3. > Up to 10 buildings
> Up to 500,000 square feet of space
> Circa 200 canal side residential units
> c.£120m development value
> Enhanced gateway
> CW&C delivered public realm and relocated car park
Masterplan summary
11. > Up to seven storey, Grade A office building
> 70,000 square feet
> Minimum BREEAM Excellent
> Potential ground floor active use
> £16.5m value
> £19.50 - £21.00 psf rent (including parking)
> Evergreen and ERDF funding
Delivering the development – Phase 1
14. > Complete new station car park – May 2014
> Commence phase 1 building – June 2014
> Commence public realm works – August 2014
> Complete phase 1 building and public realm – September 2015
> Commence residential development – August 2015
Programme – Phase 1