SlideShare uma empresa Scribd logo
1 de 108
Baixar para ler offline
Wind energy harvesting basics,
                    resource assessment and
                 application for off grid systems.
                              part 2
                              Hanan Einav-Levy M.Sc.




Thursday, November 10, 2011
Outline




Thursday, November 10, 2011
Outline
              •      part II (2 hours)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •    Estimating the needs (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •    Estimating the needs (10)
                         •    Sizing the turbine (5)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •    Estimating the needs (10)
                         •    Sizing the turbine (5)

                         •    AC or DC (5)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •    Estimating the needs (10)
                         •    Sizing the turbine (5)

                         •    AC or DC (5)
                         •    Sizing the battery bank (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •    Estimating the needs (10)
                         •    Sizing the turbine (5)

                         •    AC or DC (5)
                         •    Sizing the battery bank (10)

                         •    Sizing the inverter (5)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •    Estimating the needs (10)
                         •    Sizing the turbine (5)

                         •    AC or DC (5)
                         •    Sizing the battery bank (10)

                         •    Sizing the inverter (5)
                         •    Economics (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •        Estimating the needs (10)
                         •        Sizing the turbine (5)

                         •        AC or DC (5)
                         •        Sizing the battery bank (10)

                         •        Sizing the inverter (5)
                         •        Economics (10)
                   •          Small wind turbine product comparison (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •        Estimating the needs (10)
                         •        Sizing the turbine (5)

                         •        AC or DC (5)
                         •        Sizing the battery bank (10)

                         •        Sizing the inverter (5)
                         •        Economics (10)
                   •          Small wind turbine product comparison (10)
                   •          Case studies




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •        Estimating the needs (10)
                         •        Sizing the turbine (5)

                         •        AC or DC (5)
                         •        Sizing the battery bank (10)

                         •        Sizing the inverter (5)
                         •        Economics (10)
                   •          Small wind turbine product comparison (10)
                   •          Case studies
                         •        Practical action - Peru (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •        Estimating the needs (10)
                         •        Sizing the turbine (5)

                         •        AC or DC (5)
                         •        Sizing the battery bank (10)

                         •        Sizing the inverter (5)
                         •        Economics (10)
                   •          Small wind turbine product comparison (10)
                   •          Case studies
                         •        Practical action - Peru (10)
                         •        AWP - Zimbabwe (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •        Estimating the needs (10)
                         •        Sizing the turbine (5)

                         •        AC or DC (5)
                         •        Sizing the battery bank (10)

                         •        Sizing the inverter (5)
                         •        Economics (10)
                   •          Small wind turbine product comparison (10)
                   •          Case studies
                         •        Practical action - Peru (10)
                         •        AWP - Zimbabwe (10)
                         •        WindAid - Peru (10)




Thursday, November 10, 2011
Outline
              •      part II (2 hours)
                   •      Example project
                         •      Estimating the wind resource (5)

                         •        Estimating the needs (10)
                         •        Sizing the turbine (5)

                         •        AC or DC (5)
                         •        Sizing the battery bank (10)

                         •        Sizing the inverter (5)
                         •        Economics (10)
                   •          Small wind turbine product comparison (10)
                   •          Case studies
                         •        Practical action - Peru (10)
                         •        AWP - Zimbabwe (10)
                         •        WindAid - Peru (10)
                         •        CometME - Israel / Palestinian authority (10)




Thursday, November 10, 2011
Resource: ITDG_2001_bookletwind.pdf




                                Example project
Thursday, November 10, 2011
Small wind development by technology
                                 transfer




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system
                         •       Estimating the wind resource




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system
                         •       Estimating the wind resource
                         •       Estimating the needs




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system
                         •       Estimating the wind resource
                         •       Estimating the needs
                         •       Sizing the turbine




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system
                         •       Estimating the wind resource
                         •       Estimating the needs
                         •       Sizing the turbine
                         •       AC or DC




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system
                         •       Estimating the wind resource
                         •       Estimating the needs
                         •       Sizing the turbine
                         •       AC or DC
                         •       Sizing the battery bank




Thursday, November 10, 2011
Small wind development by technology
                                         transfer
                  • ITDG (now called Practical Action)
                  • One method to develop wind turbines for rural communities -
                    there are others.
                   •          We will use this to study the design of the system
                         •       Estimating the wind resource
                         •       Estimating the needs
                         •       Sizing the turbine
                         •       AC or DC
                         •       Sizing the battery bank
                         •       Sizing the inverter



Thursday, November 10, 2011
Current situation
           •      12V Car batteries are used for
                  radios and TVs

           •      60Ah or 90Ah battery typically
                  used

           •      A large market for existing
                  battery users (300,000
                  households)

           •      Monthly battery cost 6.5$ (5$
                  battery replacement, 1$ travel,
                  0.5$ charging)



Thursday, November 10, 2011
Estimating the wind
           •      Anecdotal evidence

           •      The local vegetation

           •      The Beaufort scale

           •      Wind map

           •      Installing an anemometer+data
                  logging equipment - 200-1000$

           •      Installing a wind turbine with data
                  logging equipment with the same
                  funds



Thursday, November 10, 2011
Beaufort scale




Thursday, November 10, 2011
Siting the
        wind turbine
           •      The highest
                  point

           •      Open to
                  prevailing winds

           •      Not too far
                  from load

           •      On a tall
                  tower!



Thursday, November 10, 2011
Siting the                  Highest
                                      point
        wind turbine
           •      The highest
                  point

           •      Open to
                  prevailing winds

           •      Not too far
                  from load

           •      On a tall
                  tower!



Thursday, November 10, 2011
Siting the                                       Highest
                                     Too far from loads    point
        wind turbine
           •      The highest
                  point

           •      Open to
                  prevailing winds

           •      Not too far
                  from load

           •      On a tall
                  tower!



Thursday, November 10, 2011
Choosing AC vs. DC
           •      For a wind turbine installed far from
                  the load normally the battery voltage
                  will be as high as possible (48V)

           •      If not enough - using an DC-AC
                  inverter at the tower makes sense

           •      Allows to work at 230 volts, and
                  therefor less current

           •      Losses are proportional to the
                  current squared

           •      Benefit: Allows to work with regular
                  230V AC loads




Thursday, November 10, 2011
Choosing AC vs. DC

           •      But cost of DC-AC inverter
                  can be substantial

           •      Alternative - site wind
                  turbine close to load

           •      Shorter cables - less loss

           •      Downside: only DC loads




Thursday, November 10, 2011
Conservative estimate of monthly
                               electricity production
      •      Assuming efficiency is 15%
             (see previous lecture for
             more refined estimate by
             Paul Gipe)
                 D × V ⎡ kWh ⎤2   3

      •      E=
                    10 ⎢ month ⎥
                         ⎣       ⎦
             V = average wind speed [m/s]
             D = diameter [m]




Thursday, November 10, 2011
Estimating the loads
           •      What the wind shouldn’t power:

                 •      Electric heaters

                 •      Electric cookers

           •      For whom will the system be
                  designed?

                 •      Single household

                 •      Several households




Thursday, November 10, 2011
Single household




Thursday, November 10, 2011
Single household
                                           Rule of thumb -
                                       battery charging losses




Thursday, November 10, 2011
Breaking down the load for a typical day




Thursday, November 10, 2011
3 households sharing a turbine




Thursday, November 10, 2011
3 households sharing a turbine




Thursday, November 10, 2011
3 households sharing a turbine




Thursday, November 10, 2011
3 households sharing a turbine




Thursday, November 10, 2011
Sizing the turbine
            In an ideal world -
           1. Identify wind resource

           2. Identify electricity needs

           3. Size turbine accordingly

           4. Size battery bank according
              to measured wind pattern




Thursday, November 10, 2011
Sizing the turbine for our two examples




Thursday, November 10, 2011
Sizing the turbine for our two examples




                              Enough spare energy




Thursday, November 10, 2011
Sizing the turbine for our two examples




                                Not enough energy




Thursday, November 10, 2011
Sizing the battery
      • The battery is charged and discharged
            over a period of hours or days.

      • This is a cycle
      • Two parameters important in a battery
            life:

           • Number of cycles
           • The depth of discharge




Thursday, November 10, 2011
Sizing the battery




Thursday, November 10, 2011
Sizing the battery




Thursday, November 10, 2011
Sizing the battery




Thursday, November 10, 2011
Sizing the Battery
           •      Calculate Ep, the daily consumption in
                  Wh
                  (for example Ep = 400 Wh/day)

           •      Choose N, number of days of autonomy,
                  typically 3-5 days
                  (for example N = 3 days)

           •      Choose maximum allowable depth of
                  discharge, D
                  (for example D = 0.5, which means 50%)

           •      Choose U, battery voltage (typically
                  12,24 or 48 volts)
                  (for example U = 12V)




Thursday, November 10, 2011
Sizing the Battery                          Calculate C, battery capacity:

           •      Calculate Ep, the daily consumption in      Ep × N
                  Wh                                       C=          [Ah]
                  (for example Ep = 400 Wh/day)                D ×U
                                                              400 × 3
           •      Choose N, number of days of autonomy,     =           = 200[Ah]
                  typically 3-5 days
                  (for example N = 3 days)
                                                              0.5 × 12

           •      Choose maximum allowable depth of
                  discharge, D
                  (for example D = 0.5, which means 50%)

           •      Choose U, battery voltage (typically
                  12,24 or 48 volts)
                  (for example U = 12V)




Thursday, November 10, 2011
Cost of wind turbine - 2 meter
                                diameter, 100 watt rated




Thursday, November 10, 2011
Economics
                   •          Financing ownership by battery charging services
                   •          Current batteries are 60 Ah car batteries (DOD 50%)
                   •          To charge battery (with efficiency of charging loss of
                              25%) 0.5X60X12X1.25 = 450 Wh
                   •          2 meter diameter at 3.5 m/s site produces 17 kWh/
                              month or 600 Wh/day on average
                   •          Therefor one battery charged per day
                   •          charging 1 day a week for the owner, and the rest for
                              customers



Thursday, November 10, 2011
Economics




Thursday, November 10, 2011
Final system components




Thursday, November 10, 2011
Final system components



            Sizing according to local
            need and wind resource




Thursday, November 10, 2011
Final system components




Thursday, November 10, 2011
Final system components
                              Sizing according to wind
                               variability and “spares”
                                     requirement




Thursday, November 10, 2011
Final system components




Thursday, November 10, 2011
Final system components
                                  For an AC system -
                                according to maximum
                                         load




Thursday, November 10, 2011
Final system components




Thursday, November 10, 2011
Small wind turbine market
Thursday, November 10, 2011
WT brochure
                                                                                                                                           Proven WT6000 6kW Wind Turbine
                                                                                                                                           Proven TM900 9m (or TM1500 15m)
                                                                                                                                           Self-Supporting Mast
                                                                                                           

                                                                                                                                           Performance
                                                                                                                                           Cut-In Wind Speed 2.5 metres/second (5.6 mph)
                                                                                                                                           Cut-Out Wind Speed none
                                                                                                                                           Rated Wind Speed   12 metres/second (25 mph)

                                                                                                                                           Rotor




           •
                                                                                                                                           Type                                           Down-wind, Self-Regulating


                  Includes many details
                                                                                                                                           Number of Blades                               3, Flexible
                                                                                                                                           Rotor Diameter                                 5.6 metres
                                                                                                                                           Blade Material                                 Wood/Epoxy/PU

                                                                                                                                           Generator
                                                                                                                                           Type                                          Brushless, Direct Drive,




           •
                                                                                                                                                                                         Permanent Magnet


                  Most important parameter -
                                                                                                                                                                                         (No Gear-Box, Zero Maintenance)
                                                                                                                                           Output                                        48V/120V/240V/300V 3-phase AC
                                                                      7000
                                                                                                                                                                                         (25Hz nom)
                                                                      6000
                                                                                                                                           Rated RPM                                     200 nominal

                  diameter, or swept area
                                                                      5000
                                                                                                                                           Rated Power                                   6000 Watts




                                               Power Output (Watts)
                                                                      4000

                                                                      3000
                                                                                                                                           Annual Output                                 7000-18 000 kWh depending on site
                                                                      2000

                                                                      1000
                                                                                                                                           TM900 Mast
                                                                          0
                                                                                                                                           Type                                           Self supporting/Tilt Down.
                                                                                                                                           Hub Height                                     9m




           •
                                                                              0          5           10            15        20
                                                                                      Wind speed in m etres/second
                                                                                        (m ultiply by 2.2 for m .p.h.)                     Foundations                                    35 Newton Concrete Pad 2.5 x 2.5 x 1 m


                  Make sure is intended for                 Rotor Speed Control
                                                                                                                                           Tube ∅                                         175 mm top A/F
                                                                                                                                                                                          350 mm bottom A/F
                                                                                                                                                                                          530 mm square mast base


                  battery charging
                                                      Above 12m/s (25mph) the blade                                                        TM1500 Mast
                                                      pitch is automatically adjusted to                                                   Type                                           Self supporting/Tilt Down.
                                                      maintain 200 rpm and full output                                                     Hub Height                                     15m
                                                                                                                                           Foundations                                    35 Newton Concrete Pad 3 x 3 x 1.2 m
                                                        High Build Quality                                                                 Tube ∅                                         200 mm top A/F
                                               All components are hot-dipped                                                                                                              440 mm bottom A/F




           •
                                               galvanised steel, stainless steel or                                                                                                       750 mm x 739mm mast base
                                               plastic.

                  Must have aerodynamic          Low Speed Equals Durability
                                               Low rotor speed (half the speed of
                                                                                                                                           Noise
                                                                                                                                           <45dB
                                                                                                                                           <60dB
                                                                                                                                                                                          (approximate)
                                                                                                                                                                                          At 5m/s
                                                                                                                                                                                          At 20m/s

                  control option
                                               comparable machines) ensures                                                                70-80dB                                        Car 15m away at approx 40 mph.
                                               extended durability of blades and
                                               bearings.   It also means that
                                                                                                                                           Weight
                                               Proven WTs are the quietest in the
                                               world!                                                                                      WT6000                                         500 kg
                                                                                                                                           TM900/6000                                     360 kg (+ 70kg gin pole)
                                                                                                                                           TM1500/6000                                    656 kg (+ 240kg gin pole)

                                                                                                                                  z :  a l l  wi n d t u r b  s a l e s l i t  m a n u a l  w t 6 0 0 0  s s s p e c s h ee t s  6 0 0 0 s s 0 0 1 r e v 2 . d o c




Thursday, November 10, 2011
Small wind turbine market
Thursday, November 10, 2011
Source -
  American magazine.
   2 mph = 1 m/s




               Small wind turbine market
Thursday, November 10, 2011
Small wind turbine market
Thursday, November 10, 2011
Most important
       parameter




               Small wind turbine market
Thursday, November 10, 2011
Small wind turbine market
Thursday, November 10, 2011
Case studies
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
small wind:
                                      0.2$-1.15$ / kWh


                                solar PV:
                              1.21$ / kWh




Thursday, November 10, 2011
African Wind Power
Thursday, November 10, 2011
•       Example of
                 technology
                 transfer




                          African Wind Power
Thursday, November 10, 2011
•       Example of
                 technology
                 transfer
         •       Turbines now
                 installed from
                 Africa to
                 Antarctica!


                          African Wind Power
Thursday, November 10, 2011
AWP - Zimbabwe - Masampa Village Lake Kariba
                   •          AWP3.6 - 48V 13.5M tilt up tower, 275Ahr 48V Battery bank, 3KW sine
                              wave inverter, 12V battery charging station.




Thursday, November 10, 2011
AWP - Zimbabwe - Masampa Village Lake Kariba
   •      AWP3.6 - 48V 13.5M tilt up tower, 275Ahr 48V Battery bank, 3KW sine wave inverter,
          12V battery charging station.

   •      This fishing co-operative village is on the shores of Lake Kariba, 45Km by boat from the
          nearest town. Crocodiles inhabit the shore line and Hippos amble through the village at
          night while foraging ( startling a hippo is not good for your health). With funds provided by
          the Dutch government via the NGO ZERO, AWP implemented the entire project in all its
          stages:

         •      (1) Initial location of the people in need

         •      (2) discussions with the village committee

         •      (3) resulting in motivation of the villagers to contribute labour to the installation,
                transportation of all materials to site, construction and commissioning

         •      (4) and finally training of operators.

   •      The system provides lighting for the main thoroughfares and also a popular 12v car battery
          charging center which draws customers from a 20 Km radius. Income from this activity is
          used for village development.




Thursday, November 10, 2011
WindAid - Peru




Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Thursday, November 10, 2011
Comet-ME




Thursday, November 10, 2011
Comet-ME




Thursday, November 10, 2011
Comet-ME




Thursday, November 10, 2011
Comet-ME




Thursday, November 10, 2011
Comet-ME




Thursday, November 10, 2011
Comet-ME
      •       The systems are designed for producing 2-3 kWh/
              day for a large beduin family.
      •       Systems are DIY wind turbines and solar PV panels
      •       Systems used for powering:
            •      Lights
            •      Refrigirator
            •      Butter churn
            •      TV
            •      Cellphone charging
      •       Costs are between 5000$-8000$



Thursday, November 10, 2011
Resources




Thursday, November 10, 2011
Resources




Thursday, November 10, 2011

Mais conteúdo relacionado

Destaque

Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]
Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]
Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]Vitor Figueiredo
 
Solar charkha khadi production
Solar charkha khadi productionSolar charkha khadi production
Solar charkha khadi productionAdane Nega
 
Wind by Tom and Morgan
Wind by Tom and MorganWind by Tom and Morgan
Wind by Tom and Morgantmelburn
 
Rural Product strategy
Rural Product strategyRural Product strategy
Rural Product strategyBrahm Sharma
 
PRODUCT LAUNCH IN RURAL MARKET
PRODUCT LAUNCH IN RURAL MARKETPRODUCT LAUNCH IN RURAL MARKET
PRODUCT LAUNCH IN RURAL MARKETpreeti garg
 
Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)KAMALAKKANNAN G
 
Products for rural markets
Products for rural marketsProducts for rural markets
Products for rural marketsJitendra Kumar
 
Wind energy I. Lesson 1. Introduction
Wind energy I. Lesson 1. IntroductionWind energy I. Lesson 1. Introduction
Wind energy I. Lesson 1. IntroductionTuong Do
 

Destaque (10)

Rural Marketing
Rural MarketingRural Marketing
Rural Marketing
 
Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]
Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]
Boruto: The Next Generations - Capítulo 1 [Naruto 3GP]
 
Solar charkha khadi production
Solar charkha khadi productionSolar charkha khadi production
Solar charkha khadi production
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
Wind by Tom and Morgan
Wind by Tom and MorganWind by Tom and Morgan
Wind by Tom and Morgan
 
Rural Product strategy
Rural Product strategyRural Product strategy
Rural Product strategy
 
PRODUCT LAUNCH IN RURAL MARKET
PRODUCT LAUNCH IN RURAL MARKETPRODUCT LAUNCH IN RURAL MARKET
PRODUCT LAUNCH IN RURAL MARKET
 
Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)
 
Products for rural markets
Products for rural marketsProducts for rural markets
Products for rural markets
 
Wind energy I. Lesson 1. Introduction
Wind energy I. Lesson 1. IntroductionWind energy I. Lesson 1. Introduction
Wind energy I. Lesson 1. Introduction
 

Mais de Hanan E. Levy

Piggott turbine design_code_dakar_presentation
Piggott turbine design_code_dakar_presentationPiggott turbine design_code_dakar_presentation
Piggott turbine design_code_dakar_presentationHanan E. Levy
 
Wind power siting_and_environmental_issues_newman
Wind power siting_and_environmental_issues_newmanWind power siting_and_environmental_issues_newman
Wind power siting_and_environmental_issues_newmanHanan E. Levy
 
EWB israel conference
EWB israel conferenceEWB israel conference
EWB israel conferenceHanan E. Levy
 
Lag baomer after AMS measuremetns 2009
Lag baomer after AMS measuremetns 2009Lag baomer after AMS measuremetns 2009
Lag baomer after AMS measuremetns 2009Hanan E. Levy
 
הזמנה לכנס חברים ינואר 2012
הזמנה לכנס חברים ינואר 2012הזמנה לכנס חברים ינואר 2012
הזמנה לכנס חברים ינואר 2012Hanan E. Levy
 
מחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניון
מחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניוןמחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניון
מחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניוןHanan E. Levy
 
הקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשות
הקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשותהקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשות
הקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשותHanan E. Levy
 
הקמת צוות התנדבותי להקמת טורבינת רוח קהילתית
הקמת צוות התנדבותי להקמת טורבינת רוח קהילתיתהקמת צוות התנדבותי להקמת טורבינת רוח קהילתית
הקמת צוות התנדבותי להקמת טורבינת רוח קהילתיתHanan E. Levy
 
3 endurance 3120-brochure
3 endurance 3120-brochure3 endurance 3120-brochure
3 endurance 3120-brochureHanan E. Levy
 
2b wind turbine_sizes_small_medium
2b wind turbine_sizes_small_medium2b wind turbine_sizes_small_medium
2b wind turbine_sizes_small_mediumHanan E. Levy
 
2a wind turbine_sizes_big
2a wind turbine_sizes_big2a wind turbine_sizes_big
2a wind turbine_sizes_bigHanan E. Levy
 
4 endurance sound_levels
4 endurance sound_levels4 endurance sound_levels
4 endurance sound_levelsHanan E. Levy
 
5 endurance installation_pictures
5 endurance installation_pictures5 endurance installation_pictures
5 endurance installation_picturesHanan E. Levy
 
6 endurance economic_numbers
6 endurance economic_numbers6 endurance economic_numbers
6 endurance economic_numbersHanan E. Levy
 
1 israel wind_potential
1 israel wind_potential1 israel wind_potential
1 israel wind_potentialHanan E. Levy
 
הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"
הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"
הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"Hanan E. Levy
 
הודעה על יציאה לדרך ספטמבר 2011
הודעה על יציאה לדרך ספטמבר 2011הודעה על יציאה לדרך ספטמבר 2011
הודעה על יציאה לדרך ספטמבר 2011Hanan E. Levy
 
פרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBY
פרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBYפרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBY
פרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBYHanan E. Levy
 
טורבינות רוח מסמך מדיניות לדיון 10.7.11
טורבינות רוח   מסמך מדיניות לדיון 10.7.11טורבינות רוח   מסמך מדיניות לדיון 10.7.11
טורבינות רוח מסמך מדיניות לדיון 10.7.11Hanan E. Levy
 
שאלות ותשובות - טורבינות רוח קטנות
שאלות ותשובות - טורבינות רוח קטנותשאלות ותשובות - טורבינות רוח קטנות
שאלות ותשובות - טורבינות רוח קטנותHanan E. Levy
 

Mais de Hanan E. Levy (20)

Piggott turbine design_code_dakar_presentation
Piggott turbine design_code_dakar_presentationPiggott turbine design_code_dakar_presentation
Piggott turbine design_code_dakar_presentation
 
Wind power siting_and_environmental_issues_newman
Wind power siting_and_environmental_issues_newmanWind power siting_and_environmental_issues_newman
Wind power siting_and_environmental_issues_newman
 
EWB israel conference
EWB israel conferenceEWB israel conference
EWB israel conference
 
Lag baomer after AMS measuremetns 2009
Lag baomer after AMS measuremetns 2009Lag baomer after AMS measuremetns 2009
Lag baomer after AMS measuremetns 2009
 
הזמנה לכנס חברים ינואר 2012
הזמנה לכנס חברים ינואר 2012הזמנה לכנס חברים ינואר 2012
הזמנה לכנס חברים ינואר 2012
 
מחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניון
מחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניוןמחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניון
מחזור קירור - מתוך תרגול בתרמודינמיקה לסטודנטים בטכניון
 
הקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשות
הקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשותהקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשות
הקמת טורבינת רוח קהילתית - הקואופרטיב לאנרגיות מתחדשות
 
הקמת צוות התנדבותי להקמת טורבינת רוח קהילתית
הקמת צוות התנדבותי להקמת טורבינת רוח קהילתיתהקמת צוות התנדבותי להקמת טורבינת רוח קהילתית
הקמת צוות התנדבותי להקמת טורבינת רוח קהילתית
 
3 endurance 3120-brochure
3 endurance 3120-brochure3 endurance 3120-brochure
3 endurance 3120-brochure
 
2b wind turbine_sizes_small_medium
2b wind turbine_sizes_small_medium2b wind turbine_sizes_small_medium
2b wind turbine_sizes_small_medium
 
2a wind turbine_sizes_big
2a wind turbine_sizes_big2a wind turbine_sizes_big
2a wind turbine_sizes_big
 
4 endurance sound_levels
4 endurance sound_levels4 endurance sound_levels
4 endurance sound_levels
 
5 endurance installation_pictures
5 endurance installation_pictures5 endurance installation_pictures
5 endurance installation_pictures
 
6 endurance economic_numbers
6 endurance economic_numbers6 endurance economic_numbers
6 endurance economic_numbers
 
1 israel wind_potential
1 israel wind_potential1 israel wind_potential
1 israel wind_potential
 
הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"
הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"
הצעת מחקר לדוקטורט - "חקירת תפוקת האנרגיה של טורבינות רוח המוצבות באזור הררי"
 
הודעה על יציאה לדרך ספטמבר 2011
הודעה על יציאה לדרך ספטמבר 2011הודעה על יציאה לדרך ספטמבר 2011
הודעה על יציאה לדרך ספטמבר 2011
 
פרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBY
פרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBYפרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBY
פרויקט אנרגיית רוח באיטליה - בבקשה אצלי בחצר - PIMBY
 
טורבינות רוח מסמך מדיניות לדיון 10.7.11
טורבינות רוח   מסמך מדיניות לדיון 10.7.11טורבינות רוח   מסמך מדיניות לדיון 10.7.11
טורבינות רוח מסמך מדיניות לדיון 10.7.11
 
שאלות ותשובות - טורבינות רוח קטנות
שאלות ותשובות - טורבינות רוח קטנותשאלות ותשובות - טורבינות רוח קטנות
שאלות ותשובות - טורבינות רוח קטנות
 

Último

Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 

Último (20)

Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 

Small wind power for rural locations - part 2

  • 1. Wind energy harvesting basics, resource assessment and application for off grid systems. part 2 Hanan Einav-Levy M.Sc. Thursday, November 10, 2011
  • 3. Outline • part II (2 hours) Thursday, November 10, 2011
  • 4. Outline • part II (2 hours) • Example project Thursday, November 10, 2011
  • 5. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) Thursday, November 10, 2011
  • 6. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) Thursday, November 10, 2011
  • 7. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) Thursday, November 10, 2011
  • 8. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) Thursday, November 10, 2011
  • 9. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) Thursday, November 10, 2011
  • 10. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) Thursday, November 10, 2011
  • 11. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) Thursday, November 10, 2011
  • 12. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) • Small wind turbine product comparison (10) Thursday, November 10, 2011
  • 13. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) • Small wind turbine product comparison (10) • Case studies Thursday, November 10, 2011
  • 14. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) • Small wind turbine product comparison (10) • Case studies • Practical action - Peru (10) Thursday, November 10, 2011
  • 15. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) • Small wind turbine product comparison (10) • Case studies • Practical action - Peru (10) • AWP - Zimbabwe (10) Thursday, November 10, 2011
  • 16. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) • Small wind turbine product comparison (10) • Case studies • Practical action - Peru (10) • AWP - Zimbabwe (10) • WindAid - Peru (10) Thursday, November 10, 2011
  • 17. Outline • part II (2 hours) • Example project • Estimating the wind resource (5) • Estimating the needs (10) • Sizing the turbine (5) • AC or DC (5) • Sizing the battery bank (10) • Sizing the inverter (5) • Economics (10) • Small wind turbine product comparison (10) • Case studies • Practical action - Peru (10) • AWP - Zimbabwe (10) • WindAid - Peru (10) • CometME - Israel / Palestinian authority (10) Thursday, November 10, 2011
  • 18. Resource: ITDG_2001_bookletwind.pdf Example project Thursday, November 10, 2011
  • 19. Small wind development by technology transfer Thursday, November 10, 2011
  • 20. Small wind development by technology transfer • ITDG (now called Practical Action) Thursday, November 10, 2011
  • 21. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. Thursday, November 10, 2011
  • 22. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system Thursday, November 10, 2011
  • 23. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system • Estimating the wind resource Thursday, November 10, 2011
  • 24. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system • Estimating the wind resource • Estimating the needs Thursday, November 10, 2011
  • 25. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system • Estimating the wind resource • Estimating the needs • Sizing the turbine Thursday, November 10, 2011
  • 26. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system • Estimating the wind resource • Estimating the needs • Sizing the turbine • AC or DC Thursday, November 10, 2011
  • 27. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system • Estimating the wind resource • Estimating the needs • Sizing the turbine • AC or DC • Sizing the battery bank Thursday, November 10, 2011
  • 28. Small wind development by technology transfer • ITDG (now called Practical Action) • One method to develop wind turbines for rural communities - there are others. • We will use this to study the design of the system • Estimating the wind resource • Estimating the needs • Sizing the turbine • AC or DC • Sizing the battery bank • Sizing the inverter Thursday, November 10, 2011
  • 29. Current situation • 12V Car batteries are used for radios and TVs • 60Ah or 90Ah battery typically used • A large market for existing battery users (300,000 households) • Monthly battery cost 6.5$ (5$ battery replacement, 1$ travel, 0.5$ charging) Thursday, November 10, 2011
  • 30. Estimating the wind • Anecdotal evidence • The local vegetation • The Beaufort scale • Wind map • Installing an anemometer+data logging equipment - 200-1000$ • Installing a wind turbine with data logging equipment with the same funds Thursday, November 10, 2011
  • 32. Siting the wind turbine • The highest point • Open to prevailing winds • Not too far from load • On a tall tower! Thursday, November 10, 2011
  • 33. Siting the Highest point wind turbine • The highest point • Open to prevailing winds • Not too far from load • On a tall tower! Thursday, November 10, 2011
  • 34. Siting the Highest Too far from loads point wind turbine • The highest point • Open to prevailing winds • Not too far from load • On a tall tower! Thursday, November 10, 2011
  • 35. Choosing AC vs. DC • For a wind turbine installed far from the load normally the battery voltage will be as high as possible (48V) • If not enough - using an DC-AC inverter at the tower makes sense • Allows to work at 230 volts, and therefor less current • Losses are proportional to the current squared • Benefit: Allows to work with regular 230V AC loads Thursday, November 10, 2011
  • 36. Choosing AC vs. DC • But cost of DC-AC inverter can be substantial • Alternative - site wind turbine close to load • Shorter cables - less loss • Downside: only DC loads Thursday, November 10, 2011
  • 37. Conservative estimate of monthly electricity production • Assuming efficiency is 15% (see previous lecture for more refined estimate by Paul Gipe) D × V ⎡ kWh ⎤2 3 • E= 10 ⎢ month ⎥ ⎣ ⎦ V = average wind speed [m/s] D = diameter [m] Thursday, November 10, 2011
  • 38. Estimating the loads • What the wind shouldn’t power: • Electric heaters • Electric cookers • For whom will the system be designed? • Single household • Several households Thursday, November 10, 2011
  • 40. Single household Rule of thumb - battery charging losses Thursday, November 10, 2011
  • 41. Breaking down the load for a typical day Thursday, November 10, 2011
  • 42. 3 households sharing a turbine Thursday, November 10, 2011
  • 43. 3 households sharing a turbine Thursday, November 10, 2011
  • 44. 3 households sharing a turbine Thursday, November 10, 2011
  • 45. 3 households sharing a turbine Thursday, November 10, 2011
  • 46. Sizing the turbine In an ideal world - 1. Identify wind resource 2. Identify electricity needs 3. Size turbine accordingly 4. Size battery bank according to measured wind pattern Thursday, November 10, 2011
  • 47. Sizing the turbine for our two examples Thursday, November 10, 2011
  • 48. Sizing the turbine for our two examples Enough spare energy Thursday, November 10, 2011
  • 49. Sizing the turbine for our two examples Not enough energy Thursday, November 10, 2011
  • 50. Sizing the battery • The battery is charged and discharged over a period of hours or days. • This is a cycle • Two parameters important in a battery life: • Number of cycles • The depth of discharge Thursday, November 10, 2011
  • 51. Sizing the battery Thursday, November 10, 2011
  • 52. Sizing the battery Thursday, November 10, 2011
  • 53. Sizing the battery Thursday, November 10, 2011
  • 54. Sizing the Battery • Calculate Ep, the daily consumption in Wh (for example Ep = 400 Wh/day) • Choose N, number of days of autonomy, typically 3-5 days (for example N = 3 days) • Choose maximum allowable depth of discharge, D (for example D = 0.5, which means 50%) • Choose U, battery voltage (typically 12,24 or 48 volts) (for example U = 12V) Thursday, November 10, 2011
  • 55. Sizing the Battery Calculate C, battery capacity: • Calculate Ep, the daily consumption in Ep × N Wh C= [Ah] (for example Ep = 400 Wh/day) D ×U 400 × 3 • Choose N, number of days of autonomy, = = 200[Ah] typically 3-5 days (for example N = 3 days) 0.5 × 12 • Choose maximum allowable depth of discharge, D (for example D = 0.5, which means 50%) • Choose U, battery voltage (typically 12,24 or 48 volts) (for example U = 12V) Thursday, November 10, 2011
  • 56. Cost of wind turbine - 2 meter diameter, 100 watt rated Thursday, November 10, 2011
  • 57. Economics • Financing ownership by battery charging services • Current batteries are 60 Ah car batteries (DOD 50%) • To charge battery (with efficiency of charging loss of 25%) 0.5X60X12X1.25 = 450 Wh • 2 meter diameter at 3.5 m/s site produces 17 kWh/ month or 600 Wh/day on average • Therefor one battery charged per day • charging 1 day a week for the owner, and the rest for customers Thursday, November 10, 2011
  • 60. Final system components Sizing according to local need and wind resource Thursday, November 10, 2011
  • 62. Final system components Sizing according to wind variability and “spares” requirement Thursday, November 10, 2011
  • 64. Final system components For an AC system - according to maximum load Thursday, November 10, 2011
  • 66. Small wind turbine market Thursday, November 10, 2011
  • 67. WT brochure Proven WT6000 6kW Wind Turbine Proven TM900 9m (or TM1500 15m) Self-Supporting Mast            Performance Cut-In Wind Speed 2.5 metres/second (5.6 mph) Cut-Out Wind Speed none Rated Wind Speed 12 metres/second (25 mph) Rotor • Type Down-wind, Self-Regulating Includes many details Number of Blades 3, Flexible Rotor Diameter 5.6 metres Blade Material Wood/Epoxy/PU Generator Type Brushless, Direct Drive, • Permanent Magnet Most important parameter - (No Gear-Box, Zero Maintenance) Output 48V/120V/240V/300V 3-phase AC 7000 (25Hz nom) 6000 Rated RPM 200 nominal diameter, or swept area 5000 Rated Power 6000 Watts Power Output (Watts) 4000 3000 Annual Output 7000-18 000 kWh depending on site 2000 1000 TM900 Mast 0 Type Self supporting/Tilt Down. Hub Height 9m • 0 5 10 15 20 Wind speed in m etres/second (m ultiply by 2.2 for m .p.h.) Foundations 35 Newton Concrete Pad 2.5 x 2.5 x 1 m Make sure is intended for Rotor Speed Control Tube ∅ 175 mm top A/F 350 mm bottom A/F 530 mm square mast base battery charging Above 12m/s (25mph) the blade TM1500 Mast pitch is automatically adjusted to Type Self supporting/Tilt Down. maintain 200 rpm and full output Hub Height 15m Foundations 35 Newton Concrete Pad 3 x 3 x 1.2 m High Build Quality Tube ∅ 200 mm top A/F All components are hot-dipped 440 mm bottom A/F • galvanised steel, stainless steel or 750 mm x 739mm mast base plastic. Must have aerodynamic Low Speed Equals Durability Low rotor speed (half the speed of Noise <45dB <60dB (approximate) At 5m/s At 20m/s control option comparable machines) ensures 70-80dB Car 15m away at approx 40 mph. extended durability of blades and bearings. It also means that Weight Proven WTs are the quietest in the world! WT6000 500 kg TM900/6000 360 kg (+ 70kg gin pole) TM1500/6000 656 kg (+ 240kg gin pole) z : a l l wi n d t u r b s a l e s l i t m a n u a l w t 6 0 0 0 s s s p e c s h ee t s 6 0 0 0 s s 0 0 1 r e v 2 . d o c Thursday, November 10, 2011
  • 68. Small wind turbine market Thursday, November 10, 2011
  • 69. Source - American magazine. 2 mph = 1 m/s Small wind turbine market Thursday, November 10, 2011
  • 70. Small wind turbine market Thursday, November 10, 2011
  • 71. Most important parameter Small wind turbine market Thursday, November 10, 2011
  • 72. Small wind turbine market Thursday, November 10, 2011
  • 82. small wind: 0.2$-1.15$ / kWh solar PV: 1.21$ / kWh Thursday, November 10, 2011
  • 83. African Wind Power Thursday, November 10, 2011
  • 84. Example of technology transfer African Wind Power Thursday, November 10, 2011
  • 85. Example of technology transfer • Turbines now installed from Africa to Antarctica! African Wind Power Thursday, November 10, 2011
  • 86. AWP - Zimbabwe - Masampa Village Lake Kariba • AWP3.6 - 48V 13.5M tilt up tower, 275Ahr 48V Battery bank, 3KW sine wave inverter, 12V battery charging station. Thursday, November 10, 2011
  • 87. AWP - Zimbabwe - Masampa Village Lake Kariba • AWP3.6 - 48V 13.5M tilt up tower, 275Ahr 48V Battery bank, 3KW sine wave inverter, 12V battery charging station. • This fishing co-operative village is on the shores of Lake Kariba, 45Km by boat from the nearest town. Crocodiles inhabit the shore line and Hippos amble through the village at night while foraging ( startling a hippo is not good for your health). With funds provided by the Dutch government via the NGO ZERO, AWP implemented the entire project in all its stages: • (1) Initial location of the people in need • (2) discussions with the village committee • (3) resulting in motivation of the villagers to contribute labour to the installation, transportation of all materials to site, construction and commissioning • (4) and finally training of operators. • The system provides lighting for the main thoroughfares and also a popular 12v car battery charging center which draws customers from a 20 Km radius. Income from this activity is used for village development. Thursday, November 10, 2011
  • 88. WindAid - Peru Thursday, November 10, 2011
  • 106. Comet-ME • The systems are designed for producing 2-3 kWh/ day for a large beduin family. • Systems are DIY wind turbines and solar PV panels • Systems used for powering: • Lights • Refrigirator • Butter churn • TV • Cellphone charging • Costs are between 5000$-8000$ Thursday, November 10, 2011