SlideShare a Scribd company logo
1 of 30
Download to read offline
“Debeljaca”
WS RCTank (700m3)
Construction
Reinforced Concrete WS Tank
“Debeljaca” (V=700m3),
a part of Water Supplying System of
Bihac City,
Bosnia & Herzegovina
The new RC water reservoir
constructed app. 100 m north of the
old reservoir. The maximum operating
water level is at a height of
293,00masl, the minimum water level
is at a height of 288,50masl.
In the first stage only one chamber of
the reservoir with a volume of 700m³
will be constructed. The walls and the
piping built in a manner that an
extension in the future with further
700m³ is possible without any
changing.
Construction Period:
2009 / 2010
RCTank - Construction
Sequence
COMPACTION OF STRUCTURAL FILL PLATE LOAD TEST (AS PER DIN18134)
PREPARED SUB-GRADE
LAND SLIDE ON WORK-PIT SIDE STOPPED BY GABIONS,
PLASTIC SHEETING AGAINST RAIN
PVC DN100MM DRAINAGE PIPES SYSTEM INSTALLED
WITHIN THE SUB-GRADE
BLINDING CONCRETE INSTALLATION
CONCRETE CLASS C12/15, D=8.0CM
BLINDINGCONCRETE (C12/15; 8CM) VALVE CHAMBER AND RESERVOIR BASE SLAB
REINFORCED CONCRETE BASE SLAB (C30/37; 40CM)
CONCRETE (C12/15; 5CM)
HYDRO-INSULATION (BITUVAL V4)
COLD BITUMINOUS COATING (IBITOL)
BLINDING CONCRETE (C12/15; 8CM)
VALVE CHAMBER BASE SLAB – C30/37 CONCRETE, D=30.0CM
PIPE-FITTINGS INSTALLATION IN PARTITION WALL
INSTALLATION OF PIPE NOZZLES, HORIZONTAL PVC
WATER-STOP
VALVE CHAMBER DRAIN PIPE, WALL KICKER HORIZONTAL
PVC WATER-STOP
PARTITIONWALL PIPE NOZZLES
PVC WATER STOP 30MM WIDTH ON HORIZONTAL
CONSTRUCTION JOINT BETWEEN WALL KICKERS AND
FUTURE WALLS. CONCRETE CLASS C30/37, D=40.0CM
VALVE CHAMBER FITTINGS INSTALLATION AND
PROTECTION AGAINST DAMAGE. WALLS THICKNESS
D=40.0CM
Reservoir SideWalls
concrete installation
Wall’s construction joints with
vertical PVCWater-stop
30mm
SLUMPTEST ON EACH DELIVERED MIXTRUCK
FORVERIFICATIONOFWORKABILITY
AIR CONTENTTAKEN ON EACH
DELIVERED MIXTRUCK
VALVE CHAMBER REINFORCEMENT & FORMWORKS
VALVE CHAMBER OUTSIDE WALL C30/37, D=30.0CM
RESERVOIR INLET WALL CONCRETE INSTALLATION
CONCRETE CLASS C30/37, D=40CM, H=5.54M
RESERVOIR PARTITION WALL REINFORCEMENT WORKS
CONCRETE CLASS C30/37, D=40CM
RESERVOIR VALVE CHAMBER SIDE WALLS CONCRETE
INSTALLATION
CONCRETE CLASS C30/37, D=30CM
RESERVOIR PARTITION WALL FORMWORKS
WALL THICKNESS D=40CM
RESERVOIR COLUMNS (3NR) CONCRETE INSTALLATION
CIRCULAR COLUMNS 3NR; D=35CM, H=5.54M
VALVE CHAMBER SLAB FORMWORK
TANK’S VALVE CHAMBER SLAB REINFORCEMENT WORKS,
WATER CHAMBER ROOF SLAB FORMWORKS
VALVE CHAMBER UPPER WALLS, WATER CHAMBER ROOF
SLAB REINFORCEMENT WORKS
ROOF SLAB REINFORCEMENT WORKS, VALVE CHAMBER
WALLS FORMWORK
RESERVOIR ROOF SLAB C30/37, D=22CM WATER CHAMBER ROOF SLAB CONCRETE WORKS
WATER CHAMBER ROOF SLAB CONCRETE
C30/37, D=22.0CM
VALVE CHAMBER ROOF SLAB CONCRETE
ROOF SLAB TIGHTNESS TESTING AS PER EN 1508 A.6-8.3.4,
8.4,4. NO LEAKAGES RECORDED
RESERVOIR (WATER CHAMBER) WATER-TIGHTNESS
TESTING IN ACCORDANCE WITH EN1508
WATER-TIGHTNESS TESTING AS PER EN 1508 A.6-8.3.4, 8.4,4
SEEPAGE ON WALL’S OUTER SURFACE SELF-HEALED
WITHIN 2 WEEKS PERIOD
Hydro &Thermal
InsulationWorks
Roof Slab Hydro/Thermal
Insulation:
-Trench rampart Protective
membrane (Tefond)
-Thermal Insulation (Fibran)
- Hydro-insulation (BituvalV4)
- Cold bituminous coating
(Ibitol)
- ReinforcedConcrete Roof
Slab (C30/37; 22cm)
Hydro &Thermal
Insulation
OutsideWalls Hydro/Thermal
Insulation:
VentilationSteel Pipes DN200
Reinforced ConcreteWall
(C30/37; 40cm)
Cold bituminous coating
(Ibitol)
Hydro-insulation (BituvalV4)
Thermal insulation (Fibran)
Protective membrane
(Tefond)
CrushedStoneAggregate
RESERVOIR INLET PRESSURE PIPELINE DI DN300 WATER CHAMBER PERFORATED INTAKE PIPE DN300
Final Status -
Reservoir Entry
Old, abandoned reservoir
visible behind the new
reservoir entry
Final Status – SCADA
System
SUCTION PIPE DI DN300WITH AUTOMATICAIRVALVE FINAL STATUS – VALVE CHAMBER
ELECTRO MAGNETIC FLOW METER PROMAG 50W ACTUATOR
Debeljaca WS Reservoir 700m3

More Related Content

Similar to Debeljaca WS Reservoir 700m3

SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENTSUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
Atang Maphela
 
electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1
Atang Maphela
 
(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)
(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)
(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)
Nazaruddin Hairazi
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project Overview
Vladimir Popovic
 

Similar to Debeljaca WS Reservoir 700m3 (20)

soft permeable pipe
soft permeable pipesoft permeable pipe
soft permeable pipe
 
Teoria bocatoma
Teoria bocatomaTeoria bocatoma
Teoria bocatoma
 
STUDIO PRESENTATIO.pptx
STUDIO PRESENTATIO.pptxSTUDIO PRESENTATIO.pptx
STUDIO PRESENTATIO.pptx
 
over veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesover veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelines
 
Rehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgiaRehabilitation of ws system, lanchkhuti, georgia
Rehabilitation of ws system, lanchkhuti, georgia
 
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENTSUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
 
electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe ppt
 
FAREMS ORE.pptx
FAREMS ORE.pptxFAREMS ORE.pptx
FAREMS ORE.pptx
 
Applications of BDJ - EN.pptx
Applications of BDJ - EN.pptxApplications of BDJ - EN.pptx
Applications of BDJ - EN.pptx
 
(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)
(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)
(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)
 
subsea
subseasubsea
subsea
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project Overview
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
unit-4 design drawing of steel stru.pptx
unit-4 design drawing of steel stru.pptxunit-4 design drawing of steel stru.pptx
unit-4 design drawing of steel stru.pptx
 
Ws project ozurgeti, georgia
Ws project ozurgeti, georgiaWs project ozurgeti, georgia
Ws project ozurgeti, georgia
 
Ozurgeti City / Water Supply Project
Ozurgeti City / Water Supply ProjectOzurgeti City / Water Supply Project
Ozurgeti City / Water Supply Project
 
Sc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-aSc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-a
 
Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12
 

More from Vladimir Popovic

More from Vladimir Popovic (12)

Waste water project derventa, bosnia
Waste water project derventa, bosniaWaste water project derventa, bosnia
Waste water project derventa, bosnia
 
Rehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgiaRehabilitation of ws system vani, georgia
Rehabilitation of ws system vani, georgia
 
Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3Lanchkhuti Oragvis gele ws rc tank 1,900m3
Lanchkhuti Oragvis gele ws rc tank 1,900m3
 
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstructionLanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
Lanchkhuti - Oragvis gele rc ws tank 2,000m3 reconstruction
 
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitationLanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
Lanchkhuti - Lashis gele rs ws tank 500m3 rehabilitation
 
Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3Lashis gele rc ws tank 500m3
Lashis gele rc ws tank 500m3
 
Kostajnica, ws, ww project
Kostajnica, ws, ww projectKostajnica, ws, ww project
Kostajnica, ws, ww project
 
Kakanj wastewater project
Kakanj wastewater projectKakanj wastewater project
Kakanj wastewater project
 
Ghadames project, minor structures
Ghadames project, minor structuresGhadames project, minor structures
Ghadames project, minor structures
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
 
Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3Garayan Water Supplying Tank, 300,000m3
Garayan Water Supplying Tank, 300,000m3
 
Derventa, Water Supply Project
Derventa, Water Supply ProjectDerventa, Water Supply Project
Derventa, Water Supply Project
 

Recently uploaded

Complex plane, Modulus, Argument, Graphical representation of a complex numbe...
Complex plane, Modulus, Argument, Graphical representation of a complex numbe...Complex plane, Modulus, Argument, Graphical representation of a complex numbe...
Complex plane, Modulus, Argument, Graphical representation of a complex numbe...
MohammadAliNayeem
 

Recently uploaded (20)

Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
 
Lesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxLesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsx
 
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
 
EMPLOYEE MANAGEMENT SYSTEM FINAL presentation
EMPLOYEE MANAGEMENT SYSTEM FINAL presentationEMPLOYEE MANAGEMENT SYSTEM FINAL presentation
EMPLOYEE MANAGEMENT SYSTEM FINAL presentation
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)
 
Introduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoIntroduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of Arduino
 
Introduction to Heat Exchangers: Principle, Types and Applications
Introduction to Heat Exchangers: Principle, Types and ApplicationsIntroduction to Heat Exchangers: Principle, Types and Applications
Introduction to Heat Exchangers: Principle, Types and Applications
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2
 
Geometric constructions Engineering Drawing.pdf
Geometric constructions Engineering Drawing.pdfGeometric constructions Engineering Drawing.pdf
Geometric constructions Engineering Drawing.pdf
 
Complex plane, Modulus, Argument, Graphical representation of a complex numbe...
Complex plane, Modulus, Argument, Graphical representation of a complex numbe...Complex plane, Modulus, Argument, Graphical representation of a complex numbe...
Complex plane, Modulus, Argument, Graphical representation of a complex numbe...
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
Intelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent ActsIntelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent Acts
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
Circuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineeringCircuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineering
 
Quiz application system project report..pdf
Quiz application system project report..pdfQuiz application system project report..pdf
Quiz application system project report..pdf
 

Debeljaca WS Reservoir 700m3

  • 1. “Debeljaca” WS RCTank (700m3) Construction Reinforced Concrete WS Tank “Debeljaca” (V=700m3), a part of Water Supplying System of Bihac City, Bosnia & Herzegovina The new RC water reservoir constructed app. 100 m north of the old reservoir. The maximum operating water level is at a height of 293,00masl, the minimum water level is at a height of 288,50masl. In the first stage only one chamber of the reservoir with a volume of 700m³ will be constructed. The walls and the piping built in a manner that an extension in the future with further 700m³ is possible without any changing. Construction Period: 2009 / 2010
  • 3. COMPACTION OF STRUCTURAL FILL PLATE LOAD TEST (AS PER DIN18134)
  • 4. PREPARED SUB-GRADE LAND SLIDE ON WORK-PIT SIDE STOPPED BY GABIONS, PLASTIC SHEETING AGAINST RAIN
  • 5. PVC DN100MM DRAINAGE PIPES SYSTEM INSTALLED WITHIN THE SUB-GRADE BLINDING CONCRETE INSTALLATION CONCRETE CLASS C12/15, D=8.0CM
  • 6. BLINDINGCONCRETE (C12/15; 8CM) VALVE CHAMBER AND RESERVOIR BASE SLAB
  • 7. REINFORCED CONCRETE BASE SLAB (C30/37; 40CM) CONCRETE (C12/15; 5CM) HYDRO-INSULATION (BITUVAL V4) COLD BITUMINOUS COATING (IBITOL) BLINDING CONCRETE (C12/15; 8CM) VALVE CHAMBER BASE SLAB – C30/37 CONCRETE, D=30.0CM
  • 8. PIPE-FITTINGS INSTALLATION IN PARTITION WALL INSTALLATION OF PIPE NOZZLES, HORIZONTAL PVC WATER-STOP
  • 9. VALVE CHAMBER DRAIN PIPE, WALL KICKER HORIZONTAL PVC WATER-STOP PARTITIONWALL PIPE NOZZLES
  • 10. PVC WATER STOP 30MM WIDTH ON HORIZONTAL CONSTRUCTION JOINT BETWEEN WALL KICKERS AND FUTURE WALLS. CONCRETE CLASS C30/37, D=40.0CM VALVE CHAMBER FITTINGS INSTALLATION AND PROTECTION AGAINST DAMAGE. WALLS THICKNESS D=40.0CM
  • 11. Reservoir SideWalls concrete installation Wall’s construction joints with vertical PVCWater-stop 30mm
  • 12. SLUMPTEST ON EACH DELIVERED MIXTRUCK FORVERIFICATIONOFWORKABILITY AIR CONTENTTAKEN ON EACH DELIVERED MIXTRUCK
  • 13. VALVE CHAMBER REINFORCEMENT & FORMWORKS VALVE CHAMBER OUTSIDE WALL C30/37, D=30.0CM RESERVOIR INLET WALL CONCRETE INSTALLATION CONCRETE CLASS C30/37, D=40CM, H=5.54M
  • 14. RESERVOIR PARTITION WALL REINFORCEMENT WORKS CONCRETE CLASS C30/37, D=40CM RESERVOIR VALVE CHAMBER SIDE WALLS CONCRETE INSTALLATION CONCRETE CLASS C30/37, D=30CM
  • 15. RESERVOIR PARTITION WALL FORMWORKS WALL THICKNESS D=40CM RESERVOIR COLUMNS (3NR) CONCRETE INSTALLATION CIRCULAR COLUMNS 3NR; D=35CM, H=5.54M
  • 16. VALVE CHAMBER SLAB FORMWORK TANK’S VALVE CHAMBER SLAB REINFORCEMENT WORKS, WATER CHAMBER ROOF SLAB FORMWORKS
  • 17. VALVE CHAMBER UPPER WALLS, WATER CHAMBER ROOF SLAB REINFORCEMENT WORKS ROOF SLAB REINFORCEMENT WORKS, VALVE CHAMBER WALLS FORMWORK
  • 18. RESERVOIR ROOF SLAB C30/37, D=22CM WATER CHAMBER ROOF SLAB CONCRETE WORKS
  • 19. WATER CHAMBER ROOF SLAB CONCRETE C30/37, D=22.0CM VALVE CHAMBER ROOF SLAB CONCRETE
  • 20. ROOF SLAB TIGHTNESS TESTING AS PER EN 1508 A.6-8.3.4, 8.4,4. NO LEAKAGES RECORDED RESERVOIR (WATER CHAMBER) WATER-TIGHTNESS TESTING IN ACCORDANCE WITH EN1508
  • 21. WATER-TIGHTNESS TESTING AS PER EN 1508 A.6-8.3.4, 8.4,4 SEEPAGE ON WALL’S OUTER SURFACE SELF-HEALED WITHIN 2 WEEKS PERIOD
  • 22. Hydro &Thermal InsulationWorks Roof Slab Hydro/Thermal Insulation: -Trench rampart Protective membrane (Tefond) -Thermal Insulation (Fibran) - Hydro-insulation (BituvalV4) - Cold bituminous coating (Ibitol) - ReinforcedConcrete Roof Slab (C30/37; 22cm)
  • 23. Hydro &Thermal Insulation OutsideWalls Hydro/Thermal Insulation: VentilationSteel Pipes DN200 Reinforced ConcreteWall (C30/37; 40cm) Cold bituminous coating (Ibitol) Hydro-insulation (BituvalV4) Thermal insulation (Fibran) Protective membrane (Tefond) CrushedStoneAggregate
  • 24. RESERVOIR INLET PRESSURE PIPELINE DI DN300 WATER CHAMBER PERFORATED INTAKE PIPE DN300
  • 25. Final Status - Reservoir Entry Old, abandoned reservoir visible behind the new reservoir entry
  • 26.
  • 27. Final Status – SCADA System
  • 28. SUCTION PIPE DI DN300WITH AUTOMATICAIRVALVE FINAL STATUS – VALVE CHAMBER
  • 29. ELECTRO MAGNETIC FLOW METER PROMAG 50W ACTUATOR