SlideShare uma empresa Scribd logo
1 de 17
Monthly Status
Briefing
October 2012
Project Background

   The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely
    destroy 2,611 tons of mustard agent in mortar rounds and artillery
    projectiles stored at the U.S. Army Pueblo Chemical Depot (PCD).

   Neutralization followed by biotreatment is the technology selected by the
    Department of Defense to destroy the Pueblo chemical weapons stockpile.

   The Program Executive Officer, Assembled Chemical Weapons Alternatives
    (ACWA), headquartered at Aberdeen Proving Ground, Maryland, is
    responsible for managing all aspects of the safe and environmentally sound
    destruction of the chemical weapons stockpiles in Colorado and Kentucky.

   The Bechtel Pueblo Team (BPT) is a partnership of Bechtel National, Inc.,
    URS, Parsons, and Battelle Memorial Institute. The BPT functions as the
    systems contractor selected to design, build, systemize, pilot test, operate,
    and close the PCAPP.



                                                                                2
     OPSEC Completed 10 October 2012
Bechtel Pueblo Team

                                           Systems Contractor

 Project management                                             Design/engineering
 Business services                                              Procurement/subcontracting
 Safety and quality                                             Construction



                                          Teaming Subcontractors




   Systemization                       Process design              Environmental permitting
   Pilot testing                       Process equipment            and compliance
   Operations                           fabrication                 Laboratory management
   Closure                             Support to systemization    Pilot testing
                                         and operations


                                                                                               3
     OPSEC Completed 10 October 2012
Staffing


                                     Bechtel Pueblo Team
                                      non-manual: 537
                                         –   Pueblo: 535 (135 local hires)

                                         – Other locations: 2


                                     Construction Workers: 373
                                         – Bechtel direct-hire craft
                                           workers: 277
                                         – Subcontractor
                                           personnel: 96




                                                                       4
  OPSEC Completed 10 October 2012
Employment Opportunities


             Hotline

     (719)549-4003

            Website

http://pueblo.bechtel.com




                                       5
     OPSEC Completed 10 October 2012
Safety


                         As of September 30, 2012,
                      PCAPP Project staff accomplished:

                                     157 Safe Work Days

                                     887,643 Safe Work Hours




                                                                6
  OPSEC Completed 10 October 2012
Destruction Technology


  Step 1           Removal of Energetics                   Step 4    Biotreatment
                   Robotic equipment removes energetics              Microbes treat the hydrolysate,
                   (explosives) from the weapon. The                 breaking it down into brine. The brine
                   energetics will be disposed of at a               is separated with water being recycled
                   permitted facility offsite.                       back to the plant and salt cakes shipped
                                                                     for disposal at a permitted facility.

 Step 2            Removal of                               Step 5   Thermal Treatment and
                   Mustard Agent                                     Disposal of Metal Parts
                   The inside of the weapon is remotely              Metal Parts are heated to 1,000 degrees
                   accessed and mustard agent is washed              Fahrenheit for 15 minutes and can then
                   out with high-pressure water.                     be recycled.


 Step 3            Neutralization of                       Neutralization followed by
                   Mustard Agent                           biotreatment will be used to
                   The mustard agent is neutralized with   destroy the Colorado chemical
                   caustic solution and hot water. The
                   byproduct is called hydrolysate.        weapons stockpile.




                                                                                                                7
   OPSEC Completed 10 October 2012
Pueblo Chemical Agent-Destruction
Pilot Plant—Site Plan




                                    8
  OPSEC Completed 10 October 2012
PCAPP Site Overview


                            4                                             3
                                                                                        7
                                                5
                                                                2

                                           1




                                                    6
                                                                                   8




                                         Northwestern Corner - Observation Point

                    1     Enhanced Reconfiguration Building         5    Agent Filtration Area
                    2     Automated Guided Vehicle Corridor         6    Munitions Service Magazine
                    3     Agent Processing Building                 7    Control and Support Building
                    4     Biotreatment Area                         8    Munitions Service Magazine corridor

                                                                                                               9
  OPSEC Completed 10 October 2012
Construction Status – In Progress

   Enhanced Reconfiguration Building–Continuing electrical punch list items;
    continued coatings placement in the Munitions Service Magazine (MSM) and
    MSM corridor areas.
   Agent Processing Building–Continuing electrical installations, piping and
    instrumentation installations as well as architectural installations.
   Laboratory—Continued HVAC and electrical installations.
   Balance of Facilities–Continue final grade, sidewalks in the yard area
   Biotreatment Area–Continuing coatings preparations for the Immobilized
    Cell Bioreactor pads; continue punch list items
   Brine Reduction System–Continuing electrical installations, including
    installations for Biotreatment
    Electrical Building; working
    punch list items.
   Entry Control Facility–Continuing
    electrical installations and
    architectural commodities.



                                                                             10
     OPSEC Completed 10 October 2012
Systemization

As the project transitions from construction to systemization, the
following systems have been turned over to the start-up group to begin
the systemization process:
                                                                Steam and Condensate—APB/Biotreatment Area
   Instrument Air—IA Compressor ―A,‖ Dryer ―A,‖
                                                                 (BTA)/Brine Reduction System (BRS) Distribution
    Main Air Receiver and Yard Distribution Piping
                                                                Bulk Chemical Storage and Distribution—DAP, UREA
   Hot Process Water—Agent Processing Building
                                                                 and 25% caustic
    (APB) Hot Process Water Tank and Heating Coil.
                                                                Projectile Handling and Projectile Disassembly—
   Agent Collection and Neutralization System—
                                                                 Projectile Mortar Disassembly systems and Related
    Hydrolysate Collection and Storage—Yard
                                                                 Equipment—Lines 1, 2, and 3
   HVAC Hot Water—Pumps and related tanks, Heat
    Exchangers and Outside Rack Piping

   Breathing Air—A & B Compressor/Purifier
    Packages, Receiver and Chiller, Bottle Filling
    Station

   Enhanced Reconfiguration Building (ERB) Supply
    Air Handling Units/Control Room and Support
    Areas Ventilation System

   Steam Supply—Fuel Oil Piping, Natural Gas
    Piping, Amine Feed Skid, Boilers A & B" and
    Outside Rack Steam


                                      To learn more about Systemization, watch the video at
                                 http://www.peoacwa.army.mil/info/video/systemization_yt.html

                                                                                                            11
     OPSEC Completed 10 October 2012
Systemization (cont.)
    ERB 480V Substation
                                                          Non-Essential Power Panel-Entry Control Facility (ECF)
    Brine Reduction Belt Feed System
                                                          Critical Power Panels—ERB
    Chilled Water—Chillers, Distribution to
                                                          Essential Power Panel—ECF
     various HVAC units, recirculation units,
     autoclave and Off-Gas Treatment scrubber             Water Recovery—Brine Concentrator Feed Tanks
                                                           ―A―, ―B‖, and ―C‖ and BC Feed Tanks Off-Gas Treatment
    Decon Solution Storage and Distribution—
     APB                                                  Munitions Washout System-Instrument Air Distribution,
                                                           Process Water Distribution, Hydraulic Power Line 1 & 2
    Immobilized Cell Bioreactor (ICB) Feed,
     Biotreatment, ICB Blower and Off Gas
     Treatment—Modules 1/2/3/4

    Plant Air–BTA, APB and ERB Distribution

    Process Cooling Water—BRS Distribution

    Potable Water—ERB, APB and BRS

    ERB Electrical Room Ventilation System

    Munitions/Parts Monitoring-ERB

    Process Cooling Water—PCW Pumps, Tanks,
     Chemical Feed Skids, Cooling Towers, BRS
     Distribution

    Main Sanitary Waste—Lift Stations, Waste
     Tank and Pumps

                                        To learn more about Systemization, watch the video at            *Newly added
                                   http://www.peoacwa.army.mil/info/video/systemization_yt.html

                                                                                                                    12
       OPSEC Completed 10 October 2012
Agent Processing Building




                 In the off-gas treatment system room, all process gasses enter through
                 the large white pipe on the right. Large blowers will pull all of the gases
                 through the system.

                                                                                               13
  OPSEC Completed 10 October 2012
Enhanced Reconfiguration Building
(ERB)




                Three Projectile Mortar Disassembly systems are in place in three
                Explosion Containment Rooms inside the ERB.
                                                                                    14
  OPSEC Completed 10 October 2012
Control and Support Building




                  A very complex HVAC system, which preheats, filters and absorbs
                  contaminants, is located to the north of the Control and Support Building.

                                                                                               15
  OPSEC Completed 10 October 2012
Biotreatment Area




                   Coating preparations have begun on the Immobilized Cell Bioreactors (ICB)
                   pads. The ICB system breaks down the hydrolysate before making its way to
                   the Brine Reduction System.


                                                                                           16
   OPSEC Completed 10 October 2012
Contact Information


    Pueblo Chemical                        U.S. Army
Stockpile Outreach Office            Pueblo Chemical Depot
       104 West B Street               45825 Highway 96 East
         719-546-0400                      719-549-4135

           Tom Schultz                   Chuck Sprague
            PCAPP                        Public Affairs Officer
   Public Affairs Specialist
                                            Ken Roque
       Bob Kennemer                  Deputy Public Affairs Officer
    Community Outreach
        Manager

        Sandy Romero
    Bechtel Pueblo Team
  Communications Manager


                                                                  17
   OPSEC Completed 10 October 2012

Mais conteúdo relacionado

Mais de Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

Mais de Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update
Economic Development Working Group Update
 
Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012
 

October 2012 PCAPP Monthly Status Briefing

  • 2. Project Background  The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611 tons of mustard agent in mortar rounds and artillery projectiles stored at the U.S. Army Pueblo Chemical Depot (PCD).  Neutralization followed by biotreatment is the technology selected by the Department of Defense to destroy the Pueblo chemical weapons stockpile.  The Program Executive Officer, Assembled Chemical Weapons Alternatives (ACWA), headquartered at Aberdeen Proving Ground, Maryland, is responsible for managing all aspects of the safe and environmentally sound destruction of the chemical weapons stockpiles in Colorado and Kentucky.  The Bechtel Pueblo Team (BPT) is a partnership of Bechtel National, Inc., URS, Parsons, and Battelle Memorial Institute. The BPT functions as the systems contractor selected to design, build, systemize, pilot test, operate, and close the PCAPP. 2 OPSEC Completed 10 October 2012
  • 3. Bechtel Pueblo Team Systems Contractor  Project management  Design/engineering  Business services  Procurement/subcontracting  Safety and quality  Construction Teaming Subcontractors  Systemization  Process design  Environmental permitting  Pilot testing  Process equipment and compliance  Operations fabrication  Laboratory management  Closure  Support to systemization  Pilot testing and operations 3 OPSEC Completed 10 October 2012
  • 4. Staffing  Bechtel Pueblo Team non-manual: 537 – Pueblo: 535 (135 local hires) – Other locations: 2  Construction Workers: 373 – Bechtel direct-hire craft workers: 277 – Subcontractor personnel: 96 4 OPSEC Completed 10 October 2012
  • 5. Employment Opportunities Hotline (719)549-4003 Website http://pueblo.bechtel.com 5 OPSEC Completed 10 October 2012
  • 6. Safety As of September 30, 2012, PCAPP Project staff accomplished:  157 Safe Work Days  887,643 Safe Work Hours 6 OPSEC Completed 10 October 2012
  • 7. Destruction Technology Step 1 Removal of Energetics Step 4 Biotreatment Robotic equipment removes energetics Microbes treat the hydrolysate, (explosives) from the weapon. The breaking it down into brine. The brine energetics will be disposed of at a is separated with water being recycled permitted facility offsite. back to the plant and salt cakes shipped for disposal at a permitted facility. Step 2 Removal of Step 5 Thermal Treatment and Mustard Agent Disposal of Metal Parts The inside of the weapon is remotely Metal Parts are heated to 1,000 degrees accessed and mustard agent is washed Fahrenheit for 15 minutes and can then out with high-pressure water. be recycled. Step 3 Neutralization of Neutralization followed by Mustard Agent biotreatment will be used to The mustard agent is neutralized with destroy the Colorado chemical caustic solution and hot water. The byproduct is called hydrolysate. weapons stockpile. 7 OPSEC Completed 10 October 2012
  • 8. Pueblo Chemical Agent-Destruction Pilot Plant—Site Plan 8 OPSEC Completed 10 October 2012
  • 9. PCAPP Site Overview 4 3 7 5 2 1 6 8 Northwestern Corner - Observation Point 1 Enhanced Reconfiguration Building 5 Agent Filtration Area 2 Automated Guided Vehicle Corridor 6 Munitions Service Magazine 3 Agent Processing Building 7 Control and Support Building 4 Biotreatment Area 8 Munitions Service Magazine corridor 9 OPSEC Completed 10 October 2012
  • 10. Construction Status – In Progress  Enhanced Reconfiguration Building–Continuing electrical punch list items; continued coatings placement in the Munitions Service Magazine (MSM) and MSM corridor areas.  Agent Processing Building–Continuing electrical installations, piping and instrumentation installations as well as architectural installations.  Laboratory—Continued HVAC and electrical installations.  Balance of Facilities–Continue final grade, sidewalks in the yard area  Biotreatment Area–Continuing coatings preparations for the Immobilized Cell Bioreactor pads; continue punch list items  Brine Reduction System–Continuing electrical installations, including installations for Biotreatment Electrical Building; working punch list items.  Entry Control Facility–Continuing electrical installations and architectural commodities. 10 OPSEC Completed 10 October 2012
  • 11. Systemization As the project transitions from construction to systemization, the following systems have been turned over to the start-up group to begin the systemization process:  Steam and Condensate—APB/Biotreatment Area  Instrument Air—IA Compressor ―A,‖ Dryer ―A,‖ (BTA)/Brine Reduction System (BRS) Distribution Main Air Receiver and Yard Distribution Piping  Bulk Chemical Storage and Distribution—DAP, UREA  Hot Process Water—Agent Processing Building and 25% caustic (APB) Hot Process Water Tank and Heating Coil.  Projectile Handling and Projectile Disassembly—  Agent Collection and Neutralization System— Projectile Mortar Disassembly systems and Related Hydrolysate Collection and Storage—Yard Equipment—Lines 1, 2, and 3  HVAC Hot Water—Pumps and related tanks, Heat Exchangers and Outside Rack Piping  Breathing Air—A & B Compressor/Purifier Packages, Receiver and Chiller, Bottle Filling Station  Enhanced Reconfiguration Building (ERB) Supply Air Handling Units/Control Room and Support Areas Ventilation System  Steam Supply—Fuel Oil Piping, Natural Gas Piping, Amine Feed Skid, Boilers A & B" and Outside Rack Steam To learn more about Systemization, watch the video at http://www.peoacwa.army.mil/info/video/systemization_yt.html 11 OPSEC Completed 10 October 2012
  • 12. Systemization (cont.)  ERB 480V Substation  Non-Essential Power Panel-Entry Control Facility (ECF)  Brine Reduction Belt Feed System  Critical Power Panels—ERB  Chilled Water—Chillers, Distribution to  Essential Power Panel—ECF various HVAC units, recirculation units, autoclave and Off-Gas Treatment scrubber  Water Recovery—Brine Concentrator Feed Tanks ―A―, ―B‖, and ―C‖ and BC Feed Tanks Off-Gas Treatment  Decon Solution Storage and Distribution— APB  Munitions Washout System-Instrument Air Distribution, Process Water Distribution, Hydraulic Power Line 1 & 2  Immobilized Cell Bioreactor (ICB) Feed, Biotreatment, ICB Blower and Off Gas Treatment—Modules 1/2/3/4  Plant Air–BTA, APB and ERB Distribution  Process Cooling Water—BRS Distribution  Potable Water—ERB, APB and BRS  ERB Electrical Room Ventilation System  Munitions/Parts Monitoring-ERB  Process Cooling Water—PCW Pumps, Tanks, Chemical Feed Skids, Cooling Towers, BRS Distribution  Main Sanitary Waste—Lift Stations, Waste Tank and Pumps To learn more about Systemization, watch the video at *Newly added http://www.peoacwa.army.mil/info/video/systemization_yt.html 12 OPSEC Completed 10 October 2012
  • 13. Agent Processing Building In the off-gas treatment system room, all process gasses enter through the large white pipe on the right. Large blowers will pull all of the gases through the system. 13 OPSEC Completed 10 October 2012
  • 14. Enhanced Reconfiguration Building (ERB) Three Projectile Mortar Disassembly systems are in place in three Explosion Containment Rooms inside the ERB. 14 OPSEC Completed 10 October 2012
  • 15. Control and Support Building A very complex HVAC system, which preheats, filters and absorbs contaminants, is located to the north of the Control and Support Building. 15 OPSEC Completed 10 October 2012
  • 16. Biotreatment Area Coating preparations have begun on the Immobilized Cell Bioreactors (ICB) pads. The ICB system breaks down the hydrolysate before making its way to the Brine Reduction System. 16 OPSEC Completed 10 October 2012
  • 17. Contact Information Pueblo Chemical U.S. Army Stockpile Outreach Office Pueblo Chemical Depot 104 West B Street 45825 Highway 96 East 719-546-0400 719-549-4135 Tom Schultz Chuck Sprague PCAPP Public Affairs Officer Public Affairs Specialist Ken Roque Bob Kennemer Deputy Public Affairs Officer Community Outreach Manager Sandy Romero Bechtel Pueblo Team Communications Manager 17 OPSEC Completed 10 October 2012