Scrum tools and_meetings
1. EURO MPM
European Master
In Proyect Management
Bilbao, 23, October 2010
Andoni Gonzalo
Scrum Tools and Meetings
2. EURO MPM
European Master
In Proyect Management 2
Agenda
I. Sprint
II. Product Backlog
III. Sprint Backlog
IV. Increment
V. Planning Meeting
VI. Sprint Meeting
VII.Daily Meeting
VIII.Retrospective Meeting
3. EURO MPM
European Master
In Proyect Management 3
Review
PP
PP E
SMPP E
Exposición de prioridades
Resolución de dudas
Estimación del esfuerzo para
cada requisito
Objetivo del Sprint
Reunión diaria SM E
( )IPP
Revisión del trabajo;
resolución de trabas
PPSM E I
Presentación del incremento,
sugerencias, anuncio próximo sprint
COMPONENTES
PRODUCT
BACKLOG
SPRINT
BACKLOG
INCREMENTO
PDP
PDS
INC
4. EURO MPM
European Master
In Proyect Management 4
Sprint
• Length of an iteration
• 2 weeks – 8 weeks
• Recommended to keep same length (may be exceptions)
• Can’t be extended to finish the work
• Starts with Sprint Meeting and finishes with Review Meeting
Iteration
2-8 weeks
5. EURO MPM
European Master
In Proyect Management 5
Tools
Product
Backlog
Sprint
Backlog
Increment
System requirement
Work to be done in a Sprint
Part of the product developed
in a sprint
Daily
cycle
6. EURO MPM
European Master
In Proyect Management 6
• Premises for agile
• The needed output can be decomposed in functionality
• Each functionality makes sense and have value for the client and
can be deliver independently as soon as possible.
Product Backlog
• Client’s first step
• Define vision and scope of the project
• Identify first requirements (Product Backlog)
• Prioritize them depending on the ROI
7. EURO MPM
European Master
In Proyect Management 7
• Alive Document
• Is updated when needed, continuously revised
• User Stories
• Prioritized by the Product Owner
Product Backlog
ID Priority User Story Long Description Estimation
1 Very High User Story 1 As a User I want… in order to… 5
2 Very High User Story 2 As Administrator I want… in order to… 2
3 High User Story 3 As Support I want… in order to… 3
4 Medium User Story 4 As Sales I want… in order to… 8
8. EURO MPM
European Master
In Proyect Management 8
• Final output’s requirements
• Visible to everyone involved in the project
• PO
• Scrum manager
• Team
• Stakeholders
• Everyone can contribute to add items
• It’s own by the PO
• Only the PO can prioritized
• Needs to determine:
• How valuable or urgent is each User Story
• How much each User Story costs (effort)
Have the needed decision criteria for the Sprint Meeting
Product Backlog
9. EURO MPM
European Master
In Proyect Management 9
Product Backlog
System Requirement and Product Backlog: similar
Predictive Development
SYSTEM
• System
Requirements
• SOFTWARE
• Predictive Gantt
Agile Development
• Product Vision
• Product Backlog
• User Stories
Sprint Objective
Sprint Backlog
11. EURO MPM
European Master
In Proyect Management 11
Sprint Backlog
• User Stories that will be done during the Sprint
• The Team is compromised
• Assigned (Not a must)
• Re- estimated
• May divided in Sub-Tasks
13. EURO MPM
European Master
In Proyect Management 13
Sub-Tasks
No more than 16 hours
DONE-DONE
Implemented Tested Documented
14. EURO MPM
European Master
In Proyect Management 14
Increment
• Part of the product developed in one Sprint
• It should be deployable if wanted
• Potentially shippable product
15. EURO MPM
European Master
In Proyect Management 15
Meetings
Project Scope
Meeting
(Create first
Product Backlog)
Sprint Meeting
(Create Sprint
Backlog)
Daily Meeting
(Follow up and
update Burn
Chart)
Review Meeting
(Show the work DONE
during the sprint)
Retrospective
Meeting
(What goes well
and what not)
16. EURO MPM
European Master
In Proyect Management 16
Project Scope Meeting
• Vision of the project
• First Product Backlog
• Prioritize the most important items
• First estimation of the project length
• Product Owner
• Team
• Stakeholder
17. EURO MPM
European Master
In Proyect Management 17
Sprint Meeting
• Resources are known
• There is a valid Product Backlog
• PO and Team work together
• Scrum Manager moderate meeting
• The Team masters the needed technology to execute the work to be
done
BEFORE STARTING THE SPRINT
18. EURO MPM
European Master
In Proyect Management 18
Sprint Meeting
Product Backlog
Developed Product
Other information
INPUT
OUTPUT
Sprint
Objective
Sprint
Backlog
Sprint
Planning
19. EURO MPM
European Master
In Proyect Management 19
Sprint Meeting
Product Backlog
Exposition
1 Day Max
Sprint Backlog
Resolution
20. EURO MPM
European Master
In Proyect Management 20
Sprint Meeting
• Same place, same time – Recommended
• All Team members must attend
• Stand-up meeting agile meeting
• Scrum Master moderates
• Product Owner invited to listen
EVERY DAY – MAX 15 minutes
Each team member answers three questions:
1. What did you accomplish yesterday?
2. What is your goal for today?
3. What is preventing you from accomplishing your goals?
21. EURO MPM
European Master
In Proyect Management 21
Review Meeting
• Max 4 h
• Live demo of the development done – NO PPT
• Shouldn’t need any special preparation
• Only show what is REALLY working
Objectives:
• Check the work done
• PO accepts or not the work
• Feedback for the evolution of the Backlog
• No criticism on this meeting
• New Sprint meeting date
At the end of the Sprint
22. EURO MPM
European Master
In Proyect Management 22
Retrospective Meeting
• After the review meeting
Objectives:
• Check what was well done – Repeat in the future
• Check what was not well done – Avoid in the future
When needed
24. EURO MPM
European Master
In Proyect Management 24
References
www.scrummanager.net
Flexibilidad con Scrum -- http://www.navegapolis.net/content/view/905/89/
(Juan Palacio) https://www.safecreative.org/work/0711140303769