SlideShare uma empresa Scribd logo
1 de 54
ABA
       March 26, 2013



Design-Build Gone Wrong
    Lessons Learned



     J. Mark Dungan
  Delta Consulting Group
           1
Design-Build vs. Design-Bid-Build

   90.0%
                                                                 Design-Build Projected
              82.3%
                                                                      Trend in 2004
   80.0%
                                    72.0%

   70.0%                                                65.0%


   60.0%
                                                                         54.0%

   50.0%
                                                                                                                 50.0%
                                                                                         45.3%
   40.0%
                                                                                                                 40.5%
                                                                       36.0%
   30.0%
                                                      26.0%
   20.0%                         16.0%


   10.0%   12.4%                 12.0%
                                                      9.0%             10.0%             9.4%                9.5%
               5.3%
    0.0%
           1985                 1990                 1995              2000             2005                2010

           Traditional Design/Bid/Build                 Design/Build             Construction Management @Risk




                                          The Growth of D/B Method (DBIA 2004)

                                                             2
Design-Build vs. Design-Bid-Build




                        3
Design-Bid-Build vs. Design-Build

       Design Risk in a Design-Bid-Build Contract




                           4
Design-Bid-Build vs. Design-Build

         Design Risk in a Design-Build Contract




                           5
Comparison of Contractual Structure
Design-Bid-Build vs. Design-Build
             Design-Bid-Build


                                Bid Based on
                    Owner       Defined Scope

         CONTRACT           CONTRACT




    Design
  Professional
                              Contractor

     Construction                    SUB
     Documents                     CONTRACT




                                  Sub
                               Contractors

                                                6
Comparison of Contractual Structure
Design-Bid-Build vs. Design-Build
           Design-Bid-Build                                Design-Build
                                                                             Bid Based on
                                                                             Performance
                                                                              Criteria and
                                Bid Based on
                   Owner                                     Owner              General
                                Defined Scope
                                                                             Specifications

        CONTRACT      Construction
                            CONTRACT                                   CONTRACT
                      Documents




    Design                                               Contractor
  Professional
                              Contractor
                                                    Designer          Builder

                                    SUB               Construction        SUB
                                  CONTRACT            Documents         CONTRACT




                                 Sub                                    Sub
                              Contractors                            Contractors

                                                7
Design-Build


                                                                      Bid Based on
               • Provides Performance                                 Performance
                 Criteria                                              Criteria and
   Owner       • Provides General                                        General
                                                      Owner
                 Specifications
                                                                      Specifications

                                                                CONTRACT




                                                  Contractor
               • Provides Design Team
                                             Designer          Builder
               • Detailed Construction
  Contractor     Documents                     Construction        SUB
                                               Documents         CONTRACT
               • Management of
                 Construction




                                                                 Sub
                                                              Contractors

                                         8
Design Build Concept




                                     Design Builder                  Contractor
                     Owner and                           Owner
        Owner                          Prepares          Owner         Builds
                    Design Builder                      Reviews
      Specifies                        Detailed        Approves     According to
                    agree on Price                     Design for
    Project Needs                       Design          Design        Agreed
                     and Contract                     Compliance
                                      Documents                       Designs




                                           9
Design-Build vs. Design-Bid-Build




    Both Owners and the Design Builders
    Occasionally Misapply the Design
    Build Concept…

    We will present examples of each.



                        10
Typical Problem Areas

     Design              Scope                Construction




  DB designs        Unlike DBB, Scope is       DB may provide
  minimal to meet   sometimes vague, a         basic industry
  performance, Ow   change to the DB is a      standards while
  ner expected      design evolution to the    Owner expected
  higher standard   Owner                      greater standards


                              11
Example of Owner Misapplied Concept




                                                              Contractor
                  Owner and      Design Builder    Owner
    Owner                                          Owner        Builds
                Design Builder     Prepares       Burdens
  Specifies                                       Approves   According to
                Agree on Price      Design         Design
Project Needs                                      Design      Agreed
                 and Contract     Documents       Process
                                                               Designs




                                      12
Typical Problem Areas

   Design

                         Example:
                         Large Industrial Complex.




DB designs
minimal to meet
performance, Ow
ner expected
higher standard


                            13
DB’s Expected Drawing Development




      A1             AFC or         Rev 01
                     Rev 00

• Design          • Incorporates   • Incorporates
  development       Owners           any minor
  to point of       Comments to      comments or
  Owner review.     A1, Approved     from
                    for              unforeseen
                    Construction     issues




                         14
Evolution of Drawing 101

         101 – A1
         101 – A2
          101 - 00
         101 Rev. 1
         101 Rev. 2
         101 Rev. 3
         101 Rev. 4
       ………………….
        101 Rev. 12




             15
2007                                            2008                                            2009
J    F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J      J   A   S   O   N   D




                                         12/21/07

                                                                 Work Started in July 2007. The
                                                                 evolving design, due to owner
                                                                  changes, delayed the initial
                                                                   drawing submittals until
                                                                           December.




                                                                                                                                            E1
16
Evolution of Drawing 101

           Owner Rejects Drawing:

• Comment #1: Owner prefers the two plans be
  combined and produced at a larger scale.

• Comment #2: Owner directs preferred labeling
  of Walls




                       17
2007                                              2008                                            2009
J    F   M   A   M   J   J   A   S   O   N   D   J     F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J      J   A   S   O   N   D



                                                                         Contractor adds changes
                                                     2/24/08           complying with Owner changes.




             The two drawings were
              combined into one as
                   requested.




                                                                                                                                              E2
18
Evolution of Drawing 101

            Owner Rejects Drawing:

• Comment #3: Owner states that the combined
  drawing scale is now too small to describe the
  details desired.

• Comment #4: Owner comments that the line
  width used on the drawings was to narrow.




                        19
2007                                             2008                                              2009
J    F   M   A   M   J   J   A   S   O   N   D   J   F   M   A    M   J   J   A   S   O   N   D   J   F   M     A   M   J      J   A   S   O   N   D




                                                         4/4/08




                       Rev 00
          The Owner requires what was a
         single drawing now be broken out
            into six new detail drawings
                                                                                          102             103




                                                                                          104             105




                                                                                          106             107




                                                                                                                                               00
20
Drawing 101 Becomes 7 Separate Drawings


                          Effort x 1

                             101
                           Key Plan




  102    103        104                105   106   107




               Design Effort Increased x 6

                              21
2007                                              2008                                             2009
J    F   M   A   M   J   J   A   S   O   N   D   J   F   M    A   M    J   J    A   S   O   N   D   J   F   M   A   M   J      J   A   S   O   N   D



                                                                              Drawings Issued for
                                                             4/20/08          Construction on April 4th




                    Floor slab revised to
                 accommodate preferential
                   Owner decision to add
                  Storage and Bathrooms.
                    Change required on
                    3 separate drawings




                                                                                                                                               01
22
Evolution of Drawing 101

            Owner Rejects Drawing:

• Comment #5: Owner requires the removal of an
  a reference to another drawing, wants detail on
  each drawing.

• Comment #6: Owner requires that a note
  describing a typical expansion joint be
  specifically added at each joint location.



                         23
2007                                            2008                                            2009
J    F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J      J   A   S   O   N   D




                                                                                 10/18/08




                     Walls moved to increase
                              size.




                                                                                                                                            03
24
Evolution of Drawing 101

            Owner Rejects Drawing:

• Comment #7: Owner now wants 20 more
  expansion joints. Although all are the same, the
  Owner requires that each has to be specifically
  detailed.




                         25
2007                                            2008                                             2009
J    F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J   J   A   S    O   N   D   J   F   M   A   M   J      J   A   S   O   N   D




                                                                                     10/31/08




                 All 7 Drawings reissued
                 specifically detailing 20
                    Expansion Joints.




                                                                                                                                             04
26
Evolution of Drawing 101

            Owner Rejects Drawing:

• Comment #8: Owner increases size of
  equipment in the building, rejects drawing and
  directs that it be changed to accommodate the
  new equipment.




                        27
101



           102   103   104   105   106   107   108   Count of
                                                     Drawings

11/4/07    A1    A1    A1    A1    A1    A1    A1       7

11/18/07   00    00    00    00    00    00    00       7


12/12/07         01    01    01    01    01    01       6


2/7/08     01    02    02    02    02    02    02       7

2/14/08          03                03                   2

3/21/08          04                04                   2

10/10/08   02    05    02    03    05    03    03       7


5/22/09                                        04       1

5/29/09    03                04                         2

8/19/09          06                06                   2



                             28
Expected Drawing Development




      A1             AFC or         Rev 01
                     Rev 00

• Design          • Incorporates   • Incorporates
  development       Owners           any minor
  to point of       Comments to      comments or
  Owner review.     A1, Approved     from
                    for              unforeseen
                    Construction     issues




                         29
Impacts Caused by Owner’s Design Process Involvement




           A1                AFC                     Rev
                                                      1
A2

                                     Rev 2   Rev3      Rev4
      A3


           A4                        Rev 5   Rev 6            Rev12




           >10,000 Additional Drawings
                              30
Impacts of Owner Misapplied Concept
          Over 12,000 Drawing                      Over 30,000 Individual
           Review documents                         Owner Comments
          Issued by the Owner



Review    Review   Review   Review   Review
 Sheet     Sheet    Sheet    Sheet    Sheet



                                                        Anticipated
Review    Review   Review   Review   Review
 Sheet     Sheet    Sheet    Sheet    Sheet



                                                          Scope
Review    Review   Review   Review   Review
 Sheet     Sheet    Sheet    Sheet    Sheet



                                                        Preferential
Review    Review   Review   Review   Review
 Sheet     Sheet    Sheet    Sheet    Sheet




                                              31
Impacts of Owner Misapplied Concept

• The Owner’s design involvement caused the
  Contractor:

  – Unplanned additional resources needed for
    management, development, and production of
    drawings

  – More time required to progress job

  – Contractor’s costs to complete the project increased
    above what was bid




                           32
Example of Contractor
Misapplied Concept
                             Construction



 Example:
 Power Station



                              DB may provide
                              basic industry
                              standards while
                              Owner expected
                              greater standards


                        33
Example of Contractor Misapplied Concept




                                                                  Contractor
     Owner        Owner and       Design Builder      Owner
                                                                  Does Not
                                                                    Builds
   Specifies     Design Builder     Prepares         Reviews
                                                                 According to
                                                                  Work With
 Project Needs   agree on Price      Design         Design for
                                                                   Agreed
                                                                    Owner
   and Price      and Contract     Documents       Compliance
                                                                 Specification
                                                                   Designs




                                       34
Comparison of Contractual Structure
                Design-Bid-Build vs. Design-Build

                 DBB                                DB

                 Owner                            Owner

      CONTRACT           CONTRACT                          CONTRACT




  Design
Professional
                           Contractor                          Contractor

                                  SUB             SUB               SUB
                                CONTRACT        CONTRACT          CONTRACT




                               Sub                Design          Sub
                            Contractors         Professional   Contractors


                                           35
Design Build – Liabilities

                                     DB
• Design Errors and
  Omissions are
                                   Owner
  Under Contractor
  Liability
                                            CONTRACT



• Subcontractor
  Time and Money

                            $              $
  Claims are charged
                                                Contractor
  against Contractor
  to correct design
                                   SUB               SUB
  issues                         CONTRACT          CONTRACT




• Possible LD’s to
  Owner
                                   Design          Sub
                                 Professional   Contractors


                       36
Example of Contractor Misapplied Concept
             Completion Work Status
                  At Termination:


     • Plant was nearly operational
     • Over half of systems turned over
     • ~500 well defined punch list items




                         37
Opposing Views of Project

 Contractor’s Story              Owner’s Story

• Project will Perform        • Project Not Built as
  as Contracted                 Contracted

• Essentially                 • Auxiliary Systems not
  Operational                   Built Per Design

• Owner Being                 • Contractor Failed to
  Unreasonable                  Perform




                         38
Example of Contractor
 Misapplied Concept

Upon Investigating the Work-in-Place,

  – Design did not Conform to Owner’s
    Criteria,

  – Work in Place did not Conform to Detail
    Construction Design



                         39
Design Build – Liabilities

                                      DB
Design Professional’s
Contract was essentially a          Owner
Typical Subcontract
Agreement.                                   CONTRACT




When General Contractor
was Terminated, Design
Professional took the
                                             $  Contractor

position they had no                SUB               SUB
                                  CONTRACT          CONTRACT
further contractual
obligation.

                                    Design          Sub
                                  Professional   Contractors


                             40
Example of Contractor Misapplied Concept
           EXAMPLE of DESIGN ISSUES


                 Unit Drain System



                 Punchlist Item:


“Drain funnels are spraying fuel oil on the ground”




                         41
EXAMPLE of DESIGN ISSUES


  Unit Drain System
  Problem Encountered:
    Fuel Oil Is Spilling



                                 Owner Equipment




                           • Unexpected Result
                           • Environmental Issue




            42
EXAMPLE of DESIGN ISSUES


               What Was SPECIFIED:
 Funnel Connection was Specified by Manufacturer
         of this Owner Supplied Equipment
Vendor Required Funnel
     Connection                             Owner Equipment




          1”




         2”



                            43
EXAMPLE of DESIGN ISSUES




    Conflict in Specifications and Design Drawings.


•     Design-Build contractor Changed the Owner’s
      Requirement for a funnel connection without
      the Owner’s Review of Approval.




                           44
EXAMPLE of DESIGN ISSUES


                 What was DESIGNED:
Contractor’s Design Drawings showed the 1” pipe being
 connected to a 1” underground pipe by a Flange Joint


                                           Owner Equipment



         1”




         1”




                           45
EXAMPLE of DESIGN ISSUES




    Conflict in Engineering Design Drawings and
                  Actual Construction.


•   Owner Refused to Accept Flanged
    Connection, they were supposed to have a
    Funnel Connection.
•   Design-Build Contractor, Cut Off the Flange
    and Welded on a Funnel Connection.




                         46
EXAMPLE of DESIGN ISSUES


                   Field Change:
Contractor makes field change for a funnel connection
      without the Owner’s Review or Approval


                                          Owner Equipment




                          47
EXAMPLE of DESIGN ISSUES


       Contractor’s Resolution:
A 1” pipe with funnel connection runs
        underground to a tank

                                    Owner Equipment

   1”




   1”




                    48
EXAMPLE of DESIGN ISSUES


          New Design




                                Owner Equipment


1”




2”




                49
EXAMPLE of DESIGN CORRECTIONS


                 Steps to Resolve
      Remove Work-in-Place and Install New Work



                                                Owner Equipment
• Stop System
• Hand excavate and
  Remove 1” Pipe
• Install 2” Pipe and
  Appropriate Funnel
• Backfill




                             50
Example of Contractor Misapplied Concept

• Unapproved and non-conforming design had to be
  corrected by the replacement engineer


• Significant portions of work-in-place had to be
  removed and re-constructed in accordance with
  corrected design


• As more systems were inspected and design was
  corrected, the Punch list grew to over 2,000 items




                          51
Lessons Learned

       Design                Scope              Construction




Owner strive to         Define Scope matrices    Define Standards
specify its desires     that specifically        pre-contract,
pre-contract and        identify items and       evaluate
then limit review to    responsible party        experience of
compliance                                       Design Builder


                                 52
Thank You for this Opportunity



          The End




             53
Delta Consulting Group is an international consulting firm of multi-
disciplined professionals in engineering, accounting, construction,
project management and litigation support. Our key services
include: Dispute Avoidance/Resolution, Expert Witness Testimony,
Project Management, Financial Advisory, as well as Troubled
Project and Surety Consulting.


     Delta Consulting Group, Inc.
     4330 Prince William Pkwy., Suite 301
     Woodbridge, VA 22192
     703.580.8801 (p) | 703.580.8802 (f)
     www.DELTA-CGI.com

     J. Mark Dungan: Co-Founding Partner
     Email: mdungan@delta-cgi.com




                           54

Mais conteúdo relacionado

Mais de Roland_Nikles

Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27Roland_Nikles
 
Risks & Advantages of P3 Projects by Sid Scott, Hill International
Risks & Advantages of P3 Projects by Sid Scott, Hill InternationalRisks & Advantages of P3 Projects by Sid Scott, Hill International
Risks & Advantages of P3 Projects by Sid Scott, Hill InternationalRoland_Nikles
 
Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Roland_Nikles
 
Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Roland_Nikles
 
Ashrae denver business project development and ipd_ springer
Ashrae denver business project development and ipd_ springerAshrae denver business project development and ipd_ springer
Ashrae denver business project development and ipd_ springerRoland_Nikles
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Aba february 2013_presentation
Aba february 2013_presentationAba february 2013_presentation
Aba february 2013_presentationRoland_Nikles
 
Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Roland_Nikles
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Roland_Nikles
 

Mais de Roland_Nikles (9)

Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27
 
Risks & Advantages of P3 Projects by Sid Scott, Hill International
Risks & Advantages of P3 Projects by Sid Scott, Hill InternationalRisks & Advantages of P3 Projects by Sid Scott, Hill International
Risks & Advantages of P3 Projects by Sid Scott, Hill International
 
Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17
 
Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...
 
Ashrae denver business project development and ipd_ springer
Ashrae denver business project development and ipd_ springerAshrae denver business project development and ipd_ springer
Ashrae denver business project development and ipd_ springer
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Aba february 2013_presentation
Aba february 2013_presentationAba february 2013_presentation
Aba february 2013_presentation
 
Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 

Division 4 presentation_dugan_design_build_claims_2013_03_26

  • 1. ABA March 26, 2013 Design-Build Gone Wrong Lessons Learned J. Mark Dungan Delta Consulting Group 1
  • 2. Design-Build vs. Design-Bid-Build 90.0% Design-Build Projected 82.3% Trend in 2004 80.0% 72.0% 70.0% 65.0% 60.0% 54.0% 50.0% 50.0% 45.3% 40.0% 40.5% 36.0% 30.0% 26.0% 20.0% 16.0% 10.0% 12.4% 12.0% 9.0% 10.0% 9.4% 9.5% 5.3% 0.0% 1985 1990 1995 2000 2005 2010 Traditional Design/Bid/Build Design/Build Construction Management @Risk The Growth of D/B Method (DBIA 2004) 2
  • 4. Design-Bid-Build vs. Design-Build Design Risk in a Design-Bid-Build Contract 4
  • 5. Design-Bid-Build vs. Design-Build Design Risk in a Design-Build Contract 5
  • 6. Comparison of Contractual Structure Design-Bid-Build vs. Design-Build Design-Bid-Build Bid Based on Owner Defined Scope CONTRACT CONTRACT Design Professional Contractor Construction SUB Documents CONTRACT Sub Contractors 6
  • 7. Comparison of Contractual Structure Design-Bid-Build vs. Design-Build Design-Bid-Build Design-Build Bid Based on Performance Criteria and Bid Based on Owner Owner General Defined Scope Specifications CONTRACT Construction CONTRACT CONTRACT Documents Design Contractor Professional Contractor Designer Builder SUB Construction SUB CONTRACT Documents CONTRACT Sub Sub Contractors Contractors 7
  • 8. Design-Build Bid Based on • Provides Performance Performance Criteria Criteria and Owner • Provides General General Owner Specifications Specifications CONTRACT Contractor • Provides Design Team Designer Builder • Detailed Construction Contractor Documents Construction SUB Documents CONTRACT • Management of Construction Sub Contractors 8
  • 9. Design Build Concept Design Builder Contractor Owner and Owner Owner Prepares Owner Builds Design Builder Reviews Specifies Detailed Approves According to agree on Price Design for Project Needs Design Design Agreed and Contract Compliance Documents Designs 9
  • 10. Design-Build vs. Design-Bid-Build Both Owners and the Design Builders Occasionally Misapply the Design Build Concept… We will present examples of each. 10
  • 11. Typical Problem Areas Design Scope Construction DB designs Unlike DBB, Scope is DB may provide minimal to meet sometimes vague, a basic industry performance, Ow change to the DB is a standards while ner expected design evolution to the Owner expected higher standard Owner greater standards 11
  • 12. Example of Owner Misapplied Concept Contractor Owner and Design Builder Owner Owner Owner Builds Design Builder Prepares Burdens Specifies Approves According to Agree on Price Design Design Project Needs Design Agreed and Contract Documents Process Designs 12
  • 13. Typical Problem Areas Design Example: Large Industrial Complex. DB designs minimal to meet performance, Ow ner expected higher standard 13
  • 14. DB’s Expected Drawing Development A1 AFC or Rev 01 Rev 00 • Design • Incorporates • Incorporates development Owners any minor to point of Comments to comments or Owner review. A1, Approved from for unforeseen Construction issues 14
  • 15. Evolution of Drawing 101 101 – A1 101 – A2 101 - 00 101 Rev. 1 101 Rev. 2 101 Rev. 3 101 Rev. 4 …………………. 101 Rev. 12 15
  • 16. 2007 2008 2009 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 12/21/07 Work Started in July 2007. The evolving design, due to owner changes, delayed the initial drawing submittals until December. E1 16
  • 17. Evolution of Drawing 101 Owner Rejects Drawing: • Comment #1: Owner prefers the two plans be combined and produced at a larger scale. • Comment #2: Owner directs preferred labeling of Walls 17
  • 18. 2007 2008 2009 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Contractor adds changes 2/24/08 complying with Owner changes. The two drawings were combined into one as requested. E2 18
  • 19. Evolution of Drawing 101 Owner Rejects Drawing: • Comment #3: Owner states that the combined drawing scale is now too small to describe the details desired. • Comment #4: Owner comments that the line width used on the drawings was to narrow. 19
  • 20. 2007 2008 2009 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 4/4/08 Rev 00 The Owner requires what was a single drawing now be broken out into six new detail drawings 102 103 104 105 106 107 00 20
  • 21. Drawing 101 Becomes 7 Separate Drawings Effort x 1 101 Key Plan 102 103 104 105 106 107 Design Effort Increased x 6 21
  • 22. 2007 2008 2009 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Drawings Issued for 4/20/08 Construction on April 4th Floor slab revised to accommodate preferential Owner decision to add Storage and Bathrooms. Change required on 3 separate drawings 01 22
  • 23. Evolution of Drawing 101 Owner Rejects Drawing: • Comment #5: Owner requires the removal of an a reference to another drawing, wants detail on each drawing. • Comment #6: Owner requires that a note describing a typical expansion joint be specifically added at each joint location. 23
  • 24. 2007 2008 2009 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 10/18/08 Walls moved to increase size. 03 24
  • 25. Evolution of Drawing 101 Owner Rejects Drawing: • Comment #7: Owner now wants 20 more expansion joints. Although all are the same, the Owner requires that each has to be specifically detailed. 25
  • 26. 2007 2008 2009 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 10/31/08 All 7 Drawings reissued specifically detailing 20 Expansion Joints. 04 26
  • 27. Evolution of Drawing 101 Owner Rejects Drawing: • Comment #8: Owner increases size of equipment in the building, rejects drawing and directs that it be changed to accommodate the new equipment. 27
  • 28. 101 102 103 104 105 106 107 108 Count of Drawings 11/4/07 A1 A1 A1 A1 A1 A1 A1 7 11/18/07 00 00 00 00 00 00 00 7 12/12/07 01 01 01 01 01 01 6 2/7/08 01 02 02 02 02 02 02 7 2/14/08 03 03 2 3/21/08 04 04 2 10/10/08 02 05 02 03 05 03 03 7 5/22/09 04 1 5/29/09 03 04 2 8/19/09 06 06 2 28
  • 29. Expected Drawing Development A1 AFC or Rev 01 Rev 00 • Design • Incorporates • Incorporates development Owners any minor to point of Comments to comments or Owner review. A1, Approved from for unforeseen Construction issues 29
  • 30. Impacts Caused by Owner’s Design Process Involvement A1 AFC Rev 1 A2 Rev 2 Rev3 Rev4 A3 A4 Rev 5 Rev 6 Rev12 >10,000 Additional Drawings 30
  • 31. Impacts of Owner Misapplied Concept Over 12,000 Drawing Over 30,000 Individual Review documents Owner Comments Issued by the Owner Review Review Review Review Review Sheet Sheet Sheet Sheet Sheet Anticipated Review Review Review Review Review Sheet Sheet Sheet Sheet Sheet Scope Review Review Review Review Review Sheet Sheet Sheet Sheet Sheet Preferential Review Review Review Review Review Sheet Sheet Sheet Sheet Sheet 31
  • 32. Impacts of Owner Misapplied Concept • The Owner’s design involvement caused the Contractor: – Unplanned additional resources needed for management, development, and production of drawings – More time required to progress job – Contractor’s costs to complete the project increased above what was bid 32
  • 33. Example of Contractor Misapplied Concept Construction Example: Power Station DB may provide basic industry standards while Owner expected greater standards 33
  • 34. Example of Contractor Misapplied Concept Contractor Owner Owner and Design Builder Owner Does Not Builds Specifies Design Builder Prepares Reviews According to Work With Project Needs agree on Price Design Design for Agreed Owner and Price and Contract Documents Compliance Specification Designs 34
  • 35. Comparison of Contractual Structure Design-Bid-Build vs. Design-Build DBB DB Owner Owner CONTRACT CONTRACT CONTRACT Design Professional Contractor Contractor SUB SUB SUB CONTRACT CONTRACT CONTRACT Sub Design Sub Contractors Professional Contractors 35
  • 36. Design Build – Liabilities DB • Design Errors and Omissions are Owner Under Contractor Liability CONTRACT • Subcontractor Time and Money $ $ Claims are charged Contractor against Contractor to correct design SUB SUB issues CONTRACT CONTRACT • Possible LD’s to Owner Design Sub Professional Contractors 36
  • 37. Example of Contractor Misapplied Concept Completion Work Status At Termination: • Plant was nearly operational • Over half of systems turned over • ~500 well defined punch list items 37
  • 38. Opposing Views of Project Contractor’s Story Owner’s Story • Project will Perform • Project Not Built as as Contracted Contracted • Essentially • Auxiliary Systems not Operational Built Per Design • Owner Being • Contractor Failed to Unreasonable Perform 38
  • 39. Example of Contractor Misapplied Concept Upon Investigating the Work-in-Place, – Design did not Conform to Owner’s Criteria, – Work in Place did not Conform to Detail Construction Design 39
  • 40. Design Build – Liabilities DB Design Professional’s Contract was essentially a Owner Typical Subcontract Agreement. CONTRACT When General Contractor was Terminated, Design Professional took the $ Contractor position they had no SUB SUB CONTRACT CONTRACT further contractual obligation. Design Sub Professional Contractors 40
  • 41. Example of Contractor Misapplied Concept EXAMPLE of DESIGN ISSUES Unit Drain System Punchlist Item: “Drain funnels are spraying fuel oil on the ground” 41
  • 42. EXAMPLE of DESIGN ISSUES Unit Drain System Problem Encountered: Fuel Oil Is Spilling Owner Equipment • Unexpected Result • Environmental Issue 42
  • 43. EXAMPLE of DESIGN ISSUES What Was SPECIFIED: Funnel Connection was Specified by Manufacturer of this Owner Supplied Equipment Vendor Required Funnel Connection Owner Equipment 1” 2” 43
  • 44. EXAMPLE of DESIGN ISSUES Conflict in Specifications and Design Drawings. • Design-Build contractor Changed the Owner’s Requirement for a funnel connection without the Owner’s Review of Approval. 44
  • 45. EXAMPLE of DESIGN ISSUES What was DESIGNED: Contractor’s Design Drawings showed the 1” pipe being connected to a 1” underground pipe by a Flange Joint Owner Equipment 1” 1” 45
  • 46. EXAMPLE of DESIGN ISSUES Conflict in Engineering Design Drawings and Actual Construction. • Owner Refused to Accept Flanged Connection, they were supposed to have a Funnel Connection. • Design-Build Contractor, Cut Off the Flange and Welded on a Funnel Connection. 46
  • 47. EXAMPLE of DESIGN ISSUES Field Change: Contractor makes field change for a funnel connection without the Owner’s Review or Approval Owner Equipment 47
  • 48. EXAMPLE of DESIGN ISSUES Contractor’s Resolution: A 1” pipe with funnel connection runs underground to a tank Owner Equipment 1” 1” 48
  • 49. EXAMPLE of DESIGN ISSUES New Design Owner Equipment 1” 2” 49
  • 50. EXAMPLE of DESIGN CORRECTIONS Steps to Resolve Remove Work-in-Place and Install New Work Owner Equipment • Stop System • Hand excavate and Remove 1” Pipe • Install 2” Pipe and Appropriate Funnel • Backfill 50
  • 51. Example of Contractor Misapplied Concept • Unapproved and non-conforming design had to be corrected by the replacement engineer • Significant portions of work-in-place had to be removed and re-constructed in accordance with corrected design • As more systems were inspected and design was corrected, the Punch list grew to over 2,000 items 51
  • 52. Lessons Learned Design Scope Construction Owner strive to Define Scope matrices Define Standards specify its desires that specifically pre-contract, pre-contract and identify items and evaluate then limit review to responsible party experience of compliance Design Builder 52
  • 53. Thank You for this Opportunity The End 53
  • 54. Delta Consulting Group is an international consulting firm of multi- disciplined professionals in engineering, accounting, construction, project management and litigation support. Our key services include: Dispute Avoidance/Resolution, Expert Witness Testimony, Project Management, Financial Advisory, as well as Troubled Project and Surety Consulting. Delta Consulting Group, Inc. 4330 Prince William Pkwy., Suite 301 Woodbridge, VA 22192 703.580.8801 (p) | 703.580.8802 (f) www.DELTA-CGI.com J. Mark Dungan: Co-Founding Partner Email: mdungan@delta-cgi.com 54