6. Euclid Creek Tunnel:
By the Numbers
• Tunnel • Shafts: 5 total
– 24’ diameter – 24’ to 60’ diameter
– 17,750’ in length – 185-225’ deep
– 60,100,000 gallons • 2,440 linear feet of
• ~30 near surface open cut pipe placed
structures • 2,110 linear feet of
– 10 complete microtunnel complete
– 9 under construction – 240 more to go
euclidcreek.blogspot.com
7. Construction Updates
• New sewer, Lakeshore Boulevard
East 150th Street to (east of) Collinwood Rec.
– Work completed: Sept 2013
• New sewer, St. Clair Ave. and Nottingham Rd.
– Work completed: Oct 2013
euclidcreek.blogspot.com
8. Shaft #1
Construction Staging Site
• “Mackenzie” tunneled and lined 5400’
• Operating 24/7 with regularly-scheduled
maintenance periods
• Currently beneath Easterly WWTP
euclidcreek.blogspot.com
13. Shaft #2
Easterly Wastewater Treatment Plant
• 80 feet excavated
• Installing base slab for adjacent structure
(Structure 2-1).
• Blasting last 100 feet
– Will begin this year
– Field trips… any interest?
euclidcreek.blogspot.com
14. Shaft #3
Beulah Park
• Construction staging area
– Secant pile wall installation
• Increased truck traffic (spoils removal and
concrete delivery)
• 17 piles complete
– 10 primary piles, 7 secondary
– East 156th Street
• West side sidewalk still closed
• Will be replaced when feasible
euclidcreek.blogspot.com
16. Shaft #3: Schedule* 2013 2014
January February March April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug
Shaft Support & Excvation
Shaft Structural Work
Strs 3-2 & 3-3 (Btw Wadsworth &
Gordon)
Close E 156th Street
Diversion Sructure E 156th
Microtunneling
Str 3-5 (Lakeshore & E 156th)
Non-Working Holidays
Memorial Day
July 4th
Labor Day
Thanksgiving Day
Christmas Day
New Years Day
*Schedule subject to change
euclidcreek.blogspot.com
19. Shaft #4
Triangle Park
• Excavation work is complete at this site
• Currently installing rebar to reinforce shaft
• Fencing will remain throughout 2014
euclidcreek.blogspot.com
21. Shaft #5
Nottingham & St. Clair
• Excavation nearing
completion
– 210 feet excavated
– 10 more to go
euclidcreek.blogspot.com
22. Stay Informed
• Blog
– EuclidCreek.blogspot.com
• Semi-Monthly Newsletter
– E-mail distribution
– eltingj@neorsd.org to be added to the list
euclidcreek.blogspot.com
23. How to Reach Us
Social Media
facebook.com/yoursewerdistrict
@neorsd | @wallywaterdrop
Customer Service
(216) 881-8247
Emergencies: NEORSD ECT Field Office
(216) 268-5469
Ryan Sullivan, sullivanr@neorsd.org
Jenn Elting, eltingj@neorsd.org
euclidcreek.blogspot.com
24. Next Meeting
Tuesday, March 19, 2013 Dates
6:00 p.m. May
Cleveland Public Library, Change!
Memorial-Nottingham Branch
Save the Date!
– April 16 (possible location/date change)
– May 21
– June 18
euclidcreek.blogspot.com