SlideShare uma empresa Scribd logo
1 de 54
YOUR PARTNER WITH
   SOLUTIONS
Carbon Fiber Wraps
Carbon Fiber Wraps
What Are FRP Composites?


         Reinforcing Fiber
         (Glass, Carbon, Kevlar, etc.)

           Interphase Coupling Agent
           Polymer Resin Matrix
Advantages of Carbon Fiber
•   High Strength (400 KSI Tensile)
•   Low Weight (less than 0.5 pounds per sq. ft.)
•   Corrosion Resistance (pH 2 – pH 13)
•   Thermal Compatibility
•   Excellent Fatigue Behavior
•   Non-conductive (glass), Conductive (carbon)
•   Speed of Construction
•   Low Cost
Engineering Support
• Full range of support
• Software assistance
• Full engineering capabilities including
  stamp
• Minor support and design assistance
Examples of Applications
•   PCCP hoop strengthening
•   Missing/under designed reinforcement
•   Seismic strengthening
•   Cutting or drilling of structural members
•   Low cylinder breaks
•   Adding capacity
•   Underground/Sewer/Water Infrastructure
•   Fatigued Members
•   Corrosion Mitigation
•   Steel Pipe Repair & Strengthening
PCCP Hoop Strengthening
Cholla Power Plant

     Situation:
     The 66" circ line had experienced enough wire breaks
     that a possible rupture was a major concern. The original
     repair was only 40-60 linear feet depending on the
     condition of the pipe. We needed to be able to restore the
     pressure bearing capacity of the circ line, the overburden
     was only 8’.



      Challenges:
      Time restraint was a major factor, this job there was only
      a small window of time to do the entire job. The prep
      work for the job was limited to only within 2 weeks. To
      remove and replace the line would have involved too
      much time and disruption of the existing above ground
      infrastructure. Likewise external tensioning would have
      taken too long with too much disruption.
Cholla Power Plant

     Solution:
     We went ahead and came up with a comparable solution
     that would not affect any of the above ground
     infrastructure and still provide the needed support.
     Carbon fiber was installed in two layers of 20 oz
     unidirectional in a hoop direction.




     Conclusion:
     The original 40 linear feet was done in 2 days. After the
     completion of the work, APS requested us to complete
     an additional 120 lf. We mobilized within 72 working
     hours and completed the additional 120 lf within 5 days.
•San Juan Power Plant


      Situation:
      Wire breaks in the 10' diameter pipes severely limited
      the capacity of the pipe to with stand internal pressure.
      The goal was to restore the capacity of the pipeline.




       Challenges:
       All work needed to be done within the time frame of the
       shut down of 3 weeks for the # 3 circ line and 3 days for
       the #4 circ line. Replacement was far too costly and too
       much down time. Steel lining would reduce the flow,
       cause future corrosion, and would have high
       mobilization costs.
•San Juan Power Plant

       Solution:
       It was decided to install 20 oz of unidirectional carbon
       fiber in hoop direction, because this solution can be done
       quickly and with little invasiveness. Another supporting
       reason was because the risk of corrosion would be
       nonexistent.




        Conclusion:
        Before installation took place it was discovered that
        there were severe cracks where the carbon fiber was to
        be installed in the hoop direction. 20 oz of carbon fiber
        was installed perpendicular to the cracks before
        installing in the hoop direction to help maintain the
        integrity of the pipe. The job was completed in the time
        required and is still functioning today.
Missing/Under designed reinforcing


•   Downtown Lofts
•   Missing rebar in High Rise
•   Column cage missing
•   Scottsdale office building floor
    strengthening
B of A Bank Renovation
This building in Old Town Scottsdale was being renovated to provide a new home
for a B of A Bank branch. The bank vault was being installed on the first floor
slab over a parking garage below. The slab needed to be strengthened to carry
the load of the vault.
B of A Bank Renovation
Existing cracks in the slab were first epoxy injected then carbon fiber fabric
was installed on the top of the slab.
B of A Bank Renovation
The double T’s were then strengthened by adding carbon fiber laminates strips
on the under sides of the T stems then the entire T was wrapped with carbon
fiber fabric.

This engineered solution provided the additional capacity to carry the
additional load of the new vault.
Seismic Strengthening
• Harvest Prep
• AmeriSchools
AmeriSchools Academy
• The City of Yuma dictated that
  AmeriSchools Academy, built of CMU
  masonry, be reinforced to protect the
  students, teachers and workers in case of
  an earthquake.
The Solution
After several solutions were investigated, it was determined that seismic
reinforcement could best be achieved with carbon-fiber composites applied to the
exterior and interior wall surfaces.


  North side of building after sandblasting to   Front entrance is shown with windows
  remove paint in areas where carbon-fiber is    removed and surface sandblasted, now ready
  to be installed.                               for 2 layers of fabric to be installed
The Results
The application of carbon-fiber fabrics and laminates proved to be the least
expensive and most effective way to provide seismic reinforcement. The client was
very satisfied with the product and job coordination. Realizing the challenges the
crew faced doing this in the summer when the temperature was between 110 and
120 degrees. The job was completed in time for the school to reopen for classes
the end of July.


  Shown below the crew is installing          This shows the front entry after the
  carbon-fiber laminates on the interior      application of bi-directional fabrics.
  walls and openings.                         Stucco was later added then painted.
AmeriSchools Academy
   The completed project
Cutting or Drilling Structural Members

• DEMA
• Summit at Copper Square
DEMA Renovation

• On this renovation project (10) 6” pre-cast
  hollow-core floor planks had numerous
  penetrations through them for utilities.
  Many of them were old existing and
  several new penetrations were created for
  new plumbing. In many cases these
  penetrations had severed the post tension
  cables.
The Solution
Fill the old penetrations that were not to be reused. Install 4” wide carbon fiber
laminate strips to the underside of the planks in the areas where the penetrations
had been filled.
At the areas where the new plumbing was protruding we overlaid 12” wide carbon
fiber fabric strips in a cross hash pattern over the laminate going 24” past the
plumbing on all sides.
The Results
The strength lost because of the penetrations and the post tension cables being
cut was restored. This allowed the restoration to continue at a great cost saving
over replacing the floor planks. Which would have been an enormous construction
issue at best.
The Summit at Copper Square
• This 23 story concrete shear wall
  residential building had 35 spandrel
  beams that were cored for pipe sleeves
  below the approved zone per criteria given
  by the engineer of record. This caused a
  lost of capacity of 35 kips in downward
  shear.
The Solution
Install one layer of uni-directional carbon fiber fabric the full width of the beams and
wrapping the complete beam. It was determined that any beam with a core 8 ½” or
less from the bottom of the beam need carbon fiber support. This replaced the 35
kips structural strength lost by the cores while maintaining the ceiling height in the
hallways.
The Results
Because some of the plumbing had already been installed the fabric had to be cut
to allow the installers to wrap the fabric around the pipes. A second layer of fabric
was installed over the cuts in a horizontal direction to prevent lose of strength from
the cuts. The job was completed in 2 weeks and the contractor was able to get
back on schedule with construction.
Low Cylinder Breaks
Adding Capacity
•   Garden roofs
•   Upsizing HVAC
•   Machinery changes
•   Parking Garage add ons
•   U of A Dorm retrofit
•   Wells Fargo Shear Strengthening
Underground/Sewer/Water
       Infrastructure Vaults etc
• Roger Road
Roger Road Treatment Plant

           Situation:
           The digestive gasses eroded the existing concrete
           columns and deteriorated the existing reinforcement.




           Challenges:
           The sludge digester needed to be kept free of rocks and
           pebbles. The floor of the digester was slanted making
           scaffolding a challenge and more difficult to keep debris
           out.
Roger Road Treatment Plant
    Solution:
    Installers from the Arizona Repair Masons' Specialty
    Crew reinforced deteriorated columns with carbon fiber
    composites inside the drained digester tank of the
    sewage treatment plant. Damaged rebar was augmented
    with fiberglass rebar.



Columns being wrapped with Carbon
fiber laminates in order to reinforce
the eroded areas.




Conclusion:
Company was happy with the end results of restoration
to the columns.
Deteriorated / Spalled Columns
• Added Touch Warehouse
• CityScape Garage
Added Touch Warehouse
Badly spalled and deteriorated columns due to years of water coming
from the scuppers with no down spouts.
Added Touch Warehouse
•After the concrete repairs were made carbon fiber was installed to regain the
strength lost from the corroded rebar.
•The owner wanted the repaired columns to match the appearance of the other
columns on this structure.
•After the carbon fiber was installed sand was broadcast on the columns for a
base to apply stucco.
CityScape Garage
•Severe cracking in the column corbel had reduced the capacity
CityScape Garage
• The cracked and spalled concrete was removed to provide a solid
strata for the repair mortar and the exposed rebar was cleaned and
treated with a corrosion inhibitor.
CityScape Garage
•After the concrete repairs were made carbon fiber was installed to confine the
repair and regain the loss of strength due to the corroded rebar.
Fatigued Members
• Central Stores
• State Farm Insurance
• Transwestern
Central Stores—City of Phoenix
Situation:
The wood beams that support the roof had been
deflecting over a few years. The problems are
exacerbated with the ponding of rain water in the
dips created from the deflections. There were
approximately 190 beams that required
strengthening. The Owner (The City of Phoenix)
wanted us to arrest any continued deflections and
increase the margin of safety for the users.




                                                    Challenges:
                                                    Work in the space was to continue without
                                                    shutting down the users.
                                                    Air conditioning replacement was going on
                                                    simultaneously which caused poor ventilation.
Central Stores—City of Phoenix

                   Solution:
                   Carbon fiber laminate reinforcing with
                   fiberglass fabric stirrups were used. The
                   Carbon laminates provide continuous
                   adhesive reinforcing. The laminates were
                   placed in the middle 8' of the beams,
                   where the deflection was the greatest on
                   the tension face. The glass fabrics were
                   used to eliminate shear stresses on the
                   ends and to transfer the tensile force of
                   the laminates up through the natural axis.
Central Stores—City of Phoenix
               Conclusion:
               Arizona Repair Masons helped insure that the
               original engineering was adequate to meet the
               loads with acceptable deflection by insisting
               that the original calcs be checked. Workers
               used respirators during operations. The
               overstress on the beams was reduced to less
               than .07% and the ponds on the roof were
               filled in with foam to shed future water.
Transwestern
Transwestern
Transwestern
Transwestern
Corrosion Mitigation
• Ray Mine
 The corrosive atmosphere
Before




Before
Shoring




Patching
Installing the carbon fiber




 completed
QUESTIONS

Mais conteúdo relacionado

Mais procurados

INVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETE
INVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETEINVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETE
INVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETE
Sk Md Nayar
 

Mais procurados (20)

Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
 
Steel fiber reinforced concrete
Steel fiber reinforced concreteSteel fiber reinforced concrete
Steel fiber reinforced concrete
 
Fiber glass reinforcement
Fiber glass reinforcementFiber glass reinforcement
Fiber glass reinforcement
 
Steel fibre reinforced_concrete
Steel fibre reinforced_concreteSteel fibre reinforced_concrete
Steel fibre reinforced_concrete
 
Repair and strengthening of concrete structures
Repair and strengthening of concrete structuresRepair and strengthening of concrete structures
Repair and strengthening of concrete structures
 
Structural Strengthening
Structural StrengtheningStructural Strengthening
Structural Strengthening
 
Reactive powder-concrete
Reactive powder-concreteReactive powder-concrete
Reactive powder-concrete
 
Fibre Reinforced concrete
Fibre Reinforced concrete Fibre Reinforced concrete
Fibre Reinforced concrete
 
Polymer concrete and it's types
Polymer concrete and it's typesPolymer concrete and it's types
Polymer concrete and it's types
 
Strengthening Of Beams for flexure Using FRP
Strengthening Of Beams  for flexure Using FRPStrengthening Of Beams  for flexure Using FRP
Strengthening Of Beams for flexure Using FRP
 
INVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETE
INVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETEINVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETE
INVESTIGATION ON FLY ASH AS A PARTIAL CEMENT REPLACEMENT IN CONCRETE
 
Fiber reinforced concrete
Fiber reinforced concreteFiber reinforced concrete
Fiber reinforced concrete
 
Water in concrete
Water in concreteWater in concrete
Water in concrete
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairs
 
Aerated concrete-Concrete Technology
Aerated concrete-Concrete TechnologyAerated concrete-Concrete Technology
Aerated concrete-Concrete Technology
 
Admixtures And Their Properties
Admixtures And Their PropertiesAdmixtures And Their Properties
Admixtures And Their Properties
 
a project on fibre-reinforced-concrete.
a project on fibre-reinforced-concrete.a project on fibre-reinforced-concrete.
a project on fibre-reinforced-concrete.
 
Fiber reinforced composite materials
Fiber reinforced composite materialsFiber reinforced composite materials
Fiber reinforced composite materials
 
fibre reinforced concrete
fibre reinforced concretefibre reinforced concrete
fibre reinforced concrete
 
Fibre Reinforced Concrete
Fibre Reinforced ConcreteFibre Reinforced Concrete
Fibre Reinforced Concrete
 

Semelhante a Carbon Fiber - FRP

Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technology
LTDH2013
 
J&P Building Systems Ltd - An Introduction
J&P Building Systems Ltd - An IntroductionJ&P Building Systems Ltd - An Introduction
J&P Building Systems Ltd - An Introduction
J and P Building Systems
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Blake Johnson
 

Semelhante a Carbon Fiber - FRP (20)

Carbon Fiber
Carbon FiberCarbon Fiber
Carbon Fiber
 
Foundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic RepairsFoundation Repair Systems & Forensic Repairs
Foundation Repair Systems & Forensic Repairs
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technology
 
J&P Building Systems Ltd - An Introduction
J&P Building Systems Ltd - An IntroductionJ&P Building Systems Ltd - An Introduction
J&P Building Systems Ltd - An Introduction
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12
 
ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2
 
Jefferson County Historical High School
Jefferson County Historical High SchoolJefferson County Historical High School
Jefferson County Historical High School
 
Dn tanks prestressed_concretetank
Dn tanks prestressed_concretetankDn tanks prestressed_concretetank
Dn tanks prestressed_concretetank
 
Jacketing
JacketingJacketing
Jacketing
 
FYP Presentation group 1.pptx
FYP Presentation group 1.pptxFYP Presentation group 1.pptx
FYP Presentation group 1.pptx
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3
 
Seminar_Repair & Restoration_of_Structure
Seminar_Repair & Restoration_of_StructureSeminar_Repair & Restoration_of_Structure
Seminar_Repair & Restoration_of_Structure
 
retrofitting of fire damaged rcc slabs,colums,beams
retrofitting of fire damaged rcc slabs,colums,beamsretrofitting of fire damaged rcc slabs,colums,beams
retrofitting of fire damaged rcc slabs,colums,beams
 
autoclaved aerated concrete
autoclaved aerated concreteautoclaved aerated concrete
autoclaved aerated concrete
 
3100 Ozada Ave parkade roof membrane
3100 Ozada Ave parkade roof membrane3100 Ozada Ave parkade roof membrane
3100 Ozada Ave parkade roof membrane
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
 
Pardon Our Thunderdust 2011-2012
Pardon Our Thunderdust 2011-2012Pardon Our Thunderdust 2011-2012
Pardon Our Thunderdust 2011-2012
 
CC Intro
CC IntroCC Intro
CC Intro
 

Carbon Fiber - FRP

  • 1. YOUR PARTNER WITH SOLUTIONS
  • 4. What Are FRP Composites? Reinforcing Fiber (Glass, Carbon, Kevlar, etc.) Interphase Coupling Agent Polymer Resin Matrix
  • 5. Advantages of Carbon Fiber • High Strength (400 KSI Tensile) • Low Weight (less than 0.5 pounds per sq. ft.) • Corrosion Resistance (pH 2 – pH 13) • Thermal Compatibility • Excellent Fatigue Behavior • Non-conductive (glass), Conductive (carbon) • Speed of Construction • Low Cost
  • 6. Engineering Support • Full range of support • Software assistance • Full engineering capabilities including stamp • Minor support and design assistance
  • 7. Examples of Applications • PCCP hoop strengthening • Missing/under designed reinforcement • Seismic strengthening • Cutting or drilling of structural members • Low cylinder breaks • Adding capacity • Underground/Sewer/Water Infrastructure • Fatigued Members • Corrosion Mitigation • Steel Pipe Repair & Strengthening
  • 9. Cholla Power Plant Situation: The 66" circ line had experienced enough wire breaks that a possible rupture was a major concern. The original repair was only 40-60 linear feet depending on the condition of the pipe. We needed to be able to restore the pressure bearing capacity of the circ line, the overburden was only 8’. Challenges: Time restraint was a major factor, this job there was only a small window of time to do the entire job. The prep work for the job was limited to only within 2 weeks. To remove and replace the line would have involved too much time and disruption of the existing above ground infrastructure. Likewise external tensioning would have taken too long with too much disruption.
  • 10. Cholla Power Plant Solution: We went ahead and came up with a comparable solution that would not affect any of the above ground infrastructure and still provide the needed support. Carbon fiber was installed in two layers of 20 oz unidirectional in a hoop direction. Conclusion: The original 40 linear feet was done in 2 days. After the completion of the work, APS requested us to complete an additional 120 lf. We mobilized within 72 working hours and completed the additional 120 lf within 5 days.
  • 11. •San Juan Power Plant Situation: Wire breaks in the 10' diameter pipes severely limited the capacity of the pipe to with stand internal pressure. The goal was to restore the capacity of the pipeline. Challenges: All work needed to be done within the time frame of the shut down of 3 weeks for the # 3 circ line and 3 days for the #4 circ line. Replacement was far too costly and too much down time. Steel lining would reduce the flow, cause future corrosion, and would have high mobilization costs.
  • 12. •San Juan Power Plant Solution: It was decided to install 20 oz of unidirectional carbon fiber in hoop direction, because this solution can be done quickly and with little invasiveness. Another supporting reason was because the risk of corrosion would be nonexistent. Conclusion: Before installation took place it was discovered that there were severe cracks where the carbon fiber was to be installed in the hoop direction. 20 oz of carbon fiber was installed perpendicular to the cracks before installing in the hoop direction to help maintain the integrity of the pipe. The job was completed in the time required and is still functioning today.
  • 13. Missing/Under designed reinforcing • Downtown Lofts • Missing rebar in High Rise • Column cage missing • Scottsdale office building floor strengthening
  • 14.
  • 15.
  • 16. B of A Bank Renovation This building in Old Town Scottsdale was being renovated to provide a new home for a B of A Bank branch. The bank vault was being installed on the first floor slab over a parking garage below. The slab needed to be strengthened to carry the load of the vault.
  • 17. B of A Bank Renovation Existing cracks in the slab were first epoxy injected then carbon fiber fabric was installed on the top of the slab.
  • 18. B of A Bank Renovation The double T’s were then strengthened by adding carbon fiber laminates strips on the under sides of the T stems then the entire T was wrapped with carbon fiber fabric. This engineered solution provided the additional capacity to carry the additional load of the new vault.
  • 19. Seismic Strengthening • Harvest Prep • AmeriSchools
  • 20. AmeriSchools Academy • The City of Yuma dictated that AmeriSchools Academy, built of CMU masonry, be reinforced to protect the students, teachers and workers in case of an earthquake.
  • 21. The Solution After several solutions were investigated, it was determined that seismic reinforcement could best be achieved with carbon-fiber composites applied to the exterior and interior wall surfaces. North side of building after sandblasting to Front entrance is shown with windows remove paint in areas where carbon-fiber is removed and surface sandblasted, now ready to be installed. for 2 layers of fabric to be installed
  • 22. The Results The application of carbon-fiber fabrics and laminates proved to be the least expensive and most effective way to provide seismic reinforcement. The client was very satisfied with the product and job coordination. Realizing the challenges the crew faced doing this in the summer when the temperature was between 110 and 120 degrees. The job was completed in time for the school to reopen for classes the end of July. Shown below the crew is installing This shows the front entry after the carbon-fiber laminates on the interior application of bi-directional fabrics. walls and openings. Stucco was later added then painted.
  • 23. AmeriSchools Academy The completed project
  • 24. Cutting or Drilling Structural Members • DEMA • Summit at Copper Square
  • 25. DEMA Renovation • On this renovation project (10) 6” pre-cast hollow-core floor planks had numerous penetrations through them for utilities. Many of them were old existing and several new penetrations were created for new plumbing. In many cases these penetrations had severed the post tension cables.
  • 26. The Solution Fill the old penetrations that were not to be reused. Install 4” wide carbon fiber laminate strips to the underside of the planks in the areas where the penetrations had been filled. At the areas where the new plumbing was protruding we overlaid 12” wide carbon fiber fabric strips in a cross hash pattern over the laminate going 24” past the plumbing on all sides.
  • 27. The Results The strength lost because of the penetrations and the post tension cables being cut was restored. This allowed the restoration to continue at a great cost saving over replacing the floor planks. Which would have been an enormous construction issue at best.
  • 28. The Summit at Copper Square • This 23 story concrete shear wall residential building had 35 spandrel beams that were cored for pipe sleeves below the approved zone per criteria given by the engineer of record. This caused a lost of capacity of 35 kips in downward shear.
  • 29. The Solution Install one layer of uni-directional carbon fiber fabric the full width of the beams and wrapping the complete beam. It was determined that any beam with a core 8 ½” or less from the bottom of the beam need carbon fiber support. This replaced the 35 kips structural strength lost by the cores while maintaining the ceiling height in the hallways.
  • 30. The Results Because some of the plumbing had already been installed the fabric had to be cut to allow the installers to wrap the fabric around the pipes. A second layer of fabric was installed over the cuts in a horizontal direction to prevent lose of strength from the cuts. The job was completed in 2 weeks and the contractor was able to get back on schedule with construction.
  • 32. Adding Capacity • Garden roofs • Upsizing HVAC • Machinery changes • Parking Garage add ons • U of A Dorm retrofit • Wells Fargo Shear Strengthening
  • 33. Underground/Sewer/Water Infrastructure Vaults etc • Roger Road
  • 34. Roger Road Treatment Plant Situation: The digestive gasses eroded the existing concrete columns and deteriorated the existing reinforcement. Challenges: The sludge digester needed to be kept free of rocks and pebbles. The floor of the digester was slanted making scaffolding a challenge and more difficult to keep debris out.
  • 35. Roger Road Treatment Plant Solution: Installers from the Arizona Repair Masons' Specialty Crew reinforced deteriorated columns with carbon fiber composites inside the drained digester tank of the sewage treatment plant. Damaged rebar was augmented with fiberglass rebar. Columns being wrapped with Carbon fiber laminates in order to reinforce the eroded areas. Conclusion: Company was happy with the end results of restoration to the columns.
  • 36. Deteriorated / Spalled Columns • Added Touch Warehouse • CityScape Garage
  • 37. Added Touch Warehouse Badly spalled and deteriorated columns due to years of water coming from the scuppers with no down spouts.
  • 38. Added Touch Warehouse •After the concrete repairs were made carbon fiber was installed to regain the strength lost from the corroded rebar. •The owner wanted the repaired columns to match the appearance of the other columns on this structure. •After the carbon fiber was installed sand was broadcast on the columns for a base to apply stucco.
  • 39. CityScape Garage •Severe cracking in the column corbel had reduced the capacity
  • 40. CityScape Garage • The cracked and spalled concrete was removed to provide a solid strata for the repair mortar and the exposed rebar was cleaned and treated with a corrosion inhibitor.
  • 41. CityScape Garage •After the concrete repairs were made carbon fiber was installed to confine the repair and regain the loss of strength due to the corroded rebar.
  • 42. Fatigued Members • Central Stores • State Farm Insurance • Transwestern
  • 43. Central Stores—City of Phoenix Situation: The wood beams that support the roof had been deflecting over a few years. The problems are exacerbated with the ponding of rain water in the dips created from the deflections. There were approximately 190 beams that required strengthening. The Owner (The City of Phoenix) wanted us to arrest any continued deflections and increase the margin of safety for the users. Challenges: Work in the space was to continue without shutting down the users. Air conditioning replacement was going on simultaneously which caused poor ventilation.
  • 44. Central Stores—City of Phoenix Solution: Carbon fiber laminate reinforcing with fiberglass fabric stirrups were used. The Carbon laminates provide continuous adhesive reinforcing. The laminates were placed in the middle 8' of the beams, where the deflection was the greatest on the tension face. The glass fabrics were used to eliminate shear stresses on the ends and to transfer the tensile force of the laminates up through the natural axis.
  • 45. Central Stores—City of Phoenix Conclusion: Arizona Repair Masons helped insure that the original engineering was adequate to meet the loads with acceptable deflection by insisting that the original calcs be checked. Workers used respirators during operations. The overstress on the beams was reduced to less than .07% and the ponds on the roof were filled in with foam to shed future water.
  • 50. Corrosion Mitigation • Ray Mine The corrosive atmosphere
  • 53. Installing the carbon fiber completed