SlideShare uma empresa Scribd logo
1 de 19
1 | P a g e
DESIGN OF 130 MW, 200 KM TRANSMISSION LINE
Most Economical Voltage Calculation:
The most economical voltage is given by the following empirical formula:
Economical Voltage (V eco) =5.5*
150**cos
1000*
6.1 Nc
PLt


Where,
Lt = length of transmission line =200 Km
P = Power to be transmitted =130 MW
cosØ = Power factor =0.96
For Nc= 1
Then, using the above values
V eco =5.5*
150*1*96.0
1000*130
6.1
200

= 177.137 KV
Nearest Standard Voltage= 220 kV
For Nc= 2
Then, using the above values
V eco =5.5*
150*2*96.0
1000*130
6.1
200

= 132.587 KV
Nearest Standard Voltage= 132 kV
2 | P a g e
Checking technical criterion:
For Nc=1
Surge impedance Loading (SIL) = V2
/Z0
= 2202
/400 =121
Multiplying factor (MF) =
SIL
P max
= 130/121 = 1.0834
MFlimit for 160 KM from provided standard table = 2.0614
MFcalculated (1.08) < MFlimit (2.0614)
Power transfer capability = MFlimi* SIL
=2.0614*121
=249.4294
For Nc=2
Surge impedance Loading (SIL) = V2
/Z0
= 1322
/200 =87.12
Multiplying factor (MF) =
SIL
P max
= 130/87.12 = 1.4921
MFlimit for 160 KM from provided standard table = 2.25
MFcalculated (1.1921) < MFlimit (2.0614)
Power transfer capability = MFlimi* SIL
=2.0614*87.12
=179.58
Since the power transfer capability for double circuit is near to the power to be transferred .
s so Nc=2 is taken in this design. Since the voltage level 132Kv is not meet the voltage
regulation for any conductor available. So we have to chose double circuit 220 KV.
3 | P a g e
Calculation of Insulation Discs
For all the calculations of number of insulator discs, we considered following value of different
factor:
FOWR = Flashover Withstand Ratio =1.15
NACF = Non Atmospheric Condition Factor = 1.1
FS = Factor of Safety =1.2
1) Number of Insulator Discs Required for the temporary O/V
Temporary O/V = Earth Factor (EF) * Maximum system voltage
= 0.8 * (220*√2 * 1.1)
= 273.7917 KV
Equivalent Flashover Voltage (Veq= Temporary O/V * FOWR *NACF * FS
Equivalent Voltage (Veq) = 273.7917* *1.15 * 1.1 *1.2
= 415.6158 KV
From standard table number of insulator discs required to withstand above equivalent
voltage (Na) = 11
2) Number of Insulator Discs Required to withstand continuous operating voltage:
a) Voltage Level for dry condition = Equiv dry 1 min. voltage*FOWR*NACF * FS
Where,
Equivalent dry 1 min voltage is taken from standard table = 435 KV
Equivalent 1 min dry flashover Voltage = 265 * 1.15 * 1.1 *1.2
= 660.33 kV
From Standard Table number of discs required to withstand above equivalent voltage level
(Nb1) =12
Voltage Level for given Power Transmission =220 KV
Number of Circuit = 2
Power Factor ( cosØ ) = 0.96
Length of Transmission Line (L) = 200Km
4 | P a g e
b) Voltage Level for Wet condition = Equiv dry 1 min. voltage*FOWR*NACF * FS
Where,
Equivalent wet 1 min voltage is taken from standard table = 395 KV
Equivalent Voltage Level = 395* 1.15 * 1.1 *1.2
= 599.61 KV
From Standard Table number of discs required to withstand the above equivalent voltage level
(Nb2) =9
3) Number of Insulator Discs required for switching over voltage:
Voltage Level = switching o/v * Switching to impulse ratio * FOWR *NACF* FS
Where,
Switching to impulse ratio (SIR) = 1.2
SSR = Switching Surge Ratio =2.75
Switching O/V =SSR* ( 2 / 3 )*Max system voltage*SIR
So Switching O/V =652.0541KV
Equivalent flashover Voltage Level = 652.0541*1.15*1.1*1.2
= 989.8182 KV
From Standard Table number of discs required to withstand the above voltage level (Nc) = 11
3) Number of Insulator Discs required for over voltage due to Lightning:
From standard table Equivalent voltage level for the given system voltage =900 KV
Equivalent flashover Voltage Level = 900* FOWR *NACF* FS
= 900*1.15*1.1*1.2
= 1366.2
From Standard Table number of discs required to withstand the above voltage level (Nd) = 16
5 | P a g e
Hence from above table the required number of insulator discs to withstand all types voltage
level in all condition for given system voltage = 16
Air Clearance Calculation
Air clearance parameters calculation for double circuit tower configuration:
a = minimum distance (clearance requirement) from a line conductor to any earthed
object, and is given by the following relation:
a =6.5 inch per 10 KV (rms)
=(6.5*220*1.1)/( 10*3 )+8
=98.8171 inch
=250.995cm
=2.5099m
SN Voltage Level Description Voltage Level Number of
Discs
1)
2)
3)
4)
Temporary O/V appearing across the insulator
Continuous voltage
i) Continuous operating Voltage in Dry condition
ii) Continuous operating Voltage in Wet
condition
Switching Over voltage
O/V due to lightning
415.6158KV
660.33KV
599.61 KV
989.8182KV
1366.2 KV
11
12
9
11
16
Required Number of Insulator Discs =16
6 | P a g e
Now String Length (l) = 2 a =3.5495m
Tower width (b) = 1.5*a = 3.7648m
Cross arm length(CL) = 2*a = 5.0198m
Vertical distance between two adjacent line conductor (y) =
22
2
1
)(





 








a
al
y
x
al
Where 0.25 < x/y< 0.333
=
 
2
2
5099.2*2
5099.25495.3
25.01
)5099.25495.3(





 


= 6.3557m
Horizontal distance between adj. conductor =5.5 a = 5.5*2.5099 =13.804 m
Height of earth wire from top (d) =
= 5.14504m
Conductor and Tower Selection
Conductor and Tower Selection
Line current is calculated as:
Air clearance from earthed object (a) = 2.5099 m
String Length (l) = 3.5495 m
Tower Width (b) = 3.7648m
Cross Arm Length = 5.0198m
Vertical distance between two adjacent line conductor (y) = 6.3557m
Horizontal distance between two adj. line conductor =13.804 m
Height of Earth wire from top cross arm (d) = 5.14504m
7 | P a g e
Line current (I) =
cos**3
2/
llV
P
=
96.0*220*3
1000*)2/130(
= 177.688 amp
Comparing this value of the current with the current carrying capacity from the given standard
ASCR conductor table, Conductor “FERRET” is selected.
For Ferret conductor, From ASCR conductor table,
Resistance at 200
C (R20) = 0.67950 Ώ/Km
Coefficient of Resistivity (α20) =
So Resistance at 650
C (R65) = R20 (1 + α20(65-20))
= 0.67950 (1+0.004*45)
= 0.80181Ώ/Km
Transmission Efficiency Criterion
Power Loss for single conductor = I2
*R*L
= (177.688)2
*0.80181s*200
= 5.063MW/conductor
Transmission Efficiency (ή) = 65 / (65+3*5.063)
= 0.8105
= 81.058%
Transmission Efficiency<94 %. So this conductor is not used used . To get higher efficiency we
proceed in same way and calculate efficiency finally we got the conductor “Wolf” which has
efficiency 94.036%.
Voltage Regulation Criterion
For Conductor Wolf,
This conductor has 37 strands 7Aluminum strands and 1steel strands.
Diameter of each strands = 2.59mm
Conductor diameter (D)=18.13mm
Radius of the conductor(R)=9.065mm
GMR for inductance (GMRi) =0.768R
=6.1692smm
8 | P a g e
GMR for capacitance (GMRc) = R
=9.065mm
Geometric mean distance(GMD)=
=
=8.00768m
Resistance of the whole line (R) = 43.518 Ώ
Inductance of Whole length (L) =2 * 10-4
ln (GMD/GMRi)*L
=2e-4*ln(8.00768/ )*200
=0.2867H
Capacitance of whole Length(C) = 3**
ln
2
eL
GMRc
GMD







=
=1.640µF
Now Impedance of the Line (Z) = R + j 314.15 *L
= 43.518+j90.0694
= 100.031<64.211
Susceptance of the Line (Y) = j314.15*C
= j5.1522* e-04
= (5.1522* e-04) <90
A, B, C, D parameters calculation
A = 1 + ZY/2 = 0.9768<0.657
B = Z= 100.031<64.211
C= Y (1+ZY/4)
D = A
Now, Sending end Voltage (Vs) = A*Vr +B*Ir
= 0.9768<0.657* 220*e3/√3<0 + 100.031<64.211* 177.688<-16.26
9 | P a g e
= 12.407*e4<0.657+17.774*e3<47.951
= 136.7502<6.1377KV
Now Voltage Regulation = (|Vs|/A -|Vr| )/|Vr|
= 0.1021
= 10.219%
Voltage regulation < 12% so this conductor Wolf can be used.
Corona Inception Voltage Criterion
For wolf conductors
Corona Inception voltage (Vci) = *21.1*GMR*m*δ*ln(GMD/GMR)
Where, m = factor of roughness =0.9
δ = relative density of air =.95
Vci = 21.1 * 0.9065*0.9*0.95* ln (8.00768/9.065e-3)
= 192.152KV
Here Vci < Vs so Corona Inception Voltage criterion is met. So we go for next higher conductor.
For conductor Panther
GMRc=10.5mm
GMD=8.00768m
Vci= 21.1 * 1.05*0.9*0.95* ln (8.00768/10.5e-3)
=217.748KV
For conductor Lion
GMRc=11.13mm
GMD=8.00768m
Vci= 21.1 * 1.113*0.9*0.95* ln (8.00768/11.13e-3)
= 228.787KV
Since Vci>Vs for conductor Lion. So no corona occurs in that conductor.
10 | P a g e
Tension Calculation for Different Conductors with Different Span in Different
Condition
Four Different conductors below conductor LION in ASCR conductor table is chosen. Hence
Tension calculation will be done for conductor “lion, Bear, Goat , Sheep and Dear” with Span
length 250 m, 275 m, 300 m, 325 m, and 350 m. Tensions for Toughest, Stringing and Easiest
condition are calculated and tabulated below. Sample calculation is also shown.
Sample calculation; Conductor 1: Lion
Area of conductor = 2.94 cm2
Linear expansion coefficient = 1.773 e-5 per 0
C
Modulus of elasticity (E) = 7.87 e+5 kg/cm2
Tension at toughest condition (T1) = = = 5105Kg.
Weight of conductor (wc) = 1097Kg/Km
Wind pressure (Fw) = 100 kg/m2
Weight due to wind force (ww) = Fw*d*(2/3)
=100*1000*22.26e-3*2/3 = 1484kg
Weight of ice (wice) = 0
Weight for toughest condition (w1) =
= 1845.444 kg
Weight for the stringing and easiest condition (w2) = 1097kg.
Then, the tension at stringing (T2) and the easiest condition (T3) is calculated using the following
equation known as STRINGING EQUATION.
T2
2
[T2+k1] - k2 = 0 ………………………………….. (1)
11 | P a g e
Where,
 








 AE
T
LW
AETK 2
1
22
1
1
24
121  and,
K2= AE
LW
24
22
2
.
From the above data, the values of K1 and K2 for the span of 250m are given by:
K1 = -3210.60; K2 = 7.25e+9;
Using the stringing equation, the value of T2 is found to be,
T2 = 3731.26 kg.
Similarly, T3 is calculated by the similar procedure as above. For the calculation of T3 the value
of K1 and K2 for 250 m of length are given by:
K1 = -903.54; K2 = 7.25e+9;
Using the stringing equation, we get the value of T3 as:
T3 = 2288.303 kg.
In the similar manner, the values of tensions of different conductor for different span length is
calculated and presented in the table below:
12 | P a g e
Sag and height of tower calculation
We have the relation,
Maximum sag (Dmax) = (W L2
)/ (8*T3);
Where, W = weight of conductor.
L = length of span.
T3 = tension at easiest condition.
Sample calculation:
For Lion, W = 1097kg/km.
L = 0.25 Km.
T3 =2288.303Kg.
Using the above equation, Dmax = 3.74527m.
Let the minimum ground clearance (hg) = 7.5m.
Height of lower conductor (H1) = hg+ Dmax =11.2452m.
Height of middle conductor (H2) = H1+y = 17.60m.
Height of top most conductor (H3) = H2+y = 23.956m.
Total height of tower (Ht) = H3+l+d = 32.6512m.
Similarly, the maximum sag, H1, H2, H3 and the total height of the tower are calculated and
presented in the table below:
Earth wire selection
From earth wire table, earth wire GUINEA is chosen as follows:
No of strands = 19; diameter of a strand = 2.92mm; weight of conductor = 590kg/km;
Conductor diameter = 14.60mm; conductor area = 127.20mm2
;
Ultimate tensile strength = 6664 kg;
Hence, maximum tension (Te) = 6664/2 = 3332 kg.
Bending moment and tower weight calculation
Sample calculation: for Lion, Ht=32.6512m, 250m span
Taking 80% for tower A; 15% for tower B; and 5% for tower C
Due to Earth wire
1) Bending moment acting on tower due to E/W considering wind force:
13 | P a g e
BMe1 = Fwe*Ht*Ne
= (100*14.60e-3*250*2/3)*32.6512*2
= 15890.2506 kg-m.
2) Bending moment due to turning of the E/W
BMe2=Fte*Ht*Ne
=
BMe2 = 2*Te*(sin10
*0.80 + sin7.50
*0.15 + sin150
*.05)*Ht*2
=2*3332*(0.046481)*32.6512*2
= 20227.378Kg-m
Due to power conductor
1) Bending moment acting on tower due to power conductor considering wind force
BMpw = Fw*(H1+H2+H3)*2
= (100*22.26e-3*250*2/3)*(11.2452+17.60+23.956)*2
= 39178.4904 kg-m
2) Bending moment due to turning of the power conductor
BMpt = 2*T1*(sin10
*0.80 + sin7.50
*0.15 + sin150
*.05) *(H1+H2+H3)*2
= 2*5105*0.046481*52.8012*2
=50117.261kg-m
Then the total bending moment is calculated as;
BMtotal = BMe1 + BMe2 + BMpw +BMpt
=125413.38 kg-m
Weight of tower
Weight of tower (Wt) = ; Where, Ht is in Ft; BM is in lb-ft.
=0.000631*Ht* ; where, Ht is in m; Bm is in kg-m.
The bending moment of different conductors at different length of span and weight of tower
are calculated and shown in the tabulated form below:
14 | P a g e
15
Cost per unit length calculation
Assumptions: Cost of the steel used in tower = Rs.150000 per tonne
Number of towers (Nt) = ((total length)/(length of span))+1
Cost of tower per unit length = (cost per tower*Nt)/length of transmission
Sample calculation:
For Lion; 250m; weight of tower= 10.30955 tonne
Number of tower = (200/0.25 ) +1= 801 nos
Cost per tower = cost per tonne* weight of tower
= Rs.150000*10.3185
= Rs. 1547775
Cost of tower per unit length = (1547775*801)/200
= Rs.6198838.875
Similarly the cost of tower per unit length of different conductor and different span are
shown in table below:
Most economical span and conductor selection
Data available;
Cost of aluminum per tonne = Rs.20150
Cost of steel per tonne = Rs. 150000
Sample calculation:
For Lion; span =325m; aluminum weight per Km = 659 kg; steel weight per
km = 438 kg
Cost of power conductor
Cost of aluminum per km = Rs. 20150*0.659 = Rs.13278.85
Cost of steel per km = Rs 150000*.438 = Rs. 65700
Total Cost of power conductor = (Rs. 13278.85 + Rs. 65700)*6 = Rs.473873.1/km
From table above,
Tower cost per unit length = Rs. 5915213.448
16
Capital cost/length = conductor cost/km + tower cost/km
= Rs.473873.1+ Rs. 5915213.448
(P) =Rs. 6389086.548
Annual capital cost (A) is calculated as:
A=
Where i=10% and n=25 years
This gives annual capital cost (A) = Rs. 703873.348
Power loss per Km PL=27.338 Kw;
load loss factor (LLf)=k1*LF+K2*LF^2
= (0.2*0.5)+(0.8*0.5*0.5)
=0.3
Cost of Energy loss/Km = PL *LLf * time* rate per Kwh
=27.338*0.3*365*24*7.5
=Rs. 538831.98
Total annual cost = Rs. 703873.348+ Rs. 538831.98
=Rs. 1242705.328
The total annual cost calculation is shown in table below:
From the above table,
The minimum total annual cost is acquired by the conductor Sheep. Hence we go
for the conductor Bear for the transmission line of 130 Mw and 200Km.
17
Transmission line characteristics of the conductor Sheep
Electrical characteristics
 67 strands with 7 Steel strands and 32Aluminum strands.
Diameter of each strands = 3.99 mm
GMR for inductance (GMRi) = 10.7251mm
GMR for capacitance (GMRc) =13.965mm
Resistance of the whole line per phase(R) = 18.3395Ώ
Inductance of Whole length (L) =0.264H
Capacitance of whole Length(C) = 1.7517 μF
Now Impedance of the Line (Z) = 84.9414<77.531 Ώ
Susceptance of the Line (Y) =j5.5031*e-04 siemen
= 5.5031*e-04<90
18
A, B, C, D parameters calculation
A = 1 + ZY/2 = 0.979<0.2711
B = Z= 84.9414<77.531
C = 5.440*e-04<90.146
D = A=0.979<0.2711
Now, Sending end Voltage
(Vs) = A*Vr +B*Ir
= 0.979<0.2711* 220/√3<0 + 84.9414<77.056* 177.688*e-03<-16.26
= 132.4296<5.9652KV
Sending end current(Is) = C*Vr +D*Ir
= 168.563<7.2185
Now Voltage Regulation = (|Vs|/A -|Vr| )/|Vr|
= 0.0649
= 6.497%
Corona Inception Voltage Criterion
Corona Inception voltage (Vci) =21.1*GMR*m*δ*ln(GMD/GMR)
Where, m = factor of roughness =0.9
δ = relative density of air =0.95
Vci = 21.1 * 1.3965*0.9*0.95* ln (8.00768/13.965e-3)
= 277.161KV
19
Mechanical characteristics
Length of span =350m.
Tension at toughest condition = 7955kg
Tension at stringing condition = 5902.87kg
Tension at easiest condition = 3923.8231kg
Heights:
Maximum sag =6.73561 m; H1=14.2356m; H2=20.591m; H3=26.947m; Ht=35.6415m
Bending moment =178830.9kg-m
Tower weight=14.3985 tonne
Tower Cost per unit length=Rs.6187763.968 /Km
Total annual cost =Rs. 1106280.389/km

Mais conteúdo relacionado

Mais procurados

Tranformer Design
Tranformer DesignTranformer Design
Tranformer DesignArnab Nandi
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculationobaidurbd
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parametersfiraoltemesgen1
 
Three phase full wave rectifier
Three phase  full wave rectifierThree phase  full wave rectifier
Three phase full wave rectifierVinay Singh
 
Electrical Power Distribution System (ArnabNandi_WBSEDCL)
Electrical Power Distribution System (ArnabNandi_WBSEDCL)Electrical Power Distribution System (ArnabNandi_WBSEDCL)
Electrical Power Distribution System (ArnabNandi_WBSEDCL)Arnab Nandi
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7Power System Operation
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault AnalysisSANTOSH GADEKAR
 
Exp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdfExp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdfvenkataraoHanumanthu1
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission linesfiraoltemesgen1
 
Sag in overhead transmission line, sag calculation &amp; string chart
Sag in overhead transmission line, sag   calculation &amp; string chartSag in overhead transmission line, sag   calculation &amp; string chart
Sag in overhead transmission line, sag calculation &amp; string chartvishalgohel12195
 
Power cable - Voltage drop
Power cable - Voltage dropPower cable - Voltage drop
Power cable - Voltage dropLeonardo ENERGY
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power systemsneh pratap singh
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performancefiraoltemesgen1
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notesmichaeljmack
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Theory of HVDC transmission
Theory of HVDC transmission Theory of HVDC transmission
Theory of HVDC transmission SAURAV DAYAL SING
 

Mais procurados (20)

Tranformer Design
Tranformer DesignTranformer Design
Tranformer Design
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculation
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
Three phase full wave rectifier
Three phase  full wave rectifierThree phase  full wave rectifier
Three phase full wave rectifier
 
Electrical Power Distribution System (ArnabNandi_WBSEDCL)
Electrical Power Distribution System (ArnabNandi_WBSEDCL)Electrical Power Distribution System (ArnabNandi_WBSEDCL)
Electrical Power Distribution System (ArnabNandi_WBSEDCL)
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7Principles of Power Systems V.K Mehta Complete Book - Chapter 7
Principles of Power Systems V.K Mehta Complete Book - Chapter 7
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
Exp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdfExp 7 for Impulse Voltage Breakdown.pdf
Exp 7 for Impulse Voltage Breakdown.pdf
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
Sag in overhead transmission line, sag calculation &amp; string chart
Sag in overhead transmission line, sag   calculation &amp; string chartSag in overhead transmission line, sag   calculation &amp; string chart
Sag in overhead transmission line, sag calculation &amp; string chart
 
Types of-tower
Types of-towerTypes of-tower
Types of-tower
 
Unsymmetrical Fault
Unsymmetrical FaultUnsymmetrical Fault
Unsymmetrical Fault
 
Power cable - Voltage drop
Power cable - Voltage dropPower cable - Voltage drop
Power cable - Voltage drop
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
 
Per unit system
Per unit systemPer unit system
Per unit system
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
 
substation internship report
substation internship report substation internship report
substation internship report
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
 
Theory of HVDC transmission
Theory of HVDC transmission Theory of HVDC transmission
Theory of HVDC transmission
 

Destaque

transmission line
transmission line transmission line
transmission line singh1515
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design conceptKumar VEL
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission LineSURESH GOPAL
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Kathmandu Univesity
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission towernaqeeb04
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 
Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower IJMER
 
Design of Transmission Tower
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission TowerAbhijit Kumar
 
analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication towerRohithasangaraju
 
5 cired2013 planning of power distribution systems
5   cired2013 planning of power distribution systems5   cired2013 planning of power distribution systems
5 cired2013 planning of power distribution systemsDutch Power
 
Why are Critical Infrastructure Failures such an Issue?
Why are Critical Infrastructure Failures such an Issue?Why are Critical Infrastructure Failures such an Issue?
Why are Critical Infrastructure Failures such an Issue?Blackash Bushfire Consulting
 

Destaque (20)

transmission line
transmission line transmission line
transmission line
 
INSULATORS AND ITS TYPES
INSULATORS AND ITS TYPESINSULATORS AND ITS TYPES
INSULATORS AND ITS TYPES
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Transmission Line
Transmission LineTransmission Line
Transmission Line
 
Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
 
design of tower
design of towerdesign of tower
design of tower
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Types of insulator
Types of insulatorTypes of insulator
Types of insulator
 
Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower
 
Design of Transmission Tower
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission Tower
 
analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication tower
 
Rock star
Rock starRock star
Rock star
 
Presentation new
Presentation newPresentation new
Presentation new
 
CV of Jhahidul Islam
CV of Jhahidul IslamCV of Jhahidul Islam
CV of Jhahidul Islam
 
5 cired2013 planning of power distribution systems
5   cired2013 planning of power distribution systems5   cired2013 planning of power distribution systems
5 cired2013 planning of power distribution systems
 
generating equipment
generating equipmentgenerating equipment
generating equipment
 
Why are Critical Infrastructure Failures such an Issue?
Why are Critical Infrastructure Failures such an Issue?Why are Critical Infrastructure Failures such an Issue?
Why are Critical Infrastructure Failures such an Issue?
 

Semelhante a Transmission and distribution line design final

Electrical Machine design
Electrical Machine designElectrical Machine design
Electrical Machine designAsifAdnanTajwer
 
EE6604 unit2
EE6604 unit2EE6604 unit2
EE6604 unit2Sri Kumar
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrentmichaeljmack
 
16th July 2015 Road lighting_modified
16th July 2015 Road  lighting_modified16th July 2015 Road  lighting_modified
16th July 2015 Road lighting_modifiedPrateek Singh
 
Main dimension & rotor design of squirrel cage Induction Motor.pdf
Main dimension & rotor design of squirrel cage Induction Motor.pdfMain dimension & rotor design of squirrel cage Induction Motor.pdf
Main dimension & rotor design of squirrel cage Induction Motor.pdfMohammadAtaurRahmanA
 
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Hamza Waheed
 
Calculation Method for Normal Inducedlongitudinal Voltage on Pilot Cable
Calculation Method for Normal Inducedlongitudinal Voltage on Pilot CableCalculation Method for Normal Inducedlongitudinal Voltage on Pilot Cable
Calculation Method for Normal Inducedlongitudinal Voltage on Pilot CableIJERA Editor
 
Solved problems to_chapter_09
Solved problems to_chapter_09Solved problems to_chapter_09
Solved problems to_chapter_09Shah Zaib
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...Hossam Shafiq II
 
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)Hossam Shafiq II
 
180953548-Current-Transformer-ppt.ppt
180953548-Current-Transformer-ppt.ppt180953548-Current-Transformer-ppt.ppt
180953548-Current-Transformer-ppt.pptelectrical1012000
 
Design of transformer and chock coil
Design of transformer and chock coilDesign of transformer and chock coil
Design of transformer and chock coilShubham Champaneri
 

Semelhante a Transmission and distribution line design final (20)

Electrical Machine design
Electrical Machine designElectrical Machine design
Electrical Machine design
 
EE6604 unit2
EE6604 unit2EE6604 unit2
EE6604 unit2
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrent
 
16th July 2015 Road lighting_modified
16th July 2015 Road  lighting_modified16th July 2015 Road  lighting_modified
16th July 2015 Road lighting_modified
 
Main dimension & rotor design of squirrel cage Induction Motor.pdf
Main dimension & rotor design of squirrel cage Induction Motor.pdfMain dimension & rotor design of squirrel cage Induction Motor.pdf
Main dimension & rotor design of squirrel cage Induction Motor.pdf
 
ECNG 3013 C
ECNG 3013 CECNG 3013 C
ECNG 3013 C
 
Elecmachine
ElecmachineElecmachine
Elecmachine
 
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
 
Calculation Method for Normal Inducedlongitudinal Voltage on Pilot Cable
Calculation Method for Normal Inducedlongitudinal Voltage on Pilot CableCalculation Method for Normal Inducedlongitudinal Voltage on Pilot Cable
Calculation Method for Normal Inducedlongitudinal Voltage on Pilot Cable
 
ECNG 3013 B
ECNG 3013 BECNG 3013 B
ECNG 3013 B
 
EE503.29.ppt
EE503.29.pptEE503.29.ppt
EE503.29.ppt
 
Solved problems to_chapter_09
Solved problems to_chapter_09Solved problems to_chapter_09
Solved problems to_chapter_09
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
 
12 transformer
12 transformer12 transformer
12 transformer
 
PSpice Tutorial
PSpice TutorialPSpice Tutorial
PSpice Tutorial
 
FINAL
FINALFINAL
FINAL
 
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
 
Current-Transformer-ppt.ppt
Current-Transformer-ppt.pptCurrent-Transformer-ppt.ppt
Current-Transformer-ppt.ppt
 
180953548-Current-Transformer-ppt.ppt
180953548-Current-Transformer-ppt.ppt180953548-Current-Transformer-ppt.ppt
180953548-Current-Transformer-ppt.ppt
 
Design of transformer and chock coil
Design of transformer and chock coilDesign of transformer and chock coil
Design of transformer and chock coil
 

Último

Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.MateoGardella
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Último (20)

Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 

Transmission and distribution line design final

  • 1. 1 | P a g e DESIGN OF 130 MW, 200 KM TRANSMISSION LINE Most Economical Voltage Calculation: The most economical voltage is given by the following empirical formula: Economical Voltage (V eco) =5.5* 150**cos 1000* 6.1 Nc PLt   Where, Lt = length of transmission line =200 Km P = Power to be transmitted =130 MW cosØ = Power factor =0.96 For Nc= 1 Then, using the above values V eco =5.5* 150*1*96.0 1000*130 6.1 200  = 177.137 KV Nearest Standard Voltage= 220 kV For Nc= 2 Then, using the above values V eco =5.5* 150*2*96.0 1000*130 6.1 200  = 132.587 KV Nearest Standard Voltage= 132 kV
  • 2. 2 | P a g e Checking technical criterion: For Nc=1 Surge impedance Loading (SIL) = V2 /Z0 = 2202 /400 =121 Multiplying factor (MF) = SIL P max = 130/121 = 1.0834 MFlimit for 160 KM from provided standard table = 2.0614 MFcalculated (1.08) < MFlimit (2.0614) Power transfer capability = MFlimi* SIL =2.0614*121 =249.4294 For Nc=2 Surge impedance Loading (SIL) = V2 /Z0 = 1322 /200 =87.12 Multiplying factor (MF) = SIL P max = 130/87.12 = 1.4921 MFlimit for 160 KM from provided standard table = 2.25 MFcalculated (1.1921) < MFlimit (2.0614) Power transfer capability = MFlimi* SIL =2.0614*87.12 =179.58 Since the power transfer capability for double circuit is near to the power to be transferred . s so Nc=2 is taken in this design. Since the voltage level 132Kv is not meet the voltage regulation for any conductor available. So we have to chose double circuit 220 KV.
  • 3. 3 | P a g e Calculation of Insulation Discs For all the calculations of number of insulator discs, we considered following value of different factor: FOWR = Flashover Withstand Ratio =1.15 NACF = Non Atmospheric Condition Factor = 1.1 FS = Factor of Safety =1.2 1) Number of Insulator Discs Required for the temporary O/V Temporary O/V = Earth Factor (EF) * Maximum system voltage = 0.8 * (220*√2 * 1.1) = 273.7917 KV Equivalent Flashover Voltage (Veq= Temporary O/V * FOWR *NACF * FS Equivalent Voltage (Veq) = 273.7917* *1.15 * 1.1 *1.2 = 415.6158 KV From standard table number of insulator discs required to withstand above equivalent voltage (Na) = 11 2) Number of Insulator Discs Required to withstand continuous operating voltage: a) Voltage Level for dry condition = Equiv dry 1 min. voltage*FOWR*NACF * FS Where, Equivalent dry 1 min voltage is taken from standard table = 435 KV Equivalent 1 min dry flashover Voltage = 265 * 1.15 * 1.1 *1.2 = 660.33 kV From Standard Table number of discs required to withstand above equivalent voltage level (Nb1) =12 Voltage Level for given Power Transmission =220 KV Number of Circuit = 2 Power Factor ( cosØ ) = 0.96 Length of Transmission Line (L) = 200Km
  • 4. 4 | P a g e b) Voltage Level for Wet condition = Equiv dry 1 min. voltage*FOWR*NACF * FS Where, Equivalent wet 1 min voltage is taken from standard table = 395 KV Equivalent Voltage Level = 395* 1.15 * 1.1 *1.2 = 599.61 KV From Standard Table number of discs required to withstand the above equivalent voltage level (Nb2) =9 3) Number of Insulator Discs required for switching over voltage: Voltage Level = switching o/v * Switching to impulse ratio * FOWR *NACF* FS Where, Switching to impulse ratio (SIR) = 1.2 SSR = Switching Surge Ratio =2.75 Switching O/V =SSR* ( 2 / 3 )*Max system voltage*SIR So Switching O/V =652.0541KV Equivalent flashover Voltage Level = 652.0541*1.15*1.1*1.2 = 989.8182 KV From Standard Table number of discs required to withstand the above voltage level (Nc) = 11 3) Number of Insulator Discs required for over voltage due to Lightning: From standard table Equivalent voltage level for the given system voltage =900 KV Equivalent flashover Voltage Level = 900* FOWR *NACF* FS = 900*1.15*1.1*1.2 = 1366.2 From Standard Table number of discs required to withstand the above voltage level (Nd) = 16
  • 5. 5 | P a g e Hence from above table the required number of insulator discs to withstand all types voltage level in all condition for given system voltage = 16 Air Clearance Calculation Air clearance parameters calculation for double circuit tower configuration: a = minimum distance (clearance requirement) from a line conductor to any earthed object, and is given by the following relation: a =6.5 inch per 10 KV (rms) =(6.5*220*1.1)/( 10*3 )+8 =98.8171 inch =250.995cm =2.5099m SN Voltage Level Description Voltage Level Number of Discs 1) 2) 3) 4) Temporary O/V appearing across the insulator Continuous voltage i) Continuous operating Voltage in Dry condition ii) Continuous operating Voltage in Wet condition Switching Over voltage O/V due to lightning 415.6158KV 660.33KV 599.61 KV 989.8182KV 1366.2 KV 11 12 9 11 16 Required Number of Insulator Discs =16
  • 6. 6 | P a g e Now String Length (l) = 2 a =3.5495m Tower width (b) = 1.5*a = 3.7648m Cross arm length(CL) = 2*a = 5.0198m Vertical distance between two adjacent line conductor (y) = 22 2 1 )(                a al y x al Where 0.25 < x/y< 0.333 =   2 2 5099.2*2 5099.25495.3 25.01 )5099.25495.3(          = 6.3557m Horizontal distance between adj. conductor =5.5 a = 5.5*2.5099 =13.804 m Height of earth wire from top (d) = = 5.14504m Conductor and Tower Selection Conductor and Tower Selection Line current is calculated as: Air clearance from earthed object (a) = 2.5099 m String Length (l) = 3.5495 m Tower Width (b) = 3.7648m Cross Arm Length = 5.0198m Vertical distance between two adjacent line conductor (y) = 6.3557m Horizontal distance between two adj. line conductor =13.804 m Height of Earth wire from top cross arm (d) = 5.14504m
  • 7. 7 | P a g e Line current (I) = cos**3 2/ llV P = 96.0*220*3 1000*)2/130( = 177.688 amp Comparing this value of the current with the current carrying capacity from the given standard ASCR conductor table, Conductor “FERRET” is selected. For Ferret conductor, From ASCR conductor table, Resistance at 200 C (R20) = 0.67950 Ώ/Km Coefficient of Resistivity (α20) = So Resistance at 650 C (R65) = R20 (1 + α20(65-20)) = 0.67950 (1+0.004*45) = 0.80181Ώ/Km Transmission Efficiency Criterion Power Loss for single conductor = I2 *R*L = (177.688)2 *0.80181s*200 = 5.063MW/conductor Transmission Efficiency (ή) = 65 / (65+3*5.063) = 0.8105 = 81.058% Transmission Efficiency<94 %. So this conductor is not used used . To get higher efficiency we proceed in same way and calculate efficiency finally we got the conductor “Wolf” which has efficiency 94.036%. Voltage Regulation Criterion For Conductor Wolf, This conductor has 37 strands 7Aluminum strands and 1steel strands. Diameter of each strands = 2.59mm Conductor diameter (D)=18.13mm Radius of the conductor(R)=9.065mm GMR for inductance (GMRi) =0.768R =6.1692smm
  • 8. 8 | P a g e GMR for capacitance (GMRc) = R =9.065mm Geometric mean distance(GMD)= = =8.00768m Resistance of the whole line (R) = 43.518 Ώ Inductance of Whole length (L) =2 * 10-4 ln (GMD/GMRi)*L =2e-4*ln(8.00768/ )*200 =0.2867H Capacitance of whole Length(C) = 3** ln 2 eL GMRc GMD        = =1.640µF Now Impedance of the Line (Z) = R + j 314.15 *L = 43.518+j90.0694 = 100.031<64.211 Susceptance of the Line (Y) = j314.15*C = j5.1522* e-04 = (5.1522* e-04) <90 A, B, C, D parameters calculation A = 1 + ZY/2 = 0.9768<0.657 B = Z= 100.031<64.211 C= Y (1+ZY/4) D = A Now, Sending end Voltage (Vs) = A*Vr +B*Ir = 0.9768<0.657* 220*e3/√3<0 + 100.031<64.211* 177.688<-16.26
  • 9. 9 | P a g e = 12.407*e4<0.657+17.774*e3<47.951 = 136.7502<6.1377KV Now Voltage Regulation = (|Vs|/A -|Vr| )/|Vr| = 0.1021 = 10.219% Voltage regulation < 12% so this conductor Wolf can be used. Corona Inception Voltage Criterion For wolf conductors Corona Inception voltage (Vci) = *21.1*GMR*m*δ*ln(GMD/GMR) Where, m = factor of roughness =0.9 δ = relative density of air =.95 Vci = 21.1 * 0.9065*0.9*0.95* ln (8.00768/9.065e-3) = 192.152KV Here Vci < Vs so Corona Inception Voltage criterion is met. So we go for next higher conductor. For conductor Panther GMRc=10.5mm GMD=8.00768m Vci= 21.1 * 1.05*0.9*0.95* ln (8.00768/10.5e-3) =217.748KV For conductor Lion GMRc=11.13mm GMD=8.00768m Vci= 21.1 * 1.113*0.9*0.95* ln (8.00768/11.13e-3) = 228.787KV Since Vci>Vs for conductor Lion. So no corona occurs in that conductor.
  • 10. 10 | P a g e Tension Calculation for Different Conductors with Different Span in Different Condition Four Different conductors below conductor LION in ASCR conductor table is chosen. Hence Tension calculation will be done for conductor “lion, Bear, Goat , Sheep and Dear” with Span length 250 m, 275 m, 300 m, 325 m, and 350 m. Tensions for Toughest, Stringing and Easiest condition are calculated and tabulated below. Sample calculation is also shown. Sample calculation; Conductor 1: Lion Area of conductor = 2.94 cm2 Linear expansion coefficient = 1.773 e-5 per 0 C Modulus of elasticity (E) = 7.87 e+5 kg/cm2 Tension at toughest condition (T1) = = = 5105Kg. Weight of conductor (wc) = 1097Kg/Km Wind pressure (Fw) = 100 kg/m2 Weight due to wind force (ww) = Fw*d*(2/3) =100*1000*22.26e-3*2/3 = 1484kg Weight of ice (wice) = 0 Weight for toughest condition (w1) = = 1845.444 kg Weight for the stringing and easiest condition (w2) = 1097kg. Then, the tension at stringing (T2) and the easiest condition (T3) is calculated using the following equation known as STRINGING EQUATION. T2 2 [T2+k1] - k2 = 0 ………………………………….. (1)
  • 11. 11 | P a g e Where,            AE T LW AETK 2 1 22 1 1 24 121  and, K2= AE LW 24 22 2 . From the above data, the values of K1 and K2 for the span of 250m are given by: K1 = -3210.60; K2 = 7.25e+9; Using the stringing equation, the value of T2 is found to be, T2 = 3731.26 kg. Similarly, T3 is calculated by the similar procedure as above. For the calculation of T3 the value of K1 and K2 for 250 m of length are given by: K1 = -903.54; K2 = 7.25e+9; Using the stringing equation, we get the value of T3 as: T3 = 2288.303 kg. In the similar manner, the values of tensions of different conductor for different span length is calculated and presented in the table below:
  • 12. 12 | P a g e Sag and height of tower calculation We have the relation, Maximum sag (Dmax) = (W L2 )/ (8*T3); Where, W = weight of conductor. L = length of span. T3 = tension at easiest condition. Sample calculation: For Lion, W = 1097kg/km. L = 0.25 Km. T3 =2288.303Kg. Using the above equation, Dmax = 3.74527m. Let the minimum ground clearance (hg) = 7.5m. Height of lower conductor (H1) = hg+ Dmax =11.2452m. Height of middle conductor (H2) = H1+y = 17.60m. Height of top most conductor (H3) = H2+y = 23.956m. Total height of tower (Ht) = H3+l+d = 32.6512m. Similarly, the maximum sag, H1, H2, H3 and the total height of the tower are calculated and presented in the table below: Earth wire selection From earth wire table, earth wire GUINEA is chosen as follows: No of strands = 19; diameter of a strand = 2.92mm; weight of conductor = 590kg/km; Conductor diameter = 14.60mm; conductor area = 127.20mm2 ; Ultimate tensile strength = 6664 kg; Hence, maximum tension (Te) = 6664/2 = 3332 kg. Bending moment and tower weight calculation Sample calculation: for Lion, Ht=32.6512m, 250m span Taking 80% for tower A; 15% for tower B; and 5% for tower C Due to Earth wire 1) Bending moment acting on tower due to E/W considering wind force:
  • 13. 13 | P a g e BMe1 = Fwe*Ht*Ne = (100*14.60e-3*250*2/3)*32.6512*2 = 15890.2506 kg-m. 2) Bending moment due to turning of the E/W BMe2=Fte*Ht*Ne = BMe2 = 2*Te*(sin10 *0.80 + sin7.50 *0.15 + sin150 *.05)*Ht*2 =2*3332*(0.046481)*32.6512*2 = 20227.378Kg-m Due to power conductor 1) Bending moment acting on tower due to power conductor considering wind force BMpw = Fw*(H1+H2+H3)*2 = (100*22.26e-3*250*2/3)*(11.2452+17.60+23.956)*2 = 39178.4904 kg-m 2) Bending moment due to turning of the power conductor BMpt = 2*T1*(sin10 *0.80 + sin7.50 *0.15 + sin150 *.05) *(H1+H2+H3)*2 = 2*5105*0.046481*52.8012*2 =50117.261kg-m Then the total bending moment is calculated as; BMtotal = BMe1 + BMe2 + BMpw +BMpt =125413.38 kg-m Weight of tower Weight of tower (Wt) = ; Where, Ht is in Ft; BM is in lb-ft. =0.000631*Ht* ; where, Ht is in m; Bm is in kg-m. The bending moment of different conductors at different length of span and weight of tower are calculated and shown in the tabulated form below:
  • 14. 14 | P a g e
  • 15. 15 Cost per unit length calculation Assumptions: Cost of the steel used in tower = Rs.150000 per tonne Number of towers (Nt) = ((total length)/(length of span))+1 Cost of tower per unit length = (cost per tower*Nt)/length of transmission Sample calculation: For Lion; 250m; weight of tower= 10.30955 tonne Number of tower = (200/0.25 ) +1= 801 nos Cost per tower = cost per tonne* weight of tower = Rs.150000*10.3185 = Rs. 1547775 Cost of tower per unit length = (1547775*801)/200 = Rs.6198838.875 Similarly the cost of tower per unit length of different conductor and different span are shown in table below: Most economical span and conductor selection Data available; Cost of aluminum per tonne = Rs.20150 Cost of steel per tonne = Rs. 150000 Sample calculation: For Lion; span =325m; aluminum weight per Km = 659 kg; steel weight per km = 438 kg Cost of power conductor Cost of aluminum per km = Rs. 20150*0.659 = Rs.13278.85 Cost of steel per km = Rs 150000*.438 = Rs. 65700 Total Cost of power conductor = (Rs. 13278.85 + Rs. 65700)*6 = Rs.473873.1/km From table above, Tower cost per unit length = Rs. 5915213.448
  • 16. 16 Capital cost/length = conductor cost/km + tower cost/km = Rs.473873.1+ Rs. 5915213.448 (P) =Rs. 6389086.548 Annual capital cost (A) is calculated as: A= Where i=10% and n=25 years This gives annual capital cost (A) = Rs. 703873.348 Power loss per Km PL=27.338 Kw; load loss factor (LLf)=k1*LF+K2*LF^2 = (0.2*0.5)+(0.8*0.5*0.5) =0.3 Cost of Energy loss/Km = PL *LLf * time* rate per Kwh =27.338*0.3*365*24*7.5 =Rs. 538831.98 Total annual cost = Rs. 703873.348+ Rs. 538831.98 =Rs. 1242705.328 The total annual cost calculation is shown in table below: From the above table, The minimum total annual cost is acquired by the conductor Sheep. Hence we go for the conductor Bear for the transmission line of 130 Mw and 200Km.
  • 17. 17 Transmission line characteristics of the conductor Sheep Electrical characteristics  67 strands with 7 Steel strands and 32Aluminum strands. Diameter of each strands = 3.99 mm GMR for inductance (GMRi) = 10.7251mm GMR for capacitance (GMRc) =13.965mm Resistance of the whole line per phase(R) = 18.3395Ώ Inductance of Whole length (L) =0.264H Capacitance of whole Length(C) = 1.7517 μF Now Impedance of the Line (Z) = 84.9414<77.531 Ώ Susceptance of the Line (Y) =j5.5031*e-04 siemen = 5.5031*e-04<90
  • 18. 18 A, B, C, D parameters calculation A = 1 + ZY/2 = 0.979<0.2711 B = Z= 84.9414<77.531 C = 5.440*e-04<90.146 D = A=0.979<0.2711 Now, Sending end Voltage (Vs) = A*Vr +B*Ir = 0.979<0.2711* 220/√3<0 + 84.9414<77.056* 177.688*e-03<-16.26 = 132.4296<5.9652KV Sending end current(Is) = C*Vr +D*Ir = 168.563<7.2185 Now Voltage Regulation = (|Vs|/A -|Vr| )/|Vr| = 0.0649 = 6.497% Corona Inception Voltage Criterion Corona Inception voltage (Vci) =21.1*GMR*m*δ*ln(GMD/GMR) Where, m = factor of roughness =0.9 δ = relative density of air =0.95 Vci = 21.1 * 1.3965*0.9*0.95* ln (8.00768/13.965e-3) = 277.161KV
  • 19. 19 Mechanical characteristics Length of span =350m. Tension at toughest condition = 7955kg Tension at stringing condition = 5902.87kg Tension at easiest condition = 3923.8231kg Heights: Maximum sag =6.73561 m; H1=14.2356m; H2=20.591m; H3=26.947m; Ht=35.6415m Bending moment =178830.9kg-m Tower weight=14.3985 tonne Tower Cost per unit length=Rs.6187763.968 /Km Total annual cost =Rs. 1106280.389/km