SlideShare uma empresa Scribd logo
1 de 1
Baixar para ler offline
ENERGY EFFICIENT TECHNOLOGY PROCUREMENT:SOME GOOD PRACTCES:
Once an Energy auditor presents to the management a list of opportunities with potential, cost
benefits, vendor information etc, the implementation process begins and while housekeeping,
no cost, low cost measures are easy enough to implement without hassles, EET procurement
and implementation is often a concern area, especially in several SMEs and traditional units,
where in- house techno-managerial skills are found wanting.
These concerns include Information overload on one hand and EET vendor push on the other,
alongside considerable technical and financial risks.
Some proven good practices for management consideration in EET Procurements are as
follows:
1. Categorize opportunities and, for prioritized high investment, high technology interventions,
opt for a DPR preparation with due sensitivity analysis before implementation. Some projects
may involve residual life assessment, renovation and modernization, process line balancing
etc.
2. Assign a dedicated and empowered in-house project management team, inter-departmental
preferably, and provide for its capacity building on EETs proposed.
3. Just lowest quotation approach in procurements is dangerous and can lead to repentance
later.
Here follow supportive procurement criteria that managements may insist on, apart from
competitive financial bids:
• Information on Design/Technical specifications, QA features. (Sometimes sharing
proprietary design information may be denied)
• EET Compliance with relevant International/local standards
• International partners/tie-ups of suppliers
• Vendor readiness to include supply, erection, testing and commissioning in scope.
• Referrals of vendor clients served in the region/ facilitation of visits to such sites.
• Performance guarantees.
• Vendor acceptance of third party verification.
• Acceptance of Penalty clause in case of non-performance.
• Vendor training of plant staff and hand-holding for a few weeks, if not an O&M contract,
as needed.
• Local/regional presence of EET suppliers for spares, consumables, maintenance
services.
• On line Instruments provision to facilitate Pre and Post performance monitoring of EETs.
Given that EET vendors may not agree to fulfill all these criteria, it is desirable that
managements may incorporate selectively, some of these criteria in EET procurement process
for technical and financial risk minimization.

Mais conteúdo relacionado

Mais procurados

BOMA presentation - June - 2015
BOMA presentation - June - 2015BOMA presentation - June - 2015
BOMA presentation - June - 2015
Larry Wash
 
Observations on just culture development for VNA
Observations on just culture development for VNAObservations on just culture development for VNA
Observations on just culture development for VNA
DigitalPower
 
Compliance plus presentation slide share
Compliance plus presentation slide shareCompliance plus presentation slide share
Compliance plus presentation slide share
Andy Brooks
 
Fleet Management Diagnostic Approach
Fleet Management Diagnostic ApproachFleet Management Diagnostic Approach
Fleet Management Diagnostic Approach
722consulting
 
Facility engineering and Maintenance
Facility engineering and MaintenanceFacility engineering and Maintenance
Facility engineering and Maintenance
Pat Cabangis
 

Mais procurados (20)

Vibration preventive maintenance, types , advantages
Vibration  preventive maintenance, types , advantagesVibration  preventive maintenance, types , advantages
Vibration preventive maintenance, types , advantages
 
BOMA presentation - June - 2015
BOMA presentation - June - 2015BOMA presentation - June - 2015
BOMA presentation - June - 2015
 
Airport Asset management chapter 1
Airport Asset management chapter 1Airport Asset management chapter 1
Airport Asset management chapter 1
 
Observations on just culture development for VNA
Observations on just culture development for VNAObservations on just culture development for VNA
Observations on just culture development for VNA
 
Day 5: ESCOs Rules and Roles
Day 5:  ESCOs Rules and Roles Day 5:  ESCOs Rules and Roles
Day 5: ESCOs Rules and Roles
 
How To Improve Your Maintenance Spare Parts Management
How To Improve Your Maintenance Spare Parts ManagementHow To Improve Your Maintenance Spare Parts Management
How To Improve Your Maintenance Spare Parts Management
 
10. Process: ocp cfops security and access
10. Process: ocp cfops security and access10. Process: ocp cfops security and access
10. Process: ocp cfops security and access
 
Solar power plant management by OutSmart
Solar power plant management by OutSmartSolar power plant management by OutSmart
Solar power plant management by OutSmart
 
Preventive Maintenance Presentation
Preventive Maintenance PresentationPreventive Maintenance Presentation
Preventive Maintenance Presentation
 
Compliance plus presentation slide share
Compliance plus presentation slide shareCompliance plus presentation slide share
Compliance plus presentation slide share
 
Building A Winning Maintenance Strategy
Building A Winning Maintenance StrategyBuilding A Winning Maintenance Strategy
Building A Winning Maintenance Strategy
 
Fleet Management Diagnostic Approach
Fleet Management Diagnostic ApproachFleet Management Diagnostic Approach
Fleet Management Diagnostic Approach
 
maintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay methodmaintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay method
 
Predictive maintenance
Predictive maintenancePredictive maintenance
Predictive maintenance
 
International Auditing Standards (ISA)
International Auditing Standards (ISA)International Auditing Standards (ISA)
International Auditing Standards (ISA)
 
Facility engineering and Maintenance
Facility engineering and MaintenanceFacility engineering and Maintenance
Facility engineering and Maintenance
 
Fm ws report
Fm ws reportFm ws report
Fm ws report
 
Engineering plant facilities 12 mechanics building preventive maintenance and...
Engineering plant facilities 12 mechanics building preventive maintenance and...Engineering plant facilities 12 mechanics building preventive maintenance and...
Engineering plant facilities 12 mechanics building preventive maintenance and...
 
Guide to CNC Machine Maintenance and Calibration
Guide to CNC Machine Maintenance and CalibrationGuide to CNC Machine Maintenance and Calibration
Guide to CNC Machine Maintenance and Calibration
 
Maintenance module 1 ppt number 2
Maintenance module 1 ppt number 2Maintenance module 1 ppt number 2
Maintenance module 1 ppt number 2
 

Semelhante a Energy efficient technology procurement

Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.ppt
Thushan9
 

Semelhante a Energy efficient technology procurement (20)

Regulatory Affairs Outsourcing Considerations and Models
Regulatory Affairs Outsourcing Considerations and ModelsRegulatory Affairs Outsourcing Considerations and Models
Regulatory Affairs Outsourcing Considerations and Models
 
Tech connect fall 2015 value proposition to encouraging adoption
Tech connect fall 2015   value proposition to encouraging adoption Tech connect fall 2015   value proposition to encouraging adoption
Tech connect fall 2015 value proposition to encouraging adoption
 
Accountability – Managing the Risks of Innovation Procurement
Accountability – Managing the Risks of Innovation ProcurementAccountability – Managing the Risks of Innovation Procurement
Accountability – Managing the Risks of Innovation Procurement
 
Practical tips for implementing corporate performance management system
Practical tips for implementing corporate performance management systemPractical tips for implementing corporate performance management system
Practical tips for implementing corporate performance management system
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf
 
Unit viii preparation of project report
Unit viii preparation of project reportUnit viii preparation of project report
Unit viii preparation of project report
 
Presentation maintenence management
Presentation maintenence managementPresentation maintenence management
Presentation maintenence management
 
It opslink slidesharebidpresentation v1
It opslink slidesharebidpresentation v1It opslink slidesharebidpresentation v1
It opslink slidesharebidpresentation v1
 
Return on investment for Electronic Health Records
Return on investment for Electronic Health RecordsReturn on investment for Electronic Health Records
Return on investment for Electronic Health Records
 
FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST
 
Strategic Cost Optimization: Driving Business Innovation While Reducing IT Costs
Strategic Cost Optimization: Driving Business Innovation While Reducing IT CostsStrategic Cost Optimization: Driving Business Innovation While Reducing IT Costs
Strategic Cost Optimization: Driving Business Innovation While Reducing IT Costs
 
Practical Issues of Public Tenders- A Consultant's Perspective
Practical Issues of Public Tenders- A Consultant's PerspectivePractical Issues of Public Tenders- A Consultant's Perspective
Practical Issues of Public Tenders- A Consultant's Perspective
 
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
 
Sucessful BPO Through Technology Enablement
Sucessful BPO Through Technology EnablementSucessful BPO Through Technology Enablement
Sucessful BPO Through Technology Enablement
 
A Next-Generation Approach to Integrated Warranty Management
A Next-Generation Approach to Integrated Warranty ManagementA Next-Generation Approach to Integrated Warranty Management
A Next-Generation Approach to Integrated Warranty Management
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentation
 
Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.ppt
 
Credicon Introduction
Credicon  IntroductionCredicon  Introduction
Credicon Introduction
 
Reliability Engineering in Biomanufacturing - Presentation by Michael Andrews
Reliability Engineering in Biomanufacturing - Presentation by Michael AndrewsReliability Engineering in Biomanufacturing - Presentation by Michael Andrews
Reliability Engineering in Biomanufacturing - Presentation by Michael Andrews
 

Mais de D.Pawan Kumar

Water conservation opportunities.
Water conservation opportunities.Water conservation opportunities.
Water conservation opportunities.
D.Pawan Kumar
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
D.Pawan Kumar
 
Cogeneration: regional experiences
Cogeneration: regional experiencesCogeneration: regional experiences
Cogeneration: regional experiences
D.Pawan Kumar
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasi
D.Pawan Kumar
 
Ea of cw, ct & cond. system
Ea of cw, ct & cond. systemEa of cw, ct & cond. system
Ea of cw, ct & cond. system
D.Pawan Kumar
 
Electricity demand side management and end use efficiency
Electricity demand side management and end use efficiencyElectricity demand side management and end use efficiency
Electricity demand side management and end use efficiency
D.Pawan Kumar
 
As run energy efficiency of cooling towers
As run energy efficiency of cooling towersAs run energy efficiency of cooling towers
As run energy efficiency of cooling towers
D.Pawan Kumar
 
Focus areas in economic operation of DG sets
Focus areas in economic operation of DG setsFocus areas in economic operation of DG sets
Focus areas in economic operation of DG sets
D.Pawan Kumar
 
Hrsg & turbine as run energy efficiency assessment
Hrsg  & turbine as run energy efficiency assessmentHrsg  & turbine as run energy efficiency assessment
Hrsg & turbine as run energy efficiency assessment
D.Pawan Kumar
 
How to conduct energy audit
How to conduct energy auditHow to conduct energy audit
How to conduct energy audit
D.Pawan Kumar
 
Desirable as run information system for energy efficiency of utility clas...
Desirable as run information system  for energy efficiency  of  utility  clas...Desirable as run information system  for energy efficiency  of  utility  clas...
Desirable as run information system for energy efficiency of utility clas...
D.Pawan Kumar
 
As run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiencyAs run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiency
D.Pawan Kumar
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
D.Pawan Kumar
 
Energy efficiency in buildings
Energy efficiency in buildingsEnergy efficiency in buildings
Energy efficiency in buildings
D.Pawan Kumar
 
Compressed air and refrigeration system
Compressed air and refrigeration systemCompressed air and refrigeration system
Compressed air and refrigeration system
D.Pawan Kumar
 

Mais de D.Pawan Kumar (19)

Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.
 
Roadmap for distribution loss reduction.. a step by step approach
Roadmap  for distribution loss reduction.. a step by step approachRoadmap  for distribution loss reduction.. a step by step approach
Roadmap for distribution loss reduction.. a step by step approach
 
Water conservation opportunities.
Water conservation opportunities.Water conservation opportunities.
Water conservation opportunities.
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
Cogeneration: regional experiences
Cogeneration: regional experiencesCogeneration: regional experiences
Cogeneration: regional experiences
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasi
 
Ea of cw, ct & cond. system
Ea of cw, ct & cond. systemEa of cw, ct & cond. system
Ea of cw, ct & cond. system
 
Ee opportunities
Ee opportunities Ee opportunities
Ee opportunities
 
Training manual on energy efficiency for SMEs
Training manual on energy efficiency for SMEsTraining manual on energy efficiency for SMEs
Training manual on energy efficiency for SMEs
 
Electricity demand side management and end use efficiency
Electricity demand side management and end use efficiencyElectricity demand side management and end use efficiency
Electricity demand side management and end use efficiency
 
As run energy efficiency of cooling towers
As run energy efficiency of cooling towersAs run energy efficiency of cooling towers
As run energy efficiency of cooling towers
 
Focus areas in economic operation of DG sets
Focus areas in economic operation of DG setsFocus areas in economic operation of DG sets
Focus areas in economic operation of DG sets
 
Hrsg & turbine as run energy efficiency assessment
Hrsg  & turbine as run energy efficiency assessmentHrsg  & turbine as run energy efficiency assessment
Hrsg & turbine as run energy efficiency assessment
 
How to conduct energy audit
How to conduct energy auditHow to conduct energy audit
How to conduct energy audit
 
Desirable as run information system for energy efficiency of utility clas...
Desirable as run information system  for energy efficiency  of  utility  clas...Desirable as run information system  for energy efficiency  of  utility  clas...
Desirable as run information system for energy efficiency of utility clas...
 
As run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiencyAs run boiler performance assessment for energy efficiency
As run boiler performance assessment for energy efficiency
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
 
Energy efficiency in buildings
Energy efficiency in buildingsEnergy efficiency in buildings
Energy efficiency in buildings
 
Compressed air and refrigeration system
Compressed air and refrigeration systemCompressed air and refrigeration system
Compressed air and refrigeration system
 

Energy efficient technology procurement

  • 1. ENERGY EFFICIENT TECHNOLOGY PROCUREMENT:SOME GOOD PRACTCES: Once an Energy auditor presents to the management a list of opportunities with potential, cost benefits, vendor information etc, the implementation process begins and while housekeeping, no cost, low cost measures are easy enough to implement without hassles, EET procurement and implementation is often a concern area, especially in several SMEs and traditional units, where in- house techno-managerial skills are found wanting. These concerns include Information overload on one hand and EET vendor push on the other, alongside considerable technical and financial risks. Some proven good practices for management consideration in EET Procurements are as follows: 1. Categorize opportunities and, for prioritized high investment, high technology interventions, opt for a DPR preparation with due sensitivity analysis before implementation. Some projects may involve residual life assessment, renovation and modernization, process line balancing etc. 2. Assign a dedicated and empowered in-house project management team, inter-departmental preferably, and provide for its capacity building on EETs proposed. 3. Just lowest quotation approach in procurements is dangerous and can lead to repentance later. Here follow supportive procurement criteria that managements may insist on, apart from competitive financial bids: • Information on Design/Technical specifications, QA features. (Sometimes sharing proprietary design information may be denied) • EET Compliance with relevant International/local standards • International partners/tie-ups of suppliers • Vendor readiness to include supply, erection, testing and commissioning in scope. • Referrals of vendor clients served in the region/ facilitation of visits to such sites. • Performance guarantees. • Vendor acceptance of third party verification. • Acceptance of Penalty clause in case of non-performance. • Vendor training of plant staff and hand-holding for a few weeks, if not an O&M contract, as needed. • Local/regional presence of EET suppliers for spares, consumables, maintenance services. • On line Instruments provision to facilitate Pre and Post performance monitoring of EETs. Given that EET vendors may not agree to fulfill all these criteria, it is desirable that managements may incorporate selectively, some of these criteria in EET procurement process for technical and financial risk minimization.