5 Immutable Principles of Project Success
Thank you for inviting me here today.
The topic should be one we all are
familiar with, since it is nearly impossible
to not have experienced a project failure
at least once in our career.
The principles I’m going to speak to you
about are universal. Applicable to any
project, of any size, in any domain.
The example project was one I was
involved with as a Program Manager. One
that was manifestly important, and nearly
impossible. One that shaped how I see
the principles, practices, and processes of
managing projects in ways I had not
considered before.
What you’re going to hear is not the
solution to project failure. It is the
framework for that solution. The actual
mechanics of managing a project are
based on these principles. The practices
used in this management should be
based on the se principles. And of course
the process ad tools should implement
the practices.
I’d like to present the 5 Immutable
Principles of project success using
examples from a program I was a
participant in. Rocky Flats Environmental
Technology Site, in Golden Colorado.

Page 1

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Let’s start with positioning our interest in
the project domain.
Nearly every business activity is based on
a project in some way. Even the
operational aspects of a business are
projectized through processes,
procedures, and business management.
Today I’d like to focus that types of
projects Land speaks of. The really
important ones that are nearly
impossible.
I was a participant in one of those
projects – Rocky Flats Environmental
Technology Site. The name of the site was
a nice marketing term for the cleanup of
a nuclear bomb factory.
It was nearly impossible. The previous
contractor had spent $4B and not done
much.
When Kaiser-Hill (a joint venture between
ICF Kaiser and CH2MHill) won the
contract, they had a plan that was
dramatically different from the past
attempts to cleanup and close the site.

Page 2

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Rocky Flats was a U.S. Department of
Energy National Nuclear Security Agency
production site that operated from 1952
to 1992.
Rocky Flats was the most contaminated
nuclear weapons plant in the country,
was an environmental disaster and the
site of rampant worker unrest.
Estimates projected that cleaning up and
closing the facility would take 70 years
and $36 Billion. The actual project was
completed in 10 years for $6B.

Page 3

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

For projects where success is mandatory,
the outcome critical to the business, and
risks are high, success comes about
through principles, practices, and
processes.

I’m going to try and convince you today
that the 5 Immutable Principles are the
foundation of any projects success.
These Principles are “Immutable”
because they must always be present.
They are the foundation on which the
Practices and Processes are built.
We won’t look at the Practices and
Processes, but they are critical to the
success of any project as well.

Page 4

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

After the Rocky Flats project had completed,
the book Making the Impossible Possible was
written about the lessons learned from the
cleanup. This book examines the cleanup
and closure of 800 buildings with 3 million
square feet under roof, on a 6,000 acre site
with many tons of hazardous materials just
10 miles from Denver’s suburban
population.
Success is explained in the book through the
model of Positive Deviance or Heliotropic
Abundance. The theoretical framework of
Competing Values (shown here) is the basis
of the book.
The 5 Immutable Principles of Project
Success are derived from my experiences as
a Program Manager at this site.
Two elements of the competing values
framework are the basis of this talk. Control
and Create. Both are needed for success.
Control alone limits creativity. Creativity
alone results in out of control work
activities.
Control provides stability measurement,
clarity of objectives, discipline, and detailed
planning.
Creativity enables agility in the presence of
constant change.

Page 5

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
Of the four quadrants of positive
Deviance we are interested in Control and
Create as the basis of the 5 Immutable
Principles of project success.
The focus is on clear and concise
descriptions of Done, while innovative
solutions to technical, programmatic, and
operational problems are needed at
every step along the way to Done.
We need both, but Control is the basis of
Create. Control is often criticized as
inhibiting or sabotaging performance.
Control emphasizes efficiency, smooth
functioning, predictability and
standardized procedures. It focuses on
tight control of internal activities. The
result is consistency and dependability in
contrast to innovation and dynamism.

The success of any project is still
grounded in extending beyond doing well
to doing spectacularly well, and
developing the mechanism that produces
extraordinary results.
This requires creativity, a clear and shared
vision of the future, symbolic leadership
(leaders doing the work as well),
innovative ideas about work, and creating
a sense of meaning and importance
attached to the tasks being pursued.

Page 6

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

With this background, let’s look at the 5
Immutable Principles of Project Success.
I would suggest these are applicable to
any technical domain. Any project
management method. Any business
domain. They are universal and
Immutable – meaning they don’t change
over time. They are permanent principles
that must be applied for the success of
any project.
The Principles are in the form of
questions in this example. There are more
formal statements about the Principles,
but starting by asking 5 questions shows
how the principles can be applied in any
situation.
When there is not a credible answer to
the question, this is an indication there is
likely trouble on the project and the
probability of success has been lowered.

In the next charts there will be the
questions – numbered 1 through 5. Then
there are 3 answers. Starting with the
simplest answer – Number 1 – through
the best answer – Number 3.
It is the Number 3 answer that we are
after.
Being able to produce the answer in that
style may be difficult and require
Practices and Processes. But we have to
start with the Principles.
So let’s start.
Page 7

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

The first Principle is to ask if we know
what Done looks like. This sounds like a
simple question. But turns out to be the
root cause of most project failure.
Done must be described in meaningful
units of measure for the decision makers.
1. Our first response is usually to make a
list of features and functions for the
product of service produced by the
project. This is necessary but far from
sufficient to describe Done. We don’t
know how these features and
functions interact, how they provide
value to the customer.
2. The interdependencies are next. We
need to show how each feature or
function is dependent – if it is – on
other features and functions. This
usually starts with the Work
Breakdown Structure (WBS) showing
all the deliverables from the project.
The WBS needs a WBS Dictionary to
show how we are going to measure
the performance, quality, compliance
of these outcomes with each other
and the customer.
3. But the WBS and its Dictionary are
not enough to know what Done looks
like. We need to know what
Capabilities are being provided by the
project. What is the customer going
to DO with these outcomes? How are
they going to satisfy the business
needs or mission?
The Capability to do something is what
the customer bought.

Page 8

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
These Capability statements are clear and
concise. Long before we ever arrived in the
moon, Robert Goddard knew what
capabilities were needed to get there.
On October 19, 1899, Goddard climbed a
dead tree to trim some branches. He was 17.
He is quoted as saying … “I imagined,” he
later recalled, “how wonderful it would be to
make some device which had even
the possibility of ascending to Mars, and how
it would look on a small scale, if sent up from
the meadow at my feet. . . I was a different
boy when I descended the tree from when I
ascended, for existence at last seemed very
purposive.”
He had in his mind what capabilities were
needed to fly outside the Earths atmosphere.
He knew some of the units of measure that
had to be fulfilled to do this.
If we don’t have some vision of the project at
the Capabilities level, we really can’t say what
Done looks like. We can describe the
technical aspects, but we can’t say what we
are going to do with those technical aspects.
This definition of Capabilities is a Systems
Engineering role. There are formal processes
to elicit these Capabilities through the
Concept of Operations, Scenarios, and Use
Cases, making tradeoffs between cost, risk,
schedule, and technical performance, and
balancing all the feasible alternatives.
The result is the Measures of Effectiveness
which tell the customer the project will meet
the needed capabilities.

Page 9

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
With the needed Capabilities we can now
develop a plan and schedule for the work.
Knowing how to get Done on–budget and
on–schedule means knowing what
requirements will have to be fulfilled.
Poorly formed requirements contribute
as much as 25% to the failure modes of
programs and projects.
This starts with Fact Finding, Gathering
and Classifying the Requirements,
Evaluating and Rationalizing the
Requirements, Prioritizing them, and
Integrating and Validating the
Requirements.

With this in hand we can start building
the packages of work that implement the
requirements.
The result is a Plan and a Schedule. The
Plan is the Strategy for the proper
delivery of the Capabilities produced by
the project. The Schedule is the sequence
of work needed to implement the
Strategy. Both are needed.
The Plan is emergent, since it is a
strategy. The Schedule tests this strategy
on short term boundaries, with measures
of physical percent complete.
Both the Plan and the Schedule must be
capable of responding to change as new
information about requirements, program
performance, and risk emerge.
But the needed capabilities should
remain stable if we are to have a baseline
on which to execute our project.
Page 10

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

The Plan can be very simple or it can be
complex.
Here’s a plan that took us to the moon
and back. This picture shows a simple
concept. Build the launch vehicle,
develop the fuel to power it, the space
craft on the top, train the astronauts, do
the testing, and fly.
The Plan shows the 6 major systems ,
their approximate duration in years, and
the dependencies between them are all
that is needed to confirm the feasibility of
the project.
Notice the longest activity is the training
of the crew. No one had ever flown in
space before all the way to the moon and
back. So training was high risk and critical
to success.

Page 11

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

One view of the Plan is the vertical
integration of the deliverables.
This is the deliverables traceability view.
At the bottom is our deliverable.
The deliverable is produced by work
contained in a work package. A Work
Package says its name. it produces a
single outcome.
The technical capabilities needed for the
project’s success are produced by the
Work Packages.
Finally these Technical Capabilities
produce business or mission capabilities
needed by the customer for business
success.
This traceability is necessary for a
credible Plan and Schedule. It is also
necessary for a credible project delivery
process.
This traceability tells everyone what Done
looks like and how we are going to get
there.

Page 12

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
With the Plan in place and the “packages of
work” identified in the Schedule, we can
construct a picture of how we are going to
reach Done.
This picture is not like the typical horizontal
scheduling activities we see in all the
scheduling tools.
This picture starts with the vertical
integration of the deliverables as they
progress through their maturity life cycle.
This is called the Integrated Master Plan. This
Plan shows the Measures of Effectiveness and
Measures of Performance we need to achieve
to reach a specific level of maturity.

This notion of levels of maturity can be seen
is we use some words Preliminary is a work
description. We all know what preliminary
means. It means we’re not done yet. We
have a preliminary design we have a
preliminary cost estimate or a preliminary list
of subcontractors. We know enough about
the project to make some decisions, but we
need more details before we can say for sure
the cost, the design, and the subcontractors
are all in place.
This incremental approach allows us to move
foreword without all the details, while still
having visibility into what Done looks like.
Since RFETS was many times discovery driven,
planning had to be increasing maturity driven
without the planning horizon reaching the
final date. This incremental and iterative
approach is a critical success factor for all
projects.

Page 13

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Projects are executed by people.
People consume time, money, and
materials.
How can we know if we have enough of
everything we need for success?
We need a Plan of course, in this case a
Resource Management Plan, showing
people, funding, and materials, and when
and where we need it.
1. We can start with a simple list. This
gets us to write it down.
2. Next we need to assign people and
money to the needed resources. How
many of each special skill type will we
need for this project.
3. In the end though, we need to lay out
these needs against the schedule of
work. We need to resource load the
schedule. This sounds like a lot of
work and it is. But without this in
place we really have no idea if the
project is feasible.

Page 14

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Matching people to needs is at the heart
of resource management.
Without understanding what skills are
needed we can’t do this matching. This
information comes from the subject
matter experts that have defined the
“packages of work” and their
deliverables.

Page 15

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
We usually start by identifying risks. But
risk is the result of uncertainty. There are
two types of uncertainty – reducible
uncertainty and irreducible uncertainty.
We can do something about reducible
uncertainty. We can buy more knowledge
about this uncertainty – it is epistemic.
We can run tests, build prototypes, look
at what others have done. The risk that
results is reducible.
The irreducible uncertainty is part of the
world around us. This uncertainty cannot
be reduced – it is aleatory uncertainty.
The only way to deal with this uncertainty
is through margin. Cost margin, schedule
margin, technical margin.
1. We have to start by identifying these
uncertainties and associating them
with the risks.
2. Then the impacts of the risk are
identified along with their
dependencies.
3. The probability of occurrence and the
probability of their impact can be
assessed and once the reducible risks
are handled the residual uncertainty
and its resulting risk.
With these impediments in hand we can
take actions to either protect our project
with margin or spend money to retire or
handle the resulting risk.
Page 16

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
The resulting Risk Management Plan
becomes part of the Integrated Master
Plan.
Risk management is how adults manage
projects – Tim Lister.
We can manage the risk with either
margin or with specific risk reducing
actions. Either way, we must manage the
risk.
The discovery of uncertainty and the
resulting risk is a continuous work
process. It is repeated weekly, monthly,
quarterly, annually. It is never ending.
Risk drives variance and variance must be
managed actively as part of the project
management process.
The retirement of risk must be defined in
the planning documents. The reduction
from RED to YELLOW to GREEN must take
place as planned. If we miss the buy
down target we will have created more
risk, since the retired risk was not
removed as planned.
If we spend more money than planned to
retire the risk, we are over budget as
well. Retiring risk is a project work
activity funded on the baseline.
Management Reserve maybe used to
those “reducible” risks we have not yet
decided to retire.
Page 17

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
With our Plan, Schedule, Resources, and Risk
Management Plan, we can now determine
how we are going to measure progress to
these plans.
1. The customer bought outcomes,
deliverables, capabilities. We need to
describe these in a way the customer
understands. Units of measure that are
meaningful for making decisions.
2. These are best described as Technical
Performance Measures. These are
attributes that determine how well a
system or system element is satisfying or
expected to satisfy a technical
requirement or goal.

3. But these alone are not sufficient for the
success of the project. We need
Measures of Effectiveness (MoE),
Measures of Performance (MoP), and Key
Performance Parameters (KPP).
 MoEs are operational measures of
success that are closely related to the
achievements of the mission or
operational objectives evaluated in the
operational environment, under a
specific set of conditions. These are
“customer satisfaction” measures.
 MoPs characterize physical or
functional attributes relating to the
system operation, measured or
estimated under specific conditions.
 KPPs represent the capabilities and
characteristics so significant that
failure to meet them can be cause for
reevaluation, reassessing, or
termination of the program.

Page 18

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Measuring progress to plan means
measuring physical percent complete at a
fine grained level, where a 0% / 100%
assessments can be made.
You’re either done or your not done. No
in between. No vague assessment of
done.

This means the planning of the work
must identify tangible deliverables at that
level.
This may appear more difficult, but it
provides unassailable measures of
progress. No opinions. No almost done.
No “we’ll be done real soon.” Either
you’re done or not done.
This approach provides the foundation of
Earned Value at the Work Package level. It
makes measuring progress easy.
More importantly it provides the basis to
answer the question – How long are you
willing to wait before you find out you are
late?
With these fine grained measures of
progress to plan, the answer can be the
tangible evidence of progress.
Typically this evidence is produced every
two weeks. No longer than monthly.
But it has to be tangible.
In this picture the tangible evidence is
barrels of waste packaged, sealed, and
ready to leave the site.
Page 19

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

If we don’t have a plan. If we don’t have
the proper resources available at the
needed time. Of we don’t handle risks if
we don’t have measures of physical;
percent complete.
We can’t have confidence the project will
be successful.
Without these elements, the probability
of project success is reduced. Possibly to
the point of project failure.
Without these elements, we have created
risk to our success with no handling
plans.
It is this unmitigated risk that creates the
unanticipated growth in our Estimate At
Completion.

Page 20

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Over a large number of complex, high risk
programs there have been a small
number of root causes discovered for
project failure.
There are shown here.
Reading them they seem obvious.
Dealing with them is more difficult .
But we must deal with them and we must
have information needed to deal with
them.
This information comes from the
practices, processes, and tools used to
manage the project.
Scheduling, cost, risk, performance
measurement, and forecasting tools and
the processes used to apply them.
Only when all this information in
integrated though a single “lens” can we
have the needed visibility to take
corrective action to keep the project
GREEN.
Stay on schedule, stay on budget, comply
with the technical requirements. Or if
not, know about the variances soon
enough to take corrective action.

Page 21

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success
Let’s quickly review the 5 principles of
project success in the time remaining.
1. What does done look like? The
customer needs to know what
capabilities will be possessed when
the project is done. The capabilities
produce the business value or fulfill a
mission objective.
2. How do we get there? We need a
plan and a schedule. We need to
arrange the work properly in the
sequence to produce continuous
value.
3. Are there enough resources? People,
material, facilities? Are they the right
people, does the material arrive at
the needed time, are the facilities
adequate to produce the needed
outcomes?
4. What are the impediments to
progress? Risk management is how
adults manage projects. Do we have a
risk register? Do the risks have
handling plans? Is the cost and
schedule baseline adjusted for these
risks?
5. How do we measure progress? The
only way is tangible evidence of
physical percent complete. This
means “show me” the outcomes and
show me they meet the
specifications, on the planned day for
the planned cost. If not we’re late,
over budget, and out outcomes
probably don’t work right.
Page 22

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

At the end of the Rocky Flats program,
this is what done looked like.

All cleaned up, lock the gate and throw
the keys over the fence.
On-time, on-budget, met technical
requirements.
Project of the Year, 2006 PMI.
http://goo.gl/oCL0WJ

Page 23

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Thank you for your time.
I hope you got some new ideas about
how to increase the probability of success
for your projects.
The advice shown here should be applied
to everything you do in managing your
projects.
Evidence to the answers from the
questions that represent the five
immutable principles.
Evidence of what done looks like.
Evidence that you have a credible plan
and schedule.
Evidence that you have the right
resources, people, facilities, capacity for
work.
Evidence you have identified the risks,
assessed them, have handling plans.
And most of all evidence that your are
making progress to plan through tangible
measures of physical percent complete.

Page 24

Glen B. Alleman, Niwot Ridge Consulting, LLC
5 Immutable Principles of Project Success

Page 25

Glen B. Alleman, Niwot Ridge Consulting, LLC

Mais conteúdo relacionado

Mais procurados

Todd williams
Todd williamsTodd williams
Todd williams
NASAPMC
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management Skills
Jessica Booth
 
Five Big Ideas For Proj Delivery
Five Big Ideas For Proj DeliveryFive Big Ideas For Proj Delivery
Five Big Ideas For Proj Delivery
sundong
 
Accelerated solutions environment
Accelerated solutions environmentAccelerated solutions environment
Accelerated solutions environment
Bill Rogers
 
Week01 slides spring_2013
Week01 slides spring_2013Week01 slides spring_2013
Week01 slides spring_2013
henry KKK
 
Kerry.mushkin
Kerry.mushkinKerry.mushkin
Kerry.mushkin
NASAPMC
 
Evaluation post mortems
Evaluation post mortemsEvaluation post mortems
Evaluation post mortems
agermuth
 

Mais procurados (20)

Todd williams
Todd williamsTodd williams
Todd williams
 
Prosci Roles in Change Management
Prosci Roles in Change ManagementProsci Roles in Change Management
Prosci Roles in Change Management
 
Why Projects Fail + Four Steps to Succeed
Why Projects Fail + Four Steps to SucceedWhy Projects Fail + Four Steps to Succeed
Why Projects Fail + Four Steps to Succeed
 
Agility mgt v2md
Agility mgt v2mdAgility mgt v2md
Agility mgt v2md
 
Esteem and Estimates (Ti Stimo Fratello)
Esteem and Estimates (Ti Stimo Fratello)Esteem and Estimates (Ti Stimo Fratello)
Esteem and Estimates (Ti Stimo Fratello)
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management Skills
 
Five Big Ideas For Proj Delivery
Five Big Ideas For Proj DeliveryFive Big Ideas For Proj Delivery
Five Big Ideas For Proj Delivery
 
Accelerated solutions environment
Accelerated solutions environmentAccelerated solutions environment
Accelerated solutions environment
 
Week01 slides spring_2013
Week01 slides spring_2013Week01 slides spring_2013
Week01 slides spring_2013
 
Project rescue fix it ot kill it
Project rescue fix it ot kill itProject rescue fix it ot kill it
Project rescue fix it ot kill it
 
How To Assess Project Proposals
How To Assess Project ProposalsHow To Assess Project Proposals
How To Assess Project Proposals
 
Martin folwer
Martin folwerMartin folwer
Martin folwer
 
Kepner-Tregoe, Adding Enterprise-Wide Value to you Organization
Kepner-Tregoe, Adding Enterprise-Wide Value to you OrganizationKepner-Tregoe, Adding Enterprise-Wide Value to you Organization
Kepner-Tregoe, Adding Enterprise-Wide Value to you Organization
 
Kerry.mushkin
Kerry.mushkinKerry.mushkin
Kerry.mushkin
 
Evaluation post mortems
Evaluation post mortemsEvaluation post mortems
Evaluation post mortems
 
Agile Gurgaon 2016 Conference | The game has changed! | Sudipta Lahiri
Agile Gurgaon 2016 Conference | The game has changed! | Sudipta LahiriAgile Gurgaon 2016 Conference | The game has changed! | Sudipta Lahiri
Agile Gurgaon 2016 Conference | The game has changed! | Sudipta Lahiri
 
10 causes of project failure.
10 causes of project failure.10 causes of project failure.
10 causes of project failure.
 
Agile And Lean Practices - The Mobile Academy
Agile And Lean Practices - The Mobile AcademyAgile And Lean Practices - The Mobile Academy
Agile And Lean Practices - The Mobile Academy
 
3 Critical Steps to Project Management Office (PMO) Development
3 Critical Steps to Project Management Office (PMO) Development3 Critical Steps to Project Management Office (PMO) Development
3 Critical Steps to Project Management Office (PMO) Development
 
20 things you should know
20 things you should know20 things you should know
20 things you should know
 

Semelhante a 5 immutable principles of project success (v3)(notes)

Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)
Glen Alleman
 
1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx
aulasnilda
 
The Value PMLC Process Capability
The Value PMLC Process CapabilityThe Value PMLC Process Capability
The Value PMLC Process Capability
Bill Monroe
 
HU245 Employee Rights Case Study Employee Rights C.docx
HU245 Employee Rights Case Study     Employee Rights C.docxHU245 Employee Rights Case Study     Employee Rights C.docx
HU245 Employee Rights Case Study Employee Rights C.docx
wellesleyterresa
 
Managing the portfolio
Managing the portfolioManaging the portfolio
Managing the portfolio
Stuart Robb
 
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docxSafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
rtodd599
 

Semelhante a 5 immutable principles of project success (v3)(notes) (20)

Increasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your ProjectIncreasing The Probability Of Success For Your Project
Increasing The Probability Of Success For Your Project
 
Five immutable principles of project success
Five immutable principles of project successFive immutable principles of project success
Five immutable principles of project success
 
Del
DelDel
Del
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
Gestión de Proyectos y mejores practicas
Gestión de Proyectos y mejores practicas Gestión de Proyectos y mejores practicas
Gestión de Proyectos y mejores practicas
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
Agile And Your Business V2
Agile And Your Business V2Agile And Your Business V2
Agile And Your Business V2
 
1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx
 
Why do the Projects fail
Why do the Projects failWhy do the Projects fail
Why do the Projects fail
 
The Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessThe Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccess
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
The Value PMLC Process Capability
The Value PMLC Process CapabilityThe Value PMLC Process Capability
The Value PMLC Process Capability
 
HU245 Employee Rights Case Study Employee Rights C.docx
HU245 Employee Rights Case Study     Employee Rights C.docxHU245 Employee Rights Case Study     Employee Rights C.docx
HU245 Employee Rights Case Study Employee Rights C.docx
 
Managing the portfolio
Managing the portfolioManaging the portfolio
Managing the portfolio
 
Fundamentals of value engineering
Fundamentals of value engineering Fundamentals of value engineering
Fundamentals of value engineering
 
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docxSafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
 

Mais de Glen Alleman

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Último

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 

Último (20)

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 

5 immutable principles of project success (v3)(notes)

  • 1. 5 Immutable Principles of Project Success Thank you for inviting me here today. The topic should be one we all are familiar with, since it is nearly impossible to not have experienced a project failure at least once in our career. The principles I’m going to speak to you about are universal. Applicable to any project, of any size, in any domain. The example project was one I was involved with as a Program Manager. One that was manifestly important, and nearly impossible. One that shaped how I see the principles, practices, and processes of managing projects in ways I had not considered before. What you’re going to hear is not the solution to project failure. It is the framework for that solution. The actual mechanics of managing a project are based on these principles. The practices used in this management should be based on the se principles. And of course the process ad tools should implement the practices. I’d like to present the 5 Immutable Principles of project success using examples from a program I was a participant in. Rocky Flats Environmental Technology Site, in Golden Colorado. Page 1 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 2. 5 Immutable Principles of Project Success Let’s start with positioning our interest in the project domain. Nearly every business activity is based on a project in some way. Even the operational aspects of a business are projectized through processes, procedures, and business management. Today I’d like to focus that types of projects Land speaks of. The really important ones that are nearly impossible. I was a participant in one of those projects – Rocky Flats Environmental Technology Site. The name of the site was a nice marketing term for the cleanup of a nuclear bomb factory. It was nearly impossible. The previous contractor had spent $4B and not done much. When Kaiser-Hill (a joint venture between ICF Kaiser and CH2MHill) won the contract, they had a plan that was dramatically different from the past attempts to cleanup and close the site. Page 2 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 3. 5 Immutable Principles of Project Success Rocky Flats was a U.S. Department of Energy National Nuclear Security Agency production site that operated from 1952 to 1992. Rocky Flats was the most contaminated nuclear weapons plant in the country, was an environmental disaster and the site of rampant worker unrest. Estimates projected that cleaning up and closing the facility would take 70 years and $36 Billion. The actual project was completed in 10 years for $6B. Page 3 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 4. 5 Immutable Principles of Project Success For projects where success is mandatory, the outcome critical to the business, and risks are high, success comes about through principles, practices, and processes. I’m going to try and convince you today that the 5 Immutable Principles are the foundation of any projects success. These Principles are “Immutable” because they must always be present. They are the foundation on which the Practices and Processes are built. We won’t look at the Practices and Processes, but they are critical to the success of any project as well. Page 4 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 5. 5 Immutable Principles of Project Success After the Rocky Flats project had completed, the book Making the Impossible Possible was written about the lessons learned from the cleanup. This book examines the cleanup and closure of 800 buildings with 3 million square feet under roof, on a 6,000 acre site with many tons of hazardous materials just 10 miles from Denver’s suburban population. Success is explained in the book through the model of Positive Deviance or Heliotropic Abundance. The theoretical framework of Competing Values (shown here) is the basis of the book. The 5 Immutable Principles of Project Success are derived from my experiences as a Program Manager at this site. Two elements of the competing values framework are the basis of this talk. Control and Create. Both are needed for success. Control alone limits creativity. Creativity alone results in out of control work activities. Control provides stability measurement, clarity of objectives, discipline, and detailed planning. Creativity enables agility in the presence of constant change. Page 5 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 6. 5 Immutable Principles of Project Success Of the four quadrants of positive Deviance we are interested in Control and Create as the basis of the 5 Immutable Principles of project success. The focus is on clear and concise descriptions of Done, while innovative solutions to technical, programmatic, and operational problems are needed at every step along the way to Done. We need both, but Control is the basis of Create. Control is often criticized as inhibiting or sabotaging performance. Control emphasizes efficiency, smooth functioning, predictability and standardized procedures. It focuses on tight control of internal activities. The result is consistency and dependability in contrast to innovation and dynamism. The success of any project is still grounded in extending beyond doing well to doing spectacularly well, and developing the mechanism that produces extraordinary results. This requires creativity, a clear and shared vision of the future, symbolic leadership (leaders doing the work as well), innovative ideas about work, and creating a sense of meaning and importance attached to the tasks being pursued. Page 6 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 7. 5 Immutable Principles of Project Success With this background, let’s look at the 5 Immutable Principles of Project Success. I would suggest these are applicable to any technical domain. Any project management method. Any business domain. They are universal and Immutable – meaning they don’t change over time. They are permanent principles that must be applied for the success of any project. The Principles are in the form of questions in this example. There are more formal statements about the Principles, but starting by asking 5 questions shows how the principles can be applied in any situation. When there is not a credible answer to the question, this is an indication there is likely trouble on the project and the probability of success has been lowered. In the next charts there will be the questions – numbered 1 through 5. Then there are 3 answers. Starting with the simplest answer – Number 1 – through the best answer – Number 3. It is the Number 3 answer that we are after. Being able to produce the answer in that style may be difficult and require Practices and Processes. But we have to start with the Principles. So let’s start. Page 7 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 8. 5 Immutable Principles of Project Success The first Principle is to ask if we know what Done looks like. This sounds like a simple question. But turns out to be the root cause of most project failure. Done must be described in meaningful units of measure for the decision makers. 1. Our first response is usually to make a list of features and functions for the product of service produced by the project. This is necessary but far from sufficient to describe Done. We don’t know how these features and functions interact, how they provide value to the customer. 2. The interdependencies are next. We need to show how each feature or function is dependent – if it is – on other features and functions. This usually starts with the Work Breakdown Structure (WBS) showing all the deliverables from the project. The WBS needs a WBS Dictionary to show how we are going to measure the performance, quality, compliance of these outcomes with each other and the customer. 3. But the WBS and its Dictionary are not enough to know what Done looks like. We need to know what Capabilities are being provided by the project. What is the customer going to DO with these outcomes? How are they going to satisfy the business needs or mission? The Capability to do something is what the customer bought. Page 8 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 9. 5 Immutable Principles of Project Success These Capability statements are clear and concise. Long before we ever arrived in the moon, Robert Goddard knew what capabilities were needed to get there. On October 19, 1899, Goddard climbed a dead tree to trim some branches. He was 17. He is quoted as saying … “I imagined,” he later recalled, “how wonderful it would be to make some device which had even the possibility of ascending to Mars, and how it would look on a small scale, if sent up from the meadow at my feet. . . I was a different boy when I descended the tree from when I ascended, for existence at last seemed very purposive.” He had in his mind what capabilities were needed to fly outside the Earths atmosphere. He knew some of the units of measure that had to be fulfilled to do this. If we don’t have some vision of the project at the Capabilities level, we really can’t say what Done looks like. We can describe the technical aspects, but we can’t say what we are going to do with those technical aspects. This definition of Capabilities is a Systems Engineering role. There are formal processes to elicit these Capabilities through the Concept of Operations, Scenarios, and Use Cases, making tradeoffs between cost, risk, schedule, and technical performance, and balancing all the feasible alternatives. The result is the Measures of Effectiveness which tell the customer the project will meet the needed capabilities. Page 9 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 10. 5 Immutable Principles of Project Success With the needed Capabilities we can now develop a plan and schedule for the work. Knowing how to get Done on–budget and on–schedule means knowing what requirements will have to be fulfilled. Poorly formed requirements contribute as much as 25% to the failure modes of programs and projects. This starts with Fact Finding, Gathering and Classifying the Requirements, Evaluating and Rationalizing the Requirements, Prioritizing them, and Integrating and Validating the Requirements. With this in hand we can start building the packages of work that implement the requirements. The result is a Plan and a Schedule. The Plan is the Strategy for the proper delivery of the Capabilities produced by the project. The Schedule is the sequence of work needed to implement the Strategy. Both are needed. The Plan is emergent, since it is a strategy. The Schedule tests this strategy on short term boundaries, with measures of physical percent complete. Both the Plan and the Schedule must be capable of responding to change as new information about requirements, program performance, and risk emerge. But the needed capabilities should remain stable if we are to have a baseline on which to execute our project. Page 10 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 11. 5 Immutable Principles of Project Success The Plan can be very simple or it can be complex. Here’s a plan that took us to the moon and back. This picture shows a simple concept. Build the launch vehicle, develop the fuel to power it, the space craft on the top, train the astronauts, do the testing, and fly. The Plan shows the 6 major systems , their approximate duration in years, and the dependencies between them are all that is needed to confirm the feasibility of the project. Notice the longest activity is the training of the crew. No one had ever flown in space before all the way to the moon and back. So training was high risk and critical to success. Page 11 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 12. 5 Immutable Principles of Project Success One view of the Plan is the vertical integration of the deliverables. This is the deliverables traceability view. At the bottom is our deliverable. The deliverable is produced by work contained in a work package. A Work Package says its name. it produces a single outcome. The technical capabilities needed for the project’s success are produced by the Work Packages. Finally these Technical Capabilities produce business or mission capabilities needed by the customer for business success. This traceability is necessary for a credible Plan and Schedule. It is also necessary for a credible project delivery process. This traceability tells everyone what Done looks like and how we are going to get there. Page 12 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 13. 5 Immutable Principles of Project Success With the Plan in place and the “packages of work” identified in the Schedule, we can construct a picture of how we are going to reach Done. This picture is not like the typical horizontal scheduling activities we see in all the scheduling tools. This picture starts with the vertical integration of the deliverables as they progress through their maturity life cycle. This is called the Integrated Master Plan. This Plan shows the Measures of Effectiveness and Measures of Performance we need to achieve to reach a specific level of maturity. This notion of levels of maturity can be seen is we use some words Preliminary is a work description. We all know what preliminary means. It means we’re not done yet. We have a preliminary design we have a preliminary cost estimate or a preliminary list of subcontractors. We know enough about the project to make some decisions, but we need more details before we can say for sure the cost, the design, and the subcontractors are all in place. This incremental approach allows us to move foreword without all the details, while still having visibility into what Done looks like. Since RFETS was many times discovery driven, planning had to be increasing maturity driven without the planning horizon reaching the final date. This incremental and iterative approach is a critical success factor for all projects. Page 13 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 14. 5 Immutable Principles of Project Success Projects are executed by people. People consume time, money, and materials. How can we know if we have enough of everything we need for success? We need a Plan of course, in this case a Resource Management Plan, showing people, funding, and materials, and when and where we need it. 1. We can start with a simple list. This gets us to write it down. 2. Next we need to assign people and money to the needed resources. How many of each special skill type will we need for this project. 3. In the end though, we need to lay out these needs against the schedule of work. We need to resource load the schedule. This sounds like a lot of work and it is. But without this in place we really have no idea if the project is feasible. Page 14 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 15. 5 Immutable Principles of Project Success Matching people to needs is at the heart of resource management. Without understanding what skills are needed we can’t do this matching. This information comes from the subject matter experts that have defined the “packages of work” and their deliverables. Page 15 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 16. 5 Immutable Principles of Project Success We usually start by identifying risks. But risk is the result of uncertainty. There are two types of uncertainty – reducible uncertainty and irreducible uncertainty. We can do something about reducible uncertainty. We can buy more knowledge about this uncertainty – it is epistemic. We can run tests, build prototypes, look at what others have done. The risk that results is reducible. The irreducible uncertainty is part of the world around us. This uncertainty cannot be reduced – it is aleatory uncertainty. The only way to deal with this uncertainty is through margin. Cost margin, schedule margin, technical margin. 1. We have to start by identifying these uncertainties and associating them with the risks. 2. Then the impacts of the risk are identified along with their dependencies. 3. The probability of occurrence and the probability of their impact can be assessed and once the reducible risks are handled the residual uncertainty and its resulting risk. With these impediments in hand we can take actions to either protect our project with margin or spend money to retire or handle the resulting risk. Page 16 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 17. 5 Immutable Principles of Project Success The resulting Risk Management Plan becomes part of the Integrated Master Plan. Risk management is how adults manage projects – Tim Lister. We can manage the risk with either margin or with specific risk reducing actions. Either way, we must manage the risk. The discovery of uncertainty and the resulting risk is a continuous work process. It is repeated weekly, monthly, quarterly, annually. It is never ending. Risk drives variance and variance must be managed actively as part of the project management process. The retirement of risk must be defined in the planning documents. The reduction from RED to YELLOW to GREEN must take place as planned. If we miss the buy down target we will have created more risk, since the retired risk was not removed as planned. If we spend more money than planned to retire the risk, we are over budget as well. Retiring risk is a project work activity funded on the baseline. Management Reserve maybe used to those “reducible” risks we have not yet decided to retire. Page 17 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 18. 5 Immutable Principles of Project Success With our Plan, Schedule, Resources, and Risk Management Plan, we can now determine how we are going to measure progress to these plans. 1. The customer bought outcomes, deliverables, capabilities. We need to describe these in a way the customer understands. Units of measure that are meaningful for making decisions. 2. These are best described as Technical Performance Measures. These are attributes that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal. 3. But these alone are not sufficient for the success of the project. We need Measures of Effectiveness (MoE), Measures of Performance (MoP), and Key Performance Parameters (KPP).  MoEs are operational measures of success that are closely related to the achievements of the mission or operational objectives evaluated in the operational environment, under a specific set of conditions. These are “customer satisfaction” measures.  MoPs characterize physical or functional attributes relating to the system operation, measured or estimated under specific conditions.  KPPs represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the program. Page 18 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 19. 5 Immutable Principles of Project Success Measuring progress to plan means measuring physical percent complete at a fine grained level, where a 0% / 100% assessments can be made. You’re either done or your not done. No in between. No vague assessment of done. This means the planning of the work must identify tangible deliverables at that level. This may appear more difficult, but it provides unassailable measures of progress. No opinions. No almost done. No “we’ll be done real soon.” Either you’re done or not done. This approach provides the foundation of Earned Value at the Work Package level. It makes measuring progress easy. More importantly it provides the basis to answer the question – How long are you willing to wait before you find out you are late? With these fine grained measures of progress to plan, the answer can be the tangible evidence of progress. Typically this evidence is produced every two weeks. No longer than monthly. But it has to be tangible. In this picture the tangible evidence is barrels of waste packaged, sealed, and ready to leave the site. Page 19 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 20. 5 Immutable Principles of Project Success If we don’t have a plan. If we don’t have the proper resources available at the needed time. Of we don’t handle risks if we don’t have measures of physical; percent complete. We can’t have confidence the project will be successful. Without these elements, the probability of project success is reduced. Possibly to the point of project failure. Without these elements, we have created risk to our success with no handling plans. It is this unmitigated risk that creates the unanticipated growth in our Estimate At Completion. Page 20 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 21. 5 Immutable Principles of Project Success Over a large number of complex, high risk programs there have been a small number of root causes discovered for project failure. There are shown here. Reading them they seem obvious. Dealing with them is more difficult . But we must deal with them and we must have information needed to deal with them. This information comes from the practices, processes, and tools used to manage the project. Scheduling, cost, risk, performance measurement, and forecasting tools and the processes used to apply them. Only when all this information in integrated though a single “lens” can we have the needed visibility to take corrective action to keep the project GREEN. Stay on schedule, stay on budget, comply with the technical requirements. Or if not, know about the variances soon enough to take corrective action. Page 21 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 22. 5 Immutable Principles of Project Success Let’s quickly review the 5 principles of project success in the time remaining. 1. What does done look like? The customer needs to know what capabilities will be possessed when the project is done. The capabilities produce the business value or fulfill a mission objective. 2. How do we get there? We need a plan and a schedule. We need to arrange the work properly in the sequence to produce continuous value. 3. Are there enough resources? People, material, facilities? Are they the right people, does the material arrive at the needed time, are the facilities adequate to produce the needed outcomes? 4. What are the impediments to progress? Risk management is how adults manage projects. Do we have a risk register? Do the risks have handling plans? Is the cost and schedule baseline adjusted for these risks? 5. How do we measure progress? The only way is tangible evidence of physical percent complete. This means “show me” the outcomes and show me they meet the specifications, on the planned day for the planned cost. If not we’re late, over budget, and out outcomes probably don’t work right. Page 22 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 23. 5 Immutable Principles of Project Success At the end of the Rocky Flats program, this is what done looked like. All cleaned up, lock the gate and throw the keys over the fence. On-time, on-budget, met technical requirements. Project of the Year, 2006 PMI. http://goo.gl/oCL0WJ Page 23 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 24. 5 Immutable Principles of Project Success Thank you for your time. I hope you got some new ideas about how to increase the probability of success for your projects. The advice shown here should be applied to everything you do in managing your projects. Evidence to the answers from the questions that represent the five immutable principles. Evidence of what done looks like. Evidence that you have a credible plan and schedule. Evidence that you have the right resources, people, facilities, capacity for work. Evidence you have identified the risks, assessed them, have handling plans. And most of all evidence that your are making progress to plan through tangible measures of physical percent complete. Page 24 Glen B. Alleman, Niwot Ridge Consulting, LLC
  • 25. 5 Immutable Principles of Project Success Page 25 Glen B. Alleman, Niwot Ridge Consulting, LLC