SlideShare a Scribd company logo
1 of 44
Presentation to Engineers Ireland (Thomond / West Region)
                     8th March, 2011
                         March, 0

 GCCC Contracts – Experience to date:
A review of the operation of the GCCC
Contracts on Civil Engineering projects

                Ciaran McGovern
            TOBIN Consulting Engineers
Topics
•   Background 
•   Risk Management
•   Works Requirements
    W k R        i
•   VAT Issues
•   Suitability Assessment Questionnaires
    Suitability Assessment Questionnaires
•   Delegation of duties to ER’s Site Representative
•   Construction Issues
•   Delay & Compensation Events
•   Employer Claims
•   Client Communications
Background        (1)


• Personal greatest exposure to date primarily with 
  Conditions of Contract for Civil Engineering Works designed 
  by the Employer (Aug 2007)
  by the Employer (Aug 2007)
• Documents downloaded from 
  http://www.constructionprocurement.gov.ie/ 
• No change log for updates
• Difficult to keep current when documents are constantly 
  changing
• Suggest an RSS feed is prepared for the site which would 
  alert of changes?
Background          (2)


• Guiding Principles: (DEHLG training material)
   – “To ensure as far as practicable that the accepted tender 
     prices and the final outturn costs are the same
     prices and the final outturn costs are the same”
   – “To allocate risk so there is optimal transfer to the 
     Contractor”
• Launch date was February 2007, we are now four years in!
Risk Management                    (1)


• Fundamental concept is that risk can be managed, 
  minimised shared or accepted. It cannot be ignored.
• Structured approach / early engagement yields dividends
  Structured approach / early engagement yields dividends
   – Focuses the Consultant / LA to look at the difficult decisions up front e.g. 
     “do we divert the ESB cables or dig around them?”
   – Think about the issues likely to threaten the success of the project and
     Think about the issues likely to threaten the success of the project and 
     address them. Engagement with third parties, decide what is needed 
     and provide for them in the Contract in a clear way e.g. accommodation 
     works, traffic requirements, what are the particular constraints being 
     placed on the Contractor.
   – Can the risks be eliminated entirely – worth considering advance works 
     contracts. Does the programme support this?
   – Heretofore, risks managed in part through the use of Provisional / PC 
            f        k         d          h     h h        f            l/
     Sums / Dayworks. No longer an option in New Works Contracts
Risk Management              (2)


• Risk Treatment Options in a workshop environment
   – Should the risks be accepted by the Employer or transferred to 
     the Contractor
     the Contractor
   – The need to have comprehensive information e.g. type of Site 
     Investigation works, uncovering works in buildings, Ground 
     Penetrating Radar, Utilities mapping
     Penetrating Radar Utilities mapping
Risk Management                 (3)


• Risk allocated to whichever party is best placed to manage 
  them.
   – Optimal risk transfer is not the same as maximum risk transfer
              risk transfer is not the same as maximum risk transfer
   – Circulars from DEHLG / NRA on what default position is for standard 
     Contract types – schedule Part 1K default positions for Delay & 
     compensation events
     compensation events
   – The temptation may be to transfer all risk, but this needs to 
     supported by analysis of the optimal position.
   – Risk transfer consideration may influence Contract type selection
     Risk transfer consideration may influence Contract type selection
Risk Management                   (4)


• Contract Selection –
   – Guidance note 1.4 ‐ Capital Works Management Framework Guidance 
     Note: Procurement and Contract Strategy for Public Works Contracts”. 
                                             gy f
   – Section 2 of that document states: “On projects valued below €5 million, 
     it is more usual to use the Minor Works Contract (PW‐CF5). However, in 
     certain exceptional circumstances the Employer may deem the project 
     sufficiently complex to warrant the use of one of the major works 
         ffi i tl      l t          t th       f       f th    j    k
     contracts (PW‐CF1 or PW‐CF3)”. 
   – Is the use of a monetary threshold the most important arbiter in 
     determining the default position for use of Minor / Major forms of 
     determining the default position for use of Minor / Major forms of
     Contract 
   – What are the exceptional circumstances, what makes the project 
     sufficiently complex?
   – Risk transfer considerations lead into this selection process
Risk Management                (5)


• Consideration of particular types of Complex Projects.
   – Construction of Engineered Landfill Cells
   – Major Civil Engineering Works but typically rolled out in works
     Major Civil Engineering Works, but typically rolled out in works 
     packages less than €5M
   – Civil Engineering Works designed by the Employer, but placing 
     particular design related to Bentonite Enhanced soils with the 
     particular design related to Bentonite Enhanced soils with the
     Contractor
   – Contractor has to source all materials and retain Specialist to 
     batch / mix
     batch / mix
   – Risk on remeasurement considered to be optimal if passed to the 
     Contractor
   – First review suggests Minor Works Form but optimal risk transfer
     First review suggests Minor Works Form, but optimal risk transfer 
     suggests Major Forms
Risk Management               (6)


• Watermains / Trenchless Technology – Water Services
   – Very often tendered as open cut trench using Minor Works Form 
     of Contract
     of Contract
   – Contractor wishes to propose trenchless technology
   – No Value Engineering Clause in Minor Works Forms (clause 4.8)
   – G
     Ground risk optimally managed by contractor if proposal accepted
           d i k ti ll              db     t t if             l    t d
   – Minor works Forms pre‐selects allocation of Ground Risk as being 
     an Employer retained 
   – Optimal risk transfer suggests Ground Risk should be retained by 
                       f
     the Contractor for such technologies as he is best placed to 
     manage it.
Works Requirements                      (1)


• Should they include….
   – Digital design models in 3D
   – If risk K17 (remeasurement) is not a Compensation event is the
     If risk K17 (remeasurement) is not a Compensation event, is the 
     contractor then obliged to undertake a detailed analysis of the quantum.
   – Does a 3D model assist with such an exercise.
   – Would such a proposal be of equal benefit to both small and large 
                       p p           q                                g
     Contractors
   – If such information was provided, should it be included within the 
     “Relevant Background Information” or part of the Works Requirements
   – If it is part of the Works Requirements, can the contractor then rely 
     upon it 
   – Would this undermine the original intent of transferring the risk related 
     to remeasurement i.e. Risk K5 – F t l E
     t                    t i Ri k K5 Factual Error about the site 
                                                     b t th it
Works Requirements                    (2)


• Is a Bill of Quantities needed? 
   – In Water Service Projects, the default position is that a detailed 
     Bill of Quantities using CESMM should be prepared
     Bill of Quantities using CESMM should be prepared
   – Similarly Roads projects use MMRB
   – In the absence of guidance from Specific Government Sections, 
     what do the Department of Finance Guidance Notes say
     what do the Department of Finance Guidance Notes say
Works Requirements            (3)


• Guidance Note 1.5 as available from the Government 
  Construction Procurement website 
  http://www.constructionprocurement.gov.ie/,  prescribes 
  http://www constructionprocurement gov ie/ prescribes
  details of the format of the BOQ
Works Requirements                      (4)


• Referring specifically to “Section 2.6.3 ‐ Prescribing the Content
  of the Pricing Document” and specifically to the guidance on
  “Compiling the Pricing Document”, it states:
       p g              g            ,

       “The primary pricing document may be one of the following:
           – A comprehensive and fully measured list of quantities and
             specifications drawn up in a formal Bill of Quantities; tenderers
             can then insert their rates against the categories specified by the
             Employer (this is appropriate for Employer‐designed contracts
             only); or.
           – A multiple‐page tender cost analysis detailing how the tender
             price is to be broken down – the Employer should follow best
             practice in specifying the headings under which price details are
             to be presented.”
Works Requirements                (5)


• Factors influencing the decision to prepare a detailed BOQ 
  or to specify the headings under which the Contractor 
  prepares his tender
  prepares his tender
   – If risk K17 (remeasurement) is not a compensation event the 
     Contractor is obliged to undertake a detailed analysis of all 
     the quantities / inputs
     the quantities / inputs
   – If the Quantities that the Contractor determines are the 
     inputs into the Works Requirements are different to those 
     quantities within the Bill; what happens
            titi   ithi th Bill h t h
Works Requirements                    (6)


• In the case where a detailed BOQ is prepared by the ER
   – The quantities set down within the BOQ cannot be altered. If the 
                  q                           ,
      Contractors quantities are not the same, but are derived from his 
      commercial judgement, then the amount inserted against each 
      item must be deemed to be fully inclusive
            q      y
   – If the quantity entered does not match the contractors 
      assessment, then the rate entered will not be a “true rate”
   –   Example:          Quantity      Unit   Rate    Amount (€)
   –   Tender BOQ                79    m³
   –   Contractor take off       55    m³     €0.60   €33.00
   –   Final BOQ                 79    m³     €0.42   €33.00
Works Requirements               (7)


  – How are Change Orders valued later; Clause 10.6.1 requires 
    that a determination “shall be valued”….”using those rates”. 
  – In the example the Contractor would only be recovering
    In the example, the Contractor would only be recovering 
    €0.42 per m³ for any ordered additional works rather than 
    the true cost of €0.60 per m³ (assuming 55m³ was correct!)
  – If the Contractor determines that quantities are different at
    If the Contractor determines that quantities are different at 
    tender stage than those declared within the BOQ, should he 
    raise a tender clarification asking for the quantity to be 
    changed based upon his commercial judgement.
    changed based upon his commercial judgement
  – Is a Contractor who doesn’t declare his own assessment of 
    the quantities deemed to have accepted those transparently 
    declared within the BOQ
    d l d ithi th BOQ
Works Requirements                (8)




• Alternative position is not to prepare a detailed BOQ
   – I thi
     In this case, the tenderer provides an overall summary of the 
                   th t d           id           ll           f th
     BOQ under the headings specified prior to tender.
   – A detailed breakdown of the tender is supplied prior to 
     Contract signing
Works Requirements                   (9)




• Programme contingency
  – Clause 9 4 defines that “The Contractor has included in the initial
    Clause 9.4 defines that  The Contractor has included in the initial 
    Contract Sum and shall include in its programme a contingency for 
    delays to the date for Substantial completion of the Works caused by 
    compensation Events”
  – The programme contingency therefore includes both time and
    money
  – The Time element is defined in Schedule Part 1K prior to going to 
    tender for traditional Employer Designed Contracts (Thresholds T1 
    and T2)
  – The Contractor determines the financial provision within his tender 
    sum
  – What is this financial provision deemed to include?
Works Requirements                (10)




• Adjustments to the Contract Sum – Clause 10.6
   – Additional works shall be valued using the mechanisms
     Additional works shall be valued using the mechanisms 
     described in 10.6.1 to 4
   – Schedule part 2E does not include rates other than for those 
     prescribed
            ib d
   – Rates for Contractors site management etc. can be deemed 
     to be included within the Programme Contingency up to the 
     date for completion.
   – Rates for Contractors personnel other than those defined in 
     Part 2E, deemed to be included within the Daily Cost defined 
     Part 2E, deemed to be included within the Daily Cost defined
     within Clause 10.7
VAT Issues           (1)


• There are strict rules that govern how VAT is accounted for 
  in construction. Feedback from Revenue is:  
   – Important to note VAT is continually under review – rules and rates 
     change
   – A “Principal Contractor” is generally that entity at the top of the supply 
     chain
   – Where the Employer is a Local Authority (or any body to whom 
     Relevant Contracts Tax applies), that Employer becomes the “Principal 
                              pp ),           p y                          p
     Contractor”
   – In construction, where the VAT reverse charge rule applies (see below), 
     VAT is paid directly to Revenue by the  Principal Contractor , rather 
     VAT is paid directly to Revenue by the “Principal Contractor”, rather
     than to the construction service supplier.        
VAT Issues      (2)


• Feedback from Revenue (contd):
  – The Contract Fixed Price Lump Sum (FPLS) can vary
    depending on whether the Employer is a “Principal 
    Contractor” or not
  – Where the Employer is a “Principal Contractor” (e g Local
    Where the Employer is a  Principal Contractor (e.g. Local 
    Authority), the FPLS should normally include any 21% VAT 
    (where applicable) but not the 13.5% VAT – The Employer as 
    “Principal Contractor” pays the 13.5% VAT directly to 
    Revenue, and the 21% VAT down the line in the usual way.
VAT Issues         (3)


  – Where the Employer is not a “Principal Contractor”, the FPLS should 
    include any 21% VAT (where applicable) and the 13.5% VAT – The 
    Employer pays all VAT down the line in the usual way. An example of 
    Employer pays all VAT down the line in the usual way. An example of
    where 21% VAT would apply in construction is the supply and 
    installation of fittings that are removable (not permanent fixtures)
  – The special case of Geotechnical Investigations is considered
    The special case of Geotechnical Investigations is considered 
    essential to the construction process and thus subject to the VAT 
    Reverse Charge rule and thus paid directly by the Principal Contractor 
    to the Revenue.     Revenue decided that, in the special case of 
    to the Revenue Revenue decided that in the special case of
    Geotechnical Investigation, both the 13.5% (e.g. fieldwork) and the 
    21% (e.g. report) would both be paid directly by the Principal 
    Contractor to the Revenue. 
    C t t t th R
VAT Issues         (4)


  – Based on above, where the Employer is a “Principal Contractor” (e.g. 
    Local Authority), the FPLS for a Geotechnical Contract should not
    include any VAT
    include any VAT
  – Archaeology is not considered essential to the construction process 
    and does not fall under VAT Reverse Charge rule, so VAT is paid 
    down the line in the usual way.
    down the line in the usual way
  – Lots to consider when looking at advance Contracts i.e. Roads 
    advance Contracts for Geotechnical works and Archaeological works 
    are treated differently for VAT.
Suitability assessment questionnaires             (1)


• Large changes in this area in recent years
   – Self Certification
   – The only mechanism for meeting minimum criteria is
     The only mechanism for meeting minimum criteria is 
     essentially experience
   – Workload for tenderers reduced with self certification
   – Financial information in the current climate needs to be up 
     to date
   – Standardisation of template broadly welcomed
     Standardisation of template broadly welcomed
Suitability assessment questionnaires           (2)


• Suitability Assessment
   – Recommendation from DEHLG is that all qualified applicants 
     are invited to tender to ensure greater SME participation
     are invited to tender to ensure greater SME participation
     (Circular 10/10, Circular L3/11 on Water Conservation
     reiterates SME participation)
   – Separation of the Assessment process from the tender
     Separation of the Assessment process from the tender 
     assessment
   – Procedures required to allow this to happen (two envelope 
     system) are generally understood at this stage.
             )           ll    d        d   h
   – Omission of declarations are deemed grounds for rejection
   – Advice is that ER can clarify information rather than seek
     Advice is that ER can clarify information rather than seek 
     submission of new information originally omitted
Resident Engineering Staff                     (1)


• Employers Representative defined in Clause 4.3 of the Contract. 
  Clause 4.3.3 of the Contract gives the ER the power to delegate 
              p
  to named representatives
   – “4.3.3. The Employer’s Representative may delegate in writing to 
     named representatives any functions or powers under the 
                             y      g             pp         f
     Contract and revoke any delegation. The appointment of such a 
     representative shall not prevent the Employer’s Representative 
     from exercising directly any functions or powers. The Employer’s 
     Representative shall notify the Contractor and the Employer of any 
     delegation, and the names of representatives, and of any 
     d l     i      d h            f            i      d f
     subsequent changes, within 5 working days after the event in each 
     case.”
   – C t t
     Contractors do ask for notification of the powers delegated to the 
                  d    kf      tifi ti    f th         d l t d t th
     ER named representative
Resident Engineering Staff                      (2)




• Typically, notices sent to the ER remaining with the Consultant 
  and copied to the ER. 
  and copied to the ER
   – The ER’s representative on‐site is traditionally defined as the 
     Resident Engineer / Clerk of Works 
   – ER’s Site Representative needs to be given clear direction on their
     ER s Site Representative needs to be given clear direction on their 
     day to day functions from both a contractual and site 
     administration point of view
Resident Engineering Staff                 (3)


• What functions or powers might be delegated to the ER’s 
  on‐site representative?

   – Power to issue instructions which are directions in 
     accordance with the Contract
   – Power to sign off on the materials, labour and plant content 
     of Change Orders for record purposes only
   – Power to inspect the works under clause 8 3 and witness on
     Power to inspect the works under clause 8.3 and witness on 
     site tests
   – Power to schedule regular meetings under clause 4.15.1 and 
     to issue site meeting minutes un Clause 4.15.2
     to iss e site meeting min tes n Cla se 4 15 2
Resident Engineering Staff                (4)


• What functions or powers might be delegated to the ER’s 
  on‐site representative (contd.)?
   – Power to accept and check details of any Contractors Things 
     removed from site under Clause 4.17
   – Power to carry out checks on quality requirements under the
     Power to carry out checks on quality requirements under the 
     Works Requirements or Works Proposals
   – Power to initiate searches for defects
   – St t
     Statements of account for Interim Valuation should be 
               t f         t f I t i V l ti        h ld b
     submitted both to Tobin offices and copied to the Resident 
     Engineer
   – RE to assess % completion on all works if not a 
     remeasurement contract
Construction Issues             (1)


• Clause 4.9 Programme
  – The programme is no longer just a time based MS Project 
    Chart,  The programme shall be of a quality that will permit 
    Chart “The programme shall be of a quality that will permit
    the effective monitoring of the works”
  – Nine separate inclusions defined within Clause 4.9.1
  – It is now a significant undertaking to prepare all of this 
                     f             k                ll f h
    before the starting date
  – Progress Report requirements are defined
         g       p       q
  – Employer now has the power to withhold 15% of any 
    payment if a revised programme is not submitted within 15 
    working days. Employers are exercising this right.
    working days. Employers are exercising this right.
Construction Issues              (2)


• Time for Completion & Extension of time
   – First and second thresholds not generally being exhausted
   – Only those delay events deemed to cause a delay to
     Only those delay events deemed to cause a delay to 
     substantial completion of the works are considered against 
     the programme contingency 
   – Critical path analysis part of the consideration in determining 
            l    h    l           f h
     if change orders affect the time for completion
   – Liquidated damages are being kept low as a genuine pre‐
        q              g             g p            g       p
     tender estimate of the Financial loss.  Employers are 
     exercising LDs.
Construction Issues                   (3)


• Compensation Events
   – Timelines as specified under Clause 10.3 are not always being met
     (Contractor has no rights if the ER does not stick to the stated 
     timelines)
   – ERs have no options other than to reject submissions not made 
     strictly in accordance with timelines
   – Apparent lack of understanding at present that claims submitted as 
     “delay, disruption, loss of productivity or knock‐on effect” cannot be 
     considered by the ER (Clause 10.7.4)
   – There is no ready contractual mechanism after an ERs determination 
       h     i        d             l    h i       f          d      i i
     to refer a decision on a Compensation event to Clause 13 ‐ Dispute
   – Clause 4 – Management permits “without prejudice” discussions
   – Projects work more effectively when the lines of communication are 
                    k       ff      l h       h l      f
     held open throughout the lifespan of the project
Construction Issues                   (4)


• Disputes
  –   Formal notification requirements prescribed in Clause 13
  –   Compensation events can be referred individually or collectively
      Compensation events can be referred individually or collectively
  –   Early resolution may benefit both parties
  –   Concern on availability of Conciliators on short notice if project is 
      moving on quickly
           i        i kl
Delay & Compensation events                           (1)


• Good housekeeping essential
   – Incoming correspondence register should record all salient data
Delay & Compensation events                             (2)


• Register
   – Automatically calculates relevant dates of responses / notifications
Delay & Compensation events                         (3)


• Register of changes to the Contract Sum
   – Revised Contract Sum and any disputed amounts clearly understood
Valuation of Omissions                (Employer Claims)


• Mechanism for the Employer to adjust the Contract Sum
   – Change Order required to omit part of the works
   – In an inflationary market Contractors will put in place
     In an inflationary market, Contractors will put in place 
     purchase agreements with suppliers at the outset of the 
     Contract to manage PVC risks
   – Employer may have to take possession of such materials if 
          l          h        k               f    h           l f
     they form part of the works being omitted
   – Clause 10.9 defines the protocol to be followed by the ER
                             p                          y
Valuation of Omissions                (Employer Claims)


• Mechanism for the Employer to adjust the Contract Sum
  (contd.)
   – The calculation of the proposed adjustment to the Contract
     The calculation of the proposed adjustment to the Contract 
     Sum must be transparent and the Contractor is given an 
     opportunity to respond to the proposal
   – Cl
     Clause 10.6 in reverse: are Bill rates appropriate for valuing 
             10 6 i              Bill t             i t f       l i
     the works omitted. It’s a fair starting point but likely to be 
     challenged in the Contractor’s response
   – Employer claims can be raised as a dispute under Clause 13 
     also
   – Changes of this nature during construction stage will 
          g                        g                  g
     typically represent poor value for money
Client Communications – ER’s determinations
• Requirement specified in Clause 4.8.3 to notify the 
  Employer of a Value engineering proposal submitted by the 
  Contractor

       “(2) notify the Contractor and the Employer that the 
  Contractor’s proposals are agreed and make any resulting 
              ’          l          d d      k          l
  adjustments to the Contract Sum, use of the programme 
  contingency referred to in sub‐clause 9.4 or extension to the 
  Date for Substantial Completion of the Works and any affected 
        f      b       l     l       f h      k    d       ff    d
  Section”
Client Communications – ER’s determinations

 – This assumes that the value of the determination is less than the 
                       p                                   g       g
   limits allowed as specified in Schedule Part 1 for a single Change 
   Order or for the aggregated value over a 3 month period.
 – If the value of the determination required is greater than the limits 
   specified, the Employer must be consulted in making the 
   determination.
 – The contractor will not have any visibility of communications 
   between the ER and the Employer in this respect and the timelines 
   within which responses must be made still hold valid
 – Client needs to have an internal point of contact available to 
   discuss such issues, who is empowered to liaise with the ER within 
   the timelines specified.
Client Communications – Value Engineering
• Requirement specified in Clause 4.8.3 to notify the 
  Employer of a Value engineering proposal submitted by the 
  Contractor

  “4.8.3. The Employer’s Representative shall, as soon as practicable, notify the
   4.8.3. The Employer s Representative shall, as soon as practicable, notify the 
  Contractor whether the Employer agrees to or rejects the proposal. If the 
  Employer agrees to the proposal, the Employer’s Representative shall, if 
  agreed, determine a reduction to the Contract Sum and an adjustment to the 
  agreed, determine a reduction to the Contract Sum and an adjustment to the
  Date for Substantial Completion of the Works and any affected Section in 
  accordance with the agreed proposal and the Contractor shall implement the 
  agreed proposal. If the proposal is rejected, this shall be conclusive.”
   g      p p       f     p p           j     ,
Client Communications – Value Engineering
– It is the Employer’s sole responsibility to accept or reject a 
  Value Engineering proposal.
   – Typically the format of such arrangements are:
     Typically the format of such arrangements are:
      – To notify the Employer initially that a Value Engineering 
        proposal has been submitted
      – To carry out an assessment of the merits of the proposal
      – To recommend acceptance or rejection of the proposal
      – To notify the Contractor of the Employer’s decision
        To notify the Contractor of the Employer s decision
Presentation to Engineers Ireland (Thomond / West Region)
                     8th March 2011
                         March, 2011 



               End of Presentation

                          mcgovern@tobin.ie

                           @cmcgovernceng
               http://www.linkedin.com/in/cmcgoverntobin 

More Related Content

What's hot

Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposalSadegh Yazdani
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5VancityInstitute
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Commercial Management Scenarios
Commercial Management ScenariosCommercial Management Scenarios
Commercial Management ScenariosCKMCforstudents
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9Moustafa Ismail Abu Dief
 
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4Moustafa Ismail Abu Dief
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUGL Engineering
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...Moustafa Ismail Abu Dief
 
EPC_Business_model
EPC_Business_modelEPC_Business_model
EPC_Business_modelavnish
 
03 e measurement book-ver-1.0
03 e measurement book-ver-1.003 e measurement book-ver-1.0
03 e measurement book-ver-1.0Amulie Jarjusey
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeepSandeep Yadav
 

What's hot (19)

Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposal
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Commercial Management Scenarios
Commercial Management ScenariosCommercial Management Scenarios
Commercial Management Scenarios
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM Contracts
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
 
EPC_Business_model
EPC_Business_modelEPC_Business_model
EPC_Business_model
 
03 e measurement book-ver-1.0
03 e measurement book-ver-1.003 e measurement book-ver-1.0
03 e measurement book-ver-1.0
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 

Viewers also liked

Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...HIMADRI BANERJI
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentationnipuna_bopage
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Tender ecr (revised)
Tender ecr (revised)Tender ecr (revised)
Tender ecr (revised)sunilcel
 
Tender Document for Solar Power Plant in Gujarat Part 2
Tender Document for Solar Power Plant in Gujarat Part 2Tender Document for Solar Power Plant in Gujarat Part 2
Tender Document for Solar Power Plant in Gujarat Part 2Headway Solar
 

Viewers also liked (7)

Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Tender ecr (revised)
Tender ecr (revised)Tender ecr (revised)
Tender ecr (revised)
 
Tender Document for Solar Power Plant in Gujarat Part 2
Tender Document for Solar Power Plant in Gujarat Part 2Tender Document for Solar Power Plant in Gujarat Part 2
Tender Document for Solar Power Plant in Gujarat Part 2
 

Similar to GCCC contracts experience to date 08'03'11

IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case StudyIRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case StudyIRJET Journal
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...César del Riego y Fuentes
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...Moustafa Ismail Abu Dief
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
INFRA CIVIL EPC Presentation -NAIR 22.12.2015.ppt
INFRA CIVIL EPC Presentation -NAIR  22.12.2015.pptINFRA CIVIL EPC Presentation -NAIR  22.12.2015.ppt
INFRA CIVIL EPC Presentation -NAIR 22.12.2015.pptGogreenFields
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02Bodenbr
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02Bodenbr
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptxssuser4ae21a
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017Browne Jacobson LLP
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Risk Management Plan Version 6 062811 Page 1 of 6 .docx
Risk Management Plan Version 6 062811 Page 1 of 6 .docxRisk Management Plan Version 6 062811 Page 1 of 6 .docx
Risk Management Plan Version 6 062811 Page 1 of 6 .docxjoellemurphey
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 

Similar to GCCC contracts experience to date 08'03'11 (20)

IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case StudyIRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
INFRA CIVIL EPC Presentation -NAIR 22.12.2015.ppt
INFRA CIVIL EPC Presentation -NAIR  22.12.2015.pptINFRA CIVIL EPC Presentation -NAIR  22.12.2015.ppt
INFRA CIVIL EPC Presentation -NAIR 22.12.2015.ppt
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Public-private-partnerships in Italy – Federico Antellini Russo – June 2014 m...
Public-private-partnerships in Italy – Federico Antellini Russo – June 2014 m...Public-private-partnerships in Italy – Federico Antellini Russo – June 2014 m...
Public-private-partnerships in Italy – Federico Antellini Russo – June 2014 m...
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Risk Management Plan Version 6 062811 Page 1 of 6 .docx
Risk Management Plan Version 6 062811 Page 1 of 6 .docxRisk Management Plan Version 6 062811 Page 1 of 6 .docx
Risk Management Plan Version 6 062811 Page 1 of 6 .docx
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 

Recently uploaded

Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 

Recently uploaded (20)

Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 

GCCC contracts experience to date 08'03'11

  • 1. Presentation to Engineers Ireland (Thomond / West Region) 8th March, 2011 March, 0 GCCC Contracts – Experience to date: A review of the operation of the GCCC Contracts on Civil Engineering projects Ciaran McGovern TOBIN Consulting Engineers
  • 2. Topics • Background  • Risk Management • Works Requirements W k R i • VAT Issues • Suitability Assessment Questionnaires Suitability Assessment Questionnaires • Delegation of duties to ER’s Site Representative • Construction Issues • Delay & Compensation Events • Employer Claims • Client Communications
  • 3. Background (1) • Personal greatest exposure to date primarily with  Conditions of Contract for Civil Engineering Works designed  by the Employer (Aug 2007) by the Employer (Aug 2007) • Documents downloaded from  http://www.constructionprocurement.gov.ie/  • No change log for updates • Difficult to keep current when documents are constantly  changing • Suggest an RSS feed is prepared for the site which would  alert of changes?
  • 4. Background (2) • Guiding Principles: (DEHLG training material) – “To ensure as far as practicable that the accepted tender  prices and the final outturn costs are the same prices and the final outturn costs are the same” – “To allocate risk so there is optimal transfer to the  Contractor” • Launch date was February 2007, we are now four years in!
  • 5. Risk Management (1) • Fundamental concept is that risk can be managed,  minimised shared or accepted. It cannot be ignored. • Structured approach / early engagement yields dividends Structured approach / early engagement yields dividends – Focuses the Consultant / LA to look at the difficult decisions up front e.g.  “do we divert the ESB cables or dig around them?” – Think about the issues likely to threaten the success of the project and Think about the issues likely to threaten the success of the project and  address them. Engagement with third parties, decide what is needed  and provide for them in the Contract in a clear way e.g. accommodation  works, traffic requirements, what are the particular constraints being  placed on the Contractor. – Can the risks be eliminated entirely – worth considering advance works  contracts. Does the programme support this? – Heretofore, risks managed in part through the use of Provisional / PC  f k d h h h f l/ Sums / Dayworks. No longer an option in New Works Contracts
  • 6. Risk Management (2) • Risk Treatment Options in a workshop environment – Should the risks be accepted by the Employer or transferred to  the Contractor the Contractor – The need to have comprehensive information e.g. type of Site  Investigation works, uncovering works in buildings, Ground  Penetrating Radar, Utilities mapping Penetrating Radar Utilities mapping
  • 7. Risk Management (3) • Risk allocated to whichever party is best placed to manage  them. – Optimal risk transfer is not the same as maximum risk transfer risk transfer is not the same as maximum risk transfer – Circulars from DEHLG / NRA on what default position is for standard  Contract types – schedule Part 1K default positions for Delay &  compensation events compensation events – The temptation may be to transfer all risk, but this needs to  supported by analysis of the optimal position. – Risk transfer consideration may influence Contract type selection Risk transfer consideration may influence Contract type selection
  • 8. Risk Management (4) • Contract Selection – – Guidance note 1.4 ‐ Capital Works Management Framework Guidance  Note: Procurement and Contract Strategy for Public Works Contracts”.  gy f – Section 2 of that document states: “On projects valued below €5 million,  it is more usual to use the Minor Works Contract (PW‐CF5). However, in  certain exceptional circumstances the Employer may deem the project  sufficiently complex to warrant the use of one of the major works  ffi i tl l t t th f f th j k contracts (PW‐CF1 or PW‐CF3)”.  – Is the use of a monetary threshold the most important arbiter in  determining the default position for use of Minor / Major forms of  determining the default position for use of Minor / Major forms of Contract  – What are the exceptional circumstances, what makes the project  sufficiently complex? – Risk transfer considerations lead into this selection process
  • 9. Risk Management (5) • Consideration of particular types of Complex Projects. – Construction of Engineered Landfill Cells – Major Civil Engineering Works but typically rolled out in works Major Civil Engineering Works, but typically rolled out in works  packages less than €5M – Civil Engineering Works designed by the Employer, but placing  particular design related to Bentonite Enhanced soils with the  particular design related to Bentonite Enhanced soils with the Contractor – Contractor has to source all materials and retain Specialist to  batch / mix batch / mix – Risk on remeasurement considered to be optimal if passed to the  Contractor – First review suggests Minor Works Form but optimal risk transfer First review suggests Minor Works Form, but optimal risk transfer  suggests Major Forms
  • 10. Risk Management (6) • Watermains / Trenchless Technology – Water Services – Very often tendered as open cut trench using Minor Works Form  of Contract of Contract – Contractor wishes to propose trenchless technology – No Value Engineering Clause in Minor Works Forms (clause 4.8) – G Ground risk optimally managed by contractor if proposal accepted d i k ti ll db t t if l t d – Minor works Forms pre‐selects allocation of Ground Risk as being  an Employer retained  – Optimal risk transfer suggests Ground Risk should be retained by  f the Contractor for such technologies as he is best placed to  manage it.
  • 11. Works Requirements (1) • Should they include…. – Digital design models in 3D – If risk K17 (remeasurement) is not a Compensation event is the If risk K17 (remeasurement) is not a Compensation event, is the  contractor then obliged to undertake a detailed analysis of the quantum. – Does a 3D model assist with such an exercise. – Would such a proposal be of equal benefit to both small and large  p p q g Contractors – If such information was provided, should it be included within the  “Relevant Background Information” or part of the Works Requirements – If it is part of the Works Requirements, can the contractor then rely  upon it  – Would this undermine the original intent of transferring the risk related  to remeasurement i.e. Risk K5 – F t l E t t i Ri k K5 Factual Error about the site  b t th it
  • 12. Works Requirements (2) • Is a Bill of Quantities needed?  – In Water Service Projects, the default position is that a detailed  Bill of Quantities using CESMM should be prepared Bill of Quantities using CESMM should be prepared – Similarly Roads projects use MMRB – In the absence of guidance from Specific Government Sections,  what do the Department of Finance Guidance Notes say what do the Department of Finance Guidance Notes say
  • 13. Works Requirements (3) • Guidance Note 1.5 as available from the Government  Construction Procurement website  http://www.constructionprocurement.gov.ie/,  prescribes  http://www constructionprocurement gov ie/ prescribes details of the format of the BOQ
  • 14. Works Requirements (4) • Referring specifically to “Section 2.6.3 ‐ Prescribing the Content of the Pricing Document” and specifically to the guidance on “Compiling the Pricing Document”, it states: p g g , “The primary pricing document may be one of the following: – A comprehensive and fully measured list of quantities and specifications drawn up in a formal Bill of Quantities; tenderers can then insert their rates against the categories specified by the Employer (this is appropriate for Employer‐designed contracts only); or. – A multiple‐page tender cost analysis detailing how the tender price is to be broken down – the Employer should follow best practice in specifying the headings under which price details are to be presented.”
  • 15. Works Requirements (5) • Factors influencing the decision to prepare a detailed BOQ  or to specify the headings under which the Contractor  prepares his tender prepares his tender – If risk K17 (remeasurement) is not a compensation event the  Contractor is obliged to undertake a detailed analysis of all  the quantities / inputs the quantities / inputs – If the Quantities that the Contractor determines are the  inputs into the Works Requirements are different to those  quantities within the Bill; what happens titi ithi th Bill h t h
  • 16. Works Requirements (6) • In the case where a detailed BOQ is prepared by the ER – The quantities set down within the BOQ cannot be altered. If the  q , Contractors quantities are not the same, but are derived from his  commercial judgement, then the amount inserted against each  item must be deemed to be fully inclusive q y – If the quantity entered does not match the contractors  assessment, then the rate entered will not be a “true rate” – Example: Quantity Unit Rate Amount (€) – Tender BOQ 79 m³ – Contractor take off 55 m³ €0.60 €33.00 – Final BOQ 79 m³ €0.42 €33.00
  • 17. Works Requirements (7) – How are Change Orders valued later; Clause 10.6.1 requires  that a determination “shall be valued”….”using those rates”.  – In the example the Contractor would only be recovering In the example, the Contractor would only be recovering  €0.42 per m³ for any ordered additional works rather than  the true cost of €0.60 per m³ (assuming 55m³ was correct!) – If the Contractor determines that quantities are different at If the Contractor determines that quantities are different at  tender stage than those declared within the BOQ, should he  raise a tender clarification asking for the quantity to be  changed based upon his commercial judgement. changed based upon his commercial judgement – Is a Contractor who doesn’t declare his own assessment of  the quantities deemed to have accepted those transparently  declared within the BOQ d l d ithi th BOQ
  • 18. Works Requirements (8) • Alternative position is not to prepare a detailed BOQ – I thi In this case, the tenderer provides an overall summary of the  th t d id ll f th BOQ under the headings specified prior to tender. – A detailed breakdown of the tender is supplied prior to  Contract signing
  • 19. Works Requirements (9) • Programme contingency – Clause 9 4 defines that “The Contractor has included in the initial Clause 9.4 defines that  The Contractor has included in the initial  Contract Sum and shall include in its programme a contingency for  delays to the date for Substantial completion of the Works caused by  compensation Events” – The programme contingency therefore includes both time and money – The Time element is defined in Schedule Part 1K prior to going to  tender for traditional Employer Designed Contracts (Thresholds T1  and T2) – The Contractor determines the financial provision within his tender  sum – What is this financial provision deemed to include?
  • 20. Works Requirements (10) • Adjustments to the Contract Sum – Clause 10.6 – Additional works shall be valued using the mechanisms Additional works shall be valued using the mechanisms  described in 10.6.1 to 4 – Schedule part 2E does not include rates other than for those  prescribed ib d – Rates for Contractors site management etc. can be deemed  to be included within the Programme Contingency up to the  date for completion. – Rates for Contractors personnel other than those defined in  Part 2E, deemed to be included within the Daily Cost defined  Part 2E, deemed to be included within the Daily Cost defined within Clause 10.7
  • 21. VAT Issues (1) • There are strict rules that govern how VAT is accounted for  in construction. Feedback from Revenue is:   – Important to note VAT is continually under review – rules and rates  change – A “Principal Contractor” is generally that entity at the top of the supply  chain – Where the Employer is a Local Authority (or any body to whom  Relevant Contracts Tax applies), that Employer becomes the “Principal  pp ), p y p Contractor” – In construction, where the VAT reverse charge rule applies (see below),  VAT is paid directly to Revenue by the  Principal Contractor , rather  VAT is paid directly to Revenue by the “Principal Contractor”, rather than to the construction service supplier.        
  • 22. VAT Issues (2) • Feedback from Revenue (contd): – The Contract Fixed Price Lump Sum (FPLS) can vary depending on whether the Employer is a “Principal  Contractor” or not – Where the Employer is a “Principal Contractor” (e g Local Where the Employer is a  Principal Contractor (e.g. Local  Authority), the FPLS should normally include any 21% VAT  (where applicable) but not the 13.5% VAT – The Employer as  “Principal Contractor” pays the 13.5% VAT directly to  Revenue, and the 21% VAT down the line in the usual way.
  • 23. VAT Issues (3) – Where the Employer is not a “Principal Contractor”, the FPLS should  include any 21% VAT (where applicable) and the 13.5% VAT – The  Employer pays all VAT down the line in the usual way. An example of  Employer pays all VAT down the line in the usual way. An example of where 21% VAT would apply in construction is the supply and  installation of fittings that are removable (not permanent fixtures) – The special case of Geotechnical Investigations is considered The special case of Geotechnical Investigations is considered  essential to the construction process and thus subject to the VAT  Reverse Charge rule and thus paid directly by the Principal Contractor  to the Revenue.     Revenue decided that, in the special case of  to the Revenue Revenue decided that in the special case of Geotechnical Investigation, both the 13.5% (e.g. fieldwork) and the  21% (e.g. report) would both be paid directly by the Principal  Contractor to the Revenue.  C t t t th R
  • 24. VAT Issues (4) – Based on above, where the Employer is a “Principal Contractor” (e.g.  Local Authority), the FPLS for a Geotechnical Contract should not include any VAT include any VAT – Archaeology is not considered essential to the construction process  and does not fall under VAT Reverse Charge rule, so VAT is paid  down the line in the usual way. down the line in the usual way – Lots to consider when looking at advance Contracts i.e. Roads  advance Contracts for Geotechnical works and Archaeological works  are treated differently for VAT.
  • 25. Suitability assessment questionnaires (1) • Large changes in this area in recent years – Self Certification – The only mechanism for meeting minimum criteria is The only mechanism for meeting minimum criteria is  essentially experience – Workload for tenderers reduced with self certification – Financial information in the current climate needs to be up  to date – Standardisation of template broadly welcomed Standardisation of template broadly welcomed
  • 26. Suitability assessment questionnaires (2) • Suitability Assessment – Recommendation from DEHLG is that all qualified applicants  are invited to tender to ensure greater SME participation are invited to tender to ensure greater SME participation (Circular 10/10, Circular L3/11 on Water Conservation reiterates SME participation) – Separation of the Assessment process from the tender Separation of the Assessment process from the tender  assessment – Procedures required to allow this to happen (two envelope  system) are generally understood at this stage. ) ll d d h – Omission of declarations are deemed grounds for rejection – Advice is that ER can clarify information rather than seek Advice is that ER can clarify information rather than seek  submission of new information originally omitted
  • 27. Resident Engineering Staff (1) • Employers Representative defined in Clause 4.3 of the Contract.  Clause 4.3.3 of the Contract gives the ER the power to delegate  p to named representatives – “4.3.3. The Employer’s Representative may delegate in writing to  named representatives any functions or powers under the  y g pp f Contract and revoke any delegation. The appointment of such a  representative shall not prevent the Employer’s Representative  from exercising directly any functions or powers. The Employer’s  Representative shall notify the Contractor and the Employer of any  delegation, and the names of representatives, and of any  d l i d h f i d f subsequent changes, within 5 working days after the event in each  case.” – C t t Contractors do ask for notification of the powers delegated to the  d kf tifi ti f th d l t d t th ER named representative
  • 28. Resident Engineering Staff (2) • Typically, notices sent to the ER remaining with the Consultant  and copied to the ER.  and copied to the ER – The ER’s representative on‐site is traditionally defined as the  Resident Engineer / Clerk of Works  – ER’s Site Representative needs to be given clear direction on their ER s Site Representative needs to be given clear direction on their  day to day functions from both a contractual and site  administration point of view
  • 29. Resident Engineering Staff (3) • What functions or powers might be delegated to the ER’s  on‐site representative? – Power to issue instructions which are directions in  accordance with the Contract – Power to sign off on the materials, labour and plant content  of Change Orders for record purposes only – Power to inspect the works under clause 8 3 and witness on Power to inspect the works under clause 8.3 and witness on  site tests – Power to schedule regular meetings under clause 4.15.1 and  to issue site meeting minutes un Clause 4.15.2 to iss e site meeting min tes n Cla se 4 15 2
  • 30. Resident Engineering Staff (4) • What functions or powers might be delegated to the ER’s  on‐site representative (contd.)? – Power to accept and check details of any Contractors Things  removed from site under Clause 4.17 – Power to carry out checks on quality requirements under the Power to carry out checks on quality requirements under the  Works Requirements or Works Proposals – Power to initiate searches for defects – St t Statements of account for Interim Valuation should be  t f t f I t i V l ti h ld b submitted both to Tobin offices and copied to the Resident  Engineer – RE to assess % completion on all works if not a  remeasurement contract
  • 31. Construction Issues (1) • Clause 4.9 Programme – The programme is no longer just a time based MS Project  Chart,  The programme shall be of a quality that will permit  Chart “The programme shall be of a quality that will permit the effective monitoring of the works” – Nine separate inclusions defined within Clause 4.9.1 – It is now a significant undertaking to prepare all of this  f k ll f h before the starting date – Progress Report requirements are defined g p q – Employer now has the power to withhold 15% of any  payment if a revised programme is not submitted within 15  working days. Employers are exercising this right. working days. Employers are exercising this right.
  • 32. Construction Issues (2) • Time for Completion & Extension of time – First and second thresholds not generally being exhausted – Only those delay events deemed to cause a delay to Only those delay events deemed to cause a delay to  substantial completion of the works are considered against  the programme contingency  – Critical path analysis part of the consideration in determining  l h l f h if change orders affect the time for completion – Liquidated damages are being kept low as a genuine pre‐ q g g p g p tender estimate of the Financial loss.  Employers are  exercising LDs.
  • 33. Construction Issues (3) • Compensation Events – Timelines as specified under Clause 10.3 are not always being met (Contractor has no rights if the ER does not stick to the stated  timelines) – ERs have no options other than to reject submissions not made  strictly in accordance with timelines – Apparent lack of understanding at present that claims submitted as  “delay, disruption, loss of productivity or knock‐on effect” cannot be  considered by the ER (Clause 10.7.4) – There is no ready contractual mechanism after an ERs determination  h i d l h i f d i i to refer a decision on a Compensation event to Clause 13 ‐ Dispute – Clause 4 – Management permits “without prejudice” discussions – Projects work more effectively when the lines of communication are  k ff l h h l f held open throughout the lifespan of the project
  • 34. Construction Issues (4) • Disputes – Formal notification requirements prescribed in Clause 13 – Compensation events can be referred individually or collectively Compensation events can be referred individually or collectively – Early resolution may benefit both parties – Concern on availability of Conciliators on short notice if project is  moving on quickly i i kl
  • 35. Delay & Compensation events (1) • Good housekeeping essential – Incoming correspondence register should record all salient data
  • 36. Delay & Compensation events (2) • Register – Automatically calculates relevant dates of responses / notifications
  • 37. Delay & Compensation events (3) • Register of changes to the Contract Sum – Revised Contract Sum and any disputed amounts clearly understood
  • 38. Valuation of Omissions (Employer Claims) • Mechanism for the Employer to adjust the Contract Sum – Change Order required to omit part of the works – In an inflationary market Contractors will put in place In an inflationary market, Contractors will put in place  purchase agreements with suppliers at the outset of the  Contract to manage PVC risks – Employer may have to take possession of such materials if  l h k f h l f they form part of the works being omitted – Clause 10.9 defines the protocol to be followed by the ER p y
  • 39. Valuation of Omissions (Employer Claims) • Mechanism for the Employer to adjust the Contract Sum (contd.) – The calculation of the proposed adjustment to the Contract The calculation of the proposed adjustment to the Contract  Sum must be transparent and the Contractor is given an  opportunity to respond to the proposal – Cl Clause 10.6 in reverse: are Bill rates appropriate for valuing  10 6 i Bill t i t f l i the works omitted. It’s a fair starting point but likely to be  challenged in the Contractor’s response – Employer claims can be raised as a dispute under Clause 13  also – Changes of this nature during construction stage will  g g g typically represent poor value for money
  • 40. Client Communications – ER’s determinations • Requirement specified in Clause 4.8.3 to notify the  Employer of a Value engineering proposal submitted by the  Contractor “(2) notify the Contractor and the Employer that the  Contractor’s proposals are agreed and make any resulting  ’ l d d k l adjustments to the Contract Sum, use of the programme  contingency referred to in sub‐clause 9.4 or extension to the  Date for Substantial Completion of the Works and any affected  f b l l f h k d ff d Section”
  • 41. Client Communications – ER’s determinations – This assumes that the value of the determination is less than the  p g g limits allowed as specified in Schedule Part 1 for a single Change  Order or for the aggregated value over a 3 month period. – If the value of the determination required is greater than the limits  specified, the Employer must be consulted in making the  determination. – The contractor will not have any visibility of communications  between the ER and the Employer in this respect and the timelines  within which responses must be made still hold valid – Client needs to have an internal point of contact available to  discuss such issues, who is empowered to liaise with the ER within  the timelines specified.
  • 42. Client Communications – Value Engineering • Requirement specified in Clause 4.8.3 to notify the  Employer of a Value engineering proposal submitted by the  Contractor “4.8.3. The Employer’s Representative shall, as soon as practicable, notify the 4.8.3. The Employer s Representative shall, as soon as practicable, notify the  Contractor whether the Employer agrees to or rejects the proposal. If the  Employer agrees to the proposal, the Employer’s Representative shall, if  agreed, determine a reduction to the Contract Sum and an adjustment to the  agreed, determine a reduction to the Contract Sum and an adjustment to the Date for Substantial Completion of the Works and any affected Section in  accordance with the agreed proposal and the Contractor shall implement the  agreed proposal. If the proposal is rejected, this shall be conclusive.” g p p f p p j ,
  • 43. Client Communications – Value Engineering – It is the Employer’s sole responsibility to accept or reject a  Value Engineering proposal. – Typically the format of such arrangements are: Typically the format of such arrangements are: – To notify the Employer initially that a Value Engineering  proposal has been submitted – To carry out an assessment of the merits of the proposal – To recommend acceptance or rejection of the proposal – To notify the Contractor of the Employer’s decision To notify the Contractor of the Employer s decision
  • 44. Presentation to Engineers Ireland (Thomond / West Region) 8th March 2011 March, 2011  End of Presentation mcgovern@tobin.ie @cmcgovernceng http://www.linkedin.com/in/cmcgoverntobin