A Credible PMB is the window to
Program Performance
1
Risk
SOW
Cost
WBS
IMP/IMS
TPM
PMB
❺ Deliverables
defined in the SOW,
traced to the WBS,
with narratives and
Measures of
Performance (MoP)
❹ BCWS at the Work
Package, rolled to the
Control Accounts
showing cost spreads for
all work in the IMS
❻ Measures of
Performance (MoP) for
each critical deliverable in
the WBS and identified in
each Work Package in the
IMS, used to assess
maturity in the IMP
❶ The Products and
Processes in a “well
structured” decomposition
traceable to the deliverables
❷ IMS contains all
the Work Packages,
BCWS, Risk mitigation
plans, with traces to
the IMP measuring
increasing maturity
through Measures of
Effectiveness (MoE)
and JROC KPP’s
❸ Technical and Programmatic
Risks Connected through the
WBS, IMP, and IMS
The PMB is the Document
of Record for the Program
Performance is Measured
through the PMB
1.0 Introduction

Mais conteúdo relacionado

Mais procurados

Agile evm earned value management in scrum projects
Agile evm   earned value management in scrum projectsAgile evm   earned value management in scrum projects
Agile evm earned value management in scrum projects
JULIO GONZALEZ SANZ
 

Mais procurados (20)

Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Integrated Master Plan / Integrated Master Schedule (IMP/IMS)
Integrated Master Plan / Integrated Master Schedule (IMP/IMS)Integrated Master Plan / Integrated Master Schedule (IMP/IMS)
Integrated Master Plan / Integrated Master Schedule (IMP/IMS)
 
CMMI and Agile
CMMI and AgileCMMI and Agile
CMMI and Agile
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Agile evm earned value management in scrum projects
Agile evm   earned value management in scrum projectsAgile evm   earned value management in scrum projects
Agile evm earned value management in scrum projects
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Glen alleman agile 04 ev+agile=success
Glen alleman agile 04 ev+agile=successGlen alleman agile 04 ev+agile=success
Glen alleman agile 04 ev+agile=success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
IMP as the Definition of Done
IMP as the Definition of DoneIMP as the Definition of Done
IMP as the Definition of Done
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
Lifecycle
LifecycleLifecycle
Lifecycle
 
IMP IMS overview
IMP IMS overviewIMP IMS overview
IMP IMS overview
 
Integrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program successIntegrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program success
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
 
WBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsWBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP Projects
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 

Destaque

Vision goal csf kpi
Vision goal csf kpiVision goal csf kpi
Vision goal csf kpi
Glen Alleman
 

Destaque (13)

Social network analysis for modeling & tuning social media website
Social network analysis for modeling & tuning social media websiteSocial network analysis for modeling & tuning social media website
Social network analysis for modeling & tuning social media website
 
MOE MOP TPM KPP
MOE MOP TPM KPPMOE MOP TPM KPP
MOE MOP TPM KPP
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance Measures
 
Hockey Kit for Android
Hockey Kit for AndroidHockey Kit for Android
Hockey Kit for Android
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connections
 
Cpm 200 c technical performance measures - alleman (ppm)
Cpm 200 c   technical performance measures - alleman (ppm)Cpm 200 c   technical performance measures - alleman (ppm)
Cpm 200 c technical performance measures - alleman (ppm)
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Vision goal csf kpi
Vision goal csf kpiVision goal csf kpi
Vision goal csf kpi
 
Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project management
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
 
Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business value
 

Semelhante a A credible pmb is the window to program

Semelhante a A credible pmb is the window to program (20)

Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
DPPM1
DPPM1DPPM1
DPPM1
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = Success
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
EVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresEVMS with Technical Performance Measures
EVMS with Technical Performance Measures
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance Measures
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
SE-Lecture-5.pptx
SE-Lecture-5.pptxSE-Lecture-5.pptx
SE-Lecture-5.pptx
 

Mais de Glen Alleman

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 

A credible pmb is the window to program

  • 1. A Credible PMB is the window to Program Performance 1 Risk SOW Cost WBS IMP/IMS TPM PMB ❺ Deliverables defined in the SOW, traced to the WBS, with narratives and Measures of Performance (MoP) ❹ BCWS at the Work Package, rolled to the Control Accounts showing cost spreads for all work in the IMS ❻ Measures of Performance (MoP) for each critical deliverable in the WBS and identified in each Work Package in the IMS, used to assess maturity in the IMP ❶ The Products and Processes in a “well structured” decomposition traceable to the deliverables ❷ IMS contains all the Work Packages, BCWS, Risk mitigation plans, with traces to the IMP measuring increasing maturity through Measures of Effectiveness (MoE) and JROC KPP’s ❸ Technical and Programmatic Risks Connected through the WBS, IMP, and IMS The PMB is the Document of Record for the Program Performance is Measured through the PMB 1.0 Introduction