Gerrit Zenner. Sarens UK Ltd. 29th January
1. Range of available
Heavy Transportation
&
Heavy Lifting Techniques
Gerrit Zenner - Global Area Sales Manager – Sarens Group
Nuclear & Thermal Plants
1
Presentation title - edit in the Master slide
2. Modular or Stick Built Solutions
•
Partially or entirely constructed in factory
•
Transport to site for assembly and installation
•
Needs depend of technology provider
•
There are some copy / paste systems (e.g. AP1000)
•
Equipment build on frames (skid) or tailor made
3. Modular or Stick Built Solutions
•
Primary circuit equipment is
tested prior to arrival – in one
piece – example reactor & steam
generators
•
Need for good supply chain
•
Plenty of modular yards on
West coast of UK & Scotland
4. Options for Transportation
•
Moorside Sellafield & Wylfa : will have
interface between Sea & Land
•
Inventive solutions:
River transport
Beach landing
5. Building a Jetty (temporary)
• Building jetty (for maintenance afterwards)
• Port facilities
• Semi Submersible ships
• Geared ships
• Barges (different sizes) – draft - roro
7. Super Heavy Lifting Equipment
•
Up to 200,000 M/T is available
•
Capacity up to
5.000 ton @ 40m radius
•
Global experience:
ALE – Mammoet – Sarens
•
OPEN TOP for installations of
equipment or …..
8. Availability of Techniques
•
Skidding & Jacking in via
Hatch
•
Bringing in equipment after
Polar Crane & Dome is
installed
•
Reactor & Steam generators
Our advise :
early engineering & involvement
Why :
Different concepts with feasibility study