SlideShare uma empresa Scribd logo
1 de 12
Baixar para ler offline
Free PMP Questions & Answers

         1   All of the following processes form part of the Executing process group              Ch.3
             except:
             a     Performing activities in accordance with the project management plan.
             b     Managing changes to the deliverables.
             c     Completing the work in accordance with the defined quality framework and
                   specification.
             d     Coordinating people and resources.
         Answers         Reference: PMBOK® Guide p55-56 Sect: 3.5
             e     The best answer is B
                    i    Managing changes is part of Integrated Change Control; this is part of
                         the Monitoring and Controlling process group.
                   ii    The Executing process group consists of those processes performed
                         to complete the work defined in the project management plan to
                         satisfy the project specifications.
                   iii   An output from Integrated Change Control is updates to the project
                         management plan to incorporate approved changes.


         2   Which calculation is correct for the To-Complete Performance Index (TCPI)            Ch.7
             based on the Estimate At Completion (EAC)?
             a     AC + (BAC – EV)
             b     (BAC - EV)/(BAC - AC)
                             cum
             c     BAC/CPI
             d     (BAC - EV)/(EAC - AC)
         Answers         Reference: PMBOK® Guide p185 Sect 7.3.2.3
             e     The best answer is D
                    i    TCPI is the projection of the future cost performance that must be
                         achieved on the remaining work to achieve a management goal such
                         as the original Budget At Completion (BAC) or a calculated Estimate
                         At Completion (EAC).
                   ii    All of these formula use standard Earned Value Management
                         acronyms:
                         Option ‘a’ calculates EAC based on future work being performed at
                         budgeted rates
                         Option ‘b’ calculates TCPI based on BAC (the question asked for
                         EAC)
                         Option ‘c’ calculates EAC based on future work being performed at
                         the same CPI as the completed work.


     Take any of our PMP courses, you will have access to 100’s of similar questions and importantly,
     the knowledge needed to answer them effectively.
     -   More on the PMP Examination:                     www.mosaicprojects.com.au/Training-CAPM.html
     -   Mosaic’s self-paced Mentored Email™ course: www.mosaicprojects.com.au/Training-Mentored.html
     -   More questions? Our PM Final exam simulator: www.mosaicprojects.com.au/Training_PM-Final.html



© Practical PM Pty Ltd                                   1                          www.mosaicprojects.com.au
Free PMP Questions & Answers

        3    A Pareto diagram shows:                                                               Ch.8
             a    The 80% of the work that is important.
             b    The qualitative improvement trend demonstrated by implementing a Six
                  Sigma initiative.
             c    A histogram ordered by frequency of occurrence.
             d    The 20% of the work that is causing the most issues.
        Answers          Reference: PMBOK® Guide p210-211 Section 8.3.2.5
             e    The best answer is C
                   i     A Pareto diagram is a specific type of histogram, ordered by
                         frequency of occurrence.
                  ii     It is used to show how many defects were generated by each
                         category of identified cause to allow remedial action to be focussed on
                         the most significant.
                  iii    The Pareto principle (also known as the 80-20 rule) is different, see:
                         http://en.wikipedia.org/wiki/Pareto_principle


        4    Integrated Change Control includes all of the following tools and                     Ch.4
             techniques except:
             a    Project plan updates.
             b    Expert judgement.
             c    Change control meetings.
             d    A change control board to approve or reject changes.
        Answers          Reference: PMBOK® Guide p.98-99 Sect:4.5.2
             e    The best answer is A
                   i     Project plan updates are an output from Integrated Change Control.
                  ii     Expert judgement and the change control meetings, of the change
                         control board are the defined tools and techniques for this process.


        5    All of the following are true concerning expected monetary value (EMV)                Ch.11
             except:
             a    Decision tree analysis is more effective using net present values (NPV) in
                  its calculations rather than EMV.
             b    The EMV of an opportunity is generally a positive value.
             c    EMV is a statistical concept that calculates the average value of a future
                  scenario that may, or may not happen by multiplying the value of each
                  possible outcome by the probability of it occurring and summing the
                  products.
             d    The EMV of a threat is generally a negative value.
        Answers          Reference: PMBOK® Guide p298 Sect: 11.4.2.2
             e    The best answer is A
                   i     EMV is calculated by EMV = probability * impact.
                  ii     If there are several different possibilities, the EMV is calculated for
                         each option and the EMVs added together to give an overall, value.
                  iii    Decision tree analysis is based on EMV.




© Practical PM Pty Ltd                                    2                            www.mosaicprojects.com.au
Free PMP Questions & Answers

        6    Co-location is one of the techniques used to:                                          Ch.9
             a    Ensure effective control over the work of the project team.
             b    Develop the project team.
             c    Define the organisation structure.
             d    Acquire the project team.
        Answers          Reference: PMBOK® Guide p234 Sect: 9.3.2.5
             e    The best answer is B
                   i     Co-location involves placing the active project team members in one
                         location to enhance their ability to perform as a team.
                  ii     This is one of the tools and techniques listed in the Develop Project
                         Team process.
                  iii    Co-location may assist in improving the coordination and control of
                         the project’s work but this is a secondary benefit and consequently not
                         the best answer from the PMBOK’s perspective.


        7    When managing a complex, cross functional project; which of the                        Ch.2
             following structures will give the project manager the most authority?
             a    Balanced matrix.
             b    Strong matrix.
             c    Functional.
             d    Weak matrix.
        Answers          Reference: PMBOK® Guide p28-30 Sect:2.4.2
             e    The best answer is B
                   i     Strong matrix organisations provide the project manager with a similar
                         high level of authority to a projectized organisation and full time
                         project administration staff.
                  ii     Matrix organisations include both functional and projectized
                         management structures.


        8    Leadership in a project environment should demonstrate all of the                      Apx.G
             following characteristics except:
             a    The focusing of the efforts of a group of people on achieving a common
                  objective.
             b    High levels of respect and trust.
             c    The ability to get things done through others.
             d    A primary focus on external senior managers and other key stakeholders to
                  ensure the project is a success through managing upwards.
        Answers          Reference: PMBOK® Guide Appendix G, p409
             e    The best answer is D
                   i     Whilst managing upwards (or advising upwards) is a key skill of the
                         project manager, it is not the primary focus of leadership.
                  ii     The primary focus of project leadership is on developing the project
                         team and empowering them to achieve the project outcomes.




© Practical PM Pty Ltd                                   3                              www.mosaicprojects.com.au
Free PMP Questions & Answers

        9    The processes included in project communication management are:                             Ch.10
             a       Collect Requirements, Plan Communications, Distribute Information,
                     Manage Expectations and Report Performance.
             b       Identify Stakeholders, Collect Requirements, Plan Communications,
                     Distribute Information, Manage Stakeholder Expectations and Report
                     Performance.
             c       Identify Stakeholders, Plan Communications, Distribute Information,
                     Manage Stakeholder Expectations and Report Performance.
             d       Collect Requirements, Plan Communications, Distribute Information,
                     Update Project Documentation and Report Performance.
        Answers                 Reference: PMBOK® Guide p243-244
             e       The best answer is C
                      i         This is a common type of question.
                     ii         Collect Requirements is a Scope Management process.
                     iii        Update project documentation is an output from a range of processes.


        10       Which of the following is true concerning the work breakdown structure                  Ch.5
                 (WBS)?
                 a        The PMI WBS and PRINCE2 product breakdown structure (PBS) are
                          effectively the same thing.
                 b        The WBS is the same as the organisational breakdown structure (OBS).
                 c        The WBS is a deliverable oriented, hierarchical decomposition of the work
                          to be executed by the project team.
                 d        The WBS is the bill of materials (BoM) needed to accomplish the work of
                          the project.
        Answers                  Reference: PMBOK® Guide p116 Sect: 5.3
                 e        The best answer is C
                           i     The difference between the PBS and the WBS is the PBS only
                                 contains the products to be delivered, the WBS contains all of the
                                 work needed to achieve the project’s objectives including all of the
                                 deliverables (not just the ‘product’). Non-product elements in the
                                 WBS include project management work, safety and hygiene work, etc.
                          ii     The OBS is the document that defines the lines of management
                                 responsibility within the project. The point where the OBS and WBS
                                 intersect is known as a ‘control account’ and defines the manager
                                 responsible for a section of the project work.
                          iii    The BoM only describes the materials used in the work, not the other
                                 elements of the project (eg, labour). The WBS defines all of the work
                                 and consequently all of the costs.


        11       All of the following are true of cost plus fixed fee (CPFF) contracts, except:          Ch.12
                 a        The seller is reimbursed for all allowable costs incurred performing the
                          contract work.
                 b        The seller receives a fixed fee calculated as a percentage of the initial
                          estimated project cost.
                 c        The fee does not change based on the performance of the seller.
                 d        The seller receives a fee calculated as a fixed percentage of the actual
                          project cost.



© Practical PM Pty Ltd                                          4                           www.mosaicprojects.com.au
Free PMP Questions & Answers

        Answers          Reference: PMBOK® Guide p323 Sect: 12.1.2.3
              e    The best answer is D
                    i    CPFF contracts pay a fixed fee to the seller based on the initial
                         estimated value of the work.
                   ii    All allowable costs are reimbursed by the buyer.
                   iii   The only time the fee will change is if the buyer changes the scope of
                         the work.


        12    During a meeting with some of your project's stakeholders, you are asked               Ethics
              to add to the project's scope of work. The project records contain
              correspondence from before the Charter was signed in which the project
              sponsor specifically declined the work being requested by these
              stakeholders. The BEST thing for you to do is:
              a    Tell the stakeholders the work cannot be added.
              b    Evaluate the cost and time impacts of adding the work.
              c    Add the work if it can be accommodated within the existing budget.
              d    Talk to the sponsor and let her know of the request.
        Answers          Reference: PMI Code of Professional Conduct
              e    The best answer is A
                    i    PMI expects the project manager to manage! The best thing to do first
                         is try to resolve the problem with the stakeholders. Only is that fails
                         should the problem be escalated to the sponsor.
                   ii    Whilst planning and evaluation are normal 'first steps' in assessing a
                         change, this work was formally excluded from the project before the
                         Charter was signed. Therefore it should not be added without the
                         sponsor's prior approval.


        13    Analogous estimating when applied to a duration is:                                    Ch.6
              a    Based on expert judgement and is consequently more accurate than
                   standard critical path estimating.
              b    Used when there is a limited amount of detailed information available.
              c    A calculation based on a three point estimate using a modified BETA
                   distribution.
              d    The same as ‘bottom up’ estimating.
        Answers          Reference: PMBOK® Guide p149 Sect: 6.4.2.2
              e    The best answer is B
                    i    Analogous estimating uses the duration from a similar completed
                         activity or project as the basis for the current estimate. This is a ‘top
                         down’ estimating technique used when there is little detailed
                         information available.
                   ii    The critical path method is a precise set of calculations applied to the
                         schedule (including the estimated durations). It is not an estimating
                         process.
                   iii   The PERT technique uses three point estimates and a modified BETA
                         distribution to assess the probability of completing the project in a
                         given timeframe.




© Practical PM Pty Ltd                                    5                             www.mosaicprojects.com.au
Free PMP Questions & Answers

        14    The code of accounts:                                                                  Gloss.
              a    Is the system used to keep track of purchases and contracts.
              b    Is any numbering system used to uniquely identify each component of the
                   work breakdown structure.
              c    Links the work breakdown structure to the schedule task identifier.
              d    Is the alpha-numeric reference used in the organisations accounts system
                   to identify cost centres.
        Answers          Reference: PMBOK® Guide Glossary p421
              e    The best answer is B
                   i     The chart of accounts refers to the accounting system, the code of
                         accounts to the WBS. Whilst these should be linked, they are not the
                         same.
                   ii    Links between the WBS and the activities in the schedule are
                         required; however, this information is usually in a code field or a text
                         field, not the Task ID. There are likely to be several activities to each
                         WBS element and the WBS code of accounts is a fixed structure.
                         Task IDs can change.


        15    A procurement audit will consider all of the following except:                         Ch.12
              a    The changes in market conditions between the contract date and the
                   current time.
              b    Any successes or failures in the process that warrant recognition.
              c    The complete procurement process from initial planning through to the
                   administration of the procurement.
              d    Any lessons learned that can be applied to future procurement processes.
        Answers          Reference: PMBOK® Guide p343 Sect: 12.4.2.1
              e    The best answer is A
                   i     PMBOK audits are focused on process improvement. They review
                         how the system is working to learn lessons to apply to future
                         procurements both within the project and on other projects within the
                         organisation.


        16    The Delphi technique has all of the following characteristics except:                  Ch.11
              a    It is a technique to reduce bias and prevent any one person from exerting
                   undue influence.
              b    It is a way to reach a consensus of experts.
              c    It is an Oracle® database application used to optimise future outcomes.
              d    Individual experts are unaware of who else is participating in the process.
        Answers          Reference: PMBOK® Guide p286 sect:11.2.2.2
              e    The best answer is C
                   i     The Delphi technique is a facilitated process to reach a consensus of
                         experts using questions and feedback. Only the facilitator is aware of
                         who is participating.
                   ii    No PMI question is likely to have a proprietary tool as the correct
                         answer.




© Practical PM Pty Ltd                                    6                            www.mosaicprojects.com.au
Free PMP Questions & Answers

        17    A binding contract is legally created when:                                              Law
              a    The formal contract documents are signed by your senior management.
              b    When your legal department advises the contract is acceptable.
              c    The formal contract documents are signed by official representatives of
                   both parties.
              d    There is an offer, acceptance, performance and consideration.
        Answers          Reference: Contract Law
              e    The best answer is D
                    i    Contracts do not have to be in writing or signed. Whilst it is difficult to
                         enforce the terms of a verbal contracts the law will recognise the
                         validity of the agreement.
                   ii    The four basic requirements for a contract are:
                         - Someone makes an offer to do something,
                         - The offer is accepted unconditionally,
                         - There is an intention or actual performance of the offer,
                         - There is an intention or actual transfer of a valuable consideration
                           (the consideration does not have to be money, just of value).
                   iii   There are many additional factors that can influence this basic starting
                         point that project managers and administrators need to be aware of.


        18    The basic decision making styles normally used by project managers                       Apx.G
              include all of the following except:
              a    Coin flip (random).
              b    Command.
              c    Consultation.
              d    Rational choice theory
        Answers          Reference: PMBOK® Guide Appendix G6 p412
              e    The best answer is D
                    i    Rational choice theory is a framework for understanding and often
                         formally modelling social and economic behaviour.
                   ii    The 4 options in the PMBOK are command, consultation, consensus
                         and coin flip.
                   iii   Coin flip is used when it really does not matter which option is chosen
                         as long as there is a decision (eg, should we meet at McDonald’s or
                         Burger King for lunch).


        19    FPIF is an acronym for:                                                                  Gloss.
              a    Fixed Price Incentive Fee
              b    Firm Price Incentive Free
              c    Fixed Price Indicator Factor
              d    Fast Performance Incentive Fee
        Answers          Reference: PMBOK® Guide Glossary p416
              e    The best answer is A
                    i    FPIF is a form of contract where the seller can earn an incentive fee
                         on top of its fixed price for the work if it achieves a specified objective
                         such as a zero accident or defect rate or completion before a
                         specified target date.



© Practical PM Pty Ltd                                     7                             www.mosaicprojects.com.au
Free PMP Questions & Answers


        20    The Control Costs process includes all of the following except:                      Ch.7
              a    Informing appropriate stakeholders of all approved changes and associated
                   costs.
              b    Influencing factors that create changes in the authorised cost baseline.
              c    Developing the cost performance baseline.
              d    Acting to bring expected cost overruns within acceptable limits.
        Answers          Reference: PMBOK® Guide p179-180 Sect 7.3
              e    The best answer is C
                    i    Developing the cost performance baseline is part of the Determine
                         Budget process (see: 7.2.3.1).
                   ii    All of the other options are listed as inclusions in the Control Costs
                         process.


        21    All of the following statements are true about product and project life              Ch.2
              cycles except:
              a    Generally a product lifecycle is contained within a project lifecycle.
              b    A project life cycle is determined by the organisation and generally consists
                   of phases that may be sequential or overlapping.
              c    A product lifecycle is determined by the organisation and generally consists
                   of sequential phases.
              d    Generally a project lifecycle is contained within a product lifecycle.
        Answers          Reference: PMBOK® Guide p18 Sect: 2.1.2
              e    The best answer is A
                    i    Products are created, marketed, upgraded and eventually retired or
                         decommissioned. The phases are determined by the organisation.
                   ii    Projects are used to create the product, upgrade the product and
                         potentially decommission the product. Projects typically fit within or
                         form one phase of the overall product lifecycle.
                   iii   The phases of a project’s lifecycle (eg, design, build, install) are
                         different to the ‘project management phases’ discussed in the
                         PMBOK; project management phases are synonymous with the five
                         process groups. The five process groups (initiate, plan, execute,
                         monitor & control, and close) occur at different levels of intensity in
                         each project, and each phase of a project.


        22    As part of a successful communication, the receiver is responsible for:              Ch.10
              a    Making sure the information is clear and complete, understood and
                   acknowledged.
              b    Making sure the information is received in its entirety, understood correctly
                   and acknowledged.
              c    Making sure the information is clear and complete, understood and agreed
                   with.
              d    Listening actively to ensure all of the information is received.
        Answers          Reference: PMBOK® Guide p255 Sect: 10.2.2.3
              e    The best answer is B




© Practical PM Pty Ltd                                   8                            www.mosaicprojects.com.au
Free PMP Questions & Answers

                    i    Communication can be written or oral, therefore ‘d’ is not the best
                         answer. Both the sender and receiver need to use active listening if
                         the communication is oral.
                   ii    The sender is responsible for making sure the information is clear and
                         complete, not the receiver.
                   iii   For a communication to be successful the receiver needs to
                         acknowledge its receipt to the sender, the receiver does not have to
                         agree with the information.


        23    All of the following people developed management theories focused on                 Mgt.
              motivation except:
              a    Maslow.
              b    McGregor.
              c    Hertzberg.
              d    Deming.
        Answers          Reference: General management theory.
              e    The best answer is D
                    i    W. Edwards Deming is a quality guru.
                   ii    Maslow developed the Hierarchy of Needs.
                   iii   McGregor developed the Theory X and Theory Y
                   iv    Herzberg’s developed the Hygiene Theory


        24    The project charter has all of the following characteristics except:                 Ch.4
              a    Its primary use is to authorise the start of a project or phase.
              b    It provides the project manager with authority to apply resources and
                   expend money on project activities.
              c    Its primary use is to request bids or proposals for the work it defines.
              d    The project charter can be created by the person external to the project,
                   responsible for the authorisation of the work, or that person can delegate
                   the creation of the project charter to the project manager.
        Answers          Reference: PMBOK® Guide p73-74 Sect: 4.1
              e    The best answer is C
                    i    Statements of work (SOW) and other procurement documents are
                         used to request bids or proposals.
                   ii    The work of creating the project charter can be delegated to the
                         project manager; however, the charter should be signed by the person
                         responsible for authorising the project.


        25    All of the following are true concerning enterprise environmental factors           Ch.1
              (EEF) except:
              a    EEF do not include the organisations purchasing guidelines because this
                   type of function is managed by the Accounts Department.
              b    EEF include the tools, systems and software that comprise the project
                   management information system (PMIS).
              c    EEF incorporates the organisation’s culture, structure and processes.
              d    EEF include all relevant laws, regulations and standards imposed by all
                   levels of government, industry bodies and society.



© Practical PM Pty Ltd                                   9                            www.mosaicprojects.com.au
Free PMP Questions & Answers

        Answers          Reference: PMBOK® Guide p14, sect: 1.8
              e    The best answer is A
                   i     EEF refer to both the internal and external environmental factors that
                         surround or influence a project.
                   ii    Purchasing guidelines constrain the project management’s options in
                         respect of acquiring goods and services.


        26    All of the following statements concerning the project scope statement are            Ch.5
              true except:
              a    It is an output of the Verify Scope process.
              b    It describes the project’s deliverables and the work needed to create them.
              c    It may contain explicit scope exclusions that can assist in managing
                   stakeholder expectations.
              d    It provides a common understanding of the project’s scope among the
                   project’s stakeholders.
        Answers          Reference: PMBOK® Guide p115 Sect: 5.2.3.1
              e    The best answer is A
                   i     The project scope statement is an output from the Define Scope
                         process.
                   ii    Clearly documenting work that is ‘out of scope’ helps everyone. A
                         typical example is a project may be scoped to develop training
                         materials for the product being developed, but not to conduct the
                         training. A clear statement that ‘All training will be undertaken by
                         others and is outside of the scope of this project’ prevents
                         stakeholders expecting the project team will undertake the initial
                         training or ‘train-the-trainer’ training. If these requirements are
                         needed, they can be brought into the project’s scope through a
                         change management process.


        27    The cost of quality includes all of the following except:                             Ch.8
              a    Buying professional indemnity insurance.
              b    The cost of defects and rework caused by failing to achieve requirements.
              c    The cost of inspecting and appraising conforming products produced by the
                   project.
              d    Preventing non-conformance to requirements.
        Answers          Reference: PMBOK® Guide p195 Sect: 8.1.2.2
              e    The best answer is A
                   i     Buying insurance is a risk transference process (the risk is transferred
                         to the insurer).
                   ii    The cost of quality (COQ) is the direct costs incurred in prevention,
                         inspection and repairs.




© Practical PM Pty Ltd                                  10                           www.mosaicprojects.com.au
Free PMP Questions & Answers

        28    The responsibility assignment matrix (RAM) shows:                                    Ch.9
              a    The connections between activities and project team members.
              b    The delegation of responsibility through the hierarchically organised
                   management structure.
              c    Accountabilities to assist in team performance appraisals.
              d    The sequence of activities a named resource is responsible for
                   accomplishing.
        Answers          Reference: PMBOK® Guide p221 Sect: 9.1.2.1
              e    The best answer is A
                   i     The RAM chart is used to illustrate the connections between work
                         packages or activities and project team members.


        29    Project management process groups have all of the following                          Ch.3
              characteristics except:
              a    All of the process groups are needed on all projects and all of their
                   interactions apply to each phase of a project as well as the overall project.
              b    The process groups are seldom one time, discrete events; they are
                   overlapping activities that occur throughout the project.
              c    Where a project is divided into phases, the process groups are invoked as
                   appropriate.
              d    The process groups are linked by the outputs they produce.
        Answers          Reference: PMBOK® Guide p39-41 Sect: 3.1
              e    The best answer is A
                   i     Whilst all of the process groups should occur in each project at an
                         appropriate level of intensity, ALL of the processes and interactions
                         within and between process groups are not required on every project
                         or in every phase of a project.
                   ii    The project management team are responsible for determining which
                         processes are appropriate and the appropriate degree of rigour to
                         apply (ref p 38).


        30    Which of the following represent a discretionary dependency?                         Ch.6
              a    Not starting design until all of the approvals have been received.
              b    Waiting the specified 72 hours before stripping formwork from a newly
                   poured concrete slab.
              c    Applying a start-to-start link between two tasks in a PDM network.
              d    Applying a lag of 4 days between two tasks.
        Answers          Reference: PMBOK® Guide p139-140 Sect: 6.2.2.2
              e    The best answer is A
                   i     Any link between two tasks (or activities) may be discretionary or
                         mandatory. The link types in a Precedence network (PDM) are:
                         - Finish-to-start
                         - Start-to-start
                         - Finish-to-finish
                         - Start-to-finish.
                         A lead or a lag may be applied to any of the link types.




© Practical PM Pty Ltd                                  11                           www.mosaicprojects.com.au
Free PMP Questions & Answers

                    ii   Mandatory dependencies are either inherent in the nature of the work
                         (eg, you cannot put concrete into a foundation until you have dug the
                         hole!), or are contractually required. The specification typically forms
                         part of a contract and would mandate the ‘curing time’.
                   iii   Discretionary dependencies are desirable and/or represent best
                         practice. Whilst it is desirable to wait for the final approvals for a
                         project before starting the design it is not mandatory. The project team
                         may decide to take a calculated risk and start some design work
                         before all of the approvals are received.




      References:
      -   Ch.X     = PMBOK® Guide Chapter #
      -   Gloss. = PMBOK® Guide Glossary
      -   Apx.G = PMBOK® Guide Appendix G (Interpersonal Skills)
      -   The PMP exam covers significantly more then the PMBOK, Three sample questions on
          Management Theory, Contract Law and Ethics have been included.



      Important Information: The passing score for the PMP examination is 61% - whilst these questions are
      representative of the style of questions found in the PMP examination, no warranty is offered in respect of
      your likely performance in the examination based on your performance in this limited test. Our experience
      over many years suggests an average score of 75% in our courses translates to a reasonable level of
      comfort in the examination; however, this is based on candidates answering many hundreds of questions.




      Additional Resources:
      -   More information on the PMP Examination:        www.mosaicprojects.com.au/Training-PMP.html
      -   Mosaic’s PM Final question bank:                www.mosaicprojects.com.au/Training_PM-Final.html
      -   Mosaic’s self paced Mentored Email™ course: www.mosaicprojects.com.au/Training-Mentored.html



      Mosaic Project Services Pty Ltd is a PMI approved Registered Education Provider (R.E.P.). We have been
      successfully training PMP candidates to pass their exam for over 10 years. All of Mosaic’s PMP courses are
      pre-approved by PMI for the 35 Hrs of project management training needed to be eligible to apply for the
      examination. For additional information click on the links above or follow the training prompt from our home
      page at www.mosaicprojects.com.au




© Practical PM Pty Ltd                                  12                           www.mosaicprojects.com.au

Mais conteúdo relacionado

Mais procurados

Liberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshareLiberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshareSong Love
 
175 PMP Sample Questions
175 PMP Sample Questions175 PMP Sample Questions
175 PMP Sample Questionszohaibqadir
 
Project management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projectsProject management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projectsPamelaRosaleschicago
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes examJamil Faraj , PMP
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management SampleRavi Nakulan
 
Prince2 for Value Driven Project Management
Prince2 for Value Driven Project ManagementPrince2 for Value Driven Project Management
Prince2 for Value Driven Project ManagementEdureka!
 
Prince2 quick guide
Prince2 quick guidePrince2 quick guide
Prince2 quick guideMaven
 
e-Learning project initiation template
e-Learning project initiation templatee-Learning project initiation template
e-Learning project initiation templateSaffron Interactive
 
Learn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebookLearn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebookKnowledge Train
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperThanh Nguyen
 
Profittme pmp framweork questions
Profittme pmp framweork questionsProfittme pmp framweork questions
Profittme pmp framweork questionsThabet Ali
 

Mais procurados (20)

PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4
 
Liberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshareLiberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshare
 
PgMP
PgMP PgMP
PgMP
 
Online PMP Exam Certification Training - 35 Hours
Online PMP Exam Certification Training - 35 HoursOnline PMP Exam Certification Training - 35 Hours
Online PMP Exam Certification Training - 35 Hours
 
175 PMP Sample Questions
175 PMP Sample Questions175 PMP Sample Questions
175 PMP Sample Questions
 
15 Free PMP Exam Questions
15 Free PMP Exam Questions15 Free PMP Exam Questions
15 Free PMP Exam Questions
 
Project management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projectsProject management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projects
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Exam1
Exam1Exam1
Exam1
 
PMP Exam Sample Questions Set 1
PMP Exam Sample Questions Set 1PMP Exam Sample Questions Set 1
PMP Exam Sample Questions Set 1
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Prince2 for Value Driven Project Management
Prince2 for Value Driven Project ManagementPrince2 for Value Driven Project Management
Prince2 for Value Driven Project Management
 
Prince2 quick guide
Prince2 quick guidePrince2 quick guide
Prince2 quick guide
 
e-Learning project initiation template
e-Learning project initiation templatee-Learning project initiation template
e-Learning project initiation template
 
Learn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebookLearn the PRINCE2 Principles ebook
Learn the PRINCE2 Principles ebook
 
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
 
PMP Exam Sample Questions Set 8
PMP Exam Sample Questions Set 8PMP Exam Sample Questions Set 8
PMP Exam Sample Questions Set 8
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question Paper
 
Profittme pmp framweork questions
Profittme pmp framweork questionsProfittme pmp framweork questions
Profittme pmp framweork questions
 

Semelhante a Free pmp answers

Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quize2e4
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC QuestionsMonica Waters
 
Qhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docxQhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docxamrit47
 
Pmi pba full exam1 answers
Pmi pba full exam1 answersPmi pba full exam1 answers
Pmi pba full exam1 answersShaban Osman
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdfsuhshbhosale
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docxdorishigh
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
Examination paper of project management certification
Examination paper of project management certificationExamination paper of project management certification
Examination paper of project management certificationNMIMS ASSIGNMENTS HELP
 
Iibm examination paper of project management
Iibm examination paper of project managementIibm examination paper of project management
Iibm examination paper of project managementNMIMS ASSIGNMENTS HELP
 
Examination paper of project management
Examination paper of project managementExamination paper of project management
Examination paper of project managementNMIMS ASSIGNMENTS HELP
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)May Wong, PMP
 

Semelhante a Free pmp answers (20)

Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quiz
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC Questions
 
Qhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docxQhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docx
 
Pmi pba full exam1 answers
Pmi pba full exam1 answersPmi pba full exam1 answers
Pmi pba full exam1 answers
 
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf
 
DPPM1
DPPM1DPPM1
DPPM1
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 
6 pma salehuddin - pqp & 3 core process procedures
6   pma salehuddin - pqp & 3 core process procedures6   pma salehuddin - pqp & 3 core process procedures
6 pma salehuddin - pqp & 3 core process procedures
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Examination paper of project management certification
Examination paper of project management certificationExamination paper of project management certification
Examination paper of project management certification
 
Iibm examination paper of project management
Iibm examination paper of project managementIibm examination paper of project management
Iibm examination paper of project management
 
Examination paper of project management
Examination paper of project managementExamination paper of project management
Examination paper of project management
 
pmp 200 q ans_key
pmp 200 q ans_keypmp 200 q ans_key
pmp 200 q ans_key
 
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
 

Último

Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 

Último (20)

Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 

Free pmp answers

  • 1. Free PMP Questions & Answers 1 All of the following processes form part of the Executing process group Ch.3 except: a Performing activities in accordance with the project management plan. b Managing changes to the deliverables. c Completing the work in accordance with the defined quality framework and specification. d Coordinating people and resources. Answers Reference: PMBOK® Guide p55-56 Sect: 3.5 e The best answer is B i Managing changes is part of Integrated Change Control; this is part of the Monitoring and Controlling process group. ii The Executing process group consists of those processes performed to complete the work defined in the project management plan to satisfy the project specifications. iii An output from Integrated Change Control is updates to the project management plan to incorporate approved changes. 2 Which calculation is correct for the To-Complete Performance Index (TCPI) Ch.7 based on the Estimate At Completion (EAC)? a AC + (BAC – EV) b (BAC - EV)/(BAC - AC) cum c BAC/CPI d (BAC - EV)/(EAC - AC) Answers Reference: PMBOK® Guide p185 Sect 7.3.2.3 e The best answer is D i TCPI is the projection of the future cost performance that must be achieved on the remaining work to achieve a management goal such as the original Budget At Completion (BAC) or a calculated Estimate At Completion (EAC). ii All of these formula use standard Earned Value Management acronyms: Option ‘a’ calculates EAC based on future work being performed at budgeted rates Option ‘b’ calculates TCPI based on BAC (the question asked for EAC) Option ‘c’ calculates EAC based on future work being performed at the same CPI as the completed work. Take any of our PMP courses, you will have access to 100’s of similar questions and importantly, the knowledge needed to answer them effectively. - More on the PMP Examination: www.mosaicprojects.com.au/Training-CAPM.html - Mosaic’s self-paced Mentored Email™ course: www.mosaicprojects.com.au/Training-Mentored.html - More questions? Our PM Final exam simulator: www.mosaicprojects.com.au/Training_PM-Final.html © Practical PM Pty Ltd 1 www.mosaicprojects.com.au
  • 2. Free PMP Questions & Answers 3 A Pareto diagram shows: Ch.8 a The 80% of the work that is important. b The qualitative improvement trend demonstrated by implementing a Six Sigma initiative. c A histogram ordered by frequency of occurrence. d The 20% of the work that is causing the most issues. Answers Reference: PMBOK® Guide p210-211 Section 8.3.2.5 e The best answer is C i A Pareto diagram is a specific type of histogram, ordered by frequency of occurrence. ii It is used to show how many defects were generated by each category of identified cause to allow remedial action to be focussed on the most significant. iii The Pareto principle (also known as the 80-20 rule) is different, see: http://en.wikipedia.org/wiki/Pareto_principle 4 Integrated Change Control includes all of the following tools and Ch.4 techniques except: a Project plan updates. b Expert judgement. c Change control meetings. d A change control board to approve or reject changes. Answers Reference: PMBOK® Guide p.98-99 Sect:4.5.2 e The best answer is A i Project plan updates are an output from Integrated Change Control. ii Expert judgement and the change control meetings, of the change control board are the defined tools and techniques for this process. 5 All of the following are true concerning expected monetary value (EMV) Ch.11 except: a Decision tree analysis is more effective using net present values (NPV) in its calculations rather than EMV. b The EMV of an opportunity is generally a positive value. c EMV is a statistical concept that calculates the average value of a future scenario that may, or may not happen by multiplying the value of each possible outcome by the probability of it occurring and summing the products. d The EMV of a threat is generally a negative value. Answers Reference: PMBOK® Guide p298 Sect: 11.4.2.2 e The best answer is A i EMV is calculated by EMV = probability * impact. ii If there are several different possibilities, the EMV is calculated for each option and the EMVs added together to give an overall, value. iii Decision tree analysis is based on EMV. © Practical PM Pty Ltd 2 www.mosaicprojects.com.au
  • 3. Free PMP Questions & Answers 6 Co-location is one of the techniques used to: Ch.9 a Ensure effective control over the work of the project team. b Develop the project team. c Define the organisation structure. d Acquire the project team. Answers Reference: PMBOK® Guide p234 Sect: 9.3.2.5 e The best answer is B i Co-location involves placing the active project team members in one location to enhance their ability to perform as a team. ii This is one of the tools and techniques listed in the Develop Project Team process. iii Co-location may assist in improving the coordination and control of the project’s work but this is a secondary benefit and consequently not the best answer from the PMBOK’s perspective. 7 When managing a complex, cross functional project; which of the Ch.2 following structures will give the project manager the most authority? a Balanced matrix. b Strong matrix. c Functional. d Weak matrix. Answers Reference: PMBOK® Guide p28-30 Sect:2.4.2 e The best answer is B i Strong matrix organisations provide the project manager with a similar high level of authority to a projectized organisation and full time project administration staff. ii Matrix organisations include both functional and projectized management structures. 8 Leadership in a project environment should demonstrate all of the Apx.G following characteristics except: a The focusing of the efforts of a group of people on achieving a common objective. b High levels of respect and trust. c The ability to get things done through others. d A primary focus on external senior managers and other key stakeholders to ensure the project is a success through managing upwards. Answers Reference: PMBOK® Guide Appendix G, p409 e The best answer is D i Whilst managing upwards (or advising upwards) is a key skill of the project manager, it is not the primary focus of leadership. ii The primary focus of project leadership is on developing the project team and empowering them to achieve the project outcomes. © Practical PM Pty Ltd 3 www.mosaicprojects.com.au
  • 4. Free PMP Questions & Answers 9 The processes included in project communication management are: Ch.10 a Collect Requirements, Plan Communications, Distribute Information, Manage Expectations and Report Performance. b Identify Stakeholders, Collect Requirements, Plan Communications, Distribute Information, Manage Stakeholder Expectations and Report Performance. c Identify Stakeholders, Plan Communications, Distribute Information, Manage Stakeholder Expectations and Report Performance. d Collect Requirements, Plan Communications, Distribute Information, Update Project Documentation and Report Performance. Answers Reference: PMBOK® Guide p243-244 e The best answer is C i This is a common type of question. ii Collect Requirements is a Scope Management process. iii Update project documentation is an output from a range of processes. 10 Which of the following is true concerning the work breakdown structure Ch.5 (WBS)? a The PMI WBS and PRINCE2 product breakdown structure (PBS) are effectively the same thing. b The WBS is the same as the organisational breakdown structure (OBS). c The WBS is a deliverable oriented, hierarchical decomposition of the work to be executed by the project team. d The WBS is the bill of materials (BoM) needed to accomplish the work of the project. Answers Reference: PMBOK® Guide p116 Sect: 5.3 e The best answer is C i The difference between the PBS and the WBS is the PBS only contains the products to be delivered, the WBS contains all of the work needed to achieve the project’s objectives including all of the deliverables (not just the ‘product’). Non-product elements in the WBS include project management work, safety and hygiene work, etc. ii The OBS is the document that defines the lines of management responsibility within the project. The point where the OBS and WBS intersect is known as a ‘control account’ and defines the manager responsible for a section of the project work. iii The BoM only describes the materials used in the work, not the other elements of the project (eg, labour). The WBS defines all of the work and consequently all of the costs. 11 All of the following are true of cost plus fixed fee (CPFF) contracts, except: Ch.12 a The seller is reimbursed for all allowable costs incurred performing the contract work. b The seller receives a fixed fee calculated as a percentage of the initial estimated project cost. c The fee does not change based on the performance of the seller. d The seller receives a fee calculated as a fixed percentage of the actual project cost. © Practical PM Pty Ltd 4 www.mosaicprojects.com.au
  • 5. Free PMP Questions & Answers Answers Reference: PMBOK® Guide p323 Sect: 12.1.2.3 e The best answer is D i CPFF contracts pay a fixed fee to the seller based on the initial estimated value of the work. ii All allowable costs are reimbursed by the buyer. iii The only time the fee will change is if the buyer changes the scope of the work. 12 During a meeting with some of your project's stakeholders, you are asked Ethics to add to the project's scope of work. The project records contain correspondence from before the Charter was signed in which the project sponsor specifically declined the work being requested by these stakeholders. The BEST thing for you to do is: a Tell the stakeholders the work cannot be added. b Evaluate the cost and time impacts of adding the work. c Add the work if it can be accommodated within the existing budget. d Talk to the sponsor and let her know of the request. Answers Reference: PMI Code of Professional Conduct e The best answer is A i PMI expects the project manager to manage! The best thing to do first is try to resolve the problem with the stakeholders. Only is that fails should the problem be escalated to the sponsor. ii Whilst planning and evaluation are normal 'first steps' in assessing a change, this work was formally excluded from the project before the Charter was signed. Therefore it should not be added without the sponsor's prior approval. 13 Analogous estimating when applied to a duration is: Ch.6 a Based on expert judgement and is consequently more accurate than standard critical path estimating. b Used when there is a limited amount of detailed information available. c A calculation based on a three point estimate using a modified BETA distribution. d The same as ‘bottom up’ estimating. Answers Reference: PMBOK® Guide p149 Sect: 6.4.2.2 e The best answer is B i Analogous estimating uses the duration from a similar completed activity or project as the basis for the current estimate. This is a ‘top down’ estimating technique used when there is little detailed information available. ii The critical path method is a precise set of calculations applied to the schedule (including the estimated durations). It is not an estimating process. iii The PERT technique uses three point estimates and a modified BETA distribution to assess the probability of completing the project in a given timeframe. © Practical PM Pty Ltd 5 www.mosaicprojects.com.au
  • 6. Free PMP Questions & Answers 14 The code of accounts: Gloss. a Is the system used to keep track of purchases and contracts. b Is any numbering system used to uniquely identify each component of the work breakdown structure. c Links the work breakdown structure to the schedule task identifier. d Is the alpha-numeric reference used in the organisations accounts system to identify cost centres. Answers Reference: PMBOK® Guide Glossary p421 e The best answer is B i The chart of accounts refers to the accounting system, the code of accounts to the WBS. Whilst these should be linked, they are not the same. ii Links between the WBS and the activities in the schedule are required; however, this information is usually in a code field or a text field, not the Task ID. There are likely to be several activities to each WBS element and the WBS code of accounts is a fixed structure. Task IDs can change. 15 A procurement audit will consider all of the following except: Ch.12 a The changes in market conditions between the contract date and the current time. b Any successes or failures in the process that warrant recognition. c The complete procurement process from initial planning through to the administration of the procurement. d Any lessons learned that can be applied to future procurement processes. Answers Reference: PMBOK® Guide p343 Sect: 12.4.2.1 e The best answer is A i PMBOK audits are focused on process improvement. They review how the system is working to learn lessons to apply to future procurements both within the project and on other projects within the organisation. 16 The Delphi technique has all of the following characteristics except: Ch.11 a It is a technique to reduce bias and prevent any one person from exerting undue influence. b It is a way to reach a consensus of experts. c It is an Oracle® database application used to optimise future outcomes. d Individual experts are unaware of who else is participating in the process. Answers Reference: PMBOK® Guide p286 sect:11.2.2.2 e The best answer is C i The Delphi technique is a facilitated process to reach a consensus of experts using questions and feedback. Only the facilitator is aware of who is participating. ii No PMI question is likely to have a proprietary tool as the correct answer. © Practical PM Pty Ltd 6 www.mosaicprojects.com.au
  • 7. Free PMP Questions & Answers 17 A binding contract is legally created when: Law a The formal contract documents are signed by your senior management. b When your legal department advises the contract is acceptable. c The formal contract documents are signed by official representatives of both parties. d There is an offer, acceptance, performance and consideration. Answers Reference: Contract Law e The best answer is D i Contracts do not have to be in writing or signed. Whilst it is difficult to enforce the terms of a verbal contracts the law will recognise the validity of the agreement. ii The four basic requirements for a contract are: - Someone makes an offer to do something, - The offer is accepted unconditionally, - There is an intention or actual performance of the offer, - There is an intention or actual transfer of a valuable consideration (the consideration does not have to be money, just of value). iii There are many additional factors that can influence this basic starting point that project managers and administrators need to be aware of. 18 The basic decision making styles normally used by project managers Apx.G include all of the following except: a Coin flip (random). b Command. c Consultation. d Rational choice theory Answers Reference: PMBOK® Guide Appendix G6 p412 e The best answer is D i Rational choice theory is a framework for understanding and often formally modelling social and economic behaviour. ii The 4 options in the PMBOK are command, consultation, consensus and coin flip. iii Coin flip is used when it really does not matter which option is chosen as long as there is a decision (eg, should we meet at McDonald’s or Burger King for lunch). 19 FPIF is an acronym for: Gloss. a Fixed Price Incentive Fee b Firm Price Incentive Free c Fixed Price Indicator Factor d Fast Performance Incentive Fee Answers Reference: PMBOK® Guide Glossary p416 e The best answer is A i FPIF is a form of contract where the seller can earn an incentive fee on top of its fixed price for the work if it achieves a specified objective such as a zero accident or defect rate or completion before a specified target date. © Practical PM Pty Ltd 7 www.mosaicprojects.com.au
  • 8. Free PMP Questions & Answers 20 The Control Costs process includes all of the following except: Ch.7 a Informing appropriate stakeholders of all approved changes and associated costs. b Influencing factors that create changes in the authorised cost baseline. c Developing the cost performance baseline. d Acting to bring expected cost overruns within acceptable limits. Answers Reference: PMBOK® Guide p179-180 Sect 7.3 e The best answer is C i Developing the cost performance baseline is part of the Determine Budget process (see: 7.2.3.1). ii All of the other options are listed as inclusions in the Control Costs process. 21 All of the following statements are true about product and project life Ch.2 cycles except: a Generally a product lifecycle is contained within a project lifecycle. b A project life cycle is determined by the organisation and generally consists of phases that may be sequential or overlapping. c A product lifecycle is determined by the organisation and generally consists of sequential phases. d Generally a project lifecycle is contained within a product lifecycle. Answers Reference: PMBOK® Guide p18 Sect: 2.1.2 e The best answer is A i Products are created, marketed, upgraded and eventually retired or decommissioned. The phases are determined by the organisation. ii Projects are used to create the product, upgrade the product and potentially decommission the product. Projects typically fit within or form one phase of the overall product lifecycle. iii The phases of a project’s lifecycle (eg, design, build, install) are different to the ‘project management phases’ discussed in the PMBOK; project management phases are synonymous with the five process groups. The five process groups (initiate, plan, execute, monitor & control, and close) occur at different levels of intensity in each project, and each phase of a project. 22 As part of a successful communication, the receiver is responsible for: Ch.10 a Making sure the information is clear and complete, understood and acknowledged. b Making sure the information is received in its entirety, understood correctly and acknowledged. c Making sure the information is clear and complete, understood and agreed with. d Listening actively to ensure all of the information is received. Answers Reference: PMBOK® Guide p255 Sect: 10.2.2.3 e The best answer is B © Practical PM Pty Ltd 8 www.mosaicprojects.com.au
  • 9. Free PMP Questions & Answers i Communication can be written or oral, therefore ‘d’ is not the best answer. Both the sender and receiver need to use active listening if the communication is oral. ii The sender is responsible for making sure the information is clear and complete, not the receiver. iii For a communication to be successful the receiver needs to acknowledge its receipt to the sender, the receiver does not have to agree with the information. 23 All of the following people developed management theories focused on Mgt. motivation except: a Maslow. b McGregor. c Hertzberg. d Deming. Answers Reference: General management theory. e The best answer is D i W. Edwards Deming is a quality guru. ii Maslow developed the Hierarchy of Needs. iii McGregor developed the Theory X and Theory Y iv Herzberg’s developed the Hygiene Theory 24 The project charter has all of the following characteristics except: Ch.4 a Its primary use is to authorise the start of a project or phase. b It provides the project manager with authority to apply resources and expend money on project activities. c Its primary use is to request bids or proposals for the work it defines. d The project charter can be created by the person external to the project, responsible for the authorisation of the work, or that person can delegate the creation of the project charter to the project manager. Answers Reference: PMBOK® Guide p73-74 Sect: 4.1 e The best answer is C i Statements of work (SOW) and other procurement documents are used to request bids or proposals. ii The work of creating the project charter can be delegated to the project manager; however, the charter should be signed by the person responsible for authorising the project. 25 All of the following are true concerning enterprise environmental factors Ch.1 (EEF) except: a EEF do not include the organisations purchasing guidelines because this type of function is managed by the Accounts Department. b EEF include the tools, systems and software that comprise the project management information system (PMIS). c EEF incorporates the organisation’s culture, structure and processes. d EEF include all relevant laws, regulations and standards imposed by all levels of government, industry bodies and society. © Practical PM Pty Ltd 9 www.mosaicprojects.com.au
  • 10. Free PMP Questions & Answers Answers Reference: PMBOK® Guide p14, sect: 1.8 e The best answer is A i EEF refer to both the internal and external environmental factors that surround or influence a project. ii Purchasing guidelines constrain the project management’s options in respect of acquiring goods and services. 26 All of the following statements concerning the project scope statement are Ch.5 true except: a It is an output of the Verify Scope process. b It describes the project’s deliverables and the work needed to create them. c It may contain explicit scope exclusions that can assist in managing stakeholder expectations. d It provides a common understanding of the project’s scope among the project’s stakeholders. Answers Reference: PMBOK® Guide p115 Sect: 5.2.3.1 e The best answer is A i The project scope statement is an output from the Define Scope process. ii Clearly documenting work that is ‘out of scope’ helps everyone. A typical example is a project may be scoped to develop training materials for the product being developed, but not to conduct the training. A clear statement that ‘All training will be undertaken by others and is outside of the scope of this project’ prevents stakeholders expecting the project team will undertake the initial training or ‘train-the-trainer’ training. If these requirements are needed, they can be brought into the project’s scope through a change management process. 27 The cost of quality includes all of the following except: Ch.8 a Buying professional indemnity insurance. b The cost of defects and rework caused by failing to achieve requirements. c The cost of inspecting and appraising conforming products produced by the project. d Preventing non-conformance to requirements. Answers Reference: PMBOK® Guide p195 Sect: 8.1.2.2 e The best answer is A i Buying insurance is a risk transference process (the risk is transferred to the insurer). ii The cost of quality (COQ) is the direct costs incurred in prevention, inspection and repairs. © Practical PM Pty Ltd 10 www.mosaicprojects.com.au
  • 11. Free PMP Questions & Answers 28 The responsibility assignment matrix (RAM) shows: Ch.9 a The connections between activities and project team members. b The delegation of responsibility through the hierarchically organised management structure. c Accountabilities to assist in team performance appraisals. d The sequence of activities a named resource is responsible for accomplishing. Answers Reference: PMBOK® Guide p221 Sect: 9.1.2.1 e The best answer is A i The RAM chart is used to illustrate the connections between work packages or activities and project team members. 29 Project management process groups have all of the following Ch.3 characteristics except: a All of the process groups are needed on all projects and all of their interactions apply to each phase of a project as well as the overall project. b The process groups are seldom one time, discrete events; they are overlapping activities that occur throughout the project. c Where a project is divided into phases, the process groups are invoked as appropriate. d The process groups are linked by the outputs they produce. Answers Reference: PMBOK® Guide p39-41 Sect: 3.1 e The best answer is A i Whilst all of the process groups should occur in each project at an appropriate level of intensity, ALL of the processes and interactions within and between process groups are not required on every project or in every phase of a project. ii The project management team are responsible for determining which processes are appropriate and the appropriate degree of rigour to apply (ref p 38). 30 Which of the following represent a discretionary dependency? Ch.6 a Not starting design until all of the approvals have been received. b Waiting the specified 72 hours before stripping formwork from a newly poured concrete slab. c Applying a start-to-start link between two tasks in a PDM network. d Applying a lag of 4 days between two tasks. Answers Reference: PMBOK® Guide p139-140 Sect: 6.2.2.2 e The best answer is A i Any link between two tasks (or activities) may be discretionary or mandatory. The link types in a Precedence network (PDM) are: - Finish-to-start - Start-to-start - Finish-to-finish - Start-to-finish. A lead or a lag may be applied to any of the link types. © Practical PM Pty Ltd 11 www.mosaicprojects.com.au
  • 12. Free PMP Questions & Answers ii Mandatory dependencies are either inherent in the nature of the work (eg, you cannot put concrete into a foundation until you have dug the hole!), or are contractually required. The specification typically forms part of a contract and would mandate the ‘curing time’. iii Discretionary dependencies are desirable and/or represent best practice. Whilst it is desirable to wait for the final approvals for a project before starting the design it is not mandatory. The project team may decide to take a calculated risk and start some design work before all of the approvals are received. References: - Ch.X = PMBOK® Guide Chapter # - Gloss. = PMBOK® Guide Glossary - Apx.G = PMBOK® Guide Appendix G (Interpersonal Skills) - The PMP exam covers significantly more then the PMBOK, Three sample questions on Management Theory, Contract Law and Ethics have been included. Important Information: The passing score for the PMP examination is 61% - whilst these questions are representative of the style of questions found in the PMP examination, no warranty is offered in respect of your likely performance in the examination based on your performance in this limited test. Our experience over many years suggests an average score of 75% in our courses translates to a reasonable level of comfort in the examination; however, this is based on candidates answering many hundreds of questions. Additional Resources: - More information on the PMP Examination: www.mosaicprojects.com.au/Training-PMP.html - Mosaic’s PM Final question bank: www.mosaicprojects.com.au/Training_PM-Final.html - Mosaic’s self paced Mentored Email™ course: www.mosaicprojects.com.au/Training-Mentored.html Mosaic Project Services Pty Ltd is a PMI approved Registered Education Provider (R.E.P.). We have been successfully training PMP candidates to pass their exam for over 10 years. All of Mosaic’s PMP courses are pre-approved by PMI for the 35 Hrs of project management training needed to be eligible to apply for the examination. For additional information click on the links above or follow the training prompt from our home page at www.mosaicprojects.com.au © Practical PM Pty Ltd 12 www.mosaicprojects.com.au