DISCOUNTED MEASURES
OF PROJECT WORTH
Net Present Value (NPV)
 The cashflows estimated for the project

are in the future; they are not yet
realised
 The future is not here yet, but decisions
would have to be taken in the present
time
Net Present Value (NPV)
 The question then is, what is the value of

these future estimated cashflows in the
present or current period, or better still
today?
 future estimated cashflows would have
to be ‘brought’ to the current or present
period
Net Present Value (NPV)

Bt - Ct
NPV = ∑
t
(1+r)
t=1
T
Net Present Value (NPV)

Bt
Ct
NPV = ∑
-∑
t
t
(1+r) t=1 (1+r)
t=1
T

T
Net Present Value (NPV)

Where :
Bt

is periodic benefit

Ct

is periodic cos t

∑

is the summation sign
Net Present Value (NPV)
 Decision Rule:




NPV > 0; project is viable, accept.
NPV < 0; project is not viable, reject.
NPV = 0; project is neither viable nor not
viable
Net Present Value (NPV)
 The value of NPV suggests how much a

project is adding in value terms to an
existing entity or how much value the
project is creating.
 A positive NPV means that the project is
expected to add value to the firm and will
therefore increase the wealth of the
owners.
Net Present Value (NPV)
 Since the goal of projects is to add value

or increase owner’s wealth, NPV is a
direct measure of how well this project
will meet the goal.
 NPV has units of currency such as Rs or
US dollars (US$).
Net Present Value (NPV)
Year

0

1

2

3

4

5

6

7

A

-100

30

30

40

20

10

0

0

B

-100

30

30

30

30

30

10

10
Net Present Value (NPV)
Cashflow Analysis for Project A and B
Cashflow

Discount Factor

Year

A

B

(1+0.30)^-t

0

-100

-100

1

30

2

Discounted Cashflow
A

B

1.0000

-100.00

-100.00

30

0.7692

23.08

23.08

30

30

0.5917

17.75

17.75

3

40

30

0.4552

18.21

13.65

4

20

30

0.3501

7.00

10.50

5

10

30

0.2693

2.69

8.08

6

0

10

0.2072

0.00

2.07

7

0

10

0.1594

0.00

1.59

-31.2691

-23.2675

Net Present Value
Net Present Value (NPV)
 Advantages
 Takes opportunity cost of money into

account.
 A single measure, which takes the
amount and timing of cashflows into
account.
 With NPV one can consider different
scenarios.
Net Present Value (NPV)
Results are expressed in value terms
units of currency. So one is able to
know the impact the value that the
project would create.
 It is based on cashflows, which are
less subjective than profits.

Net Present Value (NPV)
 Disadvantages
 Complex to calculate and communicate.
 Meaning of the result is often misunderstood.
 Only comparable between projects if the initial

investment is the same.
Net Present Value (NPV)
 It can be difficult to identify an

appropriate discount rate.
 Cashflows are usually assumed to occur
at the end of a year, but in practice this
is over simplistic.
Net Benefit Investment Ratio
 Investments are required for project

benefits to be realised.
 These investments in the project
cashflow can be identified as negatives.
Net Benefit Investment Ratio
 The procedure:







discount all the positive cashflows
separately
discount all the negative cashflows
separately.
Sum each of them
The sum of positive discounted cashflows
is divided by sum of negative discounted
cashflows.
Net Benefit Investment Ratio
T

∑B
t =1

NBIR =

t

(1 + i)

t

T

∑K
t =1

t

(1 + i)
where K is sum of negative net benefit or investment
t
Net Benefit Investment Ratio
 The decision rule:



NBIR > 1 accept;
NBIR < 1 reject.
Net Benefit Investment Ratio
Cashflow Analysis for Project A and B
Cashflow

Discount Factor

Year

A

B

(1+0.30)^-t

0
1

-100
30

-100
30

2

30

3

Discounted Cashflow
A

B

1.0000

-100.00

-100.00

0.7692

23.08

23.08

30

0.5917

17.75

17.75

40

30

0.4552

18.21

13.65

4

20

30

0.3501

7.00

10.50

5

10

30

0.2693

2.69

8.08

6

0

10

0.2072

0.00

2.07

7

0

10

0.1594

0.00

1.59

Sum of +ves

68.7309

76.7325

Sum of -ves

100.00

100.00

0.687309

0.767325

NBIR
Net Benefit Investment Ratio
 NBIR is also referred to as Profitability

Index by the accounting profession.
 It is often used for ranking projects
especially if rationing is in place.
Benefit – Cost Ratio (BCR)
 A variant of the formula for NPV uses the

subtraction of discounted cash outflow
from discounted cash inflow.
 In the case of BCR, the discounted cash
inflow is expressed in terms of the
discounted cash outflow.
Benefit – Cost Ratio (BCR)
T

Bt
∑ +r )t
(1
t
BCR = T
Ct
∑ +r )t
(1
t
Benefit – Cost Ratio (BCR)
 This can be viewed as:


how many times the discounted cash
inflow covers the discounted cash outflow
over the project horizon.
Benefit – Cost Ratio (BCR)
 Decision criteria




For a single project, a B/C ratio which is
greater than 1 indicates acceptability
For multiple (competing) projects, the
project(s) with the highest B/C ratios
(greater than 1) should receive highest
priority
Benefit – Cost Ratio (BCR)
 NPV measures totals, indicates the

amount by which benefits exceed (or do
not exceed) costs.
 B/C measures the ratio (or rate) by
which benefits do or do not exceed
costs.
 They are clearly similar, but not identical.
 With multiple projects, some may do
better under NPV analysis, others under
B/C.
Internal Rate of Return (IRR)
 IRR is the rate of return or discount rate

that makes the NPV = 0.
 Decision Rule:


Accept the project if the IRR is greater than
the required return
Internal Rate of Return (IRR)
 This is the most important alternative to NPV.
 It is often used in practice and is intuitively

appealing.
 It is based entirely on the estimated cashflows and
is independent of interest rates found elsewhere.
 Without a financial calculator, this becomes a trial
and error process.
Internal Rate of Return (IRR)
 A critical thing to note is that there

should be at least one change of sign in
order to realise IRR.
 there should be a negative net cashflow
among positive net cashflows or a
positive cashflow among negative
cashflows.
 The change in sign is crucial.
Internal Rate of Return (IRR)
 Using a spreadsheet;
 Start with the cashflows.
 You first enter your range of cashflows,

beginning with the initial cash outlay
(negative).
Internal Rate of Return (IRR)
 Call the IRR function







Choose insert on the menu bar
Select function
Choose IRR from among the list
Select the range of cashflows
Enter a guess rate, but it is not necessary; Excel
will start at 10% as a default
The default format is a whole percent – you will
normally want to increase the decimal places to at
least two to get the most accurate output.
Internal Rate of Return (IRR)
 NPV and IRR will generally give us the

same decision.
 There are however some exceptions.


Non-conventional cashflows
 cashflow



signs change more than once

Mutually exclusive projects
 Initial

investments are substantially different
 Timing of cashflows is substantially different
Internal Rate of Return (IRR)
 When the cashflows change sign more than

once, there is more than one IRR.
 When we solve for IRR it would be noticed that
we are solving for the root of an equation and
when we cross the x-axis more than once, there
will be more than one return that solves the
equation.
 Therefore, IRR may be unreliable if we have
any negative cashflows after our original
investment.
Internal Rate of Return (IRR)
 Suppose an investment will cost ¢90,000

initially and will generate the following
cashflows:




Year 1: 132,000
Year 2: 100,000
Year 3: -150,000

 The required return is 15%.
 Should we accept or reject the project?
Internal Rate of Return (IRR)
Year 0

-90,000

Year 1

132,000

Year 2

100,000

Year 3

-150,000

IRR

NPV fx 15%
Less inv.
NPV at 15%

10.11%

reject

91,770
-90,000
1,770

IRR says to reject, but NPV says to accept. Go with NPV.

accept
Internal Rate of Return (IRR)
 Mutually exclusive projects




If you choose one, you can’t choose the
other
Example: You can choose to attend
graduate school next year at either Legon
or Central, but not both
Internal Rate of Return (IRR)
 Intuitively you would use the following

decision rules:




NPV – choose the project with the higher
NPV
IRR – choose the project with the higher
IRR
Internal Rate of Return (IRR)
Period

Project A

Project B

0

-500

-400

1

325

325

2

325

200

IRR

19.43%

22.17%

NPV

64.05

60.74
Internal Rate of Return (IRR)
 The required return for both projects is

10%.
 Which project should you accept and
why?
 (Accept Project A because of NPV)
Internal Rate of Return (IRR)
 Conflicts between NPV and IRR








NPV directly measures the increase in value to the
firm.
Whenever there is a conflict between NPV and
another decision rule, you should always use NPV.
IRR is unreliable in the following situations
Non-conventional cashflows
Mutually exclusive projects
Internal Rate of Return (IRR)

 Advantages of IRR
 It takes into account the time value of money,

which is a good basis for decision-making.
 Results are expressed as a simple percentage,
and are more easily understood than some other
methods.
 It indicates how sensitive decisions are to a
change in interest rates.
Internal Rate of Return (IRR)
 Advantages of IRR
 It is a simple way to communicate

the value of a project to someone
who doesn’t know all the estimation
details.
 If the IRR is high enough, you may
not need to estimate a required
return, which is often a difficult task.
Internal Rate of Return (IRR)
 Disadvantages
 For mutually exclusive projects: timing and scale

differences. This may lead to incorrect decisions
in comparisons of mutually exclusive
investments.
 Assumes funds are re-invested at a rate
equivalent to the IRR itself, which may be
unrealistically high.
Internal Rate of Return (IRR)
 IRR will produce more than one

mathematically correct rate for each year
in which inflows are followed by outflows
and vice versa. This is common with
projects with unconventional cashflows.
This can create some confusion to the
user.
Choice of Discount Rate
 Cost of capital - weighted average and marginal

(financing rate)
 ‘Opportunity cost’ of capital - what could they
earn if that money was elsewhere
 Current capital position and expected capital
position over next few years
 The rates of return for alternative investments.
 Market sentiments.
Sources of discount rate
 Banks
 Long term government papers
 Ministry of Finance
 Sponsors
Suggestions
 For industrial projects use market rate or

cost of borrowing funds.
 For public sector projects use social time
preference rate.
 For public projects to be funded from
international loans use the cost of
borrowing.
Suggestions
 Generally, in financial analysis, the market rate is

used, whilst the social time preference rate is
used for public sector projects.
 When funding comes from various sources or
from the same source but at different rates, then,
compute and use the weighted average.
Choosing Year 0 or Year 1
 World Bank




World Bank believes that since investment
is made and some returns may accrue
from the first year, then discounting should
start from 0 to first year.
In this case, the initial year is Year 1.
Choosing Year 0 or Year 1
 Others





Other international originations use Year 0.
Their argument is that investment must
take place before benefits accrue.
Thus, discounting should start from the
second year.

 Choose any convention but be

consistent.
Deciding on a Project
 We should consider several investment

criteria when making decisions.
 NPV and IRR are the most commonly
used primary investment criteria.
 Payback is a commonly used secondary
investment criteria, but only because of
its ease of use.
Deciding on a Project
 For a single project, a positive NPV

indicates acceptability.
 For multiple (competing) projects, the
project(s) with the highest NPVs should
receive highest priority.

Mais conteúdo relacionado

Mais procurados

Common property RIGHT by abhinav
Common property RIGHT by abhinavCommon property RIGHT by abhinav
Common property RIGHT by abhinav
DEVIKA ANTHARJANAM
 
3 R's OF CREDIT ANALYSIS
3 R's OF CREDIT ANALYSIS3 R's OF CREDIT ANALYSIS
3 R's OF CREDIT ANALYSIS
Dronak Sahu
 

Mais procurados (20)

Natural resource economics
Natural resource economicsNatural resource economics
Natural resource economics
 
Lecture 12 economic principles applicable to farm management
Lecture 12   economic principles applicable to farm managementLecture 12   economic principles applicable to farm management
Lecture 12 economic principles applicable to farm management
 
Producers surplus and market structure conduct performance
Producers surplus and market structure conduct performanceProducers surplus and market structure conduct performance
Producers surplus and market structure conduct performance
 
Agricultural finance
Agricultural finance Agricultural finance
Agricultural finance
 
agriculture_credit
agriculture_creditagriculture_credit
agriculture_credit
 
Chapter 1 Introduction, Scope and Nature of Agricultural finance
Chapter 1 Introduction, Scope and Nature of Agricultural financeChapter 1 Introduction, Scope and Nature of Agricultural finance
Chapter 1 Introduction, Scope and Nature of Agricultural finance
 
Lecture 19 Risk and Uncertainty
Lecture 19   Risk and UncertaintyLecture 19   Risk and Uncertainty
Lecture 19 Risk and Uncertainty
 
Lecture 11 Farm Management Decisions
Lecture 11  Farm Management DecisionsLecture 11  Farm Management Decisions
Lecture 11 Farm Management Decisions
 
Common property RIGHT by abhinav
Common property RIGHT by abhinavCommon property RIGHT by abhinav
Common property RIGHT by abhinav
 
Agriculture price policy
Agriculture price policyAgriculture price policy
Agriculture price policy
 
Agricultural marketing basics
Agricultural marketing basicsAgricultural marketing basics
Agricultural marketing basics
 
Agriculture price policy
Agriculture price policyAgriculture price policy
Agriculture price policy
 
Farm Budgeting
Farm Budgeting Farm Budgeting
Farm Budgeting
 
Ricardian Theory of Rent
Ricardian Theory of RentRicardian Theory of Rent
Ricardian Theory of Rent
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
3 R's OF CREDIT ANALYSIS
3 R's OF CREDIT ANALYSIS3 R's OF CREDIT ANALYSIS
3 R's OF CREDIT ANALYSIS
 
Aae 301
Aae 301Aae 301
Aae 301
 
Chapter 7(partial budgeting)
Chapter 7(partial budgeting)Chapter 7(partial budgeting)
Chapter 7(partial budgeting)
 
Consumer surplus
Consumer surplusConsumer surplus
Consumer surplus
 
Classical production function and three stages of production
Classical production function and three stages of production Classical production function and three stages of production
Classical production function and three stages of production
 

Semelhante a Discounted measures

Relationship between IRR & NPV
Relationship between IRR & NPVRelationship between IRR & NPV
Relationship between IRR & NPV
Zeeshan Ali
 
Sesi 6 cap budgeting
Sesi 6 cap budgetingSesi 6 cap budgeting
Sesi 6 cap budgeting
reran999
 
Comparison of NPV IRR and Profitability Index.pdf
Comparison of NPV IRR and Profitability Index.pdfComparison of NPV IRR and Profitability Index.pdf
Comparison of NPV IRR and Profitability Index.pdf
janeguinumtad3
 
THAI MUSIC-Mariestela e
THAI MUSIC-Mariestela eTHAI MUSIC-Mariestela e
THAI MUSIC-Mariestela e
Mj Rufin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
Bsgr Planmin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
Bsgr Planmin
 
Risk In Capital Budgeting
Risk In Capital BudgetingRisk In Capital Budgeting
Risk In Capital Budgeting
Noman
 

Semelhante a Discounted measures (20)

Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Relationship between IRR & NPV
Relationship between IRR & NPVRelationship between IRR & NPV
Relationship between IRR & NPV
 
Evaluation techniques
Evaluation techniquesEvaluation techniques
Evaluation techniques
 
capital budgeting concept meaning and types
capital budgeting concept meaning and typescapital budgeting concept meaning and types
capital budgeting concept meaning and types
 
Internal Rate of Return
Internal Rate of ReturnInternal Rate of Return
Internal Rate of Return
 
CAPITAL BUDGETING DECISIONS.ppt
CAPITAL BUDGETING DECISIONS.pptCAPITAL BUDGETING DECISIONS.ppt
CAPITAL BUDGETING DECISIONS.ppt
 
Internal rate of return
Internal rate of returnInternal rate of return
Internal rate of return
 
Futurum training capital budgeting (intermediate)
Futurum training capital budgeting (intermediate)Futurum training capital budgeting (intermediate)
Futurum training capital budgeting (intermediate)
 
Updated IRR PPT
Updated IRR PPTUpdated IRR PPT
Updated IRR PPT
 
Sesi 6 cap budgeting
Sesi 6 cap budgetingSesi 6 cap budgeting
Sesi 6 cap budgeting
 
Comparison of NPV IRR and Profitability Index.pdf
Comparison of NPV IRR and Profitability Index.pdfComparison of NPV IRR and Profitability Index.pdf
Comparison of NPV IRR and Profitability Index.pdf
 
THAI MUSIC-Mariestela e
THAI MUSIC-Mariestela eTHAI MUSIC-Mariestela e
THAI MUSIC-Mariestela e
 
Capital Budgeting : capital budgeting decision
Capital Budgeting : capital budgeting decisionCapital Budgeting : capital budgeting decision
Capital Budgeting : capital budgeting decision
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Risk In Capital Budgeting
Risk In Capital BudgetingRisk In Capital Budgeting
Risk In Capital Budgeting
 
Discounted cash flow applications
Discounted cash flow applicationsDiscounted cash flow applications
Discounted cash flow applications
 
OL_06-07_IPE 4111_ Capital Budgeting.pptx
OL_06-07_IPE 4111_ Capital Budgeting.pptxOL_06-07_IPE 4111_ Capital Budgeting.pptx
OL_06-07_IPE 4111_ Capital Budgeting.pptx
 
Chapter 09 Capital Budgeting
Chapter 09 Capital BudgetingChapter 09 Capital Budgeting
Chapter 09 Capital Budgeting
 

Último

Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂EscortCall Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
dlhescort
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
lizamodels9
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Anamikakaur10
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 

Último (20)

Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂EscortCall Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 

Discounted measures

  • 2. Net Present Value (NPV)  The cashflows estimated for the project are in the future; they are not yet realised  The future is not here yet, but decisions would have to be taken in the present time
  • 3. Net Present Value (NPV)  The question then is, what is the value of these future estimated cashflows in the present or current period, or better still today?  future estimated cashflows would have to be ‘brought’ to the current or present period
  • 4. Net Present Value (NPV) Bt - Ct NPV = ∑ t (1+r) t=1 T
  • 5. Net Present Value (NPV) Bt Ct NPV = ∑ -∑ t t (1+r) t=1 (1+r) t=1 T T
  • 6. Net Present Value (NPV) Where : Bt is periodic benefit Ct is periodic cos t ∑ is the summation sign
  • 7. Net Present Value (NPV)  Decision Rule:    NPV > 0; project is viable, accept. NPV < 0; project is not viable, reject. NPV = 0; project is neither viable nor not viable
  • 8. Net Present Value (NPV)  The value of NPV suggests how much a project is adding in value terms to an existing entity or how much value the project is creating.  A positive NPV means that the project is expected to add value to the firm and will therefore increase the wealth of the owners.
  • 9. Net Present Value (NPV)  Since the goal of projects is to add value or increase owner’s wealth, NPV is a direct measure of how well this project will meet the goal.  NPV has units of currency such as Rs or US dollars (US$).
  • 10. Net Present Value (NPV) Year 0 1 2 3 4 5 6 7 A -100 30 30 40 20 10 0 0 B -100 30 30 30 30 30 10 10
  • 11. Net Present Value (NPV) Cashflow Analysis for Project A and B Cashflow Discount Factor Year A B (1+0.30)^-t 0 -100 -100 1 30 2 Discounted Cashflow A B 1.0000 -100.00 -100.00 30 0.7692 23.08 23.08 30 30 0.5917 17.75 17.75 3 40 30 0.4552 18.21 13.65 4 20 30 0.3501 7.00 10.50 5 10 30 0.2693 2.69 8.08 6 0 10 0.2072 0.00 2.07 7 0 10 0.1594 0.00 1.59 -31.2691 -23.2675 Net Present Value
  • 12. Net Present Value (NPV)  Advantages  Takes opportunity cost of money into account.  A single measure, which takes the amount and timing of cashflows into account.  With NPV one can consider different scenarios.
  • 13. Net Present Value (NPV) Results are expressed in value terms units of currency. So one is able to know the impact the value that the project would create.  It is based on cashflows, which are less subjective than profits. 
  • 14. Net Present Value (NPV)  Disadvantages  Complex to calculate and communicate.  Meaning of the result is often misunderstood.  Only comparable between projects if the initial investment is the same.
  • 15. Net Present Value (NPV)  It can be difficult to identify an appropriate discount rate.  Cashflows are usually assumed to occur at the end of a year, but in practice this is over simplistic.
  • 16. Net Benefit Investment Ratio  Investments are required for project benefits to be realised.  These investments in the project cashflow can be identified as negatives.
  • 17. Net Benefit Investment Ratio  The procedure:     discount all the positive cashflows separately discount all the negative cashflows separately. Sum each of them The sum of positive discounted cashflows is divided by sum of negative discounted cashflows.
  • 18. Net Benefit Investment Ratio T ∑B t =1 NBIR = t (1 + i) t T ∑K t =1 t (1 + i) where K is sum of negative net benefit or investment t
  • 19. Net Benefit Investment Ratio  The decision rule:   NBIR > 1 accept; NBIR < 1 reject.
  • 20. Net Benefit Investment Ratio Cashflow Analysis for Project A and B Cashflow Discount Factor Year A B (1+0.30)^-t 0 1 -100 30 -100 30 2 30 3 Discounted Cashflow A B 1.0000 -100.00 -100.00 0.7692 23.08 23.08 30 0.5917 17.75 17.75 40 30 0.4552 18.21 13.65 4 20 30 0.3501 7.00 10.50 5 10 30 0.2693 2.69 8.08 6 0 10 0.2072 0.00 2.07 7 0 10 0.1594 0.00 1.59 Sum of +ves 68.7309 76.7325 Sum of -ves 100.00 100.00 0.687309 0.767325 NBIR
  • 21. Net Benefit Investment Ratio  NBIR is also referred to as Profitability Index by the accounting profession.  It is often used for ranking projects especially if rationing is in place.
  • 22. Benefit – Cost Ratio (BCR)  A variant of the formula for NPV uses the subtraction of discounted cash outflow from discounted cash inflow.  In the case of BCR, the discounted cash inflow is expressed in terms of the discounted cash outflow.
  • 23. Benefit – Cost Ratio (BCR) T Bt ∑ +r )t (1 t BCR = T Ct ∑ +r )t (1 t
  • 24. Benefit – Cost Ratio (BCR)  This can be viewed as:  how many times the discounted cash inflow covers the discounted cash outflow over the project horizon.
  • 25. Benefit – Cost Ratio (BCR)  Decision criteria   For a single project, a B/C ratio which is greater than 1 indicates acceptability For multiple (competing) projects, the project(s) with the highest B/C ratios (greater than 1) should receive highest priority
  • 26. Benefit – Cost Ratio (BCR)  NPV measures totals, indicates the amount by which benefits exceed (or do not exceed) costs.  B/C measures the ratio (or rate) by which benefits do or do not exceed costs.  They are clearly similar, but not identical.  With multiple projects, some may do better under NPV analysis, others under B/C.
  • 27. Internal Rate of Return (IRR)  IRR is the rate of return or discount rate that makes the NPV = 0.  Decision Rule:  Accept the project if the IRR is greater than the required return
  • 28. Internal Rate of Return (IRR)  This is the most important alternative to NPV.  It is often used in practice and is intuitively appealing.  It is based entirely on the estimated cashflows and is independent of interest rates found elsewhere.  Without a financial calculator, this becomes a trial and error process.
  • 29. Internal Rate of Return (IRR)  A critical thing to note is that there should be at least one change of sign in order to realise IRR.  there should be a negative net cashflow among positive net cashflows or a positive cashflow among negative cashflows.  The change in sign is crucial.
  • 30. Internal Rate of Return (IRR)  Using a spreadsheet;  Start with the cashflows.  You first enter your range of cashflows, beginning with the initial cash outlay (negative).
  • 31. Internal Rate of Return (IRR)  Call the IRR function       Choose insert on the menu bar Select function Choose IRR from among the list Select the range of cashflows Enter a guess rate, but it is not necessary; Excel will start at 10% as a default The default format is a whole percent – you will normally want to increase the decimal places to at least two to get the most accurate output.
  • 32. Internal Rate of Return (IRR)  NPV and IRR will generally give us the same decision.  There are however some exceptions.  Non-conventional cashflows  cashflow  signs change more than once Mutually exclusive projects  Initial investments are substantially different  Timing of cashflows is substantially different
  • 33. Internal Rate of Return (IRR)  When the cashflows change sign more than once, there is more than one IRR.  When we solve for IRR it would be noticed that we are solving for the root of an equation and when we cross the x-axis more than once, there will be more than one return that solves the equation.  Therefore, IRR may be unreliable if we have any negative cashflows after our original investment.
  • 34. Internal Rate of Return (IRR)  Suppose an investment will cost ¢90,000 initially and will generate the following cashflows:    Year 1: 132,000 Year 2: 100,000 Year 3: -150,000  The required return is 15%.  Should we accept or reject the project?
  • 35. Internal Rate of Return (IRR) Year 0 -90,000 Year 1 132,000 Year 2 100,000 Year 3 -150,000 IRR NPV fx 15% Less inv. NPV at 15% 10.11% reject 91,770 -90,000 1,770 IRR says to reject, but NPV says to accept. Go with NPV. accept
  • 36. Internal Rate of Return (IRR)  Mutually exclusive projects   If you choose one, you can’t choose the other Example: You can choose to attend graduate school next year at either Legon or Central, but not both
  • 37. Internal Rate of Return (IRR)  Intuitively you would use the following decision rules:   NPV – choose the project with the higher NPV IRR – choose the project with the higher IRR
  • 38. Internal Rate of Return (IRR) Period Project A Project B 0 -500 -400 1 325 325 2 325 200 IRR 19.43% 22.17% NPV 64.05 60.74
  • 39. Internal Rate of Return (IRR)  The required return for both projects is 10%.  Which project should you accept and why?  (Accept Project A because of NPV)
  • 40. Internal Rate of Return (IRR)  Conflicts between NPV and IRR      NPV directly measures the increase in value to the firm. Whenever there is a conflict between NPV and another decision rule, you should always use NPV. IRR is unreliable in the following situations Non-conventional cashflows Mutually exclusive projects
  • 41. Internal Rate of Return (IRR)  Advantages of IRR  It takes into account the time value of money, which is a good basis for decision-making.  Results are expressed as a simple percentage, and are more easily understood than some other methods.  It indicates how sensitive decisions are to a change in interest rates.
  • 42. Internal Rate of Return (IRR)  Advantages of IRR  It is a simple way to communicate the value of a project to someone who doesn’t know all the estimation details.  If the IRR is high enough, you may not need to estimate a required return, which is often a difficult task.
  • 43. Internal Rate of Return (IRR)  Disadvantages  For mutually exclusive projects: timing and scale differences. This may lead to incorrect decisions in comparisons of mutually exclusive investments.  Assumes funds are re-invested at a rate equivalent to the IRR itself, which may be unrealistically high.
  • 44. Internal Rate of Return (IRR)  IRR will produce more than one mathematically correct rate for each year in which inflows are followed by outflows and vice versa. This is common with projects with unconventional cashflows. This can create some confusion to the user.
  • 45. Choice of Discount Rate  Cost of capital - weighted average and marginal (financing rate)  ‘Opportunity cost’ of capital - what could they earn if that money was elsewhere  Current capital position and expected capital position over next few years  The rates of return for alternative investments.  Market sentiments.
  • 46. Sources of discount rate  Banks  Long term government papers  Ministry of Finance  Sponsors
  • 47. Suggestions  For industrial projects use market rate or cost of borrowing funds.  For public sector projects use social time preference rate.  For public projects to be funded from international loans use the cost of borrowing.
  • 48. Suggestions  Generally, in financial analysis, the market rate is used, whilst the social time preference rate is used for public sector projects.  When funding comes from various sources or from the same source but at different rates, then, compute and use the weighted average.
  • 49. Choosing Year 0 or Year 1  World Bank   World Bank believes that since investment is made and some returns may accrue from the first year, then discounting should start from 0 to first year. In this case, the initial year is Year 1.
  • 50. Choosing Year 0 or Year 1  Others    Other international originations use Year 0. Their argument is that investment must take place before benefits accrue. Thus, discounting should start from the second year.  Choose any convention but be consistent.
  • 51. Deciding on a Project  We should consider several investment criteria when making decisions.  NPV and IRR are the most commonly used primary investment criteria.  Payback is a commonly used secondary investment criteria, but only because of its ease of use.
  • 52. Deciding on a Project  For a single project, a positive NPV indicates acceptability.  For multiple (competing) projects, the project(s) with the highest NPVs should receive highest priority.