We enjoyed meeting Saturday with the Ward 5 Brookland Middle School community. If you happened to have missed the meeting or simply wish to share the update and new proposed work hours with your neighbors, friends and family feel free to share! Thanks.
6. SCHEDULE & WORK HOURS
UPDATE
SCHEDULE
• Students and staff to occupy building 2015-16 school year
• Construction to complete in January 2015
WORK HOURS
• Work to take place during standard DCRA work hours
7AM-7PM Monday through Saturday
• No applications for extended work hours
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
7. CONSTRUCTION UPDATE
ACTIVITY SCHEDULE
COMPLETE
•
Building demolition
•
Ground improvements
ONGOING & UPCOMING
•
Concrete foundations and
waterproofing
•
Steel structure
•
Geothermal Well Drilling (Requires closure of baseball
field and track from December 1, 2013 – April 15, 2014)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
8. CONSTRUCTION UPDATE
PARK USAGE
WORK ACTIVITY
Ongoing DPR modernization of Turkey Thicket park
Baseball field and track closed during geothermal well drilling and
field restoration
Basketball courts closed during expansion of Turkey Thicket
parking lot and basketball court relocation
Two (2) Tennis courts closest to school not in use during school
structure and façade work
All eight (8) tennis courts closed during court re-surfacing
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
TIMEFRAME
Present –
December 2013
December 2013 –
April 2014
April 2014 –
May 2014
Present –
October 2014
October 2014
9. CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
STRUCTURE / SKIN
Present – December 2013
Two (2) Tennis courts closest to
school not in use during school
structure and façade work
(Present – October 2014)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
10. CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
GEOTHERMAL & FACADE
December 2013 – April 2014
Baseball field and track closed during
geothermal well drilling and field
restoration (Present – October 2014)
Two (2) Tennis courts closest to
school not in use during school
structure and façade work
(Present – October 2014)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
11. CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
INTERIORS
May 2013 – January 2015
Parking lot expanded and basketball
courts relocated during April & May 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
Tennis courts get resurfaced
in October 2014
12. NEXT STEPS
• Next SIT Meeting in December 2013
• Focus on interior finishes and design
• Resume “envelope” meetings
• Monthly updates to be e-mailed at end of each
month
• Community Meeting in February 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013