SlideShare a Scribd company logo
1 of 39
Download to read offline
Modern Practices for the Design and Planning of Underground Mines 
Rob McGill 
Head of Mining 
WorleyParsonsTWP
Contents 
•Underground Mining Trends 
•Mine Life-cycle 
•Key Success Factors for Mine Planning and Design 
•Mine Planning Process and Tools 
•Examples of Outputs 
•Expected developments in Underground Mining 
•Conclusion
Underground Mining Trends 
•Low commodity prices/tight margins 
•Fewer projects meeting hurdle rates 
•Access to funding/risk aversion 
•Deeper underground deposits 
•Higher opex costs 
•Safety and regulation 
•But demand for commodities will be lasting 
•Increased underground focus 
–Mature pits 
–Environmental pressures
Mine Life-cycle 
Resource Definition 
Target Identification 
Exploration 
Resource Estimate 
Project Evaluation Phase 
Concept/Scoping 
Pre-feasibility 
Feasibility 
Mine Construction Phase 
Detailed design 
Project Execution 
Mine Production Phase 
Build-up 
Steady state 
Mine Closure 
Production decline 
Rehab and closure
Value Curve
Project Evaluation Phase 
Concept/Scoping 
Pre-feasibility 
Feasibility 
Phase Objective Key Focus Areas Costs CONCEPT/PEA  To identify major options for opportunity realisation  Confirm alignment with the business case  Assess the potential value of the opportunity  Define the work required to assess the opportunity  Establish a plan for the Pre-Feasibility phase  Is this the right opportunity for the client?  Is the opportunity consistent with the client’s overall business strategy?  Does the potential value from the opportunity justify further investigation?  The thoroughness of evaluation of alternative technology, costing and implementation approaches.  Integrity of Pre-feasibility planning.  Have areas of opportunity and risk been investigated in later stages to enhance value? Capital Cost + / -25%
Project Evaluation Phase 
Concept/Scoping 
Pre-feasibility 
Feasibility 
Phase Objective Key Focus Areas Costs PRE-FEASIBILITY  The best project size, scope, technical and production solution has been selected and is a viable business concept aligned to business strategy.  Demonstration that all the discarded project options have been studied and are clearly inferior and have no probability of re-emerging as viable options.  A workable plan for taking the concept through the Feasibility development stage.  Have all of the options been adequately considered and reviewed on an equal basis?  What criteria were used to select the preferred option?  Have all opportunities for optimisation been reasonable pursued?  Are the risks and possible mitigators well understood?  Does the potential value from the opportunity still justify further investigation?  Integrity of Feasibility planning. Capital Cost + 25% to –15%
Project Evaluation Phase 
Concept/Scoping 
Pre-feasibility 
Feasibility 
Phase Objective Key Focus Areas Costs FEASIBILITY  Develop a Proven Business proposition at the appropriate level of detail and accuracy for implementation funding.  Is there a thorough understanding of the value and risks associated with the opportunity prior to moving into Implementation?  Is there an acceptable risk profile?  Is there a workable plan for taking the Project through the implementation & Operational readiness stages?  Is the opportunity recommended for approval? Capital Cost + 15% to – 5%
Typical Project Organogram 
Project Manager 
Mining 
Geologist 
Geotechnical Engineer 
Mining Engineer 
Ventilation Engineer 
Mine Planner 
Engineering 
Discipline Engineers 
Drawing Office 
Capital Estimator 
Project Services 
Project Secretary 
Project Planner
Key Success Factors for Mine Planning and Design 
•Quality/quantity of inputs 
•Understanding of value chain and link between inputs and outputs 
•Experience and skill 
–Mining operations and projects 
–Planning tools 
•Team integration 
• Consistency and applicability of design criteria 
•Benchmarking/callibration
Mine Planning and Design Inputs 
Mine Design and Planning 
Geology 
-Block Model 
-Geometric and structure model 
-Stratigraphic model 
Geotech 
-Rock Mass ratings 
-Empirical design “rules-of- thumb” 
Ventilation 
- Empirical design “rules-of- thumb” 
-Regulatory design criteria 
-Mining equipment specifications 
Mining Engineering -Mining method -Development and stoping rates -Preferred equipment specs -Targeted production schedule and volumes 
Infrastructure 
- Preferred access methodology 
-Requirements for services/transport 
-Capacities and constrants 
Strategic Goals -Life-of-mine -Payback Period -Financial goals
Mining Method Selection 
Common Methods 
•Block Cave 
•Sub-level cave 
•Open-stoping 
•Sub-level open-stoping 
•Cut and fill 
•Drift and fill 
•Shrinkage 
•Bord-and-pillar 
•Step bord-and-pillar 
•Narrow flat tabular 
Design Considerations 
•Ore body geometry 
•Rock Mass properties 
•Required production volumes 
•Opex/Capex cost 
•Safety/Productivity 
•Skills available 
•Equipment available 
•Grade control
Access Methodologies 
•Declines 
–Drill and blast 
–TBM 
•Ramps 
•Shafts 
–Blind-sink 
–Raise-bored 
–Bored 
•Combinations 
•Criteria: 
–Depth/Geometry 
–Timing 
–Bottom Access 
–Production Volume 
–Cost and capital availablity
Project Construction Time 
12 
24 
36 
48 
60 
72 
84 
600 
800 
1000 
1200 
1400 
1600 
1800 
2000 
Development time in months 
Depth in metres 
Drill and Blast 
TBM 
Conventional Shaft 
Bored Shaft
Advantages of TBM Access Development 
Seems obvious 
Quicker 
One pass 
Safer 
Continuous and reliable 
But slow to catch on in mining 
Hard rock applications and non-isotropic/non-homogenous material 
High rock stress and fracturing 
Geometry and size of equipment 
Lack of hands-on experience 
Seen as expensive and elegant
Mine Planning Software Tools 
•Gemcom –Surpac/Mineshed/Minex 
•CAE – 5D Planner / Enhanced Production Scheduler(EPS) 
•MINERP – CADSmine / No scheduler (Reporting done in spreadsheets) 
•MINERP – MINE2-4D / Enhanced Production Scheduler(EPS)
•29.486 Moz 
•LoM – 43 years (2052) 
•Building up to 330 Kt/m 
•To produce up to 800,000 ounces/ year (25 tonnes) 
DESIGN CRITERIA OVERVIEW
MINERAL RESERVES AND LOM 
Main and Vent shaft 
Current Mine
MINERAL RESERVES AND LOM 
Main and Vent shaft 
Current Mine
MINERAL RESERVES AND LOM 
Current Mine 
Main and Vent shaft
MINERAL RESERVES AND LOM 
Main and Vent shaft
MINERAL RESERVES AND LOM 
Main and Vent shaft
MINERAL RESERVES AND LOM 
Main and Vent shaft
Project Footprint 
2 
4
- 
100,000 
200,000 
300,000 
400,000 
500,000 
600,000 
Gold Ounces 
BP12 Level 1 
Phase 2 
Phase 3 
Production Profile 
25
Mine design 
Criteria 
Remarks 
Stoping Design 
Sequential Grid Mining Method 
Mining Levels 
113,116,120 
ORD development rate 
45m/month 
Reef development rate 
30 m/month 
Mining Crews per raise line( between levels) 
5 maximum 
Ledging Face Advance 
10 m/month (average) 
Stope Face Advance 
7.2 m/month (average) 
Ledging crews(between levels) 
Dependant on available raise lines – with not more than3 crews per raise line 
Stope Width 
120 cm 
Panel Length 
25 m to 35 m 
MCF(as per BP2013) 
60% 
Plant recovery factor 
97,4%
0 
5000 
10000 
15000 
20000 
25000 
30000 
2013 
2014 
2015 
2016 
2017 
2018 
2019 
2020 
2021 
2022 
Project Carbon Leader reef monthly tonnes milled 
Average – 4500 m2/month 
Average – 120kg/month 
Average – 23000 tonnes month 
Average – 253m/ month
28 
Thickness and Grade Distribution 
> 8 
6 - 8 
4 - 6 
2 - 4 
< 2 
THICKNESS COLOUR 
20 - 100 
15 - 20 
10 - 15 
8 - 10 
6 - 8 
4 - 6 
2.2 - 4 
0 - 2.2 
GRADE COLOUR
29 
Isometric View of Design Options 
Longitudinal 
Sub Level Open Stoping 
Longitudinal Retreat
Existing mining 
Existing infrastructure 
Different colours represent different months schedule 
Animation output
Production Report 
Production Report fed from outputs of Enhanced Production Scheduler
Vertical shaft access
Planta en caverna 
Chancadoras 
Longitudinal Sub Level Stoping / Bench and Fill Stoping
Expected Developments in Underground Mining 
•Increased mechanization and automation 
•Tunnel and shaft boring 
•Environmental/safety pressures 
•Margin pressures 
•Better quality design and planning 
•More standardization in design and planning
Conclusion 
•Mine design and planning has become more critical in projects and operations in recent years 
•Quality of tools have improved with better computer graphics and processing speeds 
•Projects now require full designs and plans using software tools for auditability 
• These designs and plans are only as good as the inputs provided and the skills of the engineers and planners. Actual hands-on mining experience is critical in applying the tools correctly
Av. La Encalada N° 1257 
Centro Empresarial La Encalada 
Oficina N° 801 
Santiago de Surco 
Lima 33, Perú 
Hector Paredes Tarazona 
Managing Director - Peru 
Hector.Paredes@Worleyparsons.com
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines

More Related Content

What's hot

Mike R Williams Resume
Mike R Williams  ResumeMike R Williams  Resume
Mike R Williams Resume
Mike Williams
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Carl Greenstreet
 
George Dounis_PID_509
George Dounis_PID_509George Dounis_PID_509
George Dounis_PID_509
George Dounis
 
underground_4-page_12142015_LR
underground_4-page_12142015_LRunderground_4-page_12142015_LR
underground_4-page_12142015_LR
Anne Fellini
 

What's hot (20)

EOR vs. Storage, Ed Steadman, EERC
EOR vs. Storage, Ed Steadman, EERCEOR vs. Storage, Ed Steadman, EERC
EOR vs. Storage, Ed Steadman, EERC
 
Miek Resume Feb 2016.pdf
Miek Resume Feb 2016.pdfMiek Resume Feb 2016.pdf
Miek Resume Feb 2016.pdf
 
TNR Gold Shotgun Gold Project in Alaska Presentation.
TNR Gold Shotgun Gold Project in Alaska Presentation.TNR Gold Shotgun Gold Project in Alaska Presentation.
TNR Gold Shotgun Gold Project in Alaska Presentation.
 
Mike R Williams Resume
Mike R Williams  ResumeMike R Williams  Resume
Mike R Williams Resume
 
Henri_silalahi_CV2016
Henri_silalahi_CV2016Henri_silalahi_CV2016
Henri_silalahi_CV2016
 
Unit 4
Unit 4Unit 4
Unit 4
 
Denver Gold Forum 2014
Denver Gold Forum 2014Denver Gold Forum 2014
Denver Gold Forum 2014
 
Seia public consultation dec 2013
Seia public consultation dec 2013Seia public consultation dec 2013
Seia public consultation dec 2013
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
 
The cost-effective upgrading, preservation and rehabilitation of roads - opti...
The cost-effective upgrading, preservation and rehabilitation of roads - opti...The cost-effective upgrading, preservation and rehabilitation of roads - opti...
The cost-effective upgrading, preservation and rehabilitation of roads - opti...
 
George Dounis_PID_509
George Dounis_PID_509George Dounis_PID_509
George Dounis_PID_509
 
News Release: Completion of Drill Program at Eldor
News Release: Completion of Drill Program at EldorNews Release: Completion of Drill Program at Eldor
News Release: Completion of Drill Program at Eldor
 
Economic Assessment and Value Maximizations of a Mining Operation based on an...
Economic Assessment and Value Maximizations of a Mining Operation based on an...Economic Assessment and Value Maximizations of a Mining Operation based on an...
Economic Assessment and Value Maximizations of a Mining Operation based on an...
 
A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...
 
Reservoir Characterization of “G900” Sandstones Using Wireline Logs and Cores...
Reservoir Characterization of “G900” Sandstones Using Wireline Logs and Cores...Reservoir Characterization of “G900” Sandstones Using Wireline Logs and Cores...
Reservoir Characterization of “G900” Sandstones Using Wireline Logs and Cores...
 
Terrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse PlanningTerrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse Planning
 
News Release: Commerce Resources Completes 22 Drill Holes at Ashram Rare Ear...
News Release:  Commerce Resources Completes 22 Drill Holes at Ashram Rare Ear...News Release:  Commerce Resources Completes 22 Drill Holes at Ashram Rare Ear...
News Release: Commerce Resources Completes 22 Drill Holes at Ashram Rare Ear...
 
Reservoir characterization technique based on geostatistical inversion method
Reservoir characterization technique based on geostatistical inversion methodReservoir characterization technique based on geostatistical inversion method
Reservoir characterization technique based on geostatistical inversion method
 
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
 
underground_4-page_12142015_LR
underground_4-page_12142015_LRunderground_4-page_12142015_LR
underground_4-page_12142015_LR
 

Viewers also liked

Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
sou_suk_sou
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
Tayyab Anwar
 
UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION
UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATIONUNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION
UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION
Joseph Obeng-Sika
 
Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...
Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...
Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...
John Sykes
 
Grafico diario del dax perfomance index para el 11 05-2012
Grafico diario del dax perfomance index para el 11 05-2012Grafico diario del dax perfomance index para el 11 05-2012
Grafico diario del dax perfomance index para el 11 05-2012
Experiencia Trading
 
איתמר ורלי
איתמר ורליאיתמר ורלי
איתמר ורלי
merkazy
 
2013-09-12 - SUGDC - Office 365 and Hybrid Solutions
2013-09-12 - SUGDC - Office 365 and Hybrid Solutions2013-09-12 - SUGDC - Office 365 and Hybrid Solutions
2013-09-12 - SUGDC - Office 365 and Hybrid Solutions
Dan Usher
 
Replacement of legacy cis with sap cr&b at phi
Replacement of legacy cis with sap cr&b at phiReplacement of legacy cis with sap cr&b at phi
Replacement of legacy cis with sap cr&b at phi
robgirvan
 

Viewers also liked (18)

Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
 
Lecture 4: Underground Mining
Lecture 4: Underground MiningLecture 4: Underground Mining
Lecture 4: Underground Mining
 
Underground mining
Underground miningUnderground mining
Underground mining
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION
UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATIONUNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION
UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION
 
Health economic evaluation throughout the ages
Health economic evaluation throughout the agesHealth economic evaluation throughout the ages
Health economic evaluation throughout the ages
 
Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...
Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...
Why is developing a new mine so difficult? - Oct 2013 - John P Sykes - Centre...
 
General mining and underground induction
General mining and underground inductionGeneral mining and underground induction
General mining and underground induction
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Underground mine
Underground mineUnderground mine
Underground mine
 
HAPPYWEEK 172 2016.05.30.
HAPPYWEEK 172 2016.05.30.HAPPYWEEK 172 2016.05.30.
HAPPYWEEK 172 2016.05.30.
 
Grafico diario del dax perfomance index para el 11 05-2012
Grafico diario del dax perfomance index para el 11 05-2012Grafico diario del dax perfomance index para el 11 05-2012
Grafico diario del dax perfomance index para el 11 05-2012
 
איתמר ורלי
איתמר ורליאיתמר ורלי
איתמר ורלי
 
μεγαουρητήρας
μεγαουρητήραςμεγαουρητήρας
μεγαουρητήρας
 
2013-09-12 - SUGDC - Office 365 and Hybrid Solutions
2013-09-12 - SUGDC - Office 365 and Hybrid Solutions2013-09-12 - SUGDC - Office 365 and Hybrid Solutions
2013-09-12 - SUGDC - Office 365 and Hybrid Solutions
 
Replacement of legacy cis with sap cr&b at phi
Replacement of legacy cis with sap cr&b at phiReplacement of legacy cis with sap cr&b at phi
Replacement of legacy cis with sap cr&b at phi
 
Aulas
AulasAulas
Aulas
 

Similar to PERUMIN 31: Modern Practices for the Design and Planning Underground Mines

Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept Engineer
Marcel Zeestraten
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
Egyptian Engineers Association
 
Curriculum Vitae-Ashish Trivedi
Curriculum Vitae-Ashish TrivediCurriculum Vitae-Ashish Trivedi
Curriculum Vitae-Ashish Trivedi
Ashish Trivedi
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
Prabhu Bose
 
Mahendiran Resume 07.08.15
Mahendiran Resume 07.08.15Mahendiran Resume 07.08.15
Mahendiran Resume 07.08.15
Mahendiran N
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
Hetal Visaria
 
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
GreenData.IO
 

Similar to PERUMIN 31: Modern Practices for the Design and Planning Underground Mines (20)

Modern practices for the design and
Modern practices for the design andModern practices for the design and
Modern practices for the design and
 
Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept Engineer
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Curriculum Vitae-Ashish Trivedi
Curriculum Vitae-Ashish TrivediCurriculum Vitae-Ashish Trivedi
Curriculum Vitae-Ashish Trivedi
 
ChE: 1st Principles Approach to Problem Solving
ChE: 1st Principles Approach to Problem Solving  ChE: 1st Principles Approach to Problem Solving
ChE: 1st Principles Approach to Problem Solving
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016
 
MERCC-Generic-Profile-Dec18.pdf MINING CONSULTANT
MERCC-Generic-Profile-Dec18.pdf MINING CONSULTANTMERCC-Generic-Profile-Dec18.pdf MINING CONSULTANT
MERCC-Generic-Profile-Dec18.pdf MINING CONSULTANT
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
FUNDAMENTALS OF MINE DESIGN, AND PLANNINGS
FUNDAMENTALS OF MINE DESIGN, AND PLANNINGSFUNDAMENTALS OF MINE DESIGN, AND PLANNINGS
FUNDAMENTALS OF MINE DESIGN, AND PLANNINGS
 
2015 Toronto Section Presentation
2015 Toronto Section Presentation2015 Toronto Section Presentation
2015 Toronto Section Presentation
 
CV
CVCV
CV
 
Mahendiran Resume 07.08.15
Mahendiran Resume 07.08.15Mahendiran Resume 07.08.15
Mahendiran Resume 07.08.15
 
Project Management: Minimizing Risk and Maximizing Project Success
Project Management: Minimizing Risk and Maximizing Project SuccessProject Management: Minimizing Risk and Maximizing Project Success
Project Management: Minimizing Risk and Maximizing Project Success
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
engineering portfolio 26-11-22.pdf
engineering portfolio 26-11-22.pdfengineering portfolio 26-11-22.pdf
engineering portfolio 26-11-22.pdf
 
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
 

More from PERUMIN - Convención Minera

More from PERUMIN - Convención Minera (20)

Cóctel de Agradecimiento - Lima
Cóctel de Agradecimiento - LimaCóctel de Agradecimiento - Lima
Cóctel de Agradecimiento - Lima
 
IIMP entregó modernas instalaciones del vivero de la UNSA
IIMP entregó modernas instalaciones del vivero de la UNSAIIMP entregó modernas instalaciones del vivero de la UNSA
IIMP entregó modernas instalaciones del vivero de la UNSA
 
Especialistas debatieron sobre la Encíclica Laudato Si y su relación con la m...
Especialistas debatieron sobre la Encíclica Laudato Si y su relación con la m...Especialistas debatieron sobre la Encíclica Laudato Si y su relación con la m...
Especialistas debatieron sobre la Encíclica Laudato Si y su relación con la m...
 
Programa de la conferencia magistral: La Encíclica Laudato Si y su relación c...
Programa de la conferencia magistral: La Encíclica Laudato Si y su relación c...Programa de la conferencia magistral: La Encíclica Laudato Si y su relación c...
Programa de la conferencia magistral: La Encíclica Laudato Si y su relación c...
 
Debatirán Encíclica Laudato Si del Papa Francisco y su relación con la minería
Debatirán Encíclica Laudato Si del Papa Francisco y su relación con la mineríaDebatirán Encíclica Laudato Si del Papa Francisco y su relación con la minería
Debatirán Encíclica Laudato Si del Papa Francisco y su relación con la minería
 
Kieren Moffat: "La aceptación social va de la mano con la solidez del gobierno"
Kieren Moffat: "La aceptación social va de la mano con la solidez del gobierno"Kieren Moffat: "La aceptación social va de la mano con la solidez del gobierno"
Kieren Moffat: "La aceptación social va de la mano con la solidez del gobierno"
 
IIMP Y CSIRO analizarán los procedimientos para mantener la licencia social
IIMP Y CSIRO analizarán los procedimientos para mantener la licencia socialIIMP Y CSIRO analizarán los procedimientos para mantener la licencia social
IIMP Y CSIRO analizarán los procedimientos para mantener la licencia social
 
Invitación a la Ceremonia de Inauguración de la FIL Arequipa 2015
Invitación a la Ceremonia de Inauguración de la FIL Arequipa 2015Invitación a la Ceremonia de Inauguración de la FIL Arequipa 2015
Invitación a la Ceremonia de Inauguración de la FIL Arequipa 2015
 
Suplemento PERUMIN (25 de setiembre, 2015)
Suplemento PERUMIN (25 de setiembre, 2015)Suplemento PERUMIN (25 de setiembre, 2015)
Suplemento PERUMIN (25 de setiembre, 2015)
 
Festival de la Juventud se posterga hasta próximo aviso
Festival de la Juventud se posterga hasta próximo avisoFestival de la Juventud se posterga hasta próximo aviso
Festival de la Juventud se posterga hasta próximo aviso
 
Cartilla Informativa de Seguridad
Cartilla Informativa de SeguridadCartilla Informativa de Seguridad
Cartilla Informativa de Seguridad
 
Suplemento PERUMIN (24 de setiembre, 2015)
Suplemento PERUMIN (24 de setiembre, 2015)Suplemento PERUMIN (24 de setiembre, 2015)
Suplemento PERUMIN (24 de setiembre, 2015)
 
Suplemento perumin (23 de setiembre)
Suplemento perumin (23 de setiembre)Suplemento perumin (23 de setiembre)
Suplemento perumin (23 de setiembre)
 
Suplemento PERUMIN (22 de setiembre)
Suplemento PERUMIN (22 de setiembre)Suplemento PERUMIN (22 de setiembre)
Suplemento PERUMIN (22 de setiembre)
 
Cronograma de Conferencias de Prensa
Cronograma de Conferencias de PrensaCronograma de Conferencias de Prensa
Cronograma de Conferencias de Prensa
 
Plano Sede - Guía del Visitante
Plano Sede - Guía del VisitantePlano Sede - Guía del Visitante
Plano Sede - Guía del Visitante
 
PERUMIN 32 - Programa Resumido
PERUMIN 32 - Programa ResumidoPERUMIN 32 - Programa Resumido
PERUMIN 32 - Programa Resumido
 
Inscripciones vía online para PERUMIN 32 culminan el 20 de setiembre
Inscripciones vía online para PERUMIN 32 culminan el 20 de setiembreInscripciones vía online para PERUMIN 32 culminan el 20 de setiembre
Inscripciones vía online para PERUMIN 32 culminan el 20 de setiembre
 
Comunicado: ¡Inscripciones vía online culminan el 20 de setiembre!
Comunicado: ¡Inscripciones vía online culminan el 20 de setiembre!Comunicado: ¡Inscripciones vía online culminan el 20 de setiembre!
Comunicado: ¡Inscripciones vía online culminan el 20 de setiembre!
 
Estados Unidos iniciará el Encuentro Internacional
Estados Unidos iniciará el Encuentro InternacionalEstados Unidos iniciará el Encuentro Internacional
Estados Unidos iniciará el Encuentro Internacional
 

Recently uploaded

Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
Kayode Fayemi
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New Nigeria
Kayode Fayemi
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
Sheetaleventcompany
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
raffaeleoman
 

Recently uploaded (20)

Air breathing and respiratory adaptations in diver animals
Air breathing and respiratory adaptations in diver animalsAir breathing and respiratory adaptations in diver animals
Air breathing and respiratory adaptations in diver animals
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatment
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
 
My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Bailey
 
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New Nigeria
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio III
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfThe workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
 
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
 
Causes of poverty in France presentation.pptx
Causes of poverty in France presentation.pptxCauses of poverty in France presentation.pptx
Causes of poverty in France presentation.pptx
 
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, YardstickSaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubs
 

PERUMIN 31: Modern Practices for the Design and Planning Underground Mines

  • 1. Modern Practices for the Design and Planning of Underground Mines Rob McGill Head of Mining WorleyParsonsTWP
  • 2. Contents •Underground Mining Trends •Mine Life-cycle •Key Success Factors for Mine Planning and Design •Mine Planning Process and Tools •Examples of Outputs •Expected developments in Underground Mining •Conclusion
  • 3. Underground Mining Trends •Low commodity prices/tight margins •Fewer projects meeting hurdle rates •Access to funding/risk aversion •Deeper underground deposits •Higher opex costs •Safety and regulation •But demand for commodities will be lasting •Increased underground focus –Mature pits –Environmental pressures
  • 4. Mine Life-cycle Resource Definition Target Identification Exploration Resource Estimate Project Evaluation Phase Concept/Scoping Pre-feasibility Feasibility Mine Construction Phase Detailed design Project Execution Mine Production Phase Build-up Steady state Mine Closure Production decline Rehab and closure
  • 6. Project Evaluation Phase Concept/Scoping Pre-feasibility Feasibility Phase Objective Key Focus Areas Costs CONCEPT/PEA  To identify major options for opportunity realisation  Confirm alignment with the business case  Assess the potential value of the opportunity  Define the work required to assess the opportunity  Establish a plan for the Pre-Feasibility phase  Is this the right opportunity for the client?  Is the opportunity consistent with the client’s overall business strategy?  Does the potential value from the opportunity justify further investigation?  The thoroughness of evaluation of alternative technology, costing and implementation approaches.  Integrity of Pre-feasibility planning.  Have areas of opportunity and risk been investigated in later stages to enhance value? Capital Cost + / -25%
  • 7. Project Evaluation Phase Concept/Scoping Pre-feasibility Feasibility Phase Objective Key Focus Areas Costs PRE-FEASIBILITY  The best project size, scope, technical and production solution has been selected and is a viable business concept aligned to business strategy.  Demonstration that all the discarded project options have been studied and are clearly inferior and have no probability of re-emerging as viable options.  A workable plan for taking the concept through the Feasibility development stage.  Have all of the options been adequately considered and reviewed on an equal basis?  What criteria were used to select the preferred option?  Have all opportunities for optimisation been reasonable pursued?  Are the risks and possible mitigators well understood?  Does the potential value from the opportunity still justify further investigation?  Integrity of Feasibility planning. Capital Cost + 25% to –15%
  • 8. Project Evaluation Phase Concept/Scoping Pre-feasibility Feasibility Phase Objective Key Focus Areas Costs FEASIBILITY  Develop a Proven Business proposition at the appropriate level of detail and accuracy for implementation funding.  Is there a thorough understanding of the value and risks associated with the opportunity prior to moving into Implementation?  Is there an acceptable risk profile?  Is there a workable plan for taking the Project through the implementation & Operational readiness stages?  Is the opportunity recommended for approval? Capital Cost + 15% to – 5%
  • 9. Typical Project Organogram Project Manager Mining Geologist Geotechnical Engineer Mining Engineer Ventilation Engineer Mine Planner Engineering Discipline Engineers Drawing Office Capital Estimator Project Services Project Secretary Project Planner
  • 10. Key Success Factors for Mine Planning and Design •Quality/quantity of inputs •Understanding of value chain and link between inputs and outputs •Experience and skill –Mining operations and projects –Planning tools •Team integration • Consistency and applicability of design criteria •Benchmarking/callibration
  • 11. Mine Planning and Design Inputs Mine Design and Planning Geology -Block Model -Geometric and structure model -Stratigraphic model Geotech -Rock Mass ratings -Empirical design “rules-of- thumb” Ventilation - Empirical design “rules-of- thumb” -Regulatory design criteria -Mining equipment specifications Mining Engineering -Mining method -Development and stoping rates -Preferred equipment specs -Targeted production schedule and volumes Infrastructure - Preferred access methodology -Requirements for services/transport -Capacities and constrants Strategic Goals -Life-of-mine -Payback Period -Financial goals
  • 12. Mining Method Selection Common Methods •Block Cave •Sub-level cave •Open-stoping •Sub-level open-stoping •Cut and fill •Drift and fill •Shrinkage •Bord-and-pillar •Step bord-and-pillar •Narrow flat tabular Design Considerations •Ore body geometry •Rock Mass properties •Required production volumes •Opex/Capex cost •Safety/Productivity •Skills available •Equipment available •Grade control
  • 13. Access Methodologies •Declines –Drill and blast –TBM •Ramps •Shafts –Blind-sink –Raise-bored –Bored •Combinations •Criteria: –Depth/Geometry –Timing –Bottom Access –Production Volume –Cost and capital availablity
  • 14. Project Construction Time 12 24 36 48 60 72 84 600 800 1000 1200 1400 1600 1800 2000 Development time in months Depth in metres Drill and Blast TBM Conventional Shaft Bored Shaft
  • 15. Advantages of TBM Access Development Seems obvious Quicker One pass Safer Continuous and reliable But slow to catch on in mining Hard rock applications and non-isotropic/non-homogenous material High rock stress and fracturing Geometry and size of equipment Lack of hands-on experience Seen as expensive and elegant
  • 16. Mine Planning Software Tools •Gemcom –Surpac/Mineshed/Minex •CAE – 5D Planner / Enhanced Production Scheduler(EPS) •MINERP – CADSmine / No scheduler (Reporting done in spreadsheets) •MINERP – MINE2-4D / Enhanced Production Scheduler(EPS)
  • 17. •29.486 Moz •LoM – 43 years (2052) •Building up to 330 Kt/m •To produce up to 800,000 ounces/ year (25 tonnes) DESIGN CRITERIA OVERVIEW
  • 18. MINERAL RESERVES AND LOM Main and Vent shaft Current Mine
  • 19. MINERAL RESERVES AND LOM Main and Vent shaft Current Mine
  • 20. MINERAL RESERVES AND LOM Current Mine Main and Vent shaft
  • 21. MINERAL RESERVES AND LOM Main and Vent shaft
  • 22. MINERAL RESERVES AND LOM Main and Vent shaft
  • 23. MINERAL RESERVES AND LOM Main and Vent shaft
  • 25. - 100,000 200,000 300,000 400,000 500,000 600,000 Gold Ounces BP12 Level 1 Phase 2 Phase 3 Production Profile 25
  • 26. Mine design Criteria Remarks Stoping Design Sequential Grid Mining Method Mining Levels 113,116,120 ORD development rate 45m/month Reef development rate 30 m/month Mining Crews per raise line( between levels) 5 maximum Ledging Face Advance 10 m/month (average) Stope Face Advance 7.2 m/month (average) Ledging crews(between levels) Dependant on available raise lines – with not more than3 crews per raise line Stope Width 120 cm Panel Length 25 m to 35 m MCF(as per BP2013) 60% Plant recovery factor 97,4%
  • 27. 0 5000 10000 15000 20000 25000 30000 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Project Carbon Leader reef monthly tonnes milled Average – 4500 m2/month Average – 120kg/month Average – 23000 tonnes month Average – 253m/ month
  • 28. 28 Thickness and Grade Distribution > 8 6 - 8 4 - 6 2 - 4 < 2 THICKNESS COLOUR 20 - 100 15 - 20 10 - 15 8 - 10 6 - 8 4 - 6 2.2 - 4 0 - 2.2 GRADE COLOUR
  • 29. 29 Isometric View of Design Options Longitudinal Sub Level Open Stoping Longitudinal Retreat
  • 30. Existing mining Existing infrastructure Different colours represent different months schedule Animation output
  • 31. Production Report Production Report fed from outputs of Enhanced Production Scheduler
  • 33.
  • 34.
  • 35. Planta en caverna Chancadoras Longitudinal Sub Level Stoping / Bench and Fill Stoping
  • 36. Expected Developments in Underground Mining •Increased mechanization and automation •Tunnel and shaft boring •Environmental/safety pressures •Margin pressures •Better quality design and planning •More standardization in design and planning
  • 37. Conclusion •Mine design and planning has become more critical in projects and operations in recent years •Quality of tools have improved with better computer graphics and processing speeds •Projects now require full designs and plans using software tools for auditability • These designs and plans are only as good as the inputs provided and the skills of the engineers and planners. Actual hands-on mining experience is critical in applying the tools correctly
  • 38. Av. La Encalada N° 1257 Centro Empresarial La Encalada Oficina N° 801 Santiago de Surco Lima 33, Perú Hector Paredes Tarazona Managing Director - Peru Hector.Paredes@Worleyparsons.com