SlideShare uma empresa Scribd logo
1 de 33
International Approach to Predicting
       Construction Labour Hours
         Speaker – Shane Forth
       Vice President – Association of Cost Engineers
Manager of Project Controls – AMEC Power and Process Europe




           Siberian Regional Cost Estimating Centre
        International Research and Practice Conference
          10th – 11th November 2009 – OMSK, Russia
Shane Forth FACostE, FAPM

           Power and Process Europe            Association of Cost Engineers
    –   Project Controls Strategy                – Vice-President
    –   Operational Excellence                   – Chairman, Planning & Scheduling SIG
    –   AMEC Project Management Academy
    –   Project Support
                                                 – Chairman Project Control Managers
   Whessoe Oil & Gas                              Working Group
    – Bid Manager and Project Services

   Kuwait Santa Fe Braun
    – Scheduling Engineer                        – Various Working Groups, Graduate &
                                                   Apprenticeship Schemes Occupational
                                                   Standards
   Other Experience
    – Kvaerner, ICI, Simon Carves, John Laing



                                                                                       2
Estimate Accuracy
There is no merit in attempting to achieve a level of
accuracy that is inconsistent to the amount of
information available, particularly as this could lead to
the Estimate being given a ”perceived” credibility it
does not deserve




                                                            3
Estimate Accuracy
                    1 Feasibility (- 25% to + 50%)
                          2 Concept (- 15% to + 25%)
                                   3 Basic Design (- 10% to + 15%)
Estimate Accuracy




                                                          4 Detail Design (- 5% to + 10%)
                    +


                    _

                        0%          Completeness of Design                     95%
                                                                                      4
Information for Estimating
1 Feasibility   Generalised scope definition
                Required capacity of plant
                Approximate Weights
                Preliminary project schedule




                                               5
Information for Estimating
2 Concept   Plant Location
            Preliminary process diagram
            Main statutory requirements
            Equipment list
            Outline engineering specifications
            Preliminary “block” plot plan
            Offsites and utilities by system and capacity
            Budget quotes for Equipment
            Preliminary equipment data sheets
            Preliminary process and instrument diagram




                                                            6
Information for Estimating
3 Basic Design Firm quotes for major equipment
               Detailed scope definition
               Finalised heat and mass balance calculations
               P & ID’s for process and offsites
               Detailed plot plans
               Detailed engineering specifications
               Preliminary Material Take Offs
               Operators requirements
               Local authority requirements
               Project master schedules
               Information on site conditions



                                                              7
Information for Estimating
4 Detail Design Local availability of labour and materials
                Detailed equipment list
                 Completed and approved plant layout
                 Electrical single line diagrams
                 Detailed equipment specifications/data sheets
                 Detailed material take offs
                 Firm quotations from potential vendors
                 Quotations from potential contractors
                 Commissioning and operating information
                 Installation and fabrication specifications
                 Construction subcontract enquiries
                 Production design phase continues

                                                                 8
1 Feasibility - Factors


  Cost x 4.0                          Cost x 5.0



            Estimated Total Installed Cost
(from which construction manhours can be estimated)




  Cost x 3.0                         Cost x 6.0       9
1 Feasibility - Factors


Construction % of Total Installed Cost
   Average Labour Manhour Rate
 = Estimated Construction Manhours




                                         10
1 Feasibility - Order of Magnitude




                                     11
1 Feasibility - Order of Magnitude




                                     12
2 Concept - Principle Quantities
                             Unit of    Unit
                            Measure     Qty
      Piping
      Pipework             Metres      75000
      Supports             Tonnes       200
      Tests                No off       40
      Valves               No off       300
      E&I
      Electrical cable     Metres      100000
      Instrument cable     Metres      50000
      Electrical devices   No off       800
      Motors               No off       26
      Instruments          No off       400
      Control Systems      I/O Count   6000     13
Onshore
1 Feasibility                                  2 Concept
(typically - 25 % to + 50 %)                   (typically - 15 % to + 25 %)
 In house Estimates for Equipment and          Preliminary details from suppliers for Major
  Tagged Items                                   Equipment and Tagged Items
 Factored from Equipment and Tagged            Principle quantities (approximate) for
  Items for Bulk Materials                       bulk materials
 Order of Magnitude from historical data on    Base norms adjusted for location factors and
  similar projects                               productivity assumptions
 Estimate for Project Sanction                 Estimates for Optioneering

3 Basic Design                                 4 Detail Design
(typically - 10 % to + 15 %)                   (typically - 5 % to + 10 %)
 Firm details from suppliers for 80%-90% of    Firm details from suppliers for 90% -100% of
  Equipment and Tagged Items                     Equipment and Tagged Items
 Preliminary MTO – in house, forced detail     Intermediate and Final MTO’s
 Base component norms adjusted in house        Base component norms adjusted in house
  for location factors and productivity          for location factors and productivity
  assumptions, or as provided by                 assumptions, or as provided by
  subcontractors                                 subcontractors
 Target Cost Estimate                          Definitive Estimate                            14
Offshore
1 Feasibility                                  2 Concept
(typically - 25 % to + 50 %)                   (typically - 15 % to + 25 %)
 In house Estimates for Equipment and          Preliminary details from suppliers for Major
  Tagged Items                                   Equipment and Tagged Items
 Estimated Weight                              Estimated Weights for Bulk Materials
 Order of magnitude from historical data on    Base norms adjusted for location factors and
  similar projects                               productivity assumptions
 Estimate for Project Sanction                 Estimates for Optioneering


3 Basic Design                                 4 Detail Design
(typically - 10 % to + 15 %)                   (typically - 5 % to + 10 %)
 Firm details from suppliers for 80%-90% of    Firm details from suppliers for 90% -100% of
  Equipment and Tagged Items                     Equipment and Tagged Items
 Preliminary MTO – in house, forced detail     Intermediate and Final MTO’s
 Base component norms adjusted in house        Base component norms adjusted in house
  for location factors and productivity          for location factors and productivity
  assumptions, or as provided by                 assumptions, or as provided by
  subcontractors                                 subcontractors
 Target Cost Estimate                          Definitive Estimate                            15
Shutdown
For Poorly Defined scope                  Rough Estimate
Estimate in manhour ranges                  500 Jobcards
+ management fee                           7000 Activities           =    140,000 Manhours
                                             20 Manhours per Activity
          116
                                          Improved Estimate
 120                                      - Lump Sum, must exclude emergent work
                                          - For repeat shutdown at the same plant,
                     89                     estimate manhours using historical data
 100
                                          - Visit site during tender period for preliminary
                             75      71     discussions and assessment - especially important
  80                                        for unfamiliar plant

  60
                                            49
                                                    30      30
  40                                                                23
                                                                              17

  20


   0 Vessels   Control Exchangers Drums   NRVs   Fin     Pumps   Towers    Other
     Inspect   Valves                            Fans
                                                                                         16
Shutdown
    Tender Period                           Preparation                       Shutdown Event
 (typically 2 months)                   (typically 6 months)                (typically 3 weeks)

A Preliminary Turnaround list         D Prepare Work Packs



                         E Prepare Jobcards            F Preliminary Plan      H Final Plan and
B Assess Workscope       (activities, manhours, etc)                           Manhours Agreed




C Outline Plan
                                           G Review Preliminary Plan          J Shutdown Event


                                                                                                  17
Shutdown




           18
Estimate - Base Norms
Location Factor Adjustments




                              19
Estimate – Base Norms
Project Specific Adjustments
            Considerations
             Climate
             Site Layout and Access
             Site Location – How Remote ?
             Clock In and Walking Time to Workface
             Work Days and Hours
             Labour Density
             Industrial Relations
             Availability of Skilled Trades
              (Competing Projects, use of Local & Travelling Labour)

             Use of Equipment, Working Methods
              (eg.Machine or Hand Excavate)

             Permit to Work on Brownfield Sites
             Contract Conditions                                20
Estimate - Quantity Allowances
Certain quantity allowance may also be applied to the base estimate
for expected but unidentified work:
Engineering           Material           Cutting           Construction
  Growth              Take Off           & Waste            Increase
 Allowance           Allowance          Allowance           Allowance
Anticipated        Applied to for      Anticipated         Applied to
design growth      additional          amount of           construction
due to internal    materials to be     materials that is   labour,
design changes     supplied due to     cut and wasted      equipment and
                   anticipated         (eg.due to          services due to
                   Engineering         standard            anticipated
                   Growth              pipe lengths,       Engineering
                   Allowance           loose flanges       Growth
                                                           Allowance

                                                                        21
Component Norms - Construction
INDEX



        1




                                 22
Component Norms - Construction
INDEX



        1


        2




                                 23
Component Norms - Construction
INDEX



        1


        2   3




                                 24
Component Norms - Construction
INDEX



        1
                            4
        2   3




                                 25
Construction Manhours Prediction
  INDEX




1 Estimated Manhours = Component Norms x Estimated Quantities




                                                                26
Construction Manhours Prediction
  INDEX




1 Estimated Manhours = Component Norms x Estimated Quantities
2 Revised Manhours = Component Norms x AFC Revised Quantities




                                                                27
Construction Manhours Prediction
  INDEX




1 Estimated Manhours = Component Norms x Estimated Quantities
2 Revised Manhours = Component Norms x AFC Revised Quantities
3 Achieved Manhours = Component Norms x Installed Quantities




                                                                28
Construction Manhours Prediction
  INDEX




1 Estimated Manhours = Component Norms x Estimated Quantities
2 Revised Manhours = Component Norms x AFC Revised Quantities
3 Achieved Manhours = Component Norms x Installed Quantities
4 Actual Manhours    = Expended Manhours




                                                                29
Construction Manhours Prediction
  INDEX




1 Estimated Manhours = Component Norms x Estimated Quantities
2 Revised Manhours = Component Norms x AFC Revised Quantities
3 Achieved Manhours = Component Norms x Installed Quantities
4 Actual Manhours    = Expended Manhours
5 Predicted Manhours = Actual Manhours + Productivity Forecast for Revised to go



                                                                             30
Construction Manhours Prediction
  INDEX




1 Estimated Manhours = Component Norms x Estimated Quantities
2 Revised Manhours = Component Norms x AFC Revised Quantities
3 Achieved Manhours = Component Norms x Installed Quantities
4 Actual Manhours    = Expended Manhours
5 Predicted Manhours = Actual Manhours + Productivity Forecast for Revised to go
             This is part of Earned Value Analysis (EVA)

                                                                             31
Estimating – Historical Data
                             Key Aspect
  Production of accurate estimates from high quality estimating base data

                             The Solution

Past projects close-out information and statistics
 Bulk material quantities, weights and costs
 Engineered items details and costs
 Project Controls Information (documents, changes, man-hours and costs)

        must be processed promptly at project completion
                 to maintain factors, norms etc.

                                                                        32
Thank you for your attention.

   Excellence in Cost Engineering
          www.acoste.org




          The Association of Cost Engineers
                                              33

Mais conteúdo relacionado

Mais procurados

Productivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying ActivityProductivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying ActivityManish Kumar PGP - NICMAR Pune
 
CV Senior Quantity Surveyor(CIVIL)
CV Senior Quantity Surveyor(CIVIL)CV Senior Quantity Surveyor(CIVIL)
CV Senior Quantity Surveyor(CIVIL)Naeem Altaf Chughtai
 
CV - MEP Inspector Engineer Froilan Ramos Balanao
CV -  MEP Inspector Engineer  Froilan Ramos BalanaoCV -  MEP Inspector Engineer  Froilan Ramos Balanao
CV - MEP Inspector Engineer Froilan Ramos BalanaoFroilan Balanao
 
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...Mechanical Engineer having 5+ years experience in Erection & Commissioning En...
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...Qamar Ahmad
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerSankar Sundaram PMP
 
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENTQA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENTmuhammad jamil
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and EstimationGide India
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW TW Carl
 
Mohamad Elyaas CV & Certf
Mohamad Elyaas CV & CertfMohamad Elyaas CV & Certf
Mohamad Elyaas CV & CertfMohamad Elyaas
 
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGERCV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGERAZHAR QAZI
 
CV-Mechanical Engineer.
CV-Mechanical Engineer.CV-Mechanical Engineer.
CV-Mechanical Engineer.AZHAR QAZI
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
MEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIO
MEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIOMEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIO
MEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIOramy zidan
 

Mais procurados (20)

Productivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying ActivityProductivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying Activity
 
CV Senior Quantity Surveyor(CIVIL)
CV Senior Quantity Surveyor(CIVIL)CV Senior Quantity Surveyor(CIVIL)
CV Senior Quantity Surveyor(CIVIL)
 
Resume-Wail
Resume-WailResume-Wail
Resume-Wail
 
RESUME-Sijin
RESUME-SijinRESUME-Sijin
RESUME-Sijin
 
CV - MEP Inspector Engineer Froilan Ramos Balanao
CV -  MEP Inspector Engineer  Froilan Ramos BalanaoCV -  MEP Inspector Engineer  Froilan Ramos Balanao
CV - MEP Inspector Engineer Froilan Ramos Balanao
 
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...Mechanical Engineer having 5+ years experience in Erection & Commissioning En...
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...
 
3rd generation modularization by flour
3rd generation modularization   by flour3rd generation modularization   by flour
3rd generation modularization by flour
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENTQA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
N.Sadhasivam_CV
N.Sadhasivam_CVN.Sadhasivam_CV
N.Sadhasivam_CV
 
Mohamad Elyaas CV & Certf
Mohamad Elyaas CV & CertfMohamad Elyaas CV & Certf
Mohamad Elyaas CV & Certf
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
 
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGERCV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
CV---MECHANICAL ENGINEER / EPC-PROPOSALS MANAGER
 
CV-Mechanical Engineer.
CV-Mechanical Engineer.CV-Mechanical Engineer.
CV-Mechanical Engineer.
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
MEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIO
MEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIOMEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIO
MEP BIM ENGINEER -RAMY ZIDAN -PORTFOLIO
 
CV Preparateur-Superviseur_Tayou J
CV Preparateur-Superviseur_Tayou JCV Preparateur-Superviseur_Tayou J
CV Preparateur-Superviseur_Tayou J
 

Destaque

Ontario construction labour assessment 2012 2020
  Ontario construction labour assessment 2012 2020  Ontario construction labour assessment 2012 2020
Ontario construction labour assessment 2012 2020Shawna Henderson
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSIAEME Publication
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Energy Construction Forum
 
ecosys-brochure-digital
ecosys-brochure-digitalecosys-brochure-digital
ecosys-brochure-digitalZoe MacDonald
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptp6academy
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Energy Construction Forum
 
Curve of influence mar 2014
Curve of influence mar 2014Curve of influence mar 2014
Curve of influence mar 2014Niall M Reynolds
 
Contracts & Cost Breakdown Structure
Contracts & Cost Breakdown StructureContracts & Cost Breakdown Structure
Contracts & Cost Breakdown StructureSteven Eady
 
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRYSTUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRYIAEME Publication
 
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSIAEME Publication
 
LABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIES
LABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIESLABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIES
LABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIESIAEME Publication
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvementHemant Patil
 
Improving Productivity by Lean
Improving Productivity by LeanImproving Productivity by Lean
Improving Productivity by LeanANITHA BALA
 
Productivity improvement slide share
Productivity improvement slide shareProductivity improvement slide share
Productivity improvement slide shareK. M. Hasan Ripon
 
Work breakdown structurep
Work breakdown structurepWork breakdown structurep
Work breakdown structurepRavi Malik
 

Destaque (17)

00 project control tools
00 project control tools00 project control tools
00 project control tools
 
Ontario construction labour assessment 2012 2020
  Ontario construction labour assessment 2012 2020  Ontario construction labour assessment 2012 2020
Ontario construction labour assessment 2012 2020
 
Manitoba
ManitobaManitoba
Manitoba
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
 
ecosys-brochure-digital
ecosys-brochure-digitalecosys-brochure-digital
ecosys-brochure-digital
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
 
Curve of influence mar 2014
Curve of influence mar 2014Curve of influence mar 2014
Curve of influence mar 2014
 
Contracts & Cost Breakdown Structure
Contracts & Cost Breakdown StructureContracts & Cost Breakdown Structure
Contracts & Cost Breakdown Structure
 
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRYSTUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
 
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
 
LABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIES
LABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIESLABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIES
LABOUR MANAGEMENT IN CONSTRUCTION MANAGEMENT IN THE DEVELOPING COUNTRIES
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvement
 
Improving Productivity by Lean
Improving Productivity by LeanImproving Productivity by Lean
Improving Productivity by Lean
 
Productivity improvement slide share
Productivity improvement slide shareProductivity improvement slide share
Productivity improvement slide share
 
Work breakdown structurep
Work breakdown structurepWork breakdown structurep
Work breakdown structurep
 

Semelhante a International Approach to Predicting Construction Labour Hours

Ot Tech Site Ahlgren
Ot Tech Site AhlgrenOt Tech Site Ahlgren
Ot Tech Site AhlgrenDeb Ahlgren
 
Resume_Shruti Maurya
Resume_Shruti MauryaResume_Shruti Maurya
Resume_Shruti MauryaSHRUTI MAURYA
 
EPC Services Capability Tra International limited
EPC Services Capability  Tra International limitedEPC Services Capability  Tra International limited
EPC Services Capability Tra International limitedHimanshu9974
 
Rf optimisation
Rf optimisationRf optimisation
Rf optimisationUma Mahesh
 
Introduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBIIntroduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBIEdwin A Merrick
 
PMI 3D Laser Scanning (As Built) Services
PMI 3D Laser Scanning (As Built) ServicesPMI 3D Laser Scanning (As Built) Services
PMI 3D Laser Scanning (As Built) Servicesssoni747
 
Nuclear Capabilities
Nuclear CapabilitiesNuclear Capabilities
Nuclear CapabilitiesQuEST Global
 
Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Chad Broussard
 
Reliability Growth Planning: Its Concept, Applications, and Challenges
Reliability Growth Planning: Its Concept, Applications, and Challenges Reliability Growth Planning: Its Concept, Applications, and Challenges
Reliability Growth Planning: Its Concept, Applications, and Challenges ASQ Reliability Division
 
Walley.tina
Walley.tinaWalley.tina
Walley.tinaNASAPMC
 
Manufacturing Costing Manufacturing Costing Manufacturing Costing
Manufacturing Costing Manufacturing Costing Manufacturing CostingManufacturing Costing Manufacturing Costing Manufacturing Costing
Manufacturing Costing Manufacturing Costing Manufacturing Costingssusercecf0d
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo
 
Reliability integration across the product life cycle
Reliability integration across the product life cycleReliability integration across the product life cycle
Reliability integration across the product life cycleAccendo Reliability
 

Semelhante a International Approach to Predicting Construction Labour Hours (20)

Shivamtech brochure
Shivamtech brochureShivamtech brochure
Shivamtech brochure
 
Ot Tech Site Ahlgren
Ot Tech Site AhlgrenOt Tech Site Ahlgren
Ot Tech Site Ahlgren
 
Resume_Shruti Maurya
Resume_Shruti MauryaResume_Shruti Maurya
Resume_Shruti Maurya
 
EPC Services Capability Tra International limited
EPC Services Capability  Tra International limitedEPC Services Capability  Tra International limited
EPC Services Capability Tra International limited
 
Rf optimisation
Rf optimisationRf optimisation
Rf optimisation
 
Chapter 5
Chapter 5Chapter 5
Chapter 5
 
Core pmo services
Core pmo servicesCore pmo services
Core pmo services
 
Imran_CV
Imran_CV Imran_CV
Imran_CV
 
My resume 2015
My resume 2015My resume 2015
My resume 2015
 
Introduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBIIntroduction to The Augustus Group and RBI
Introduction to The Augustus Group and RBI
 
PMI 3D Laser Scanning (As Built) Services
PMI 3D Laser Scanning (As Built) ServicesPMI 3D Laser Scanning (As Built) Services
PMI 3D Laser Scanning (As Built) Services
 
Nuclear Capabilities
Nuclear CapabilitiesNuclear Capabilities
Nuclear Capabilities
 
Reliability Program Approval Presentation_
Reliability Program Approval Presentation_Reliability Program Approval Presentation_
Reliability Program Approval Presentation_
 
P4Q services
P4Q servicesP4Q services
P4Q services
 
Reliability Growth Planning: Its Concept, Applications, and Challenges
Reliability Growth Planning: Its Concept, Applications, and Challenges Reliability Growth Planning: Its Concept, Applications, and Challenges
Reliability Growth Planning: Its Concept, Applications, and Challenges
 
Walley.tina
Walley.tinaWalley.tina
Walley.tina
 
Manufacturing Costing Manufacturing Costing Manufacturing Costing
Manufacturing Costing Manufacturing Costing Manufacturing CostingManufacturing Costing Manufacturing Costing Manufacturing Costing
Manufacturing Costing Manufacturing Costing Manufacturing Costing
 
Resume rahul iyer jan 2014 international
Resume rahul iyer jan 2014 internationalResume rahul iyer jan 2014 international
Resume rahul iyer jan 2014 international
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
 
Reliability integration across the product life cycle
Reliability integration across the product life cycleReliability integration across the product life cycle
Reliability integration across the product life cycle
 

International Approach to Predicting Construction Labour Hours

  • 1. International Approach to Predicting Construction Labour Hours Speaker – Shane Forth Vice President – Association of Cost Engineers Manager of Project Controls – AMEC Power and Process Europe Siberian Regional Cost Estimating Centre International Research and Practice Conference 10th – 11th November 2009 – OMSK, Russia
  • 2. Shane Forth FACostE, FAPM Power and Process Europe  Association of Cost Engineers – Project Controls Strategy – Vice-President – Operational Excellence – Chairman, Planning & Scheduling SIG – AMEC Project Management Academy – Project Support – Chairman Project Control Managers  Whessoe Oil & Gas Working Group – Bid Manager and Project Services  Kuwait Santa Fe Braun – Scheduling Engineer – Various Working Groups, Graduate & Apprenticeship Schemes Occupational Standards  Other Experience – Kvaerner, ICI, Simon Carves, John Laing 2
  • 3. Estimate Accuracy There is no merit in attempting to achieve a level of accuracy that is inconsistent to the amount of information available, particularly as this could lead to the Estimate being given a ”perceived” credibility it does not deserve 3
  • 4. Estimate Accuracy 1 Feasibility (- 25% to + 50%) 2 Concept (- 15% to + 25%) 3 Basic Design (- 10% to + 15%) Estimate Accuracy 4 Detail Design (- 5% to + 10%) + _ 0% Completeness of Design 95% 4
  • 5. Information for Estimating 1 Feasibility Generalised scope definition Required capacity of plant Approximate Weights Preliminary project schedule 5
  • 6. Information for Estimating 2 Concept Plant Location Preliminary process diagram Main statutory requirements Equipment list Outline engineering specifications Preliminary “block” plot plan Offsites and utilities by system and capacity Budget quotes for Equipment Preliminary equipment data sheets Preliminary process and instrument diagram 6
  • 7. Information for Estimating 3 Basic Design Firm quotes for major equipment Detailed scope definition Finalised heat and mass balance calculations P & ID’s for process and offsites Detailed plot plans Detailed engineering specifications Preliminary Material Take Offs Operators requirements Local authority requirements Project master schedules Information on site conditions 7
  • 8. Information for Estimating 4 Detail Design Local availability of labour and materials Detailed equipment list Completed and approved plant layout Electrical single line diagrams Detailed equipment specifications/data sheets Detailed material take offs Firm quotations from potential vendors Quotations from potential contractors Commissioning and operating information Installation and fabrication specifications Construction subcontract enquiries Production design phase continues 8
  • 9. 1 Feasibility - Factors Cost x 4.0 Cost x 5.0 Estimated Total Installed Cost (from which construction manhours can be estimated) Cost x 3.0 Cost x 6.0 9
  • 10. 1 Feasibility - Factors Construction % of Total Installed Cost Average Labour Manhour Rate = Estimated Construction Manhours 10
  • 11. 1 Feasibility - Order of Magnitude 11
  • 12. 1 Feasibility - Order of Magnitude 12
  • 13. 2 Concept - Principle Quantities Unit of Unit Measure Qty Piping Pipework Metres 75000 Supports Tonnes 200 Tests No off 40 Valves No off 300 E&I Electrical cable Metres 100000 Instrument cable Metres 50000 Electrical devices No off 800 Motors No off 26 Instruments No off 400 Control Systems I/O Count 6000 13
  • 14. Onshore 1 Feasibility 2 Concept (typically - 25 % to + 50 %) (typically - 15 % to + 25 %)  In house Estimates for Equipment and  Preliminary details from suppliers for Major Tagged Items Equipment and Tagged Items  Factored from Equipment and Tagged  Principle quantities (approximate) for Items for Bulk Materials bulk materials  Order of Magnitude from historical data on  Base norms adjusted for location factors and similar projects productivity assumptions  Estimate for Project Sanction  Estimates for Optioneering 3 Basic Design 4 Detail Design (typically - 10 % to + 15 %) (typically - 5 % to + 10 %)  Firm details from suppliers for 80%-90% of  Firm details from suppliers for 90% -100% of Equipment and Tagged Items Equipment and Tagged Items  Preliminary MTO – in house, forced detail  Intermediate and Final MTO’s  Base component norms adjusted in house  Base component norms adjusted in house for location factors and productivity for location factors and productivity assumptions, or as provided by assumptions, or as provided by subcontractors subcontractors  Target Cost Estimate  Definitive Estimate 14
  • 15. Offshore 1 Feasibility 2 Concept (typically - 25 % to + 50 %) (typically - 15 % to + 25 %)  In house Estimates for Equipment and  Preliminary details from suppliers for Major Tagged Items Equipment and Tagged Items  Estimated Weight  Estimated Weights for Bulk Materials  Order of magnitude from historical data on  Base norms adjusted for location factors and similar projects productivity assumptions  Estimate for Project Sanction  Estimates for Optioneering 3 Basic Design 4 Detail Design (typically - 10 % to + 15 %) (typically - 5 % to + 10 %)  Firm details from suppliers for 80%-90% of  Firm details from suppliers for 90% -100% of Equipment and Tagged Items Equipment and Tagged Items  Preliminary MTO – in house, forced detail  Intermediate and Final MTO’s  Base component norms adjusted in house  Base component norms adjusted in house for location factors and productivity for location factors and productivity assumptions, or as provided by assumptions, or as provided by subcontractors subcontractors  Target Cost Estimate  Definitive Estimate 15
  • 16. Shutdown For Poorly Defined scope Rough Estimate Estimate in manhour ranges 500 Jobcards + management fee 7000 Activities = 140,000 Manhours 20 Manhours per Activity 116 Improved Estimate 120 - Lump Sum, must exclude emergent work - For repeat shutdown at the same plant, 89 estimate manhours using historical data 100 - Visit site during tender period for preliminary 75 71 discussions and assessment - especially important 80 for unfamiliar plant 60 49 30 30 40 23 17 20 0 Vessels Control Exchangers Drums NRVs Fin Pumps Towers Other Inspect Valves Fans 16
  • 17. Shutdown Tender Period Preparation Shutdown Event (typically 2 months) (typically 6 months) (typically 3 weeks) A Preliminary Turnaround list D Prepare Work Packs E Prepare Jobcards F Preliminary Plan H Final Plan and B Assess Workscope (activities, manhours, etc) Manhours Agreed C Outline Plan G Review Preliminary Plan J Shutdown Event 17
  • 18. Shutdown 18
  • 19. Estimate - Base Norms Location Factor Adjustments 19
  • 20. Estimate – Base Norms Project Specific Adjustments Considerations  Climate  Site Layout and Access  Site Location – How Remote ?  Clock In and Walking Time to Workface  Work Days and Hours  Labour Density  Industrial Relations  Availability of Skilled Trades (Competing Projects, use of Local & Travelling Labour)  Use of Equipment, Working Methods (eg.Machine or Hand Excavate)  Permit to Work on Brownfield Sites  Contract Conditions 20
  • 21. Estimate - Quantity Allowances Certain quantity allowance may also be applied to the base estimate for expected but unidentified work: Engineering Material Cutting Construction Growth Take Off & Waste Increase Allowance Allowance Allowance Allowance Anticipated Applied to for Anticipated Applied to design growth additional amount of construction due to internal materials to be materials that is labour, design changes supplied due to cut and wasted equipment and anticipated (eg.due to services due to Engineering standard anticipated Growth pipe lengths, Engineering Allowance loose flanges Growth Allowance 21
  • 22. Component Norms - Construction INDEX 1 22
  • 23. Component Norms - Construction INDEX 1 2 23
  • 24. Component Norms - Construction INDEX 1 2 3 24
  • 25. Component Norms - Construction INDEX 1 4 2 3 25
  • 26. Construction Manhours Prediction INDEX 1 Estimated Manhours = Component Norms x Estimated Quantities 26
  • 27. Construction Manhours Prediction INDEX 1 Estimated Manhours = Component Norms x Estimated Quantities 2 Revised Manhours = Component Norms x AFC Revised Quantities 27
  • 28. Construction Manhours Prediction INDEX 1 Estimated Manhours = Component Norms x Estimated Quantities 2 Revised Manhours = Component Norms x AFC Revised Quantities 3 Achieved Manhours = Component Norms x Installed Quantities 28
  • 29. Construction Manhours Prediction INDEX 1 Estimated Manhours = Component Norms x Estimated Quantities 2 Revised Manhours = Component Norms x AFC Revised Quantities 3 Achieved Manhours = Component Norms x Installed Quantities 4 Actual Manhours = Expended Manhours 29
  • 30. Construction Manhours Prediction INDEX 1 Estimated Manhours = Component Norms x Estimated Quantities 2 Revised Manhours = Component Norms x AFC Revised Quantities 3 Achieved Manhours = Component Norms x Installed Quantities 4 Actual Manhours = Expended Manhours 5 Predicted Manhours = Actual Manhours + Productivity Forecast for Revised to go 30
  • 31. Construction Manhours Prediction INDEX 1 Estimated Manhours = Component Norms x Estimated Quantities 2 Revised Manhours = Component Norms x AFC Revised Quantities 3 Achieved Manhours = Component Norms x Installed Quantities 4 Actual Manhours = Expended Manhours 5 Predicted Manhours = Actual Manhours + Productivity Forecast for Revised to go This is part of Earned Value Analysis (EVA) 31
  • 32. Estimating – Historical Data Key Aspect Production of accurate estimates from high quality estimating base data The Solution Past projects close-out information and statistics  Bulk material quantities, weights and costs  Engineered items details and costs  Project Controls Information (documents, changes, man-hours and costs) must be processed promptly at project completion to maintain factors, norms etc. 32
  • 33. Thank you for your attention. Excellence in Cost Engineering www.acoste.org The Association of Cost Engineers 33