Planning for NASA Procurements
MS Project Schedule Template
Small & Large Actions
$25-125K & $10-50M

Disclaimer: This briefing is not a
government document.

1
Objectives
• To identify repeatable process steps in small
and large procurements that can be called out
in MS Project schedule templates.
– The two templates are available for schedulers
working on Space Flight Systems projects.

• To support load balancing for procurement
actions throughout the year.
– It will help prevent a log jam of actions in the
fourth quarter.
Disclaimer: This briefing is not a government document.

2
Scope of the Problem
Based on a one-year sample of 3,500 procurement
actions for Spaceflight Systems
• Fewer than 600 (17%) exceeded $25,000.
• 6 procurements exceed $1 million
• 65 procurements range from $200K to $1 million
• 517 procurements range in value from $25K to
$200K
• Conclusion – Complex scheduling issues are linked to
a small number of high-value actions.
Disclaimer: This briefing is not a
government document.

3
Solutions
•
•
•
•
•

Simplified WBS for $25-125K procurements
“Plug-in” Schedule template for $25-125K
“Plug-in” Schedule template for $10-50M
Roles & Responsibility Matrix for $10-50M
Each project task in the template is set to start as early as
possible. All durations are “business days.”
Procurement Roles & Responsibilities / Process Steps Guide can be found at:
http://prod.nais.nasa.gov/portals/pl/documents/Source_Selection_Guide_March_2012.pdf

Disclaimer: This briefing is not a
government document.

4
Template Contents
• Using the templates will help project managers avoid
surprises in procurement schedules.
• Each template shows all procurement process steps
and nominal duration of tasks from start of
requirements definition to finish with award to a
vendor.
• Templates have no “date constrained” tasks and can
be directly inserted in new or existing schedules.
• They will cascade forward from the start date of the
procurement action.
Disclaimer: This briefing is not a
government document.

5
Simplified Actions $25-150K
Best & Worst Case Scenarios

Disclaimer: This briefing is not a
government document.

6
$10-50M Procurements
Best & Worst Case Scenarios
• The “typical case” depends on completing process
steps with experienced staff and managers.

Value
$1-10M

Space Flight Systems Expectations
of Business Days to Complete $10-50M
Procurement Actions at NASA GRC
Based on Federal Acquisition Regulations
Best
Typical
Case
Case
100
250

Worst
Case
300+

$10-50M

150

300

450+

>$50M

200

400

550+

Disclaimer: This briefing is not a
government document.

7
$10-50M Procurements
Estimated Duration
• Matches NASA Task and Time Estimates
Estimated Duration of NASA Procurements for $10 -50 Million
Procurement
Phase

Estimated
Duration

Business Days
Min-Max

PPIO Schedule
Using Parallel
Execution of Tasks

Phase 1

2-3 months

60-90

60

Phase 2

2-3 months

60-90

97

Phase 3

4-6 months

120-180

111

Totals

8-12 months

240-360

268

Disclaimer: This briefing is not a
government document.

8
$10-50M Procurements
Major Milestones

Disclaimer: This briefing is not a
government document.

9
Roles & Responsibilities - 1
SEC/SEB tasks displayed by who does what when
Source: GRC procurement office. See citations below.
Contracing
Officer

PHASE 1 - Estimate: 2 - 3 Months
Create SEC Schedule (incorporate planned leave)
IDIQ Task Structure (Planning for Set-up in Procurement Systems/Administration of Tasks)
Develop Work Breakdown/Funding Structure
Identify SEC Team
Source Selection Authority (Selection Official) Appointment Letter
Source Evaluation Committee Appointment Letter
OGE-450/SF-278 Financial Disclosure Forms by SEC Members
Procurement Briefing to SEC Team
Facility/Information Technology Security Plan
SEB/Security/Legal Briefing
Post Sources Sought Notice for Market Research/Small-Business Set-aside Possibilities
Draft SOW
Select/Edit Contract Clauses
Obtain E-Room or other Electronic Evaluation Tool (Protected Server)
E-Room/Electronic Tool Briefing (i.e. how to use system, enter findings)
Obtain Secure Room for Committee; Distribute Keys
Furnish Room with Materials, Supplies, Equipment
Personal Services Determination
Sources Sought Notice Responses Due
Final SOW
Develop Past Performance Questionnaire/Instructions
Develop Cost Templates/Instructions
Budget Verification (Out-year Forecasts)

Disclaimer: This briefing is not a
government document.

SEB
Chair

Project
Team

Finance

Support
& Other

Legal

Admin
Admin
Admin
Admin

10
Roles & Responsibilities - 2
SEC/SEB tasks displayed by who does what when
Source: NASA

Contracing

SEB

Project

Officer

Chair

Team

Support
Finance

& Other

PHASE 2 - Estimate: 2 - 3 Months
Industry Day/ Site Tour
DRFP/Industry Day Questions Due
Respond to DRFP/Industry Day Questions
Briefing to Source Selection Authority for Final RFP Approval
Final RFP Issue (including Cover Letter summarizing Major Changes)
Black-Out Notice
Final RFP Questions Due
Respond to Final RFP Questions
Past Performance Proposals Due
Additional Planning for Evaluation (Methodology) using RFP Sections L & M
Proposals Due
Briefing on the proper creation of a Finding
Acceptance of Proposals/ SEC Members Conflict of Interest Verification
EEO/VETS-100/CCR/Reps and Certs Compliance
Distribute Proposals for review

Disclaimer: This briefing is not a
government document.

Legal

11
Roles & Responsibilities - 3
SEC/SEB tasks displayed by who does what when
Source: NASA

Contracing

SEB

Project

Officer

Chair

Team

Support
Finance

& Other

PHASE 3 - Estimate: 4 - 6 Months (number of proposals is huge factor)
Individual Mission Suitability Evaluations
Consensus Mission Suitability Evaluations
Past Performance Evaluations
Cost Evaluations
Create Source Selection Authority Presentation
Dry-Run of Selection/Competitive Range SSA Presentation
SSA Presentation for Selection or Competitive Range Determination
Notification to Offerors; Open Discussions
Competitive Range Discussions
Interim Proposals Due
Evaluate Interim Proposals/Advise Offerors of Further Issues
Interim Questions to Offerors
Final Proposals Due
Final Proposal Evaluation; Revisions to Findings
Create Final SSA Presentation
Dry-Run of SSA Presentation
Final SSA Presentation
Source Selection Statement
ANOSCA/Press Release
Debriefings
Protest Period
Award Contract; Process in Procurement's CMM System
Commence Phase-In

Disclaimer: This briefing is not a
government document.

Ex-Officio

12
Caveats
• Real experiences in terms of duration will be longer
than the ideal.
• A full team will staff up and remain available
throughout the procurement process.
• Wait time for managers to get to decision packages is
minimal though not always achievable.
• Post award engagement with the vendor for long
lead time items will reduce risks.

Disclaimer: This briefing is not a
government document.

13
Wrap Up
• A $10-50M procurement is a full time job for
the “wagon master” in charge of it.

Disclaimer: This briefing is not a
government document.

14
Backup Slides

Disclaimer: This briefing is not a
government document.

15
Large Procurements
• Detailed schedule
• Three major phases
• Work tasks conducted in parallel

Disclaimer: This briefing is not a
government document.

16
Phase 1 Milestones
Create Schedules / WBS
1.
2.
3.
4.
5.
6.

Create procurement WBS
Form source evaluation team
Set up admin support / logistics
Draft statement of work (SOW)
Draft request for proposal (RFP)
Procurement Strategy Briefing

Disclaimer: This briefing is not a
government document.

17
Phase 1 Schedule
Parts 1-3 Milestones

Disclaimer: This briefing is not a
government document.

18
Phase 1 Schedule
Parts 4-5 Milestones

Disclaimer: This briefing is not a government document.

19
Phase 1 Schedule
Part 6 Milestone

Disclaimer: This briefing is not a
government document.

20
Phase 2 Milestones
Publish RFP/ Receive Bids
1. Complete RFP
2. Vendor Response Completion

Disclaimer: This briefing is not a
government document.

21
Phase 2 Schedule
Part 1 Milestone

Disclaimer: This briefing is not a
government document.

22
Phase 2 Schedule
Part 2 Milestone

Disclaimer: This briefing is not a
government document.

23
Part 3 Milestones
Review Bids / Award Contract
1. Review RFP Responses
2. Source Selection Decision

Disclaimer: This briefing is not a
government document.

24
Phase 3 Schedule
Part 1 Milestone

Disclaimer: This briefing is not a
government document.

25
Phase 3 Schedule
Part 2 Milestone

Disclaimer: This briefing is not a
government document.

26
Conceptual Blockbusting
• Very large procurements can and will bog
down under the weight of multiple layers of
complex requirements.
• Project managers can reduce procurement
time by breaking up acquisitions into a parallel
series of lower cost buys creating a “portfolio”
of smaller, faster moving actions such as
design, fabrication, and system integration.
Disclaimer: This briefing is not a
government document.

27
Causes of Procurement Delays
• Incomplete specifications
– Vendors cannot fabricate based on poorly defined
requirements.

• Incomplete or incorrect paperwork
– NASA GRC Forms C-376 & 1707 cannot be processed with
missing or incorrect information.

• Incorrect color of money is used
– CFO funds approval and financial checks of the
procurement include that the correct WBS is being used.

• Insufficient time allowed for vendor to deliver
– Especially for the selected vendor to fabricate and deliver
the materials, goods, components, and/or services.
Disclaimer: This briefing is not a
government document.

28
Vendor Relations
Post Award
• Don’t let the vendor be a black box on long-lead
time, high-value procurements.
– If delivery time for a high-value procurement is more
than six weeks, consider including a series of check-ins
starting at the 20-day mark.
– Consider on-site visits, including design and
engineering reviews, especially if fabrication involves
a first-of-a-kind product.

• Be sure to address these issues in the initial
requirements that are sent to the vendor.
Disclaimer: This briefing is not a
government document.

29
Sole Source Actions > $150K
• Sole source procurements greater than $150K require a
“Justification of Other than Competitive” action (JOFOC).
• The approved document is published on www.fbo.gov for
15 days.
• When in doubt about a sole source approach, contact
procurement for advice.
• A response from a valid vendor stops the clock and may
start one for a competitive process.
• If your procurement is not approved to be sole-source, and
is for more than $150K, the contracting officer has
discretion in setting reasonable time frames for publishing
a pre-solicitation synopsis for large buys as well as vendor
response time for a solicitation.
Disclaimer: This briefing is not a
government document.

30
Contact
Dan Yurman
Email: djysrv@gmail.com
Linkedin
http://www.linkedin.com/in/danyurman/
Mobile: 216-218-3823
Twitter: @djysrv
Disclaimer: This briefing is not a
government document.

31

More Related Content

What's hot

PMBOK 6 Summary: Module 2 (Planning Processes)
PMBOK 6 Summary: Module 2 (Planning Processes)PMBOK 6 Summary: Module 2 (Planning Processes)
PMBOK 6 Summary: Module 2 (Planning Processes)Awaludin Zakaria
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmovinghats
 
Project management office value
Project management office valueProject management office value
Project management office valueHumanWare
 
Rise and fall of project portfolio management triumph&collapse a case study
Rise and fall of project portfolio management triumph&collapse a case studyRise and fall of project portfolio management triumph&collapse a case study
Rise and fall of project portfolio management triumph&collapse a case studyromluc
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off PresentationEbru Seiwert
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagramriosabel
 
How to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMOHow to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMOLaura Barnard, PMP
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Pmbok 02 the environment in which projects operate
Pmbok 02 the environment in which projects operatePmbok 02 the environment in which projects operate
Pmbok 02 the environment in which projects operateWisam Shamroukh
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
What is Program Management - An Overview
What is Program Management - An OverviewWhat is Program Management - An Overview
What is Program Management - An OverviewYolanda Williams
 

What's hot (20)

PMBOK 6 Summary: Module 2 (Planning Processes)
PMBOK 6 Summary: Module 2 (Planning Processes)PMBOK 6 Summary: Module 2 (Planning Processes)
PMBOK 6 Summary: Module 2 (Planning Processes)
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010
 
Project management office value
Project management office valueProject management office value
Project management office value
 
Rise and fall of project portfolio management triumph&collapse a case study
Rise and fall of project portfolio management triumph&collapse a case studyRise and fall of project portfolio management triumph&collapse a case study
Rise and fall of project portfolio management triumph&collapse a case study
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
 
Develop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow DiagramDevelop Project Management Plan Data Flow Diagram
Develop Project Management Plan Data Flow Diagram
 
How to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMOHow to Setup a High-IMPACT PMO
How to Setup a High-IMPACT PMO
 
I2m - Strategy PMO Case Study Presentation
I2m - Strategy PMO Case Study PresentationI2m - Strategy PMO Case Study Presentation
I2m - Strategy PMO Case Study Presentation
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Pmbok 02 the environment in which projects operate
Pmbok 02 the environment in which projects operatePmbok 02 the environment in which projects operate
Pmbok 02 the environment in which projects operate
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
What is Program Management - An Overview
What is Program Management - An OverviewWhat is Program Management - An Overview
What is Program Management - An Overview
 

Viewers also liked

Viewers also liked (7)

omah coffee 15.08
omah coffee 15.08omah coffee 15.08
omah coffee 15.08
 
Action Road Map Planning Tool
Action Road Map Planning ToolAction Road Map Planning Tool
Action Road Map Planning Tool
 
Project Schedule Template
Project Schedule TemplateProject Schedule Template
Project Schedule Template
 
Timeline and checklist for event planning
Timeline and checklist for event planningTimeline and checklist for event planning
Timeline and checklist for event planning
 
EVENT MANAGEMENT PLAN CHECKLIST AND GUIDE
EVENT MANAGEMENT PLAN CHECKLIST AND GUIDEEVENT MANAGEMENT PLAN CHECKLIST AND GUIDE
EVENT MANAGEMENT PLAN CHECKLIST AND GUIDE
 
Event checklist
Event checklistEvent checklist
Event checklist
 
Project Planning
Project PlanningProject Planning
Project Planning
 

Similar to MS Project 2010 schedule template for large NASA procurements $10-450 million

Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintSunil Guglani
 
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%GoLeanSixSigma.com
 
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...GoLeanSixSigma.com
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
IT Operations Consulting
IT Operations Consulting  IT Operations Consulting
IT Operations Consulting Anubhav Lal
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
Inbound MIPR Process
Inbound MIPR ProcessInbound MIPR Process
Inbound MIPR ProcessJames Foster
 
USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Dronetkjohns1
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1Fred Zuercher
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperIan Heptinstall
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxPhngPhmTrung
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...Invest Northern Ireland
 

Similar to MS Project 2010 schedule template for large NASA procurements $10-450 million (20)

Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple Constraint
 
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
 
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Case Study - Deficit Analysis
Case Study - Deficit AnalysisCase Study - Deficit Analysis
Case Study - Deficit Analysis
 
IT Operations Consulting
IT Operations Consulting  IT Operations Consulting
IT Operations Consulting
 
Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Inbound MIPR Process
Inbound MIPR ProcessInbound MIPR Process
Inbound MIPR Process
 
USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Drone
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Lec 8.....week 12-14.ppt
Lec 8.....week 12-14.pptLec 8.....week 12-14.ppt
Lec 8.....week 12-14.ppt
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptx
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
Scope Management
Scope ManagementScope Management
Scope Management
 
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
 

More from Self employed

BVU Encore IT project July 2018 status report
BVU Encore IT project  July  2018 status report BVU Encore IT project  July  2018 status report
BVU Encore IT project July 2018 status report Self employed
 
Organizing a Project Management Office
Organizing a Project Management OfficeOrganizing a Project Management Office
Organizing a Project Management OfficeSelf employed
 
Strategic planning and technology management
Strategic planning and technology managementStrategic planning and technology management
Strategic planning and technology managementSelf employed
 
Not Even Close And No Cigar
Not Even Close And No CigarNot Even Close And No Cigar
Not Even Close And No CigarSelf employed
 

More from Self employed (6)

BVU Encore IT project July 2018 status report
BVU Encore IT project  July  2018 status report BVU Encore IT project  July  2018 status report
BVU Encore IT project July 2018 status report
 
Organizing a Project Management Office
Organizing a Project Management OfficeOrganizing a Project Management Office
Organizing a Project Management Office
 
Strategic planning and technology management
Strategic planning and technology managementStrategic planning and technology management
Strategic planning and technology management
 
Blogs tell stories
Blogs tell storiesBlogs tell stories
Blogs tell stories
 
Do you have klout?
Do you have klout?Do you have klout?
Do you have klout?
 
Not Even Close And No Cigar
Not Even Close And No CigarNot Even Close And No Cigar
Not Even Close And No Cigar
 

Recently uploaded

Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 

Recently uploaded (20)

Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 

MS Project 2010 schedule template for large NASA procurements $10-450 million

  • 1. Planning for NASA Procurements MS Project Schedule Template Small & Large Actions $25-125K & $10-50M Disclaimer: This briefing is not a government document. 1
  • 2. Objectives • To identify repeatable process steps in small and large procurements that can be called out in MS Project schedule templates. – The two templates are available for schedulers working on Space Flight Systems projects. • To support load balancing for procurement actions throughout the year. – It will help prevent a log jam of actions in the fourth quarter. Disclaimer: This briefing is not a government document. 2
  • 3. Scope of the Problem Based on a one-year sample of 3,500 procurement actions for Spaceflight Systems • Fewer than 600 (17%) exceeded $25,000. • 6 procurements exceed $1 million • 65 procurements range from $200K to $1 million • 517 procurements range in value from $25K to $200K • Conclusion – Complex scheduling issues are linked to a small number of high-value actions. Disclaimer: This briefing is not a government document. 3
  • 4. Solutions • • • • • Simplified WBS for $25-125K procurements “Plug-in” Schedule template for $25-125K “Plug-in” Schedule template for $10-50M Roles & Responsibility Matrix for $10-50M Each project task in the template is set to start as early as possible. All durations are “business days.” Procurement Roles & Responsibilities / Process Steps Guide can be found at: http://prod.nais.nasa.gov/portals/pl/documents/Source_Selection_Guide_March_2012.pdf Disclaimer: This briefing is not a government document. 4
  • 5. Template Contents • Using the templates will help project managers avoid surprises in procurement schedules. • Each template shows all procurement process steps and nominal duration of tasks from start of requirements definition to finish with award to a vendor. • Templates have no “date constrained” tasks and can be directly inserted in new or existing schedules. • They will cascade forward from the start date of the procurement action. Disclaimer: This briefing is not a government document. 5
  • 6. Simplified Actions $25-150K Best & Worst Case Scenarios Disclaimer: This briefing is not a government document. 6
  • 7. $10-50M Procurements Best & Worst Case Scenarios • The “typical case” depends on completing process steps with experienced staff and managers. Value $1-10M Space Flight Systems Expectations of Business Days to Complete $10-50M Procurement Actions at NASA GRC Based on Federal Acquisition Regulations Best Typical Case Case 100 250 Worst Case 300+ $10-50M 150 300 450+ >$50M 200 400 550+ Disclaimer: This briefing is not a government document. 7
  • 8. $10-50M Procurements Estimated Duration • Matches NASA Task and Time Estimates Estimated Duration of NASA Procurements for $10 -50 Million Procurement Phase Estimated Duration Business Days Min-Max PPIO Schedule Using Parallel Execution of Tasks Phase 1 2-3 months 60-90 60 Phase 2 2-3 months 60-90 97 Phase 3 4-6 months 120-180 111 Totals 8-12 months 240-360 268 Disclaimer: This briefing is not a government document. 8
  • 9. $10-50M Procurements Major Milestones Disclaimer: This briefing is not a government document. 9
  • 10. Roles & Responsibilities - 1 SEC/SEB tasks displayed by who does what when Source: GRC procurement office. See citations below. Contracing Officer PHASE 1 - Estimate: 2 - 3 Months Create SEC Schedule (incorporate planned leave) IDIQ Task Structure (Planning for Set-up in Procurement Systems/Administration of Tasks) Develop Work Breakdown/Funding Structure Identify SEC Team Source Selection Authority (Selection Official) Appointment Letter Source Evaluation Committee Appointment Letter OGE-450/SF-278 Financial Disclosure Forms by SEC Members Procurement Briefing to SEC Team Facility/Information Technology Security Plan SEB/Security/Legal Briefing Post Sources Sought Notice for Market Research/Small-Business Set-aside Possibilities Draft SOW Select/Edit Contract Clauses Obtain E-Room or other Electronic Evaluation Tool (Protected Server) E-Room/Electronic Tool Briefing (i.e. how to use system, enter findings) Obtain Secure Room for Committee; Distribute Keys Furnish Room with Materials, Supplies, Equipment Personal Services Determination Sources Sought Notice Responses Due Final SOW Develop Past Performance Questionnaire/Instructions Develop Cost Templates/Instructions Budget Verification (Out-year Forecasts) Disclaimer: This briefing is not a government document. SEB Chair Project Team Finance Support & Other Legal Admin Admin Admin Admin 10
  • 11. Roles & Responsibilities - 2 SEC/SEB tasks displayed by who does what when Source: NASA Contracing SEB Project Officer Chair Team Support Finance & Other PHASE 2 - Estimate: 2 - 3 Months Industry Day/ Site Tour DRFP/Industry Day Questions Due Respond to DRFP/Industry Day Questions Briefing to Source Selection Authority for Final RFP Approval Final RFP Issue (including Cover Letter summarizing Major Changes) Black-Out Notice Final RFP Questions Due Respond to Final RFP Questions Past Performance Proposals Due Additional Planning for Evaluation (Methodology) using RFP Sections L & M Proposals Due Briefing on the proper creation of a Finding Acceptance of Proposals/ SEC Members Conflict of Interest Verification EEO/VETS-100/CCR/Reps and Certs Compliance Distribute Proposals for review Disclaimer: This briefing is not a government document. Legal 11
  • 12. Roles & Responsibilities - 3 SEC/SEB tasks displayed by who does what when Source: NASA Contracing SEB Project Officer Chair Team Support Finance & Other PHASE 3 - Estimate: 4 - 6 Months (number of proposals is huge factor) Individual Mission Suitability Evaluations Consensus Mission Suitability Evaluations Past Performance Evaluations Cost Evaluations Create Source Selection Authority Presentation Dry-Run of Selection/Competitive Range SSA Presentation SSA Presentation for Selection or Competitive Range Determination Notification to Offerors; Open Discussions Competitive Range Discussions Interim Proposals Due Evaluate Interim Proposals/Advise Offerors of Further Issues Interim Questions to Offerors Final Proposals Due Final Proposal Evaluation; Revisions to Findings Create Final SSA Presentation Dry-Run of SSA Presentation Final SSA Presentation Source Selection Statement ANOSCA/Press Release Debriefings Protest Period Award Contract; Process in Procurement's CMM System Commence Phase-In Disclaimer: This briefing is not a government document. Ex-Officio 12
  • 13. Caveats • Real experiences in terms of duration will be longer than the ideal. • A full team will staff up and remain available throughout the procurement process. • Wait time for managers to get to decision packages is minimal though not always achievable. • Post award engagement with the vendor for long lead time items will reduce risks. Disclaimer: This briefing is not a government document. 13
  • 14. Wrap Up • A $10-50M procurement is a full time job for the “wagon master” in charge of it. Disclaimer: This briefing is not a government document. 14
  • 15. Backup Slides Disclaimer: This briefing is not a government document. 15
  • 16. Large Procurements • Detailed schedule • Three major phases • Work tasks conducted in parallel Disclaimer: This briefing is not a government document. 16
  • 17. Phase 1 Milestones Create Schedules / WBS 1. 2. 3. 4. 5. 6. Create procurement WBS Form source evaluation team Set up admin support / logistics Draft statement of work (SOW) Draft request for proposal (RFP) Procurement Strategy Briefing Disclaimer: This briefing is not a government document. 17
  • 18. Phase 1 Schedule Parts 1-3 Milestones Disclaimer: This briefing is not a government document. 18
  • 19. Phase 1 Schedule Parts 4-5 Milestones Disclaimer: This briefing is not a government document. 19
  • 20. Phase 1 Schedule Part 6 Milestone Disclaimer: This briefing is not a government document. 20
  • 21. Phase 2 Milestones Publish RFP/ Receive Bids 1. Complete RFP 2. Vendor Response Completion Disclaimer: This briefing is not a government document. 21
  • 22. Phase 2 Schedule Part 1 Milestone Disclaimer: This briefing is not a government document. 22
  • 23. Phase 2 Schedule Part 2 Milestone Disclaimer: This briefing is not a government document. 23
  • 24. Part 3 Milestones Review Bids / Award Contract 1. Review RFP Responses 2. Source Selection Decision Disclaimer: This briefing is not a government document. 24
  • 25. Phase 3 Schedule Part 1 Milestone Disclaimer: This briefing is not a government document. 25
  • 26. Phase 3 Schedule Part 2 Milestone Disclaimer: This briefing is not a government document. 26
  • 27. Conceptual Blockbusting • Very large procurements can and will bog down under the weight of multiple layers of complex requirements. • Project managers can reduce procurement time by breaking up acquisitions into a parallel series of lower cost buys creating a “portfolio” of smaller, faster moving actions such as design, fabrication, and system integration. Disclaimer: This briefing is not a government document. 27
  • 28. Causes of Procurement Delays • Incomplete specifications – Vendors cannot fabricate based on poorly defined requirements. • Incomplete or incorrect paperwork – NASA GRC Forms C-376 & 1707 cannot be processed with missing or incorrect information. • Incorrect color of money is used – CFO funds approval and financial checks of the procurement include that the correct WBS is being used. • Insufficient time allowed for vendor to deliver – Especially for the selected vendor to fabricate and deliver the materials, goods, components, and/or services. Disclaimer: This briefing is not a government document. 28
  • 29. Vendor Relations Post Award • Don’t let the vendor be a black box on long-lead time, high-value procurements. – If delivery time for a high-value procurement is more than six weeks, consider including a series of check-ins starting at the 20-day mark. – Consider on-site visits, including design and engineering reviews, especially if fabrication involves a first-of-a-kind product. • Be sure to address these issues in the initial requirements that are sent to the vendor. Disclaimer: This briefing is not a government document. 29
  • 30. Sole Source Actions > $150K • Sole source procurements greater than $150K require a “Justification of Other than Competitive” action (JOFOC). • The approved document is published on www.fbo.gov for 15 days. • When in doubt about a sole source approach, contact procurement for advice. • A response from a valid vendor stops the clock and may start one for a competitive process. • If your procurement is not approved to be sole-source, and is for more than $150K, the contracting officer has discretion in setting reasonable time frames for publishing a pre-solicitation synopsis for large buys as well as vendor response time for a solicitation. Disclaimer: This briefing is not a government document. 30
  • 31. Contact Dan Yurman Email: djysrv@gmail.com Linkedin http://www.linkedin.com/in/danyurman/ Mobile: 216-218-3823 Twitter: @djysrv Disclaimer: This briefing is not a government document. 31