FACULTY OF CIVIL AND ENVIROMENTAL ENGINEERING
BUILDING CONSTRUCTION
BFC4083/ BFC40803 (SECTION-01)

GROUP PROJECT:
PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION

(MAKMAL NANO TEKNOLOGI UNTUK PUSAT KECEMERLANGAN
MICROELEKTRONIK DAN NANO TEKNOLOGI – SHAMSUDIN
RESEARCH CENTRE (MINT-SRC) FKEE)
PRESENTATION DATE: 15th May 2013 (Week 12nd)
LECTURER
: PN. NOR AZIZAH BT. ADNAN
GROUP MEMBERS:
MUHAMAD FIRDAURS BIN ABDULLAH
(AF090289)
NUR HAMIZAH BT ISMAIL
(AF090337)
MOHD FARIS BIN NASRUDIN
(CF100089)
MOHD NASRUL NIZAM BIN MOHD YAHAYA (CF100126)
MOHD KHUSYAIRIE BIN ARSAD
(CF100232)
TITLE OF PROJECT & BUILDING
CADANGAN MEMBINA DAN MENYIAPKAN MAKMAL
NANO TEKNOLOGI UNTUK PUSAT
KECEMERLANGAN MICROELEKTRONIK DAN NANO
TEKNOLOGI – SHAMSUDIN RESEARCH CENTRE
(MINT-SRC) FAKULTI KEJURUTERAAN ELEKTRIK
DAN ELEKTRONIK (FKEE) DI UNIVERSITI TUN
HUSSEIN ONN MALAYSIA.









Owner Project
: UTHM
Project Start
: 7/02/2011
Project Finish
: 11/12/2011
Construction Period : 44 weeks
Contractor :
ROSHA DYNAMIC SDN BHD
Cost of construction :
RM4,773,440.00
Superintendent Officers :
Naib Canselor UTHM
OBJECTIVE/AIMS
This proposed building is constructed for Faculty of Electric and Electronic
Engineering (FKEE) which its function to provide various state-of-the-art research
facilities such Transmission Electron Microscope Lab, Field Emission Scanning
Electron Microscope & Electron Beam Litography Lab and etc. It also will provide
comfortable Researcher Room, head of laboratory room, room for printing, meeting,
preparation and briefing. It also consist of lobby area, restroom, prayer room and M&E
utilities room (refer to Appendix 4A - Ground Floor Plan). For Block A’s 1st Floor
Level, according to plan, it consists of Reactive Ion Etching Lab, Annealing Furnace,
Pulsed Laser Deposition System Lab, Preparation Room, Focused Ion Beam Lab,
Inductively Coupled Plasma Deposition Lab, Magneton Sputtering Lab and etc.
Technically, expansion of this kind of centre of excellence is to support the university for
Research, Development and Commercialization (RDC), University-University and UniversityIndustry Partnership as well as to lead research in microelectronics, semiconductors and
nanotechnology. It also is built for developing high prestige and excellence culture, develop a
'First Class Mindset' and ability to produce high quality R&D and encourage development
through networking and co-operation.
LOCATION PLAN & SITE PLAN
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CASE STUDY: SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FKEE UTHM)
GENERAL INFO CONSIDERED BEFORE
CONSTRUCTION
PROJECT START - Received of Letter Award
-

Before a project can be started, an appointed contractor must receive an Award Letter
(also known as Letter of Acceptance) from client (UTHM)

-

Site possession is approved once the contractor received and signed Letter of
Acceptance from Pegawai Penguasa. In this project, the date of site possession is
stated begins from 7th of February 2011.

PROJECT FINISH – Granted with Certificate of Practical Completion

-

Once the work has been verified as completed, a Certificate of Practical Completion
(CPC) (see Appendix 1B) will be issued to the contractor. Since that, it marked the
start of liability period duration for the building

PRE-CONSTRUCTION WORKS
-

These included Preliminaries work that need to be done at early stage of construction
such as proper site layout planning, hoarding the area of works, site office, access
road, etc. It can be divided into three part, namely Initial Cost, Recurring Cost and
Completion Cost.
-

It also includes design stage that involved of appointment of Professional Engineer
(P.E) from contractor and preparing design/Shop Drawing. Although all the
construction drawing has been given during bidding process, but there will be some
changes need to be done once the construction need to be started.

MATERIAL PROCUREMENT
-

This procurement will occur throughout the duration of project. Engineer, consultant,
architecture and contractor will deal about the product that need to be used.
Manufacturers of product will offer their product according to the architectural
specification for the building.

Surat Setuju Terima Tender

Sijil Perakuan Siap Kerja
SITE CLEARANCE


Site clearance involves the
removal of walls, hedges,
ditches, and trees, other
vegetation and services from the
site. It can also involve the
clearance of fly-tipped materials
SITE INVESTIGATION


Site investigation is the most
important element in the
process of geotechnical design
for a building. If no site
investigation or inadequate site
investigation, geotechnical
design will be incomplete. It is
identified as the main factors
that cause failure and related
problems in construction.
SETTING OUT


Survey and record the existing ground level at each pile
location. Set out the pile location in accordance with the
Engineer’s working drawings using a theodolite with the
accuracy required in the specifications. All setting out
should refer to the reference points and the related
Contract Drawings. In order to monitor the position of the
steel casing, control pins will be established with two
orthogonal positions offset from the centre of the pile.
TESTING OF PILES


In order to assure the quality of concrete and steel that
will be used during pile construction a sequence of quality
control test shall be performed. There will be taken cube
specimens from concrete and will be reserved under the
appropriate curing ambiance. The 7 days compressive
strenght of the concrete for 2 specimen and 28 days for 1
specimen shall be checked periodically by unconfined
compression tests. Also tensile strenght tests shall be
applied to the reinforcement bars.
LOAD TEST


Planted pile capacity often set using Hiley
formula. Because it shaped the ability empirikel
then obtained must be confirmed with a test pile.
Type of test is often done for concrete pile load
test is upheld 'maintained load test'.



Function Test Pile (Load Test)


To determine the maximum liability of the
ability to realize



To ensure that the pile is acceptable from
the point of planting structure



To determine the relationship between the
deposition of 'settlement' pile with a load
'load' incurred.
DRIVE PILE

A pile driver is a mechanical device used to drive piles
into soil to provide foundation support for buildings or
other structures. The term is also used in reference to
members of the construction crew that work with piledriving rigs.
Type Drive Pile


A hydraulic hammer is a modern type of piling hammer
used in place of diesel and air hammers for driving steel
pipe, precast concrete, and timber piles. Hydraulic
hammers are more environmentally acceptable than the
older, less efficient hammers as they generate less noise
and pollutants. However, in many cases the dominant
noise is caused by the impact of the hammer on the pile,
or the impacts between components of the hammer, so
that the resulting noise level can be very similar to diesel
hammers.
PDA TEST


The Pile Driving Analyzer (PDA) is
a powerful tool to assess pile
driving and High Strain Dynamic
Pile (HSDP) load testing which
may supplement or replace static
testing. The PDA is seeing
increasing usage in the testing of
the various types of cast-in-place
piles. In some parts of the world,
this type of testing is the most
common use for the PDA. This
solution is particularly attractive for
very large, high capacity piles
where the large capacity makes a
static test extremely costly
PILE CAP


A pile cap is a thick concrete mat
that rests on concrete or timber
piles that have been driven into
soft or unstable ground to provide
a suitable stable foundation.



It usually forms part of the
foundation of a building, typically a
multi-storey building, structure or
support base for heavy equipment.



The cast concrete pile cap
distributes the load of the building
into the piles.



A similar structure to a pile cap is a
"raft", which is a concrete
foundation floor resting directly
onto soft soil which may be liable
to subsidence
COLUMN STUMP


Column Stump is a column that
considered as lower structure
because it is located in the
ground below the waterproof
layer at ground floor slab. The
position is vertical above the
foundation. The function of the
column stump is to transfer
load of building to the
foundation. Column stump will
receive load from ground beam,
column and then will transfer
the load to the foundation.The
columns can be made from
steel tube, pre cast concrete or
treated timber these need to be
designed by an engineer for
correct sizing
GROUND BEAM






This type of ground beam is the
most used in building
construction.
It is the beam which both its
ends are tied up at the column
and lying between the two
column.
The beam fixes and holds fitly
the columns in order to stabilize
it. In addition, it also acts to
bear all the loads come from
the wall which constructed
parallel with the beam


A ground beam normally should consist of following items;
· Reinforcements
· Concrete
· Linkers



The reinforcements can be placed at center of that beam.



The sizes of main reinforcement play important role in determine the
strength of a beam.



Ground beam usually does not have secondary beam, only has
primary beam. The ground beam construction will be started after a
column stump has finish. After the column stump has ingrained in
foundation and has corpulent on level as wanted.
INTRODUCTION TO SUPERSTRUCTURE WORKS
• A superstructure is an upward extension of an existing structure above
baseline. Part of areas that involved in superstructure include choice of
building fabrics :
• concrete
• choice of floor structure
• block work and steel
• beam open plans area
• selection of insulation cost and efficiency analysis
• determination of cladding material to be used
• roof structure detailing .
OBJECTIVE
The main objective of superstructure :
• To distribute the load to the foundation
• Stabilized the load from building
• To transfer the load from the roof to the
ground vertically.
FORMWORK
• A table is built pretty much the same
way as a beam formwork but the single
parts of this system are connected
together in a way that makes them
transportable. The most common
sheathing is plywood
• The joists are either made from timber,
wood I-beams, aluminium or steel.
• The stringers are sometimes made of
wood I-beams but usually from steel
channels. These are fastened together
(screwed, weld or bolted) to become a
"deck". These decks are usually
rectangular but can also be other
shapes.
ANTI TERMITE TREATMENT
• The purpose of spreading anti
termite is to prevent the
termite from degrading the
surface of the structure
• Usually the anti termite are
spread to the reinforcement
an d the base formwork.
SLAB STRUCTURE
• The plastic layer is to prevent the
water seepage from rise toward the
slab and slowly reduce the
strength of concrete and
reinforcement.
• Generally consists of a layer of sand
25 - 50 mm thick or 50 - 75 mm
thick layer of weak concrete
• Large in-situ ground slab of 150mm
thick is poured on top of the pile ca
BEAM AND COLUMN
• A suspended span are used
• .It is a simple beam supported by
the overhangs of two adjoining
spans with pinned construction
joints at points of zero moment.
• A reinforced concrete design.
INTERNAL AND EXTERNALL WALL
• a brick wall and dry wall partition are
used for the internal wall as for the
external wall, the brick wall is
selected as an external wall. Type of
bond that used in this construction is
typical Flemish bond of brick.
• Internal wall:used a dry wall partition
.It is lightweight.The drywall partition
lead for better acoustic insulation,
thermal insulation and resistance to
fire and damp conditions.
Roof strucutre
•
•

•

•

steep roof is selected for this project.a steel truss
and bracing are installed for roof frame structure
advantages of steep roof are when it was raining,
the water can drain quickly,They can therefore be
covered with materials that are fabricated and
applied in small, overlapping units which can
categorized to shingles of wood or slate and tiles of
fired clay or concrete.
The shingles are inexpensive and easy to installed.
For the effects of thermal e on and contraction, and
of movements in the structure that supports the
roof, are minimized by the ability of the small units
to move with respect to one another. It is also easy
to repaired.
The selection of material for roof is 0.48 thickness
standing seam metal roofing deck cover with 50
mm thickness of rock wool aluminium sisilation
,chicken wire mesh based on material
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CASE STUDY: SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FKEE UTHM)
Plaster/ skim coat
Wall

Tiling
Painting

FINISHING WORKS

Internal Works

Ceiling
Floor

Mineral Fibre Board (MBF)
Cement Render
Floor Tile

Wall

Staircase

Ceiling/ Soffit Beam Finishes
Floor

Plaster/ skim coat
Aluminium Louvre

Wall

External Works

Ceiling

Aluminium Composite

Painting
Aluminium Strip Ceiling

Floor

Cement Render
Internal Works

WALL: Plastering Works/ Skim Coat
After brickwall has been constructed, plastering work will take place. Plastering work
refers to construction or ornamentation done with plaster, such as a layer of plaster on an
interior wall or plaster decorative moldings on ceilings or walls
Skim Coating is the process of applying a layer of muddy plaster compound to rough
walls to either smooth or repair them. It is done to fill deep scratches or holes or to
replace water-damaged portions of drywal
Internal Works

WALL: Tiling & Painting
This tiling work is carried out on the certain part of the building wall such as pantry and
toilet. It is carried out in the same period as the plastering works/ skim coat took place.
The purpose of painting the wall is to hide the grain and texture of the substrate by
applying an opaque coating. Paint is an opaque coating made from a mixture of solid
pigment and a liquid medium.
Internal Works

CEILING: Suspended Ceiling - MBF
The ceiling is installed just a week later after plastering work is begun. It can be said this
ceiling installation is performed at the same time as the plastering, tiling and wall
painting is in progress. Suspended ceilings are ceilings that fostered the suspension
system using wire or rod suspension buffer. The ceilings are not receiving support from
the walls.
Mineral Fibre Board chosen must certified and approved by SIRIM QAS standard, comply with
BS476: Part 7: 1997. The thickness of the board is 15mm and it has density of 334kg/m3.
Internal Works

FLOOR: Cement Render & Floor Tiles
Cement rendering is the application of a premixed layer of sand and cement to brick,
cement, stone or mud brick. It is often textured, coloured or painted after application.
Depending on the 'look' required, rendering can be fine or coarse, textured or smooth,
natural or coloured, pigmented or painted.
Ceramic tile and stone flooring materials are solid and durable. In general, larger tiles
are used in larger rooms and small tiles used in smaller spaces. Ceramic floor tile is made
from various clays, is somewhat brittle, and takes a very sturdy sub-floor.
Staircase

CEILING/ SOFFIT BEAM FINISHES
This Soffit, formed as a ceiling, to fix underneath, in architecture it is described as the
underside of any construction element. Examples of soffits include the underside of a
flight of stairs, the underside of a ceiling to fill the space above the stairways, at the
corner of the ceiling and wall.
Staircase

WALL AND FLOOR FINISHES
Wall finishes are carried once the ceiling/ soffit beams finishes has been accomplished. It
is same process and using the same finishing material as the internal wall finishing
describe above such as plastering/ works, tiling works and wall painting.

After wall finishes are completed within duration of 6 days, floor finishes will take
place. The same process and material as described before for internal floor finishing, will
be applied to this staircase.
External Works

WALL: Plastering Works/ Skim Coat
This work is done together with internal wall finishes. It is started at the same week as
plastering works for internal wall, but it has been finished a month later than internal
wall finishes (plastering). There is not much different between plastering work for
internal and external wall. The thickness of plaster is 20mm on both sides.
External Works

WALL: Aluminium Louvre
Aluminium louvre that is being used is modern louvers that cannot be opened and
closed with a metal lever, pulleys, or through motorized operators. It is installed
permanently at building façade for reduce sun glare into internal space, prevent direct
heating of sunlight as well as aesthetic value. Below is the location of alumium louvre:
External Works

WALL: Aluminium Composite
Aluminium Composite Panels are the ideal cladding for interior and exterior surfaces.
The material is rigid, light and durable and can be easily transformed into curved and
multi planar surfaces. Composite Panels are available in various colours. But for this
building, it comes in grey-silvered colour to give an elegant, modern and corporate look
to the building facade:
External Works

WALL: Painting
This kind of finishing is applied throughout building external wall same as internal wall
painting process. It is denoted by ‘W1 - Plaster and Paint’ in construction plan as
shown in the previous table ‘WALL FINISHES’
External Works

CEILING: Aluminium Strip Ceiling
Aluminium Strip Ceilings are roll-formed from pre-coated aluminium coils. Strip
Ceilings are the modern way to panel for ceiling and wall fronts. It is widely use in
building external wall and ceiling to improve architectural look.
External Works

FLOOR: Cement Render
Cement render as described previously on internal floor finishes is mixture of lime,
cement, sharp sand and water. According to work planning schedule, the external floor finished
by this cement render is the last step among other kind of floor finishes of the building but once it’s
started, its progress flow simultaneously with other finishes and might end at the same time with
others.
FITTING & EXTERNAL WORKS
1.Sanitary Fititng (toilet cubicle)
2.Surau and ablution area:
 To accommodate 5 person with 1 nos.ablution tap
 To provide cabinet and shoe rack

 To provide benches
Signage

 Provide new directional, operational, regulatory

and door signs
 Provide new large illuminated external building

sign for the building
Landscaping works

 To provide hard and soft landscaping (trees, shrub and

close turf) for all areas not covered with footpaths, drains
and road pavement.
 The parking area shall be planted with shade trees and a

mixture of feature planting along building frontage.
 Features palms and shade trees shall be planted along

pedestrian path to serve as the linkage between parking
area to building.
Washroom Partition

 For block A and B washroom partition system to be used for

W.C. Cubicles forming dividers, frontals, end panels and
doors. Assembly using customizeed aluminium extrusion and
fixing with manufacturer’s standard hardwares thickness :
18mm thick double faced autoclaved high density
cementations fibreboard.
 Wall connection : Painted aluminium channels
 Head rail : Painted aluminium head rail
 Doors : 2000 x 600 x18 mm minimum solid core, moisture
resistant fibre board.
Sundries

• The perimeter drain for blok A and B use 230 mm half round reinforce
concrete drain. This work progress takes about 70 days, from 22 September

2011 to 11 December 2011.
Water Supply and Reticulation

 The water supply and reticulation work takes about 38 days,

from 30 September 2011 to 12 November 2011.These works
include the installation of piping,jointing and connection
works and the hydrant system.After finished these all
installation, testing works have been done for 7 days from 5
November 2011 to 12 November 2011.
Road Works

 The Infra works takes about 24 days from 17 October 2011

to 12 November 2011.The infra works include the road
works, road kerb and road marking.

Asphaltic Concrete
 This project use asphaltic concrete BC (ACB 28)

and (ACW 14) from Hanson Quarry SDN.BHD.
Road kerb

Road marking

 Road kerb and road marking work takes about 14 days from

28 October 2011 to 12 November 2011 to finished.
MECHANICAL & ELECTRICAL
WORKS
COLD WATER
( 7/2/2011 – 22/11/2011 )

 Piping works

Piping work for colwater supply was start at
5/7
All pipe routing shall be as shown on
approved Shop drawings. All Pipe supports
and clamps shall be installed as per
manufacturer recommendations. installation
of all supports shall be in accordance with
approved supporting detail drawings
 Installation of FRP water tank

FRP water tank was start from 7/2
The water tank that use in this building was
fiberglass reinforced plastic. The cylindrical
series with capacity up to 110,000 gallons
 Testing work
After the all the piping work and the installation
was finished at 15/11.
The test can be carryout. The test has be done in
some step
SANITARY PLUMBING
( 5/7/2011 – 22/11/2011 )
 Piping work

Plumbing work carried out on 7/5 after
installation plan approved indoor toilet.
 Construct 2 nos new manhole
The work start at 10/10 after the completion
of plumbing work.
Drainage system used is below ground
drainage. VCP pipe used is 100mm in size and
approved by sirim
 Installation of septic tank

Septic tank installation started on 21/10.
Hole dug to accommodate septic tank and sandsized 1.3mx1.3mx1.3m included 10cm high.
 Testing works
The test have been done at 15/11 after the
Resident Representative witness the tests and
approve the pipe installation
PROJECT HAND OVER
( 8/11/2011 – 11/12/2011 )
 Its held on 8/11
 The transfer of ownership of the project from
contractor to client can have an effect on health
and safety, reliability, standards of operation,
maintenance and operational cost efficiencies to
the University. The transfer/handover period can
be a very stressful time for contractors’ staff, and
building owners and occupants alike as spaces
become occupied and operation of the facility
starts.
CONCLUSION
After going through all the chapters and phases conducted in order to construct this MiNTSRC research building, it can be concluded that this construction project is a conventional
procurement bidding project that involved small-scaled size construction worth about 4 million
Malaysian Ringgit. It supposed to be completed within 44 weeks (December 2011) but due to
uncertainty of weather, the progress has been delayed about 3 month later (March 2012).
However, the building construction was successfully completed and CPC had been issued.
From summary of tender for this project, total construction cost is RM 4,773,440.00. This
large amount is the breakdown costs for Preliminaries Works (RM249,300.00), Architectural and
Structure Works (RM 2,471,640.00), Cold Water Plumbing (RM48,000.00), Sewerage and
Sanitary Plumbing (RM 44,000.00), Water Reticulation System (RM30,000.00), External Works
(RM153,000.00), Provisional Sum (RM200,000.00) and lastly Prime Cost Sum
(RM1,577,500.00).
REFERENCES :
Lembaga Penyelidikan Undang-undang (2011). Undang-undang Kecil Bangunan Seragam 1984.[P.W. 5178/85].
Selangor Darul Ehsan: International Law Book Services.
Greno, R. (1995). Principles of Construction. 2nd ed. Harlow Essex, England: Longman Group UK Limited.
Austen, A. D. & Heale, R. H. (1997). Mengurus Projek Pembinaan: Panduan Bagi Proses dan Tatacara
(Norlida, A. H. & Dayang, S. A. R.). Kuala Lumpur: Dewan Bahasa dan Pustaka (DBP) (Original title was

published on 1984).
Architectural, Sivil and Quantity Surveyor Units of Pejabat Pembangunan dan Pengurusan Hartabina (PPH)
UTHM.
MiNT-SRC, UTHM (2009). Microelectronics and Nanotechnology - Shamsuddin Research Centre. Reached on
May 7, 2013, from http://fkee.uthm.edu.my/mint-src/
END OF PRESENTATION
THANK YOU FOR YOUR ATTENTION

Q & A session

Mais conteúdo relacionado

Mais procurados

SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)Chong jiayi
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''Nabeel Rajpoot
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT jolynnTJL
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Introduction to Building Construction
Introduction to Building Construction Introduction to Building Construction
Introduction to Building Construction Er.Karan Chauhan
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
PREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMPREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMFarah Sham
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1KhangWei Chin
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing ConstructionLek Yuen
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORTFresher Thinking
 
Structural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project ReportStructural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project Reportherry924
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall constructionABHISHEK THAKKAE
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?Duc Tran Xuan
 
A PowerPoint Presentation On Superstructure
A PowerPoint Presentation On SuperstructureA PowerPoint Presentation On Superstructure
A PowerPoint Presentation On Superstructurekuntansourav
 
Bungalow
Bungalow Bungalow
Bungalow Ah Jun
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 

Mais procurados (20)

Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Introduction to Building Construction
Introduction to Building Construction Introduction to Building Construction
Introduction to Building Construction
 
Construction process
Construction processConstruction process
Construction process
 
PREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMPREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEM
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
Structural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project ReportStructural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project Report
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?
 
A PowerPoint Presentation On Superstructure
A PowerPoint Presentation On SuperstructureA PowerPoint Presentation On Superstructure
A PowerPoint Presentation On Superstructure
 
Bungalow
Bungalow Bungalow
Bungalow
 
Building construction
Building constructionBuilding construction
Building construction
 

Semelhante a GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CASE STUDY: SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FKEE UTHM)

BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Progsharda123
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication TowersTowerpeople
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slabPenny3688
 
Bubble deck & hollow core slab
Bubble deck & hollow core slabBubble deck & hollow core slab
Bubble deck & hollow core slabErik Ong
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexDhananjay Singh
 
A Review On Analysis And Design Of Precast Structures
A Review On Analysis And Design Of Precast StructuresA Review On Analysis And Design Of Precast Structures
A Review On Analysis And Design Of Precast StructuresDaniel Wachtel
 
Pre-Cast Technology for Green field
Pre-Cast Technology for Green fieldPre-Cast Technology for Green field
Pre-Cast Technology for Green fieldSuresh C Tripathi
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 
Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”ankialok
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
 
Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”ankialok
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentationsomitra bhardwaj
 
Construction Estimate, Finding natives
Construction Estimate, Finding nativesConstruction Estimate, Finding natives
Construction Estimate, Finding nativesdaffysuburb8048
 

Semelhante a GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CASE STUDY: SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FKEE UTHM) (20)

Table formwork
Table formwork Table formwork
Table formwork
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Pro
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication Towers
 
Site report 1
Site report 1Site report 1
Site report 1
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
 
Bubble deck & hollow core slab
Bubble deck & hollow core slabBubble deck & hollow core slab
Bubble deck & hollow core slab
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complex
 
A Review On Analysis And Design Of Precast Structures
A Review On Analysis And Design Of Precast StructuresA Review On Analysis And Design Of Precast Structures
A Review On Analysis And Design Of Precast Structures
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
Pre-Cast Technology for Green field
Pre-Cast Technology for Green fieldPre-Cast Technology for Green field
Pre-Cast Technology for Green field
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”Seismic analysis of multi storey reinforced concrete buildings frame”
Seismic analysis of multi storey reinforced concrete buildings frame”
 
INDL PPT 1.pptx
INDL PPT 1.pptxINDL PPT 1.pptx
INDL PPT 1.pptx
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Construction Estimate, Finding natives
Construction Estimate, Finding nativesConstruction Estimate, Finding natives
Construction Estimate, Finding natives
 

Último

DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRADUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRATanmoy Mishra
 
Ultra structure and life cycle of Plasmodium.pptx
Ultra structure and life cycle of Plasmodium.pptxUltra structure and life cycle of Plasmodium.pptx
Ultra structure and life cycle of Plasmodium.pptxDr. Asif Anas
 
The Singapore Teaching Practice document
The Singapore Teaching Practice documentThe Singapore Teaching Practice document
The Singapore Teaching Practice documentXsasf Sfdfasd
 
How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17Celine George
 
M-2- General Reactions of amino acids.pptx
M-2- General Reactions of amino acids.pptxM-2- General Reactions of amino acids.pptx
M-2- General Reactions of amino acids.pptxDr. Santhosh Kumar. N
 
How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17Celine George
 
General views of Histopathology and step
General views of Histopathology and stepGeneral views of Histopathology and step
General views of Histopathology and stepobaje godwin sunday
 
Quality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICEQuality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICESayali Powar
 
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdfP4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdfYu Kanazawa / Osaka University
 
How to Use api.constrains ( ) in Odoo 17
How to Use api.constrains ( ) in Odoo 17How to Use api.constrains ( ) in Odoo 17
How to Use api.constrains ( ) in Odoo 17Celine George
 
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptxSandy Millin
 
Drug Information Services- DIC and Sources.
Drug Information Services- DIC and Sources.Drug Information Services- DIC and Sources.
Drug Information Services- DIC and Sources.raviapr7
 
The Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George WellsThe Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George WellsEugene Lysak
 
CapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapitolTechU
 
Patient Counselling. Definition of patient counseling; steps involved in pati...
Patient Counselling. Definition of patient counseling; steps involved in pati...Patient Counselling. Definition of patient counseling; steps involved in pati...
Patient Counselling. Definition of patient counseling; steps involved in pati...raviapr7
 
Maximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdf
Maximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdfMaximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdf
Maximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdfTechSoup
 
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...Nguyen Thanh Tu Collection
 
Prescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptxPrescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptxraviapr7
 
Philosophy of Education and Educational Philosophy
Philosophy of Education  and Educational PhilosophyPhilosophy of Education  and Educational Philosophy
Philosophy of Education and Educational PhilosophyShuvankar Madhu
 
Diploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdfDiploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdfMohonDas
 

Último (20)

DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRADUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
 
Ultra structure and life cycle of Plasmodium.pptx
Ultra structure and life cycle of Plasmodium.pptxUltra structure and life cycle of Plasmodium.pptx
Ultra structure and life cycle of Plasmodium.pptx
 
The Singapore Teaching Practice document
The Singapore Teaching Practice documentThe Singapore Teaching Practice document
The Singapore Teaching Practice document
 
How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17
 
M-2- General Reactions of amino acids.pptx
M-2- General Reactions of amino acids.pptxM-2- General Reactions of amino acids.pptx
M-2- General Reactions of amino acids.pptx
 
How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17
 
General views of Histopathology and step
General views of Histopathology and stepGeneral views of Histopathology and step
General views of Histopathology and step
 
Quality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICEQuality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICE
 
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdfP4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
 
How to Use api.constrains ( ) in Odoo 17
How to Use api.constrains ( ) in Odoo 17How to Use api.constrains ( ) in Odoo 17
How to Use api.constrains ( ) in Odoo 17
 
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
2024.03.23 What do successful readers do - Sandy Millin for PARK.pptx
 
Drug Information Services- DIC and Sources.
Drug Information Services- DIC and Sources.Drug Information Services- DIC and Sources.
Drug Information Services- DIC and Sources.
 
The Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George WellsThe Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George Wells
 
CapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptx
 
Patient Counselling. Definition of patient counseling; steps involved in pati...
Patient Counselling. Definition of patient counseling; steps involved in pati...Patient Counselling. Definition of patient counseling; steps involved in pati...
Patient Counselling. Definition of patient counseling; steps involved in pati...
 
Maximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdf
Maximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdfMaximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdf
Maximizing Impact_ Nonprofit Website Planning, Budgeting, and Design.pdf
 
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
CHUYÊN ĐỀ DẠY THÊM TIẾNG ANH LỚP 11 - GLOBAL SUCCESS - NĂM HỌC 2023-2024 - HK...
 
Prescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptxPrescribed medication order and communication skills.pptx
Prescribed medication order and communication skills.pptx
 
Philosophy of Education and Educational Philosophy
Philosophy of Education  and Educational PhilosophyPhilosophy of Education  and Educational Philosophy
Philosophy of Education and Educational Philosophy
 
Diploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdfDiploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdf
 

GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CASE STUDY: SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FKEE UTHM)

  • 1. FACULTY OF CIVIL AND ENVIROMENTAL ENGINEERING BUILDING CONSTRUCTION BFC4083/ BFC40803 (SECTION-01) GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (MAKMAL NANO TEKNOLOGI UNTUK PUSAT KECEMERLANGAN MICROELEKTRONIK DAN NANO TEKNOLOGI – SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FKEE) PRESENTATION DATE: 15th May 2013 (Week 12nd) LECTURER : PN. NOR AZIZAH BT. ADNAN GROUP MEMBERS: MUHAMAD FIRDAURS BIN ABDULLAH (AF090289) NUR HAMIZAH BT ISMAIL (AF090337) MOHD FARIS BIN NASRUDIN (CF100089) MOHD NASRUL NIZAM BIN MOHD YAHAYA (CF100126) MOHD KHUSYAIRIE BIN ARSAD (CF100232)
  • 2. TITLE OF PROJECT & BUILDING CADANGAN MEMBINA DAN MENYIAPKAN MAKMAL NANO TEKNOLOGI UNTUK PUSAT KECEMERLANGAN MICROELEKTRONIK DAN NANO TEKNOLOGI – SHAMSUDIN RESEARCH CENTRE (MINT-SRC) FAKULTI KEJURUTERAAN ELEKTRIK DAN ELEKTRONIK (FKEE) DI UNIVERSITI TUN HUSSEIN ONN MALAYSIA.
  • 3.        Owner Project : UTHM Project Start : 7/02/2011 Project Finish : 11/12/2011 Construction Period : 44 weeks Contractor : ROSHA DYNAMIC SDN BHD Cost of construction : RM4,773,440.00 Superintendent Officers : Naib Canselor UTHM
  • 4. OBJECTIVE/AIMS This proposed building is constructed for Faculty of Electric and Electronic Engineering (FKEE) which its function to provide various state-of-the-art research facilities such Transmission Electron Microscope Lab, Field Emission Scanning Electron Microscope & Electron Beam Litography Lab and etc. It also will provide comfortable Researcher Room, head of laboratory room, room for printing, meeting, preparation and briefing. It also consist of lobby area, restroom, prayer room and M&E utilities room (refer to Appendix 4A - Ground Floor Plan). For Block A’s 1st Floor Level, according to plan, it consists of Reactive Ion Etching Lab, Annealing Furnace, Pulsed Laser Deposition System Lab, Preparation Room, Focused Ion Beam Lab, Inductively Coupled Plasma Deposition Lab, Magneton Sputtering Lab and etc. Technically, expansion of this kind of centre of excellence is to support the university for Research, Development and Commercialization (RDC), University-University and UniversityIndustry Partnership as well as to lead research in microelectronics, semiconductors and nanotechnology. It also is built for developing high prestige and excellence culture, develop a 'First Class Mindset' and ability to produce high quality R&D and encourage development through networking and co-operation.
  • 5. LOCATION PLAN & SITE PLAN
  • 7. GENERAL INFO CONSIDERED BEFORE CONSTRUCTION PROJECT START - Received of Letter Award - Before a project can be started, an appointed contractor must receive an Award Letter (also known as Letter of Acceptance) from client (UTHM) - Site possession is approved once the contractor received and signed Letter of Acceptance from Pegawai Penguasa. In this project, the date of site possession is stated begins from 7th of February 2011. PROJECT FINISH – Granted with Certificate of Practical Completion - Once the work has been verified as completed, a Certificate of Practical Completion (CPC) (see Appendix 1B) will be issued to the contractor. Since that, it marked the start of liability period duration for the building PRE-CONSTRUCTION WORKS - These included Preliminaries work that need to be done at early stage of construction such as proper site layout planning, hoarding the area of works, site office, access road, etc. It can be divided into three part, namely Initial Cost, Recurring Cost and Completion Cost.
  • 8. - It also includes design stage that involved of appointment of Professional Engineer (P.E) from contractor and preparing design/Shop Drawing. Although all the construction drawing has been given during bidding process, but there will be some changes need to be done once the construction need to be started. MATERIAL PROCUREMENT - This procurement will occur throughout the duration of project. Engineer, consultant, architecture and contractor will deal about the product that need to be used. Manufacturers of product will offer their product according to the architectural specification for the building. Surat Setuju Terima Tender Sijil Perakuan Siap Kerja
  • 9. SITE CLEARANCE  Site clearance involves the removal of walls, hedges, ditches, and trees, other vegetation and services from the site. It can also involve the clearance of fly-tipped materials
  • 10. SITE INVESTIGATION  Site investigation is the most important element in the process of geotechnical design for a building. If no site investigation or inadequate site investigation, geotechnical design will be incomplete. It is identified as the main factors that cause failure and related problems in construction.
  • 11. SETTING OUT  Survey and record the existing ground level at each pile location. Set out the pile location in accordance with the Engineer’s working drawings using a theodolite with the accuracy required in the specifications. All setting out should refer to the reference points and the related Contract Drawings. In order to monitor the position of the steel casing, control pins will be established with two orthogonal positions offset from the centre of the pile.
  • 12. TESTING OF PILES  In order to assure the quality of concrete and steel that will be used during pile construction a sequence of quality control test shall be performed. There will be taken cube specimens from concrete and will be reserved under the appropriate curing ambiance. The 7 days compressive strenght of the concrete for 2 specimen and 28 days for 1 specimen shall be checked periodically by unconfined compression tests. Also tensile strenght tests shall be applied to the reinforcement bars.
  • 13. LOAD TEST  Planted pile capacity often set using Hiley formula. Because it shaped the ability empirikel then obtained must be confirmed with a test pile. Type of test is often done for concrete pile load test is upheld 'maintained load test'.  Function Test Pile (Load Test)  To determine the maximum liability of the ability to realize  To ensure that the pile is acceptable from the point of planting structure  To determine the relationship between the deposition of 'settlement' pile with a load 'load' incurred.
  • 14. DRIVE PILE A pile driver is a mechanical device used to drive piles into soil to provide foundation support for buildings or other structures. The term is also used in reference to members of the construction crew that work with piledriving rigs.
  • 15. Type Drive Pile  A hydraulic hammer is a modern type of piling hammer used in place of diesel and air hammers for driving steel pipe, precast concrete, and timber piles. Hydraulic hammers are more environmentally acceptable than the older, less efficient hammers as they generate less noise and pollutants. However, in many cases the dominant noise is caused by the impact of the hammer on the pile, or the impacts between components of the hammer, so that the resulting noise level can be very similar to diesel hammers.
  • 16. PDA TEST  The Pile Driving Analyzer (PDA) is a powerful tool to assess pile driving and High Strain Dynamic Pile (HSDP) load testing which may supplement or replace static testing. The PDA is seeing increasing usage in the testing of the various types of cast-in-place piles. In some parts of the world, this type of testing is the most common use for the PDA. This solution is particularly attractive for very large, high capacity piles where the large capacity makes a static test extremely costly
  • 17. PILE CAP  A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation.  It usually forms part of the foundation of a building, typically a multi-storey building, structure or support base for heavy equipment.  The cast concrete pile cap distributes the load of the building into the piles.  A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence
  • 18. COLUMN STUMP  Column Stump is a column that considered as lower structure because it is located in the ground below the waterproof layer at ground floor slab. The position is vertical above the foundation. The function of the column stump is to transfer load of building to the foundation. Column stump will receive load from ground beam, column and then will transfer the load to the foundation.The columns can be made from steel tube, pre cast concrete or treated timber these need to be designed by an engineer for correct sizing
  • 19. GROUND BEAM    This type of ground beam is the most used in building construction. It is the beam which both its ends are tied up at the column and lying between the two column. The beam fixes and holds fitly the columns in order to stabilize it. In addition, it also acts to bear all the loads come from the wall which constructed parallel with the beam
  • 20.  A ground beam normally should consist of following items; · Reinforcements · Concrete · Linkers  The reinforcements can be placed at center of that beam.  The sizes of main reinforcement play important role in determine the strength of a beam.  Ground beam usually does not have secondary beam, only has primary beam. The ground beam construction will be started after a column stump has finish. After the column stump has ingrained in foundation and has corpulent on level as wanted.
  • 21. INTRODUCTION TO SUPERSTRUCTURE WORKS • A superstructure is an upward extension of an existing structure above baseline. Part of areas that involved in superstructure include choice of building fabrics : • concrete • choice of floor structure • block work and steel • beam open plans area • selection of insulation cost and efficiency analysis • determination of cladding material to be used • roof structure detailing .
  • 22. OBJECTIVE The main objective of superstructure : • To distribute the load to the foundation • Stabilized the load from building • To transfer the load from the roof to the ground vertically.
  • 23. FORMWORK • A table is built pretty much the same way as a beam formwork but the single parts of this system are connected together in a way that makes them transportable. The most common sheathing is plywood • The joists are either made from timber, wood I-beams, aluminium or steel. • The stringers are sometimes made of wood I-beams but usually from steel channels. These are fastened together (screwed, weld or bolted) to become a "deck". These decks are usually rectangular but can also be other shapes.
  • 24. ANTI TERMITE TREATMENT • The purpose of spreading anti termite is to prevent the termite from degrading the surface of the structure • Usually the anti termite are spread to the reinforcement an d the base formwork.
  • 25. SLAB STRUCTURE • The plastic layer is to prevent the water seepage from rise toward the slab and slowly reduce the strength of concrete and reinforcement. • Generally consists of a layer of sand 25 - 50 mm thick or 50 - 75 mm thick layer of weak concrete • Large in-situ ground slab of 150mm thick is poured on top of the pile ca
  • 26. BEAM AND COLUMN • A suspended span are used • .It is a simple beam supported by the overhangs of two adjoining spans with pinned construction joints at points of zero moment. • A reinforced concrete design.
  • 27. INTERNAL AND EXTERNALL WALL • a brick wall and dry wall partition are used for the internal wall as for the external wall, the brick wall is selected as an external wall. Type of bond that used in this construction is typical Flemish bond of brick. • Internal wall:used a dry wall partition .It is lightweight.The drywall partition lead for better acoustic insulation, thermal insulation and resistance to fire and damp conditions.
  • 28. Roof strucutre • • • • steep roof is selected for this project.a steel truss and bracing are installed for roof frame structure advantages of steep roof are when it was raining, the water can drain quickly,They can therefore be covered with materials that are fabricated and applied in small, overlapping units which can categorized to shingles of wood or slate and tiles of fired clay or concrete. The shingles are inexpensive and easy to installed. For the effects of thermal e on and contraction, and of movements in the structure that supports the roof, are minimized by the ability of the small units to move with respect to one another. It is also easy to repaired. The selection of material for roof is 0.48 thickness standing seam metal roofing deck cover with 50 mm thickness of rock wool aluminium sisilation ,chicken wire mesh based on material
  • 30. Plaster/ skim coat Wall Tiling Painting FINISHING WORKS Internal Works Ceiling Floor Mineral Fibre Board (MBF) Cement Render Floor Tile Wall Staircase Ceiling/ Soffit Beam Finishes Floor Plaster/ skim coat Aluminium Louvre Wall External Works Ceiling Aluminium Composite Painting Aluminium Strip Ceiling Floor Cement Render
  • 31. Internal Works WALL: Plastering Works/ Skim Coat After brickwall has been constructed, plastering work will take place. Plastering work refers to construction or ornamentation done with plaster, such as a layer of plaster on an interior wall or plaster decorative moldings on ceilings or walls Skim Coating is the process of applying a layer of muddy plaster compound to rough walls to either smooth or repair them. It is done to fill deep scratches or holes or to replace water-damaged portions of drywal
  • 32. Internal Works WALL: Tiling & Painting This tiling work is carried out on the certain part of the building wall such as pantry and toilet. It is carried out in the same period as the plastering works/ skim coat took place. The purpose of painting the wall is to hide the grain and texture of the substrate by applying an opaque coating. Paint is an opaque coating made from a mixture of solid pigment and a liquid medium.
  • 33. Internal Works CEILING: Suspended Ceiling - MBF The ceiling is installed just a week later after plastering work is begun. It can be said this ceiling installation is performed at the same time as the plastering, tiling and wall painting is in progress. Suspended ceilings are ceilings that fostered the suspension system using wire or rod suspension buffer. The ceilings are not receiving support from the walls. Mineral Fibre Board chosen must certified and approved by SIRIM QAS standard, comply with BS476: Part 7: 1997. The thickness of the board is 15mm and it has density of 334kg/m3.
  • 34. Internal Works FLOOR: Cement Render & Floor Tiles Cement rendering is the application of a premixed layer of sand and cement to brick, cement, stone or mud brick. It is often textured, coloured or painted after application. Depending on the 'look' required, rendering can be fine or coarse, textured or smooth, natural or coloured, pigmented or painted. Ceramic tile and stone flooring materials are solid and durable. In general, larger tiles are used in larger rooms and small tiles used in smaller spaces. Ceramic floor tile is made from various clays, is somewhat brittle, and takes a very sturdy sub-floor.
  • 35. Staircase CEILING/ SOFFIT BEAM FINISHES This Soffit, formed as a ceiling, to fix underneath, in architecture it is described as the underside of any construction element. Examples of soffits include the underside of a flight of stairs, the underside of a ceiling to fill the space above the stairways, at the corner of the ceiling and wall.
  • 36. Staircase WALL AND FLOOR FINISHES Wall finishes are carried once the ceiling/ soffit beams finishes has been accomplished. It is same process and using the same finishing material as the internal wall finishing describe above such as plastering/ works, tiling works and wall painting. After wall finishes are completed within duration of 6 days, floor finishes will take place. The same process and material as described before for internal floor finishing, will be applied to this staircase.
  • 37. External Works WALL: Plastering Works/ Skim Coat This work is done together with internal wall finishes. It is started at the same week as plastering works for internal wall, but it has been finished a month later than internal wall finishes (plastering). There is not much different between plastering work for internal and external wall. The thickness of plaster is 20mm on both sides.
  • 38. External Works WALL: Aluminium Louvre Aluminium louvre that is being used is modern louvers that cannot be opened and closed with a metal lever, pulleys, or through motorized operators. It is installed permanently at building façade for reduce sun glare into internal space, prevent direct heating of sunlight as well as aesthetic value. Below is the location of alumium louvre:
  • 39. External Works WALL: Aluminium Composite Aluminium Composite Panels are the ideal cladding for interior and exterior surfaces. The material is rigid, light and durable and can be easily transformed into curved and multi planar surfaces. Composite Panels are available in various colours. But for this building, it comes in grey-silvered colour to give an elegant, modern and corporate look to the building facade:
  • 40. External Works WALL: Painting This kind of finishing is applied throughout building external wall same as internal wall painting process. It is denoted by ‘W1 - Plaster and Paint’ in construction plan as shown in the previous table ‘WALL FINISHES’
  • 41. External Works CEILING: Aluminium Strip Ceiling Aluminium Strip Ceilings are roll-formed from pre-coated aluminium coils. Strip Ceilings are the modern way to panel for ceiling and wall fronts. It is widely use in building external wall and ceiling to improve architectural look.
  • 42. External Works FLOOR: Cement Render Cement render as described previously on internal floor finishes is mixture of lime, cement, sharp sand and water. According to work planning schedule, the external floor finished by this cement render is the last step among other kind of floor finishes of the building but once it’s started, its progress flow simultaneously with other finishes and might end at the same time with others.
  • 45. 2.Surau and ablution area:  To accommodate 5 person with 1 nos.ablution tap  To provide cabinet and shoe rack  To provide benches
  • 46. Signage  Provide new directional, operational, regulatory and door signs  Provide new large illuminated external building sign for the building
  • 47. Landscaping works  To provide hard and soft landscaping (trees, shrub and close turf) for all areas not covered with footpaths, drains and road pavement.  The parking area shall be planted with shade trees and a mixture of feature planting along building frontage.  Features palms and shade trees shall be planted along pedestrian path to serve as the linkage between parking area to building.
  • 48. Washroom Partition  For block A and B washroom partition system to be used for W.C. Cubicles forming dividers, frontals, end panels and doors. Assembly using customizeed aluminium extrusion and fixing with manufacturer’s standard hardwares thickness : 18mm thick double faced autoclaved high density cementations fibreboard.  Wall connection : Painted aluminium channels  Head rail : Painted aluminium head rail  Doors : 2000 x 600 x18 mm minimum solid core, moisture resistant fibre board.
  • 49. Sundries • The perimeter drain for blok A and B use 230 mm half round reinforce concrete drain. This work progress takes about 70 days, from 22 September 2011 to 11 December 2011.
  • 50. Water Supply and Reticulation  The water supply and reticulation work takes about 38 days, from 30 September 2011 to 12 November 2011.These works include the installation of piping,jointing and connection works and the hydrant system.After finished these all installation, testing works have been done for 7 days from 5 November 2011 to 12 November 2011.
  • 51. Road Works  The Infra works takes about 24 days from 17 October 2011 to 12 November 2011.The infra works include the road works, road kerb and road marking. Asphaltic Concrete  This project use asphaltic concrete BC (ACB 28) and (ACW 14) from Hanson Quarry SDN.BHD.
  • 52. Road kerb Road marking  Road kerb and road marking work takes about 14 days from 28 October 2011 to 12 November 2011 to finished.
  • 54. COLD WATER ( 7/2/2011 – 22/11/2011 )  Piping works Piping work for colwater supply was start at 5/7 All pipe routing shall be as shown on approved Shop drawings. All Pipe supports and clamps shall be installed as per manufacturer recommendations. installation of all supports shall be in accordance with approved supporting detail drawings
  • 55.  Installation of FRP water tank FRP water tank was start from 7/2 The water tank that use in this building was fiberglass reinforced plastic. The cylindrical series with capacity up to 110,000 gallons  Testing work After the all the piping work and the installation was finished at 15/11. The test can be carryout. The test has be done in some step
  • 56. SANITARY PLUMBING ( 5/7/2011 – 22/11/2011 )  Piping work Plumbing work carried out on 7/5 after installation plan approved indoor toilet.  Construct 2 nos new manhole The work start at 10/10 after the completion of plumbing work. Drainage system used is below ground drainage. VCP pipe used is 100mm in size and approved by sirim
  • 57.  Installation of septic tank Septic tank installation started on 21/10. Hole dug to accommodate septic tank and sandsized 1.3mx1.3mx1.3m included 10cm high.  Testing works The test have been done at 15/11 after the Resident Representative witness the tests and approve the pipe installation
  • 58. PROJECT HAND OVER ( 8/11/2011 – 11/12/2011 )  Its held on 8/11  The transfer of ownership of the project from contractor to client can have an effect on health and safety, reliability, standards of operation, maintenance and operational cost efficiencies to the University. The transfer/handover period can be a very stressful time for contractors’ staff, and building owners and occupants alike as spaces become occupied and operation of the facility starts.
  • 59. CONCLUSION After going through all the chapters and phases conducted in order to construct this MiNTSRC research building, it can be concluded that this construction project is a conventional procurement bidding project that involved small-scaled size construction worth about 4 million Malaysian Ringgit. It supposed to be completed within 44 weeks (December 2011) but due to uncertainty of weather, the progress has been delayed about 3 month later (March 2012). However, the building construction was successfully completed and CPC had been issued. From summary of tender for this project, total construction cost is RM 4,773,440.00. This large amount is the breakdown costs for Preliminaries Works (RM249,300.00), Architectural and Structure Works (RM 2,471,640.00), Cold Water Plumbing (RM48,000.00), Sewerage and Sanitary Plumbing (RM 44,000.00), Water Reticulation System (RM30,000.00), External Works (RM153,000.00), Provisional Sum (RM200,000.00) and lastly Prime Cost Sum (RM1,577,500.00).
  • 60. REFERENCES : Lembaga Penyelidikan Undang-undang (2011). Undang-undang Kecil Bangunan Seragam 1984.[P.W. 5178/85]. Selangor Darul Ehsan: International Law Book Services. Greno, R. (1995). Principles of Construction. 2nd ed. Harlow Essex, England: Longman Group UK Limited. Austen, A. D. & Heale, R. H. (1997). Mengurus Projek Pembinaan: Panduan Bagi Proses dan Tatacara (Norlida, A. H. & Dayang, S. A. R.). Kuala Lumpur: Dewan Bahasa dan Pustaka (DBP) (Original title was published on 1984). Architectural, Sivil and Quantity Surveyor Units of Pejabat Pembangunan dan Pengurusan Hartabina (PPH) UTHM. MiNT-SRC, UTHM (2009). Microelectronics and Nanotechnology - Shamsuddin Research Centre. Reached on May 7, 2013, from http://fkee.uthm.edu.my/mint-src/