SlideShare a Scribd company logo
1 of 22
Download to read offline
1
Static Loading Test
and Prediction
Outcome
Bengt H. Fellenius
May 9 2015
A Prediction Challenge to All Delegates to the 2nd CFPB, Santa Cruz, Bolivia.
Mario H. Terceros and Bengt H. Fellenius
We have constructed an instrumented pile and performed a static loading test that we intend to add a bit
of spice to the conference. To this end, we challenge everyone to submit a prediction of the test results.
Then, on Friday, we will start the day with a "Brief report on results of the static loading test and
outcome of the low-key prediction". The "Prediction" referred to is yours.
The Pile
The pile, TP1, is a 600 mm diameter, 16.4 m long, bored pile
constructed on April 20 by pushing a 600-mm diameter, OD,
temporary casing into the ground while augering out the core as
the pipe is pushed down taking care not to auger beyond the toe
of the pipe. Once the pipe reached the intended depth and had
been augered out, concrete (cylinder strength 21 MPa) was
poured into the pipe while it was extracted always maintaining
an inside head of concrete. A 14.0 m long reinforcing cage
consisting of six 20-mm reinforcement bars placed in a circle
with an 450-mm outside diameter was then inserted into the pipe.
The cage had been instrumented with three levels of a single
strain-gage pair at depth 1.80, 9.30, and 13.80 m below the top of
the cage (i.e., at the ground surface). A 310 mm high hydraulic
jack was attached to the bottom of the cage to serve as a
bidirectional cell (BDC) in the first phase of the static loading
test. Thus, in the test, the pile would be separated in an upper
14.8 m length and a lower 1.6 m long length. Telltale guide
pipes were attached to the cage so as to measure the opening of
the BDC and movement of the lower end of the BDC.
The static loading test was performed in two phases. Phase 1
was performed on May 7, 2015, and consisted of a bi-directional
test. In the bidirectional test, the BDC pushes the length above
the BDC (the "upper length") upward and the length below (the
"lower length") downward. The load increments were 50-kN,
each with a 10-minute load-holding time. At the maximum load
of 700 kN, the lower length (1.6 m) plunged. No movement
occurred at the pile head and the net BDC opening was 60+ mm.
16.4m
13.8m
9.3m
1.8m
Strain
Gages
Strain
Gages
Ground Surface
PILE
Strain
Gages
BDC
May 9 2015
Phase 2 test was performed on May 8, 2015. It consisted of leaving the BDC open (free-draining) and
performing a head-down test by means of a conventional reaction pile arrangement. The load increments
were 100-kN, each with a 10-minute load-holding time. The prediction event deals with Phase 2 test, only.
F.y.i., a companion pile, TP2, was constructed on the same day 5 m away from TP1. It was tested as a
full-length pile after the tests on TP1. Pile TP2 is not a part of the prediction event.
The Soil--CPTU and SPT diagrams
The bar in the figure represents the N-indices and the bl/0.3m scale is numerically the same as the qt cone
stress, MPa. The SPT was performed with a constant height-of-fall. The soil profile consists of 9 m thick
layer of silty fine sand, followed by 6 m of fine sand on sand. A 0.2 m thick clay layer was encountered
at 15.0 m depth. The groundwater table is located at 5.0 m depth. The saturated solid densities of the
three soil layers are 2,100, 2,000, 2,100 kg/m3
, respectively.
The Prediction Submission
The primary submission is a prediction of the load-movement of the pile shaft (Phase 2) and the capacity
of the shaft, as determined from that same load-movement curve. Submit the values in table showing two
columns, one for load (kN) and one for movement (mm). Use at least 8 load-movement points on the
curve to the maximum load. Give the evaluated capacity as a separate value. You can use either a Word
document or an Excel file. Please submit your prediction to Bengt by e-mail to address:
Bengt@Fellenius.net. The submission deadline is noon May 14.
0
5
10
15
20
25
0 10 20 30 40
DEPTH(m)
Cone Stress, qt (MPa)
0
5
10
15
20
25
0 100 200 300 400
DEPTH(m)
Sleeve Friction, fs (kPa)
0
5
10
15
20
25
0 100 200 300 400
DEPTH(m)
Pore Pressure (kPa)
0
5
10
15
20
25
0 1 2 3 4
DEPTH(m)
Friction Ratio, fR (%)
2
3
Soil Profile
0
5
10
15
20
25
0 10 20 30 40
DEPTH(m)
Cone Stress, qt (MPa)
0
5
10
15
20
25
0 100 200 300 400
DEPTH(m)
Sleeve Friction, fs (kPa)
0
5
10
15
20
25
0 100 200 300 400
DEPTH(m)
Pore Pressure (kPa)
0
5
10
15
20
25
0 1 2 3 4
DEPTH(m)
Friction Ratio, fR (%)
SPT
4
5
“BDC” = Bidirectional Cell; a sacrificial
hydraulic jack
16.4m
13.8m
9.3m
1.8m
Strain
Gages
Strain
Gages
Ground Surface
PILE
Strain
Gages
BDC and
telltales
6
Test Programme
Phase 1 Activate the BDC to perform a bidirectional test, pushing the
upper length upward and the lower length downward. This will
create an opening between the two pile lengths.
Phase 2 Activate the jack on the pile head to perform a head-down test
on the upper pile length with the BDC free-draining The pile will
then function in shaft-bearing only with no toe resistance until
the BDC opening is closed).
Phase 3 If the full resistance of the lower length was not engaged in
Phase 1, then , the jack at the pile head will be closed and the
BDC be re-engaged (The jack at the pile head will now provide
the additional resistance needed).
7
Test Results
Phase 1
The bidirectional (BDC) test pushed the lower length
downward a distance of abut 60 mm at the 700-kN
maximum load---plunging type response. The
measurement is approximate, only, due to friction of the
telltales in the guide pipes. The pile head showed no
movement. Upward movement at the BDC level was
small representing the pile shortening for the load.
8
0
1,000
2,000
3,000
4,000
5,000
6,000
0 10 20 30 40 50 60 70
LOAD(kN)
MOVEMENT (mm)
My Prediction
Predictions
0
1,000
2,000
3,000
4,000
5,000
6,000
0 10 20 30 40 50 60 70
LOAD(kN)
MOVEMENT (mm)
All Predictions Received
0
1,000
2,000
3,000
4,000
5,000
6,000
0 10 20 30 40 50 60 70
LOAD(kN)
MOVEMENT (mm)
All Predictions Received with Capacity Interpretations
The circles are the capacities as interpreted
from each curve by the particular predictor
Dashed curve is my prediction prepared with full benefit of the results
of the 2013 tests on similar piles in very similar soil—hardly Class A .
9
0
1,000
2,000
3,000
4,000
5,000
6,000
0 10 20 30 40 50 60 70
LOAD(kN)
MOVEMENT (mm)
with Measured Load-Movement
0
500
1,000
1,500
2,000
2,500
3,000
3,500
0 5 10 15 20 25 30 35
LOAD(kN)
MOVEMENT (mm)
Enlarged View of Predictions and Head-down Test on TP1 Upper Length
10
11
rs = βσ'z
z
Movement =
function of
E-modulus
rs = f(movement)
The pile is
assumed made
up of a series of
short elements,
each affected by
soil resistance
?WHICH
TO USE
AND
HOW TO
MODIFY
12
The t-z functions actually
used for the fit
13
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP1 Phase 2
Head-down
UniPile
Simulation
of Test
Head-down,
Test
Load-Movement for the Upper Pile (14.8 m)
The final fit
14
y = -0.0026x + 6.7169
0
1
2
3
4
5
6
7
8
0 200 400 600 800
SECANTSTIFFNESS,Q/μԑ(GN)
STRAIN (ԑ)
TP2
Es (GPa) for zero strain = 23.8 GPa
Es (GPa) for 700 μԑ = 17.3 GPa
1.7 m
y = -0.0052x + 6.7904
0
1
2
3
4
5
6
7
0 200 400 600 800
TANGENTSTIFFNESS,ΔQ/Δμԑ
(GN)
STRAIN (ԑ)
TP2
Es (GPa) for zero strain = 24.0 GPa
Es (GPa) for 700 μԑ = 17.6 GPa
1.7 m
The Pile Stiffness (EA) Evaluated
from the Uppermost Strain-Gage
Unfortunately, the other strain-gages either did not
survive the construction or survived, but were
dislocated--–No usable strain-gage data were obtained
15
Now the results of Phase 1, the
bidirectional test
The downward movements are unfortunately
impaired due to friction along the telltales
0
500
1,000
1,500
2,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP1
Bidirectional
Downward
0
500
1,000
1,500
2,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP1
Bidirectional
Downward
16
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP1
Bidirectional
Downward
Head-down,
Test
The blue curve is the probable load-movement
curve for the lower length; “Downward”
Phases 1 and 2 together
17
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP1
Bidirectional
Downward
Head-down
UniPile
Simulation
of Test
Head-down,
Test
Full Length Head-down
UniPile Simulation
Combining the results to the load-movement curve
for a head-down test on the full length of pile
18
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP2
TP1Compression
Head
Toe
UniPile
Simulation
Measured
The load-movement curves for the head-down
test on Pile 2 with a fit (UniPile) to the data
and a comparison to same for Pile 1.
19
0
2
4
6
8
10
12
14
16
18
0 1,000 2,000 3,000 4,000DEPTH(m)
LOAD (kN)
Load Distribution, TP2
From fit to Load-
Movement Curve
at 5mm elementCPTU E-F
SPT Decourt
Load distributions at the ≈5-mm
element movements for Phase 2
(TP1) combined with the
distribution from CPTU and SPT
analysis of shaft resistance
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
0 10 20 30 40 50 60
LOAD(kN)
MOVEMENT (mm)
TP2
TP1Compression
Head
Toe
UniPile
Simulation
Measured
Thank You

More Related Content

What's hot

Worked Examples for Timber Beam Design to AS1720.1 Webinar
Worked Examples for Timber Beam Design to AS1720.1 WebinarWorked Examples for Timber Beam Design to AS1720.1 Webinar
Worked Examples for Timber Beam Design to AS1720.1 WebinarClearCalcs
 
AS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesAS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesClearCalcs
 
Statnamic testing of soils
Statnamic testing of soilsStatnamic testing of soils
Statnamic testing of soilsSravan Muguda
 
Pda capwap - frank rausche
Pda capwap - frank rauschePda capwap - frank rausche
Pda capwap - frank rauschecfpbolivia
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingElise M. Mansour
 
Presentation_Abdul Aziz Zantout_UP706051
Presentation_Abdul Aziz Zantout_UP706051Presentation_Abdul Aziz Zantout_UP706051
Presentation_Abdul Aziz Zantout_UP706051Abdul Aziz Zantout
 
Sachpazis_PILE Analysis_Design to EC2
Sachpazis_PILE Analysis_Design to EC2Sachpazis_PILE Analysis_Design to EC2
Sachpazis_PILE Analysis_Design to EC2Dr.Costas Sachpazis
 
Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...
Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...
Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...João Baltazar
 
Vehicle load transfer part III 2021
Vehicle load transfer part III 2021Vehicle load transfer part III 2021
Vehicle load transfer part III 2021William Harbin
 
Increasing life of spur gears with the help of finite element analysis
Increasing life of spur gears with the help of finite element analysisIncreasing life of spur gears with the help of finite element analysis
Increasing life of spur gears with the help of finite element analysisijmech
 
91751123 solucionario-capitulo-13-paul-e-tippens
91751123 solucionario-capitulo-13-paul-e-tippens91751123 solucionario-capitulo-13-paul-e-tippens
91751123 solucionario-capitulo-13-paul-e-tippensMaitriSamayoa
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021William Harbin
 
Vehicle load transfer part II 2021
Vehicle load transfer part II 2021Vehicle load transfer part II 2021
Vehicle load transfer part II 2021William Harbin
 
Vehicle load transfer part I 2021
Vehicle load transfer part I 2021Vehicle load transfer part I 2021
Vehicle load transfer part I 2021William Harbin
 
Barge stabilityguidelines
Barge stabilityguidelinesBarge stabilityguidelines
Barge stabilityguidelinesdattavan
 
1.4 latifs 17 dramix sog
1.4 latifs 17 dramix sog 1.4 latifs 17 dramix sog
1.4 latifs 17 dramix sog Latifs Chile
 
Worked examples - Wind webinar to AS1170.2 - ClearCalcs
Worked examples - Wind webinar to AS1170.2 - ClearCalcsWorked examples - Wind webinar to AS1170.2 - ClearCalcs
Worked examples - Wind webinar to AS1170.2 - ClearCalcsClearCalcs
 
Propagation of Ground Vibrations Due to Explosives
Propagation of Ground Vibrations Due to ExplosivesPropagation of Ground Vibrations Due to Explosives
Propagation of Ground Vibrations Due to ExplosivesNicholas_Matthews
 

What's hot (20)

Worked Examples for Timber Beam Design to AS1720.1 Webinar
Worked Examples for Timber Beam Design to AS1720.1 WebinarWorked Examples for Timber Beam Design to AS1720.1 Webinar
Worked Examples for Timber Beam Design to AS1720.1 Webinar
 
AS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesAS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked Examples
 
Statnamic testing of soils
Statnamic testing of soilsStatnamic testing of soils
Statnamic testing of soils
 
Pda capwap - frank rausche
Pda capwap - frank rauschePda capwap - frank rausche
Pda capwap - frank rausche
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft Loading
 
Presentation_Abdul Aziz Zantout_UP706051
Presentation_Abdul Aziz Zantout_UP706051Presentation_Abdul Aziz Zantout_UP706051
Presentation_Abdul Aziz Zantout_UP706051
 
Sachpazis_PILE Analysis_Design to EC2
Sachpazis_PILE Analysis_Design to EC2Sachpazis_PILE Analysis_Design to EC2
Sachpazis_PILE Analysis_Design to EC2
 
Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...
Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...
Unsteady Analysis of a Horizontal Axis Marine Current Turbine in Yawed Inflow...
 
Vehicle load transfer part III 2021
Vehicle load transfer part III 2021Vehicle load transfer part III 2021
Vehicle load transfer part III 2021
 
Increasing life of spur gears with the help of finite element analysis
Increasing life of spur gears with the help of finite element analysisIncreasing life of spur gears with the help of finite element analysis
Increasing life of spur gears with the help of finite element analysis
 
91751123 solucionario-capitulo-13-paul-e-tippens
91751123 solucionario-capitulo-13-paul-e-tippens91751123 solucionario-capitulo-13-paul-e-tippens
91751123 solucionario-capitulo-13-paul-e-tippens
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021
 
Vehicle load transfer part II 2021
Vehicle load transfer part II 2021Vehicle load transfer part II 2021
Vehicle load transfer part II 2021
 
Presentation CIE619
Presentation CIE619 Presentation CIE619
Presentation CIE619
 
Vehicle load transfer part I 2021
Vehicle load transfer part I 2021Vehicle load transfer part I 2021
Vehicle load transfer part I 2021
 
17 appendix a
17 appendix a17 appendix a
17 appendix a
 
Barge stabilityguidelines
Barge stabilityguidelinesBarge stabilityguidelines
Barge stabilityguidelines
 
1.4 latifs 17 dramix sog
1.4 latifs 17 dramix sog 1.4 latifs 17 dramix sog
1.4 latifs 17 dramix sog
 
Worked examples - Wind webinar to AS1170.2 - ClearCalcs
Worked examples - Wind webinar to AS1170.2 - ClearCalcsWorked examples - Wind webinar to AS1170.2 - ClearCalcs
Worked examples - Wind webinar to AS1170.2 - ClearCalcs
 
Propagation of Ground Vibrations Due to Explosives
Propagation of Ground Vibrations Due to ExplosivesPropagation of Ground Vibrations Due to Explosives
Propagation of Ground Vibrations Due to Explosives
 

Viewers also liked

Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testingcfpbolivia
 
Ringtracs andre estevao silva
Ringtracs   andre estevao silvaRingtracs   andre estevao silva
Ringtracs andre estevao silvacfpbolivia
 
Bauer csm bolivia 2013-04-24
Bauer   csm bolivia 2013-04-24Bauer   csm bolivia 2013-04-24
Bauer csm bolivia 2013-04-24cfpbolivia
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testingcfpbolivia
 
HPBS INDUCTION PRESENTATION
HPBS INDUCTION PRESENTATIONHPBS INDUCTION PRESENTATION
HPBS INDUCTION PRESENTATIONJohn Miranda
 
SIEL PRECAST BUILDING SYSTEM
SIEL PRECAST  BUILDING SYSTEMSIEL PRECAST  BUILDING SYSTEM
SIEL PRECAST BUILDING SYSTEMsegun ilori
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge SystemAltosMarketing
 
Bauer fdp lost bit projects english
Bauer   fdp lost bit projects englishBauer   fdp lost bit projects english
Bauer fdp lost bit projects englishcfpbolivia
 
IBS is a system not a machine
IBS is a system not a machineIBS is a system not a machine
IBS is a system not a machineTeow Beng Hur
 
Bc open pre fabricated construction system
Bc open pre fabricated construction systemBc open pre fabricated construction system
Bc open pre fabricated construction systemAnuj Singhal
 
รายการประมาณราคา สพฐ 2555
รายการประมาณราคา สพฐ 2555รายการประมาณราคา สพฐ 2555
รายการประมาณราคา สพฐ 2555mybuilt
 
SHM (Structural Health Monitoring)
SHM (Structural Health Monitoring)SHM (Structural Health Monitoring)
SHM (Structural Health Monitoring)Sreekanth G
 
Introduction of Prefabricated structures
Introduction  of Prefabricated structuresIntroduction  of Prefabricated structures
Introduction of Prefabricated structuresYogi Yogesh
 
Structural Health Monitoring
Structural Health MonitoringStructural Health Monitoring
Structural Health MonitoringJNTU
 
Structural Health Monitoring Presentation
Structural Health Monitoring PresentationStructural Health Monitoring Presentation
Structural Health Monitoring Presentationaileencv
 
Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.Communications Branding
 
PREFABRICATED STRUCTURES
PREFABRICATED STRUCTURESPREFABRICATED STRUCTURES
PREFABRICATED STRUCTURESRajendran s.
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 

Viewers also liked (20)

Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
Ringtracs andre estevao silva
Ringtracs   andre estevao silvaRingtracs   andre estevao silva
Ringtracs andre estevao silva
 
Bauer csm bolivia 2013-04-24
Bauer   csm bolivia 2013-04-24Bauer   csm bolivia 2013-04-24
Bauer csm bolivia 2013-04-24
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
The Stone Strong System
The Stone Strong SystemThe Stone Strong System
The Stone Strong System
 
HPBS INDUCTION PRESENTATION
HPBS INDUCTION PRESENTATIONHPBS INDUCTION PRESENTATION
HPBS INDUCTION PRESENTATION
 
SIEL PRECAST BUILDING SYSTEM
SIEL PRECAST  BUILDING SYSTEMSIEL PRECAST  BUILDING SYSTEM
SIEL PRECAST BUILDING SYSTEM
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge System
 
Bauer fdp lost bit projects english
Bauer   fdp lost bit projects englishBauer   fdp lost bit projects english
Bauer fdp lost bit projects english
 
IBS is a system not a machine
IBS is a system not a machineIBS is a system not a machine
IBS is a system not a machine
 
Bc open pre fabricated construction system
Bc open pre fabricated construction systemBc open pre fabricated construction system
Bc open pre fabricated construction system
 
รายการประมาณราคา สพฐ 2555
รายการประมาณราคา สพฐ 2555รายการประมาณราคา สพฐ 2555
รายการประมาณราคา สพฐ 2555
 
SHM (Structural Health Monitoring)
SHM (Structural Health Monitoring)SHM (Structural Health Monitoring)
SHM (Structural Health Monitoring)
 
Prefabricated
PrefabricatedPrefabricated
Prefabricated
 
Introduction of Prefabricated structures
Introduction  of Prefabricated structuresIntroduction  of Prefabricated structures
Introduction of Prefabricated structures
 
Structural Health Monitoring
Structural Health MonitoringStructural Health Monitoring
Structural Health Monitoring
 
Structural Health Monitoring Presentation
Structural Health Monitoring PresentationStructural Health Monitoring Presentation
Structural Health Monitoring Presentation
 
Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.
 
PREFABRICATED STRUCTURES
PREFABRICATED STRUCTURESPREFABRICATED STRUCTURES
PREFABRICATED STRUCTURES
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 

Similar to Static load testing and prediction bengt h. fellenius

DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in pilesInfocengrs63
 
assignmnet material project of bridge.docx
assignmnet material project of bridge.docxassignmnet material project of bridge.docx
assignmnet material project of bridge.docxumair ahmad
 
Seismic Capacity Assessment of Sanyi Old Railway Tunnel
Seismic Capacity Assessment of Sanyi Old Railway TunnelSeismic Capacity Assessment of Sanyi Old Railway Tunnel
Seismic Capacity Assessment of Sanyi Old Railway TunnelCes Nit Silchar
 
Prestressed concrete course assignments 2021
Prestressed concrete course assignments 2021Prestressed concrete course assignments 2021
Prestressed concrete course assignments 2021JanneHanka
 
Gte ii-readytoprint
Gte ii-readytoprintGte ii-readytoprint
Gte ii-readytoprintjagadish108
 
CIVE 416 report(final)
CIVE 416 report(final)CIVE 416 report(final)
CIVE 416 report(final)Monique F M
 
Post graduate exam in hydraulic 2018.docx
Post graduate exam in hydraulic   2018.docxPost graduate exam in hydraulic   2018.docx
Post graduate exam in hydraulic 2018.docxDr. Ezzat Elsayed Gomaa
 
Lecture 4 5 Urm Shear Walls
Lecture 4 5 Urm Shear WallsLecture 4 5 Urm Shear Walls
Lecture 4 5 Urm Shear WallsTeja Ande
 
Presentation final
Presentation finalPresentation final
Presentation finalhemutaman
 
6._Bearing_Capacity_from_other_methods.pdf
6._Bearing_Capacity_from_other_methods.pdf6._Bearing_Capacity_from_other_methods.pdf
6._Bearing_Capacity_from_other_methods.pdfAristotleMedina
 
Unit 2 simple stresses and strain
Unit 2 simple stresses and strainUnit 2 simple stresses and strain
Unit 2 simple stresses and strainPratikAkarte2
 
Analysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationAnalysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationMonojit Mondal
 

Similar to Static load testing and prediction bengt h. fellenius (20)

2015.11.12 15 arc binh nguyen
2015.11.12 15 arc  binh nguyen2015.11.12 15 arc  binh nguyen
2015.11.12 15 arc binh nguyen
 
DFI india 2014 defects in piles
DFI india 2014 defects in pilesDFI india 2014 defects in piles
DFI india 2014 defects in piles
 
Gunther koller
Gunther kollerGunther koller
Gunther koller
 
gantry crane report
gantry crane reportgantry crane report
gantry crane report
 
Lisbonne
LisbonneLisbonne
Lisbonne
 
2008 - NOV.pdf
2008 - NOV.pdf2008 - NOV.pdf
2008 - NOV.pdf
 
assignmnet material project of bridge.docx
assignmnet material project of bridge.docxassignmnet material project of bridge.docx
assignmnet material project of bridge.docx
 
Post graduate exam in hydraulics
Post graduate exam in hydraulicsPost graduate exam in hydraulics
Post graduate exam in hydraulics
 
Seismic Capacity Assessment of Sanyi Old Railway Tunnel
Seismic Capacity Assessment of Sanyi Old Railway TunnelSeismic Capacity Assessment of Sanyi Old Railway Tunnel
Seismic Capacity Assessment of Sanyi Old Railway Tunnel
 
Prestressed concrete course assignments 2021
Prestressed concrete course assignments 2021Prestressed concrete course assignments 2021
Prestressed concrete course assignments 2021
 
Gte ii-readytoprint
Gte ii-readytoprintGte ii-readytoprint
Gte ii-readytoprint
 
CIVE 416 report(final)
CIVE 416 report(final)CIVE 416 report(final)
CIVE 416 report(final)
 
Presentation
PresentationPresentation
Presentation
 
Post graduate exam in hydraulic 2018.docx
Post graduate exam in hydraulic   2018.docxPost graduate exam in hydraulic   2018.docx
Post graduate exam in hydraulic 2018.docx
 
Lecture 4 5 Urm Shear Walls
Lecture 4 5 Urm Shear WallsLecture 4 5 Urm Shear Walls
Lecture 4 5 Urm Shear Walls
 
Presentation final
Presentation finalPresentation final
Presentation final
 
Unit-3-Design of shallow foundation.pdf
Unit-3-Design of shallow foundation.pdfUnit-3-Design of shallow foundation.pdf
Unit-3-Design of shallow foundation.pdf
 
6._Bearing_Capacity_from_other_methods.pdf
6._Bearing_Capacity_from_other_methods.pdf6._Bearing_Capacity_from_other_methods.pdf
6._Bearing_Capacity_from_other_methods.pdf
 
Unit 2 simple stresses and strain
Unit 2 simple stresses and strainUnit 2 simple stresses and strain
Unit 2 simple stresses and strain
 
Analysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationAnalysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundation
 

More from cfpbolivia

Risk evaluation according to standards cristina de hc tsuha
Risk evaluation according to standards  cristina de hc tsuhaRisk evaluation according to standards  cristina de hc tsuha
Risk evaluation according to standards cristina de hc tsuhacfpbolivia
 
Ingeniería sostenible de fundaciones profundas alessandro mandolini
Ingeniería sostenible de fundaciones profundas   alessandro mandoliniIngeniería sostenible de fundaciones profundas   alessandro mandolini
Ingeniería sostenible de fundaciones profundas alessandro mandolinicfpbolivia
 
Integrity frank rausche
Integrity  frank rauscheIntegrity  frank rausche
Integrity frank rauschecfpbolivia
 
Grlweap frank rausche
Grlweap  frank rauscheGrlweap  frank rausche
Grlweap frank rauschecfpbolivia
 
4.4 integrity gray
4.4   integrity gray4.4   integrity gray
4.4 integrity graycfpbolivia
 
3.6 spt energy calibration -gray
3.6   spt energy calibration -gray3.6   spt energy calibration -gray
3.6 spt energy calibration -graycfpbolivia
 
2.5 pda-capwap - gray
2.5   pda-capwap - gray2.5   pda-capwap - gray
2.5 pda-capwap - graycfpbolivia
 
1.1 grlweap - gray
1.1   grlweap - gray1.1   grlweap - gray
1.1 grlweap - graycfpbolivia
 
Bolivia seismic properties k. rainer massarsch
Bolivia seismic properties   k. rainer massarschBolivia seismic properties   k. rainer massarsch
Bolivia seismic properties k. rainer massarschcfpbolivia
 
Bolivia driven vibrated piles 04 30.compressed
Bolivia driven vibrated piles 04 30.compressedBolivia driven vibrated piles 04 30.compressed
Bolivia driven vibrated piles 04 30.compressedcfpbolivia
 
Bolivia driven vibrated piles k. rainer masssarsch
Bolivia driven vibrated piles   k. rainer masssarschBolivia driven vibrated piles   k. rainer masssarsch
Bolivia driven vibrated piles k. rainer masssarschcfpbolivia
 
The flat dilatomer test silvano marchetti
The flat dilatomer test   silvano marchettiThe flat dilatomer test   silvano marchetti
The flat dilatomer test silvano marchetticfpbolivia
 
Keynote silvano marchetti
Keynote   silvano marchettiKeynote   silvano marchetti
Keynote silvano marchetticfpbolivia
 
El ensayo dilatométrico de marchetti silvano marchetti
El ensayo dilatométrico de marchetti   silvano marchettiEl ensayo dilatométrico de marchetti   silvano marchetti
El ensayo dilatométrico de marchetti silvano marchetticfpbolivia
 
Spt spt t procedures and practical applications -luciano decourt
Spt  spt t procedures and practical applications -luciano decourtSpt  spt t procedures and practical applications -luciano decourt
Spt spt t procedures and practical applications -luciano decourtcfpbolivia
 
Influence of deep foundation installation methods morgan nesmith
Influence of deep foundation installation methods   morgan nesmithInfluence of deep foundation installation methods   morgan nesmith
Influence of deep foundation installation methods morgan nesmithcfpbolivia
 
Prospección geofísica aplicada en las investigaciones geotécnicas noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas  noel perezProspección geofísica aplicada en las investigaciones geotécnicas  noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas noel perezcfpbolivia
 
Patologia das fundaçõe desafios para melhoria - jarbas milititsky
Patologia das fundaçõe  desafios para melhoria - jarbas milititskyPatologia das fundaçõe  desafios para melhoria - jarbas milititsky
Patologia das fundaçõe desafios para melhoria - jarbas milititskycfpbolivia
 
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.cfpbolivia
 
Congreso cfpb2015 huesker
Congreso cfpb2015   hueskerCongreso cfpb2015   huesker
Congreso cfpb2015 hueskercfpbolivia
 

More from cfpbolivia (20)

Risk evaluation according to standards cristina de hc tsuha
Risk evaluation according to standards  cristina de hc tsuhaRisk evaluation according to standards  cristina de hc tsuha
Risk evaluation according to standards cristina de hc tsuha
 
Ingeniería sostenible de fundaciones profundas alessandro mandolini
Ingeniería sostenible de fundaciones profundas   alessandro mandoliniIngeniería sostenible de fundaciones profundas   alessandro mandolini
Ingeniería sostenible de fundaciones profundas alessandro mandolini
 
Integrity frank rausche
Integrity  frank rauscheIntegrity  frank rausche
Integrity frank rausche
 
Grlweap frank rausche
Grlweap  frank rauscheGrlweap  frank rausche
Grlweap frank rausche
 
4.4 integrity gray
4.4   integrity gray4.4   integrity gray
4.4 integrity gray
 
3.6 spt energy calibration -gray
3.6   spt energy calibration -gray3.6   spt energy calibration -gray
3.6 spt energy calibration -gray
 
2.5 pda-capwap - gray
2.5   pda-capwap - gray2.5   pda-capwap - gray
2.5 pda-capwap - gray
 
1.1 grlweap - gray
1.1   grlweap - gray1.1   grlweap - gray
1.1 grlweap - gray
 
Bolivia seismic properties k. rainer massarsch
Bolivia seismic properties   k. rainer massarschBolivia seismic properties   k. rainer massarsch
Bolivia seismic properties k. rainer massarsch
 
Bolivia driven vibrated piles 04 30.compressed
Bolivia driven vibrated piles 04 30.compressedBolivia driven vibrated piles 04 30.compressed
Bolivia driven vibrated piles 04 30.compressed
 
Bolivia driven vibrated piles k. rainer masssarsch
Bolivia driven vibrated piles   k. rainer masssarschBolivia driven vibrated piles   k. rainer masssarsch
Bolivia driven vibrated piles k. rainer masssarsch
 
The flat dilatomer test silvano marchetti
The flat dilatomer test   silvano marchettiThe flat dilatomer test   silvano marchetti
The flat dilatomer test silvano marchetti
 
Keynote silvano marchetti
Keynote   silvano marchettiKeynote   silvano marchetti
Keynote silvano marchetti
 
El ensayo dilatométrico de marchetti silvano marchetti
El ensayo dilatométrico de marchetti   silvano marchettiEl ensayo dilatométrico de marchetti   silvano marchetti
El ensayo dilatométrico de marchetti silvano marchetti
 
Spt spt t procedures and practical applications -luciano decourt
Spt  spt t procedures and practical applications -luciano decourtSpt  spt t procedures and practical applications -luciano decourt
Spt spt t procedures and practical applications -luciano decourt
 
Influence of deep foundation installation methods morgan nesmith
Influence of deep foundation installation methods   morgan nesmithInfluence of deep foundation installation methods   morgan nesmith
Influence of deep foundation installation methods morgan nesmith
 
Prospección geofísica aplicada en las investigaciones geotécnicas noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas  noel perezProspección geofísica aplicada en las investigaciones geotécnicas  noel perez
Prospección geofísica aplicada en las investigaciones geotécnicas noel perez
 
Patologia das fundaçõe desafios para melhoria - jarbas milititsky
Patologia das fundaçõe  desafios para melhoria - jarbas milititskyPatologia das fundaçõe  desafios para melhoria - jarbas milititsky
Patologia das fundaçõe desafios para melhoria - jarbas milititsky
 
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.Las fundaciones profundas en bolivia en los últimos 50 años   mario terceros h.
Las fundaciones profundas en bolivia en los últimos 50 años mario terceros h.
 
Congreso cfpb2015 huesker
Congreso cfpb2015   hueskerCongreso cfpb2015   huesker
Congreso cfpb2015 huesker
 

Recently uploaded

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 

Recently uploaded (20)

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 

Static load testing and prediction bengt h. fellenius

  • 1. 1 Static Loading Test and Prediction Outcome Bengt H. Fellenius
  • 2. May 9 2015 A Prediction Challenge to All Delegates to the 2nd CFPB, Santa Cruz, Bolivia. Mario H. Terceros and Bengt H. Fellenius We have constructed an instrumented pile and performed a static loading test that we intend to add a bit of spice to the conference. To this end, we challenge everyone to submit a prediction of the test results. Then, on Friday, we will start the day with a "Brief report on results of the static loading test and outcome of the low-key prediction". The "Prediction" referred to is yours. The Pile The pile, TP1, is a 600 mm diameter, 16.4 m long, bored pile constructed on April 20 by pushing a 600-mm diameter, OD, temporary casing into the ground while augering out the core as the pipe is pushed down taking care not to auger beyond the toe of the pipe. Once the pipe reached the intended depth and had been augered out, concrete (cylinder strength 21 MPa) was poured into the pipe while it was extracted always maintaining an inside head of concrete. A 14.0 m long reinforcing cage consisting of six 20-mm reinforcement bars placed in a circle with an 450-mm outside diameter was then inserted into the pipe. The cage had been instrumented with three levels of a single strain-gage pair at depth 1.80, 9.30, and 13.80 m below the top of the cage (i.e., at the ground surface). A 310 mm high hydraulic jack was attached to the bottom of the cage to serve as a bidirectional cell (BDC) in the first phase of the static loading test. Thus, in the test, the pile would be separated in an upper 14.8 m length and a lower 1.6 m long length. Telltale guide pipes were attached to the cage so as to measure the opening of the BDC and movement of the lower end of the BDC. The static loading test was performed in two phases. Phase 1 was performed on May 7, 2015, and consisted of a bi-directional test. In the bidirectional test, the BDC pushes the length above the BDC (the "upper length") upward and the length below (the "lower length") downward. The load increments were 50-kN, each with a 10-minute load-holding time. At the maximum load of 700 kN, the lower length (1.6 m) plunged. No movement occurred at the pile head and the net BDC opening was 60+ mm. 16.4m 13.8m 9.3m 1.8m Strain Gages Strain Gages Ground Surface PILE Strain Gages BDC
  • 3. May 9 2015 Phase 2 test was performed on May 8, 2015. It consisted of leaving the BDC open (free-draining) and performing a head-down test by means of a conventional reaction pile arrangement. The load increments were 100-kN, each with a 10-minute load-holding time. The prediction event deals with Phase 2 test, only. F.y.i., a companion pile, TP2, was constructed on the same day 5 m away from TP1. It was tested as a full-length pile after the tests on TP1. Pile TP2 is not a part of the prediction event. The Soil--CPTU and SPT diagrams The bar in the figure represents the N-indices and the bl/0.3m scale is numerically the same as the qt cone stress, MPa. The SPT was performed with a constant height-of-fall. The soil profile consists of 9 m thick layer of silty fine sand, followed by 6 m of fine sand on sand. A 0.2 m thick clay layer was encountered at 15.0 m depth. The groundwater table is located at 5.0 m depth. The saturated solid densities of the three soil layers are 2,100, 2,000, 2,100 kg/m3 , respectively. The Prediction Submission The primary submission is a prediction of the load-movement of the pile shaft (Phase 2) and the capacity of the shaft, as determined from that same load-movement curve. Submit the values in table showing two columns, one for load (kN) and one for movement (mm). Use at least 8 load-movement points on the curve to the maximum load. Give the evaluated capacity as a separate value. You can use either a Word document or an Excel file. Please submit your prediction to Bengt by e-mail to address: Bengt@Fellenius.net. The submission deadline is noon May 14. 0 5 10 15 20 25 0 10 20 30 40 DEPTH(m) Cone Stress, qt (MPa) 0 5 10 15 20 25 0 100 200 300 400 DEPTH(m) Sleeve Friction, fs (kPa) 0 5 10 15 20 25 0 100 200 300 400 DEPTH(m) Pore Pressure (kPa) 0 5 10 15 20 25 0 1 2 3 4 DEPTH(m) Friction Ratio, fR (%)
  • 4. 2
  • 5. 3
  • 6. Soil Profile 0 5 10 15 20 25 0 10 20 30 40 DEPTH(m) Cone Stress, qt (MPa) 0 5 10 15 20 25 0 100 200 300 400 DEPTH(m) Sleeve Friction, fs (kPa) 0 5 10 15 20 25 0 100 200 300 400 DEPTH(m) Pore Pressure (kPa) 0 5 10 15 20 25 0 1 2 3 4 DEPTH(m) Friction Ratio, fR (%) SPT 4
  • 7. 5 “BDC” = Bidirectional Cell; a sacrificial hydraulic jack 16.4m 13.8m 9.3m 1.8m Strain Gages Strain Gages Ground Surface PILE Strain Gages BDC and telltales
  • 8. 6 Test Programme Phase 1 Activate the BDC to perform a bidirectional test, pushing the upper length upward and the lower length downward. This will create an opening between the two pile lengths. Phase 2 Activate the jack on the pile head to perform a head-down test on the upper pile length with the BDC free-draining The pile will then function in shaft-bearing only with no toe resistance until the BDC opening is closed). Phase 3 If the full resistance of the lower length was not engaged in Phase 1, then , the jack at the pile head will be closed and the BDC be re-engaged (The jack at the pile head will now provide the additional resistance needed).
  • 9. 7 Test Results Phase 1 The bidirectional (BDC) test pushed the lower length downward a distance of abut 60 mm at the 700-kN maximum load---plunging type response. The measurement is approximate, only, due to friction of the telltales in the guide pipes. The pile head showed no movement. Upward movement at the BDC level was small representing the pile shortening for the load.
  • 10. 8 0 1,000 2,000 3,000 4,000 5,000 6,000 0 10 20 30 40 50 60 70 LOAD(kN) MOVEMENT (mm) My Prediction Predictions 0 1,000 2,000 3,000 4,000 5,000 6,000 0 10 20 30 40 50 60 70 LOAD(kN) MOVEMENT (mm) All Predictions Received 0 1,000 2,000 3,000 4,000 5,000 6,000 0 10 20 30 40 50 60 70 LOAD(kN) MOVEMENT (mm) All Predictions Received with Capacity Interpretations The circles are the capacities as interpreted from each curve by the particular predictor
  • 11. Dashed curve is my prediction prepared with full benefit of the results of the 2013 tests on similar piles in very similar soil—hardly Class A . 9 0 1,000 2,000 3,000 4,000 5,000 6,000 0 10 20 30 40 50 60 70 LOAD(kN) MOVEMENT (mm) with Measured Load-Movement
  • 12. 0 500 1,000 1,500 2,000 2,500 3,000 3,500 0 5 10 15 20 25 30 35 LOAD(kN) MOVEMENT (mm) Enlarged View of Predictions and Head-down Test on TP1 Upper Length 10
  • 13. 11 rs = βσ'z z Movement = function of E-modulus rs = f(movement) The pile is assumed made up of a series of short elements, each affected by soil resistance ?WHICH TO USE AND HOW TO MODIFY
  • 14. 12 The t-z functions actually used for the fit
  • 15. 13 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP1 Phase 2 Head-down UniPile Simulation of Test Head-down, Test Load-Movement for the Upper Pile (14.8 m) The final fit
  • 16. 14 y = -0.0026x + 6.7169 0 1 2 3 4 5 6 7 8 0 200 400 600 800 SECANTSTIFFNESS,Q/μԑ(GN) STRAIN (ԑ) TP2 Es (GPa) for zero strain = 23.8 GPa Es (GPa) for 700 μԑ = 17.3 GPa 1.7 m y = -0.0052x + 6.7904 0 1 2 3 4 5 6 7 0 200 400 600 800 TANGENTSTIFFNESS,ΔQ/Δμԑ (GN) STRAIN (ԑ) TP2 Es (GPa) for zero strain = 24.0 GPa Es (GPa) for 700 μԑ = 17.6 GPa 1.7 m The Pile Stiffness (EA) Evaluated from the Uppermost Strain-Gage Unfortunately, the other strain-gages either did not survive the construction or survived, but were dislocated--–No usable strain-gage data were obtained
  • 17. 15 Now the results of Phase 1, the bidirectional test The downward movements are unfortunately impaired due to friction along the telltales 0 500 1,000 1,500 2,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP1 Bidirectional Downward 0 500 1,000 1,500 2,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP1 Bidirectional Downward
  • 18. 16 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP1 Bidirectional Downward Head-down, Test The blue curve is the probable load-movement curve for the lower length; “Downward” Phases 1 and 2 together
  • 19. 17 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP1 Bidirectional Downward Head-down UniPile Simulation of Test Head-down, Test Full Length Head-down UniPile Simulation Combining the results to the load-movement curve for a head-down test on the full length of pile
  • 20. 18 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP2 TP1Compression Head Toe UniPile Simulation Measured The load-movement curves for the head-down test on Pile 2 with a fit (UniPile) to the data and a comparison to same for Pile 1.
  • 21. 19 0 2 4 6 8 10 12 14 16 18 0 1,000 2,000 3,000 4,000DEPTH(m) LOAD (kN) Load Distribution, TP2 From fit to Load- Movement Curve at 5mm elementCPTU E-F SPT Decourt Load distributions at the ≈5-mm element movements for Phase 2 (TP1) combined with the distribution from CPTU and SPT analysis of shaft resistance 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 0 10 20 30 40 50 60 LOAD(kN) MOVEMENT (mm) TP2 TP1Compression Head Toe UniPile Simulation Measured