Netwerkbijeenkomst
    Eemshaven




February 2012



                Making Sustainability Bankable
                               CONFIDENTIAL
Disclaimer
This presentation was prepared by Typhoon Offshore B.V. (“TO”) exclusively for use at the
“Netwerkbijeenkomst Eemshaven”.
This presentation is incomplete without reference to, and should be viewed solely in conjunction
with, the oral briefing provided by TO. Information in this presentation may be based upon
management forecasts and reflects prevailing conditions and our views as of this date, which are
accordingly subject to change. No representation or warranty is made or accepted in respect of the
information contained herein.
This presentation is proprietary to TO and may not be disclosed to any third party or used for any
other purpose. By accepting this document, the recipient agrees that he/she will not copy,
reproduce, distribute or otherwise disclose this document or the contents hereof at any time
without the prior written consent of TO.




                                  Making Sustainability Bankable                                     2
                                                 CONFIDENTIAL
Contents




 1.   Introduction Typhoon Offshore

 2.   Realisation offshore windproject Gemini

 3.   Innovation/choices

 4.   Local Impact




                                                     3
                                      CONFIDENTIAL
1. INTRODUCTION




                                 4
                  CONFIDENTIAL
Typhoon Offshore: Building on Expertise
Typhoon Offshore

 Typhoon Offshore is the daughter company of
  Typhoon Capital (Est. Amsterdam 2009) and is
  dedicated to investing in and development of offshore
  wind energy projects.

 Typhoon Offshore’s objective is to acquire stakes in
  offshore wind projects in the North Sea. Typhoon
  Offshore then contributes its expertise to bring these
  projects to financial close, creating value and
  compelling investment cases for long term investors.

 Members of Typhoon Offshore’s core-team                   •   Strong transaction execution skills
  successfully managed the landmark projects Belwind        •   M&A and financing expertise
  and PrinsesAmalia [Q7] to financial close and during      •   Structuring capabilities
  construction, and were responsible for innovations        •   Technical expertise
  which have become market practice. The team has a         •   Project management experience
  strong network in Europe, Asia and the Middle East.       •   Financial control experience



                                                                                                      5
                                             CONFIDENTIAL
Typhoon Offshore: Building on Expertise




                                             The team already
                                             developed, financed and/or
                                             commissioned over 20 renewable
                                             energy infrastructure projects with a
                                             total capacity in excess of 1GW and a
                                             transaction value of around EUR 2
                                             billion


                                                                                     6
                              CONFIDENTIAL
Typhoon Offshore: position in the value chain




 Key project milestones




Securing
                   permits   Structuring       Contracting        Financing   Construction   Operational
site rights




      2 – 10 yrs
                                           1 – 2 yrs
                                                                                 2 – 4 yrs
                                                                                                20 yrs+




                                                                                                           7
                                                   CONFIDENTIAL
2. REALIZATION OFFSHORE WINDPROJECT GEMINI




                                             8
                    CONFIDENTIAL
Project Gemini 600MW Offshore wind in the Netherlands
•   Involved since September 2009, TO acquired 30% interest in
    early 2010 and in August 2011 TO acquired full ownership of
    the Dutch Project “Gemini” (formerly BARD Offshore
    Netherlands).
•   With its planned 600 MW capacity, it is the largest offshore
    wind farm to date in the North Sea area, totalling a CAPEX of
    €2.4 Bln.
•   Financial close is scheduled for Summer 2012 and start of
    construction in 2013


 Project characteristics

 • Project Gemini consists of 2 X 300 MW fully permitted
   offshore wind farms in the Netherlands.

 • Buitengaats (300MW) and ZeeEnergie (300MW) have both an
   approved permit (“Wbr”) and a granted Dutch feed-in tariff
   (‘SDE”).


                                                                    9
                                                CONFIDENTIAL
Project Gemini…..continue
Gemini Offshore Nederland:

• 600MW
• (100-200) x (3- 6MW turbines
• Waterdepth : 20-40m.
• Distance to shore: ca. 85KM
• 2 Offshore platforms + 1 On shore grid station.
Total amount of steel: ±200.000’MT’ (Foundations, tower, platform)
Approx 500km Cabling
          Construction Costs:
• Turbine supplier agreement € 800m
• EPC/BoP € 700m
• Grid € 550m
          Other Costs:
• Financial and structuring, devex €350m

15 yrs Full Maintenance & Insurance contract

                                                                     Tennet


                                                                              10
                                                    CONFIDENTIAL
Project Gemini – Green Energy
                                • Project Gemini is located at one of the best offshore wind
                                  location in NL with average wind
                                  speeds of ±10 m/s Estimated annual production for
                                  600MW: 2,400 GWh.


                                • Electricity for ± 700,000 households / 1,500,000
                                  habitants per annum which almost equals the number of
                                  people living in the 3 Northern provinces of The
                                  Netherlands.


                                • Annual emission reduction
                                   • 1,250,000 Ton CO₂
                                   • 3968 Ton Nox
                                   • 4284 Ton SO2

                                                                                         11
                                CONFIDENTIAL
Stakeholders

                                       Sponsors:
                                                                   Debt Providers
                                       HVC (15%)
                                                                   EIB
                                       Typhoon Offshore (85%)
  Contracts, supplier &                                            Korean Banks
  construction                                                     KfW
                                                                   ECAs
  1. WTG supplier for turbine supply                               Global Commercial Banks
  2. Consortium for EPC/BoP
  •Consortium also for installation
  turbines
  •Consortium main EPC contractor                                  Mezzanine Providers
  Grid                                          PROJECT
                                                  ±                EPC/Supply parties (vendor
                                                 GEMINI            finance)
  •WTG O&M contract                                                Electricity Off-takers (PPA)
  •Grid O&M contract

  •Insurance Contract(CAR & BI)                                    Envisaged Strategic +
                                                                   financial investors (equity)
                                                                   @FC
                                                                   HVC (15%)
                                                                   Typhoon Offshore (10%)
                                       Revenue from:               Contractors + Supplier (24%)
                                       PPA contract                Undisclosed as of yet (51%)
                                       SDE subsidy
                                       Green certificates (GVOs)




                                                                                                  12
                                              CONFIDENTIAL
A typical offshore wind farm: how does it work?
                                   2



                                   3




                                                                                                           6
                                                                       5
                                                                                         7




                                                   4


                            1
                                                                                                               Source:BWEA




•   Piles are driven into the seabed at a suitable place. The top of the foundation is painted a bright colour to make it visible to ships and has
    an access platform to allow maintenance teams to dock
•   Once the turbine is assembled, sensors on the turbine detect the wind direction and turn the head, known as the nacelle, to face into the
    wind, so that the blades can collect the maximum amount of energy. The movement of the wind over the aerodynamically shaped blades
    (2) makes them rotate around a horizontal hub, which is connected to a shaft inside the nacelle (3). This shaft, via a gearbox, powers a
    generator which converts the energy into electricity
•   Submarine cables (4 & 7) transport the power to an offshore transformer (5) which converts the electricity to a high voltage before
    running it back to connect to the grid at a substation on land (6)

                                                                                                                                                 13
                                                                 CONFIDENTIAL
Outline workschedule


•   Pile driving and installation of the foundations (1)
•   Installation wind turbine (2 & 3)
•   Infield cabling (4)
•   Transformer platform & Transformer AC/ DC Convertor platform (5)
•   Export cable (7)
•   Onshore Convertor DC/ AC Transformerstation (6)




                                                                       14
                                                  CONFIDENTIAL
Contracting Strategy: Two contract strategy

                                           Our business:
                                           Structuring, Contracting, Financing



                                           Typhoon Offshore
                                           • combines capital and industry leading knowhow
                                           • aims at superior financial and environmental returns
                                           • innovates by applying the dual contract model
                                           • resulting in bankable projects
                                           •Non recourse construction & project finance




       Clear Contracting strategy & Reliable contractors = No loose ends = Bankability


                                                                                                    15
                                       CONFIDENTIAL
3. INNOVATION / CHOICES




                                    16
                     CONFIDENTIAL
Start detailed design and engineering




                                              17
                               CONFIDENTIAL
Type of Foundations for Offshore wind




                                             18
                              CONFIDENTIAL
Design & detailed engineering


                                    •    Tenor 15 yrs
                                    •    Minimum 25 yrs
                                    •    Hostile environment
                                    •    Installation Challenges




  www.flyingfocus.nl

                                                                   19
                                CONFIDENTIAL
Foundation examples: Monopiles


                                           •   Water depths max 35 mtrs
                                           •   Turbines max 3,6MW
                                           •   Proven design
                                           •   Sufficient production capacity available




                                                                                          20
                            CONFIDENTIAL
Foundation examples: Tri-pod & Jackets
      Water depth >40mtrs                Water depths >20mtrs




      Turbines > 5MW                             Turbines > 5MW




                                                                  21
                              CONFIDENTIAL
Wind turbine structure


                             60 mtr                  Turbine 200 - 500 ton

                                                     Tower 200 ton


                                                     Foundation weight
                             67 mtr                  800 - 1250 ton


                                        235mtr

                             23 mtr



                             35 mtr
                                            97 mtr


                             50 mtr



                                                                         22
                         CONFIDENTIAL
Construction




               CONFIDENTIAL
Pile driving and scour protection




                                              24
                               CONFIDENTIAL
Vessel/Barge for pile driving and transition piece installation




                                CONFIDENTIAL
Transition piece and Installation of tower/ wind turbine




                               CONFIDENTIAL
Installation Transformer platform




                                              27
                               CONFIDENTIAL
Transformer platform & exportcable laying vessel




                              CONFIDENTIAL
Onshore cabling




                  CONFIDENTIAL
Maintenance


•   Full time maintenance

•   Scheduled and un-scheduled

•   Operations




                                                30
                                 CONFIDENTIAL
4. LOCAL IMPACT




                                 31
                  CONFIDENTIAL
(Possible) Impact of investments


•   New permanent job creation in the region; direct as well as indirect

    For our 600MW project:
    – During installation and construction on average 500 fte/yr
    – During operational phase on average 120 fte/yr


    In Germany about 25,000MW will be realized
    In the UK approximately 35,000MW

•   Further development of the Dutch maritime and installation industry

•   Dutch ports could become hubs for maintanence

•   The Netherlands are located at a central position in the North Sea Area.




                                                CONFIDENTIAL
Eemshaven leading the way in offshore wind
North Sea: global centre for Offshore Wind
 Largest, most dedicated and concentrated area for
offshore wind power > planned capacity of 60 to 80 GW
to be operational in the next 20 years.


 After the nuclear disaster in Japan, several European
governments emphasised their necessity to switch to
other sustainable energy sources. Germany not only
decided to fully cancel their nuclear energy
development program, they even decided to
completely stop their nuclear energy production


 Offshore wind considered one of the main sources
for sustainable Job creation and renewable energy in
North-West Europe. Strong dedication and support
from the public/governmental sector will accelerate           UK: 36 GW / Germany: 25 GW / Belgium: 2 GW / Netherlands:
                                                              3 GW /France 6 GW / Others (Scandinavia):
development and further shorten the planned timelines         10 GW
towards project completion.


                                                                                                                          33
                                               CONFIDENTIAL
Workshop/ factory for Monopiles and Jackets


                                            •   Foundations about 20,000 man-
                                                hours
                                            •   Based on Ikea-approach
                                            •   Pre fab tubular and other
                                            •   Secondary steel per ton 3 to 5 man-
                                                hours production.




                                                                                34
                             CONFIDENTIAL
What could all this do for the Eemshaven


•   Good geographical location

•   What industry is already present and what else is needed?

•   Steel processing

•   Logistics

•   Construction Support

•   Maintenance




                                                                35
                                               CONFIDENTIAL
Contact details




 Amsterdam - Head Office           London Office              Seoul Office
 Apollolaan 150                    133 Houndsditch            27F. Trade Tower
 1077 BG Amsterdam                 London EC3A 7BX            159-1 Samsung Dong, Seoul 135-729
 The Netherlands                   United Kingdom             South Korea
 Tel: +31 (0)20 840 8600           Tel: +44 (0)203 402 6022   Tel: +82 (0)2 6007 2677
 E-mail: info@typhoonoffshore.eu




                                                                                                  36
                                          CONFIDENTIAL

Mais conteúdo relacionado

Semelhante a To presentatie netwerkbijeenkomst eemshaven 120209

Gem general presentation-120207-sent
Gem general presentation-120207-sentGem general presentation-120207-sent
Gem general presentation-120207-sentTyphoonOffshore
 
Offshore wind supply chain bilbao alan 28 feb 2012
Offshore wind supply chain bilbao   alan 28 feb 2012Offshore wind supply chain bilbao   alan 28 feb 2012
Offshore wind supply chain bilbao alan 28 feb 2012British Embassy Madrid
 
140728 zeewind risk analysis eng v sent (meewind)
140728 zeewind risk analysis eng v sent (meewind)140728 zeewind risk analysis eng v sent (meewind)
140728 zeewind risk analysis eng v sent (meewind)Jaap Smelik
 
140617 zeewind risk_analysis_eng
140617 zeewind risk_analysis_eng140617 zeewind risk_analysis_eng
140617 zeewind risk_analysis_engJaap Smelik
 
Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010
Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010
Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010Burton Lee
 
Offshore Wind Energy In Europe Conference
Offshore Wind Energy In Europe ConferenceOffshore Wind Energy In Europe Conference
Offshore Wind Energy In Europe ConferenceTom
 
C offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide shareC offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide sharejbtolstoy
 
C offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide shareC offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide sharejbtolstoy
 
C offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide shareC offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide sharejbtolstoy
 
UNDERSTANDING THE LICENSING PROCESS FOR LARGE SCALE SOLAR PROJECTS
UNDERSTANDING THE LICENSING PROCESS FOR  LARGE SCALE SOLAR PROJECTSUNDERSTANDING THE LICENSING PROCESS FOR  LARGE SCALE SOLAR PROJECTS
UNDERSTANDING THE LICENSING PROCESS FOR LARGE SCALE SOLAR PROJECTSSuat Furkan ISIK
 
Pressrelease about Financial Close Gemini
Pressrelease about Financial Close GeminiPressrelease about Financial Close Gemini
Pressrelease about Financial Close GeminiGemini Windpark
 
Ie Wind Venture Business Plan
Ie Wind Venture Business PlanIe Wind Venture Business Plan
Ie Wind Venture Business Planfptoscano
 
Conference Call Presentation 1Q11
Conference Call Presentation 1Q11Conference Call Presentation 1Q11
Conference Call Presentation 1Q11MPX_RI
 
What it buyers really want john shaw - mainstream renewable power - 17 01-10
What it buyers really want   john shaw - mainstream renewable power - 17 01-10What it buyers really want   john shaw - mainstream renewable power - 17 01-10
What it buyers really want john shaw - mainstream renewable power - 17 01-10Sales Institute Ireland
 
Northland Power Investor Presentation
Northland Power Investor PresentationNorthland Power Investor Presentation
Northland Power Investor PresentationCompany Spotlight
 

Semelhante a To presentatie netwerkbijeenkomst eemshaven 120209 (20)

Gem general presentation-120207-sent
Gem general presentation-120207-sentGem general presentation-120207-sent
Gem general presentation-120207-sent
 
Emerging Africa Infrastructure Fund
Emerging Africa Infrastructure FundEmerging Africa Infrastructure Fund
Emerging Africa Infrastructure Fund
 
Offshore wind supply chain bilbao alan 28 feb 2012
Offshore wind supply chain bilbao   alan 28 feb 2012Offshore wind supply chain bilbao   alan 28 feb 2012
Offshore wind supply chain bilbao alan 28 feb 2012
 
140728 zeewind risk analysis eng v sent (meewind)
140728 zeewind risk analysis eng v sent (meewind)140728 zeewind risk analysis eng v sent (meewind)
140728 zeewind risk analysis eng v sent (meewind)
 
140617 zeewind risk_analysis_eng
140617 zeewind risk_analysis_eng140617 zeewind risk_analysis_eng
140617 zeewind risk_analysis_eng
 
Sgcp12 beel-ofgem
Sgcp12 beel-ofgemSgcp12 beel-ofgem
Sgcp12 beel-ofgem
 
Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010
Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010
Floating Power Plant Overview - Carsten Bech - Floating Power Plant - April 2010
 
Offshore Wind Energy In Europe Conference
Offshore Wind Energy In Europe ConferenceOffshore Wind Energy In Europe Conference
Offshore Wind Energy In Europe Conference
 
C offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide shareC offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide share
 
C offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide shareC offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide share
 
C offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide shareC offshore jeju 2013 02 24 f slide share
C offshore jeju 2013 02 24 f slide share
 
LOI 4 MW
LOI 4 MWLOI 4 MW
LOI 4 MW
 
UNDERSTANDING THE LICENSING PROCESS FOR LARGE SCALE SOLAR PROJECTS
UNDERSTANDING THE LICENSING PROCESS FOR  LARGE SCALE SOLAR PROJECTSUNDERSTANDING THE LICENSING PROCESS FOR  LARGE SCALE SOLAR PROJECTS
UNDERSTANDING THE LICENSING PROCESS FOR LARGE SCALE SOLAR PROJECTS
 
02 decc ukccsc_winter_school_2012_updated
02 decc ukccsc_winter_school_2012_updated02 decc ukccsc_winter_school_2012_updated
02 decc ukccsc_winter_school_2012_updated
 
Pressrelease about Financial Close Gemini
Pressrelease about Financial Close GeminiPressrelease about Financial Close Gemini
Pressrelease about Financial Close Gemini
 
Pelamis bilbao ukti pwp 2012
Pelamis bilbao ukti pwp 2012Pelamis bilbao ukti pwp 2012
Pelamis bilbao ukti pwp 2012
 
Ie Wind Venture Business Plan
Ie Wind Venture Business PlanIe Wind Venture Business Plan
Ie Wind Venture Business Plan
 
Conference Call Presentation 1Q11
Conference Call Presentation 1Q11Conference Call Presentation 1Q11
Conference Call Presentation 1Q11
 
What it buyers really want john shaw - mainstream renewable power - 17 01-10
What it buyers really want   john shaw - mainstream renewable power - 17 01-10What it buyers really want   john shaw - mainstream renewable power - 17 01-10
What it buyers really want john shaw - mainstream renewable power - 17 01-10
 
Northland Power Investor Presentation
Northland Power Investor PresentationNorthland Power Investor Presentation
Northland Power Investor Presentation
 

Último

2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 

Último (20)

2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 

To presentatie netwerkbijeenkomst eemshaven 120209

  • 1. Netwerkbijeenkomst Eemshaven February 2012 Making Sustainability Bankable CONFIDENTIAL
  • 2. Disclaimer This presentation was prepared by Typhoon Offshore B.V. (“TO”) exclusively for use at the “Netwerkbijeenkomst Eemshaven”. This presentation is incomplete without reference to, and should be viewed solely in conjunction with, the oral briefing provided by TO. Information in this presentation may be based upon management forecasts and reflects prevailing conditions and our views as of this date, which are accordingly subject to change. No representation or warranty is made or accepted in respect of the information contained herein. This presentation is proprietary to TO and may not be disclosed to any third party or used for any other purpose. By accepting this document, the recipient agrees that he/she will not copy, reproduce, distribute or otherwise disclose this document or the contents hereof at any time without the prior written consent of TO. Making Sustainability Bankable 2 CONFIDENTIAL
  • 3. Contents 1. Introduction Typhoon Offshore 2. Realisation offshore windproject Gemini 3. Innovation/choices 4. Local Impact 3 CONFIDENTIAL
  • 4. 1. INTRODUCTION 4 CONFIDENTIAL
  • 5. Typhoon Offshore: Building on Expertise Typhoon Offshore  Typhoon Offshore is the daughter company of Typhoon Capital (Est. Amsterdam 2009) and is dedicated to investing in and development of offshore wind energy projects.  Typhoon Offshore’s objective is to acquire stakes in offshore wind projects in the North Sea. Typhoon Offshore then contributes its expertise to bring these projects to financial close, creating value and compelling investment cases for long term investors.  Members of Typhoon Offshore’s core-team • Strong transaction execution skills successfully managed the landmark projects Belwind • M&A and financing expertise and PrinsesAmalia [Q7] to financial close and during • Structuring capabilities construction, and were responsible for innovations • Technical expertise which have become market practice. The team has a • Project management experience strong network in Europe, Asia and the Middle East. • Financial control experience 5 CONFIDENTIAL
  • 6. Typhoon Offshore: Building on Expertise The team already developed, financed and/or commissioned over 20 renewable energy infrastructure projects with a total capacity in excess of 1GW and a transaction value of around EUR 2 billion 6 CONFIDENTIAL
  • 7. Typhoon Offshore: position in the value chain Key project milestones Securing permits Structuring Contracting Financing Construction Operational site rights 2 – 10 yrs 1 – 2 yrs 2 – 4 yrs 20 yrs+ 7 CONFIDENTIAL
  • 8. 2. REALIZATION OFFSHORE WINDPROJECT GEMINI 8 CONFIDENTIAL
  • 9. Project Gemini 600MW Offshore wind in the Netherlands • Involved since September 2009, TO acquired 30% interest in early 2010 and in August 2011 TO acquired full ownership of the Dutch Project “Gemini” (formerly BARD Offshore Netherlands). • With its planned 600 MW capacity, it is the largest offshore wind farm to date in the North Sea area, totalling a CAPEX of €2.4 Bln. • Financial close is scheduled for Summer 2012 and start of construction in 2013  Project characteristics • Project Gemini consists of 2 X 300 MW fully permitted offshore wind farms in the Netherlands. • Buitengaats (300MW) and ZeeEnergie (300MW) have both an approved permit (“Wbr”) and a granted Dutch feed-in tariff (‘SDE”). 9 CONFIDENTIAL
  • 10. Project Gemini…..continue Gemini Offshore Nederland: • 600MW • (100-200) x (3- 6MW turbines • Waterdepth : 20-40m. • Distance to shore: ca. 85KM • 2 Offshore platforms + 1 On shore grid station. Total amount of steel: ±200.000’MT’ (Foundations, tower, platform) Approx 500km Cabling Construction Costs: • Turbine supplier agreement € 800m • EPC/BoP € 700m • Grid € 550m Other Costs: • Financial and structuring, devex €350m 15 yrs Full Maintenance & Insurance contract Tennet 10 CONFIDENTIAL
  • 11. Project Gemini – Green Energy • Project Gemini is located at one of the best offshore wind location in NL with average wind speeds of ±10 m/s Estimated annual production for 600MW: 2,400 GWh. • Electricity for ± 700,000 households / 1,500,000 habitants per annum which almost equals the number of people living in the 3 Northern provinces of The Netherlands. • Annual emission reduction • 1,250,000 Ton CO₂ • 3968 Ton Nox • 4284 Ton SO2 11 CONFIDENTIAL
  • 12. Stakeholders Sponsors: Debt Providers HVC (15%) EIB Typhoon Offshore (85%) Contracts, supplier & Korean Banks construction KfW ECAs 1. WTG supplier for turbine supply Global Commercial Banks 2. Consortium for EPC/BoP •Consortium also for installation turbines •Consortium main EPC contractor Mezzanine Providers Grid PROJECT ± EPC/Supply parties (vendor GEMINI finance) •WTG O&M contract Electricity Off-takers (PPA) •Grid O&M contract •Insurance Contract(CAR & BI) Envisaged Strategic + financial investors (equity) @FC HVC (15%) Typhoon Offshore (10%) Revenue from: Contractors + Supplier (24%) PPA contract Undisclosed as of yet (51%) SDE subsidy Green certificates (GVOs) 12 CONFIDENTIAL
  • 13. A typical offshore wind farm: how does it work? 2 3 6 5 7 4 1 Source:BWEA • Piles are driven into the seabed at a suitable place. The top of the foundation is painted a bright colour to make it visible to ships and has an access platform to allow maintenance teams to dock • Once the turbine is assembled, sensors on the turbine detect the wind direction and turn the head, known as the nacelle, to face into the wind, so that the blades can collect the maximum amount of energy. The movement of the wind over the aerodynamically shaped blades (2) makes them rotate around a horizontal hub, which is connected to a shaft inside the nacelle (3). This shaft, via a gearbox, powers a generator which converts the energy into electricity • Submarine cables (4 & 7) transport the power to an offshore transformer (5) which converts the electricity to a high voltage before running it back to connect to the grid at a substation on land (6) 13 CONFIDENTIAL
  • 14. Outline workschedule • Pile driving and installation of the foundations (1) • Installation wind turbine (2 & 3) • Infield cabling (4) • Transformer platform & Transformer AC/ DC Convertor platform (5) • Export cable (7) • Onshore Convertor DC/ AC Transformerstation (6) 14 CONFIDENTIAL
  • 15. Contracting Strategy: Two contract strategy Our business: Structuring, Contracting, Financing Typhoon Offshore • combines capital and industry leading knowhow • aims at superior financial and environmental returns • innovates by applying the dual contract model • resulting in bankable projects •Non recourse construction & project finance Clear Contracting strategy & Reliable contractors = No loose ends = Bankability 15 CONFIDENTIAL
  • 16. 3. INNOVATION / CHOICES 16 CONFIDENTIAL
  • 17. Start detailed design and engineering 17 CONFIDENTIAL
  • 18. Type of Foundations for Offshore wind 18 CONFIDENTIAL
  • 19. Design & detailed engineering • Tenor 15 yrs • Minimum 25 yrs • Hostile environment • Installation Challenges www.flyingfocus.nl 19 CONFIDENTIAL
  • 20. Foundation examples: Monopiles • Water depths max 35 mtrs • Turbines max 3,6MW • Proven design • Sufficient production capacity available 20 CONFIDENTIAL
  • 21. Foundation examples: Tri-pod & Jackets Water depth >40mtrs Water depths >20mtrs Turbines > 5MW Turbines > 5MW 21 CONFIDENTIAL
  • 22. Wind turbine structure 60 mtr Turbine 200 - 500 ton Tower 200 ton Foundation weight 67 mtr 800 - 1250 ton 235mtr 23 mtr 35 mtr 97 mtr 50 mtr 22 CONFIDENTIAL
  • 23. Construction CONFIDENTIAL
  • 24. Pile driving and scour protection 24 CONFIDENTIAL
  • 25. Vessel/Barge for pile driving and transition piece installation CONFIDENTIAL
  • 26. Transition piece and Installation of tower/ wind turbine CONFIDENTIAL
  • 28. Transformer platform & exportcable laying vessel CONFIDENTIAL
  • 29. Onshore cabling CONFIDENTIAL
  • 30. Maintenance • Full time maintenance • Scheduled and un-scheduled • Operations 30 CONFIDENTIAL
  • 31. 4. LOCAL IMPACT 31 CONFIDENTIAL
  • 32. (Possible) Impact of investments • New permanent job creation in the region; direct as well as indirect For our 600MW project: – During installation and construction on average 500 fte/yr – During operational phase on average 120 fte/yr In Germany about 25,000MW will be realized In the UK approximately 35,000MW • Further development of the Dutch maritime and installation industry • Dutch ports could become hubs for maintanence • The Netherlands are located at a central position in the North Sea Area. CONFIDENTIAL
  • 33. Eemshaven leading the way in offshore wind North Sea: global centre for Offshore Wind  Largest, most dedicated and concentrated area for offshore wind power > planned capacity of 60 to 80 GW to be operational in the next 20 years.  After the nuclear disaster in Japan, several European governments emphasised their necessity to switch to other sustainable energy sources. Germany not only decided to fully cancel their nuclear energy development program, they even decided to completely stop their nuclear energy production  Offshore wind considered one of the main sources for sustainable Job creation and renewable energy in North-West Europe. Strong dedication and support from the public/governmental sector will accelerate UK: 36 GW / Germany: 25 GW / Belgium: 2 GW / Netherlands: 3 GW /France 6 GW / Others (Scandinavia): development and further shorten the planned timelines 10 GW towards project completion. 33 CONFIDENTIAL
  • 34. Workshop/ factory for Monopiles and Jackets • Foundations about 20,000 man- hours • Based on Ikea-approach • Pre fab tubular and other • Secondary steel per ton 3 to 5 man- hours production. 34 CONFIDENTIAL
  • 35. What could all this do for the Eemshaven • Good geographical location • What industry is already present and what else is needed? • Steel processing • Logistics • Construction Support • Maintenance 35 CONFIDENTIAL
  • 36. Contact details Amsterdam - Head Office London Office Seoul Office Apollolaan 150 133 Houndsditch 27F. Trade Tower 1077 BG Amsterdam London EC3A 7BX 159-1 Samsung Dong, Seoul 135-729 The Netherlands United Kingdom South Korea Tel: +31 (0)20 840 8600 Tel: +44 (0)203 402 6022 Tel: +82 (0)2 6007 2677 E-mail: info@typhoonoffshore.eu 36 CONFIDENTIAL