SlideShare uma empresa Scribd logo
1 de 30
DSV Bibby Topaz
Incident 18th Sept 2012
Agenda

•   Welcome & introductions
•   Investigation team & TOR
•   Incident Timeline
•   Emergency Response notification
•   Diver Medical Treatment Timeline
•   Vessel Assurance
•   Lessons Learned
Investigation
• Internal Investigation Team
   – Gail Ritchie, Lead Risk & Safety Advisor (Team Lead)
   – Katherine Meffen, Risk & Safety Advisor
   – Barry Porter, Diving Operations Manager
   – Tom Paling, OSS General Manager
   – Martyn Ramsbottom, Marine Superintendent
   – Chris Cleghorn, Offshore Risk & Safety Advisor
• External Investigation Team
   – EON (Client)
   – Kongsberg
   – Health & Safety Executive
   – Noble Denton
   – Wartsila
Investigation
• Terms of Reference (5 Barrier Analysis)
   – Design;
   – Maintenance;
   – Process / Procedures;
   – Competence;
   – Behaviours;
Investigation - References
• Witness statements / interviews;
   – Dive team, ROV, Bridge, Marine, Survey,
• Blackbox;
   – Diver 1 & 2 hat camera / audio, Dive Supervisor audio, Bell interior & exterior,
     ROV, Bridge VDR
• Logs;
   – Dive, DP log, DP alarm, Bridge, Survey, DPR
• Design;
   – FMECA, DP Control System (Software & Hardware)
• Documentation;
   – Vessel Assurance, FMEA, Dive & Vessels Ops Manual, Emergency
     Contingency Manuals, Subsea Installation procedures, project risk
     management, TM Master PMS, Change Management, Competence &
     Training records,
DSV Bibby Topaz – Build 2008




• Propulsion
   – 2 x Main Propulsion , 2 x Retractable Azimuth, 2 x Tunnel Thrusters (1 fwd &
     1 aft)
• Reference Systems
   – 2 x DGPS; Kongsberg, 2 x HIPAP; Kongsberg,
   – 2 x Light Taut Wire, 1 x RadaScan
Scope of Work
•   Development of Huntington Field as a subsea tieback to FPSO
•   Date 18th Sept 2012
•   Water depth 91m
•   Weather;
     – Wind NW
     – Wind speed gusting up to 30 kts
     – Sig wave height 4.0m
• 2 x DGPS, 2 x HiPap, 1 x taut wire
• 3 Generators online
• 5 out of 6 thrusters running & selected into DP
• Thruster 4, stern thruster shut down
Scope of Work
• Vessel set up west of drilling template
• MOC conducted addressing change of opening roof panel to gaining
  access from side
• Spool metrology within Drilling Template
• Venting annulus gas prior to barrier testing
• HPPS Downline deployed
• Tugger line deployed
Time Line
• 20.13 - Dive 047, starboard bell locked off
• 20.31 – Bell at depth
    – Bell located upstream of template structure
• 20.37 – diver 2 left bell
• 20.46 – diver 1 left bell
    – Divers umbilical length into template – 27m from bell
Time Line – 20.49 to 22.09
• Diver 1 & 2 located
  inside drilling
  template structure
  carrying out barrier
  testing activities
• ROV monitoring
Time Line - 22.09
• Alarm for ‘RBUS’
  activated
• DP amber alert activated
• Vessel starts to drift
• Master & Dive Control
  informed
• Dive Supervisor
  instructed divers to leave
  structure and locate to
  bell stage
• Attempts made to
  reselect thrusters into DP
Vessel Tracking
Time Line – 22.11
• DP Red alert activated
• Vessel continued drifting
  to East, all references &
  thrusters unavailable to
  DP                           Easterly Direction

• Master switched from DP
  to manual thruster control
• Standby generator started
  with thruster 4
• Diver 1 & 2 located onto
  top of template
Time Line – 22.12
• Diver 2 umbilical
  snagged on transponder
  bucket located on side of
  structure
• Diver 1 pulled off          Easterly Direction
  template
• Momentary loss of
  comms to bell
Time Line – 22.13 to 22.15
•   Loss of comms / video to diver 2; umbilical severed
•   Diver 1 made way back to bell stage
•   OPM relocated from Dive Control to Bridge
•   Port Taut Wire stowed (wire parted)
•   Downline and tugger parted
Time Line – 22.17
• Vessel position 240m East of Drilling Template
• Vessel being manually driven using fwd and aft azimuths
• Chief Officer on thrusters 2 & 3, Master on main propulsion thrusters 5
  &6
• Diver 2 locator beacon
                                                 240m
  identified to be at
  template
Time Line - 22.29 – 22.34
•   ROV back at Drilling Template
•   Diver 2 located on top of template
                                         150m
•   DP controllers power recycled
•   Vessel back on full auto DP
Time Line – 22.40
• Vessel back at Drilling
  Template
• Diver 1 left stage, bell
  18m from template
• Recovery of Diver 2
  commenced
Time Line – 22.46
 Investigation
• Diver 2 recovered to
  bell, unconscious &
  breathing
• 23.04 Diver 2 stable,
  vital signs good,
  talking
• 23.13 Bell sealed and
  left bottom
• 23.38 Bell locked on
• 23.50 ROV recovered
• 24.00 commenced
  transit to port
Emergency Response

•   OPM - Call made to ERSC
•   Master - Call made to BSM
•   ERSC - Call made to Duty Manager
•   ERSC – Call made to BSM
•   ERSC – Call made to Client
•   Duty Manager – Call made to Project Manager
•   Duty Manager – Call made to Snr Management
•   Snr Management discussion
•   Vessel made way to Port
•   Snr Management meeting early morning
Medical Treatment
• 18th 22.30 - Medic reported to dive control to assess the situation.
• 22.46 - Diver recovered back into bell, appeared to be unconscious
  with shallow breathing
   − Diver regained consciousness & movement of digits ; gripping
      hand of the bellman
• 23.15 - DMAC 15 equipment sent into chamber 1 (medical
  chamber) ; defibrillator, stretcher & neck brace in situ
• 23.38 - Diver climbed down steps from bell with assistance from the
  other divers
   − Diver core temp raised, fluid replacement
• 19th 00.45 - Medic contacted Capita Dive Dr; satisfied with progress
Medical Treatment
• 02.00 - Diver stable, moved onto ½ hrly observations
• 03.00 - hrly observations commenced
• 07.45 - Dive Dr granted permission for diver to commence
  decompression (12 man team commenced deco)
• 15.00 - Dive Dr onboard to speak to diver; 4hrly observations
  commenced
• 20th 06.00 - good progress, 8 hrly observations commenced
• 22nd 13.20 - Decompression completed
   − Diver met by Dive Dr, post sat medical completed
   − Councillor available for teams
• 23rd - Further examination at Capita Health Solutions
Vessel Assurance – DP System
• Determine the fault which caused loss of control of the thrusters
  along with loss of all reference & environmental signals to the DP
  control system
• Assess actions of personnel re change status of the DP control
• Assessment & analysis of DP alarm log / printout
• Conduct non-intrusive testing of Software & Hardware
• Interrogation of software
• Interrogation of bridge VDR
• FMEA review
• DP proving trials schedule for testing and verification of the system
Vessel Assurance – DP System
• Testing on the system to try to replicate the failure, in conjunction
  with the testing on the switchboards; in accordance with DNV
  approved trials schedule .
• Able to replicate the failure of the module to provide the various
  alarms that were seen on the 18th
• All options exhausted in terms of testing on the vessel; DNV
  agreement
• DP hardware replaced & existing units taken off & sent back to
  Norway; DNV agreement
• Power management system testing carried out
• Kongsberg disassembling module by module to fully substantiate
  root cause of the failure
• DP FMEA proving trials conducted
Immediate Causal Factors
• Communication jamming of the RBUS network caused loss of
  control of the thrusters along with loss of all reference and
  environmental signals to the DP control system and resulted in
  vessel losing position and drift off
• Vessel loss of position and Diver 2 umbilical snagging on
  transponder bucket located on side of template resulted in diver 2
  umbilical being severed.
Underlying Causal Factors
• Several anomalies found relating to electrical grounding, shielding &
  electrical noise.
• Fault mechanism behind the RBUS communication error related to
  jamming of the RBUS; based the results from testing & comparing
  sequence of events from the tests with what was observed on-
  board.
• RBUS communication problems started due to a rare sequence of
  events involving the combined effects of the findings and a failure(s)
  in one or more modules in the DPC-3 cabinet.
• One or more module(s) in the DPC-3 cabinet could have been
  degraded due the long term effects
• Transponder buckets not identified as potential snag hazards for
  operations being carried out
• Not removed prior to work starting in the structure.
Root Causal Factors
• Due to the lack of a well-defined root cause KM shipped all
  components that were present in the DPC-3 cabinet at the time of
  the incident to Kongsberg head office to undergo a thorough
  manufacturing test.
• This is being done to include or exclude a possible fault in a specific
  module.
DP Control System
                                                                  Operator Stations




                                      RCU (Remote                  RCU (Remote                    RCU (Remote                      Controllers - Bridge DP computers
                                      Control Unit)                Control Unit)                  Control Unit)
                                       Controller                   Controller                     Controller


                                                  RHUB (Network                       RHUB (Network
                              24Vdc                  Hub)                                Hub)                     24Vdc           Each of the RHUB (Network Hub) has two
                UPS 1                                                                                                     UPS 2
                230V                                                                                                      230V    24Vdc power supplies
                              24Vdc                                                                               24Vdc

                                                                                                                                  Information from the RIO Units are
                                      RBUS Network A                                          RBUS Network B                      conveyed to the controllers via 2
                                                                                                                                  dedicated RBUS Networks; A & B
 Reference
  systems /                                                                                                                       Remote Input Output (RIO) units. Take all
                        RIO            RIO            RIO                        RIO             RIO         RIO
Environmental                                                                                                                     feedback from the reference &
  Sensors                                                                                                                         environmental sensors along with
                                                                                                                                  command & feedback signals for the
                                                                                                                                  thrusters. Each Thruster has RIO unit
Dive System Assurance
• Starboard main bell umbilical
   − cables checked for insulation, continuity & resistance
   − pressure leak tested to maximum working pressure
• Diver 2 excursion umbilical (55mtr) replaced, Diver 1 excursion
  umbilical (55mtr) serviced
• The Diver 2 hat and neck dam fully serviced
• Diver 2 umbilical horns inside Starboard bell removed &
  straightened
• Bell wires & Guide weight wires have been cut back and re-
  terminated & load tested
• All excursion umbilical 6 monthly testing has been completed.
• The Stbd tools winch wire replaced
Lessons Learned

• Conduct engagement sessions with internal & external stakeholders
• Share incident and lessons learned with industry; IMCA, OGP,
  Subsea UK, Stepchange
• Initiate project to look into enhancement of diver safety using
  experiences from this incident
• Review FMEA / FMECA documentation
• Review emergency response & contingency planning process,
  procedures, drills, exercises
• Review media liaison arrangements

Mais conteúdo relacionado

Mais procurados

Basic stability 1
Basic stability 1Basic stability 1
Basic stability 1Acex Aribal
 
Dynamic Positioning & Power Management Awareness Training
Dynamic Positioning & Power Management Awareness TrainingDynamic Positioning & Power Management Awareness Training
Dynamic Positioning & Power Management Awareness TrainingLloyd's Register Energy
 
Lect 9 ship propellers (new)
Lect 9 ship propellers (new)Lect 9 ship propellers (new)
Lect 9 ship propellers (new)Saif Alenzi
 
Parts of a ship1
Parts of a ship1Parts of a ship1
Parts of a ship1Ruranha
 
offshore support vessel design
offshore support vessel designoffshore support vessel design
offshore support vessel designAhmed Taha
 
Container Securing System for ships
Container Securing System for shipsContainer Securing System for ships
Container Securing System for shipsPawanexh Kohli
 
TankerCalc for Bunker Surveyors
TankerCalc for Bunker SurveyorsTankerCalc for Bunker Surveyors
TankerCalc for Bunker SurveyorsMd. Moynul Islam
 
Shipping industry-guidance-on-pilot-transfer-arrangements
Shipping industry-guidance-on-pilot-transfer-arrangementsShipping industry-guidance-on-pilot-transfer-arrangements
Shipping industry-guidance-on-pilot-transfer-arrangementsblacks0u1
 
Dökme yük gemilerinde boyuna mukavemet analizi
Dökme yük gemilerinde boyuna mukavemet analiziDökme yük gemilerinde boyuna mukavemet analizi
Dökme yük gemilerinde boyuna mukavemet analiziSevilay Can
 
Structural rules bulk and tanker
Structural rules bulk and tankerStructural rules bulk and tanker
Structural rules bulk and tankerGeorge Teriakidis
 
Celestial navigation 2014 (pdf)
Celestial navigation 2014 (pdf)Celestial navigation 2014 (pdf)
Celestial navigation 2014 (pdf)Chia-Yi Yen
 

Mais procurados (20)

Basic stability 1
Basic stability 1Basic stability 1
Basic stability 1
 
Dynamic Positioning & Power Management Awareness Training
Dynamic Positioning & Power Management Awareness TrainingDynamic Positioning & Power Management Awareness Training
Dynamic Positioning & Power Management Awareness Training
 
Lect 9 ship propellers (new)
Lect 9 ship propellers (new)Lect 9 ship propellers (new)
Lect 9 ship propellers (new)
 
Ship's Transverse Stability
Ship's Transverse StabilityShip's Transverse Stability
Ship's Transverse Stability
 
Stability of ships
Stability of shipsStability of ships
Stability of ships
 
Parts of a ship1
Parts of a ship1Parts of a ship1
Parts of a ship1
 
SEAM-5-GROUP-5.pptx
SEAM-5-GROUP-5.pptxSEAM-5-GROUP-5.pptx
SEAM-5-GROUP-5.pptx
 
offshore support vessel design
offshore support vessel designoffshore support vessel design
offshore support vessel design
 
Container Securing System for ships
Container Securing System for shipsContainer Securing System for ships
Container Securing System for ships
 
TankerCalc for Bunker Surveyors
TankerCalc for Bunker SurveyorsTankerCalc for Bunker Surveyors
TankerCalc for Bunker Surveyors
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
 
Shipping industry-guidance-on-pilot-transfer-arrangements
Shipping industry-guidance-on-pilot-transfer-arrangementsShipping industry-guidance-on-pilot-transfer-arrangements
Shipping industry-guidance-on-pilot-transfer-arrangements
 
Ship Motion and Stresses
Ship Motion and StressesShip Motion and Stresses
Ship Motion and Stresses
 
Dökme yük gemilerinde boyuna mukavemet analizi
Dökme yük gemilerinde boyuna mukavemet analiziDökme yük gemilerinde boyuna mukavemet analizi
Dökme yük gemilerinde boyuna mukavemet analizi
 
Structural rules bulk and tanker
Structural rules bulk and tankerStructural rules bulk and tanker
Structural rules bulk and tanker
 
Celestial navigation 2014 (pdf)
Celestial navigation 2014 (pdf)Celestial navigation 2014 (pdf)
Celestial navigation 2014 (pdf)
 
Walk to work offshore
Walk to work offshoreWalk to work offshore
Walk to work offshore
 
Ship Rudder
Ship RudderShip Rudder
Ship Rudder
 
Bunker survey calculation
Bunker survey calculationBunker survey calculation
Bunker survey calculation
 
Wk 3 effect of free surface of liquids
Wk 3 effect of free surface of liquidsWk 3 effect of free surface of liquids
Wk 3 effect of free surface of liquids
 

Destaque (6)

20041201 - IMCA Presentation: DP in a hurry - December 2004, Singapore
20041201 - IMCA Presentation: DP in a hurry - December 2004, Singapore20041201 - IMCA Presentation: DP in a hurry - December 2004, Singapore
20041201 - IMCA Presentation: DP in a hurry - December 2004, Singapore
 
Dp Presentation
Dp PresentationDp Presentation
Dp Presentation
 
Resume Siripong E42
Resume Siripong E42Resume Siripong E42
Resume Siripong E42
 
Bombay high
Bombay highBombay high
Bombay high
 
Dynamic positioning
Dynamic positioningDynamic positioning
Dynamic positioning
 
CV.2016
CV.2016CV.2016
CV.2016
 

Semelhante a Incident summary 08.10.12 "Bibby Topaz"

Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Sarthak Panigrahi
 
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.144.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14Kristipoom R-khubut
 
Julie.webster
Julie.websterJulie.webster
Julie.websterNASAPMC
 
INPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPINPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPD. Alan Day
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
R1_Project - QC Safety System
R1_Project - QC Safety SystemR1_Project - QC Safety System
R1_Project - QC Safety SystemBhupendra Meher
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptxTalhaAbdulRehman2
 
Significant incident review 415 v arc flash - Michael Wood
Significant incident review   415 v arc flash - Michael WoodSignificant incident review   415 v arc flash - Michael Wood
Significant incident review 415 v arc flash - Michael WoodNSW Environment and Planning
 
Ess.robert
Ess.robertEss.robert
Ess.robertNASAPMC
 
Restoration Drill & Pre-Drill Training ; System Restoration Overview
Restoration Drill & Pre-Drill Training ; System Restoration OverviewRestoration Drill & Pre-Drill Training ; System Restoration Overview
Restoration Drill & Pre-Drill Training ; System Restoration OverviewPower System Operation
 
Thermo scientific pro line overview - sales training
Thermo scientific pro line overview - sales trainingThermo scientific pro line overview - sales training
Thermo scientific pro line overview - sales trainingTechno Service
 
HV Interface Presentation (1)
HV Interface Presentation (1)HV Interface Presentation (1)
HV Interface Presentation (1)paul doherty
 
Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer
 
Nonlinear hydrodynamic forces - manufacture and transducer selection
Nonlinear hydrodynamic forces - manufacture and transducer selectionNonlinear hydrodynamic forces - manufacture and transducer selection
Nonlinear hydrodynamic forces - manufacture and transducer selectionSachindra Max
 

Semelhante a Incident summary 08.10.12 "Bibby Topaz" (20)

Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System
 
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.144.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
 
Julie.webster
Julie.websterJulie.webster
Julie.webster
 
Shell Subsea Control.pdf
Shell Subsea Control.pdfShell Subsea Control.pdf
Shell Subsea Control.pdf
 
INPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPINPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRP
 
Power System Restoration Drill
Power System Restoration DrillPower System Restoration Drill
Power System Restoration Drill
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
R1_Project - QC Safety System
R1_Project - QC Safety SystemR1_Project - QC Safety System
R1_Project - QC Safety System
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
Significant incident review 415 v arc flash - Michael Wood
Significant incident review   415 v arc flash - Michael WoodSignificant incident review   415 v arc flash - Michael Wood
Significant incident review 415 v arc flash - Michael Wood
 
Ess.robert
Ess.robertEss.robert
Ess.robert
 
Restoration Drill & Pre-Drill Training ; System Restoration Overview
Restoration Drill & Pre-Drill Training ; System Restoration OverviewRestoration Drill & Pre-Drill Training ; System Restoration Overview
Restoration Drill & Pre-Drill Training ; System Restoration Overview
 
Thermo scientific pro line overview - sales training
Thermo scientific pro line overview - sales trainingThermo scientific pro line overview - sales training
Thermo scientific pro line overview - sales training
 
HV Interface Presentation (1)
HV Interface Presentation (1)HV Interface Presentation (1)
HV Interface Presentation (1)
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
Iain Palmer Resume 29012015
Iain Palmer Resume 29012015Iain Palmer Resume 29012015
Iain Palmer Resume 29012015
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Nonlinear hydrodynamic forces - manufacture and transducer selection
Nonlinear hydrodynamic forces - manufacture and transducer selectionNonlinear hydrodynamic forces - manufacture and transducer selection
Nonlinear hydrodynamic forces - manufacture and transducer selection
 

Último

Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Último (20)

Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 

Incident summary 08.10.12 "Bibby Topaz"

  • 1. DSV Bibby Topaz Incident 18th Sept 2012
  • 2. Agenda • Welcome & introductions • Investigation team & TOR • Incident Timeline • Emergency Response notification • Diver Medical Treatment Timeline • Vessel Assurance • Lessons Learned
  • 3. Investigation • Internal Investigation Team – Gail Ritchie, Lead Risk & Safety Advisor (Team Lead) – Katherine Meffen, Risk & Safety Advisor – Barry Porter, Diving Operations Manager – Tom Paling, OSS General Manager – Martyn Ramsbottom, Marine Superintendent – Chris Cleghorn, Offshore Risk & Safety Advisor • External Investigation Team – EON (Client) – Kongsberg – Health & Safety Executive – Noble Denton – Wartsila
  • 4. Investigation • Terms of Reference (5 Barrier Analysis) – Design; – Maintenance; – Process / Procedures; – Competence; – Behaviours;
  • 5. Investigation - References • Witness statements / interviews; – Dive team, ROV, Bridge, Marine, Survey, • Blackbox; – Diver 1 & 2 hat camera / audio, Dive Supervisor audio, Bell interior & exterior, ROV, Bridge VDR • Logs; – Dive, DP log, DP alarm, Bridge, Survey, DPR • Design; – FMECA, DP Control System (Software & Hardware) • Documentation; – Vessel Assurance, FMEA, Dive & Vessels Ops Manual, Emergency Contingency Manuals, Subsea Installation procedures, project risk management, TM Master PMS, Change Management, Competence & Training records,
  • 6. DSV Bibby Topaz – Build 2008 • Propulsion – 2 x Main Propulsion , 2 x Retractable Azimuth, 2 x Tunnel Thrusters (1 fwd & 1 aft) • Reference Systems – 2 x DGPS; Kongsberg, 2 x HIPAP; Kongsberg, – 2 x Light Taut Wire, 1 x RadaScan
  • 7. Scope of Work • Development of Huntington Field as a subsea tieback to FPSO • Date 18th Sept 2012 • Water depth 91m • Weather; – Wind NW – Wind speed gusting up to 30 kts – Sig wave height 4.0m • 2 x DGPS, 2 x HiPap, 1 x taut wire • 3 Generators online • 5 out of 6 thrusters running & selected into DP • Thruster 4, stern thruster shut down
  • 8. Scope of Work • Vessel set up west of drilling template • MOC conducted addressing change of opening roof panel to gaining access from side • Spool metrology within Drilling Template • Venting annulus gas prior to barrier testing • HPPS Downline deployed • Tugger line deployed
  • 9. Time Line • 20.13 - Dive 047, starboard bell locked off • 20.31 – Bell at depth – Bell located upstream of template structure • 20.37 – diver 2 left bell • 20.46 – diver 1 left bell – Divers umbilical length into template – 27m from bell
  • 10. Time Line – 20.49 to 22.09 • Diver 1 & 2 located inside drilling template structure carrying out barrier testing activities • ROV monitoring
  • 11. Time Line - 22.09 • Alarm for ‘RBUS’ activated • DP amber alert activated • Vessel starts to drift • Master & Dive Control informed • Dive Supervisor instructed divers to leave structure and locate to bell stage • Attempts made to reselect thrusters into DP
  • 13. Time Line – 22.11 • DP Red alert activated • Vessel continued drifting to East, all references & thrusters unavailable to DP Easterly Direction • Master switched from DP to manual thruster control • Standby generator started with thruster 4 • Diver 1 & 2 located onto top of template
  • 14. Time Line – 22.12 • Diver 2 umbilical snagged on transponder bucket located on side of structure • Diver 1 pulled off Easterly Direction template • Momentary loss of comms to bell
  • 15. Time Line – 22.13 to 22.15 • Loss of comms / video to diver 2; umbilical severed • Diver 1 made way back to bell stage • OPM relocated from Dive Control to Bridge • Port Taut Wire stowed (wire parted) • Downline and tugger parted
  • 16. Time Line – 22.17 • Vessel position 240m East of Drilling Template • Vessel being manually driven using fwd and aft azimuths • Chief Officer on thrusters 2 & 3, Master on main propulsion thrusters 5 &6 • Diver 2 locator beacon 240m identified to be at template
  • 17. Time Line - 22.29 – 22.34 • ROV back at Drilling Template • Diver 2 located on top of template 150m • DP controllers power recycled • Vessel back on full auto DP
  • 18. Time Line – 22.40 • Vessel back at Drilling Template • Diver 1 left stage, bell 18m from template • Recovery of Diver 2 commenced
  • 19. Time Line – 22.46 Investigation • Diver 2 recovered to bell, unconscious & breathing • 23.04 Diver 2 stable, vital signs good, talking • 23.13 Bell sealed and left bottom • 23.38 Bell locked on • 23.50 ROV recovered • 24.00 commenced transit to port
  • 20. Emergency Response • OPM - Call made to ERSC • Master - Call made to BSM • ERSC - Call made to Duty Manager • ERSC – Call made to BSM • ERSC – Call made to Client • Duty Manager – Call made to Project Manager • Duty Manager – Call made to Snr Management • Snr Management discussion • Vessel made way to Port • Snr Management meeting early morning
  • 21. Medical Treatment • 18th 22.30 - Medic reported to dive control to assess the situation. • 22.46 - Diver recovered back into bell, appeared to be unconscious with shallow breathing − Diver regained consciousness & movement of digits ; gripping hand of the bellman • 23.15 - DMAC 15 equipment sent into chamber 1 (medical chamber) ; defibrillator, stretcher & neck brace in situ • 23.38 - Diver climbed down steps from bell with assistance from the other divers − Diver core temp raised, fluid replacement • 19th 00.45 - Medic contacted Capita Dive Dr; satisfied with progress
  • 22. Medical Treatment • 02.00 - Diver stable, moved onto ½ hrly observations • 03.00 - hrly observations commenced • 07.45 - Dive Dr granted permission for diver to commence decompression (12 man team commenced deco) • 15.00 - Dive Dr onboard to speak to diver; 4hrly observations commenced • 20th 06.00 - good progress, 8 hrly observations commenced • 22nd 13.20 - Decompression completed − Diver met by Dive Dr, post sat medical completed − Councillor available for teams • 23rd - Further examination at Capita Health Solutions
  • 23. Vessel Assurance – DP System • Determine the fault which caused loss of control of the thrusters along with loss of all reference & environmental signals to the DP control system • Assess actions of personnel re change status of the DP control • Assessment & analysis of DP alarm log / printout • Conduct non-intrusive testing of Software & Hardware • Interrogation of software • Interrogation of bridge VDR • FMEA review • DP proving trials schedule for testing and verification of the system
  • 24. Vessel Assurance – DP System • Testing on the system to try to replicate the failure, in conjunction with the testing on the switchboards; in accordance with DNV approved trials schedule . • Able to replicate the failure of the module to provide the various alarms that were seen on the 18th • All options exhausted in terms of testing on the vessel; DNV agreement • DP hardware replaced & existing units taken off & sent back to Norway; DNV agreement • Power management system testing carried out • Kongsberg disassembling module by module to fully substantiate root cause of the failure • DP FMEA proving trials conducted
  • 25. Immediate Causal Factors • Communication jamming of the RBUS network caused loss of control of the thrusters along with loss of all reference and environmental signals to the DP control system and resulted in vessel losing position and drift off • Vessel loss of position and Diver 2 umbilical snagging on transponder bucket located on side of template resulted in diver 2 umbilical being severed.
  • 26. Underlying Causal Factors • Several anomalies found relating to electrical grounding, shielding & electrical noise. • Fault mechanism behind the RBUS communication error related to jamming of the RBUS; based the results from testing & comparing sequence of events from the tests with what was observed on- board. • RBUS communication problems started due to a rare sequence of events involving the combined effects of the findings and a failure(s) in one or more modules in the DPC-3 cabinet. • One or more module(s) in the DPC-3 cabinet could have been degraded due the long term effects • Transponder buckets not identified as potential snag hazards for operations being carried out • Not removed prior to work starting in the structure.
  • 27. Root Causal Factors • Due to the lack of a well-defined root cause KM shipped all components that were present in the DPC-3 cabinet at the time of the incident to Kongsberg head office to undergo a thorough manufacturing test. • This is being done to include or exclude a possible fault in a specific module.
  • 28. DP Control System Operator Stations RCU (Remote RCU (Remote RCU (Remote Controllers - Bridge DP computers Control Unit) Control Unit) Control Unit) Controller Controller Controller RHUB (Network RHUB (Network 24Vdc Hub) Hub) 24Vdc Each of the RHUB (Network Hub) has two UPS 1 UPS 2 230V 230V 24Vdc power supplies 24Vdc 24Vdc Information from the RIO Units are RBUS Network A RBUS Network B conveyed to the controllers via 2 dedicated RBUS Networks; A & B Reference systems / Remote Input Output (RIO) units. Take all RIO RIO RIO RIO RIO RIO Environmental feedback from the reference & Sensors environmental sensors along with command & feedback signals for the thrusters. Each Thruster has RIO unit
  • 29. Dive System Assurance • Starboard main bell umbilical − cables checked for insulation, continuity & resistance − pressure leak tested to maximum working pressure • Diver 2 excursion umbilical (55mtr) replaced, Diver 1 excursion umbilical (55mtr) serviced • The Diver 2 hat and neck dam fully serviced • Diver 2 umbilical horns inside Starboard bell removed & straightened • Bell wires & Guide weight wires have been cut back and re- terminated & load tested • All excursion umbilical 6 monthly testing has been completed. • The Stbd tools winch wire replaced
  • 30. Lessons Learned • Conduct engagement sessions with internal & external stakeholders • Share incident and lessons learned with industry; IMCA, OGP, Subsea UK, Stepchange • Initiate project to look into enhancement of diver safety using experiences from this incident • Review FMEA / FMECA documentation • Review emergency response & contingency planning process, procedures, drills, exercises • Review media liaison arrangements