Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Change Management
1. Changes Management
Change Management is the process of developing
a planned approach to change in an organization.
The objective is to maximize the collective benefits for
all people involved in the change and minimize the
risk of failure of implementing the change.
It is a procedure to ensure that proposed changes are
merited and will not adversely affect other elements of
the plan or interdependent plans.
Change must be realistic, achievable and measurable.
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 1
2. Types of Changes
Scope changes (modify product documentation and
often project plan):
Requirements changes
Clarifications
Site emergencies
Work changes (modify project plan):
Resource changes
Modified approach
Corrective action
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 2
3. Evaluating Change Requests
All change requests are documented:
Emergency changes are documented after the fact.
Non-emergencies are documented before being
considered.
Change requests should be documented by the
requestor
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 3
4. Change Management Process
Control
Start
Detection
Diagnosis
Repair
Recovery
Restoration
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 4
5. First Level Approval
of Change Requests
Usually provided by the project manager or a senior
team member:
Are the expected benefits significant enough to
merit further investigation?
Implications:
Must have budget for this work!
Benefits may include cost avoidance
Organizational politics must be considered
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 5
6. Second Level Approval of Change
Requests
Usually provided by a Change Control Board (CCB):
Do the expected benefits outweigh any negative
impacts?
Implications:
Must have budget for this work!
Benefits may include cost avoidance
Organizational politics must be considered
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 6
7. Change Control Board
A formally constituted group responsible for
approving or rejecting change requests.
Powers and responsibilities should be well-defined
and agreed upon in advance.
On larger, more complex projects, there may be
multiple CCBs.
6/20/2010 Author: Dr. Tomas U. Ganiron Jr 7