SlideShare uma empresa Scribd logo
1 de 2
Baixar para ler offline
Dulles Metro is Coming
                                                                                                                                             March 2011


Progress Marks Second Construction Anniversary
March marks the second anniversary of the start
of construction of Phase 1 of the Dulles Corridor
Metrorail Project.
On March 9, 2009, the U.S. Department of
Transportation approved a Full Funding Grant
Agreement that provided $900 million in federal
funding for the project, completing the financial
package.
Within days, construction started and the past
24 months have been filled with significant
construction successes. The landscape all along
the 11.7 miles of the Phase 1 alignment has been
altered as construction races along on this
public infrastructure project that is already
setting the stage for the transformation of
Tysons Corner.                                      READY TO CROSS I-495: This horizontal crane, or truss, is being used to build segments between piers to cre-
                                                    ate bridges to carry Dulles Rail trains across the Capital Beltway. Photo by Chuck Samuelson, Dulles Corridor
Tunnels in Tysons                                   Metrorail Project
Construction has reached the 33 percent mark, including                   •        Tysons West, in the median of Route 7 between Spring Hill
completion of the mining of both the inbound and outbound                          and Tyco roads;
tunnels under the Route 7 and Route 123 intersection where                •        Wiehle Avenue, in the median of the Dulles International
crews are now working inside both those tunnel cavities.                           Airport Access Highway/Dulles Toll Road west of Wiehle
Crews have been reinforcing the walls with steel framework                         Avenue.
and are waterproofing. A large steel arch form is being used             Along Route 7
to mold the arches.                                                      •     Relocation of 21 different utilities is almost complete along
At the ends of the mined tunnels, a “cut and cover”                            Route 7 between the Dulles Toll Road and Route 123.
construction method is being used to build the tunnel                    •     Utilities have been placed underground.
connections to the Tysons Central 7 and Tysons 123 Metrorail             •     Sidewalks have been built.
Stations.                                                                •     This mile-long stretch of Route 7 has been shifted as much
                                                                               as 60 feet to create a much wider median where the
At the Future Orange Line Connection                                           Tysons West and Tysons Central 7 Stations are being built;
At I-66 and the Dulles Connector Road (Route 267) where the                    the last lane shift near Koons Toyota will take place in April.
new rail line will connect with Metro’s Orange Line, traditional         •     Piers for the aerial bridges are almost complete.
bridge building methods are being used to erect the structure            •     Service roads along Route 7 have been removed.
to carry the tracks.                                                     •     Access to all businesses is being maintained.
Last month, night crews began working in this area as                   In the Skies at Tysons
construction accelerated. Bridge decking will be completed              Large concrete segments are being hoisted into place above
by Summer.                                                              Interstate 495 (the Capital Beltway) to build spans between piers
At the Future Metrorail Stations                                        that will be connected to create the bridges for Dulles Corridor
Construction of all five stations has started:                           Metrorail tracks. Similar bridges continue to be built along the
 •      Tysons East, along the northwest side of Route 123              northwest side of Route 123 from the Dulles Connector Road
        at Scotts Crossing Road near Capital One;                       southward to Tysons Boulevard. Crews officially began working on
 •      Tysons Central 123, on the northwest side of Route              the crossing of the Beltway in mid-February. Project officials
        123 at Tysons Boulevard near Tysons Corner Center               estimate this work will take almost a year to complete.
        and Tysons Galleria;                                            Partial and full closings of lanes on the inner and outer loops of
 •      Tysons Central 7, in the median of Route 7 west of              I-495 are required from time to time. The full closures will take
        Route 123 near SAIC and Marshalls;                              place this Summer. Advance notifications will be provided.
 For general information on the Dulles Corridor Metrorail Project, please visit our website at
                       www.dullesmetro.com or call (703) 572-0506.
Two Years of Construction in Pictures




                                            Dulles Corridor Metrorail Project photos by Stephen Barna, Chuck Samuelson
                                            and Dulles Transit Partners
1593 Spring Hill Road, Suite 300, Vienna, VA 22182 www.dullesmetro.com 703.572.0506

Mais conteúdo relacionado

Mais procurados

Bridge Engineering - Lusher Charter School (November 2016)
Bridge Engineering - Lusher Charter School (November 2016)Bridge Engineering - Lusher Charter School (November 2016)
Bridge Engineering - Lusher Charter School (November 2016)David Kanger, P.E.
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Construction of a High Level Bridge
Construction of a High Level BridgeConstruction of a High Level Bridge
Construction of a High Level BridgeIJSRD
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
I-670, North Fourth Street Exit Redesign
I-670, North Fourth Street Exit RedesignI-670, North Fourth Street Exit Redesign
I-670, North Fourth Street Exit RedesignSean Deken
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesHussein Zidan
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaT.Y. Lin International
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridgemantukr4ever
 
Sonal Gupta , Interior Design
Sonal Gupta , Interior DesignSonal Gupta , Interior Design
Sonal Gupta , Interior Designdezyneecole
 
Rohit jain 0809
Rohit jain 0809Rohit jain 0809
Rohit jain 0809Dhruv Seth
 

Mais procurados (20)

flyover and bridge problems and its solutions
flyover and bridge problems and its solutionsflyover and bridge problems and its solutions
flyover and bridge problems and its solutions
 
CHENAB BRIDGE
CHENAB BRIDGECHENAB BRIDGE
CHENAB BRIDGE
 
ASCEMLSTPRESENTATION 05-06-03.PPT
ASCEMLSTPRESENTATION 05-06-03.PPTASCEMLSTPRESENTATION 05-06-03.PPT
ASCEMLSTPRESENTATION 05-06-03.PPT
 
Construction of bridges
Construction of bridgesConstruction of bridges
Construction of bridges
 
Chenab bridge ppt
Chenab bridge pptChenab bridge ppt
Chenab bridge ppt
 
Bridges construction
Bridges constructionBridges construction
Bridges construction
 
Senior Project PSR
Senior Project PSRSenior Project PSR
Senior Project PSR
 
Bridge Engineering - Lusher Charter School (November 2016)
Bridge Engineering - Lusher Charter School (November 2016)Bridge Engineering - Lusher Charter School (November 2016)
Bridge Engineering - Lusher Charter School (November 2016)
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Construction of a High Level Bridge
Construction of a High Level BridgeConstruction of a High Level Bridge
Construction of a High Level Bridge
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
I-670, North Fourth Street Exit Redesign
I-670, North Fourth Street Exit RedesignI-670, North Fourth Street Exit Redesign
I-670, North Fourth Street Exit Redesign
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed Bridges
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridge
 
Sonal Gupta , Interior Design
Sonal Gupta , Interior DesignSonal Gupta , Interior Design
Sonal Gupta , Interior Design
 
Chenab Bridge
Chenab BridgeChenab Bridge
Chenab Bridge
 
Rohit jain 0809
Rohit jain 0809Rohit jain 0809
Rohit jain 0809
 
Bridges
BridgesBridges
Bridges
 

Destaque

Your Home will be Everywhere!
Your Home will be Everywhere!Your Home will be Everywhere!
Your Home will be Everywhere!Brian Block
 
Fuller presentation nvar economic summit
Fuller presentation nvar economic summitFuller presentation nvar economic summit
Fuller presentation nvar economic summitBrian Block
 
Dulles metro construction update oct 2010
Dulles metro construction update oct 2010Dulles metro construction update oct 2010
Dulles metro construction update oct 2010Brian Block
 
Dulles Metro June 2012
Dulles Metro June 2012Dulles Metro June 2012
Dulles Metro June 2012Brian Block
 
Construction of joka majherhat phase-i metro corridor considering the requir...
Construction of joka  majherhat phase-i metro corridor considering the requir...Construction of joka  majherhat phase-i metro corridor considering the requir...
Construction of joka majherhat phase-i metro corridor considering the requir...Rajesh Prasad
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyIPPAI
 

Destaque (7)

Your Home will be Everywhere!
Your Home will be Everywhere!Your Home will be Everywhere!
Your Home will be Everywhere!
 
Fuller presentation nvar economic summit
Fuller presentation nvar economic summitFuller presentation nvar economic summit
Fuller presentation nvar economic summit
 
Dulles metro construction update oct 2010
Dulles metro construction update oct 2010Dulles metro construction update oct 2010
Dulles metro construction update oct 2010
 
Dulles Metro June 2012
Dulles Metro June 2012Dulles Metro June 2012
Dulles Metro June 2012
 
Construction of joka majherhat phase-i metro corridor considering the requir...
Construction of joka  majherhat phase-i metro corridor considering the requir...Construction of joka  majherhat phase-i metro corridor considering the requir...
Construction of joka majherhat phase-i metro corridor considering the requir...
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
 
Hyderabad Metro Rail Project
Hyderabad Metro Rail ProjectHyderabad Metro Rail Project
Hyderabad Metro Rail Project
 

Semelhante a Dulles Metro Progress Marks 2nd Construction Anniversary

Update on Dulles Metro Construction - Tysons Corner
Update on Dulles Metro Construction - Tysons CornerUpdate on Dulles Metro Construction - Tysons Corner
Update on Dulles Metro Construction - Tysons CornerBrian Block
 
RMS121_Viaduct_construction_Factsheet_FINAL_print_no_trim
RMS121_Viaduct_construction_Factsheet_FINAL_print_no_trimRMS121_Viaduct_construction_Factsheet_FINAL_print_no_trim
RMS121_Viaduct_construction_Factsheet_FINAL_print_no_trimHudson Bawden
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown UpdateCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Crosstown TO
 
Silver Line Update (February 2013 Meeting)
Silver Line Update (February 2013 Meeting)Silver Line Update (February 2013 Meeting)
Silver Line Update (February 2013 Meeting)novacsi
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Golden gate bridge 2
Golden gate bridge 2Golden gate bridge 2
Golden gate bridge 2caltec
 
Finishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes DigestFinishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes DigestPhilip Tunnah
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 

Semelhante a Dulles Metro Progress Marks 2nd Construction Anniversary (20)

Update on Dulles Metro Construction - Tysons Corner
Update on Dulles Metro Construction - Tysons CornerUpdate on Dulles Metro Construction - Tysons Corner
Update on Dulles Metro Construction - Tysons Corner
 
August
August August
August
 
RMS121_Viaduct_construction_Factsheet_FINAL_print_no_trim
RMS121_Viaduct_construction_Factsheet_FINAL_print_no_trimRMS121_Viaduct_construction_Factsheet_FINAL_print_no_trim
RMS121_Viaduct_construction_Factsheet_FINAL_print_no_trim
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Silver Line Update (February 2013 Meeting)
Silver Line Update (February 2013 Meeting)Silver Line Update (February 2013 Meeting)
Silver Line Update (February 2013 Meeting)
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Golden gate bridge 2
Golden gate bridge 2Golden gate bridge 2
Golden gate bridge 2
 
Finishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes DigestFinishing Strong_July 2014_Water & Wastes Digest
Finishing Strong_July 2014_Water & Wastes Digest
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 

Mais de Brian Block

8353 moline place brochure
8353 moline place brochure8353 moline place brochure
8353 moline place brochureBrian Block
 
Virginia real estate 1st quarter report
Virginia real estate 1st quarter reportVirginia real estate 1st quarter report
Virginia real estate 1st quarter reportBrian Block
 
Trends in Virginia Housing Market - 1st Quarter 2010
Trends in Virginia Housing Market - 1st Quarter 2010Trends in Virginia Housing Market - 1st Quarter 2010
Trends in Virginia Housing Market - 1st Quarter 2010Brian Block
 
Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010Brian Block
 
Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010Brian Block
 
Economic and Real Estate Market Update from National Association of REALTORS
Economic and Real Estate Market Update from National Association of REALTORSEconomic and Real Estate Market Update from National Association of REALTORS
Economic and Real Estate Market Update from National Association of REALTORSBrian Block
 

Mais de Brian Block (6)

8353 moline place brochure
8353 moline place brochure8353 moline place brochure
8353 moline place brochure
 
Virginia real estate 1st quarter report
Virginia real estate 1st quarter reportVirginia real estate 1st quarter report
Virginia real estate 1st quarter report
 
Trends in Virginia Housing Market - 1st Quarter 2010
Trends in Virginia Housing Market - 1st Quarter 2010Trends in Virginia Housing Market - 1st Quarter 2010
Trends in Virginia Housing Market - 1st Quarter 2010
 
Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010
 
Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010Trends in Virginia's Housing Markets - 1st Quarter 2010
Trends in Virginia's Housing Markets - 1st Quarter 2010
 
Economic and Real Estate Market Update from National Association of REALTORS
Economic and Real Estate Market Update from National Association of REALTORSEconomic and Real Estate Market Update from National Association of REALTORS
Economic and Real Estate Market Update from National Association of REALTORS
 

Último

FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | GurgaonFULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaonsoniya singh
 
call girls in lajapat nagar 9811711561/..
call girls in lajapat nagar 9811711561/..call girls in lajapat nagar 9811711561/..
call girls in lajapat nagar 9811711561/..vikas rana
 
Sankla East World Hadapsar Pune E-Brochure.pdf
Sankla East World Hadapsar Pune  E-Brochure.pdfSankla East World Hadapsar Pune  E-Brochure.pdf
Sankla East World Hadapsar Pune E-Brochure.pdfManishSaxena95
 
3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGIPanoram CGI
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needsaidasheikh47
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Pooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired Fantasies
Pooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired FantasiesPooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired Fantasies
Pooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired FantasiesPooja Nehwal
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...delhimodel235
 
Omaxe Dwarka In Delhi E Brochure Pdf
Omaxe Dwarka In Delhi E Brochure     PdfOmaxe Dwarka In Delhi E Brochure     Pdf
Omaxe Dwarka In Delhi E Brochure Pdfashiyadav24
 
The Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdfThe Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdfkratirudram
 
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...delhimodel235
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDFMs Riya
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruShivaSeo3
 
Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCRGirls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCRasmaqueen5
 
Listing Turkey Sylvana Istanbul - Bahcesehir
Listing Turkey Sylvana Istanbul - BahcesehirListing Turkey Sylvana Istanbul - Bahcesehir
Listing Turkey Sylvana Istanbul - BahcesehirListing Turkey
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝soniya singh
 

Último (20)

FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | GurgaonFULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
 
call girls in lajapat nagar 9811711561/..
call girls in lajapat nagar 9811711561/..call girls in lajapat nagar 9811711561/..
call girls in lajapat nagar 9811711561/..
 
Sankla East World Hadapsar Pune E-Brochure.pdf
Sankla East World Hadapsar Pune  E-Brochure.pdfSankla East World Hadapsar Pune  E-Brochure.pdf
Sankla East World Hadapsar Pune E-Brochure.pdf
 
3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
 
Pooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired Fantasies
Pooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired FantasiesPooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired Fantasies
Pooja Mehta 9167673311 Get Warm Welcome By Andheri Escorts For Desired Fantasies
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
 
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
 
Omaxe Dwarka In Delhi E Brochure Pdf
Omaxe Dwarka In Delhi E Brochure     PdfOmaxe Dwarka In Delhi E Brochure     Pdf
Omaxe Dwarka In Delhi E Brochure Pdf
 
The Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdfThe Omaxe State Dwarka Delhi-broucher.pdf.pdf
The Omaxe State Dwarka Delhi-broucher.pdf.pdf
 
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
 
Find Furnished Short Term Rentals in Minneapolis | CHBO
Find Furnished Short Term Rentals in Minneapolis | CHBOFind Furnished Short Term Rentals in Minneapolis | CHBO
Find Furnished Short Term Rentals in Minneapolis | CHBO
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
 
VIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts Service
VIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts ServiceVIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts Service
VIP Escorts in Delhi:🔝9953056974🔝 Hot Qutub Minar Delhi Escorts Service
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road Bengaluru
 
Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Shastri Nagar Delhi reach out to us at 🔝8264348440🔝
 
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCRGirls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
 
Listing Turkey Sylvana Istanbul - Bahcesehir
Listing Turkey Sylvana Istanbul - BahcesehirListing Turkey Sylvana Istanbul - Bahcesehir
Listing Turkey Sylvana Istanbul - Bahcesehir
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
 

Dulles Metro Progress Marks 2nd Construction Anniversary

  • 1. Dulles Metro is Coming March 2011 Progress Marks Second Construction Anniversary March marks the second anniversary of the start of construction of Phase 1 of the Dulles Corridor Metrorail Project. On March 9, 2009, the U.S. Department of Transportation approved a Full Funding Grant Agreement that provided $900 million in federal funding for the project, completing the financial package. Within days, construction started and the past 24 months have been filled with significant construction successes. The landscape all along the 11.7 miles of the Phase 1 alignment has been altered as construction races along on this public infrastructure project that is already setting the stage for the transformation of Tysons Corner. READY TO CROSS I-495: This horizontal crane, or truss, is being used to build segments between piers to cre- ate bridges to carry Dulles Rail trains across the Capital Beltway. Photo by Chuck Samuelson, Dulles Corridor Tunnels in Tysons Metrorail Project Construction has reached the 33 percent mark, including • Tysons West, in the median of Route 7 between Spring Hill completion of the mining of both the inbound and outbound and Tyco roads; tunnels under the Route 7 and Route 123 intersection where • Wiehle Avenue, in the median of the Dulles International crews are now working inside both those tunnel cavities. Airport Access Highway/Dulles Toll Road west of Wiehle Crews have been reinforcing the walls with steel framework Avenue. and are waterproofing. A large steel arch form is being used Along Route 7 to mold the arches. • Relocation of 21 different utilities is almost complete along At the ends of the mined tunnels, a “cut and cover” Route 7 between the Dulles Toll Road and Route 123. construction method is being used to build the tunnel • Utilities have been placed underground. connections to the Tysons Central 7 and Tysons 123 Metrorail • Sidewalks have been built. Stations. • This mile-long stretch of Route 7 has been shifted as much as 60 feet to create a much wider median where the At the Future Orange Line Connection Tysons West and Tysons Central 7 Stations are being built; At I-66 and the Dulles Connector Road (Route 267) where the the last lane shift near Koons Toyota will take place in April. new rail line will connect with Metro’s Orange Line, traditional • Piers for the aerial bridges are almost complete. bridge building methods are being used to erect the structure • Service roads along Route 7 have been removed. to carry the tracks. • Access to all businesses is being maintained. Last month, night crews began working in this area as In the Skies at Tysons construction accelerated. Bridge decking will be completed Large concrete segments are being hoisted into place above by Summer. Interstate 495 (the Capital Beltway) to build spans between piers At the Future Metrorail Stations that will be connected to create the bridges for Dulles Corridor Construction of all five stations has started: Metrorail tracks. Similar bridges continue to be built along the • Tysons East, along the northwest side of Route 123 northwest side of Route 123 from the Dulles Connector Road at Scotts Crossing Road near Capital One; southward to Tysons Boulevard. Crews officially began working on • Tysons Central 123, on the northwest side of Route the crossing of the Beltway in mid-February. Project officials 123 at Tysons Boulevard near Tysons Corner Center estimate this work will take almost a year to complete. and Tysons Galleria; Partial and full closings of lanes on the inner and outer loops of • Tysons Central 7, in the median of Route 7 west of I-495 are required from time to time. The full closures will take Route 123 near SAIC and Marshalls; place this Summer. Advance notifications will be provided. For general information on the Dulles Corridor Metrorail Project, please visit our website at www.dullesmetro.com or call (703) 572-0506.
  • 2. Two Years of Construction in Pictures Dulles Corridor Metrorail Project photos by Stephen Barna, Chuck Samuelson and Dulles Transit Partners 1593 Spring Hill Road, Suite 300, Vienna, VA 22182 www.dullesmetro.com 703.572.0506