The River Improvements Project is a $9.9 million project to stabilize river banks and add trails, lighting, public art, and other amenities along the river. Construction is being managed by Templeton Construction and is 78% complete, with an expected completion date of August 2013. Improvements include bank stabilization, trails, lighting, exercise areas, water features, and public art between Oakes Street and Sulphur Draw. The project is funded by sales taxes and grant money.
4. River Improvements Project
• Construction Manager at Risk: Templeton Construction, Inc.
• Time Summary
• Contract Date: October 1, 2011
• Completion Date: August 2013
• Budget Summary
• Project Budget = $9,899,321.79
• Total Change Orders to date = $599,321.79
• Billed to Date (Gross) = $7,918,778.91
• Retainage Held to Date (3%) = $234,122.70
• Billed to Date (Less Retainage) = $7,684,656.21
• % Complete = 78%
5. River Improvements Project
• Funding Sources: Half-Cent Sales Taxes and nearly
$2,000,000 in grants including 2 from Texas Parks and Wildlife,
San Angelo Health Foundation, Texas Commission on
Environmental Quality and National Endowment for the Arts.
• Improvements to Include: stabilization of the banks from
Oakes Street upriver to the vicinity of Sulphur Draw, additional
trails and trail improvements, new lighting, an outdoor exercise
area, public art, shaded sitting areas, water features and other
special elements.
• Work outside of contract includes trail section on SAHF property
and some existing trail renovation.
• Note: dredging of the river occurred in 2009 from Sulphur Draw
upriver to 14th Street at a cost of about $1,500,000.
6. River Improvements Project
• Bank stabilization complete, including extended area.
May do additional stabilization below Visitors’ Center.
• Most initial art installed (less sculpture panels).
• Work continues at Irving Street and Games area.
• Landscaping discussion with City Council.
• High pedestrian bridge update.