3. Background
What has happened in the last couple of years……
Construction Industry
• 2D -> 3D
• 3D -> BIM
• 3D -> pdf
Virtual Design and Construction
• The largest inovation in the industry since the lifting crane
IT
• Stationary -> Mobil
• PC Centric-> Diversified
• Central data -> Distributed data
• New echosystems
2012-11-12 NCC Construction Sverige AB 3
4. This has given us….
2012-11-12 NCC Construction Sverige AB 4
5. Requirements
New IT-plattform for NCC’s use of VDC
• Support coordination and production process
• Must integrate current systems
• Version control and traceability
• Available anywhere anytime
• Support ”all” new plattforms
• ”Future proof”
2012-11-12 NCC Construction Sverige AB 5
6. Not the solution!!
Traditional development
• Study / product evaluation
• Specification and development project
• Run Pilot
• Roll out
• 2-3 years and lots of million SEK later…….
2012-11-12 NCC Construction Sverige AB 6
7. Today
(we need to be faster to market)
So we did:
• Study, product and external services evaluation
• Identify key actors and trends
• Use external services and existing solutions
• Use open solutions
• Develop integrations
9 months later and with a small investment
During the last 9 months the following has happened:
BIM 360 documents, Buzzsaw client for IOS/Android
Windows-8, RT and Slate PC
2012-11-12 NCC Construction Sverige AB 7
8. Version 1.0
2012-11-12 NCC Construction Sverige AB 8
9. What did NCC achieve:
Less time during model coordination
• Automatic checks (QA/QC)
• Rule set determining who will:
• See what information
• On which plattform
Automatic generation of:
• pdf, dwf, dwg, ifc and nwd
Allow each system to do what it is best at, we just
ensure that the latest information is distributed as
efficient as possible
2012-11-12 NCC Construction Sverige AB 9
10. Sample Usecase 1
Information distribution (Data. 2D, 3D)
• Drawing´s are updated in our internal system PDS
• This is then available for:
• NCC purchasing organisation
• Supplier
• Subcontractor / Customer
• PDS
• Autodesk Buzzsaw
• NCC Site office
• PDS (offline use)
• Vault/Buzzsaw for Windows klienter
• Buzzsaw for IOS / Android
2012-11-12 NCC Construction Sverige AB 10
12. Sample Usecase 2
New Revit model from NCC Engineering
Server based sync Vault – Buzzsaw
Automation
• Check-in of a Revit model
• Create 3D DWF
• Create ifc
• Create pdf/dwg/dwf of all approved views/sheets
2012-11-12 NCC Construction Sverige AB 12