1. ON GRID/GRID TIED SOLAR PV SYSTEM FOR
CAPTIVE CONSUMPTION: ADVANTAGES,
LIMITATIONS AND POSSIBILITIES
AT
NATIONAL TRAINING CENTRE FOR SOLAR TECHNOLOGY,
BANGALORE, 29th Jan 2013 from 3 – 5 pm.
Organized By
MNRE & KPCL – With TRA INTERNATIONAL, DELHI
Prabhuraj Harakangi BE (E&E), M.Tech (Energy Systems)
Sr. Design Engineer – Solar PV Systems
Ph No: +91 8147814995, e-mail: prabhu@arraytechindia.com
ArrayTech Technologies Pvt. Ltd, Bengaluru
2. TYPES OF Solar PV SYSTEMS :
Stand alone system
Hybrid /Off Grid System
Grid Sharing System
On Grid / Grid Tied System:
1) Net Metering
2) Double metering
3) Captive Consumption
ArrayTech Technologies Pvt. Ltd, Bengaluru
3. STAND ALONE SYSTEM
MPPT Charge Controller
BATTERY BANK
Soura Bandhu
Solar Frontier CIS Thin
Film Solar Module
DC LOADS
ArrayTech Technologies Pvt. Ltd, Bengaluru
4. Stand Alone System: Direct application , which can be used to charge
the battery and use it for the DC loads
Low Conversion Losses since LOAD is DC
Charge controller (MPPT or PWM) comes with Dusk to Dawn also
which can be used fir Street Lights
Stand Alone Inverters can be used to run AC Loads
Limitations:
Load Dependent, Conventional System for small Loads
Large Battery Bank required
ArrayTech Technologies Pvt. Ltd, Bengaluru
5. HYBRID/OFF GRID SYSTEM
Solar Frontier CIS Thin
Film Solar Module
BATTERY BANK
AC
MAINS
AC LOADS
ArrayTech Technologies Pvt. Ltd, Bengaluru
6. Prime Source: Battery
Battery Charging Sources: Solar and Mains
Load Sources: Cut Off Type
Either Mains – OR – Solar + Battery (Floating or Non Floating)
Both Savings and Back Up
Limitations:
Load Dependent and only for Non – Inductive Loads
Repeated Battery Cycles
Losses in Electronics and Battery
NOTE: Proper Sizing is Important
ArrayTech Technologies Pvt. Ltd, Bengaluru
7. GRID SHARING SYSTEM
SOLAR GRID SHARING PCU
Solar
Inverter
Converter and
AC LOADS
Charger
MPPT Charge
Controller
Solar PV Plant BATTERY BANK
ArrayTech Technologies Pvt. Ltd, Bengaluru
8. Prime Source: Battery
Battery Charging Sources:
Solar and Mains DC (Converter)
Load Sources:
3 DC Sources – Solar PV, Mains, Battery
Either Mains + Solar OR Battery + Solar
Work with High Inductive Loads
Better Savings and Back Up with Less Battery Cycles
Limitations:
Load Dependent
Higher Cost
ArrayTech Technologies Pvt. Ltd, Bengaluru
9. On Grid / Grid Tied System:
The solar modules generate DC electricity. The DC power goes
through a Solar ON Grid Inverter
Solar Grid Tied Inverter: performs the conversion of the
variable DC output into a clean sinusoidal AC power
Inverter output connected to Bus Bar (Distribution Panel)
The Solar Current will be given lead angle in synchronization
process and it will be forcefully injected into the bus bar
Depending on the type of ON Grid System the revenue or profits
will be gained
ArrayTech Technologies Pvt. Ltd, Bengaluru
10. SYNCHRONISATION:
The inverter measure the grid (voltage, frequency, phasing) and use
this information to synchronize the internal regulation. It means the
inverter start up with an open grid contactor and with a grid
independent frequency. Then the controller change the internal
frequency, voltage and phasing so long as this is absolute identical to
the given values from the grid. Now the electronic will close a soft
start contactor for pre magnetise the internal transformer. Few parts
of a second later the main grid contactor will close and the inverter
will feed in. If the grid values will be changed during the inverter
feeds in grid monitoring will detect it and the controller will adjust
the internal regulation so that inverter is whole time synchronal to
the grid
ArrayTech Technologies Pvt. Ltd, Bengaluru
11. NET METERING SYSTEM BUS BAR
UPS
NM
AC LOADS
Grid Supply
Solar PV Plant Grid Tied Inverter
ArrayTech Technologies Pvt. Ltd, Bengaluru
12. DOUBLE METERING SYSTEM BUS BAR
UPS
EM
AC LOADS
Grid Supply
SM
Grid Tied Inevrter
Solar PV Plant
ArrayTech Technologies Pvt. Ltd, Bengaluru
13. Protections :
•DC Side modules will be given with SPD, DC Dis-connector Switch which
will protect the Solar System
•For all kinds of faults the Solar Inverter will react first and ISOLATE itself
from the system in Microseconds of time
Advantages :
•Simple and Safe systems which gives Direct Savings and Revenue
•Load Independent system
•Most Efficient System, Very Least Losses & Maintenance Free System
•25 years of Guaranteed Generation with 6-7 Years Payback Period
•1kW of Solar Power Plant Generates 5.5Units of Electricity per Day
•Accelerated Depreciation on the Investment
ArrayTech Technologies Pvt. Ltd, Bengaluru
14. Limitations:
•No Back up will be given from the system, since solar power directly
utilized
•Stable Grid is a must
•NO Policy from Govt
•Infrastructure problem
ArrayTech Technologies Pvt. Ltd, Bengaluru
15. CAPTIVE CONSUMPTION SYSTEM
BUS BAR
Grid
AMFD
UPS
AC LOADS
DG
Grid Tied Inevrter
Solar PV Plant
ArrayTech Technologies Pvt. Ltd, Bengaluru
16. CAPTIVE CONSUMPTION:
Working Principle: SYNCHRONISATION
Feed: Least Resistive Path
Profit: Direct Savings on Electricity Bills
Precautions:
Detailed Load Analysis
DG Rating and Health of DG
Circuit Breaker: To avoid Reverse Flow
ArrayTech Technologies Pvt. Ltd, Bengaluru
17. CASE STUDY:
Civil Survey:
Location: ……………., State: ……….. And Country:…………
Latitude.... o and Longitude….. o
Shadow free Area Available: …………….. Sq meters
North to South : ………Meters East to West : ……………….. Meters
Type of Roof : Flat Roof or Tilt Roof
If Flat Roof: RCC or any other
If Tilted : Metal Sheet, Asbustus Sheet, RCC roof or any other
Tilt Face south to north or east to west and Tilt Angle…..o,
Obstacles: Cement Columns, AC Fan Units , Chiller Units
and other if any - Height of Obstacle: …….. Meter
Attachments: Google Map, Layout of Site or Photo of Site
ArrayTech Technologies Pvt. Ltd, Bengaluru
18. Electrical Survey:
Sources of Energy :
Electricity Board:Contract Demand ……. kVA, Peak Load ………..kVA
Diesel Generator: Rating …….. kVA
Make …………… and Life: ……… Years
Other Sources: Please specify with details
Load and Consumption Details :
Load type : 1 Phase or 3 Phase
Type of Loads : Mention Type of Machines and Equipments used
Operating Hours : Hours and …… am to…..pm
(if Load works in 2 or 3 Shifts)
Weekly Holidays :Specify (Only Sunday or Saturday or Half Saturday too)
Consumption : ………….Units (Average of last six months)
ArrayTech Technologies Pvt. Ltd, Bengaluru
22. Capacity:104 kW Investment : Rs 12480000.00 System Cost: 120Rs/Watt
Units with Annual 5% of MONEY SAVED Depric 30 % of Tax AMC 5% of Total Money
Degradation of 0.5% Escalation iation Savings saved Saved in Each PRINCIPLE
After 10 Years in Tariff money Year PAY BACK
1 Yr 176512.00 7.00 1235584.00 80% 2995200.00 0.00 4230784.00 -8249216.00
2 Yr 175629.44 7.35 1290876.38 5% 37440.00 0.00 1328316.38 -6920899.62
3 Yr 174751.29 7.72 1348643.10 5% 37440.00 0.00 1386083.10 -5534816.51
4 Yr 173877.54 8.10 1408994.88 5% 37440.00 0.00 1446434.88 -4088381.63
5 Yr 173008.15 8.51 1472047.40 5% 37440.00 0.00 1509487.40 -2578894.23
6 Yr 172143.11 8.93 1537921.52 - 0.00 76896.08 1498465.45 -1080428.78
7 Yr 171282.39 9.38 1606743.51 - 0.00 80337.18 1526406.34 445977.55
8 Yr 170425.98 9.85 1678645.28 - 0.00 83932.26 1594713.02 2040690.57
- - - - - - - - -
- - - - - - - - -
- - - - - - - - -
21 Yr 159674.61 18.57 2965649.84 - 0.00 148282.49 2817367.35 30585229.40
22 Yr 158876.23 19.50 3098362.67 - 0.00 154918.13 2943444.54 33528673.94
23 Yr 158081.85 20.48 3237014.40 - 0.00 161850.72 3075163.68 36603837.63
24 Yr 157291.44 21.50 3381870.80 - 0.00 169093.54 3212777.26 39816614.88
25 Yr 156504.98 22.58 3533209.52 - 0.00 176660.48 3356549.04 43173163.92
ArrayTech Technologies Pvt. Ltd, Bengaluru
23. ON GRID SYSTEM WITH FUEL EFFICIENT
Efficiency DIESEL GENERATORS:
Efficiency
Full Load Half Load NO Load Full Load Half Load NO Load
LOAD Applied LOAD Applied
Mechanically Electronically
Controlled Governor Controlled Governor
ArrayTech Technologies Pvt. Ltd, Bengaluru
24. ON GRID SYSTEM with FUEL EFFICIENT DG BUS BAR
UPS
AC LOADS
Solar PV Plant
Grid Tied Inevrter
ArrayTech Technologies Pvt. Ltd, Bengaluru
25. Area Of Application:
HT Loads Like Factories, Hospitals, Offices, School,
Colleges, Hostels, commercial complexes
FINANCIAL POSSIBILITIES:
Third Party Investment with Accelerated Depreciation
Finding a buyer at Normal Tariff with REC
REC Constraints
ArrayTech Technologies Pvt. Ltd, Bengaluru