Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Executive Presentation
on using

Management Dashboards
to support the processes of

Infrastructure, Production, Compliance,
and Recovery Certification
Created by:
Thomas Bronack, CBCP
Phone: (917) 673-6992
Email: bronackt@dcag.com
Web Site: http://www.dcag.com

Created by: Thomas Bronack ©

A Dashboard that acts like a conduit between personnel and
the most current and accurate data. That can drill down to the
actual work being performed and connect you to the person
performing the work. All this from anywhere and at anytime,
thereby reducing the need for conference calls and remote
meetings, with a productivity improvement measured in manmonths.

Page: 1

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

My Last Project was world-wide and extensive
Phase I
Inventory

Bid

•
•
•
•
•
•
•

RFP;
Bid;
SOW;
Project Plan;
Scope;
Goals and
Timeframe

Phase II

Phase III

Build Regionals

Transition

Phase IV

What they Have;
Infrastructure;
Equipment;
Software;
Applications;
Locations;
Computer Sites;
Recovery Sites;
Applications with
Recovery Plans; and
• Applications that need
Recovery Plans.

Created by: Thomas Bronack ©

Phase VI

Build Recovery Disaster Recovery

Recovery
Site

• Prod 1;
• Prod 2;
• Prod 3.

•
•
•
•
•
•
•
•
•

Phase V

• Move Resources
and Applications
to Regional Data
Center;
• Test Successful
Operation;
• Define Recovery
Site resources;
• Virtualize;
• Prove successful
recovery from
Production to
old Recovery
Site.

Page: 2

•
•
•
•
•
•
•
•
•
•

•
•
•
•

“Proof of Concept”;
Infrastructure Readiness;
Disaster Recovery;
Application Recovery;
Business Recovery;
Workplace Safety and
Violence Prevention;
Emergency Management;
Crisis Management;
Protection, Salvage, and
Restoration;
Supply Chain
Management;
Insurance;
Community Relations;
Communications; and
Use of Social Media.

Compliance

• Laws and Regulations;
• Requirements to
Comply with;
• Present Compliance;
• Gaps & Exceptions;
• Obstacles;
• Domestic;
• International; and
• Cross Border
Requirements.

As you can see, every
step of this project
required lots of data and
many forms, which
resulted in a loss of
productivity measured
in Man-Months.

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992

What the Problem is
•

Paper, Paper, Paper
•

To much information, and unfortunately most of it is out-of-date, inaccurate, and extremely difficult
to find.

•

People lost confidence in the documents they dealt with.

•

Delays, confusion, chaos, and loss productivity was measured in man-months.

•

When important decisions needed to be made, management and personnel were not able to access
what they needed from any location at anytime.

•

Too much time was spent in conference calls and remote meetings and not enough time performing
assigned functions.

•

A better way to handle documentation and work flow was needed.

•

From the first time a service is requested to its implementation and recovery, everybody has
to be able to manage their responsibilities better.

•

This Dashboard covers the areas of:
•

Systems Development Life Cycle (SDLC);

•

Asset Management and Infrastructure;

•

Production Operations, Vital Records Management, Access Controls, and Support; and,

•

Recovery Management and Compliance.

Created by: Thomas Bronack ©

Page: 3

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

What is the Resolution
•

Provide Management with Dashboards having Drill-Down capabilities:
•

•

Infrastructure;

•

Systems Development Life Cycle (SDLC);

•

Production:

•

Recovery Management; and,

•

•

Executive Dashboard;

Compliance.

Accomplished through Enterprise Resiliency and Corporate Certification:
•

Enterprise Resiliency combines all Recovery Discipline under one Department’s control;

•

Corporate Certification guarantee’s adherence to all required Laws and Regulations in the
countries that your company conducts business;

•

Utilize a “Work Order (WO)” and “Purchase Order (PO)” mechanism;

•

Forms Management and Control is included to provide forms and track them through their Life
Cycle until completion, allowing access to the individual performing a task at any time and
from any authorized terminal anywhere;

•

Personnel Training, Career Path assistance, and Performance Management; and

•

Charge-Back system to allow for the comparison of new projects against previously performed
projects, so that effort and cost can be compared better estimated.

Created by: Thomas Bronack ©

Page: 4

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Why I developed the Dashboards
•

Project was slipping its schedule and we were losing productivity in ManMonths;

•

Too much time spent in Conference Calls and Remote Meetings, where
people had inaccurate data or forms;

•

Confusion was rampant and nobody trusted the literature, which
affected the status reporting and delivery schedule;

•

Management was getting very upset because they were not receiving
straight answers or could not examine project data directly;

•

Costs were getting out of hand and work flow tracking was not being
performed;

•

There was no way to improve efficiency following the current path; and,

•

The company and its reputation were in great peril because the final goal
of having a virtual environment that could recovery all Tiers (CA, HA, Best
Effort) of applications was no where in sight.

Created by: Thomas Bronack ©

Page: 5

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Utilizing Dashboards
• Guaranty Accurate and
Current Data;
• Viewable from any location at
any time;
• Reduce the need for many
conference calls and remote
meetings;
• Improves efficiency;
• Reduces Costs.

CRUD Access:
• Create;
• Read;
• Update; and,
• Delete

People

Libraries

Dashboard

Data

Keeping data current and accurate

• Providing a Dashboard between personnel and data will insure that current data is
being displayed when needed;
• View data at remote meetings and conference calls from anywhere at anytime;
• Allowing for data to be updated as appropriate during meetings and then saving the
updated data via Version and Release Management Guidelines will insure that all data
is in sync and improve confidence in data accuracy and currency;
• Allow Drill-Down to current activity for the task being performed;
• Provide direct connection to person performing the actual task (i.e., Name, Title,
Phone, Email, and IM for instant messages and screen viewing – Outlook based); and,
• Most efficient method for coordinating project and real-time activities.
Created by: Thomas Bronack ©

Page: 6

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Building Dashboards for everything
Dashboards
Forms Management
And Control System

Repository of Project
Related Materials

Front-End
To Data
Base
System

Front-End
To
Repository
System

Repositories
Data Base for
Forms
Management
and Control

Repository of
Flat Files used
to provide
project
information

All Company Forms,
with Help and Data
Entry Validation

All Company Project
Related Documents
with Version & Release
Management

Users can access the information at anytime and from anywhere, reducing the need for remote meeting and conference calls. Information can be
drilled-down to actual task being performed and connect you with the person doing the work (IM, Name, Phone, Email, etc.). Only authorized
personnel can update information, but everybody can access it, which allows for current and accurate information to be available upon demand.
Created by: Thomas Bronack ©

Page: 7

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

How do we get there
•

Start with defining your SDLC and all forms used within the system:
•
•

Create a Mechanism to help personnel select the right Form for what they have to do which will
insure that all Forms are of the same type and format and facilitate your being able to develop
metrics based on the information contained in Forms;

•

Make sure all Forms have a “Help Screen” to explain their use and meaning;

•

Use “Field Validation Rules” to make sure all required data is entered correctly;

•

Insure that a Forms Tracking System is used from Origination through Completion; and

•

•

Implement a Forms Management and Control System;

Utilize Performance Management to monitor work duration between estimated and actual.

Integrate this system with:
•

Asset Management (Inventory, Configuration, Infrastructure, Personnel, etc.);

•

Production Operations (OCC, Library Management, Access Controls, Back-up, etc.);

•

Utilize VMware type products to support Code Level Upgrades, Testing, and Recovery Management
as part of the SDLC Test Phase to insure production is not interrupted;

•

Insure that Version and Release Management guidelines are adhered to in order to guaranty that
documentation is at the same level as the products being delivered;

•

Provide personnel with Orientation, Awareness, Training, Certification, and Career Path support;
and,

•

Connect all current and accurate information to Dashboards for easy access and management.

Created by: Thomas Bronack ©

Page: 8

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Now what do we have to do?
•

Systems Development Life Cycle;

•

Systems Management Organization;

•

Work Order / Purchase Order Flow and Charge-Back System;

•

Enterprise Resiliency and Corporate Certification;

•

Executive Dashboard;

•

Dashboard Relationships and Drill-Down capabilities;;

•

Working Example of a current Dashboard used to support Application Recovery
Certification Management (already completed);

•

Personnel Productivity and Training System;

•

Utilizing VMware, vSphere, vConnect, and Recovery Point Application to support
rapid recovery in support of critical applications and sites;

•

Integration within the Enterprise Environment;

•

Support Organization, with Command Centers interfacing;

•

Responding to Disaster Events in support of Business Continuity; and,

•

Benefits to be gained through this approach.

Created by: Thomas Bronack ©

Page: 9

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Executive Dashboard
Executive
Dashboard

Systems Development
Life Cycle

Infrastructure
Dashboard

Operations
Dashboard

Recovery
Dashboard

Asset Management

Vital Records,
Access Controls

Disaster Planning

Production

Job Processing

DR Certification

Development

Verify Success and
Performance

Audit Compliance

Maintenance

Support

Disaster
Declaration

Test, QA, Accept

Status Reporting

Business Continuity

Created by: Thomas Bronack ©

Page: 10

Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Infrastructure Dashboard
Infrastructure
Dashboard

Asset
Management
•
•
•

•
•
•
•

Acquisition;
Redeployment;
Termination;
• Clean;
• Donate;
• Sell;
• Disposal.
Inventory
Management;
Configuration
Management;
Finance; and,
Accounting.

Created by: Thomas Bronack ©

Engineering
Management

•
•
•
•
•
•
•
•

Service Request;
Business / Technical
Service Objectives;
Design Objectives;
Schedule / Priority;
Design Document;
Implementation Plan;
Support, Maintenance
and Enhancements;
Design Changes; and,
Change Management
with Version and Release
Management guidelines.
Page: 11

Recovery
Management
•
•
•
•
•
•
•
•
•

Project Initiation and
Controls;
Service / Application
Selection;
Planning Session;
Infrastructure Readiness
(Recovery Site Resources
and Data Synchronization);
Pre-Test (Recovery site setup);
Actual Test (Application Run
Book);
Post Mortem Meeting;
Certification (Y/N); and,
Selected Improvements
added.
Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Asset Management Lifecycle Dashboard
Assets can be: People, Equipment, Locations, or any resources that goes through an Acquisition, Redeployment, Termination
cycle (which is most everything in your company). Tying them together into a WO/PO fashion allows tracking.
Asset Management Lifecycle Dashboard
Work Order:
Owner WO #:

PO #:

Category:

Function:

Resource PO #:

Acquisition:

Order:
Y/N

Owner WO #:

Resource PO #:

Owner WO #:

Resource PO #:

Reployment: Clean (Company):
Y/N
Y/N
Y/N
Y/N

Termination:
Donation
Sale
Disposal
Redeploy

Clean (DoD):
Y/N
Y/N
Y/N
Y/N

Design:

Technical:

Asset Lifecycle Phase

Architecture:
Engineering:
System Design Equipment

Ordering:
Vendor

Receiving:
Date

Infrastructure:
Inventory:
Install
Add Entry

Configuration:
Location:
Add Entry
Installed at

Finance:
Costs

Accounting:
Charge to

Architecture:
System Design
System Design
System Design
System Design

Engineering:
Equipment
Equipment
Equipment
Equipment

Ordering:
Vendor
Vendor
Vendor
Vendor

Receiving:
Date
Date
Date
Date

Infrastructure:
Uninstall
Warehouse
Move
Install

Inventory:
Update Entry
Update Entry
Update Entry
Update Entry

Configuration:
Update Entry
Update Entry
Update Entry
Update Entry

Location:
Update Entry
Update Entry
Update Entry
Update Entry

Finance:
Costs
Costs
Costs
Costs

Accounting:
Charge to
Charge to
Charge to
Charge to

Architecture:
System Design
System Design
System Design
System Design

Engineering:
Equipment
Equipment
Equipment
Equipment

Ordering:
Vendor
Vendor
Vendor
Vendor

Receiving:
Date
Date
Date
Date

Infrastructure:
Uninstall
Warehouse
Move
Move

Inventory:
Add Entry
Add Entry
Add Entry
Add Entry

Configuration:
Add Entry
Add Entry
Add Entry
Add Entry

Location:
Installed at
Installed at
Installed at
Installed at

Finance:
Costs
Costs
Costs
Costs

Accounting:
Charge to
Charge to
Charge to
Charge to

•

Tracks Asset from Acquisition, through Redeployment, and Termination;

•

Relates activity to Work Order (WO) and Purchase Order (PO) to facilitate cost
accounting;

•

Defines Resources as Owned, Leased, Rented, Employee, Vendor, or Contractor for
account and finance;

•

Interfaces with Users, Resources, Locations, Finance, and Accounting; and,

•

Provides easy tracking of required resources to determine their impact of delivery
schedules.

Created by: Thomas Bronack ©

Page: 12

Date: 1/31/2014
Recovery Dashboards

Executive

Recovery Plans
Training Materials

Steering Committee
Management
EOC, CCC, and
DR Teams

Status
Reporting

DR Planning and
Activation Dashboard

Executive Management Dashboard
on DR Planning and Activation

Application Recovery
Certification Dashboard

Library
Management

Articles
Standards and
Procedures

Business Location Recovery
Dashboard

Recovery
Planning (7
Phases, each
with 13 Steps)

Statement of
Work (SOW)
Business /
Project Plan

Recovery Site
Preparation

Application
Selection
Procedures

Business
Recovery Site

Workplace
Safety and
Violence
Prevention

Risk Analysis
and Insurance
Profile

Dedicated
BCM
Organization

Actual DR
Test, or
Activation

VMware,
vSphere,
vConnect, and
RPA

Building
Evacuation Plan

OSHA,OEM,
FEMA & Building
Codes

Audit, Legal,
and
Compliance
Requirements

Long-Term
Management
Commitment

Post Mortem
Meeting

Failover /
Failback for
HA
Applications

Business
Recovery &
Resumption Plan

First Responders
and Government
Agencies

SDLC, Integration,
and Version &
Release
Management

Created by: Thomas Bronack ©

Flip / Flop for
CA
Applications

Page: 13

Site Protection,
Salvage, &
Restoration

Date: 1/31/2014

RFP’s / Bid’s

SOW / Project Plans
Business Plan
Performance
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

Tracking Active Disaster Recovery Events – Drill Down Actions
“Top Level” – Enterprise Resiliency and Corporate Certification Dashboard
Phase VI - Initiate Recovery Plan when Disaster Event Occurs
Help Desk
Help Desk
Contingency
Failing Site
Recovery
Team is Called
Recovery
Identifies Disaster
Notifies
Coordinator
Protection, Disaster Site is
Operations are
and Recovery
Personnel are
Event or a Disaster Contingency
Declares
Salvage, and Evacuated, as
Initiated and
Tasks
Transferred to
Event is reported to Recovery Plan Disaster and
Restoration is
needed
Conducted for
Performed
Recovery Site
Help Desk
Coordinator Initiates Plan
Initiated
Life of Disaster

Failing Site is
Salvaged and
Restored

Personnel
Return to
Original Site
and Resume
Production

Recovery Steps
Post Mortem Improvements
are added to
is Conducted
are
Testing Process
and
Incorporated in
and
Improvement
Future
Periodicically
s Identified Recovery Plans
Repeated

“Sub Level”
“Activity Level”
“Action Item
Level”

DR Planning Action Items
Number: Status:

Action Item Description:

Priority:

Assigned to:

Due Date:

Actions Taken:

Comments:

“Management &
Control Level”
Created by: Thomas Bronack ©

Page: 14

Contingency
Command
Center (CCC)

Emergency
Operations
Center (EOC)
Date: 1/31/2014
Optimizing the IT and Business Environment through Dashboards

bronackt@dcag.com / (917) 673-6992

How Dashboards Help
• Improved efficiency by providing instant access to current and accurate information
from any authorized terminal or personal computer, at anytime from anyplace;
• Drill-Down capability allows viewer to get to actual task being performed and be
provided with the contact information for the person performing the task;

• Less time spent reviewing out-of-date or inaccurate information reduces chaos;
• Improved time frame for completing projects due to fewer remote meetings;
• Reduced costs associated with implementing projects due to fewer conference calls
and more time to devote to actual work;
• Better protection to the company reputation;
• More highly trained staff with an improved morale, that are easier to retain and aid
in the ability to recruit additional staff and new clients;
• Adherence to the laws and regulations where the company conducts business; and,
• Less stress and better performance helps everyone do their job better.
Created by: Thomas Bronack ©

Page: 15

Date: 1/31/2014
The Next Step
 If you believe that this approach can help your company improve performance
and bring products and services to market more rapidly, then contact Thomas
Bronack at:
 Thomas Bronack
 Phone: (917) 673-6992
 Email: bronackt@dcag.com

 We would love to assist you in integrating our approach within your
environment.
 Remember, our approach uses your existing data so you do not have to change
information to adopt to our product.

More Related Content

What's hot

T3 Consortium's Performance Center of Excellence
T3 Consortium's Performance Center of ExcellenceT3 Consortium's Performance Center of Excellence
T3 Consortium's Performance Center of Excellenceveehikle
 
Performance And Scale In Cloud Computing
Performance And Scale In Cloud ComputingPerformance And Scale In Cloud Computing
Performance And Scale In Cloud Computingdmasciorini
 
Performance And Scale In Cloud Computing 1
Performance And Scale In Cloud Computing 1Performance And Scale In Cloud Computing 1
Performance And Scale In Cloud Computing 1Scott Herson
 
Performance and scale in cloud
Performance and scale in cloudPerformance and scale in cloud
Performance and scale in cloudjeffgaris
 
Summary of Skills and Projects
Summary of Skills and ProjectsSummary of Skills and Projects
Summary of Skills and ProjectsCory Larsen
 
Help desk assessment report.x10
Help desk assessment report.x10Help desk assessment report.x10
Help desk assessment report.x10rajanam
 
Test Data Management: A Healthcare Industry Case Study
Test Data Management: A Healthcare Industry Case StudyTest Data Management: A Healthcare Industry Case Study
Test Data Management: A Healthcare Industry Case StudyTechWell
 
Ian Butler - Resume 2015
Ian Butler - Resume 2015Ian Butler - Resume 2015
Ian Butler - Resume 2015Ian Butler
 
Automating End-to-End Business Scenario Testing
Automating End-to-End Business Scenario TestingAutomating End-to-End Business Scenario Testing
Automating End-to-End Business Scenario TestingTechWell
 
f5-reference-architecture-for-vmware-nsx
f5-reference-architecture-for-vmware-nsxf5-reference-architecture-for-vmware-nsx
f5-reference-architecture-for-vmware-nsxNathan Pearce
 
Challenges in deploying AX 2012: A recipe for success!
Challenges in deploying AX 2012: A recipe for success!Challenges in deploying AX 2012: A recipe for success!
Challenges in deploying AX 2012: A recipe for success!Optimum Technology Transfer
 
SaaS PPM – How Do You Know When It’s Right for You?
SaaS PPM – How Do You Know When It’s Right for You?SaaS PPM – How Do You Know When It’s Right for You?
SaaS PPM – How Do You Know When It’s Right for You?EPM Live
 
RiskManagementPlanFinal1.3
RiskManagementPlanFinal1.3RiskManagementPlanFinal1.3
RiskManagementPlanFinal1.3Fahad Saleem
 
PeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and Planning
PeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and PlanningPeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and Planning
PeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and PlanningArvind Rajan
 
Digicom competency pool telecom-vas - ver 1-02
Digicom competency pool   telecom-vas - ver 1-02Digicom competency pool   telecom-vas - ver 1-02
Digicom competency pool telecom-vas - ver 1-02ajeeshch
 

What's hot (19)

T3 Consortium's Performance Center of Excellence
T3 Consortium's Performance Center of ExcellenceT3 Consortium's Performance Center of Excellence
T3 Consortium's Performance Center of Excellence
 
Performance And Scale In Cloud Computing
Performance And Scale In Cloud ComputingPerformance And Scale In Cloud Computing
Performance And Scale In Cloud Computing
 
Performance And Scale In Cloud Computing 1
Performance And Scale In Cloud Computing 1Performance And Scale In Cloud Computing 1
Performance And Scale In Cloud Computing 1
 
Performance and scale in cloud
Performance and scale in cloudPerformance and scale in cloud
Performance and scale in cloud
 
Summary of Skills and Projects
Summary of Skills and ProjectsSummary of Skills and Projects
Summary of Skills and Projects
 
Help desk assessment report.x10
Help desk assessment report.x10Help desk assessment report.x10
Help desk assessment report.x10
 
Test Data Management: A Healthcare Industry Case Study
Test Data Management: A Healthcare Industry Case StudyTest Data Management: A Healthcare Industry Case Study
Test Data Management: A Healthcare Industry Case Study
 
Ian Butler - Resume 2015
Ian Butler - Resume 2015Ian Butler - Resume 2015
Ian Butler - Resume 2015
 
Automating End-to-End Business Scenario Testing
Automating End-to-End Business Scenario TestingAutomating End-to-End Business Scenario Testing
Automating End-to-End Business Scenario Testing
 
CERTIFIED DATA CENTRE EXPERT
CERTIFIED DATA CENTRE EXPERTCERTIFIED DATA CENTRE EXPERT
CERTIFIED DATA CENTRE EXPERT
 
Cutover Plan V2
Cutover Plan V2Cutover Plan V2
Cutover Plan V2
 
f5-reference-architecture-for-vmware-nsx
f5-reference-architecture-for-vmware-nsxf5-reference-architecture-for-vmware-nsx
f5-reference-architecture-for-vmware-nsx
 
Mortgage Stability 20120420
Mortgage Stability 20120420Mortgage Stability 20120420
Mortgage Stability 20120420
 
Challenges in deploying AX 2012: A recipe for success!
Challenges in deploying AX 2012: A recipe for success!Challenges in deploying AX 2012: A recipe for success!
Challenges in deploying AX 2012: A recipe for success!
 
SaaS PPM – How Do You Know When It’s Right for You?
SaaS PPM – How Do You Know When It’s Right for You?SaaS PPM – How Do You Know When It’s Right for You?
SaaS PPM – How Do You Know When It’s Right for You?
 
RiskManagementPlanFinal1.3
RiskManagementPlanFinal1.3RiskManagementPlanFinal1.3
RiskManagementPlanFinal1.3
 
ReddiS
ReddiSReddiS
ReddiS
 
PeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and Planning
PeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and PlanningPeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and Planning
PeopleSoft 9.2 Webinar Series - Part 1 - Upgrade Roadmap and Planning
 
Digicom competency pool telecom-vas - ver 1-02
Digicom competency pool   telecom-vas - ver 1-02Digicom competency pool   telecom-vas - ver 1-02
Digicom competency pool telecom-vas - ver 1-02
 

Viewers also liked

Developing a Dashboard to Aid in Effective Project Management
Developing a Dashboard to Aid in Effective Project ManagementDeveloping a Dashboard to Aid in Effective Project Management
Developing a Dashboard to Aid in Effective Project Managementsimienc
 
Telelogic Dashboard Presentation
Telelogic Dashboard PresentationTelelogic Dashboard Presentation
Telelogic Dashboard PresentationBill Duncan
 
Program Management Dashboards
Program Management DashboardsProgram Management Dashboards
Program Management DashboardsBob Prieto
 
Microsoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formulaMicrosoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formulaNR Computer Learning Center
 
Management Dashboard Sample
Management Dashboard SampleManagement Dashboard Sample
Management Dashboard SampleR P
 
Dashboard For Enterprise Architects
Dashboard For Enterprise ArchitectsDashboard For Enterprise Architects
Dashboard For Enterprise ArchitectsJörgen Dahlberg
 
Planning Your Dashboard Project
Planning Your Dashboard ProjectPlanning Your Dashboard Project
Planning Your Dashboard ProjectJessica Hoopfer
 
SAP BOBJ Enterprise Dashboard - Sales Plan, Pipeline and Forecast
SAP BOBJ Enterprise Dashboard -  Sales Plan, Pipeline and ForecastSAP BOBJ Enterprise Dashboard -  Sales Plan, Pipeline and Forecast
SAP BOBJ Enterprise Dashboard - Sales Plan, Pipeline and ForecastJothi Periasamy
 
Demand Metric - Playbooks
Demand Metric - PlaybooksDemand Metric - Playbooks
Demand Metric - PlaybooksJesse Hopps
 
ERP System Development Plan
ERP System Development PlanERP System Development Plan
ERP System Development PlanSri Jayasinghe
 
Effective Dashboard Design: Why Your Baby is Ugly
Effective Dashboard Design: Why Your Baby is UglyEffective Dashboard Design: Why Your Baby is Ugly
Effective Dashboard Design: Why Your Baby is UglyAaron Hursman
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectRelu Rosenberg
 

Viewers also liked (12)

Developing a Dashboard to Aid in Effective Project Management
Developing a Dashboard to Aid in Effective Project ManagementDeveloping a Dashboard to Aid in Effective Project Management
Developing a Dashboard to Aid in Effective Project Management
 
Telelogic Dashboard Presentation
Telelogic Dashboard PresentationTelelogic Dashboard Presentation
Telelogic Dashboard Presentation
 
Program Management Dashboards
Program Management DashboardsProgram Management Dashboards
Program Management Dashboards
 
Microsoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formulaMicrosoft project 2010 creating customized field with image & formula
Microsoft project 2010 creating customized field with image & formula
 
Management Dashboard Sample
Management Dashboard SampleManagement Dashboard Sample
Management Dashboard Sample
 
Dashboard For Enterprise Architects
Dashboard For Enterprise ArchitectsDashboard For Enterprise Architects
Dashboard For Enterprise Architects
 
Planning Your Dashboard Project
Planning Your Dashboard ProjectPlanning Your Dashboard Project
Planning Your Dashboard Project
 
SAP BOBJ Enterprise Dashboard - Sales Plan, Pipeline and Forecast
SAP BOBJ Enterprise Dashboard -  Sales Plan, Pipeline and ForecastSAP BOBJ Enterprise Dashboard -  Sales Plan, Pipeline and Forecast
SAP BOBJ Enterprise Dashboard - Sales Plan, Pipeline and Forecast
 
Demand Metric - Playbooks
Demand Metric - PlaybooksDemand Metric - Playbooks
Demand Metric - Playbooks
 
ERP System Development Plan
ERP System Development PlanERP System Development Plan
ERP System Development Plan
 
Effective Dashboard Design: Why Your Baby is Ugly
Effective Dashboard Design: Why Your Baby is UglyEffective Dashboard Design: Why Your Baby is Ugly
Effective Dashboard Design: Why Your Baby is Ugly
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms Project
 

Similar to Utilizing Dashboards to improve efficiency

Intranet Solutions_IT
Intranet Solutions_ITIntranet Solutions_IT
Intranet Solutions_ITGene Ferro
 
Resume JOYCE CONRAD_0416CRM
Resume JOYCE CONRAD_0416CRMResume JOYCE CONRAD_0416CRM
Resume JOYCE CONRAD_0416CRMJoyce Conrad
 
Marc Cadden IT PM 3
Marc Cadden IT PM 3Marc Cadden IT PM 3
Marc Cadden IT PM 3Marc Cadden
 
Frank Presto resume 7-31-16
Frank Presto resume 7-31-16Frank Presto resume 7-31-16
Frank Presto resume 7-31-16Frank Presto
 
Whitepaper: Datacenter Migration - Happiest Minds
Whitepaper: Datacenter Migration - Happiest MindsWhitepaper: Datacenter Migration - Happiest Minds
Whitepaper: Datacenter Migration - Happiest MindsHappiest Minds Technologies
 
Cox alexa resume 052516
Cox alexa resume 052516 Cox alexa resume 052516
Cox alexa resume 052516 Alexa Cox
 
Managing Enterprise Content: Solutions that Fit Your Unique Needs
Managing Enterprise Content: Solutions that Fit Your Unique NeedsManaging Enterprise Content: Solutions that Fit Your Unique Needs
Managing Enterprise Content: Solutions that Fit Your Unique NeedsTy Alden Cole
 
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...ssuser835d1a
 
Sachie Thorne business resume
Sachie Thorne business resumeSachie Thorne business resume
Sachie Thorne business resumeSachie Thorne
 
How a government organization created a central hub to automate administrativ...
How a government organization created a central hub to automate administrativ...How a government organization created a central hub to automate administrativ...
How a government organization created a central hub to automate administrativ...Alain Bezançon
 
Victor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby
 
Arindam_Kuila_Resume
Arindam_Kuila_ResumeArindam_Kuila_Resume
Arindam_Kuila_ResumeArindam Kuila
 
Introducing Robert Driskell
Introducing Robert Driskell Introducing Robert Driskell
Introducing Robert Driskell Robert Driskell
 

Similar to Utilizing Dashboards to improve efficiency (20)

Aron Morgulis resume
Aron Morgulis resumeAron Morgulis resume
Aron Morgulis resume
 
Intranet Solutions_IT
Intranet Solutions_ITIntranet Solutions_IT
Intranet Solutions_IT
 
Resume JOYCE CONRAD_0416CRM
Resume JOYCE CONRAD_0416CRMResume JOYCE CONRAD_0416CRM
Resume JOYCE CONRAD_0416CRM
 
Kenneth M. Fischler
Kenneth M. FischlerKenneth M. Fischler
Kenneth M. Fischler
 
Marc Cadden IT PM 3
Marc Cadden IT PM 3Marc Cadden IT PM 3
Marc Cadden IT PM 3
 
Ryan Stewart CV
Ryan Stewart CVRyan Stewart CV
Ryan Stewart CV
 
Frank Presto resume 7-31-16
Frank Presto resume 7-31-16Frank Presto resume 7-31-16
Frank Presto resume 7-31-16
 
Whitepaper: Datacenter Migration - Happiest Minds
Whitepaper: Datacenter Migration - Happiest MindsWhitepaper: Datacenter Migration - Happiest Minds
Whitepaper: Datacenter Migration - Happiest Minds
 
Kevin Sherrard resume
Kevin Sherrard resumeKevin Sherrard resume
Kevin Sherrard resume
 
Himmelrich 8-2015
Himmelrich 8-2015Himmelrich 8-2015
Himmelrich 8-2015
 
Cox alexa resume 052516
Cox alexa resume 052516 Cox alexa resume 052516
Cox alexa resume 052516
 
Managing Enterprise Content: Solutions that Fit Your Unique Needs
Managing Enterprise Content: Solutions that Fit Your Unique NeedsManaging Enterprise Content: Solutions that Fit Your Unique Needs
Managing Enterprise Content: Solutions that Fit Your Unique Needs
 
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
 
Kamal Resume
Kamal ResumeKamal Resume
Kamal Resume
 
Sachie Thorne business resume
Sachie Thorne business resumeSachie Thorne business resume
Sachie Thorne business resume
 
How a government organization created a central hub to automate administrativ...
How a government organization created a central hub to automate administrativ...How a government organization created a central hub to automate administrativ...
How a government organization created a central hub to automate administrativ...
 
Victor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby - Project Manger
Victor Holderby - Project Manger
 
SPGregory_Resume
SPGregory_ResumeSPGregory_Resume
SPGregory_Resume
 
Arindam_Kuila_Resume
Arindam_Kuila_ResumeArindam_Kuila_Resume
Arindam_Kuila_Resume
 
Introducing Robert Driskell
Introducing Robert Driskell Introducing Robert Driskell
Introducing Robert Driskell
 

More from Thomas Bronack

Enterprise resiliency and world-wide compliance, in-depth article.
Enterprise resiliency and world-wide compliance, in-depth article.Enterprise resiliency and world-wide compliance, in-depth article.
Enterprise resiliency and world-wide compliance, in-depth article.Thomas Bronack
 
Optimizing the IT and Business Environment
Optimizing the IT and Business EnvironmentOptimizing the IT and Business Environment
Optimizing the IT and Business EnvironmentThomas Bronack
 
Dcag service optimization offering01
Dcag service optimization offering01Dcag service optimization offering01
Dcag service optimization offering01Thomas Bronack
 
Recovery and Compliance Services provided by Tom Bronack
Recovery and Compliance Services provided by Tom BronackRecovery and Compliance Services provided by Tom Bronack
Recovery and Compliance Services provided by Tom BronackThomas Bronack
 
Auditing contingency Plans
Auditing contingency PlansAuditing contingency Plans
Auditing contingency PlansThomas Bronack
 
Equipment Redeployment and Termination Procedures
Equipment Redeployment and Termination ProceduresEquipment Redeployment and Termination Procedures
Equipment Redeployment and Termination ProceduresThomas Bronack
 
Article on Emergency Management and Corporate Certification
Article on Emergency Management and Corporate CertificationArticle on Emergency Management and Corporate Certification
Article on Emergency Management and Corporate CertificationThomas Bronack
 
Updated Healthcare Industry Compliance Presentation
Updated Healthcare Industry Compliance PresentationUpdated Healthcare Industry Compliance Presentation
Updated Healthcare Industry Compliance PresentationThomas Bronack
 
Smaller Presentation on Enterprise Resiliency and Corporate Certification
Smaller Presentation on Enterprise Resiliency and Corporate CertificationSmaller Presentation on Enterprise Resiliency and Corporate Certification
Smaller Presentation on Enterprise Resiliency and Corporate CertificationThomas Bronack
 
Exec Presentation on Achieving Enterprise Resiliency and Corporate Certification
Exec Presentation on Achieving Enterprise Resiliency and Corporate CertificationExec Presentation on Achieving Enterprise Resiliency and Corporate Certification
Exec Presentation on Achieving Enterprise Resiliency and Corporate CertificationThomas Bronack
 
Executive Presentation on adhering to Healthcare Industry compliance
Executive Presentation on adhering to Healthcare Industry complianceExecutive Presentation on adhering to Healthcare Industry compliance
Executive Presentation on adhering to Healthcare Industry complianceThomas Bronack
 
Personnel Productivity System - Updated 6-6-2013
Personnel Productivity System - Updated 6-6-2013Personnel Productivity System - Updated 6-6-2013
Personnel Productivity System - Updated 6-6-2013Thomas Bronack
 
Achieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate CertificationAchieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate CertificationThomas Bronack
 
Asset Management (Acquisition, Redeployment, and Termination)(
Asset Management (Acquisition, Redeployment, and Termination)(Asset Management (Acquisition, Redeployment, and Termination)(
Asset Management (Acquisition, Redeployment, and Termination)(Thomas Bronack
 
Application migration guideline document
Application migration guideline documentApplication migration guideline document
Application migration guideline documentThomas Bronack
 
Tape vaulting audit and encryption usage analysis
Tape vaulting audit and encryption usage analysisTape vaulting audit and encryption usage analysis
Tape vaulting audit and encryption usage analysisThomas Bronack
 
Achieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate CertificationAchieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate CertificationThomas Bronack
 

More from Thomas Bronack (17)

Enterprise resiliency and world-wide compliance, in-depth article.
Enterprise resiliency and world-wide compliance, in-depth article.Enterprise resiliency and world-wide compliance, in-depth article.
Enterprise resiliency and world-wide compliance, in-depth article.
 
Optimizing the IT and Business Environment
Optimizing the IT and Business EnvironmentOptimizing the IT and Business Environment
Optimizing the IT and Business Environment
 
Dcag service optimization offering01
Dcag service optimization offering01Dcag service optimization offering01
Dcag service optimization offering01
 
Recovery and Compliance Services provided by Tom Bronack
Recovery and Compliance Services provided by Tom BronackRecovery and Compliance Services provided by Tom Bronack
Recovery and Compliance Services provided by Tom Bronack
 
Auditing contingency Plans
Auditing contingency PlansAuditing contingency Plans
Auditing contingency Plans
 
Equipment Redeployment and Termination Procedures
Equipment Redeployment and Termination ProceduresEquipment Redeployment and Termination Procedures
Equipment Redeployment and Termination Procedures
 
Article on Emergency Management and Corporate Certification
Article on Emergency Management and Corporate CertificationArticle on Emergency Management and Corporate Certification
Article on Emergency Management and Corporate Certification
 
Updated Healthcare Industry Compliance Presentation
Updated Healthcare Industry Compliance PresentationUpdated Healthcare Industry Compliance Presentation
Updated Healthcare Industry Compliance Presentation
 
Smaller Presentation on Enterprise Resiliency and Corporate Certification
Smaller Presentation on Enterprise Resiliency and Corporate CertificationSmaller Presentation on Enterprise Resiliency and Corporate Certification
Smaller Presentation on Enterprise Resiliency and Corporate Certification
 
Exec Presentation on Achieving Enterprise Resiliency and Corporate Certification
Exec Presentation on Achieving Enterprise Resiliency and Corporate CertificationExec Presentation on Achieving Enterprise Resiliency and Corporate Certification
Exec Presentation on Achieving Enterprise Resiliency and Corporate Certification
 
Executive Presentation on adhering to Healthcare Industry compliance
Executive Presentation on adhering to Healthcare Industry complianceExecutive Presentation on adhering to Healthcare Industry compliance
Executive Presentation on adhering to Healthcare Industry compliance
 
Personnel Productivity System - Updated 6-6-2013
Personnel Productivity System - Updated 6-6-2013Personnel Productivity System - Updated 6-6-2013
Personnel Productivity System - Updated 6-6-2013
 
Achieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate CertificationAchieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate Certification
 
Asset Management (Acquisition, Redeployment, and Termination)(
Asset Management (Acquisition, Redeployment, and Termination)(Asset Management (Acquisition, Redeployment, and Termination)(
Asset Management (Acquisition, Redeployment, and Termination)(
 
Application migration guideline document
Application migration guideline documentApplication migration guideline document
Application migration guideline document
 
Tape vaulting audit and encryption usage analysis
Tape vaulting audit and encryption usage analysisTape vaulting audit and encryption usage analysis
Tape vaulting audit and encryption usage analysis
 
Achieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate CertificationAchieving Enterprise Resiliency and Corporate Certification
Achieving Enterprise Resiliency and Corporate Certification
 

Recently uploaded

Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 

Recently uploaded (20)

Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 

Utilizing Dashboards to improve efficiency

  • 1. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Executive Presentation on using Management Dashboards to support the processes of Infrastructure, Production, Compliance, and Recovery Certification Created by: Thomas Bronack, CBCP Phone: (917) 673-6992 Email: bronackt@dcag.com Web Site: http://www.dcag.com Created by: Thomas Bronack © A Dashboard that acts like a conduit between personnel and the most current and accurate data. That can drill down to the actual work being performed and connect you to the person performing the work. All this from anywhere and at anytime, thereby reducing the need for conference calls and remote meetings, with a productivity improvement measured in manmonths. Page: 1 Date: 1/31/2014
  • 2. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 My Last Project was world-wide and extensive Phase I Inventory Bid • • • • • • • RFP; Bid; SOW; Project Plan; Scope; Goals and Timeframe Phase II Phase III Build Regionals Transition Phase IV What they Have; Infrastructure; Equipment; Software; Applications; Locations; Computer Sites; Recovery Sites; Applications with Recovery Plans; and • Applications that need Recovery Plans. Created by: Thomas Bronack © Phase VI Build Recovery Disaster Recovery Recovery Site • Prod 1; • Prod 2; • Prod 3. • • • • • • • • • Phase V • Move Resources and Applications to Regional Data Center; • Test Successful Operation; • Define Recovery Site resources; • Virtualize; • Prove successful recovery from Production to old Recovery Site. Page: 2 • • • • • • • • • • • • • • “Proof of Concept”; Infrastructure Readiness; Disaster Recovery; Application Recovery; Business Recovery; Workplace Safety and Violence Prevention; Emergency Management; Crisis Management; Protection, Salvage, and Restoration; Supply Chain Management; Insurance; Community Relations; Communications; and Use of Social Media. Compliance • Laws and Regulations; • Requirements to Comply with; • Present Compliance; • Gaps & Exceptions; • Obstacles; • Domestic; • International; and • Cross Border Requirements. As you can see, every step of this project required lots of data and many forms, which resulted in a loss of productivity measured in Man-Months. Date: 1/31/2014
  • 3. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 What the Problem is • Paper, Paper, Paper • To much information, and unfortunately most of it is out-of-date, inaccurate, and extremely difficult to find. • People lost confidence in the documents they dealt with. • Delays, confusion, chaos, and loss productivity was measured in man-months. • When important decisions needed to be made, management and personnel were not able to access what they needed from any location at anytime. • Too much time was spent in conference calls and remote meetings and not enough time performing assigned functions. • A better way to handle documentation and work flow was needed. • From the first time a service is requested to its implementation and recovery, everybody has to be able to manage their responsibilities better. • This Dashboard covers the areas of: • Systems Development Life Cycle (SDLC); • Asset Management and Infrastructure; • Production Operations, Vital Records Management, Access Controls, and Support; and, • Recovery Management and Compliance. Created by: Thomas Bronack © Page: 3 Date: 1/31/2014
  • 4. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 What is the Resolution • Provide Management with Dashboards having Drill-Down capabilities: • • Infrastructure; • Systems Development Life Cycle (SDLC); • Production: • Recovery Management; and, • • Executive Dashboard; Compliance. Accomplished through Enterprise Resiliency and Corporate Certification: • Enterprise Resiliency combines all Recovery Discipline under one Department’s control; • Corporate Certification guarantee’s adherence to all required Laws and Regulations in the countries that your company conducts business; • Utilize a “Work Order (WO)” and “Purchase Order (PO)” mechanism; • Forms Management and Control is included to provide forms and track them through their Life Cycle until completion, allowing access to the individual performing a task at any time and from any authorized terminal anywhere; • Personnel Training, Career Path assistance, and Performance Management; and • Charge-Back system to allow for the comparison of new projects against previously performed projects, so that effort and cost can be compared better estimated. Created by: Thomas Bronack © Page: 4 Date: 1/31/2014
  • 5. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Why I developed the Dashboards • Project was slipping its schedule and we were losing productivity in ManMonths; • Too much time spent in Conference Calls and Remote Meetings, where people had inaccurate data or forms; • Confusion was rampant and nobody trusted the literature, which affected the status reporting and delivery schedule; • Management was getting very upset because they were not receiving straight answers or could not examine project data directly; • Costs were getting out of hand and work flow tracking was not being performed; • There was no way to improve efficiency following the current path; and, • The company and its reputation were in great peril because the final goal of having a virtual environment that could recovery all Tiers (CA, HA, Best Effort) of applications was no where in sight. Created by: Thomas Bronack © Page: 5 Date: 1/31/2014
  • 6. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Utilizing Dashboards • Guaranty Accurate and Current Data; • Viewable from any location at any time; • Reduce the need for many conference calls and remote meetings; • Improves efficiency; • Reduces Costs. CRUD Access: • Create; • Read; • Update; and, • Delete People Libraries Dashboard Data Keeping data current and accurate • Providing a Dashboard between personnel and data will insure that current data is being displayed when needed; • View data at remote meetings and conference calls from anywhere at anytime; • Allowing for data to be updated as appropriate during meetings and then saving the updated data via Version and Release Management Guidelines will insure that all data is in sync and improve confidence in data accuracy and currency; • Allow Drill-Down to current activity for the task being performed; • Provide direct connection to person performing the actual task (i.e., Name, Title, Phone, Email, and IM for instant messages and screen viewing – Outlook based); and, • Most efficient method for coordinating project and real-time activities. Created by: Thomas Bronack © Page: 6 Date: 1/31/2014
  • 7. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Building Dashboards for everything Dashboards Forms Management And Control System Repository of Project Related Materials Front-End To Data Base System Front-End To Repository System Repositories Data Base for Forms Management and Control Repository of Flat Files used to provide project information All Company Forms, with Help and Data Entry Validation All Company Project Related Documents with Version & Release Management Users can access the information at anytime and from anywhere, reducing the need for remote meeting and conference calls. Information can be drilled-down to actual task being performed and connect you with the person doing the work (IM, Name, Phone, Email, etc.). Only authorized personnel can update information, but everybody can access it, which allows for current and accurate information to be available upon demand. Created by: Thomas Bronack © Page: 7 Date: 1/31/2014
  • 8. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 How do we get there • Start with defining your SDLC and all forms used within the system: • • Create a Mechanism to help personnel select the right Form for what they have to do which will insure that all Forms are of the same type and format and facilitate your being able to develop metrics based on the information contained in Forms; • Make sure all Forms have a “Help Screen” to explain their use and meaning; • Use “Field Validation Rules” to make sure all required data is entered correctly; • Insure that a Forms Tracking System is used from Origination through Completion; and • • Implement a Forms Management and Control System; Utilize Performance Management to monitor work duration between estimated and actual. Integrate this system with: • Asset Management (Inventory, Configuration, Infrastructure, Personnel, etc.); • Production Operations (OCC, Library Management, Access Controls, Back-up, etc.); • Utilize VMware type products to support Code Level Upgrades, Testing, and Recovery Management as part of the SDLC Test Phase to insure production is not interrupted; • Insure that Version and Release Management guidelines are adhered to in order to guaranty that documentation is at the same level as the products being delivered; • Provide personnel with Orientation, Awareness, Training, Certification, and Career Path support; and, • Connect all current and accurate information to Dashboards for easy access and management. Created by: Thomas Bronack © Page: 8 Date: 1/31/2014
  • 9. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Now what do we have to do? • Systems Development Life Cycle; • Systems Management Organization; • Work Order / Purchase Order Flow and Charge-Back System; • Enterprise Resiliency and Corporate Certification; • Executive Dashboard; • Dashboard Relationships and Drill-Down capabilities;; • Working Example of a current Dashboard used to support Application Recovery Certification Management (already completed); • Personnel Productivity and Training System; • Utilizing VMware, vSphere, vConnect, and Recovery Point Application to support rapid recovery in support of critical applications and sites; • Integration within the Enterprise Environment; • Support Organization, with Command Centers interfacing; • Responding to Disaster Events in support of Business Continuity; and, • Benefits to be gained through this approach. Created by: Thomas Bronack © Page: 9 Date: 1/31/2014
  • 10. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Executive Dashboard Executive Dashboard Systems Development Life Cycle Infrastructure Dashboard Operations Dashboard Recovery Dashboard Asset Management Vital Records, Access Controls Disaster Planning Production Job Processing DR Certification Development Verify Success and Performance Audit Compliance Maintenance Support Disaster Declaration Test, QA, Accept Status Reporting Business Continuity Created by: Thomas Bronack © Page: 10 Date: 1/31/2014
  • 11. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Infrastructure Dashboard Infrastructure Dashboard Asset Management • • • • • • • Acquisition; Redeployment; Termination; • Clean; • Donate; • Sell; • Disposal. Inventory Management; Configuration Management; Finance; and, Accounting. Created by: Thomas Bronack © Engineering Management • • • • • • • • Service Request; Business / Technical Service Objectives; Design Objectives; Schedule / Priority; Design Document; Implementation Plan; Support, Maintenance and Enhancements; Design Changes; and, Change Management with Version and Release Management guidelines. Page: 11 Recovery Management • • • • • • • • • Project Initiation and Controls; Service / Application Selection; Planning Session; Infrastructure Readiness (Recovery Site Resources and Data Synchronization); Pre-Test (Recovery site setup); Actual Test (Application Run Book); Post Mortem Meeting; Certification (Y/N); and, Selected Improvements added. Date: 1/31/2014
  • 12. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Asset Management Lifecycle Dashboard Assets can be: People, Equipment, Locations, or any resources that goes through an Acquisition, Redeployment, Termination cycle (which is most everything in your company). Tying them together into a WO/PO fashion allows tracking. Asset Management Lifecycle Dashboard Work Order: Owner WO #: PO #: Category: Function: Resource PO #: Acquisition: Order: Y/N Owner WO #: Resource PO #: Owner WO #: Resource PO #: Reployment: Clean (Company): Y/N Y/N Y/N Y/N Termination: Donation Sale Disposal Redeploy Clean (DoD): Y/N Y/N Y/N Y/N Design: Technical: Asset Lifecycle Phase Architecture: Engineering: System Design Equipment Ordering: Vendor Receiving: Date Infrastructure: Inventory: Install Add Entry Configuration: Location: Add Entry Installed at Finance: Costs Accounting: Charge to Architecture: System Design System Design System Design System Design Engineering: Equipment Equipment Equipment Equipment Ordering: Vendor Vendor Vendor Vendor Receiving: Date Date Date Date Infrastructure: Uninstall Warehouse Move Install Inventory: Update Entry Update Entry Update Entry Update Entry Configuration: Update Entry Update Entry Update Entry Update Entry Location: Update Entry Update Entry Update Entry Update Entry Finance: Costs Costs Costs Costs Accounting: Charge to Charge to Charge to Charge to Architecture: System Design System Design System Design System Design Engineering: Equipment Equipment Equipment Equipment Ordering: Vendor Vendor Vendor Vendor Receiving: Date Date Date Date Infrastructure: Uninstall Warehouse Move Move Inventory: Add Entry Add Entry Add Entry Add Entry Configuration: Add Entry Add Entry Add Entry Add Entry Location: Installed at Installed at Installed at Installed at Finance: Costs Costs Costs Costs Accounting: Charge to Charge to Charge to Charge to • Tracks Asset from Acquisition, through Redeployment, and Termination; • Relates activity to Work Order (WO) and Purchase Order (PO) to facilitate cost accounting; • Defines Resources as Owned, Leased, Rented, Employee, Vendor, or Contractor for account and finance; • Interfaces with Users, Resources, Locations, Finance, and Accounting; and, • Provides easy tracking of required resources to determine their impact of delivery schedules. Created by: Thomas Bronack © Page: 12 Date: 1/31/2014
  • 13. Recovery Dashboards Executive Recovery Plans Training Materials Steering Committee Management EOC, CCC, and DR Teams Status Reporting DR Planning and Activation Dashboard Executive Management Dashboard on DR Planning and Activation Application Recovery Certification Dashboard Library Management Articles Standards and Procedures Business Location Recovery Dashboard Recovery Planning (7 Phases, each with 13 Steps) Statement of Work (SOW) Business / Project Plan Recovery Site Preparation Application Selection Procedures Business Recovery Site Workplace Safety and Violence Prevention Risk Analysis and Insurance Profile Dedicated BCM Organization Actual DR Test, or Activation VMware, vSphere, vConnect, and RPA Building Evacuation Plan OSHA,OEM, FEMA & Building Codes Audit, Legal, and Compliance Requirements Long-Term Management Commitment Post Mortem Meeting Failover / Failback for HA Applications Business Recovery & Resumption Plan First Responders and Government Agencies SDLC, Integration, and Version & Release Management Created by: Thomas Bronack © Flip / Flop for CA Applications Page: 13 Site Protection, Salvage, & Restoration Date: 1/31/2014 RFP’s / Bid’s SOW / Project Plans Business Plan Performance
  • 14. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 Tracking Active Disaster Recovery Events – Drill Down Actions “Top Level” – Enterprise Resiliency and Corporate Certification Dashboard Phase VI - Initiate Recovery Plan when Disaster Event Occurs Help Desk Help Desk Contingency Failing Site Recovery Team is Called Recovery Identifies Disaster Notifies Coordinator Protection, Disaster Site is Operations are and Recovery Personnel are Event or a Disaster Contingency Declares Salvage, and Evacuated, as Initiated and Tasks Transferred to Event is reported to Recovery Plan Disaster and Restoration is needed Conducted for Performed Recovery Site Help Desk Coordinator Initiates Plan Initiated Life of Disaster Failing Site is Salvaged and Restored Personnel Return to Original Site and Resume Production Recovery Steps Post Mortem Improvements are added to is Conducted are Testing Process and Incorporated in and Improvement Future Periodicically s Identified Recovery Plans Repeated “Sub Level” “Activity Level” “Action Item Level” DR Planning Action Items Number: Status: Action Item Description: Priority: Assigned to: Due Date: Actions Taken: Comments: “Management & Control Level” Created by: Thomas Bronack © Page: 14 Contingency Command Center (CCC) Emergency Operations Center (EOC) Date: 1/31/2014
  • 15. Optimizing the IT and Business Environment through Dashboards bronackt@dcag.com / (917) 673-6992 How Dashboards Help • Improved efficiency by providing instant access to current and accurate information from any authorized terminal or personal computer, at anytime from anyplace; • Drill-Down capability allows viewer to get to actual task being performed and be provided with the contact information for the person performing the task; • Less time spent reviewing out-of-date or inaccurate information reduces chaos; • Improved time frame for completing projects due to fewer remote meetings; • Reduced costs associated with implementing projects due to fewer conference calls and more time to devote to actual work; • Better protection to the company reputation; • More highly trained staff with an improved morale, that are easier to retain and aid in the ability to recruit additional staff and new clients; • Adherence to the laws and regulations where the company conducts business; and, • Less stress and better performance helps everyone do their job better. Created by: Thomas Bronack © Page: 15 Date: 1/31/2014
  • 16. The Next Step  If you believe that this approach can help your company improve performance and bring products and services to market more rapidly, then contact Thomas Bronack at:  Thomas Bronack  Phone: (917) 673-6992  Email: bronackt@dcag.com  We would love to assist you in integrating our approach within your environment.  Remember, our approach uses your existing data so you do not have to change information to adopt to our product.