PROFESSIONAL EXPERIENCE:
Sep.2013 – Present Nexen Golden Eagle HUC Project.
Position - Lead Planning Engineer
Employed by Nexen Petroleum, UK. Located in Aberdeen, UK. Work covered the
planning and monitoring of the Golden Eagle platform HUC project.
The scope of work covered the monitoring of the contractors construction schedule and
the planning and monitoring of the commissioning and start up scopes of work.
Initially onshore the role transferred to offshore on a two week about rota following the
installation of the main platform.
Primavera P6 was the primary planning system used.
Nov.2010 – Aug.2013 Nexen Buzzard North Sea Oil & Gas Installation Major Offshore Projects
Position - Lead Planning Engineer
Employed by Nexen Petroleum, UK. Located in Aberdeen, UK. Work covered the
planning and monitoring of major brownfield modification work required to maintain and
enhance production. The major projects included an additional 60 bed accommodation,
new sand handling plant and upgraded water injection facilities.
The work covered the full life cycle of the projects through the select, define, sanction
and execution phases of the detailed engineering, offshore construction and
commissioning.
The work scopes covered both work carried out during live production and shutdown
situations.
Primavera P6 was the primary planning system used.
Jan.2008 – Oct.2010 Nexen Buzzard North Sea Oil & Gas Installation Enhancement Project.
Position - Lead Planning Engineer
Employed by Nexen Petroleum, UK. Located in Aberdeen, UK. Work covered the
planning and monitoring of brownfield modifications and the hook up and commissioning
of a new gas sweetening deck. The work scopes covered both work carried out during live
production and shutdown situations.
Page 1 of 6
2. Primavera P3 was the primary planning system used.
May.2007 – Dec.2007 Whessoe Oil & Gas
Position - Senior Planning Engineer
Employed by Whessoe Oil & Gas. Located in Darlington, UK. Work covered the
compilation of EPC bid schedules for LNG import and storage terminals with varying
storage capacities from 30,000m3 upto 160,000m3. Sometime was spent within the
research and development group providing schedule compilation and analyses of newly
developed construction methods for the building of LNG storage tanks.
Primavera P3 & P5 were the primary planning systems used.
Dec. 2006 – Apr. 2007 AGIP Kashagan Project
Position - Senior Planning Engineer
Employed by AGIP UK. Located in Milan, Italy. Work covered the compilation of the
hook up construction plan as part of an overall project integrated plan. The tracking of
design and engineering deliverables, onshore module construction status, equipment
deliveries and simultaneous offshore operations were all considered with the view of
compiling a plan which met commissioning priorities.
Primavera P3 & P5 were the primary planning systems used.
Mar. 2003 - Nov. 2006 Nexen Buzzard North Sea Oil & Gas Installation.
Position – Senior Planning Engineer
Employed by Nexen Petroleum UK.
I joined the project just prior to sanction in the John Brown Design office situated in
London.
Carried out fabrication bid evaluations and was then relocated to the Quarters & Utilities
fabrication site at Hartlepool, Teeside, UK to overview the fabrication and onshore
commissioning phases of the schedule.
Following completion of the Quarters & Utilities deck I transferred to Aberdeen to begin
planning preparations for the offshore HUC phase.
From July 2006 I was located offshore from Aberdeen on a two week about rota covering
the planning aspects of the Buzzard HUC phase.
Primavera P3 was the primary planning system used during the fabrication and HUC
phases.
PROFESSIONAL EXPERIENCE: (cont.)
Mar. 2002 - Feb. 2003 Shell Bonga Floating Production & Storage Vessel.
Position - Senior Commissiioning Planning Engineer
Employed by Amec process and energy, located at the Wallsend Yard, Tyneside, UK.
Work involved the planning of the in yard commissioning phase and interfacing with the
construction completions group.
Primavera P3 was the primary planning system used during the fabrication and HUC
phases.
Page 2 of 6
3. Nov. 2000 - Feb 2002 BNFL Technologly Centre - Sellafield.
Position - Senior Planning Engineer
Employed by the AMEC-BNFL project management team.
Work involved the compiling of discipline level 4 programmes to produce integrated
multi discipline 90 day construction lookaheads.
Primavera suretrack & P3 planning packages were the primary planning systems used.
Sep. 1997 - Oct. 2000 Shearwater Development Alliance Integrated Deck Hook Up & Commissioning.
Position - Senior Planning Engineer
Employed by AMEC process and energy I joined the project at the design stage and spent
15 months in AMEC’s Golden Lane office in London.
Initially work involved preparing schedules covering the development work to allow the
timely commencement of the onshore commissioning phase.
The Artemis 7000 planning system and various Microsoft software packages were used in
this work.
Initial plans covering the onshore commissioning and offshore hook up and
commissioning phases were prepared.
Following this I moved to AMEC’s fabrication yard in Wallsend where the detailed
planning of the onshore commissioning was continued. Interfacing with the construction
site planners was carried out to arrive at reasonable system handover dates that made up
the basis of the plan.
Precedence networks input into the Artemis 7000 system were used to produce detailed
plans, progress ‘S’ curves and manpower histograms which were monitored against each
week. Progress and productivity reports were produced using AMEC’s jobcard
management system (JMS). The schedule impact of missed handover dates were analysed
and advised and short-term lookaheads were produced. During the latter stages of the
onshore phase the detailed planning of the offshore hook up and commissioning phase
was undertaken.
Using precedence networks input to the Artemis 7000 system and AMEC’s jobcard
management system, detailed plans, progress ‘S’ curve and manpower histograms were
produced.
The project then moved to offshore on a two week about rota where I monitored actual
progress against the plan and advised of schedule impacts. Short-term lookaheads were
produced in order to indicate priority work areas
Interfacing with design was carried out in order to indicate when commissioning design
deliverables were required.
PROFESSIONAL EXPERIENCE: (cont.)
.
Jul. 1996 - Aug. 1997 Shell Curlew Floating Production & Storage Vessel
Position - Senior Planning Engineer
Working for AMEC responsible for the planning of the above F.P.S.O. Work involved
the development of a project plan to cover the construction and commissioning phases.
Initially based in the AMEC London design office work was carried out on the
integration of the design and construction plans.
Following this I moved to AMEC’s Wallsend fabrication yard to cover the construction
and commissioning phases of the project.
Page 3 of 6
4. The project plan was developed using the Artemis 7000 system. The work was
organised by using workpacks and jobcards and monitored weekly.
Short-term lookaheads were produced with key activities required to meet project
milestones closely monitored.
Apr. 1996 - Jun.1996 B.P E.T.A.P Utilities / Accommodation Module
Position - Senior Planning Engineer
Working for Kvaerner Oil & Gas at their construction yard in Fife.
Work involved the development of a detailed plan for the construction of the Marnoch
Utilities/Accommodation module and the Mungo satellite wellhead module. Artemis
6000 & 9000 software was used.
Mar. 1994 - Mar. 1996 B.P Andrew Integrated Deck Fabrication
Position - Senior Planning Engineer
Employed by Trafalgar House Offshore Fabricators. Work involved compiling detailed
fitting out programmes by means of precedence networks input into the Artemis 6000
system. These networks were integrated with design and commissioning programmes to
form an overall project plan for the monitoring and direction of work throughout the
project.
Oct. 1993 - Mar. 1994 Shell Brent Bravo Long Term Field Development
Position - Planning Engineer
Employed offshore by A.O.C.I work involved the monitoring of progress and
productivity on a daily basis. Detailed planning of the installation of new pipework
systems was undertaken using precedence networks and the Artemis 6000 system.
Jun. 1993 - Sep. 1993 Shell Brent Alpha Shutdown
Position - Planning Engineer
Employed in Aberdeen by A.O.C.I the work involved detailed pre-planning of the work to
be carried out during a six-week production shutdown for plant refurbishment. The work
then moved offshore on a two week about rota where the actual progress was monitored
against the plan in order to direct the work effort and identify potential problem areas.
PROFESSIONAL EXPERIENCE: (cont.)
Dec. 1992 - May. 1993 AGIP Tiffany Hook Up & Commissioning
Position - Planning Engineer
Working within the Saipol management team offshore. Work involved controlling the
issue of jobcards, monitoring of progress, producing reports covering progress and
outstanding work lists using the FoxPro Computer system. Short-term lookaheads were
produced to direct the work effort.
Page 4 of 6
5. Aug. 1992 - Nov. 1992 ELF Saltire Hook Up & Commissioning
Position - Planning Engineer
Working for A.O.C.I within the ELF/A.O.C.I integrated management team in Tyneside
and offshore. Detailed pre-planning of the hook up & commissioning scope was carried
out in Tyneside using the Artemis 9000 system. The work then moved offshore where
progress and productivity was monitored by means of jobcards.
Dec. 1991 - Jul. 1992 B.P Miller Hook Up & Commissioning
Position - Planning Engineer
Working offshore for A.O.C.I within the B.P./A.O.C.I integrated management team. The
main duties involved the production of computer generated reports covering weekly
progress, productivity and man-hour expenditure using the Artemis 6000 system. The
control of jobcard issue and the drawing up of short-term lookaheads was also carried out.
Jun. 1990 - Nov.1991 Shell Gannet and Shell Nelson Integrated Deck Fabrication.
Position - Planning Engineer
Employed by Redpath Offshore Limited at their Teeside fabrication yard. Work involved
producing schedules generated from precedence networks at various levels of detail using
the Artemis 6000 system. Monitoring progress & productivity and manpower forecasting
was carried out.
Sep. 1988 - May. 1990 Conoco Compression Deck Fabrication
Position - Planning Engineer
Employed by Press Offshore Limited at their Wallsend fabrication yard, Work involved
producing schedules at various levels of detail using the Artemis 6000 system.
Monitoring progress & productivity and manpower forecasting was carried out.
PROFESSIONAL EXPERIENCE: (cont.)
Oct. 1984 - Aug. 1988 North East Shipbuilders Limited
Position - Planning Engineer
Production scheduling, monitoring progress and supplying information on materials
required by production. Involved with the implementation of a new labour cost control
system.
Page 5 of 6
6. Sep. 1975 - Sep. 1984 Position - Mechanical Fitter
On successful completion of my apprenticeship was responsible for the installation of
marine machinery, pipework and instrumentation and control
systems.
Qualifications & Training :
H.N.C
Mechanical Engineering
Combined Offshore Survival & Fire Fighting Training
Offshore Safety Training (MIST)
Offshore Safety Training (CAEBS)
Page 6 of 6
7. Sep. 1975 - Sep. 1984 Position - Mechanical Fitter
On successful completion of my apprenticeship was responsible for the installation of
marine machinery, pipework and instrumentation and control
systems.