2. Hueco Mountain Wind Ranch
2 Vestas wind turbines
Location: east of Horizon, TX
On-Line: April 2001
Capacity:
– 1.32 MW
– 660 kW each turbine
– 438 homes/year
2
3. Rio Grande Solar Facilities
• Crystalline Photovoltaic Systems
• Mounting: Fixed-Mounted
• Location: Rio Grande Power Stations
• On-Line: December 2009
• Capacity:
• 64 kWAC
• 139,000 kWh/year per system
• 21 homes/year
3
4. Newman Solar Facilities
• Crystalline Photovoltaic Systems
• Mounting: Fixed Mounted
• Location: Newman Power Stations
• On-Line: December 2009
• Capacity:
• 64 kWAC
• 139,000 kWh/year
• 21 homes/year
4
7. EPCC Solar Facility
Poly-Crystalline Photovoltaic Systems
Mounting: Fixed-Mounted
Location: EPCC Valle Verde Campus
On-Line: January 2012
Capacity:
– 14 kWAC
– 31,000 kWh/year
– 5 homes/year
7
8. Camino Real Landfill Project
Methane harvested from landfill gas
Located in Camino Real Landfill, Sunland
Park, NM
Owned by Four Peaks Energy, Inc
Began operating in 2008
Capacity:
– 1-3 MW
– 1,190 homes/year
8
9. Hatch Solar PPA
• Concentrated Photovoltaic System
• Mounting: Dual-Axis Tracking
• Location: Hatch, NM
• Owner: Nextera Energy
• On-line: July 2011
• Capacity:
• 5 MWAC
• 1,400 Homes/year
9
10. Roadrunner Solar PPA
Thin-Film System
Mounting: Single-Axis Tracking
Location: Santa Teresa, NM
Owner: NRG Energy
On-line: August 2011
Capacity:
• 20 MWAC
• 5,600homes/year
10
11. SunEdison Las Cruces Solar PPA
Solar Photovoltaic System
Mounting: Single-Axis Tracking
Location: Las Cruces, New Mexico
Owner: SunEdison
On-line: May 2012
Capacity:
• 12 MWAC
• 3,300 Homes/year Photo Courtesy of SunEdison
11
12. SunEdison Chaparral Solar PPA
Solar Photovoltaic System
Mounting: Single-Axis Tracking
Location: Chaparral, New Mexico
Owner: SunEdison
On-line: June 2012
Capacity:
• 10 MWAC
• 2,800 Homes/year
Photo Courtesy of SunEdison
12