatives to
                        -   EC must ensure other options have been analysed, including generation and                      needs and
Transmission
                            demand-side alternatives.                                                                      reduce overall
                                                                                                                           costs, and
                    • Generation options considered:                                                                       incorporate
                                                                                                                           small
                        -   G1: Baseload co-generation (84MW co-generation at Marsden by 2010.)                            intermediate
                        -   G2: Baseload coal generation (320MW coal generation at Marsden by 2010 and                     investments to
                            320MW additional coal generation at Marsden by 2016.)                                          buy time (defer
                        -   G3: Baseload gas generation (385MW CCGT at either Rodney or Otahuhu by                         investments)
                            2010 and 2 x 200MW gas generators in Auckland by 2010, and 400MW CCGT
                            at either Otahuhu or Rodney by 2015, and 400MW CCGT in South Auckland by




                                                                                                                                         Page 21 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




        2025.)
    -   G4: Wind generation (75-150MW of wind generation in Auckland region by
        2015.)
    -   G5: Relocation of Whirinaki (155MW Whirinaki re-located to Auckland by 2010.)
    -   G6: Peaking plant (Peaking diesel generation in Auckland by 2010.)
    -   G7: Alternative technologies (200-250MW of emerging generation technologies
        from 2015.)

• Demand-side alternatives considered:

    -   D1: Interruptible load (IL) (Up to 200MW of IL by 2010.)
    -   D2: Distribution Network Load Management (DNLM) (130-245MW DNLM by
        2015 and 15MW ripple control replacement by 2010.)
    -   D3: Energy substitution (70MW gas substitution in Auckland by 2015 and 1-
        22MW solar water heating from 2015.)
    -   D4: Energy efficiency measures (Range of measures including 25MW
        residential lighting by 2010, 17-63MW residential heating by 2015, and 25MW
        commercial measures by 2015.)

• Transmission alternatives:

    -   T1: duplex the WKM-OTA 220kV A and B lines, then install 400kV between
        WKM and OTA in 2021.
    -   T2: install 220kV between WKM and OTA in 2017.
    -   T3: install HVDC between WKM and OTA in 2017.
    -   T4: install 400kV between WKM and OTA in 2017.

• Next steps:

    -   Assessment of ‘short short-list’ of alternatives (generation, demand-side, and
        transmission) by applying GIT (now underway).
    -   Comparison of short-listed alternatives and Transpower’s proposal (Jan 2006)
    -   Draft decision on Transpower’s proposed 400kV project (Feb/Mar 06)
    -   Consultation (Mar/Apr/May 06).
    -   Final decision (Jun 06).




                                                                                                        Page 22 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                               ISSUES           SPECIFIC
PRESENTER                                            MAIN POINTS
                                                                                                               RAISED            NEEDS


                • Lines companies can own: Non renewable generation up to 50 MW or 20% of lines                                • Advanced
                capacity.                                                                                                      metering
                                                                                                                               provides value
                • Lines companies can own: Unlimited new renewable generation (e.g. wind).                                     for managing
                                                                                                                               existing and
                • Lines companies can own: Reserve generation contracted to Electricity Commission.                            new energy
                                                                                                                               options more
                • Capacity above 5MW or 2% is subject to arms length restrictions.                                             effectively –
                                                                                                             Submissions
                                                                                                                               who is
Gareth Wilson                                                                                                should provide
                • Lines companies also prevented from trading in electricity generally and buying and                          investigating
                                                                                                             concrete,
                selling hedges.                                                                                                these
(MED)                                                                                                        evidence-
                                                                                                                               opportunities?
                                                                                                             based
                • Exemptions from some or all of the restrictions may be granted on a case by case                             Where is the
Presentation:                                                                                                information;
                basis.                                                                                                         funding to
                                                                                                             and, specific
                                                                                                                               research how
Facilitating                                                                                                 proposals for
                • Restrictions in place to minimise the opportunity and incentive for lines businesses to:                     new
Investment in                                                                                                making
                inhibit competition; and/or                                                                                    technologies
Generation by                                                                                                changes, taking
                cross-subsidise generation and retail activities.                                                              can improve
Lines                                                                                                        action etc.
                                                                                                                               the operation of
Companies                                                                                                    should be given
                • Should arms length rules be relaxed?                                                                         the electricity
                                                                                                             where possible.
                                                                                                                               market?
                    -   Should the capacity threshold be raised?
                    -   What rules should apply to generation connected to another line owner’s                                • No research
                        network?                                                                                               has been done
                                                                                                                               on whether the
                • Should the legislation explicitly set out criteria for exemptions?                                           market
                                                                                                                               structure we
                • Should lines companies be able to trade in hedges? If so, to what level?                                     now have is
                                                                                                                               appropriate.




                                                                                                                                             Page 23 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




• How could legislative uncertainty be reduced?
                                                                                                       • It is not clear
• Discussion paper to be released March 2006 for comment from relevant stakeholders.                   how the various
                                                                                                       government
                                                                                                       departments
                                                                                                       and agencies
                                                                                                       are
                                                                                                       coordinating
                                                                                                       their activities,
                                                                                                       let alone
                                                                                                       cooperating to
                                                                                                       achieve an
                                                                                                       integrated
                                                                                                       cohesive
                                                                                                       electricity
                                                                                                       market
                                                                                                       development
                                                                                                       and
                                                                                                       management
                                                                                                       strategy.




                                                                                                                      Page 24 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                                  ISSUES            SPECIFIC
PRESENTER                                              MAIN POINTS
                                                                                                                  RAISED             NEEDS


                  • The EC is responsible for: ensuring that electricity is produced and delivered to all                          • Small scale
                  classes of consumers in an efficient, fair, reliable, and environmentally sustainable                            generation only
                  manner; and, promoting and facilitating efficient use of electricity.                                            gets value for
                                                                                                                                   capacity from
                  • Key outcomes:                                                                                                  separate
                                                                                                                                   agreements
                      -   Investment in (distributed) generation, transmission, energy efficiency and                              with distribution
Robert Reilly             demand-side management.                                                                                  networks –
                                                                                                                • Electricity      retailers do not
(Electricity                                                                                                    Commission         value capacity
                      -   Remove barriers to distributed generation.
Commission)                                                                                                     wishes to be       delivered.
                                                                                                                informed about
                      -   Access to lines for distributed generation.
Presentation:                                                                                                   problems           • The cost of
                                                                                                                associated with    installing export
                      -   Arrangements for the sale of surplus small scale generation.
The Electricity                                                                                                 the model          meters could
Commission’s                                                                                                    arrangements       be a barrier to
Role and              -   Switching and reconciliation of small scale distributed generation.                   for the sale and   DG uptake.
Distributed                                                                                                     purchase of
Generation        • The Government proposes to introduce regulations prescribing reasonable terms and           surplus
                  conditions on which line owners and electricity distributors must enable generators to be                        • Separate
                                                                                                                electricity.       agreements are
                  connected to distribution lines.
                                                                                                                                   needed with
                  • The objective is to facilitate the use of distributed generation by ensuring that it does                      the retailer and
                  not face undue barriers in connecting to lines.                                                                  the distributor
                                                                                                                                   to gain full
                                                                                                                                   value from
                  • The Electricity Commission will have responsibility for administering the regulations
                                                                                                                                   operating DG.
                  and for proposing amendments as required.

                  • The Electricity Act 1992 provides powers to regulate terms and conditions for the




                                                                                                                                                  Page 25 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




purchase by retailers of small surpluses of electricity from generating units owned or
operated by consumers.

• It can be difficult for owners of distributed generation units to negotiate terms and
conditions with local retailers to purchase small surpluses of electricity generation.

• The Government would like to see this barrier to the development and uptake of
distributed generation reduced by setting appropriate terms and conditions for purchase
of small electricity surpluses by local retailers.

• The Government envisages that this policy should apply to consumers with generation
units capable of generating up to 40,000kWh over a year.

• A key principle however is that retailers should not incur ongoing financial losses by
the requirement to purchase such electricity.

• The Commission should seek to develop non-regulatory arrangements to achieve
these objectives, but should recommend regulations or rules if voluntary arrangements
are unsuccessful in achieving the policy outcomes the Government seeks.

• The Commission has a role in facilitating Distributed Generation.

• Model Retail contracts have provision for the sale and purchase of surplus electricity
from small scale generation.

• Existing rules do not prevent retailers from trading small scale generation.

• Proposed rules will facilitate trading and switching of the output from small scale
generation.




                                                                                                        Page 26 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                                   ISSUES          SPECIFIC
PRESENTER                                               MAIN POINTS
                                                                                                                   RAISED           NEEDS


                   • Load management is useful when aggregated – due to scale and diversity.                                      • Purchase of
                                                                                                                                  cheap
                   • Demand-side is the ability for customers to effect an outcome on the electricity system                      controllable
                   / market.                                                                                                      load (from
                                                                                                                                  customers) is a
                   • Load management involves an agreement with a customer to turn off a nominated                                big opportunity
                   appliance or replace dependence on the network for an agreed duration.                                         for lines
                                                                                                                                  companies to
                   • There are a variety of historical technologies in place. Future ability and scope is                         increase
Duncan Head        growing with convergence of communications and energy infrastructures.                                         network asset
                                                                                                                                  management
(Vector Networks   • Demand-side participation is not a “public good”, and it depends on the consumer’s          • Coordination   efficiency and
Ltd.)              choice between price and quality. It is left to value-seekers to incentivise uptake.          of energy        economic value
                                                                                                                 investment       – but load
Presentation:      • Demand-side has many valuing-adding applications:                                           signals with     management
                                                                                                                 energy usage     solutions must
Mass Market            -   Transmission: congestion relief, alternatives, emergency management.                  required.        provide value
Load Control           -   Distribution: capital deferment, asset utilization.                                                    to all
Issues                 -   Customer: transmission pricing, load management (under time of use pricing).                           stakeholders in
                       -   Retail/Generation: energy hedging, portfolio & risk management.                                        the value chain.
                       -   Other: energy hedging, spot market influence, compliance management,
                           ancillary energy market services (e.g. voltage, under frequency).                                      • Issues for
                                                                                                                                  effective load
                   • It is doubtful whether any real long-term benefit is provided by the Transmission Pricing                    management
                   Methodology (‘TPM’).                                                                                           include: gaining
                                                                                                                                  benefit from the
                   • Controlling to TPM targets can bring forward investment in distribution network without                      transmission
                   minimizing Transmission build.                                                                                 pricing
                                                                                                                                  methodology




                                                                                                                                                Page 27 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




• Ability to reconcile actual benefits to third parties limiting demand-side application to             including
non-distribution users.                                                                                 reconciling
                                                                                                        peak load
• Alignment of basic building blocks will enable value of demand-side to be realized.                   reductions with
                                                                                                        GXP price
• Load management needs to create value for those involved.                                             reductions
                                                                                                        (current
• An integrated system is required to gain network benefits from load management.                       difficult).

• Specific outcomes for network distribution load management are: network                               • An integrated
management, asset deferral, and satisfactory customer price-quality trade offs.                         system is
                                                                                                        required to gain
• Focus on reducing numbers of customers on traditional controlled appliances through                   network
fuel substitution and personal choice.                                                                  benefits using
                                                                                                        SCADA
• Technology will change the current network load management paradigm.                                  technology.

• Vector Networks is currently embarking on a significant rethink of load management.                   • Vector is
                                                                                                        looking to
• Vector Networks is looking to review incentives for customers to participate in demand-               review
side management, and how they participate.                                                              incentives for
                                                                                                        customers to
• Vector Networks is looking at reducing free riders, so that demand-side benefits go                   participate in
where they are created.                                                                                 load
                                                                                                        management
• It is essential to be able to recognize value (created by demand-side participation etc.)             options.
and to be able to pass it on.
                                                                                                        • Load
• Change in technology creates opportunities to establish next generation demand-side                   management
systems and strategies, so that ripple plant’s days and historical ownership structures                 needs to create
may be numbered.                                                                                        more value for
                                                                                                        those involved.

                                                                                                        • Ripple-relay
                                                                                                        control systems
                                                                                                        act like a




                                                                                                                         Page 28 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                        ‘sledge
                                                                                        hammer’ – no
                                                                                        longer
                                                                                        appropriate for
                                                                                        managing
                                                                                        loads
                                                                                        effectively.

                                                                                        • Transmission
                                                                                        pricing does
                                                                                        not reflect
                                                                                        system peaks.




                                                                                                      Page 29 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                                  ISSUES           SPECIFIC
PRESENTER                                              MAIN POINTS
                                                                                                                  RAISED            NEEDS


                  • Technical issues associated with installing network-embedded DG include: Connection
                  Arrangements; Protection;
                  Over and Under-voltages;
                  Stability; Auto Re-closing;
                                                                                                                                  • The option of
                  Ferro-resonance; Metering; Islanding; Current Flows; Power factor; Under Frequency
                                                                                                                                  separating
                  Protection; Harmonics.
                                                                                                                                  electricity
Brent Noriss
                                                                                                                                  generators and
                  • Commercial issues associated with installing network-embedded DG include:                   • Market rules
                                                                                                                                  retailers in the
(The Lines        Recovery of Costs including Engineering; Transpower Avoidance Calculations; Loss              required to
                                                                                                                                  NZ electricity
Company)          Factor Calculations; Power factor;                                                            support the
                                                                                                                                  market might
                  Dedicated Assets; Connection Contracts.                                                       complexity
                                                                                                                                  make it harder
Presentation:                                                                                                   associated with
                                                                                                                                  to address the
                  • Industry issues associated with installing network-embedded DG include: Electricity         connecting
                                                                                                                                  technical
The               Market ability to handle complex Distributed Generation Situations; Innovative Network        distributed
                                                                                                                                  issues
Experiences of    Solutions; and, Plant Reliability.                                                            generation to
                                                                                                                                  associated with
a Network                                                                                                       networks in
                                                                                                                                  installing and
Engineer in The   • DG is exciting but involves a lot more engineering than most people realize.                reality.
                                                                                                                                  operating
King Country
                                                                                                                                  network-
                  • There is significant difficulty in getting the various stakeholders to understand the
                                                                                                                                  embedded
                  issues (let alone work together to address them!)
                                                                                                                                  generation.
                  • It is not clear who is going to pay for what with DG installations and operations, let
                  alone ensure that sufficient benefit is concentrated in few enough hands to justify project
                  commencement.




                                                                                                                                                Page 30 of 67
Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington)




                                                                                                               ISSUES        SPECIFIC
PRESENTER                                           MAIN POINTS
                                                                                                               RAISED         NEEDS


                • Eastland Networks Limited (ENL) has commercial and operational motivations for                            • Transpower’s
                investigating DG.                                                                                           plans to
                                                                                                                            upgrade
                • ENL network characteristics include: low consumer density, low average consumer                           existing circuits
                consumption, fed by a long radial transmission line with high nodal energy prices.                          is limited
                                                                                                                            considering
                • Capacity is a key issue with 47MW uncontrolled and 39MW+ controlled. There is a                           forestry trends
                single line, double circuit 110kV line, running through rugged erosion prone back-                          and the growth
                country.                                                                                                    in regional
Matt Todd
                                                                                                                            processing and
                                                                                                             • A well-
                • The transmission assets are becoming n-1 constrained.                                                     log exports.
(Eastland                                                                                                    structured,
Networks)                                                                                                    diverse
                • 38MW per circuit during the summer.                                                                       • ENL needs
                                                                                                             portfolio of
                                                                                                                            non-
Presentation:                                                                                                distributed
                • Peak consumption could grow to 80MW by 2011.                                                              transmission
                                                                                                             generation
                                                                                                                            solutions that
Maximising                                                                                                   required to
                • Price is a key issue affecting the network: large customers have been paying 4 to 7                       will address
Value from                                                                                                   make it (DG)
                c/kWh, new contracts (3 years) are being offered at 10 c/kWh.                                               energy delivery
Distributed                                                                                                  work.
                                                                                                                            prices and
Generation
                • For forestry processing energy is a top 3 input cost.                                                     capacity
                                                                                                                            constraints.
                • Investors in the region planning new developments need certainty around energy:
                price, supply (capacity) and contract terms (of supply / price).                                            • The current
                                                                                                                            electricity
                • Typical problem / challenge involves: investing in a forestry processing plant with a 25                  regulatory
                year $100m investment to make, where energy is one of its top 3 input costs, and                            environment
                energy has risen 30% over the last 3 years, with a maximum forward (hedge) term of 3                        does not
                to 5 years.                                                                                                 provide
                                                                                                                            incentives for




                                                                                                                                             Page 31 of 67
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy
Network Reliability and Firm Power Capacity with Distributed Energy

Mais conteúdo relacionado

Destaque

SP3 찬송가 옵션 작업후기 (Logic Audio)
SP3 찬송가 옵션 작업후기 (Logic Audio)SP3 찬송가 옵션 작업후기 (Logic Audio)
SP3 찬송가 옵션 작업후기 (Logic Audio)Yoon Lee
 
Design Thinking in EFL Context
Design Thinking in EFL ContextDesign Thinking in EFL Context
Design Thinking in EFL ContextDebopriyo Roy
 
The Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed GenerationThe Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed GenerationIain Sanders
 
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Oboni Riskope Associates Inc.
 
Web Configurator
Web ConfiguratorWeb Configurator
Web Configuratormikuzz
 
How to grow a business
How to grow a businessHow to grow a business
How to grow a businessJason Dunstone
 
Chi next gen-ntino-krampis
Chi next gen-ntino-krampisChi next gen-ntino-krampis
Chi next gen-ntino-krampisNtino Krampis
 
WFS AZ Future Scenarios on American Politics
WFS AZ Future Scenarios on American PoliticsWFS AZ Future Scenarios on American Politics
WFS AZ Future Scenarios on American PoliticsEric Kingsbury, MBA
 
VSTS El Hoy Y El MañAna
VSTS   El Hoy Y El MañAnaVSTS   El Hoy Y El MañAna
VSTS El Hoy Y El MañAnaGabriel Oliva
 
Proiect 1000 - Stefan Szakal
Proiect 1000 - Stefan SzakalProiect 1000 - Stefan Szakal
Proiect 1000 - Stefan SzakalGeekMeet
 
Certificación inversión o gasto
Certificación inversión o gastoCertificación inversión o gasto
Certificación inversión o gastoIvo Castillo
 
Lapcodex Aviones 1
Lapcodex Aviones 1Lapcodex Aviones 1
Lapcodex Aviones 1guest671e5e0
 
Fairgrounds Proposal
Fairgrounds ProposalFairgrounds Proposal
Fairgrounds Proposalguest12a2146
 
Eu Kyoto Prototcol Class Presentation Sumiko
Eu Kyoto Prototcol Class Presentation SumikoEu Kyoto Prototcol Class Presentation Sumiko
Eu Kyoto Prototcol Class Presentation SumikoKeith Dickson
 
IVI (Tom Nastas) Presentation At 3rd Moscow Venture Fair
IVI (Tom Nastas)  Presentation At 3rd  Moscow Venture FairIVI (Tom Nastas)  Presentation At 3rd  Moscow Venture Fair
IVI (Tom Nastas) Presentation At 3rd Moscow Venture FairThomas Nastas
 
(Online) Censorship in Southeast Asia | #rp15
(Online) Censorship in Southeast Asia | #rp15(Online) Censorship in Southeast Asia | #rp15
(Online) Censorship in Southeast Asia | #rp15Sascha Funk
 

Destaque (20)

SP3 찬송가 옵션 작업후기 (Logic Audio)
SP3 찬송가 옵션 작업후기 (Logic Audio)SP3 찬송가 옵션 작업후기 (Logic Audio)
SP3 찬송가 옵션 작업후기 (Logic Audio)
 
Email etiquette
Email etiquetteEmail etiquette
Email etiquette
 
Design Thinking in EFL Context
Design Thinking in EFL ContextDesign Thinking in EFL Context
Design Thinking in EFL Context
 
The Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed GenerationThe Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed Generation
 
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...Riskope 5 days course on Risk and Crisis Management for top managers and key ...
Riskope 5 days course on Risk and Crisis Management for top managers and key ...
 
Web Configurator
Web ConfiguratorWeb Configurator
Web Configurator
 
How to grow a business
How to grow a businessHow to grow a business
How to grow a business
 
Chi next gen-ntino-krampis
Chi next gen-ntino-krampisChi next gen-ntino-krampis
Chi next gen-ntino-krampis
 
Portfolio
PortfolioPortfolio
Portfolio
 
WFS AZ Future Scenarios on American Politics
WFS AZ Future Scenarios on American PoliticsWFS AZ Future Scenarios on American Politics
WFS AZ Future Scenarios on American Politics
 
Squizz presentation
Squizz presentationSquizz presentation
Squizz presentation
 
VSTS El Hoy Y El MañAna
VSTS   El Hoy Y El MañAnaVSTS   El Hoy Y El MañAna
VSTS El Hoy Y El MañAna
 
Proiect 1000 - Stefan Szakal
Proiect 1000 - Stefan SzakalProiect 1000 - Stefan Szakal
Proiect 1000 - Stefan Szakal
 
Certificación inversión o gasto
Certificación inversión o gastoCertificación inversión o gasto
Certificación inversión o gasto
 
Lapcodex Aviones 1
Lapcodex Aviones 1Lapcodex Aviones 1
Lapcodex Aviones 1
 
Fairgrounds Proposal
Fairgrounds ProposalFairgrounds Proposal
Fairgrounds Proposal
 
Eu Kyoto Prototcol Class Presentation Sumiko
Eu Kyoto Prototcol Class Presentation SumikoEu Kyoto Prototcol Class Presentation Sumiko
Eu Kyoto Prototcol Class Presentation Sumiko
 
IVI (Tom Nastas) Presentation At 3rd Moscow Venture Fair
IVI (Tom Nastas)  Presentation At 3rd  Moscow Venture FairIVI (Tom Nastas)  Presentation At 3rd  Moscow Venture Fair
IVI (Tom Nastas) Presentation At 3rd Moscow Venture Fair
 
(Online) Censorship in Southeast Asia | #rp15
(Online) Censorship in Southeast Asia | #rp15(Online) Censorship in Southeast Asia | #rp15
(Online) Censorship in Southeast Asia | #rp15
 
Lourenza
LourenzaLourenza
Lourenza
 

Semelhante a Network Reliability and Firm Power Capacity with Distributed Energy

White House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st CenturyWhite House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st CenturyUCSD-Strategic-Energy
 
The Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed GenerationThe Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed GenerationIain Sanders
 
Integrating renewables and grids
Integrating renewables and gridsIntegrating renewables and grids
Integrating renewables and gridsDanny De Schutter
 
DNV GL Scorecard_final version
DNV GL Scorecard_final versionDNV GL Scorecard_final version
DNV GL Scorecard_final versionSANJAY KUMAR
 
A Guide To Decs
A Guide To DecsA Guide To Decs
A Guide To Decscrenergy
 
Energy Efficiency Innovation Driver or heavy Burden?
Energy Efficiency Innovation Driver or heavy Burden?Energy Efficiency Innovation Driver or heavy Burden?
Energy Efficiency Innovation Driver or heavy Burden?Mateus Siwek
 
AR50358_BRISTOW_CAELAN_ED_DISSERTATION
AR50358_BRISTOW_CAELAN_ED_DISSERTATIONAR50358_BRISTOW_CAELAN_ED_DISSERTATION
AR50358_BRISTOW_CAELAN_ED_DISSERTATIONCaelan Bristow
 
Vacation Report 2015
Vacation Report 2015Vacation Report 2015
Vacation Report 2015Lee Clark
 
Ia demand side management
Ia demand side managementIa demand side management
Ia demand side managementRob Kool
 
"How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo...
"How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo..."How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo...
"How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo...Smart Grid Interoperability Panel
 
Americal connector company case study
Americal connector company case studyAmerical connector company case study
Americal connector company case studyShashikanthPatil1
 
wind power costing 27 nov 2012 at the Energy Talk, London
wind power costing 27 nov 2012 at the Energy Talk, Londonwind power costing 27 nov 2012 at the Energy Talk, London
wind power costing 27 nov 2012 at the Energy Talk, LondonMichael Taylor
 
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Energy Network marcus evans
 
Fellon-McCord: 2012 Webinar Library
Fellon-McCord: 2012 Webinar LibraryFellon-McCord: 2012 Webinar Library
Fellon-McCord: 2012 Webinar LibraryFellon-McCord
 
Advanced Manufacturing Research & Development at DOE h2atscale workshop_johnson
Advanced Manufacturing Research & Development at DOE  h2atscale workshop_johnsonAdvanced Manufacturing Research & Development at DOE  h2atscale workshop_johnson
Advanced Manufacturing Research & Development at DOE h2atscale workshop_johnsonSteve Wittrig
 
The Management of Critical Spares in the Electric & Gas Utility Industry
The Management of Critical Spares in the Electric & Gas Utility IndustryThe Management of Critical Spares in the Electric & Gas Utility Industry
The Management of Critical Spares in the Electric & Gas Utility IndustryScottMadden, Inc.
 
literature on bipv-added values
literature on bipv-added valuesliterature on bipv-added values
literature on bipv-added valuesA. H. Haris
 
Mannheim_Tongji_DefensePPT_WangWei0727
Mannheim_Tongji_DefensePPT_WangWei0727Mannheim_Tongji_DefensePPT_WangWei0727
Mannheim_Tongji_DefensePPT_WangWei0727e2004080
 

Semelhante a Network Reliability and Firm Power Capacity with Distributed Energy (20)

White House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st CenturyWhite House Smart Grid Strategy for 21st Century
White House Smart Grid Strategy for 21st Century
 
The Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed GenerationThe Economics of Grid-Connected Hybrid Distributed Generation
The Economics of Grid-Connected Hybrid Distributed Generation
 
Integrating renewables and grids
Integrating renewables and gridsIntegrating renewables and grids
Integrating renewables and grids
 
DNV GL Scorecard_final version
DNV GL Scorecard_final versionDNV GL Scorecard_final version
DNV GL Scorecard_final version
 
A Guide To Decs
A Guide To DecsA Guide To Decs
A Guide To Decs
 
Energy Efficiency Innovation Driver or heavy Burden?
Energy Efficiency Innovation Driver or heavy Burden?Energy Efficiency Innovation Driver or heavy Burden?
Energy Efficiency Innovation Driver or heavy Burden?
 
AR50358_BRISTOW_CAELAN_ED_DISSERTATION
AR50358_BRISTOW_CAELAN_ED_DISSERTATIONAR50358_BRISTOW_CAELAN_ED_DISSERTATION
AR50358_BRISTOW_CAELAN_ED_DISSERTATION
 
Vacation Report 2015
Vacation Report 2015Vacation Report 2015
Vacation Report 2015
 
Ia demand side management
Ia demand side managementIa demand side management
Ia demand side management
 
"How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo...
"How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo..."How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo...
"How Today's Power Grid Implementation Choices Impact Future Smart Grid Deplo...
 
Americal connector company case study
Americal connector company case studyAmerical connector company case study
Americal connector company case study
 
wind power costing 27 nov 2012 at the Energy Talk, London
wind power costing 27 nov 2012 at the Energy Talk, Londonwind power costing 27 nov 2012 at the Energy Talk, London
wind power costing 27 nov 2012 at the Energy Talk, London
 
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
 
Fellon-McCord: 2012 Webinar Library
Fellon-McCord: 2012 Webinar LibraryFellon-McCord: 2012 Webinar Library
Fellon-McCord: 2012 Webinar Library
 
Advanced Manufacturing Research & Development at DOE h2atscale workshop_johnson
Advanced Manufacturing Research & Development at DOE  h2atscale workshop_johnsonAdvanced Manufacturing Research & Development at DOE  h2atscale workshop_johnson
Advanced Manufacturing Research & Development at DOE h2atscale workshop_johnson
 
Bruce Thompson: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
Bruce Thompson: 2013 Sandia National Laboratoies Wind Plant Reliability WorkshopBruce Thompson: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
Bruce Thompson: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
 
The Management of Critical Spares in the Electric & Gas Utility Industry
The Management of Critical Spares in the Electric & Gas Utility IndustryThe Management of Critical Spares in the Electric & Gas Utility Industry
The Management of Critical Spares in the Electric & Gas Utility Industry
 
literature on bipv-added values
literature on bipv-added valuesliterature on bipv-added values
literature on bipv-added values
 
Mannheim_Tongji_DefensePPT_WangWei0727
Mannheim_Tongji_DefensePPT_WangWei0727Mannheim_Tongji_DefensePPT_WangWei0727
Mannheim_Tongji_DefensePPT_WangWei0727
 
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
 

Mais de Iain Sanders

Anti-Fragile Systems
Anti-Fragile SystemsAnti-Fragile Systems
Anti-Fragile SystemsIain Sanders
 
Decision analytics-for-bi
Decision analytics-for-biDecision analytics-for-bi
Decision analytics-for-biIain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-4)
Innovation Benefits Realization for Industrial Research (Part-4)Innovation Benefits Realization for Industrial Research (Part-4)
Innovation Benefits Realization for Industrial Research (Part-4)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-8)
Innovation Benefits Realization for Industrial Research (Part-8)Innovation Benefits Realization for Industrial Research (Part-8)
Innovation Benefits Realization for Industrial Research (Part-8)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-7)
Innovation Benefits Realization for Industrial Research (Part-7)Innovation Benefits Realization for Industrial Research (Part-7)
Innovation Benefits Realization for Industrial Research (Part-7)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-6)
Innovation Benefits Realization for Industrial Research (Part-6)Innovation Benefits Realization for Industrial Research (Part-6)
Innovation Benefits Realization for Industrial Research (Part-6)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-5)
Innovation Benefits Realization for Industrial Research (Part-5)Innovation Benefits Realization for Industrial Research (Part-5)
Innovation Benefits Realization for Industrial Research (Part-5)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-3)
Innovation Benefits Realization for Industrial Research (Part-3)Innovation Benefits Realization for Industrial Research (Part-3)
Innovation Benefits Realization for Industrial Research (Part-3)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-2)
Innovation Benefits Realization for Industrial Research (Part-2)Innovation Benefits Realization for Industrial Research (Part-2)
Innovation Benefits Realization for Industrial Research (Part-2)Iain Sanders
 
Innovation Benefits Realization for Industrial Research (Part-1)
Innovation Benefits Realization for Industrial Research (Part-1)Innovation Benefits Realization for Industrial Research (Part-1)
Innovation Benefits Realization for Industrial Research (Part-1)Iain Sanders
 
Innovation Benefits Realization Management
Innovation Benefits Realization ManagementInnovation Benefits Realization Management
Innovation Benefits Realization ManagementIain Sanders
 
Design for Innovation with Business Intelligence
Design for Innovation with Business IntelligenceDesign for Innovation with Business Intelligence
Design for Innovation with Business IntelligenceIain Sanders
 
Design for Innovation with Business Intelligence
Design for Innovation with Business IntelligenceDesign for Innovation with Business Intelligence
Design for Innovation with Business IntelligenceIain Sanders
 
Game-Changing Analytics for Electric Utilities and Smart Grids
Game-Changing Analytics for Electric Utilities and Smart GridsGame-Changing Analytics for Electric Utilities and Smart Grids
Game-Changing Analytics for Electric Utilities and Smart GridsIain Sanders
 
Integrated Distributed Energy Systems (IDES)
Integrated Distributed Energy Systems (IDES)Integrated Distributed Energy Systems (IDES)
Integrated Distributed Energy Systems (IDES)Iain Sanders
 
Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy ResourcesLine Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy ResourcesIain Sanders
 
Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy ResourcesLine Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy ResourcesIain Sanders
 
International Collaboration for the Development of Distributed Energy Resources
International Collaboration for the Development of Distributed Energy ResourcesInternational Collaboration for the Development of Distributed Energy Resources
International Collaboration for the Development of Distributed Energy ResourcesIain Sanders
 
New Product Development Process
New Product Development ProcessNew Product Development Process
New Product Development ProcessIain Sanders
 
Managing Complexity in Technology Innovation
Managing Complexity in Technology InnovationManaging Complexity in Technology Innovation
Managing Complexity in Technology InnovationIain Sanders
 

Mais de Iain Sanders (20)

Anti-Fragile Systems
Anti-Fragile SystemsAnti-Fragile Systems
Anti-Fragile Systems
 
Decision analytics-for-bi
Decision analytics-for-biDecision analytics-for-bi
Decision analytics-for-bi
 
Innovation Benefits Realization for Industrial Research (Part-4)
Innovation Benefits Realization for Industrial Research (Part-4)Innovation Benefits Realization for Industrial Research (Part-4)
Innovation Benefits Realization for Industrial Research (Part-4)
 
Innovation Benefits Realization for Industrial Research (Part-8)
Innovation Benefits Realization for Industrial Research (Part-8)Innovation Benefits Realization for Industrial Research (Part-8)
Innovation Benefits Realization for Industrial Research (Part-8)
 
Innovation Benefits Realization for Industrial Research (Part-7)
Innovation Benefits Realization for Industrial Research (Part-7)Innovation Benefits Realization for Industrial Research (Part-7)
Innovation Benefits Realization for Industrial Research (Part-7)
 
Innovation Benefits Realization for Industrial Research (Part-6)
Innovation Benefits Realization for Industrial Research (Part-6)Innovation Benefits Realization for Industrial Research (Part-6)
Innovation Benefits Realization for Industrial Research (Part-6)
 
Innovation Benefits Realization for Industrial Research (Part-5)
Innovation Benefits Realization for Industrial Research (Part-5)Innovation Benefits Realization for Industrial Research (Part-5)
Innovation Benefits Realization for Industrial Research (Part-5)
 
Innovation Benefits Realization for Industrial Research (Part-3)
Innovation Benefits Realization for Industrial Research (Part-3)Innovation Benefits Realization for Industrial Research (Part-3)
Innovation Benefits Realization for Industrial Research (Part-3)
 
Innovation Benefits Realization for Industrial Research (Part-2)
Innovation Benefits Realization for Industrial Research (Part-2)Innovation Benefits Realization for Industrial Research (Part-2)
Innovation Benefits Realization for Industrial Research (Part-2)
 
Innovation Benefits Realization for Industrial Research (Part-1)
Innovation Benefits Realization for Industrial Research (Part-1)Innovation Benefits Realization for Industrial Research (Part-1)
Innovation Benefits Realization for Industrial Research (Part-1)
 
Innovation Benefits Realization Management
Innovation Benefits Realization ManagementInnovation Benefits Realization Management
Innovation Benefits Realization Management
 
Design for Innovation with Business Intelligence
Design for Innovation with Business IntelligenceDesign for Innovation with Business Intelligence
Design for Innovation with Business Intelligence
 
Design for Innovation with Business Intelligence
Design for Innovation with Business IntelligenceDesign for Innovation with Business Intelligence
Design for Innovation with Business Intelligence
 
Game-Changing Analytics for Electric Utilities and Smart Grids
Game-Changing Analytics for Electric Utilities and Smart GridsGame-Changing Analytics for Electric Utilities and Smart Grids
Game-Changing Analytics for Electric Utilities and Smart Grids
 
Integrated Distributed Energy Systems (IDES)
Integrated Distributed Energy Systems (IDES)Integrated Distributed Energy Systems (IDES)
Integrated Distributed Energy Systems (IDES)
 
Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy ResourcesLine Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
 
Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy ResourcesLine Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
 
International Collaboration for the Development of Distributed Energy Resources
International Collaboration for the Development of Distributed Energy ResourcesInternational Collaboration for the Development of Distributed Energy Resources
International Collaboration for the Development of Distributed Energy Resources
 
New Product Development Process
New Product Development ProcessNew Product Development Process
New Product Development Process
 
Managing Complexity in Technology Innovation
Managing Complexity in Technology InnovationManaging Complexity in Technology Innovation
Managing Complexity in Technology Innovation
 

Último

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesKari Kakkonen
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 

Último (20)

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examples
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 

Network Reliability and Firm Power Capacity with Distributed Energy

  • 1. Report No. IRL99440.01 NETWORK RELIABILITY AND FIRM POWER CAPACITY WORKSHOP HELD AT INDUSTRIAL RESEARCH LIMITED, GRACEFIELD, FRIDAY 16TH DECEMBER 2005 ISSUES, NEEDS, CONCLUSIONS AND ACTION POINTS Prepared by: Dr. Iain Sanders, Sustainable Innovative Solutions Ltd. (for Industrial Research Limited)
  • 2. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Table of Contents 1. Introduction Page 3 1.1 Summary Page 3 1.2 Background Page 3 1.3 What is Firm Power Capacity? Page 4 1.4 Why is Network Reliability an Page 4 Issue for New Zealand? 1.5 Overview of the Rest of this Report Page 4 2. Key Conclusions Page 5 3. Action Points Raised Page 12 4. Workshop Summary Page 15 5. Supplementary Feedback from Participants Page 41 6. Appendices Page 42 6.1 Workshop Agenda Page 42 6.2 List of Attendees Page 43 6.3 Alternative Policy Frameworks for DG Page 45 6.4 Capacity Metering for General Customers Page 59 Editorial Statement: We have attempted to faithfully report and draw conclusions from the presentations and discussions at the workshop. Neither Industrial Research Limited nor Sustainable Innovative Solutions Limited necessarily endorse these findings. Alister Gardiner, Industrial Research Limited. Iain Sanders, Sustainable Innovative Solutions Limited. Disclaimer: The Commerce Commission does not comment on policy matters. The Commission has participated only to explain its approach to assessing breaches of quality thresholds by electricity lines businesses where caused by extreme events, and has not participated in discussions on nor makes any comment in regard to other technical matters or industry design matters. Paolo Ryan, Manager, Network Performance Group. Page 2 of 67
  • 3. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) 1. Introduction 1.1 Summary On Friday December 16th, Industrial Research Limited held a workshop in Gracefield, Lower Hutt, Wellington, on “Network Reliability Requirements” to which electricity industry stakeholders contributed. The purpose of this workshop was to provide an industry forum to discuss key reliability issues facing network operators in relation to the growing interest in connection of distributed generation plant. The workshop presenters in order of appearance were: • Alan Jenkins, Chief Executive, Electricity Networks Association • Rodney Doyle, Chief Advisor, Network Performance Group, Commerce Commission • Gareth Wilson, Manager of the Electricity Group, Ministry of Economic Development (MED) • Robert Reilly, Senior Advisor Retail, Electricity Commission • Duncan Head, Divisional Manager Business Development, Vector Networks • Brent Noriss, Engineering Manager, The Lines Company • Matt Todd, CEO, Eastland Networks Limited • Robert Reilly (speaking on behalf of Roy Hemmingway, Chair, Electricity Commission • Todd Mead, Generation Development Manager, MainPower • Iain Sanders, CEO, Sustainable Innovative Solutions Limited (formerly of Industrial Research Limited) • Alister Gardiner, Hydrogen and Distributed Energy Platform Manager, Industrial Research Limited These presenters discussed regulations, policies, technical issues, business development and research opportunities and challenges associated with delivering firm power capacity in Distribution networks from conventional network infrastructure assets (e.g. lines and poles and underground cables) and alternatives options, including: load management, embedded distributed generation and storage systems. 1.2 Background Network reliability is essential to the safe and secure operation of New Zealand’s electricity delivery infrastructure. Distributed generation adds a new level of complexity for operating networks. This workshop explored some of the needs for reliable firm power capacity in New Zealand’s electricity network infrastructure. Reliability issues were examined from conventional network delivery and alternative energy generation perspectives. This workshop was the first in a series of two workshops. The second workshop (to be held around the middle of 2006) will report on and demonstrate models and techniques developed by Industrial Research for Page 3 of 67
  • 4. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) evaluating the impact of distributed energy resources on network reliability, to providing a means for objective comparison of different distributed energy resources against network capacity costs. 1.3 What is Firm Power Capacity? Firm power capacity is defined as “the provision of power capacity when and where it is required, with a high degree of certainty” (Industrial Research Limited). This constitutes firm power capacity as described in this report and as discussed during the workshop. 1.4 Why is Network Reliability an Issue for New Zealand? Network reliability is affected by the age and cost of maintaining infrastructure assets. Alternative energy supply options such as distributed energy resources may in some circumstances provide more reliable and affordable energy delivery solutions. Ageing infrastructure assets can cost too much to maintain – there just isn’t enough revenue generated from the service provided. In other places, network delivery capacities are exceeded because growth in peak demand cannot be met by existing infrastructure capacity. Complimentary localized dispersed generation can address some of the network reliability issues mentioned. This is only possible if affordable distributed generation resources can match the network reliability requirements of the energy demand needs they address. 1.5 Overview of the Rest of this Report In the next section (2. Key Conclusions), a summary of the main conclusions derived from the workshop are presented under appropriate headings that best define the key points raised. Following the “Key Conclusions”, is a section that presents a series of action points (3. Action Points Raised) or recommendations towards helping to address some of the issues identified as needing urgent attention. After section three, there is a summary of the entire workshop (4. Workshop Summary), outlining the main points raised, issues addressed and specific needs identified by each speaker and the audience in the Q&A sessions following each formal presentation. The final section (5. Appendices), provides the workshop agenda (5.1), and a list of attendees (5.2). A couple of appendices (5.3 and 5.4) describe in further detail some of the conclusions from a technical, commercial and regulatory perspective. Page 4 of 67
  • 5. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) 2. Key Conclusions The following conclusions were derived from the forum discussion and the question and answer sessions held after each presentation. These high level conclusions indicate concern about governance in the industry affecting future reliability through an uncertain investment climate, of which the future for distributed generation is only one component. “Sustainable development” was frequently used in the workshop as the primary need for the industry and government to address. No attempt is made to define the meaning intended by participants, although network “reliability” is clearly an important contributor to this concept. Ref. Key Conclusions C1 Long-term needs not addressed by short-term political agendas. a. The energy industry of New Zealand is the economic engine critical to the nation’s survival and prosperity over the next 25 years. b. Therefore we need to do a lot more evaluation about what the way forward for the electricity supply sector ought to be. c. There are major concerns about the overall lack of integration and mismatch of issues in the energy sector regarding possible energy futures and mapping out a suitable path forward. d. The central generation electricity market model needs to be supported with reinforcement. We have a bureaucratic structure for energy policy in New Zealand that is: “confused and has a great deal of difficulty making decisions” (forum participant). e. Many reports are being written, submissions made, requests for information given etc., but no decisions are being made that address the issues and concerns raised. f. New Zealand needs an energy strategy to address mid- to long-term needs. Page 5 of 67
  • 6. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Ref. Key Conclusions C2 Untapped potential for sustainable development due to fragmented markets. a. Sustainable development is possible if there is the political will to succeed, backed by a commitment to make the hard decisions and consistently pursue policies and directives critical to achieving this outcome. b. Sustainable development includes the significant adoption of distributed energy resources, energy efficient design and utilization, load management, and energy conservation in buildings, industrial processes etc. c. With respect to sustainable development, the question is: what is technically possible if we have the will to achieve it? What is technically possible within the timeframes required? Considering grid- interconnection guidelines, the Resource Management Act (RMA), Power Purchase Agreements (PPAs) etc.? d. Credibility is a key issue for policymakers to address if progress is going to be made. If it is desirable and doable, then why aren’t we making it happen? I.e. putting structures and policies and standards and regulations etc. in place that will facilitate the uptake and establishment of a more sustainable energy market in New Zealand for our long-term growth and prosperity? Page 6 of 67
  • 7. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Ref. Key Conclusions C3 Many opportunities missed or lost due to lack of coordinated planning between Government and industry stakeholders. a. If barriers to investment in distributed energy resources were effectively reduced and removed, the New Zealand electricity industry could experience a transformation, through competition driving innovation, technology advances, business process and practice improvements, new product developments and practical contractual, regulatory and policy design. b. The electricity market only accounts for about 9% of New Zealand’s CO2 emissions. Farming is responsible for half the country’s emissions, and transport takes care of most of the rest. Industrial transformation would be possible if the electricity industry could help substantially to reduce farming and transport greenhouse gas emissions, by focusing on security of supply without increasing CO2 emissions from the energy resources required to achieve it. How much more can the electricity grid be used to supply the energy demands that are currently being met by non-electrical thermal conversion processes? E.g. fuel substitution and methane gas conversion. c. Poorly thought out strategies for banning wood burning for environmental reasons is placing an increasing strain on already capacity-constrained peak loading of networks (and doesn’t account for peak generation fossil fuel CO2 emissions). Here we have disincentives for better load management and conservation of energy resources. How do we create incentives for more efficient and effective energy management and delivery solutions? d. There is a major lack of coordination between new generation planning and network infrastructure utilization for delivering it. Consequently, many new generation and network infrastructure investments are suboptimal. Long-term needs are not addressed through lack of coordinated optimal design of solutions because they involve competing electricity market stakeholders. Short-term vested financial interests take priority over long-term sustainable security of supply. e. There are great opportunities for New Zealand to implement sustainable renewable energy options, but it only takes one barrier e.g. the Resource Management Act to bring an entire project to a halt indefinitely. Page 7 of 67
  • 8. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Ref. Key Conclusions C4 Short-term micro-management drives decision-making process because of distrust between Government and industry. a. How do we reconcile: assurance from Government to industry: for Government to implement consistent long-term policies that work, versus assurance from industry to Government: that industry will deliver solutions that work? Unless we are really clear about reconciling and balancing the need for the former with the need for the latter, we will not know what we can technically do if we have the will to achieve it. b. How do we build a market system that starts to account for and incorporate external costs and benefits as part of the total value equation; and, furthermore, Government must take responsibility for leading the sustainable development of New Zealand’s energy future. c. How well do we manage and utilize our energy resources, and how can we do it better? What do investors need for sustainable energy development to become a practical reality? Page 8 of 67
  • 9. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Ref. Key Conclusions C5 Current decision-making framework is inadequate for developing a consensus amongst Government and industry stakeholders to take appropriate action to address sustainable development of the electricity sector. a. Government agencies want views and opinions of energy market / industry stakeholders to be expressed and presented with concrete evidence-based facts and case studies for proposals for making changes, taking action etc. It is evident that the existing processes used to collect this information are not achieving the desired results to address present Government needs. b. Proper discussion and consideration of individual submissions from members of the public and industrial organizations is not possible because Government agencies do not have the expertise or the resources to properly consider and assess all the options put forward. c. Submissions are not coordinated and expressed in such a way as to effectively address integrated industrial and public concerns of different electricity market shareholders: responses are fragmented and contradict one another – confusing the primary concerns and needs addressed from lesser secondary concerns and interests. d. Lack of coordination amongst various ministries and government agencies has made it difficult to move forward with a cohesive strategy for tackling current electricity market needs. There are no clearly defined boundaries or guidelines for linking the various responsibilities, interests and policy objectives of separate agencies and ministries into a unified cohesive framework or plan that links New Zealand’s sustainable economic growth and prosperity with its security of energy supply. e. Government needs policies that are: “long(-term), loud and legal”. Page 9 of 67
  • 10. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Ref. Key Conclusions C6 Insufficient vision and uncoordinated focus, fragmented scientific and technological research, and inadequate human and financial resources are preventing significant economic benefits being derived from sustainable energy. a. “Think Global, Act Local”. New Zealand Inc. needs a clear vision: e.g. “New Zealand completely self-sustainable in energy resources by ____?”. If you provide a stable infrastructure environment that people are confident in remaining stable, reliable and dependable for a long period of time, with long-term hedge-type products with reliable investment and pricing indicators that people can start banking against, then the other stuff will follow. E.g. the Orion Networks pricing model for investing in distributed generation. The same thing is observed with transport infrastructure investments. We must have a stable long-term focus. b. Universities, Crown Research Institutes and other academic institutions need to work much more closely with industry to facilitate more effective commercialization of research, and ensure research funding / investments are relevant to developing and improving the industrial capabilities required to realize the market benefits possible. c. The group of shareholders using and benefiting from distributed and other sustainable energy resources do not necessarily represent the same group of investors needed to facilitate their adoption. This problem can be resolved if the distribution networks are given / possess the technical capability, the financial capacity, the cooperation and support of the public at large and local communities (beneficiaries / recipients of the services provided), and most importantly of all: the will and clout of the political establishment to support: business investment, R&D funding, long-term incentives, efficient and effective rules and regulations etc. to make it all work. d. In order to work out these issues, a research institute that addresses the technological, political, commercial and legal issues should be set up to facilitate and coordinate the reliable and useful adoption of sustainable distributed energy resources through the lines companies, and plot the smooth transition of New Zealand’s energy industry towards delivering a long-term sustainable, secure and competitively priced energy infrastructure that meets the needs of New Zealand Inc. for generations to come. Page 10 of 67
  • 11. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Ref. Key Conclusions C7 Government needs to establish a Leadership Task Force of people who know how the whole electricity system works and how to effectively incorporate distributed energy resources for optimum operating efficiency, reliability and security of supply. a. Government policymaking for the electricity industry is a rudderless affair. There are too many disparate parties attempting to steer electricity policy in different directions. Lack of coordination is responsible for much confusion. b. There is significant overlap and hence confusion regarding the roles of different yet similar political / governmental agencies competing for influence and resources. c. Government and industry must take a more hands-on approach towards maintaining and developing New Zealand’s energy infrastructure and untapped energy resources – including new / improved load management strategies, smart metering and distributed renewable energy resources. d. Government and industry must take a more hands-on approach towards improving the reliability and security of delivering New Zealand’s energy requirements today and for future generations. e. Greater integration and proactive coordination of industrial and economic development policy with energy security policy and environmental protection policy required. Page 11 of 67
  • 12. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) 3. Action Points Raised From the key conclusions (C1 to C7) and issues raised / specific needs identified by participants, a list of action points are proposed. A1 to A4 are derived from C1 to C7 and A5 to A6 have been drawn from the workshop proceedings. Proposed Ref. Issues Action Points Participation A1 Support long-term • Long-term contracts for Energy planning. energy supply and demand Minister; required. Electricity a. Long-term needs not Commission; addressed by short-term • Pricing arrangements MED; political agendas. (C1) should deliver long-term Commerce contractual arrangements Commission; that help new investors get Energy Users; established and give Generators; consumers who put a Retailers; premium on security, T&D contractual certainty. Networks. A2 Constructive stakeholder • Views and opinions of Energy cooperation. energy market / industry Minister; stakeholders need to be Electricity documented and presented to a. Untapped potential for Commission; the MED, Electricity sustainable development Commission, Commerce MED; MfE; due to fragmented markets. Commission and other NZTE; (C2) Government ministries and Climate agencies. Change b. Many opportunities Office; missed or lost due to lack of • Responses to Government Office of the coordinated planning Requests for Information Parliamentary between Government and (RFIs) should provide Commissioner industry stakeholders. (C3) concrete, evidence-based for the information; and, specific Environment; proposals for making c. Short-term micro- changes, taking action etc. Commerce management drives should be given where Commission; decision-making process possible. Energy Users; because of distrust between Generators; Government and industry. • Government needs to be Retailers; (C4) informed by stakeholders T&D about problems associated Networks. with regulations and policies affecting the operation, efficiency and effectiveness of the electricity and energy markets. Page 12 of 67
  • 13. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Proposed Ref. Issues Action Points Participation A3 Effective decision- • Chains of command, Energy making framework. accountability and Minister; communication need to be Electricity a. Current decision-making improved within and amongst Commission; framework is inadequate Government structures. MED; for developing a Commerce • A more robust, transparent consensus amongst and technically-qualified Commission; Government and industry decision making process is Energy Users; stakeholders to take necessary. Generators; appropriate action to Retailers; address sustainable • Industrial stakeholders must T&D development of the be engaged collectively by Networks. electricity sector. (C5) Government in such a way that interaction amongst different b. Government needs to organizations is supported and establish a Leadership enhanced to achieve better results. Task Force of people who know how the whole • Acquire timely information, electricity system works and the management of that and how to effectively information, with appropriate incorporate distributed smart metering technology. energy resources for optimum operating • Adopt Area and Time Specific efficiency, reliability and Marginal Capacity [ATSMC] security of supply. (C7) cost programmes. A4 Concentrate resources to • Restructure R&D investment Energy achieve a specific so that it supports NZ Inc., and Minister; outcome. a common long-term vision for Electricity New Zealand’s sustainable Commission; a. Insufficient vision and economic growth and MED; MfE; prosperity. uncoordinated focus, NZTE; R&D fragmented scientific and • Create a guiding industrial- organizations; technological research, Governmental coalition with Academia; and inadequate human the resources needed to Climate and financial resources are achieve the vision developed. Change preventing significant Office; economic benefits being • Empower broad-based action, Parliamentary derived from sustainable by getting rid of the obstacles Commissioner energy. (C6) and structures that undermine for Environ.; the vision created. Local govt.; • Encourage risk taking and Chambers of innovation by visibly Commerce; recognizing and rewarding the Commerce organizations that make a Commission; difference towards progressing Energy Users; the vision’s outcomes for New Generators; Zealand. Retailers; T&D Networks Page 13 of 67
  • 14. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Proposed Ref. Issues Action Points Participation A5 Encourage greater • Support the development Energy diversity of supply and of distributed energy minister; demand to reduce risks. resource portfolio business Banks and investment tools and other lending a. A well-structured, models. institutions; diverse portfolio of Business distributed energy (supply- • Encourage banks and investors and & demand-side) resources, other lending institutions to owners; that can balance provide the equivalent of R&D orgs.; fluctuating loads with revolving home loan MfE; Climate fluctuating weather accounts for distributed Change patterns, is needed for energy resource project Office; long-term investment. finance. Electricity Commission; • Support collaboration MED; NZTE; between business / project Generators; investors and load / Retailers; renewable energy T&D forecasters to develop Networks. acceptable & reliable financial risk management metrics. • Ensure coordination of energy investment signals with energy and capacity pricing signals, and energy and capacity usage. A6 Ensure multi-stakeholder • Government intervention is Energy benefits derived from required to reconcile Minister; new energy investments benefits derived from Electricity cover their costs. investing in energy supply- Commission; and demand-side products, MED; Project a. Economic and other processes and services, Investors; benefits derived from with the costs borne by Commerce investing in distributed project investors. This Commission; generation and demand means energy and capacity Energy Users; side management are not benefits obtained by energy Generators; readily realized by the wholesalers, retailers, T&D Retailers; project sponsor or system networks, insurance firms T&D operator. etc., recompense part of the Networks. investor’s project capital and operating expenditure, as applicable, by law. Page 14 of 67
  • 15. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) 4. Workshop Summary ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • Historically, the ‘Planning Division’ definition of ‘reliability’: enough plant and fuel • Long-term • Can the available to meet 7% more than normal load in a winter where lake inflows had been contracts for industry 85% of the mean. energy supply provide the required. reliability NZ • Historically the ‘Electricity Division’ definition of ‘reliability’: based around maintaining needs? frequency and voltage through a centrally coordinated generation and transmission • Pricing Alan Jenkins system operated to defined engineering standards. arrangements • Who pays for should give R&D? (Electricity • The new market structure has created the view: ‘the market will provide’, overlooking local Networks the need to plan ahead. Consequently, focus is on creating an environment for generation as • Can CPI-X Association) competition to flourish, not on delivering reliability. well as more deliver an remote economically Presentation: • In the interests of creating a flat commercial playing field, NZ has tended to have a generation sustainable transmission-centric system. options a network What is Reliable reasonable infrastructure Firm Power • Transmission nodal pricing is one manifestation of possessing a transmission-centric chance of for NZ’s future Capacity? Why system. succeeding. energy delivery Do We Need it? reliability • People don’t like building power stations near a local node, because even a relatively • Pricing requirements? small volume of new generation there will mean that the price of power from remote arrangements competing stations plummets. The net result: no significant investment, either in plant or should keep long-term contracts. old, back-up power stations • NZ’s deregulated electricity market is operationally-focused on generation and nodally- in reserve for driven by trans-mission. when things go wrong, or • It is not clear how much customers are willing to pay for reliability, and who should pay demand gets Page 15 of 67
  • 16. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) for what within the mix of customers. ahead of supply. • Between 1992 and 1998, network companies were very focused on supply security, and providing two-thirds of the new capacity being built at that time. The state was no • Pricing longer carrying the responsibility for building power stations, and new stations were arrangements actually being built close to loads. should ensure that the parties • The Bradford reforms of 1998 brought an end to this era, heavily influenced by a belief selling that the networks’ involvement in generation was occurring because local monopolies electricity are were imprudently building generation capacity that the country didn’t need – leaving selling a local consumers to carry the cost through inflated lines charges. package that includes •The Bradford Electricity Reform Act of 1998 was driven by the belief that it would defined, ‘ensure that costs and prices in the electricity industry are subjected to sustained minimum downward pressure”. reliability levels. • Since 1998: distribution and transmission prices have decreased by: 10%. • Pricing arrangements • Since 1998: energy wholesale prices have increased by: 45%. should give the parties who are • Since 1998: total energy retail prices have increased by: 18%. best equipped to put • As a result of the 1998 reforms: there is a ban on networks trading in energy hedges. commercial pressure on • As a result of the 1998 reforms: there is a ban on exercising any sort of influence over transporters a generation subsidiary, which must be managed through its own officers, with its own responsibility board. for paying transmission • The Electricity Commission was established to address problems of: and - security of supply; distribution. - transmission losses; - grid capacity constraints; • Pricing - no liquidity or transparency in forward wholesale electricity prices; and, arrangements - limited competition emerging / occurring in generation and retail. should incentivise • If network companies were investing in generation it would help Government and the consumers to Page 16 of 67
  • 17. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Electricity Commission achieve their objectives. make a contribution to • After the 1992 crisis, electricity system operations were working around a hydro reliability. ‘minizone’ (storage availability) to decide when, and if, back-up capacity is needed. Do we need to revert to these centrally imposed security arrangements? • Pricing arrangements • There are not effective contingency plans in place to keep old, back-up plant available, should deliver as a consequence of constructing the electricity market in the mid-1990s around spot long-term nodal prices without any imposed longer term pricing arrangements such as loss of load contractual probability payments. arrangements that help new • Existing network-level regulatory signals are very poor at dealing with supply reliability investors get problems. The Commerce Commission’s price control formula linking volumes established and distributed and allowed income deters: a. energy conservation and b. uptake of give consumers distributed generation options that take load off parts of their systems (source of who put a revenue). premium on security • Bad signals from the regulatory regime also disincentivise spending on research and contractual development. The CPI-X thresholds only allow R&D expenditure to come out of profits certainty. and under no circumstances be passed through to consumers. • The annual minus-X adjustment erodes network profits and gives them the same immediate, operational focus that dogs the wholesale electricity market. • Does New Zealand need a major power crisis resulting in a substantial economic recession to get reliability back firmly on the policy agenda? Page 17 of 67
  • 18. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • For Lines Companies to comply with Part 4a of the Commerce Act defining thresholds • If a subjective for declaration of control of lines businesses: they must demonstrate no material process is used deterioration in reliability to define an “extreme • SAIDI/SAIFI thresholds screening mechanism – are used to identify breaches that may event”, why use warrant further investigation. an objective mathematical • Businesses may avoid post-breach inquiry if they demonstrate: Breach due to an process to extreme event. analyze it? • Views and • What is an extreme event? Definition from the Assessment and Inquiry Guidelines: opinions of • The existing Rodney Doyle “Where one or a small number of rare but high impact events has a significant and energy market / process material impact on a business’ reliability performance”. industry proposed for (Commerce stakeholders to handling Commission) • Difficult to use meteorological definitions of extreme events. Extreme weather limits are be expressed extreme events location specific, open to argument, and Extreme events may not be meteorological. and presented cannot make Presentation: to the decisions fast • Extreme events are self-defining. Key requirements for defining a measure Commerce enough to Extreme Events to identify extreme events: Commission. address the needs raised. Consistency – Applicable to all networks large or small, urban or rural. • Priority is to Efficiency – Clear classification of normal and extreme data. encourage best practice in Practicality – Should facilitate metric setting. outage mitigation, Suitability – Should use readily available data. supply restoration and Simplicity – Easy to understand and apply. network design. Page 18 of 67
  • 19. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) There-fore • Steps to identifying an extreme event: proposal aimed at improving 1. Collect up to five years of historical outage data existing practices more 2. Calculate natural log of daily SAIDI figures. than providing an effective 3. Calculate alpha (α) (mean of the log values). method for dealing with 4. Calculate beta (β) (standard deviation of the log values). real-time operational 5. Formula for an extreme event day boundary: requirements. Focus is on e(α + 2.5 β). reducing problems and / • If an extreme event is identified: or improving responsiveness Exclude data for extreme event days from SAIDI records. to current problems. Calculate average daily SAIDI of residual (last 5 years). • Extreme Substitute extreme event days SAIDI figures with average. weather events are very difficult Calculate new annual SAIDI figure. to anticipate from historical Test if threshold is exceeded. data, weather patterns and Decide on action. the shear complexity of • Need consistent reporting practices from lines businesses; Standardised reporting the statistical information for those in breach; Issues in reporting of “Step” restoration type models (and interruptions; hence their Appropriate allocation of outage cause; Evidence of extreme events to be notified to reliability) Commission a.s.a.p. to facilitate investigation and decision. involved. • The Commerce Commission recognise the geographic diversity; • Conclusion: Page 19 of 67
  • 20. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) Distribution businesses should still identify best practice: outage mitigation, industry is very supply restoration procedures, and network design; Aim of improving overall service nervous and reliability. wants to be heard over the Commerce Commission’s proposed thresholds regime. Page 20 of 67
  • 21. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • Electricity Commission (EC) responsible primarily for: • Wide range of possible - overseeing electricity industry and markets. options and - ensuring dry-year reserve. alternatives to - Conducting electricity efficiency programmes; and transmission - regulating Transpower. upgrade in the Akld region • Transpower proposes Grid Upgrade Plans (GUPs) to EC. Focus: 400kV Whakamaru- have been Otahuhu transmission upgrade. considered. Robert Reilly Options (on behalf of Roy • EC involved because: favoured Hemmingway) include: - Load in Auckland is growing. building surplus (Electricity - A solution needed to meet demand at peak times by about 2010. capacity into Commission) - Transpower requires EC approval to be able to pass costs of investment on to existing its customers. proposed Presentation: - EC must decide if Transpower’s proposal is best solution. Assessment includes solutions to application of GIT. address future Alternatives to - EC must ensure other options have been analysed, including generation and needs and Transmission demand-side alternatives. reduce overall costs, and • Generation options considered: incorporate small - G1: Baseload co-generation (84MW co-generation at Marsden by 2010.) intermediate - G2: Baseload coal generation (320MW coal generation at Marsden by 2010 and investments to 320MW additional coal generation at Marsden by 2016.) buy time (defer - G3: Baseload gas generation (385MW CCGT at either Rodney or Otahuhu by investments) 2010 and 2 x 200MW gas generators in Auckland by 2010, and 400MW CCGT at either Otahuhu or Rodney by 2015, and 400MW CCGT in South Auckland by Page 21 of 67
  • 22. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) 2025.) - G4: Wind generation (75-150MW of wind generation in Auckland region by 2015.) - G5: Relocation of Whirinaki (155MW Whirinaki re-located to Auckland by 2010.) - G6: Peaking plant (Peaking diesel generation in Auckland by 2010.) - G7: Alternative technologies (200-250MW of emerging generation technologies from 2015.) • Demand-side alternatives considered: - D1: Interruptible load (IL) (Up to 200MW of IL by 2010.) - D2: Distribution Network Load Management (DNLM) (130-245MW DNLM by 2015 and 15MW ripple control replacement by 2010.) - D3: Energy substitution (70MW gas substitution in Auckland by 2015 and 1- 22MW solar water heating from 2015.) - D4: Energy efficiency measures (Range of measures including 25MW residential lighting by 2010, 17-63MW residential heating by 2015, and 25MW commercial measures by 2015.) • Transmission alternatives: - T1: duplex the WKM-OTA 220kV A and B lines, then install 400kV between WKM and OTA in 2021. - T2: install 220kV between WKM and OTA in 2017. - T3: install HVDC between WKM and OTA in 2017. - T4: install 400kV between WKM and OTA in 2017. • Next steps: - Assessment of ‘short short-list’ of alternatives (generation, demand-side, and transmission) by applying GIT (now underway). - Comparison of short-listed alternatives and Transpower’s proposal (Jan 2006) - Draft decision on Transpower’s proposed 400kV project (Feb/Mar 06) - Consultation (Mar/Apr/May 06). - Final decision (Jun 06). Page 22 of 67
  • 23. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • Lines companies can own: Non renewable generation up to 50 MW or 20% of lines • Advanced capacity. metering provides value • Lines companies can own: Unlimited new renewable generation (e.g. wind). for managing existing and • Lines companies can own: Reserve generation contracted to Electricity Commission. new energy options more • Capacity above 5MW or 2% is subject to arms length restrictions. effectively – Submissions who is Gareth Wilson should provide • Lines companies also prevented from trading in electricity generally and buying and investigating concrete, selling hedges. these (MED) evidence- opportunities? based • Exemptions from some or all of the restrictions may be granted on a case by case Where is the Presentation: information; basis. funding to and, specific research how Facilitating proposals for • Restrictions in place to minimise the opportunity and incentive for lines businesses to: new Investment in making inhibit competition; and/or technologies Generation by changes, taking cross-subsidise generation and retail activities. can improve Lines action etc. the operation of Companies should be given • Should arms length rules be relaxed? the electricity where possible. market? - Should the capacity threshold be raised? - What rules should apply to generation connected to another line owner’s • No research network? has been done on whether the • Should the legislation explicitly set out criteria for exemptions? market structure we • Should lines companies be able to trade in hedges? If so, to what level? now have is appropriate. Page 23 of 67
  • 24. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) • How could legislative uncertainty be reduced? • It is not clear • Discussion paper to be released March 2006 for comment from relevant stakeholders. how the various government departments and agencies are coordinating their activities, let alone cooperating to achieve an integrated cohesive electricity market development and management strategy. Page 24 of 67
  • 25. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • The EC is responsible for: ensuring that electricity is produced and delivered to all • Small scale classes of consumers in an efficient, fair, reliable, and environmentally sustainable generation only manner; and, promoting and facilitating efficient use of electricity. gets value for capacity from • Key outcomes: separate agreements - Investment in (distributed) generation, transmission, energy efficiency and with distribution Robert Reilly demand-side management. networks – • Electricity retailers do not (Electricity Commission value capacity - Remove barriers to distributed generation. Commission) wishes to be delivered. informed about - Access to lines for distributed generation. Presentation: problems • The cost of associated with installing export - Arrangements for the sale of surplus small scale generation. The Electricity the model meters could Commission’s arrangements be a barrier to Role and - Switching and reconciliation of small scale distributed generation. for the sale and DG uptake. Distributed purchase of Generation • The Government proposes to introduce regulations prescribing reasonable terms and surplus conditions on which line owners and electricity distributors must enable generators to be • Separate electricity. agreements are connected to distribution lines. needed with • The objective is to facilitate the use of distributed generation by ensuring that it does the retailer and not face undue barriers in connecting to lines. the distributor to gain full value from • The Electricity Commission will have responsibility for administering the regulations operating DG. and for proposing amendments as required. • The Electricity Act 1992 provides powers to regulate terms and conditions for the Page 25 of 67
  • 26. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) purchase by retailers of small surpluses of electricity from generating units owned or operated by consumers. • It can be difficult for owners of distributed generation units to negotiate terms and conditions with local retailers to purchase small surpluses of electricity generation. • The Government would like to see this barrier to the development and uptake of distributed generation reduced by setting appropriate terms and conditions for purchase of small electricity surpluses by local retailers. • The Government envisages that this policy should apply to consumers with generation units capable of generating up to 40,000kWh over a year. • A key principle however is that retailers should not incur ongoing financial losses by the requirement to purchase such electricity. • The Commission should seek to develop non-regulatory arrangements to achieve these objectives, but should recommend regulations or rules if voluntary arrangements are unsuccessful in achieving the policy outcomes the Government seeks. • The Commission has a role in facilitating Distributed Generation. • Model Retail contracts have provision for the sale and purchase of surplus electricity from small scale generation. • Existing rules do not prevent retailers from trading small scale generation. • Proposed rules will facilitate trading and switching of the output from small scale generation. Page 26 of 67
  • 27. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • Load management is useful when aggregated – due to scale and diversity. • Purchase of cheap • Demand-side is the ability for customers to effect an outcome on the electricity system controllable / market. load (from customers) is a • Load management involves an agreement with a customer to turn off a nominated big opportunity appliance or replace dependence on the network for an agreed duration. for lines companies to • There are a variety of historical technologies in place. Future ability and scope is increase Duncan Head growing with convergence of communications and energy infrastructures. network asset management (Vector Networks • Demand-side participation is not a “public good”, and it depends on the consumer’s • Coordination efficiency and Ltd.) choice between price and quality. It is left to value-seekers to incentivise uptake. of energy economic value investment – but load Presentation: • Demand-side has many valuing-adding applications: signals with management energy usage solutions must Mass Market - Transmission: congestion relief, alternatives, emergency management. required. provide value Load Control - Distribution: capital deferment, asset utilization. to all Issues - Customer: transmission pricing, load management (under time of use pricing). stakeholders in - Retail/Generation: energy hedging, portfolio & risk management. the value chain. - Other: energy hedging, spot market influence, compliance management, ancillary energy market services (e.g. voltage, under frequency). • Issues for effective load • It is doubtful whether any real long-term benefit is provided by the Transmission Pricing management Methodology (‘TPM’). include: gaining benefit from the • Controlling to TPM targets can bring forward investment in distribution network without transmission minimizing Transmission build. pricing methodology Page 27 of 67
  • 28. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) • Ability to reconcile actual benefits to third parties limiting demand-side application to including non-distribution users. reconciling peak load • Alignment of basic building blocks will enable value of demand-side to be realized. reductions with GXP price • Load management needs to create value for those involved. reductions (current • An integrated system is required to gain network benefits from load management. difficult). • Specific outcomes for network distribution load management are: network • An integrated management, asset deferral, and satisfactory customer price-quality trade offs. system is required to gain • Focus on reducing numbers of customers on traditional controlled appliances through network fuel substitution and personal choice. benefits using SCADA • Technology will change the current network load management paradigm. technology. • Vector Networks is currently embarking on a significant rethink of load management. • Vector is looking to • Vector Networks is looking to review incentives for customers to participate in demand- review side management, and how they participate. incentives for customers to • Vector Networks is looking at reducing free riders, so that demand-side benefits go participate in where they are created. load management • It is essential to be able to recognize value (created by demand-side participation etc.) options. and to be able to pass it on. • Load • Change in technology creates opportunities to establish next generation demand-side management systems and strategies, so that ripple plant’s days and historical ownership structures needs to create may be numbered. more value for those involved. • Ripple-relay control systems act like a Page 28 of 67
  • 29. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ‘sledge hammer’ – no longer appropriate for managing loads effectively. • Transmission pricing does not reflect system peaks. Page 29 of 67
  • 30. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • Technical issues associated with installing network-embedded DG include: Connection Arrangements; Protection; Over and Under-voltages; Stability; Auto Re-closing; • The option of Ferro-resonance; Metering; Islanding; Current Flows; Power factor; Under Frequency separating Protection; Harmonics. electricity Brent Noriss generators and • Commercial issues associated with installing network-embedded DG include: • Market rules retailers in the (The Lines Recovery of Costs including Engineering; Transpower Avoidance Calculations; Loss required to NZ electricity Company) Factor Calculations; Power factor; support the market might Dedicated Assets; Connection Contracts. complexity make it harder Presentation: associated with to address the • Industry issues associated with installing network-embedded DG include: Electricity connecting technical The Market ability to handle complex Distributed Generation Situations; Innovative Network distributed issues Experiences of Solutions; and, Plant Reliability. generation to associated with a Network networks in installing and Engineer in The • DG is exciting but involves a lot more engineering than most people realize. reality. operating King Country network- • There is significant difficulty in getting the various stakeholders to understand the embedded issues (let alone work together to address them!) generation. • It is not clear who is going to pay for what with DG installations and operations, let alone ensure that sufficient benefit is concentrated in few enough hands to justify project commencement. Page 30 of 67
  • 31. Network Reliability and Firm Power Capacity Workshop: December 2005 (IRL, Wellington) ISSUES SPECIFIC PRESENTER MAIN POINTS RAISED NEEDS • Eastland Networks Limited (ENL) has commercial and operational motivations for • Transpower’s investigating DG. plans to upgrade • ENL network characteristics include: low consumer density, low average consumer existing circuits consumption, fed by a long radial transmission line with high nodal energy prices. is limited considering • Capacity is a key issue with 47MW uncontrolled and 39MW+ controlled. There is a forestry trends single line, double circuit 110kV line, running through rugged erosion prone back- and the growth country. in regional Matt Todd processing and • A well- • The transmission assets are becoming n-1 constrained. log exports. (Eastland structured, Networks) diverse • 38MW per circuit during the summer. • ENL needs portfolio of non- Presentation: distributed • Peak consumption could grow to 80MW by 2011. transmission generation solutions that Maximising required to • Price is a key issue affecting the network: large customers have been paying 4 to 7 will address Value from make it (DG) c/kWh, new contracts (3 years) are being offered at 10 c/kWh. energy delivery Distributed work. prices and Generation • For forestry processing energy is a top 3 input cost. capacity constraints. • Investors in the region planning new developments need certainty around energy: price, supply (capacity) and contract terms (of supply / price). • The current electricity • Typical problem / challenge involves: investing in a forestry processing plant with a 25 regulatory year $100m investment to make, where energy is one of its top 3 input costs, and environment energy has risen 30% over the last 3 years, with a maximum forward (hedge) term of 3 does not to 5 years. provide incentives for Page 31 of 67