CPS Ludgate Hill HQ
Closedown Project and Move out Schedule

FMBC HQ Operations Team

January 2010


                                          1
Ludgate Hill HQ.
Stores & Office Areas – Decanting Program 2009-10.




                                                     2
Main Move Schedule
Directorate /       Location             Location (to)      Date                 Status
Division            (from)
Casework Division   Rose Court (3rd)     Rose Court (6th)   10th & 11th April
– Fraud
LOC – CPS           Ludgate Hill (7th)   New Kings Beam     17th & 18th April
London                                   House
LCJP & Met          Ludgate Hill (3rd)   New Kings Beam     17th & 18th April
Police                                   House              (Met Police – 21st
                                                            June)
CPS London –        Rose Court           Ludgate Hill       17th & 18th April
Learning &
Leadership
BIS                 Ludgate Hill (2nd)   Rose Court         1st & 2nd May


HR, EDU &           Ludgate Hill (1st,   Rose Court         8th & 9th May
Finance             7th & 3rd)
Policy & BDD        Ludgate Hill (6th)   Rose Court         15th &16th May



                                                                                          3
Main Move Schedule
 Directorate /      Location             Location (to)   Date               Status
 Division           (from)
 Casework (CTD,     Ludgate Hill (5th)   Rose Court      22nd & 23rd May
 SCD, OCD)

 Private Office /   Ludgate Hill (7th)   Rose Court      22nd & 23rd May
 Corp Comms

 Casework (CTD,     Ludgate Hill (5th)   Rose Court      29th & 30th May
 SCD, OCD)

 Restaurant (ISS    Ludgate Hill (3rd)                   31st May
 Eatons)                                                 (Shutdown)

 Recreation Room    Ludgate Hill (3rd)                   31st May
                                                         (Shutdown)

 Casework (CTD,     Ludgate Hill (5th)   Rose Court      5th & 6th June
 SCD, OCD)

 CPS London         Ludgate Hill (4th)   The Cooperage   12th & 13th June
 Direct & Complex                                                                    4
 Casework Centre
Main Move Schedule
Directorate /      Location (from)   Location (to)    Date               Status
Division

CPS London –       Ludgate Hill      New Kings Beam   12th & 13th June
Learning &                           House
Leadership
Ludgate Hill       Ludgate Hill                       12th & 13th June
Corporate                                             (Shutdown)
Meeting Rooms
Xerox & MFDs       Ludgate Hill      Rose Court       15th June


Casework (UKBA     New Kings Beam    Rose Court       26th & 27th June
& POCU) and        House
Revenue &
Customs Division
Casework (UKBA     New Kings Beam    Rose Court       3rd & 4th July
& POCU) and        House
Revenue &
Customs Division
Casework (UKBA     New Kings Beam    Rose Court       10th & 11th July
& POCU) and        House
Revenue &
Customs Division                                                                  5
Ludgate HQ Moves Schedule

       March                    April                     May                      June

Records / archives   Moves:                        Moves:                   Moves:
Contract removals    Casework Division -           BIS – LH to RC - 1st &   Casework – LH to RC -
                     Fraud                         2nd May                  5th & 6th June
Progress Reporting                                                          CPS Direct &
                     17th & 18th April – RC 3rd    HR, EDU & Finance
Check Priorities     floor to LH 3rd floor.        – LH to RC - 8th & 9th   Complex Casework
                                                   May                      centre – LH to CO -
Manage costs         LOC Team (CPS London)                                  12th & 13th June
                                                   Policy & BDD – LH to
                     – LH 7th to NKBH -            RC - 15th & 16th May.    Casework Division
Key:                 17th April                                             (UKBA and POCU)
                                                   Casework – LH to RC      and Revenue and
LH = Ludgate Hill    LCJB – LH 3rd to NKBH         - 22nd & 23rd / 29th &
                     -   17th   &   18th   April                            Customs Division –
NKBH = New Kings                                   30th May
                                                                            NKBH to RC - 26th & 27th
Beam House           L&L CPS London –                                       June. 3 & 4 July. 10 & 11
                                                                            July
RC = Rose Court      18th April – RC to LH 3rd
                     floor. Note: 1 Meeting
                                                                            Private Office – LH
CO = Cooperage                                                              to RC - 5th & 6th June
                     room plus 7 desks
                                                                            Corp Comms – LH to
                                                                            RC - 5th & 6th June
                                                                                                     6
Operational Move issues

• Redundant files disposed.            • Crates to be labelled to identify
  Basement Stores, Storage Units         owner / Directorate.
  and Office Areas.                    • If new desk or location is known
• Files required to be kept by law       crates should be labelled with
  should be archived.                    this information.
• Files necessary for work to be       • Before removal, all cupboards,
  prepared for relocation to Rose        safes and storage furniture must
  Court.                                 be checked by Business
• Clear desk policies should be          Manager, Move Champion and
  followed.                              member of the DSO team to
• Pack and store all files and items     ensure it is safe for removal.
  ready for the move. (Crates to be    • FM Teams: Audit checks of all
  supplied).                             working areas. To ensure no
                                         information is left behind.


                                                                             7
Ludgate Closedown Tasks (1)
Task                                  Action                               Team             Target      Completion
                                                                           Responsible      Date        Date
Provide a statutory compliance                                                              04 June
valid certification in its original
form.


LG examinations of all the lifts      Mark McCulloch to set up a           Cofatec /        04 June
must be valid and up-to-date at the   schedule of all ongoing              Mark
end of the lease.                     examinations                         McCulloch


CPS must strip out and remove the     HQ Operations and ISS to arrange     HQ Ops / ISS /   w/c 14
kitchen on third floor                stripping out and removal of         Brian Ford /     June
                                      kitchen. Two fridges are to be       Peter Rouse
                                      retained. From 7th June TPS to
                                      remove crockery, plates and trays.
CPS must strip out and remove the     HQ Operations to arrange to have     HQ Ops /         21 - 25
reception desk                        reception desk taken out and the     Brian Ford       June
                                      stripping out of area. HQ Ops to
                                      arrange temporary desk.

Remove / disarm any electronic        Roy Ellard to provide a programme    SSG / Roy        Wknd 26
security systems to internal doors    for the closedown of all Security    Ellard / Chris   - 27 June
                                      items and HQ Ops and Security        Duggan
                                      team to review. SSG to
                                      remove/disarm security systems on
                                      pre-arranged date.                                                             8
Ludgate Closedown Tasks (2)
Task                                   Action                                       Team                 Target    Completion
                                                                                    Responsible          Date      Date
Ensure all the internal locks are in   Roy Ellard to provide a programme for the    SSG / Roy Ellard /   Wknd
the unlocked position                  closedown of all Security items and HQ       Chris Duggan         26 - 27
                                       Ops and Security team to review. SSG to                           June
                                       leave internal locks unlocked on pre-
                                       arranged date.
All perimeter doors are to be          Roy Ellard to provide a programme for the    SSG / Roy Ellard /   Wknd
securable                              closedown of all Security items and HQ       Chris Duggan         26 - 27
                                       Ops and Security team to review. SSG to                           June
                                       ensure perimeter doors are securable.

Keys are to be provided to Land        Security team need to collate a schedule     SSG / Roy Ellard /   w/c 14
Securities on the end day of the       detailing all the keys that will be handed   Chris Duggan         June
lease with each key clearly            over.
identified

The CCTV cameras that monitor          SSG to note that CCTV cameras will be left   SSG / Roy Ellard /   30 June
the perimeter of the building          behind.                                      Chris Duggan
may be left in situ


Monitor courtyard movements            Go Green and TPS to provide a                Go Green / TPS       Ongoing
and moves in general                   programme each on their respective
                                       moves and the quantity of removal
                                       vehicles expected on each removal day.
                                       Give Hillgate House Security weekly                                                 9
                                       updates on moves.
Ludgate Closedown Tasks (3)

Task                            Action                                     Team Responsible        Target    Completion
                                                                                                   Date      Date
Provide the most up-to-date     Sue Twist of ISS to provide an up-to-      ISS / Sue Twist /       04-June
asbestos survey and register,   date asbestos survey via Peter Rouse       Peter Rouse
electronically, if possible.


To suggest a date and time      HQ Operations have suggested the 4th       DTZ / Richard Young /   04-June
for a plant room walk-round     June for the walk-round. Invitees          Andy Walker
near the time of the lease      include Andy Morgan from AECOM,
end.                            Gareth Brown from DTZ and HQ
                                Operations representative.
The end date of the lease is    To Review after the 4th June               Mark McCulloch          04-June
30th June 2010. The CPS is to
decide whether they wish to
extend the lease by a month
and to inform Paul Hunt of
decision.
Land Securities may not         HQ Operations to gain clarification        Zoe Varian              04-June
want the plant systems to be    from Zoe Varian as to whether the
isolated and drained down –     plant systems need to be isolated or
this needs to be clarified.     drained down. If they do, this will have
                                to be arranged.


                                                                                                                     10
Ludgate Closedown Tasks (3)

Task                             Action                                    Team Responsible      Target    Completion
                                                                                                 Date      Date
To ensure that all assets are    Go Green to provide a revised Master      Natalie Lewis / Go    30 June
accounted for during the         Programme of planned moves. Go            Green
move ready for                   Green to provide weekly updates on
Parliamentary Questions          progress of removals from site in line
                                 with asset list.

                                 New Kings Beam House Directors need
                                 to identify what assets have moved        Graham Callow /       28 May
                                 and where.                                David Young

To maintain security levels      Go Green must ensure that all fire        Go Green / CPS        Ongoing
during moves                     doors are shut after removals are         Guards
                                 complete each day. CPS Guards to
                                 check fire doors are shut afterwards.

To monitor meetings that         ISS to provide an update on what          Peter Rouse / ISS     28 May
continue to run at Ludgate       meetings have been booked and when
Hill so that they do not clash   up to the 12th June.
with moves
                                 HR are still using meeting rooms for      Peter Rouse / ISS /   28 May
                                 interviews on the first floor. ISS / HQ   Brian Ford / HQ Ops
                                 Ops to negotiate limiting meetings to
                                 select rooms.
                                                                                                                   11
Ludgate Closedown Tasks (3)

Task                           Action                                    Team Responsible        Target      Completion
                                                                                                 Date        Date
To ensure that all technical   Global Crossings / ACAD to collect and    Tania Zazlawska /       27/28-May
equipment is removed and       box handsets on-site at Ludgate Hill on   Global Crossings
dealt with appropriately.      Thurs 27th may and Fri 28th May


To ensure the library is       TPS to pack, remove and unpack            Doug Crighton / Chris   13-June
consolidated and moved         library materials (Mon 7th June – Sun     Mitchell / Peter
effectively.                   13th June). Approx 900 crates (480        Bailey
                               linear metres). Crates moved Fri 11th
                               (AM) and Sat 12th (AM) June.
To ensure that all ICT         Logica to remove most ICT equipment       Andy Simpson /          30-June
equipment is removed and       after 6th June (when teams vacate);       Andrew Davidson
disposed of appropriately.     phones and faxes on 28th May; ISS and
                               Library after 12th June.




                                                                                                                     12
13

Mais conteúdo relacionado

Destaque

Seminario de investigacion - plataformas de desarrollo del borde costero - ca...
Seminario de investigacion - plataformas de desarrollo del borde costero - ca...Seminario de investigacion - plataformas de desarrollo del borde costero - ca...
Seminario de investigacion - plataformas de desarrollo del borde costero - ca...Diego Garib Pavez
 
Fahrzeugklinik baut Werkstattkette mit Beteiligungskapital aus
Fahrzeugklinik baut Werkstattkette mit Beteiligungskapital ausFahrzeugklinik baut Werkstattkette mit Beteiligungskapital aus
Fahrzeugklinik baut Werkstattkette mit Beteiligungskapital ausfahrzeugklinik GmbH
 
InP Light Emitting Diodes
InP Light Emitting DiodesInP Light Emitting Diodes
InP Light Emitting Diodesrajvkk
 
Short introduction at Informatio Scientifica & Informatio Medicata 2014
Short introduction at Informatio Scientifica & Informatio Medicata 2014Short introduction at Informatio Scientifica & Informatio Medicata 2014
Short introduction at Informatio Scientifica & Informatio Medicata 2014Peter Bencsik
 
Plan social media para un blog
Plan social media para un blogPlan social media para un blog
Plan social media para un blogLluís Raga
 
Curso certificado de social media strategist
Curso certificado de social media strategistCurso certificado de social media strategist
Curso certificado de social media strategistJosep Claret
 
Herausforderungen Neuer Medien in der Lehre
Herausforderungen Neuer Medien in der LehreHerausforderungen Neuer Medien in der Lehre
Herausforderungen Neuer Medien in der LehreJohannes Dorfinger
 

Destaque (10)

Anúncios 24 12 pdf
Anúncios 24 12 pdfAnúncios 24 12 pdf
Anúncios 24 12 pdf
 
Seminario de investigacion - plataformas de desarrollo del borde costero - ca...
Seminario de investigacion - plataformas de desarrollo del borde costero - ca...Seminario de investigacion - plataformas de desarrollo del borde costero - ca...
Seminario de investigacion - plataformas de desarrollo del borde costero - ca...
 
Fahrzeugklinik baut Werkstattkette mit Beteiligungskapital aus
Fahrzeugklinik baut Werkstattkette mit Beteiligungskapital ausFahrzeugklinik baut Werkstattkette mit Beteiligungskapital aus
Fahrzeugklinik baut Werkstattkette mit Beteiligungskapital aus
 
InP Light Emitting Diodes
InP Light Emitting DiodesInP Light Emitting Diodes
InP Light Emitting Diodes
 
Act. 1 unidad 2 yannine adriana martínez valle lao
Act. 1 unidad 2 yannine adriana martínez valle laoAct. 1 unidad 2 yannine adriana martínez valle lao
Act. 1 unidad 2 yannine adriana martínez valle lao
 
Short introduction at Informatio Scientifica & Informatio Medicata 2014
Short introduction at Informatio Scientifica & Informatio Medicata 2014Short introduction at Informatio Scientifica & Informatio Medicata 2014
Short introduction at Informatio Scientifica & Informatio Medicata 2014
 
Plan social media para un blog
Plan social media para un blogPlan social media para un blog
Plan social media para un blog
 
Libros de texto 2012 2013
Libros de texto 2012 2013Libros de texto 2012 2013
Libros de texto 2012 2013
 
Curso certificado de social media strategist
Curso certificado de social media strategistCurso certificado de social media strategist
Curso certificado de social media strategist
 
Herausforderungen Neuer Medien in der Lehre
Herausforderungen Neuer Medien in der LehreHerausforderungen Neuer Medien in der Lehre
Herausforderungen Neuer Medien in der Lehre
 

CPS Ludgate Hill Closedown Progress, Relocation & Schedule

  • 1. CPS Ludgate Hill HQ Closedown Project and Move out Schedule FMBC HQ Operations Team January 2010 1
  • 2. Ludgate Hill HQ. Stores & Office Areas – Decanting Program 2009-10. 2
  • 3. Main Move Schedule Directorate / Location Location (to) Date Status Division (from) Casework Division Rose Court (3rd) Rose Court (6th) 10th & 11th April – Fraud LOC – CPS Ludgate Hill (7th) New Kings Beam 17th & 18th April London House LCJP & Met Ludgate Hill (3rd) New Kings Beam 17th & 18th April Police House (Met Police – 21st June) CPS London – Rose Court Ludgate Hill 17th & 18th April Learning & Leadership BIS Ludgate Hill (2nd) Rose Court 1st & 2nd May HR, EDU & Ludgate Hill (1st, Rose Court 8th & 9th May Finance 7th & 3rd) Policy & BDD Ludgate Hill (6th) Rose Court 15th &16th May 3
  • 4. Main Move Schedule Directorate / Location Location (to) Date Status Division (from) Casework (CTD, Ludgate Hill (5th) Rose Court 22nd & 23rd May SCD, OCD) Private Office / Ludgate Hill (7th) Rose Court 22nd & 23rd May Corp Comms Casework (CTD, Ludgate Hill (5th) Rose Court 29th & 30th May SCD, OCD) Restaurant (ISS Ludgate Hill (3rd) 31st May Eatons) (Shutdown) Recreation Room Ludgate Hill (3rd) 31st May (Shutdown) Casework (CTD, Ludgate Hill (5th) Rose Court 5th & 6th June SCD, OCD) CPS London Ludgate Hill (4th) The Cooperage 12th & 13th June Direct & Complex 4 Casework Centre
  • 5. Main Move Schedule Directorate / Location (from) Location (to) Date Status Division CPS London – Ludgate Hill New Kings Beam 12th & 13th June Learning & House Leadership Ludgate Hill Ludgate Hill 12th & 13th June Corporate (Shutdown) Meeting Rooms Xerox & MFDs Ludgate Hill Rose Court 15th June Casework (UKBA New Kings Beam Rose Court 26th & 27th June & POCU) and House Revenue & Customs Division Casework (UKBA New Kings Beam Rose Court 3rd & 4th July & POCU) and House Revenue & Customs Division Casework (UKBA New Kings Beam Rose Court 10th & 11th July & POCU) and House Revenue & Customs Division 5
  • 6. Ludgate HQ Moves Schedule March April May June Records / archives Moves: Moves: Moves: Contract removals Casework Division - BIS – LH to RC - 1st & Casework – LH to RC - Fraud 2nd May 5th & 6th June Progress Reporting CPS Direct & 17th & 18th April – RC 3rd HR, EDU & Finance Check Priorities floor to LH 3rd floor. – LH to RC - 8th & 9th Complex Casework May centre – LH to CO - Manage costs LOC Team (CPS London) 12th & 13th June Policy & BDD – LH to – LH 7th to NKBH - RC - 15th & 16th May. Casework Division Key: 17th April (UKBA and POCU) Casework – LH to RC and Revenue and LH = Ludgate Hill LCJB – LH 3rd to NKBH - 22nd & 23rd / 29th & - 17th & 18th April Customs Division – NKBH = New Kings 30th May NKBH to RC - 26th & 27th Beam House L&L CPS London – June. 3 & 4 July. 10 & 11 July RC = Rose Court 18th April – RC to LH 3rd floor. Note: 1 Meeting Private Office – LH CO = Cooperage to RC - 5th & 6th June room plus 7 desks Corp Comms – LH to RC - 5th & 6th June 6
  • 7. Operational Move issues • Redundant files disposed. • Crates to be labelled to identify Basement Stores, Storage Units owner / Directorate. and Office Areas. • If new desk or location is known • Files required to be kept by law crates should be labelled with should be archived. this information. • Files necessary for work to be • Before removal, all cupboards, prepared for relocation to Rose safes and storage furniture must Court. be checked by Business • Clear desk policies should be Manager, Move Champion and followed. member of the DSO team to • Pack and store all files and items ensure it is safe for removal. ready for the move. (Crates to be • FM Teams: Audit checks of all supplied). working areas. To ensure no information is left behind. 7
  • 8. Ludgate Closedown Tasks (1) Task Action Team Target Completion Responsible Date Date Provide a statutory compliance 04 June valid certification in its original form. LG examinations of all the lifts Mark McCulloch to set up a Cofatec / 04 June must be valid and up-to-date at the schedule of all ongoing Mark end of the lease. examinations McCulloch CPS must strip out and remove the HQ Operations and ISS to arrange HQ Ops / ISS / w/c 14 kitchen on third floor stripping out and removal of Brian Ford / June kitchen. Two fridges are to be Peter Rouse retained. From 7th June TPS to remove crockery, plates and trays. CPS must strip out and remove the HQ Operations to arrange to have HQ Ops / 21 - 25 reception desk reception desk taken out and the Brian Ford June stripping out of area. HQ Ops to arrange temporary desk. Remove / disarm any electronic Roy Ellard to provide a programme SSG / Roy Wknd 26 security systems to internal doors for the closedown of all Security Ellard / Chris - 27 June items and HQ Ops and Security Duggan team to review. SSG to remove/disarm security systems on pre-arranged date. 8
  • 9. Ludgate Closedown Tasks (2) Task Action Team Target Completion Responsible Date Date Ensure all the internal locks are in Roy Ellard to provide a programme for the SSG / Roy Ellard / Wknd the unlocked position closedown of all Security items and HQ Chris Duggan 26 - 27 Ops and Security team to review. SSG to June leave internal locks unlocked on pre- arranged date. All perimeter doors are to be Roy Ellard to provide a programme for the SSG / Roy Ellard / Wknd securable closedown of all Security items and HQ Chris Duggan 26 - 27 Ops and Security team to review. SSG to June ensure perimeter doors are securable. Keys are to be provided to Land Security team need to collate a schedule SSG / Roy Ellard / w/c 14 Securities on the end day of the detailing all the keys that will be handed Chris Duggan June lease with each key clearly over. identified The CCTV cameras that monitor SSG to note that CCTV cameras will be left SSG / Roy Ellard / 30 June the perimeter of the building behind. Chris Duggan may be left in situ Monitor courtyard movements Go Green and TPS to provide a Go Green / TPS Ongoing and moves in general programme each on their respective moves and the quantity of removal vehicles expected on each removal day. Give Hillgate House Security weekly 9 updates on moves.
  • 10. Ludgate Closedown Tasks (3) Task Action Team Responsible Target Completion Date Date Provide the most up-to-date Sue Twist of ISS to provide an up-to- ISS / Sue Twist / 04-June asbestos survey and register, date asbestos survey via Peter Rouse Peter Rouse electronically, if possible. To suggest a date and time HQ Operations have suggested the 4th DTZ / Richard Young / 04-June for a plant room walk-round June for the walk-round. Invitees Andy Walker near the time of the lease include Andy Morgan from AECOM, end. Gareth Brown from DTZ and HQ Operations representative. The end date of the lease is To Review after the 4th June Mark McCulloch 04-June 30th June 2010. The CPS is to decide whether they wish to extend the lease by a month and to inform Paul Hunt of decision. Land Securities may not HQ Operations to gain clarification Zoe Varian 04-June want the plant systems to be from Zoe Varian as to whether the isolated and drained down – plant systems need to be isolated or this needs to be clarified. drained down. If they do, this will have to be arranged. 10
  • 11. Ludgate Closedown Tasks (3) Task Action Team Responsible Target Completion Date Date To ensure that all assets are Go Green to provide a revised Master Natalie Lewis / Go 30 June accounted for during the Programme of planned moves. Go Green move ready for Green to provide weekly updates on Parliamentary Questions progress of removals from site in line with asset list. New Kings Beam House Directors need to identify what assets have moved Graham Callow / 28 May and where. David Young To maintain security levels Go Green must ensure that all fire Go Green / CPS Ongoing during moves doors are shut after removals are Guards complete each day. CPS Guards to check fire doors are shut afterwards. To monitor meetings that ISS to provide an update on what Peter Rouse / ISS 28 May continue to run at Ludgate meetings have been booked and when Hill so that they do not clash up to the 12th June. with moves HR are still using meeting rooms for Peter Rouse / ISS / 28 May interviews on the first floor. ISS / HQ Brian Ford / HQ Ops Ops to negotiate limiting meetings to select rooms. 11
  • 12. Ludgate Closedown Tasks (3) Task Action Team Responsible Target Completion Date Date To ensure that all technical Global Crossings / ACAD to collect and Tania Zazlawska / 27/28-May equipment is removed and box handsets on-site at Ludgate Hill on Global Crossings dealt with appropriately. Thurs 27th may and Fri 28th May To ensure the library is TPS to pack, remove and unpack Doug Crighton / Chris 13-June consolidated and moved library materials (Mon 7th June – Sun Mitchell / Peter effectively. 13th June). Approx 900 crates (480 Bailey linear metres). Crates moved Fri 11th (AM) and Sat 12th (AM) June. To ensure that all ICT Logica to remove most ICT equipment Andy Simpson / 30-June equipment is removed and after 6th June (when teams vacate); Andrew Davidson disposed of appropriately. phones and faxes on 28th May; ISS and Library after 12th June. 12
  • 13. 13