SlideShare uma empresa Scribd logo
1 de 2
Baixar para ler offline
 
Figure 1. Direct Push Injection of ORC Advanced® 
 
 
Remedial works at the Former Lama Petroleum site were undertaken in late 2008 as part of the ongoing 
redevelopment of the Fresh Wharf Estate in Barking. The site was to be developed for light industrial use, 
however, historical oil mixing handling and storage activities performed on the site had resulted in TPH and 
PAH contamination in the groundwater. 
Site investigation works suggested the presence of 
an  approximately  1,000m2
  source  area  in  the 
northwestern  portion  of  the  site,  as  well  as  a 
downgradient plume area, estimated to be in the 
region  of  6,000m2
  extending  toward  the 
Handtrough Creek.  Phase separated hydrocarbons 
were  detected  in  the  source  area  where  the 
former  above  ground  storage  tanks  had  been 
located  prior  to  decommissioning  circa  2003.  In 
the  down  gradient  plume  area  the  maximum 
dissolved phase TPH concentration was 1,100μg/L 
(Monitoring Well BH102) adjacent to Handtrough 
Creek. 
 
Remedial Strategy 
The remedial objective was to reduce dissolved phase concentrations of Total TPH and PAH in groundwater 
to the agreed remedial target level of 110μg/L, within 12 months of treatment. A trigger level for further 
remediation was set at 200μg/L, equating to an 80% contaminant concentration reduction within 42 weeks 
post  treatment.  If  the  trigger  TPH 
concentration  was  not  achieved  within  42 
weeks  after  treatment,  further  options  would 
be undertaken.   
The  original  assessment  of  remedial  options 
identified  that  a  combination  of  Pump  and 
Treat (P&T) to target free product in the source 
area    and  ORC  Advanced®  treatment  in  the 
groundwater plume would represent the most 
time‐efficient  and  cost‐effective  remedial 
solution  for  the  site.  However,  trial  pits 
advanced  in  the  source  area  during  site 
clearance works determined that free product 
was  not  present  in  the  groundwater,  but  was 
present  in  discrete  bands  within  the 
unsaturated  made  ground.  Following  this 
observation,  excavation  to  remove  the  most 
impacted  soils  in  the  source  area  was 
determined  to  be  the  most  suitable  approach 
and P&T was discarded as an option. 
 
 
Table 1. Subsurface Details 
Soil Type  Sand 
Depth to Groundwater  3m 
Treatment Area  7,000 m2
 
Treatment Thickness  3m 
Table 2. ORC Advanced Application Details 
Application Type  Direct Push 
Application Rate  
Zone 1 WS14 Hotspot 
17.01kg/m 
Zone 2 Source Treatment 
11.34kg/m 
Zone 3 Plume Treatment 
5.67kg/m 
TOTAL MATERIAL COST  £130,000 
TOTAL PROJECT COST  £220,000 
Rapid Reduction of Petroleum Hydrocarbons using 
ORC Advanced® allows for Redevelopment of Site
 
 
 
Soil removal works were undertaken at the site in October 2008. ORC Advanced treatment in both the source 
and plume areas was undertaken in October and November 2008. ORC Advanced was applied using three direct 
push  injection  rigs  and  a  separate  mixing  and  pumping  unit.  The  rods  were  driven  to  6mBGL  and  the  ORC 
Advanced was applied over the impacted saturated zone as the rods were slowly withdrawn to 3mBGL. The rigs 
completed a total of 813 injection points in 19 drilling days. The dose rates were varied to match the different 
contaminant concentrations and conditions encountered across the site (Tables 1 & 2). Vibro‐piling works were 
completed across the site at the same time as the ORC Advanced was being applied and were unimpeded by the 
direct push rigs. 
Results 
Following the injection of ORC Advanced, a slight increase in the dissolved phase contaminant concentrations 
was observed due to the site disturbance from injection and piling works. Both TPH and PAH concentrations 
then rapidly decreased to below the site specific remedial target values and remained low over the monitoring 
programme.  A  99%  reduction  in  the  groundwater  concentrations  of  TPH  and  PAH  was  achieved  with  no 
rebound.  Monitoring  results  are  presented  below  for  well  BH102,  which  was  located  on  the  southern  site 
boundary, adjacent to Handtrough Creek.  
Table 3: Concentrations overtime at location BH102 
Contaminant Oct 2007 
(Baseline) 
ORC Advanced 
Injection (Oct 2008) 
Dec 2008  Mar 2009 April 2009 May 2009 Aug 2009  Dec 2009  % Reduction 
Total TPH 
(μg/L) 
1,100  1,600  <10  <10  <10  <10  <10  99% 
Total PAH 
(μg/L) 
230  290  5.9  0.23  0.18  <0.1  <0.1  99% 
 
Conclusion 
Following the application of ORC Advanced, TPH and PAH concentrations were rapidly reduced and maintained 
below  the  site  specific  target  values  without  contaminant  rebound.  The  works  were  completed  safely  and 
efficiently and did not hinder the ongoing construction works occurring simultaneously at the site. The low final 
contaminant concentrations and the lack of rebound resulted in regulatory acceptance of the remediation and 
development works were completed. 
 
Jacobs 
Paul Adams 
+44 (0)118 963 5071  
Paul.Adams@jacobs.com 
www.jacobs.com 
 
Regenesis  Ltd 
Gareth Leonard 
+44 (0) 1833 630411 
gleonard@regenesis.com 
www.regenesis.com 

Mais conteúdo relacionado

Destaque

P&amp;T RegenOx ORC Adv in Herts UK
P&amp;T RegenOx ORC Adv in Herts UKP&amp;T RegenOx ORC Adv in Herts UK
P&amp;T RegenOx ORC Adv in Herts UKgleonard35
 
3 D Me Wsp Sweden SöDerkaj Halmstad
3 D Me Wsp Sweden SöDerkaj Halmstad3 D Me Wsp Sweden SöDerkaj Halmstad
3 D Me Wsp Sweden SöDerkaj Halmstadgleonard35
 
When I Need Help With...
When I Need Help With...When I Need Help With...
When I Need Help With...ConnieWilliams
 
2009 Artof Pissarro2 Text
2009 Artof Pissarro2 Text2009 Artof Pissarro2 Text
2009 Artof Pissarro2 TextMyrna Teck
 
Study: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving CarsStudy: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving CarsLinkedIn
 

Destaque (7)

P&amp;T RegenOx ORC Adv in Herts UK
P&amp;T RegenOx ORC Adv in Herts UKP&amp;T RegenOx ORC Adv in Herts UK
P&amp;T RegenOx ORC Adv in Herts UK
 
3 D Me Wsp Sweden SöDerkaj Halmstad
3 D Me Wsp Sweden SöDerkaj Halmstad3 D Me Wsp Sweden SöDerkaj Halmstad
3 D Me Wsp Sweden SöDerkaj Halmstad
 
When I Need Help With...
When I Need Help With...When I Need Help With...
When I Need Help With...
 
O'Hare Boosters
O'Hare BoostersO'Hare Boosters
O'Hare Boosters
 
Trust
TrustTrust
Trust
 
2009 Artof Pissarro2 Text
2009 Artof Pissarro2 Text2009 Artof Pissarro2 Text
2009 Artof Pissarro2 Text
 
Study: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving CarsStudy: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving Cars
 

Rapid Reduction of Petroleum Using ORC Advanced

  • 1.   Figure 1. Direct Push Injection of ORC Advanced®      Remedial works at the Former Lama Petroleum site were undertaken in late 2008 as part of the ongoing  redevelopment of the Fresh Wharf Estate in Barking. The site was to be developed for light industrial use,  however, historical oil mixing handling and storage activities performed on the site had resulted in TPH and  PAH contamination in the groundwater.  Site investigation works suggested the presence of  an  approximately  1,000m2   source  area  in  the  northwestern  portion  of  the  site,  as  well  as  a  downgradient plume area, estimated to be in the  region  of  6,000m2   extending  toward  the  Handtrough Creek.  Phase separated hydrocarbons  were  detected  in  the  source  area  where  the  former  above  ground  storage  tanks  had  been  located  prior  to  decommissioning  circa  2003.  In  the  down  gradient  plume  area  the  maximum  dissolved phase TPH concentration was 1,100μg/L  (Monitoring Well BH102) adjacent to Handtrough  Creek.    Remedial Strategy  The remedial objective was to reduce dissolved phase concentrations of Total TPH and PAH in groundwater  to the agreed remedial target level of 110μg/L, within 12 months of treatment. A trigger level for further  remediation was set at 200μg/L, equating to an 80% contaminant concentration reduction within 42 weeks  post  treatment.  If  the  trigger  TPH  concentration  was  not  achieved  within  42  weeks  after  treatment,  further  options  would  be undertaken.    The  original  assessment  of  remedial  options  identified  that  a  combination  of  Pump  and  Treat (P&T) to target free product in the source  area    and  ORC  Advanced®  treatment  in  the  groundwater plume would represent the most  time‐efficient  and  cost‐effective  remedial  solution  for  the  site.  However,  trial  pits  advanced  in  the  source  area  during  site  clearance works determined that free product  was  not  present  in  the  groundwater,  but  was  present  in  discrete  bands  within  the  unsaturated  made  ground.  Following  this  observation,  excavation  to  remove  the  most  impacted  soils  in  the  source  area  was  determined  to  be  the  most  suitable  approach  and P&T was discarded as an option.      Table 1. Subsurface Details  Soil Type  Sand  Depth to Groundwater  3m  Treatment Area  7,000 m2   Treatment Thickness  3m  Table 2. ORC Advanced Application Details  Application Type  Direct Push  Application Rate   Zone 1 WS14 Hotspot  17.01kg/m  Zone 2 Source Treatment  11.34kg/m  Zone 3 Plume Treatment  5.67kg/m  TOTAL MATERIAL COST  £130,000  TOTAL PROJECT COST  £220,000  Rapid Reduction of Petroleum Hydrocarbons using  ORC Advanced® allows for Redevelopment of Site
  • 2.       Soil removal works were undertaken at the site in October 2008. ORC Advanced treatment in both the source  and plume areas was undertaken in October and November 2008. ORC Advanced was applied using three direct  push  injection  rigs  and  a  separate  mixing  and  pumping  unit.  The  rods  were  driven  to  6mBGL  and  the  ORC  Advanced was applied over the impacted saturated zone as the rods were slowly withdrawn to 3mBGL. The rigs  completed a total of 813 injection points in 19 drilling days. The dose rates were varied to match the different  contaminant concentrations and conditions encountered across the site (Tables 1 & 2). Vibro‐piling works were  completed across the site at the same time as the ORC Advanced was being applied and were unimpeded by the  direct push rigs.  Results  Following the injection of ORC Advanced, a slight increase in the dissolved phase contaminant concentrations  was observed due to the site disturbance from injection and piling works. Both TPH and PAH concentrations  then rapidly decreased to below the site specific remedial target values and remained low over the monitoring  programme.  A  99%  reduction  in  the  groundwater  concentrations  of  TPH  and  PAH  was  achieved  with  no  rebound.  Monitoring  results  are  presented  below  for  well  BH102,  which  was  located  on  the  southern  site  boundary, adjacent to Handtrough Creek.   Table 3: Concentrations overtime at location BH102  Contaminant Oct 2007  (Baseline)  ORC Advanced  Injection (Oct 2008)  Dec 2008  Mar 2009 April 2009 May 2009 Aug 2009  Dec 2009  % Reduction  Total TPH  (μg/L)  1,100  1,600  <10  <10  <10  <10  <10  99%  Total PAH  (μg/L)  230  290  5.9  0.23  0.18  <0.1  <0.1  99%    Conclusion  Following the application of ORC Advanced, TPH and PAH concentrations were rapidly reduced and maintained  below  the  site  specific  target  values  without  contaminant  rebound.  The  works  were  completed  safely  and  efficiently and did not hinder the ongoing construction works occurring simultaneously at the site. The low final  contaminant concentrations and the lack of rebound resulted in regulatory acceptance of the remediation and  development works were completed.    Jacobs  Paul Adams  +44 (0)118 963 5071   Paul.Adams@jacobs.com  www.jacobs.com    Regenesis  Ltd  Gareth Leonard  +44 (0) 1833 630411  gleonard@regenesis.com  www.regenesis.com