EFFICIENCY FINANCE WORKSHOPS
 Session 1. Project Financing and Project Opportunities




 A Groundbreaking High-Performance
 Building District in Downtown Seattle
Performance Targets

The 2030 Challenge for Planning
Existing Buildings
10%                            50% reduction in
       20%                     water
             35%               consumption
                     50%
                           +   50% reduction in
                               Vehicle Miles
                               Traveled (VMT) for
                               auto and freight
STATEMENT OF ENERGY
                         PERFORMANCE
                         Seattle 2030 District Office Building
                      Building ID: 0000000
                      For 12-month Period Ending: Dec 31, 20121
Date SEP becomes ineligible: N/A    Date SEP Generated: Jan 20, 2013

Facility
Seattle 2030 District Office Building
2030 District
Seattle, WA 98104

Year Built: 1987
Gross Floor Area (ft2): 350,000

Energy Performance Rating2 (1-100) 60

Site Energy Use Summary3
Electricity - Grid Purchase(kBtu)                        22,866,666
Natural Gas - (kBtu)4                                    11,433,334
Total Energy (kBtu)                                      34,300,000

Energy Intensity5
Site (kBtu/ft2/yr)                                               98
Source (kBtu/ft2/yr)                                             252

Emissions (based on site energy use)
Greenhouse Gas Emissions (MtCO2e/year)                         3,233

Electric Distribution Utility
Seattle City Light

National Average Comparison
National Average Site EUI                                       110
National Average Source EUI                                      283
% Difference from National Average Source EUI                   -11%
Building Type                                           Office/Retail
S2030D Preliminary Assessment results

            savings $$
                           operational savings          20% - $ 52,185


                           system upgrade savings       60% - $ 156,556

                           shell improvement            20% - $ 52,185
                           savings

                           water savings                $ 9,736




                cost $$
                              operational costs         4% - $ 65,232 - payback – 1.25 years


                              system upgrade costs      43% - $ 782,781 - payback – 5 years


                              shell improvement costs   53% - $ 974,476 - payback – 18.75 years


                              water improvement costs $ 68,152 - payback – 7 years
General Funding Guidelines

• Pre-approval required
                                                         SCL Commercial & Industrial kWh
  – Bring your ideas, even before the project                 Savings Breakdown
    has been clearly defined
  – Site visits can help assess opportunities                     Other           HVAC
                                                                   19%             20%

• Incentive amount
  – based on total energy saved and
                                                  Refrigeration
    measure life                                       8%
  – Funding capped at 70% of total cost
    (SCL and PSE)
• Post-Installation
  – Inspection to confirm equipment and                                    Lighting
    operation; may require trend-logs or                                     53%
    metering
  – As-built conditions used to calculate final
    savings


                   - and -
Technical Assistance

• Site Visits
   – Recommendations for energy conservation and
     O&M measures
   – Identify measures that qualify for financial
     incentives
   – Review/assess bids for funding
• Energy Analysis Assistance (SCL)
   – Funding for in-depth energy analysis done by a
     consultant or a design team
   – Ranked recommendations by cost/benefit
     analysis
• Lighting Design Lab Assistance
   – Design assistance and mock-up services
   – Education and training


                    - and -                           8
Prescriptive Rebates (SCL and PSE)

• Fixed amount per unit
• Pre-authorization required
• Typical Rebates
  – Occupancy sensors for lighting (SCL, PSE)
  – Commercial kitchen equipment (SCL, PSE)
  – IT server virtualization (SCL)
  – PC power management and thin Client (SCL, PSE)
  – HVAC equipment (PSE)




                   - and -                           Conserving Today. Sustaining Tomorrow.   9
Standard Incentives (SCL)

• For common measures in existing
 buildings
  – Lighting retrofits (fluorescents, exit signs, LEDs, etc)
  – Lighting controls (central and OS)
  – Chillers (air and water cooled)
  – Air conditioners (Standard, CRAC, and PTAC)
  – Heat pumps (air to air, hydronic, and PTHP)
  – VSDs for Fans and Pumps

• Pre-formatted workbooks
  – Estimates savings and incentives
  – Can be filled in by contactors, customers or SCL
    energy analyst, step by step instructions
  – Contains all documents required, download via web

                   - and -                                     Conserving Today. Sustaining Tomorrow.   10
Custom Incentives (SCL and PSE)

• Customized calculations for non-
 routine measures
  – Typically includes multiple systems
  – May require pre-monitoring to determine
    baseline

• Incentive based on savings and
 measure life
• Numerous applications
  – HVAC (controls, heat recovery, chillers
    and cooling towers)
  – Data centers (hot/cold isle)
  – Special environments (labs, industrial,
    etc)


                  - and -                     Conserving Today. Sustaining Tomorrow.   11
Potential Incentives – Sample Building
                              Savings % of    Savings       Savings       Savings     Savings
                               Total Use       kBtu         Measure        kWh        therms       $ Utility Rebates
                                                                                                 Electric      Gas
  Current Energy Use                         34,300,000                   6,701,836   114,333
                                                             Retro-
  Operational Savings            8.8%
                                              3,018,400   commissioning    884,642               $53,079

  System Upgrade Savings         26.4%        9,055,200      Lighting      444,533              $102,243
                                                              HVAC        1,333,598   29,882    $306,728     $149,411
  Shell Improvement Savings      8.8%         3,018,400       Shell        592,710    10,172     $59,271      $50,860
  Total Savings                  44.0%       15,092,000                   3,255,484   40,054    $521,320     $200,271


• Lighting
   – Prescriptive and standard incentives to upgrade lighting and lighting controls
• HVAC Systems and Controls
   – Standard and/or custom incentives to upgrade equipment and controls
• Shell Measures
   – Custom incentives for insulation, sealing, improved glazing, etc
• Retro Commissioning
   – Enroll building in Retro commissioning program to capture operational savings


                        - and -                                              Conserving Today. Sustaining Tomorrow.     12
Contact us to get Started

• Please remember to contact us BEFORE you start a project so
 that we can discuss eligibility and help you with the rebate
 process
  • Call us:                (206) 684-3800 Seattle City Light Energy
  Advisors
  • Email us:
  SCLEnergyAdvisor@seattle.gov
  • Visit us online:
  www.seattle.gov/light/conserve
  • Call us:                    (800) 562-1482 Puget Sound Energy
  Advisors
  • Visit us online:
  http://www.pse.com/savingsandenergycenter/ForBusinesses/Pages/Co
  mprehensive-Building-Tune-Up-Program.aspx


               - and -                       Conserving Today. Sustaining Tomorrow.   13
Energy Services Contracting
                         A different mindset

     Design-spec-build                         Integrated Delivery
 •   Segmentation                     •   Single point of accountability
 •   1st cost                         •   Total Cost of Ownership
 •   Task/problem driven              •   Holistic view and deep dive on
 •   Diffused responsibility              building systems
                                           • Fix the root cause, not the
                                             symptom
                                      •   Guaranteed project outcomes
                                           •   Cost
                                           •   Savings
                                      •   Take advantage of grants and
                                          incentives
                                           • CPW
                                           • P4P/Utility rebates
                                           • Low–cost financing
Optimizing the Capital Stack
                       Utility
                      Rebates
      Cash 25%         10%
                                 Incentives
                                    15%




                 Debt 50%
Energy Services Contracting Financing
•   ESCO finance
•   ESCO Brokerage
    •   See handout for cash flows of model building at commercial rates
•   Property Assessed Clean Energy (Commercial PACE)
    •   Senior lien property tax assessment to fund efficiency measures
        and/or renewable energy on private commercial property
    •   Concept in infancy, slowly gaining traction
    •   Not available in Washington State at this time
•   Qualified Energy Conservation Bonds
    •   With enactment of King County’s Green Community Initiative,
        private property owners will be able to access QECBs for energy
        efficiency improvements
    •   QECBs enable rates of ~ 2.0%-3.0% and tenors up to 24 years
    •   See King County Green Community Initiative handout

Contact: Rachel Brombaugh, rachelb@mckinstry.com, (206) 832-8132
The Sustainable Energy Program:
  Qualified Energy Conservation Bonds and Beyond…


Avi Jacobson
Senior Sustainable Energy Coordinator
Washington State Housing Finance Commission
avi.jacobson@wshfc.org
206-254-5359
The Sustainable Energy Program
•   Introduction
•   What are QECBs? How Do They Work?
•   QECB Aggregation Efforts
•   Green Communities Programs
•   Sustainable Energy Trust
•   Conclusion
•   Questions
QECB Aggregation:
WSHFC as State QECB Clearinghouse
   • Washington State:
     o $67.8M Allocated across WA
     o ~$32M Issued
     o In conjunction with WA Department of
       Commerce, have contacted all
       jurisdictions with remaining QECB
       Authority
     o $27M reallocated to WSHFC, $13.5M+
       issued, more promised so far…
What is a Green
                      Community Program?
Two Required Elements:
  • Program Purpose
     • Program goal must be to promote energy conservation,
       energy efficiency or environmental conservation initiatives
       related to energy consumption.
  • General Public Use or Broad Public Availability
     • Financing must involve either:
         • Property available for general public use, or
         • Loan or grant program broadly available to members
           of the general public.
Financing Energy Efficiency Projects:



              Presented by:
              Dan Clarkson
      Energy Efficiency Finance Corp.
        dclarkson@eefinance.net
              206-310-8733
Energy Efficiency Pays Off
Offer to Building Owner
•   Energy Services Agreement (ESA)
•   No upfront capital costs; preserve capital for other purposes
•   Turnkey implementation by ESCO: engineering, equipment
    procurement, installation, commissioning, services, savings
    monitoring, savings guarantees
•   Grant/incentive funds used for subordinated debt financing,
    debt service reserve, & carbon reduction incentives
•   Project paid through operating cost savings; breakeven
    savings are guaranteed by ESCO
•   Payments on utility bill reduces risk for investor
How it Works                       Seattle
                                                                             City
                                                                             Light

                                                                                  Utility
                                                                                Incentives
                                                        Energy Services
                                    Turnkey               Agreement
                     Energy         Project
  Sub-
  Loan               Capital                  ESCO                        Customer
                    Solutions


  CPW
                                                                 Energy
                                                                 supply
Incentive &
  Reserve
   Fund                Retail                 Energy
                       Lock
                        Box                   Utility             Steam &
              EE project payments via                           ESA Payments
                  Escrow Services
                    Agreement
ECS Cashflow Model
1200000




1000000
                                   Retrofit
                                    22%                        Net Customer Savings
800000                             Savings


                                                            ESA Payments
600000




400000




200000
          Utility Costs

                                                                                     Cumulative Customer Savings
      0
          Year -3   Year -2   Year -1   Year 0   Year 1   Year 2   Year 3   Year 4    Year 5   Year 6   Year 7   Year 8   Year 9   Year 10

Mais conteúdo relacionado

Mais procurados

ABA Energy Star Challenge for the Industry
ABA Energy Star Challenge for the IndustryABA Energy Star Challenge for the Industry
ABA Energy Star Challenge for the Industryamericanbakers
 
Solar Energy Choices Magazine3
Solar Energy Choices Magazine3Solar Energy Choices Magazine3
Solar Energy Choices Magazine3comF5
 
20110302 on vector green datacenters
20110302 on vector green datacenters20110302 on vector green datacenters
20110302 on vector green datacentersBill St. Arnaud
 
Duke Energy 3Q 03_EPS_Reconciliation
 Duke Energy 3Q 03_EPS_Reconciliation Duke Energy 3Q 03_EPS_Reconciliation
Duke Energy 3Q 03_EPS_Reconciliationfinance21
 
European Demand Response conference
European Demand Response conferenceEuropean Demand Response conference
European Demand Response conferenceDale Butler
 
Solar Water Heating Contractor and Self Installer Training
Solar Water Heating Contractor and Self Installer TrainingSolar Water Heating Contractor and Self Installer Training
Solar Water Heating Contractor and Self Installer TrainingCenter for Sustainable Energy
 
Green it vmug presentation v1
Green it vmug presentation v1Green it vmug presentation v1
Green it vmug presentation v1subtitle
 
Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic ProjectHarry Indig
 
Duke Energy 4Q 03_EPS_Reconciliation
 Duke Energy 4Q 03_EPS_Reconciliation Duke Energy 4Q 03_EPS_Reconciliation
Duke Energy 4Q 03_EPS_Reconciliationfinance21
 
Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014
Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014
Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014Green Parking Council
 
Utility Scale PV Yield Optimization Conference & Expo 2010
Utility Scale PV Yield Optimization Conference & Expo 2010Utility Scale PV Yield Optimization Conference & Expo 2010
Utility Scale PV Yield Optimization Conference & Expo 2010New Solar Today
 
Artelia Industrial Services Asian Region
Artelia Industrial Services   Asian RegionArtelia Industrial Services   Asian Region
Artelia Industrial Services Asian Regionlequereanne
 
This is Every Building
This is Every BuildingThis is Every Building
This is Every BuildingBNIM
 
Led Street Light Test Project Report
Led Street Light Test Project ReportLed Street Light Test Project Report
Led Street Light Test Project ReportTony
 
Here Comes The Sun
Here Comes The SunHere Comes The Sun
Here Comes The Sunfsnorton
 

Mais procurados (19)

ABA Energy Star Challenge for the Industry
ABA Energy Star Challenge for the IndustryABA Energy Star Challenge for the Industry
ABA Energy Star Challenge for the Industry
 
Tokyo Initiative for a Low Carbon & Resilient City
Tokyo Initiative for a Low Carbon & Resilient CityTokyo Initiative for a Low Carbon & Resilient City
Tokyo Initiative for a Low Carbon & Resilient City
 
Solar Energy Choices Magazine3
Solar Energy Choices Magazine3Solar Energy Choices Magazine3
Solar Energy Choices Magazine3
 
20110302 on vector green datacenters
20110302 on vector green datacenters20110302 on vector green datacenters
20110302 on vector green datacenters
 
Final
FinalFinal
Final
 
Duke Energy 3Q 03_EPS_Reconciliation
 Duke Energy 3Q 03_EPS_Reconciliation Duke Energy 3Q 03_EPS_Reconciliation
Duke Energy 3Q 03_EPS_Reconciliation
 
European Demand Response conference
European Demand Response conferenceEuropean Demand Response conference
European Demand Response conference
 
Solar Water Heating Contractor and Self Installer Training
Solar Water Heating Contractor and Self Installer TrainingSolar Water Heating Contractor and Self Installer Training
Solar Water Heating Contractor and Self Installer Training
 
Fed lcc-2010-green buildings
Fed lcc-2010-green buildingsFed lcc-2010-green buildings
Fed lcc-2010-green buildings
 
Green it vmug presentation v1
Green it vmug presentation v1Green it vmug presentation v1
Green it vmug presentation v1
 
Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic Project
 
Duke Energy 4Q 03_EPS_Reconciliation
 Duke Energy 4Q 03_EPS_Reconciliation Duke Energy 4Q 03_EPS_Reconciliation
Duke Energy 4Q 03_EPS_Reconciliation
 
Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014
Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014
Lighting Energy Efficiency in Parking (LEEP) Campaign Awards 2014
 
Utility Scale PV Yield Optimization Conference & Expo 2010
Utility Scale PV Yield Optimization Conference & Expo 2010Utility Scale PV Yield Optimization Conference & Expo 2010
Utility Scale PV Yield Optimization Conference & Expo 2010
 
Artelia Industrial Services Asian Region
Artelia Industrial Services   Asian RegionArtelia Industrial Services   Asian Region
Artelia Industrial Services Asian Region
 
This is Every Building
This is Every BuildingThis is Every Building
This is Every Building
 
Eecs Cert Report
Eecs Cert ReportEecs Cert Report
Eecs Cert Report
 
Led Street Light Test Project Report
Led Street Light Test Project ReportLed Street Light Test Project Report
Led Street Light Test Project Report
 
Here Comes The Sun
Here Comes The SunHere Comes The Sun
Here Comes The Sun
 

Semelhante a Finance workshop Session 1 - Project Financing and Project Opportunities

GTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityGTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityDiana Nash
 
GRESB Greenbuild 2017 PACE Financing
GRESB Greenbuild 2017 PACE Financing GRESB Greenbuild 2017 PACE Financing
GRESB Greenbuild 2017 PACE Financing GRESB
 
Working with Trade Allies to Enhance Energy Efficiency Programs
Working with Trade Allies to Enhance Energy Efficiency ProgramsWorking with Trade Allies to Enhance Energy Efficiency Programs
Working with Trade Allies to Enhance Energy Efficiency ProgramsCenter for Energy and Environment
 
Presentation Fredricton September 2009 general
Presentation Fredricton September 2009 generalPresentation Fredricton September 2009 general
Presentation Fredricton September 2009 generalAngelo Mangatal
 
HPB Presentation DFS 11 Sep 12
HPB Presentation DFS 11 Sep 12HPB Presentation DFS 11 Sep 12
HPB Presentation DFS 11 Sep 12agreengarrett
 
Top 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOCTop 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOCMassRecycle
 
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptxSayeedHvac
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxSchneider Electric
 
MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...
MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...
MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...Midwest Energy Efficiency Alliance
 
Net-Zero Energy Case Studies
Net-Zero Energy Case StudiesNet-Zero Energy Case Studies
Net-Zero Energy Case Studiesaiahouston
 
Smart Ideas for Your Business
Smart Ideas for Your BusinessSmart Ideas for Your Business
Smart Ideas for Your BusinessIllinois ASHRAE
 
Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants  Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants Clean Coalition
 
High Performance Buidlings for Brazil
High Performance Buidlings for BrazilHigh Performance Buidlings for Brazil
High Performance Buidlings for Brazilsekkelww
 
Funding Energy Efficiency With Rebates & Incentives Kim
Funding Energy Efficiency With Rebates & Incentives KimFunding Energy Efficiency With Rebates & Incentives Kim
Funding Energy Efficiency With Rebates & Incentives Kimkimcollins01
 
Pv sales intro and session one
Pv sales intro and session one Pv sales intro and session one
Pv sales intro and session one moeshahram
 
Andrew Chant\'s CanWEA O & M Presentation
Andrew Chant\'s CanWEA  O  & M  PresentationAndrew Chant\'s CanWEA  O  & M  Presentation
Andrew Chant\'s CanWEA O & M Presentationmtingle
 

Semelhante a Finance workshop Session 1 - Project Financing and Project Opportunities (20)

Big Savings for Clean Generation Part III
Big Savings for Clean Generation Part IIIBig Savings for Clean Generation Part III
Big Savings for Clean Generation Part III
 
GTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityGTC_Energy Services_Mexico City
GTC_Energy Services_Mexico City
 
Mike Twedt on Green Energy Engineering
Mike Twedt on Green Energy EngineeringMike Twedt on Green Energy Engineering
Mike Twedt on Green Energy Engineering
 
GRESB Greenbuild 2017 PACE Financing
GRESB Greenbuild 2017 PACE Financing GRESB Greenbuild 2017 PACE Financing
GRESB Greenbuild 2017 PACE Financing
 
Working with Trade Allies to Enhance Energy Efficiency Programs
Working with Trade Allies to Enhance Energy Efficiency ProgramsWorking with Trade Allies to Enhance Energy Efficiency Programs
Working with Trade Allies to Enhance Energy Efficiency Programs
 
Presentation Fredricton September 2009 general
Presentation Fredricton September 2009 generalPresentation Fredricton September 2009 general
Presentation Fredricton September 2009 general
 
BEA deck 2.22.13
BEA deck   2.22.13BEA deck   2.22.13
BEA deck 2.22.13
 
HPB Presentation DFS 11 Sep 12
HPB Presentation DFS 11 Sep 12HPB Presentation DFS 11 Sep 12
HPB Presentation DFS 11 Sep 12
 
Top 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOCTop 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOC
 
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
 
MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...
MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...
MEEA Industrial Webinar: Industrial Load Reduction: The Role of Intelligent L...
 
Net-Zero Energy Case Studies
Net-Zero Energy Case StudiesNet-Zero Energy Case Studies
Net-Zero Energy Case Studies
 
Smart Ideas for Your Business
Smart Ideas for Your BusinessSmart Ideas for Your Business
Smart Ideas for Your Business
 
Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants  Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants
 
High Performance Buidlings for Brazil
High Performance Buidlings for BrazilHigh Performance Buidlings for Brazil
High Performance Buidlings for Brazil
 
Funding Energy Efficiency With Rebates & Incentives Kim
Funding Energy Efficiency With Rebates & Incentives KimFunding Energy Efficiency With Rebates & Incentives Kim
Funding Energy Efficiency With Rebates & Incentives Kim
 
Pv sales intro and session one
Pv sales intro and session one Pv sales intro and session one
Pv sales intro and session one
 
Integrative Design Working With Your Mep
Integrative Design Working With Your MepIntegrative Design Working With Your Mep
Integrative Design Working With Your Mep
 
Andrew Chant\'s CanWEA O & M Presentation
Andrew Chant\'s CanWEA  O  & M  PresentationAndrew Chant\'s CanWEA  O  & M  Presentation
Andrew Chant\'s CanWEA O & M Presentation
 

Finance workshop Session 1 - Project Financing and Project Opportunities

  • 1. EFFICIENCY FINANCE WORKSHOPS Session 1. Project Financing and Project Opportunities A Groundbreaking High-Performance Building District in Downtown Seattle
  • 2.
  • 3.
  • 4. Performance Targets The 2030 Challenge for Planning Existing Buildings 10% 50% reduction in 20% water 35% consumption 50% + 50% reduction in Vehicle Miles Traveled (VMT) for auto and freight
  • 5. STATEMENT OF ENERGY PERFORMANCE Seattle 2030 District Office Building Building ID: 0000000 For 12-month Period Ending: Dec 31, 20121 Date SEP becomes ineligible: N/A Date SEP Generated: Jan 20, 2013 Facility Seattle 2030 District Office Building 2030 District Seattle, WA 98104 Year Built: 1987 Gross Floor Area (ft2): 350,000 Energy Performance Rating2 (1-100) 60 Site Energy Use Summary3 Electricity - Grid Purchase(kBtu) 22,866,666 Natural Gas - (kBtu)4 11,433,334 Total Energy (kBtu) 34,300,000 Energy Intensity5 Site (kBtu/ft2/yr) 98 Source (kBtu/ft2/yr) 252 Emissions (based on site energy use) Greenhouse Gas Emissions (MtCO2e/year) 3,233 Electric Distribution Utility Seattle City Light National Average Comparison National Average Site EUI 110 National Average Source EUI 283 % Difference from National Average Source EUI -11% Building Type Office/Retail
  • 6. S2030D Preliminary Assessment results savings $$ operational savings 20% - $ 52,185 system upgrade savings 60% - $ 156,556 shell improvement 20% - $ 52,185 savings water savings $ 9,736 cost $$ operational costs 4% - $ 65,232 - payback – 1.25 years system upgrade costs 43% - $ 782,781 - payback – 5 years shell improvement costs 53% - $ 974,476 - payback – 18.75 years water improvement costs $ 68,152 - payback – 7 years
  • 7. General Funding Guidelines • Pre-approval required SCL Commercial & Industrial kWh – Bring your ideas, even before the project Savings Breakdown has been clearly defined – Site visits can help assess opportunities Other HVAC 19% 20% • Incentive amount – based on total energy saved and Refrigeration measure life 8% – Funding capped at 70% of total cost (SCL and PSE) • Post-Installation – Inspection to confirm equipment and Lighting operation; may require trend-logs or 53% metering – As-built conditions used to calculate final savings - and -
  • 8. Technical Assistance • Site Visits – Recommendations for energy conservation and O&M measures – Identify measures that qualify for financial incentives – Review/assess bids for funding • Energy Analysis Assistance (SCL) – Funding for in-depth energy analysis done by a consultant or a design team – Ranked recommendations by cost/benefit analysis • Lighting Design Lab Assistance – Design assistance and mock-up services – Education and training - and - 8
  • 9. Prescriptive Rebates (SCL and PSE) • Fixed amount per unit • Pre-authorization required • Typical Rebates – Occupancy sensors for lighting (SCL, PSE) – Commercial kitchen equipment (SCL, PSE) – IT server virtualization (SCL) – PC power management and thin Client (SCL, PSE) – HVAC equipment (PSE) - and - Conserving Today. Sustaining Tomorrow. 9
  • 10. Standard Incentives (SCL) • For common measures in existing buildings – Lighting retrofits (fluorescents, exit signs, LEDs, etc) – Lighting controls (central and OS) – Chillers (air and water cooled) – Air conditioners (Standard, CRAC, and PTAC) – Heat pumps (air to air, hydronic, and PTHP) – VSDs for Fans and Pumps • Pre-formatted workbooks – Estimates savings and incentives – Can be filled in by contactors, customers or SCL energy analyst, step by step instructions – Contains all documents required, download via web - and - Conserving Today. Sustaining Tomorrow. 10
  • 11. Custom Incentives (SCL and PSE) • Customized calculations for non- routine measures – Typically includes multiple systems – May require pre-monitoring to determine baseline • Incentive based on savings and measure life • Numerous applications – HVAC (controls, heat recovery, chillers and cooling towers) – Data centers (hot/cold isle) – Special environments (labs, industrial, etc) - and - Conserving Today. Sustaining Tomorrow. 11
  • 12. Potential Incentives – Sample Building Savings % of Savings Savings Savings Savings Total Use kBtu Measure kWh therms $ Utility Rebates Electric Gas Current Energy Use 34,300,000 6,701,836 114,333 Retro- Operational Savings 8.8% 3,018,400 commissioning 884,642 $53,079 System Upgrade Savings 26.4% 9,055,200 Lighting 444,533 $102,243 HVAC 1,333,598 29,882 $306,728 $149,411 Shell Improvement Savings 8.8% 3,018,400 Shell 592,710 10,172 $59,271 $50,860 Total Savings 44.0% 15,092,000 3,255,484 40,054 $521,320 $200,271 • Lighting – Prescriptive and standard incentives to upgrade lighting and lighting controls • HVAC Systems and Controls – Standard and/or custom incentives to upgrade equipment and controls • Shell Measures – Custom incentives for insulation, sealing, improved glazing, etc • Retro Commissioning – Enroll building in Retro commissioning program to capture operational savings - and - Conserving Today. Sustaining Tomorrow. 12
  • 13. Contact us to get Started • Please remember to contact us BEFORE you start a project so that we can discuss eligibility and help you with the rebate process • Call us: (206) 684-3800 Seattle City Light Energy Advisors • Email us: SCLEnergyAdvisor@seattle.gov • Visit us online: www.seattle.gov/light/conserve • Call us: (800) 562-1482 Puget Sound Energy Advisors • Visit us online: http://www.pse.com/savingsandenergycenter/ForBusinesses/Pages/Co mprehensive-Building-Tune-Up-Program.aspx - and - Conserving Today. Sustaining Tomorrow. 13
  • 14.
  • 15.
  • 16. Energy Services Contracting A different mindset Design-spec-build Integrated Delivery • Segmentation • Single point of accountability • 1st cost • Total Cost of Ownership • Task/problem driven • Holistic view and deep dive on • Diffused responsibility building systems • Fix the root cause, not the symptom • Guaranteed project outcomes • Cost • Savings • Take advantage of grants and incentives • CPW • P4P/Utility rebates • Low–cost financing
  • 17. Optimizing the Capital Stack Utility Rebates Cash 25% 10% Incentives 15% Debt 50%
  • 18. Energy Services Contracting Financing • ESCO finance • ESCO Brokerage • See handout for cash flows of model building at commercial rates • Property Assessed Clean Energy (Commercial PACE) • Senior lien property tax assessment to fund efficiency measures and/or renewable energy on private commercial property • Concept in infancy, slowly gaining traction • Not available in Washington State at this time • Qualified Energy Conservation Bonds • With enactment of King County’s Green Community Initiative, private property owners will be able to access QECBs for energy efficiency improvements • QECBs enable rates of ~ 2.0%-3.0% and tenors up to 24 years • See King County Green Community Initiative handout Contact: Rachel Brombaugh, rachelb@mckinstry.com, (206) 832-8132
  • 19. The Sustainable Energy Program: Qualified Energy Conservation Bonds and Beyond… Avi Jacobson Senior Sustainable Energy Coordinator Washington State Housing Finance Commission avi.jacobson@wshfc.org 206-254-5359
  • 20. The Sustainable Energy Program • Introduction • What are QECBs? How Do They Work? • QECB Aggregation Efforts • Green Communities Programs • Sustainable Energy Trust • Conclusion • Questions
  • 21. QECB Aggregation: WSHFC as State QECB Clearinghouse • Washington State: o $67.8M Allocated across WA o ~$32M Issued o In conjunction with WA Department of Commerce, have contacted all jurisdictions with remaining QECB Authority o $27M reallocated to WSHFC, $13.5M+ issued, more promised so far…
  • 22. What is a Green Community Program? Two Required Elements: • Program Purpose • Program goal must be to promote energy conservation, energy efficiency or environmental conservation initiatives related to energy consumption. • General Public Use or Broad Public Availability • Financing must involve either: • Property available for general public use, or • Loan or grant program broadly available to members of the general public.
  • 23. Financing Energy Efficiency Projects: Presented by: Dan Clarkson Energy Efficiency Finance Corp. dclarkson@eefinance.net 206-310-8733
  • 25. Offer to Building Owner • Energy Services Agreement (ESA) • No upfront capital costs; preserve capital for other purposes • Turnkey implementation by ESCO: engineering, equipment procurement, installation, commissioning, services, savings monitoring, savings guarantees • Grant/incentive funds used for subordinated debt financing, debt service reserve, & carbon reduction incentives • Project paid through operating cost savings; breakeven savings are guaranteed by ESCO • Payments on utility bill reduces risk for investor
  • 26. How it Works Seattle City Light Utility Incentives Energy Services Turnkey Agreement Energy Project Sub- Loan Capital ESCO Customer Solutions CPW Energy supply Incentive & Reserve Fund Retail Energy Lock Box Utility Steam & EE project payments via ESA Payments Escrow Services Agreement
  • 27. ECS Cashflow Model 1200000 1000000 Retrofit 22% Net Customer Savings 800000 Savings ESA Payments 600000 400000 200000 Utility Costs Cumulative Customer Savings 0 Year -3 Year -2 Year -1 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10