              18 Weeks
STROKE
              Whole Pathways
              National Priority Project
Delivering 18 weeks in cardiology was always going to


?
be one of the most challenging areas in the 18 week pathway
because it is a many headed beast. You have a number of
investigations and diagnostics to perform as well as definitive
treatment so it’s always going to be difficult. If you can deliver it in
cardiology you can deliver it anywhere.
Dr Guy Lloyd,

                                                ?
Consultant Cardiologist, Eastbourne District General Hospital
18 Weeks Whole Pathways         3




Contents
Introduction                                                                    4
Key Findings                                                                    6
Project Summaries                                                               10
Lancashire & South Cumbria Cardiac Network – Redesigning the                    11
Whole Patient Pathway for Cardiology Patients
Trent Cardiac Network – Angiography Rapid Redesign Project                      12
Leicestershire, Northamptonshire and Rutland Cardiac Network –                  14
18 Week Whole Pathway Project
Sussex Heart Network – 18 Week Whole Pathway Project                            17
South West London Cardiac Network – Cardiac Surgery: Referral to                18
Treatment in 12 Weeks (average) project
Trent Cardiac Network – Derby Hospitals Angioplasty Pathway Project             20
Trent Cardiac Network – Tertiary Referrals Pilot Project for Cardiac Services   22
Trent Cardiac Network – Reducing Waits for Cardiac Diagnostics                  24
Trent Cardiac Network – Partial Booking of Follow Ups Project                   26
Anglia Cardiac Network – Achieving 18 week Referral to                          29
Treatment pathways by March 2008
Anglia Cardiac Network – 18 Weeks Whole Patient Pathway                         32
Data Capture
Resources and Project Team Membership                                           35




                                                               www.improvement.nhs.uk/heart
4       18 Weeks Whole Pathways




       Introduction
           To ensure that by 2008   ?                    The scope of the project covers the main



      ?    no one waits more than
           18 weeks from GP referral
           to hospital treatment.
           Operating framework 07/08:
                                                         18 week bottlenecks/constraints including:

                                                         •
                                                         •
                                                         •
                                                         •
                                                             Outpatients (OPD)
                                                             Diagnostics
                                                             Secondary to tertiary care interface
                                                             Some sites taking a whole pathway
           Priority 111: Access to services: PSA13           approach.


        This project has reviewed, identified and
        supported the practical implementation of            I think that consultant buy-in is


                                                         ?
        ways to reduce the waiting time from GP
        referral to definitive treatment, exploring in       absolutely crucial to the success
        detail what really works. The specific project       of the 18 week project but not
        aims and objectives have been to:                    surprisingly consultants vary in
        • Work with identified demonstration sites
                                                             their views of the importance of
          within cardiac networks to capture                 this project. Were not going to
          learning                                           get ten more consultants and
        • Implement a peer support action learning           there is no new money so we’ll
          group drawn from members across the
          demonstration sites to facilitate the
                                                             just have to think of ways to do
          sharing of ideas and solutions in order to         this better, quicker, slicker and
          reduce duplication and to accelerate               look to how we are actually
          improvement                                        doing our jobs.
        • Develop a range of practical resources
          including demonstration site case studies
          to assist the wider health communities
          to achieve required sustainable
          improvements
        • Provide input and advice to the
          Department of Health (DH) 18 week
                                                             Programme
                                                                                  ?
                                                             Dr Gordon Murray, Consultant Cardiologist and
                                                             National Clinical Lead, NHS Heart Improvement



                                                         In addition, a number of projects have
                                                         looked at specific sub process issues
          team based on demonstration site               particularly in relation to patient data,
          progress regarding issues, challenges and      tracking and the Interprovider
          solutions with implementing 18 weeks.          Administrative Minimum Data Set
                                                         (IPTAMDS).
        The demonstration sites involve seven
        cardiac networks and some 25 NHS Trusts
        (including foundation trusts).




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways           5


Being part of a national priority project has been good in that its


?
helped people in the organisation feel really motivated. When they
achieve something like bringing waiting times down they get a
real sense of achievement.



now beginning to demonstrate:
                                      ?
Julie Juden, Service Development Manager, Frimley Park Hospital NHS Foundation Trust


With the project into its 8th month sites are          • Improved audit, monitoring and internal
                                                         reporting processes
                                                       • Shared learning of the practical
• A significant release of slots and beds                implications/ramifications of the
  into the system                                        improvement initiative as a resource for
• Reduced whole pathway waiting                          accelerating change.
  times (with certain sites showing
  significant reductions in referral to                In conjunction with the demonstration
  treatment times (RTT times)                          sites NHS Improvement (which now
• Streamlined clinical and                             incorporates the Heart Improvement
  administrative pathways                              Programme) has developed a range of
• Improved communication between                       products and resources including:
  healthcare staff and patients
• The development and testing of                       • Pocket clock start/stop cardiac pathway
  information systems to support the                     scenarios complete with RTT status code
  collection of IPTAMDS for RTT (including a             indicators
  demonstrator site for web based tracking             • An updated online interactive 18 weeks
  system)                                                resource and
• More efficient use of OPD and diagnostic             • An interactive cardiac data dashboard
  clinic slots with corresponding falls in               capturing the national data returns for
  DNAs and clinic cancellations                          RTT and diagnostic data.
• Reduction in angiography and PCI waiting
  times with increased catheter lab                    In addition, products produced across the
  efficiency                                           demonstration sites are being collated and
• Improved patient experience                          catalogued as a resource for sharing with
  • Streamlined pre assessment and post                the wider health community. These products
     procedure protocols                               complement the established demand and
  • Improved, more responsive patient                  capacity, statistical process control, and
     centred booking processes                         patient pathway analyser tools available via
     (diagnostics)                                     the national team. A list of these resources
  • Efficiencies created via the introduction          together with a brief summary and the
     of one stop/single assessment clinics             relevant link(s) is available towards the end
     and rapid follow up slots processes.              of this document.
  • Better informed patients particularly
     with regard to surgery                            The current projects are phased for
  • Reductions in bed usage with protocols             completion from March 2008 onwards with
     allowing surgical patients to be                  work continuing with demonstration sites to
     admitted on day of procedure                      ensure delivery solutions are implemented
  • Improved equity in terms of waiting                and that sustainability is in place.
     times with the removal of urgent, soon            Consequently, the summaries that follow
     and routine classifications.                      only capture a proportion of the work to
• Creative approaches to staffing and                  date. The resulting case studies and
  workforce issues                                     associated resources (process maps, policies,
• Potential for reductions in surgical                 examples of questionnaires etc) will be
  cancellations through improved multi                 available on the NHS Improvement website
  disciplinary team (MDT) working and                  as the projects are validated.
  consent processes.

                                                                         www.improvement.nhs.uk/heart
6       18 Weeks Whole Pathways




        Key Findings




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                  7



Our biggest challenges - one was accessing data, our PAS

?
systems across the trust are quite old and we weren’t able
to put our hands on good 18 week data.       Anonymous



Key findings
During December 2008 cardiac networks took
part in a voluntary audit to survey the national
picture of 18 weeks - a cardiac stock take. The
aim of the stock take was to raise awareness,
                                                                  ?
                                                     In this environment many projects or initiatives
                                                     simply ground to a halt in the face of the myriad
                                                     of competing pressures, priorities and agenda’s
                                                     with local teams struggling with the size,
demonstrate progress and inform national             complexity and time needed to address the tasks
strategy with regard to implementation of the        presented. Again this echo’s the experiences of
18 week initiative. 87% of cardiac networks          the cancer waiting time initiatives and the
completed the survey, the results of which           pivotal nature of a comprehensive strategy.
acknowledge how complex and challenging 18
weeks is as it seeks to deliver improved patient     Its interesting to note that where gains have
experiences and outcomes across diverse              been made that the initial strategic catalyst
pathways, healthcare providers, and                  emanated from a variety of sources whether it
organisational environments.                         be SHA, commissioner, provider or network (top
                                                     down, bottom up and everything in between).
Summarising the learning itself becomes a            Again this is evidenced from information
challenge as the subject matter is equally diverse   obtained through the network 18 week stock
so for the purpose of this document only the         take; 16% of approaches measured were
headlines have been articulated. The 18 week         attributed to network initiatives, 13% to whole
online resource, developed by the NHS Heart          health economy, 18% to provider with the
Improvement Programme, provides top tips and         remaining 7% being attributed to ‘other’.
more detailed approaches in an interactive
resource that runs to over 150 pages so please       It’s clear that truly inclusive health economy
follow the link at the end of this document.         strategies, together with complementary
                                                     operational plans delivered in time for
Experiences gained from within the NHS Heart         sustainability to be addressed will remain a
Improvement Programme, across the                    challenge for the country as a whole.
demonstration sites and findings from the stock
take have summarised critical success factors as     Buy in, understanding, inclusivity
being:                                               and communication
                                                     18 weeks is such a wide ranging challenge that
• Comprehensive shared strategy and plans for        all staff need to understand what it represents to
  implementation                                     the organisation, to patients, to customers and
• Buy-in, understanding, inclusivity and             of course to themselves.
  communication
• Robust project management                          Successful initiatives have an overall vision to
• IT system architecture and data collection         work to and have worked though strategies for
  within 18 weeks                                    creating the required understanding. Detailed
                                                     communication plans are key to this – with
Comprehensive shared strategy and plans              specific methods of communication being
for implementation as a whole                        developed to mitigate risks (across the full
It became evident in the early stages of the         spectrum, individual, team, organisational and
overall priority project that the development of     stakeholder) and which are threaded into the
local 18 week strategy hadn’t been addressed in      organisations strategic plan.
any meaningful way. This is demonstrated by the
fact that the priority project membership            Robust project management
reduced by 40% over the six months to                This requires highly visible leaders, a can do
December 2007 with the root cause for this           attitude and a willingness to challenge existing
drop off being the lack of an appropriate            norms.
mandated local strategy and implementation
plan.



                                                                      www.improvement.nhs.uk/heart
8       18 Weeks Whole Pathways



        Involvement with the project has helped us get the DGH and

    ?   the tertiary centre to understand what’s important for each
        organisation, and get the clinicians together to decide and
        agree what should be done at each part of the pathway.
        Julie Juden, Service Development Manager, Frimley Park Hospital NHS Foundation Trust.


        Develop robust project management routines –
        ensure senior clinical/management involvement
        and ensure that projects become the business of
        the board. Ensure that the problem and scope of
        the project have been well described with data
                                                                           patient waits. While a great deal of data exists
                                                                           within organisations, this data can be
                                                                           fragmented, un-validated, activity focused and
                                                                           contained on separate, supplemental databases
                                                                           (such as PRISM, TOMCAT) often managed by
                                                                                                                            ?
        (ditto the goal) and ensure that the ‘work before                  different departments.
        the work’ has been completed to assess the do
        ability of the project.                                            A review of all existing data collection systems
                                                                           and databases with an aim to moving towards a
        Develop affective:                                                 strategy that enables these systems to add
        • Project teams ensuring appropriate team                          greater value by integrating with existing
          members with the requisite information to                        systems should be contemplated as a driver for
          allow them to buy in and commit to the                           change. Consideration should be given to who
          project. Commissioner involvement/                               manages these separate data sources; use of a
          communication and finance involvement has                        common; user-friendly language across systems;
          become a prerequisite (particularly with regard                  linking and tracking patient episode data across
          to tariff, contract or organisational budget                     (and within) organisations using unique
          changes). Patient and carer involvement                          identifiers (NHS or HES identifier); linking to
          within the project to capture experience                         diagnostic data sources.
          encouraging patient led redesign
        • Communication and project risk mitigation                        PAS system developers should be involved at an
          plans                                                            early stage to consider additional field
        • Measurement and data collection plans and                        requirements or reusing of redundant PAS
          understand process performance (SPC) and                         screens. However, some of the initial and
          Demand and Capacity measures. Set baselines.                     ongoing data collection will require manual
          Process map and collect Voice of the customer                    intervention and will need to be resourced
          data.                                                            appropriately. The work will be intensive and
        • Ensure that solutions have been subject to                       require input from all staff groups within and
          pilot testing and have been subject to some                      across sites related to the specific pathway of
          form of Failure Mode Effects Analysis1                           care.
        • Introduce process control routines/
          dashboards and appoint a process owner                           It is important to understand the ‘real’ demand
          whose role it is to ensure that new processes                    and capacity (as opposed to just the activity) of a
          remain in control and that corrective action is                  service to enable improved service planning
          taken as appropriate.                                            through modelling and gap identification.
        • Maintain project visibility – publish learning
          and successes no matter how small.                               Note that significant progress has now been
                                                                           made in the development and roll out of
        Examples of these are available on the                             processes and protocols that support
        NHS Improvement System at                                          information that follows the patient through
        www.improvement.nhs.uk/improvementsystem                           their pathway. This includes solutions to the Inter
                                                                           Provider Transfer Administrative Minimum Data
        IT system architecture and data                                    set together with the transfer of clinical data
        collection within 18 weeks                                         and diagnostic imaging. Case studies describing
        One of the key success factors of any 18 week                      these initiatives are currently being worked up
        piece of work has been to establish good data                      and will shortly become available on the
        collection to accurately measure the reality of                    Improvement system.




        1
         Failure Mode Effects Analysis ensures that processes have been subject to stringent failure and risk mitigation tests


www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                      9




Moving forward

Sustaining 18 week cardiac pathways                            Collaborative working between NHS
2008/09 and beyond                                             Improvement (Heart Improvement Programme)
The 18 week stock take2 conducted across all                   and the DH 18 week team together with other
cardiac networks together with experiences                     key stakeholders will continue to progress the
gained from the 18 week priority projects (and                 development of practical sustainability
cancer 31/62 day waits ) has identified                        resources that will complement the existing suite
sustainability as a major issue in holding 18                  of resources found on the NHS Improvement.
weeks post December 2008.                                      website.

The reasons behind this are complex but for
the purpose of this document can be
summarised as:                                                     The peer support meetings have
• Lack of cohesive local implementation plans
  and strategy for 18 weeks
• Lack of any real redesign and a reliance of
  doing ‘more of the same’ rather than
  focussing on redesign across the whole
  pathway
                                                             ?     been extremely valuable for all
                                                                   sorts of reasons. I’ve been able
                                                                   to help them to a certain extent
                                                                   with my clinical input but
                                                                   equally I have learnt an
• Increased operational and/or organisational
  pressures, especially in light of numerous ‘vital
                                                                   enormous amount from the
  signs’ identified in the Operational                             projects themselves they have
  Framework                                                        really been excellent and I’ve
• Clinical engagement
• Hugely variable IT system, data and patient                      been able to take home lots of
  tracking capability                                              the ideas and implement them
• Contingent capacity where process efficiency
  has been optimised.
                                                                   locally and that’s been very
                                                                   helpful for me personally and
In response to the factors outlined above the                      my directorate in moving
current 18 Week Whole Pathway Priority Project
will extend its focus to the approaches required                   towards delivery of the 18
to deliver sustainable cardiac pathways post                       week project.
December 2008. The developing initiative will




                                                                                          ?
be supplemented with a spotlight on cardiac
                                                                   Dr Gordon Murray, Consultant Cardiologist and
surgery (elective and non elective).
                                                                   National Clinical Lead, NHS Heart Improvement
                                                                   Programme
The intention will be that experienced members
of the 2007/08 Diagnostics Priority Project will
join this revised project in order to fully capitalise
on the experience and expertise developed
through the existing demonstrator sites.
Additionally it is anticipated that there will be a
requirement to develop a number of new
demonstrator sites as existing projects draw to
an end.


2
 Cardiac Network 18 week stock take December 07 – a comprehensive strategic and operational assessment of approaches to
the target covering both current and planned activities within 26 Network health economies. For more information follow the
link on the NHS Improvement System.



                                                                                    www.improvement.nhs.uk/heart
10      18 Weeks Whole Pathways




        Project Summaries




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways               11




Redesigning the Whole Patient Pathway for Cardiology Patients
Lancashire Teaching Hospitals NHS Foundation Trust
(Royal Preston Hospital and Chorley District General)
Lancashire & South Cumbria Cardiac Network

Issues to address
After mapping the various pathways for
angiography, cardioversion and pacemaker
implantation it was clear that complete redesign
of cardiology pathways were needed. Without
this patients would not be able to be treated
within 18 weeks, particularly for those who
were referred on for tertiary care.

Baseline position
• 12 week waits for first cardiology
  outpatients (OPD)
• Separate waiting list for cardiac diagnostics
  often commenced after first OPD
• Frequent cancellations of elective
  cardioversions if no available coronary care       Key results/outcomes
  unit (CCU) bed or available anaesthetist           • Referral to treatment times down to eight
• No waiting list for cardioversion existed            weeks
• Frequent cancellations on pacemaker lists as all   • All patients seen in one-stop cardiology clinics
  patients required beds on Friday                   • Dedicated sessions created for cardioversion
• Considerable administrative delays for letters       with managed waiting list
  and referrals.                                     • Utilisation of catheter laboratory up 30%
                                                     • Diagnostics pre selected by clinical
Actions taken                                          physiologists to ensure results available for
• Established one-stop clinics for all four            first OPD
  cardiologists                                      • Treatment plan given and catheter lab
• Redesigned diagnostic pathway                        booked at first OPD.
• Located regular venue and anaesthetic sessions
          for cardioversion                          Contact information
• Changed pacemaker booking from single list         Kathy Blacker
  to end of angiography list to reduce               Kathy.blacker@lsccn.nhs.uk
  cancellations due to lack of available beds
• Trained clinical physiologists and receptionists
  to access Choose and Book and
• Gained agreement from cardiologists for
  clinical physiologists to pre select diagnostics
• Changed booking system for catheter lab
  procedures.




                                                                      www.improvement.nhs.uk/heart
12      18 Weeks Whole Pathways




        Angiography ‘Fast Works’ Rapid Redesign Project
        King’s Mill Hospital
        Trent Cardiac Network

        Issues to address
        Waiting times for diagnostic angiography were
        found to be too long, with the waiting times
        between cardiologists showing high levels of
        variation.

        Additionally, the productivity of the catheter lab
        was not optimal with significant list size
        variation between consultants; unused slots
        during angiography sessions; under-utilised
        nursing capacity allocated to the catheter lab.
        Without improved productivity/increased activity
        in the catheter lab, the wait time would not
        reach the trust target figure.

        Baseline position                                    available via the Improvement system website.
        Waiting time for a diagnostic angiography took       A process map of the existing pathway was
        on average five weeks, with a range of 0 weeks       developed and agreed and a large amount of
        to 18 weeks (data for five months March to July      data analysis was carried out, presenting
        2007).                                               evidence of where there was some room for
                                                             possible service improvements.
        Productivity of the catheter lab evidenced 75%
        utilisation over 12 months (May 2006 to May          A patient survey was also conducted to gather a
        2007).                                               baseline of the existing angiography service
        The list size of each session showed a variation     provided at King’s Mill Hospital from a patient
        ranging between one to six angiography               perspective. A total of 50 patient names were
        procedures per list, with a mean of four.            selected at random to be included in the survey,
                                                             all of who had undergone angiography at King’s
        Based on a target minimum of four patients per       Mill Hospital within the previous six months.
        session, there were found to be 244 unused           The survey received an 86% response rate and a
        slots over 12 months to May 2007 and 44 lost         detailed report produced outlining the findings
        lists over 12 months due to under-utilised           is available via the Improvement website.
        nursing capacity allocated to the catheter lab.
        The throughput of the Lab in May 2007 was on         Following the work of the time-limited project
        average 12 patients per week, based on four          group, a two-day event was held inviting
        angiography lists per week.                          colleagues working within the trust, who had
                                                             involvement in some way with patients requiring
        Actions taken                                        angiography. Problems identified by the fast
        A ‘Fast Works’ rapid redesign project group was      works project group were considered and
        established, comprising representation from          recommendations/solutions agreed by attendees
        clinical and non-clinical staff working within,      at the event. At the end of the two days, these
        or supporting the running of, the catheter lab.      recommendations and related actions were
        An independent fast works facilitator and a          presented for approval to a panel, comprising of
        member of the NHS Heart Improvement                  the Trust Chief Executive, Director of Nursing,
        Programme led the project group, supported by        Consultant Cardiologist, Cardiology Manager,
        the Trent Cardiac Network. Nine (two hour)           and the Divisional Manager. A number of
        weekly meetings of the group were held, during       recommendations were approved by the panel,
        which 'problems' with the existing part of this      which have subsequently led to a number of
        patient pathway were identified. A Project           service improvements.
        Charter was developed by the group which
        outlines the project in more detail and is


www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                 13




Key results/outcomes                                  • Pre-assessment, including gaining of patient
Several service improvements have been                  consent, is now carried out during the
implemented since completion of this project,           patients’ OP clinic appointment, meaning
which have led to a reduction in waiting times          patients are available to fill slots at short notice
for angiography to a maximum of six weeks as            (e.g. cancellations or additional clinics), which
at February 2008. Productivity and activity             has led to minimised lost slots
within the catheter lab has also increased,           • Improved and standardised referral process,
resulting in a minimum of four patients now             with enhanced referral forms. Proposal for all
being booked per list, often having a fifth or          referrals for angiographies to be centrally
sixth patient booked in as emergencies. Finally,        coordinated by the Central Waiting List Office
the number of lost angiography lists has              • Development of new patient information
significantly decreased due to the introduction         leaflet
of ‘flexible rotas’. Over a recent six week period,   • Introduction of a ‘catheter lab coordinator’
nine out of 12 lists were covered, which would          role to ensure communication is optimised
previously have been ‘lost slots’. This equates to      within the lab, allocate daily responsibilities,
an additional 36 routine angiography procedures         ensure things run to time etc
being scheduled during this time period, which        • Increased turnaround times within the
prior to the project would not have been carried        catheter lab due to new pre-assessment
out.                                                    process, flexible working patterns of staff,
                                                        improved communication within the lab,
A summary of the changes that have resulted in          improved audit systems
these developments so far are:                        • Introduction of ‘flexible rotas’, resulting in
                                                        catheter lab slots being utilised to maximum
• All angiographies are now fully booked from           capacity, with on-calls and leave covered by
  OP clinic appointment                                 consultant colleagues wherever possible
• Introduction of ‘partial pooled lists’ for          • Development and introduction of a written
  angiographies, which has reduced patient              competency based training package for
  waiting times and decreased the variation in          cardiac nurses has increased the skill mix of
  waiting times between cardiologists (NB To            nursing staff within the catheter lab, enabling
  ensure continuity of care, the treatment plan         cross-cover and increasing utilisation of
  remains under the patient’s main consultant, it       nursing capacity within the lab.
  is purely the angiography procedure that is
  pooled)                                             Further examples detailing the ‘Fast Works’
• An enhanced post angiography process means          approach to rapid redesign project involving
  that, wherever possible, all results are            Thames Valley Cardiac Network angiography
  discussed with the patient on the same day as       and booking waits, and Leicestershire,
  the angiography (with their main consultant)        Northamptonshire and Rutland Cardiac Network
  and next steps agreed                               reductions in unnecessary follow ups project can
                                                      be found via the Improvement System.

                                                      Contact information
                                                      Jo Evans
                                                      Joanne.evans@sfh-tr.nhs.uk




                                                                        www.improvement.nhs.uk/heart
14      18 Weeks Whole Pathways




        Leicester Northamptonshire and Rutland Cardiac Network and
        University Hospitals Leicester 18 Week Whole Pathway Project
        University Hospitals of Leicester (3 sites)
        Leicester Northamptonshire and Rutland Cardiac Network

        Issues to address
        The time taken between original GP referral to
        date of procedure in cardiac surgery exceeded a
        year, for patients being treated within cardiology
        by PCI the journey time was around 28 weeks.
        This extensive wait was similar whether the
        patient had their entire journey within the
        tertiary centre or if the patient was initially
        investigated at a secondary centre and then
        referred onwards.

        Baseline position
        A retrospective baseline audit took place in June
        2006 looking at 50 sets of patient notes
        including all treatment options and referral
        sources and repeated in October 2007. The            Actions taken
        common bottle necks were identified as:              The project was launched by raising awareness
                                                             of the current bottlenecks and demonstrating
        • The administration time between actions,           the current actual referral to treatment times
          which progress the patients pathway took an        (RTT), in comparison with the target. In addition
          average of four weeks. For example, awaiting       raising awareness of 18 week wait measurement
          typing and acceptance of referral letters or       and associated rules. This was implemented
          receiving diagnostic reports.                      through posters, meetings and contact with
        • A 12 week wait for clinic with only a              key staff culminating in a well attended
          proportion of diagnostics being pre ordered.       multidisciplinary event on 28 September 2006
          Poor co-ordination of diagnostic being             where members agreed how to progress
          completed before the first outpatient              towards an 18 week wait.
          appointment and results being made available
          on time.                                           Process mapping took place along with demand
        • Diagnostics wait of 17 weeks (max) which           and capacity calculations for each individual area
          didn’t always include the reporting time.          of delivery along all of the cardio respiratory
        • A high percentage of patients were going           patient’s pathways. This information quantified
          around the outpatient and diagnostics loop         which bottlenecks would have the highest
          two to three times before the correct              impact on delivering 18 weeks and indicated the
          information was assembled for clinical staff to    order in which 18 week wait changes should be
          make a diagnosis and progress to treating the      addressed.
          patient. This translated in some cases to a
          delay of as much as three to six months from       The work was then divided into manageable
          original referral to initial diagnosis and a       stages and staff assigned to working groups,
          treatment plan being agreed.                       with clinical, service improvement and a
        • The capacity to admit patients for treatment       managerial lead. These groups looked at the:
          was stretched in addition initiatives were used
          to meet reductions of waiting time targets.        •   Primary care interface
                                                             •   Outpatients and diagnostics
                                                             •   Chest pain and valve treatment
                                                             •   Arrhythmia treatment
                                                             •   Paediatric and congenital
                                                             •   Respiratory
                                                             •   Thoracic pathways.




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways               15




To ensure continuity and cohesive working            Initially the changes would be implemented in
between the groups a steering group formed to        adult cardiology because of the large patient
oversee progress chaired by the directorate          base and then tailored where necessary and
general manager.                                     rolled out to other specialties and sites.

Each group set specific goals, the example           Key results/outcomes
described in more detail here is the highest         The clinical annual and study leave policy was
impact area, identified as the outpatient and        updated and re established with clear processes
diagnostics portion of the patient pathway. The      and monitoring. This meant that delivery areas
aim was to deliver - referral to decision to treat   were able to plan and protect capacity for the
(or other outcome), inclusive of the outpatient      next four weeks without change and the
appointment and basic cardiac diagnostic testing     associated delays or rescheduling.
in less than four weeks.
                                                     The waiting time for diagnostics has been
This deliverable was further quantified as:          reduced to six weeks through waiting list
                                                     initiatives, validation, demand management and
• Wait for an outpatient appointment of less         recruitment drives. The reduction is continuing
  than four weeks                                    down to two weeks, supported by ongoing
• Deliver the majority of same day diagnostic        demand and capacity work. The network has
  testing with a maximum wait of two weeks           trained operational staff to calculate demand
• Electronic diagnostic test management and          and capacity within their own areas. Tests are
  shared cross site waiting lists                    booked upon request reducing the
• Single assessment clinics                          administrative workload and providing patients
• Reduce the number of follow-up patients to         with a planned date.
  release outpatient capacity
• Partially book follow-up patients to reduce        A partial booking of follow-ups system has
  outpatient wastage                                 been developed using the example of the
• Protected capacity for a minimum of four           Sherwood Forest Hospital pilot (outlined on
  weeks through a clinical annual leave policy       page 22 - Partial Bookings of Follow-ups.
• Deliver preadmission in clinic on day of           Implementation was delayed due to trust wide
  decision to treat including fully booking the      18 week wait planning but will be delivered in
  admission date.                                    May 2008. It is expected to reduce the number
                                                     of wasted appointments which will release
                                                     capacity for the single assessment clinics.

    For the network as a whole                       A change to the diagnostics IT system is under



?   the different trusts are now
                   ?
    looking at pre planning
    tests as much as they
    possibly can.
                                                     way; this will enable more staff to access
                                                     diagnostics information about appointments
                                                     and results. It will deliver better co-ordination
                                                     between tests and outpatient appointments but
                                                     also allow the diagnostics waiting lists to be
                                                     shared across the three delivery sites. This
                                                     reduces the waiting times and improves equity
                                                     of access.
    Elaine Kemp, Cardiac Service Development
    Manager, Leics, Northants & Rutland Cardiac
    Network




                                                                      www.improvement.nhs.uk/heart
16      18 Weeks Whole Pathways




        Preadmission services have been redesigned to         The changes at Leicester are being supported
        deliver medical preadmission on the day of the        through the cardiac network by sharing learning
        patient’s outpatient appointment. With the            from trusts such as Kettering, who have
        option of further psychological support and           implemented outpatient and diagnostics
        information either on the same day or later           changes, Sherwood Forest with their successful
        before admission. This means patients are             partial booking and in turn the learning at
        prepared earlier for admission reducing               Leicester will help support the Northampton
        cancellations. It is planned to fully book            team in developing their single assessment pilot.
        admissions once the preadmission changes have
        been embedded.                                        Contact information
                                                              Elaine Kemp
        Single assessment clinics have been trialed over      Elaine.Kemp@northants.nhs.uk
        17 clinical sessions with 84 new and 230 follow-
        up patients. Most tests were pre planned
        however on the day 54 patients were put
        forward for an additional 63 diagnostics; echo,
        ETT and Tapes. All patients were given the
        opportunity to stay and have tests on the day or
        return at a later date, only one patient declined.

        40 out of the 63 diagnostics were completed on
        the day; those not done were due to the timing
        of the diagnostics working day compared to
        clinic appointments which can be resolved.
        16 out of the 54 patients using the single
        assessment clinic were discharged and five
        patients were given a decision to treat of
        admission. Single assessment clinics will deliver a
        reduced waiting time for patients, less visits to
        the hospital and additional capacity in clinic.

        Implementation of all the above changes will
        deliver the aim of a four week wait, the project
        unfortunately has overrun due to operational
        pressures and several changes in the trust
        management team. It is projected that single
        assessment clinics, preadmission changes and
        partial booking will be implemented before
        June 2008.

        The less quantifiable change which will help
        deliver 18 weeks is the move from a culture in
        diagnostics and other delivery areas, of using
        waiting lists to flex the amount of work
        delivered to match the capacity which is
        available. Now the capacity is being flexed to
        match the amount of work required to deliver
        the waiting time on a shorter pathway.




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways               17




18 Weeks Whole Pathway - Sussex
Eastbourne District General Hospital, Royal Sussex County Hospital
(part of Brighton and Sussex University Hospitals NHS Trust), Hailsham
Practice Based Commissioning (PBC) Cluster
Sussex Cardiac Network

Issues to address
• Need to achieve 18 week target for cardiology
  and cardiac surgery patients from the
  Eastbourne area. Delays and bottlenecks were
  contributing to the target not being met.
• Need to demand manage referrals from
  primary care to sustain 18 week target when
  achieved.
• Waiting times had hidden elements in them as
  GP to acceptance on waiting list was not
  being recorded.

Baseline position
At July 2007:
• Maximum wait for new outpatient
  appointment was 11 weeks                            Key results/outcomes
• Maximum wait for diagnostic echo was 26             • At EDGH 85% of all patients are being
  weeks                                                 referred and treated within 18 weeks
• Maximum wait for angiogram was 19 weeks.            • New referral pathway has been rolled out to
                                                        other referring DGH’s.
Actions taken
• Extra activity to address backlog                   Cardiac surgery waits are reducing and they now
• Following an assessment of demand and               include the hidden waits.
  capacity extra investment was made into
  equipment for 24 hour testing                       Contact information
• Development of a triage clinic in secondary         Lisa Fairclough
  care to triage referrals from primary care. Aim     Lisa.fairclough@bsuh.nhs.uk
  is to reduce unnecessary consultant outpatient
  appointment, facilitate direct access to
  diagnostic investigations e.g. angiography and
  refer patients back to GP with a management
  plan if no intervention required
• Develop a proposal for a community
  cardiology service in one area of Eastbourne.
  Service to be run by a GP with an interest in
  cardiology and clinical governance
  arrangements support from secondary care.
  Aim is to for all cardiac referrals to be sent to
  the service and following assessment, the GP
  will either refer on to secondary care
  immediately or undertake some diagnostics
  tests in community and then refer back to
  original GP with a management plan or refer
  onto secondary care.
• Process mapped the referral pathway for
  cardiac surgery. A new pathway was
  developed. All referrals are now faxed or
  emailed the same day as the diagnostic
  investigation. Referral is actioned on receipt by
  the waiting list office and an OPA made within
  48 hours and occurring within two weeks.


                                                                      www.improvement.nhs.uk/heart
18      18 Weeks Whole Pathways




        Cardiac Surgery: Referral To Treatment in 12 Weeks (Average)
        Frimley Park Hospital
        St George’s Hospital
        South West London Cardiac Network

        Issues to address
        According to an 18 week pilot study conducted
        at St George's Hospital in 2006 by the South
        West London Cardiac Network, patients (n=5)
        referred from Frimley Park Hospital waited up to
        54 weeks from initial referral (18 week clock
        start) until treatment at St George's Hospital
        (clock stop). Data collected since the project
        started indicated that average referral to
        treatment (RTT) times was about 30 weeks on
        average (n=24).

        In addition, anecdotal reports of poor
        communication between the two organisations,
        one indication of which was the poor
        performance in terms of sending discharge          A comprehensive cardiology redesign workshop
        summaries to the secondary centre after patients   was held at Frimley Park Hospital in June 2007.
        had completed their course of treatment at the     As a result the following changes were made:
        tertiary centre. Also, there were problems in
        terms of administrative process delays (with       (1) Direct booking for angiography and pre-
        patients sometimes being ‘lost’ in the system),        assessment from outpatient clinics was
        and moving patients to the next stage of               instigated
        treatment.                                         (2) Rapid follow-up slots and more one-stop
                                                               clinics were introduced
        Actions taken                                      (3) The trust admissions team was made
        The project started officially on the 20 March         responsible for booking all diagnostic tests
        2007 at the first steering group meeting and is        and procedures (treatments) in the catheter
        due to end on the 31 March 2008. Below is a            laboratory
        selection of improvements made to date.            (4) An induction to cardiology was introduced
                                                               for junior doctors at each rotation
        From March 2007 demand and capacity analyses       (5) Diagnostic waiting times are monitored on a
        were undertaken at Frimley Park Hospital and           weekly basis
        strategies were identified to reduce the backlog   (6) The multidisciplinary team (MDT) meeting
        of patients waiting for diagnostic tests,              was redesigned so that all necessary
        outpatient appointments and inpatient                  diagnostic tests are performed before the
        admissions. Work was also done to ensure cross-        patient is seen jointly by the cardiologist and
        cover by staff at critical steps in the pathway,       surgeon. Test results and treatment options
        and to identify the flow of patients and time          are discussed and a treatment plan agreed
        requirements for each component of the                 with the patient. A dedicated administrator
        pathway.                                               is responsible for ensuring the efficient
                                                               coordination of the joint cardiac clinic and
        At the first steering group meeting an elective        handling onward referrals to the tertiary
        cardiac referral form was devised and agreed.          centre.
        Frimley Park Hospital started using the form in
        May 2007 and it has since been through several     Mapping of clinical and administrative processes
        modifications, most recently to reflect the        has taken place at St George’s Hospital over the
        publication of DSCN 44/2007 in December            lifetime of the project, and systems put in place
        2007.                                              to facilitate the reliable transfer of referral data
                                                           and early booking of patient appointments.




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                19


The cardiac network decided to do a joint project between two main


?
hospitals to look at the cardiac surgery pathway. We started off from a
baseline of 32 weeks on average, that’s the time from when the patient is
referred by the GP until they actually have their surgery in a tertiary hospital.
Adrianne van Heerden, Service Improvement Manager, South West London Cardiac and Stroke Network

                                                                                                            ?


Plans have been initiated to pre-assess all cardiac     trust to admit patients on the day of their
surgery patients so that they can be admitted on        procedure, rather than the day before, thereby
the day of surgery rather than the day before.          saving valuable bed days.
An 18 weeks training workshop was held for
cardiac secretaries at St George’s Hospital, and a      St George's Hospital performs around 1,150 cardiac
process will be trialled where they will email          surgery procedures per year, and could therefore
discharge summaries and 18 week referral forms          potentially save this number of bed days per year.
(with clock stop dates, where appropriate) back         As patients are better worked up at the secondary
to the referring organisations.                         centre in advance of transfer for surgery, we expect
                                                        the number of surgery cancellations to decline, as
Key results/outcomes                                    patients unfit for surgery will not be transferred.
Patients are having their initial contact with a
consultant much sooner than before the project          Since tertiary care clinicians can access diagnostic
started (now within four weeks), and the                images at the secondary centre directly via NHS
diagnostic tests required are now sometimes done        extranet, extra slots for echos, angiograms and
on the same day, or at most within a few weeks of       dopplers will become available at the tertiary centre
request. (The internal target set is two weeks for      as the need for repeat diagnostic tests are reduced
diagnostic tests. This is being achieved in most        in number.
instances, and plans are being put in place to
ensure these waiting times can be sustained.) This      Both Frimley Park Hospital and St George’s Hospital
allows the clinician to make a diagnosis much           are aiming to complete their part of the cardiac
sooner and develop a treatment plan with the            surgery pathway in an average of six weeks, giving a
patient. Patients are better informed about the         total journey time of 12 weeks (on average). Data
surgery pathway and the number of visits they           analysis to date suggests that the average referral to
need to make to St George’s Hospital has been           treatment (RTT) time has reduced from 32 weeks (on
reduced by redesigning the multidisciplinary team       average) to 9.4 weeks (on average) since the project
meeting at Frimley Park Hospital. We believe this has   started. This has had a positive effect on staff
resulted in a better patient experience and we will     morale, as they can see the results of their hard
give patients the opportunity to feed back by means     work and experience the satisfaction of providing an
of a patient questionnaire in the near future.          improved patient experience.

The redesign work has also benefited the NHS            Contact information
organisations involved. St George's Hospital is         Adriaan van Heerden
moving to a position where all cardiac surgery          adriaan.vanheerden@stgeorges.nhs.uk
patients attend pre-assessment. This will enable the

                                                                          www.improvement.nhs.uk/heart
20      18 Weeks Whole Pathways




        Derby Hospitals Angioplasty Pathway Project
        Derby Hospitals NHS Foundation Trust
        Trent Cardiac Network

                                                                          Actions taken
                                                                          A planning workshop, followed by two further
                                                                          workshops, was held with attendance from
                                                                          cardiologists, cardiac clinicians and other clinical
                                                                          and non-clinical colleagues working in or
                                                                          alongside the catheter lab. The workshops were
                                                                          led by the Trent Cardiac Network and resulted in
                                                                          the development of a robust action plan, which
                                                                          was taken forward and implemented by all
                                                                          relevant members of the cardiology team
                                                                          working in the trust.

                                                                          To support the progress of implementing the
                                                                          action plan, ad hoc meetings were held as
                                                                          necessary to focus on moving specific issues
                                                                          forward. This included meetings with IT,
                                                                          cardiology secretaries, cardiology managers,
                                                                          attending the cardiologists’ monthly meeting
                                                                          etc. The cardiac network maintained a regular
                                                                          record of progress against the action plan
                                                                          throughout the project period.

        Issues to address                                                 In addition, at the start of the project nine sets
        The trust 18 week steering group collected data                   of patient notes were scrutinised to map actual
        to determine the high priority areas to focus on                  patient pathways. Findings from this work
        with regards to ensuring compliance with the 18                   reflected the issues raised during the process
        weeks initiative. The angioplasty pathway was                     mapping exercise, highlighting key areas for
        identified as one of these key areas, having a                    improvement. A further 12 sets of patient notes
        comparatively low achievement rate in respect of                  were again scrutinised at the end of the project
        the 18 week target.                                               to provide a robust comparison of where service
                                                                          improvements to the patient pathway had been
        After initially process mapping the patient                       made.
        pathway, it was identified that activity relating to
        referrals to or from the catheter lab was one of                  Key results/outcomes
        the key areas for concern.                                        • Several service improvements have been
                                                                            implemented since completion of this project,
        Baseline position                                                   which have led to a reduction in waiting times
        Catheter lab waits peaked at a maximum during                       for angiography and PCI procedures,
        early August 2007, around the beginning of the                      consequently reducing the overall length of
        project, with patients waiting up to 17 weeks                       pathway for this set of patients
        for angiography and up to a further 15 weeks                      • As at the beginning of March 2008, the
        for their angioplasty procedure.                                    maximum wait time for angiography from
                                                                            date of listing had reduced to six weeks, with
        As at January 2007, 44% of angioplasty (PCI)                        five weeks being the maximum for PCI. The
        patients were recorded as receiving treatment                       percentage of patients being treated by PCI
        within 18 weeks of initial referral*. This                          within 18 weeks of initial referral increased
        instigated the establishment of this project.                       to 65%

        * Using most accurate data available at the time, acknowledging limitations of existing IT systems in
        recording and reporting 18 week clock statuses.




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                 21




• The changes that supported and influenced           • Introduction of outcome forms in the
  the improvement of the angioplasty pathway            catheter lab, recognising that clocks could
  at Derby include:                                     potentially start, stop or keep ticking at
  • Clinical and non-clinical engagement from           point of angiography. This supports more
    the outset, including consultant                    accurate recording of RTT data
    cardiologists, managers, nurses and admin/        • Robust audit, monitoring and internal
    clerical staff. All members took ownership          reporting processes re waiting lists.
    of relevant issues / actions which strongly
    supported the success of the project.            Contact information
  • Equity for patients requiring angiography        Jo Evans
    (removed inappropriate use of ‘urgent’ from      Joanne.evans@sfh-tr.nhs.uk
    RACPC and individual consultants, which
    resulted in more appointments becoming
    available for the 'routine' referrals and,
    therefore, these could be seen more quickly)
  • Admin delays removed for ‘discussion
    patients’ wherever possible when
    interventionalist on site. Most cases are now
    discussed and treatment plans agreed
    directly with the interventionalist working on
    that particular day, rather than awaiting a
    monthly meeting or writing to a specific
    consultant for opinion
  • Improved post angio process – patient letter
    template developed for those patients
    whose treatment plan cannot be agreed on
    day of angiography. Removes the need to
    bring the patient back for follow-up
    outpatient appointment just to inform them
    of the outcome (reduces length of patient
    pathway and frees up follow-up outpatient
    appointments)
  • Raising registrars’ awareness of 18 weeks
    has led to improved efficiency in reviewing
    of diagnostic results process - now checked
    a minimum of twice a week as opposed to
    previously checking once a month
  • Retraining of staff (both internal and
    external to the trust) to ensure that new
    referrals for OP and/or diagnostics are
    correctly addressed and delivered,
    consequently reducing administrative delays
  • Exercise tolerance test (ETT) request forms
    updated – enable direct referral for angio
    following positive ETT (removes the need for
    patients to attend outpatient appointment,
    again reducing the length of patient
    pathway and freeing up outpatient
    appointments)




                                                                     www.improvement.nhs.uk/heart
22      18 Weeks Whole Pathways




        Tertiary Referrals Pilot Project for Cardiac Services
        King’s Mill Hospital
        Nottingham University Hospitals
        Trent Cardiac Network

        Issues to address
        The national Inter Provider Transfer Admin
        Minimum Data Set (IPTAMDS) was developed to
        support the efficient management of patients
        whose pathways involved an inter-provider
        transfer, in particular facilitating the transfer of
        the necessary data to enable receiving providers
        to meet their mandatory Referral to Treatment
        (RTT) reporting requirements. Trusts were
        advised that implementation of the MDS would
        be mandatory from 1 January 2008.

        Locally, it was recognised that preliminary work
        needed to take place in order to ensure
        sufficient and accurate collection, recording and      ‘accurate as possible’ information using the data
        transfer of the MDS information. Work needed           available on the existing PAS electronic database
        to take place to identify:                             or manually looking through patient notes.

        • Where the relevant RTT data could be found           Actions taken
        • The ease of this data collection                     A specific time-limited project group was
        • Who would be best placed to complete the             established, with representation from Sherwood
          MDS forms/receive completed MDS forms                Forest Hospitals NHS Foundation Trust (SFHFT),
        • How they would be best transferred across            Nottingham University Hospitals (NUH) and Trent
          sites, for example, electronically, by post, fax     Cardiac Network. Members of the group agreed
          etc.                                                 project aims and objectives including how the
                                                               MDS data would be collected transferred and by
        The trusts would also need to move away from           whom, along with the key outcomes to be
        focusing on the previous ‘stages of treatment’         monitored and reported on at the end of the
        and individual hospital responsibilities, working      project. Data monitoring commenced on 1
        together to provide one smooth patient focused         October 2007 for two months, with a final
        pathway of care.                                       review process in December 2007. Regular
                                                               communication was maintained and project
        Baseline position                                      group meetings continued throughout the
        Prior to the publication of the MDS, there was         project period.
        no standard referral information specified for
        inter-provider referrals between these hospital        The project focused solely on those patients
        sites, particularly with regards to data relating to   being referred from King’s Mill Hospital (KMH)
        the 18 week whole patient journey. The                 (acute trust) for tertiary cardiac care at
        individual trusts and hospital sites worked            Nottingham University Hospitals (NUH) (Tertiary
        towards their specific targets for their individual    Centre). All referrals were captured via the
        stage(s) of treatment and did not provide any          catheter lab at KMH following angiography and
        related waiting time or complete pathway               included only those being referred on for
        referral data when transferring to another             selected treatment, namely angioplasty (PCI) or
        provider.                                              surgery (CABG). Patients referred to the tertiary
                                                               centre for diagnostics were not included in this
        Because the above data was not being provided          project.
        across sites, specific 18 week pathway
        information could not be monitored for this set        The pilot focused on the specific stage within
        of patients. Also, existing IT systems did not         the patient pathway, when the patient’s care
        provide the facility to enable such information to     was transferred from the secondary to tertiary
        be recorded accurately. Trusts were capturing as       care centre. It was agreed that any issues


www.improvement.nhs.uk/heart
18 Weeks Whole Pathways              23




 Example of an 18 week pathway




identified at either side of this should be            transfer of the MDS and clinical referral
addressed locally by the relevant trust outside        information, method of collection of robust RTT
the project group.                                     data, dealing with referrals for diagnostics, and
                                                       ‘roll-out’ to other specialties or trusts.
In addition, members of the project group
acknowledged the local commissioning targets           The actual lengths of patient pathways, from
that were hoping to be achieved by March 2008          referral to treatment, were accurately captured
and, with this in mind, the information collected      by manually scrutinising patient notes. This
throughout the project was used to trace and           enabled key areas for any breaches to the 18
manually plot care pathways for all patients           week target to be identified and reasons for
included within the pilot project, identifying time    these delays to be addressed. Using the actual
taken between each stage of treatment and any          patient journeys that were mapped, example
related delays.                                        pathways could be developed to help provide
                                                       clarification around clock starts and stops.
Throughout the two-month project period,
27 patient pathways were monitored, with               A full report detailing the project approach,
respective MDS forms completed and                     issues, findings, recommendations and ‘roll out’
electronically transferred from KMH to NUH.            have been produced following this project and
                                                       shared across Trent Cardiac Network. Example
Key results/outcomes                                   pathways, developed as a result of plotting real
This project enabled data completeness of the          patient journeys, have also been shared across
MDS forms to be monitored, highlighting which          the network.
data requirements were difficult, or even not
available at the time of the project, for collection   As a result of the work carried out within this
(e.g. due to awaiting implementation of PAS            project, both trusts are able to use the findings
v20). A list of concerns / problems was recorded       to support implementation of the MDS across all
and all issues were fed back to the relevant trust     specialties. The project outcome also identifies
for them to locally agree next steps and action        key areas for further service development work
points, in order to address the problems and           within cardiac services, both locally and working
ensure pathways were reduced to the shortest           across provider sites, in order to achieve the 18
clinically appropriate.                                week initiative. Other trusts within the network
                                                       are also now using the project report to support
A series of recommendations was also produced,         their implementation of the MDS.
learning from any difficulties encountered as
part of the project. These mainly related to           Contact information
ensuring efficient and effective preparation and       Jo Evans
communication prior to implementation of the           Joanne.evans@sfh-tr.nhs.uk
MDS, selecting the most appropriate method of


                                                                        www.improvement.nhs.uk/heart
24      18 Weeks Whole Pathways




        Reducing Waits for Cardiac Diagnostics
        Sherwood Forest Hospitals NHS Foundation Trust
        Trent Cardiac Network

                                                           many patients waiting up to two months or
                                                           more from referral, particularly for echo. A
                                                           workshop was held with all available members
                                                           of the cardio respiratory team, using this data as
                                                           a baseline. During the workshop a process map,
                                                           reflecting the current referral to diagnostic
                                                           process, was produced, following which problem
                                                           areas were identified and suggestions for
                                                           improvement made. As a result of the
                                                           workshop an action plan was developed.

                                                           In addition, the cardio respiratory manager
                                                           worked closely with the Information Services
                                                           Department to ensure relevant referral and
                                                           waiting time data was received on a weekly
                                                           basis. This enabled the department to move to
        Issues to address                                  a more 'demand led' service, which historically
        The maximum waiting time for some of the high      had been more 'staff led'.
        volume cardiac diagnostics was found to be too
        long. In order to improve patient experience,      Significant work was carried out during
        and for patients to realistically achieve an 18    December 2007 to clear any backlog within the
        week care pathway, these waiting times needed      system. All staff training for that month was
        to be reduced in line with Trust targets, which    cancelled and clinical time maximised across the
        aimed for a maximum wait of four weeks for         department. Use of all diagnostic slots was
        any diagnostic test by March 2008.                 maximised, with the administration team
                                                           ensuring that all efforts were made to fill
        Baseline position                                  cancellations as soon as they became apparent.
        In September 2007, echocardiography waits          Any available slots in one service that had a
        were at around nine weeks, with doctor led ETT     minimal waiting list would be converted to
        maximising at 10 weeks and other high volume       accommodate another e.g. additional echo slots
        cardiac diagnostics not far behind.                if trained staff available.
        NB. Dobutamine Stress Echo’s (DSEs) were           Key results/outcomes
        recognised to be of comparatively low volume in    The maximum wait time for any cardiac
        relation to the number of referrals received for   diagnostic (excluding DSEs) as at the beginning
        other diagnostics and, although waits for this     of February 2008 had reduced to three weeks,
        test were also too long, it was agreed that this   which was actually less than the Trust target of
        area would be picked up as a separate project      four weeks.
        (currently making significant progress).
                                                           Due to the changes made within the
        Actions taken                                      department, and the cardio respiratory manager
        Data was collected from within the cardio          and team adapting to a new way of working, it
        respiratory department for the five high volume    is anticipated that this short wait time will
        diagnostics (i.e. those receiving the most         continue to be sustainable for the future. The
        referrals), which were 24hr BP, 24hr ECG, event    new systems will ensure that clinical time
        recorders, echo and exercise tolerance testing     continues to be maximised and that the
        (ETT). This data demonstrated that an average      department continues to run as a 'demand led'
        of around four weeks wait for patients was         service. Information Services now provide data
        actually being achieved for many of these          on a weekly basis, which enables the
        diagnostics, but evidenced a huge variation with   department to continue to be 'demand led'.



www.improvement.nhs.uk/heart
18 Weeks Whole Pathways       25




More flexible working within the department
and smarter working patterns enables capacity
to be maximised, with all team members now
being aware of waiting times and targets.

Cancellations continue to be filled wherever
possible by the administration staff and
compressed hours of some of the clinical staff
are worked to advantage the department, by
providing additional slots at the beginning and
end of the day for additional patients, or for
analysis and reporting work to be carried out.

In addition, the two trainee staff have very
recently qualified which has enabled capacity to
be extended. The more senior staff, who would
previously have worked to support the trainees,
are able to see patients separately whilst the
newly qualified staff can work without
supervision. The cardio respiratory assistant role
has also been expanded to provide additional
capacity within the department.

Patients are now seen much quicker following
referral for cardiac diagnostics. This means
patients, and their carers, have less time to
become anxious and are able to reach a
diagnosis much sooner than before.

This improvement has increased efficiency within
the cardio respiratory department and has led to
significantly reduced waiting times supporting
the trust's achievement of the 18 week initiative.
These reduced waits at King’s Mill Hospital have
also provided the opportunity and additional
resource to progress towards achieving similar
results in relation to cardiac diagnostic waits at
the Newark Hospital site.

Contact information
Jo Evans
Joanne.evans@sfh-tr.nhs.uk




                                                          www.improvement.nhs.uk/heart
26      18 Weeks Whole Pathways




        Partial Booking of Follow Ups
        Sherwood Forest Hospitals NHS Foundation Trust
        Trent Cardiac Network

        Issues to address                                   There were found to be 1081 DNAs over the
        Trent Project ‘Cardiac Service Improvement’         same period, from 1 December 2004 and 30
        (‘CSI’) was established as an initial response to   November 2005, with 82% of all DNAs
        the 18 week wait target, which brought              occurring from follow ups.
        together team members from Sherwood Forest
        Hospitals NHS Trust, the Trent Cardiac Network      Planned clinic capacity was running at 64%
        and the National Heart Improvement                  utilisation prior to the project.
        Programme. The project aimed to deliver
        improvements that would make a contribution         Actions taken
        towards achieving the target within cardiology      An analysis was undertaken of the reasons for
        and one of the key problem areas identified was     cancellations occurring more than six weeks
        the system for booking follow up outpatient         before the appointment date. Most were due to
        appointments.                                       the unavailability of medical staff due to annual
                                                            leave, study leave or on-call commitments. A
        The booking process for follow up patients was      new trust leave policy was consequently
        found to be inefficient, with patients being        introduced, stating that a minimum of six weeks
        “fully” booked too far in advance (3, 6 or 12       notice was required. In line with this, clinic rotas
        months). This led to high DNA and cancellation      and on call rotas were scheduled only six weeks
        rates, as well as to lots of rescheduling every     in advance, rather than for several months,
        time an outpatient clinic was cancelled or          enabling capacity to be more flexibly planned to
        reduced. The service was driven by the demand       ensure clinics were always covered and,
        for new patient appointments, leading to follow     therefore, removing the need for cancellation or
        up patient capacity being ‘squeezed’. This could    rescheduling of clinics.
        result in patients being seen long after their
        ideal review date, often further delayed by         A ‘go live’ date was set and publicity campaign
        having appointments moved forward due to            launched via local hospitals and media. Initially,
        clinics cancelled or patients forgetting their      almost 3000 appointments were cancelled,
        advance appointment and therefore not               which had been scheduled for patients in
        attending.                                          advance of six weeks. Each patient was sent a
                                                            letter explaining why their appointment had
        As a consequence, consultants were unable to        been cancelled and informing them of the
        follow up patients in a timely fashion according    process via which their next appointment would
        to clinical need. The management of these           be booked. A leaflet explaining and
        follow-up patients was not optimal and the          highlighting the benefits of the new partial
        follow up to new ratio did not use resources to     booking process was included. This process
        the maximum efficiency.                             resulted in less than 10 patient complaints.

        Baseline position                                   The partial booking system worked by patients
        Between 1 December 2004 and 30 November             requiring follow up more than six weeks in the
        2005 there were 5397 cancellation events within     future being partially booked and given a Partial
        the cardiology outpatient service. 4092 of these    Booking Information leaflet. These patients
        cancellation events occurred more than six          were added to a review list on PAS and allocated
        weeks before the appointment date. 1305 of          a review date. Six to eight weeks before the
        these cancellations occurred less than six weeks    review date a letter was sent to the patient,
        before the appointment date.                        inviting them to telephone to arrange an
                                                            appointment. Non-responders were telephoned
        The follow up ratio was at 1 new to 2.57            and if no contact was made the case was
        (including RACPC) follow ups, with a range of       referred back to the consultant for them to
        between 1:2.7 and 1:5.75.                           decide whether to discharge the patient or refer
                                                            them back to their GP.



www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                  27




Multidisciplinary slot management meetings             • By January 2007, waiting times fell despite
were held every two weeks, which contributed             increased referrals, indicating more efficient
significantly to monitoring and improving the            use of clinic capacity
efficiency of the booking process. Related             • There was the potential risk that follow-up
policies and procedures were reviewed and                ratios would increase with easier access, but
updated accordingly throughout the pilot period.         this was not the case
An electronic outpatient request form was also         • Although the percentage utilisation of clinic
introduced.                                              slots had not changed by the end of the
                                                         project (remaining at 64% utilisation), the
Key results/outcomes                                     underpinning organisation of clinics was
Demand management for clinic appointments is             improved with over bookings no longer
now driven by the total demand in the system,            occurring, a reduction in DNAs evident and
not just new patients. Those requiring a follow          fewer patients having appointments
up appointment within six weeks are generally            rearranged. The clinic volumes are more
the first call on resources, with the second call        predictable and so run more smoothly.
being for follow ups coming up to review date
(agreed boundaries are in place on what is an          The project anticipated a further positive result
acceptable variance to review date, + or –).           in that all follow up patients would be able to
Finally, the remaining capacity is pooled on           be seen when clinically appropriate and in broad
choose and book as new patient slots, with a           chronological order by the end of the project,
conversion ratio of two follow up equivalent           which would then be sustainable.
slots to one new patient. This system of slot          Unfortunately, due to numbers of patients
management now avoids under booking of                 exceeding the existing maximum overall clinic
clinics due to unfilled new slots, as could have       capacity and the pressures for new patients to
happened with the previous system.                     be seen without delay, there is currently
                                                       insufficient space in clinics to ensure that this is
The key results and outcomes from this                 always the case and, therefore, the number of
project include:                                       follow ups outstanding is higher than desired as
                                                       at March 2008. However, the way that these
• A dramatic reduction in cancelled                    follow ups are being monitored and managed
  appointments (hospital and patient driven) –         has dramatically improved as a result of the
  no follow up events cancelled more than 6            project, enabling this issue to be highlighted as a
  weeks before appointment as this is no longer        priority area and providing evidence for a
  possible. Cancellation rates also reduced for        solution to be identified and implemented by
  new appointments, from 13% in November               the trust as a matter of relevant urgency.
  2005 to 2% in September 2006.
• An increase in patient choice with regards to        To date, the project has brought many benefits
  time / date of appointment                           to both patients and staff working within the
• A 50% improvement in DNA rates was                   trust. Patients have an improved experience
  demonstrated by the end of the project,              with no cancellation of appointments and
  thought to be directly attributed to partial         improved choice of follow up date, making
  booking for follow-ups                               them feel more involved and less likely to forget
• The ability to flexibly plan capacity, with follow   about their appointment. Better use of
  up demand being the driver                           resources means patients should no longer have
• Improved cost efficiency, with the reduction in      to wait as long as before. The clinical
  volume of staff resource required to cancel /        management of patients with follow up has
  change clinics - the introduction of an              improved, with many of them now being seen
  electronic outpatient request form reduced           at a clinically appropriate time (although
  phone calls by 80 per month                          recognising the current issue outlined above).




                                                                        www.improvement.nhs.uk/heart
28      18 Weeks Whole Pathways




        Every six weeks the service has a ‘clean sheet’ in
        terms of clinic bookings and flexible use of
        capacity enables the service to be more
        responsive to the demands and be less bound by
        previous clinic booking rules. Decisions are
        made about how to allocate resources in a more
        realistic time frame.

        Reduced DNAs has led to increased capacity in
        the service. Partial booking means that the
        majority of patients, who would previously DNA,
        do not respond to partial booking, hence no
        longer take up an appointment slot and
        consequently leave this available for another
        patient to occupy. This also leads to reduced
        overall waiting times.

        Since completion of this project, partial booking
        has been introduced for many more specialties
        across the hospital trust, benefiting significantly
        more patients and supporting the trust with its
        work to achieve the 18 week target.

        Contact information
        Sue Brewin
        Sue.brewin@sfh-tr.nhs.uk




www.improvement.nhs.uk/heart
18 Weeks Whole Pathways                29




Achieving 18 Week Referral To Treatment Pathways by March 2008
James Paget University Hospital NHS Foundation Trust (JPUH), Papworth
Hospital NHS Foundation Trust, Norfolk and Norwich University Hospital NHS
Trust (NNUH), Great Yarmouth and Waveney Primary Care Trust,
Anglia Cardiac Network

We set an admissions target for


?
the team, achieving two week,
one stop-clinics. We will spread
this practice across our other
specialties.


               ?
Adrian Pennington, Chief Executive, James
Paget University Hospital NHS Foundation Trust

Issues to address
The JPUH is a small district general hospital
situated on the East Norfolk coast. It has a
population catchment area of 220,000 and
there are high levels of deprivation.

The NNUH, a neighbouring DGH offers an                 Reducing the outpatient wait was a major
angiography and pacemaker service to the JPUH          aspect of this project and a demand and
and percutaneous coronary intervention (PCI) to a      capacity study at the beginning of the project
specific group of patients. The majority of patients   revealed the size of what lay ahead.
however have to travel to Papworth, a cardiac
tertiary provider which is a 190 mile round trip.      Each consultant had:
                                                       • Different start and finish times
Cardiologists:                                         • Saw a varying number of patients
There is one full time cardiologist, one part-time     • Where middle grades were present they often
cardiologist (outpatient work only), one locum           only saw a couple of patients
and one vacancy. There is insufficient outpatient      • New slots were frequently closed to
capacity with the staffing levels as they are to         accommodate follow ups
reduce the outpatient wait to anything less than       • There was so much wasted capacity both from
two to three weeks.                                      poor utilisation of appointments and high
                                                         DNA rates that it was clear a more efficient
The JPUH has a non-invasive cardiac diagnostic           service was required urgently.
department which means that the following
diagnostics are available: ambulatory monitoring,      A follow up audit undertaken to find out the
echo, exercise tests, TOEs, Tilts etc. This            reasons why patients were being booked to
department has been very dynamic over the last         return to clinic for a follow up appointment
few years in that the manager has applied for          revealed:
funding from the SHA to take on a student
every year for the last six years, she has             • Inappropriate follow up practice
implemented an in house echo training                  • Incorrect booking of patients who should have
programme and with additional service redesign           been new not a follow up
has sustained all diagnostic waiting times at <2       • A high number of patients were being asked
weeks for over eighteen months. Our challenge            to return to discuss results of tests and then
of implementing one stop diagnostics was                 discharged requiring no further intervention or
therefore not reducing diagnostic waits but              medical treatment. This was adding a
reducing outpatient waits. The Trust could not           considerable delay in the pathway (i.e. you
afford to waste diagnostic capacity so we were           can’t stop the clock until the result is shared
unable to implement one stop diagnostics until           with the patient and the outcome agreed).
the outpatient wait almost matched the
diagnostic wait.



                                                                        www.improvement.nhs.uk/heart
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document
18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document

Mais conteúdo relacionado

Semelhante a 18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document

Lean principles to the Design of healthcare facilities
Lean principles to the Design of healthcare facilitiesLean principles to the Design of healthcare facilities
Lean principles to the Design of healthcare facilitiesBaha'eddine Takieddine
 
The best of clinical pathway redesign - practical examples of delivering bene...
The best of clinical pathway redesign - practical examples of delivering bene...The best of clinical pathway redesign - practical examples of delivering bene...
The best of clinical pathway redesign - practical examples of delivering bene...NHS Improvement
 
Learning how to achieve a seven day turnaround in histopathology
Learning how to achieve a seven day turnaround in histopathologyLearning how to achieve a seven day turnaround in histopathology
Learning how to achieve a seven day turnaround in histopathologyNHS Improvement
 
Developing and Implementing a Patient Reported Experience Measure
Developing and Implementing a Patient Reported Experience MeasureDeveloping and Implementing a Patient Reported Experience Measure
Developing and Implementing a Patient Reported Experience MeasureRenal Association
 
World stem cell and regenerative medicine conference, london – may 2013
World stem cell and regenerative medicine conference, london – may 2013World stem cell and regenerative medicine conference, london – may 2013
World stem cell and regenerative medicine conference, london – may 2013Cell and Gene Therapy Catapult
 
Going up a gear: Practical steps to improve stroke care
Going up a gear: Practical steps to improve stroke careGoing up a gear: Practical steps to improve stroke care
Going up a gear: Practical steps to improve stroke careNHS Improvement
 
Joint Working workshop
Joint Working workshopJoint Working workshop
Joint Working workshopPM Society
 
Appendicectomy national meeting
Appendicectomy national meetingAppendicectomy national meeting
Appendicectomy national meetinganeelbhangu
 
First steps in improving phlebotomy: the challenge to improve quality, produc...
First steps in improving phlebotomy: the challenge to improve quality, produc...First steps in improving phlebotomy: the challenge to improve quality, produc...
First steps in improving phlebotomy: the challenge to improve quality, produc...NHS Improvement
 
UK-Italy dementia workshop, January 2018 - Catherine Moody
UK-Italy dementia workshop, January 2018 - Catherine MoodyUK-Italy dementia workshop, January 2018 - Catherine Moody
UK-Italy dementia workshop, January 2018 - Catherine MoodyUKinItaly
 
Measuring Improvement: Using metrics and data to evaluate seven day services
Measuring Improvement: Using metrics and data to evaluate seven day servicesMeasuring Improvement: Using metrics and data to evaluate seven day services
Measuring Improvement: Using metrics and data to evaluate seven day servicesNHS England
 
Improving home oxygen services: emerging learning from the national improveme...
Improving home oxygen services: emerging learning from the national improveme...Improving home oxygen services: emerging learning from the national improveme...
Improving home oxygen services: emerging learning from the national improveme...NHS Improvement
 
Nearly the Holy Grail – Clinical Portals for Faster, Better and Borderless Care
Nearly the Holy Grail – Clinical Portals for Faster, Better and Borderless CareNearly the Holy Grail – Clinical Portals for Faster, Better and Borderless Care
Nearly the Holy Grail – Clinical Portals for Faster, Better and Borderless CareNHSScotlandEvent
 
Stephen Shortt: GP commissioning and public engagement
Stephen Shortt: GP commissioning and public engagementStephen Shortt: GP commissioning and public engagement
Stephen Shortt: GP commissioning and public engagementNuffield Trust
 
Implementing_Edoscopy Timed_OG_Pathway.pptx
Implementing_Edoscopy Timed_OG_Pathway.pptxImplementing_Edoscopy Timed_OG_Pathway.pptx
Implementing_Edoscopy Timed_OG_Pathway.pptxradu75ro1
 
A guide to commissioning cardiac surgical services
A guide to commissioning cardiac surgical servicesA guide to commissioning cardiac surgical services
A guide to commissioning cardiac surgical servicesNHS Improvement
 
Improving post hospital and long term care: case studies from the Stroke Impr...
Improving post hospital and long term care: case studies from the Stroke Impr...Improving post hospital and long term care: case studies from the Stroke Impr...
Improving post hospital and long term care: case studies from the Stroke Impr...NHS Improvement
 
Managing COPD as a long term condition: emerging learning from the national i...
Managing COPD as a long term condition: emerging learning from the national i...Managing COPD as a long term condition: emerging learning from the national i...
Managing COPD as a long term condition: emerging learning from the national i...NHS Improvement
 

Semelhante a 18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document (20)

Lean principles to the Design of healthcare facilities
Lean principles to the Design of healthcare facilitiesLean principles to the Design of healthcare facilities
Lean principles to the Design of healthcare facilities
 
The best of clinical pathway redesign - practical examples of delivering bene...
The best of clinical pathway redesign - practical examples of delivering bene...The best of clinical pathway redesign - practical examples of delivering bene...
The best of clinical pathway redesign - practical examples of delivering bene...
 
Collaborating for the Nation's Health
Collaborating for the Nation's HealthCollaborating for the Nation's Health
Collaborating for the Nation's Health
 
Learning how to achieve a seven day turnaround in histopathology
Learning how to achieve a seven day turnaround in histopathologyLearning how to achieve a seven day turnaround in histopathology
Learning how to achieve a seven day turnaround in histopathology
 
Developing and Implementing a Patient Reported Experience Measure
Developing and Implementing a Patient Reported Experience MeasureDeveloping and Implementing a Patient Reported Experience Measure
Developing and Implementing a Patient Reported Experience Measure
 
World stem cell and regenerative medicine conference, london – may 2013
World stem cell and regenerative medicine conference, london – may 2013World stem cell and regenerative medicine conference, london – may 2013
World stem cell and regenerative medicine conference, london – may 2013
 
Going up a gear: Practical steps to improve stroke care
Going up a gear: Practical steps to improve stroke careGoing up a gear: Practical steps to improve stroke care
Going up a gear: Practical steps to improve stroke care
 
Joint Working workshop
Joint Working workshopJoint Working workshop
Joint Working workshop
 
Appendicectomy national meeting
Appendicectomy national meetingAppendicectomy national meeting
Appendicectomy national meeting
 
First steps in improving phlebotomy: the challenge to improve quality, produc...
First steps in improving phlebotomy: the challenge to improve quality, produc...First steps in improving phlebotomy: the challenge to improve quality, produc...
First steps in improving phlebotomy: the challenge to improve quality, produc...
 
UK-Italy dementia workshop, January 2018 - Catherine Moody
UK-Italy dementia workshop, January 2018 - Catherine MoodyUK-Italy dementia workshop, January 2018 - Catherine Moody
UK-Italy dementia workshop, January 2018 - Catherine Moody
 
Measuring Improvement: Using metrics and data to evaluate seven day services
Measuring Improvement: Using metrics and data to evaluate seven day servicesMeasuring Improvement: Using metrics and data to evaluate seven day services
Measuring Improvement: Using metrics and data to evaluate seven day services
 
Dr. Andy Lee
Dr. Andy LeeDr. Andy Lee
Dr. Andy Lee
 
Improving home oxygen services: emerging learning from the national improveme...
Improving home oxygen services: emerging learning from the national improveme...Improving home oxygen services: emerging learning from the national improveme...
Improving home oxygen services: emerging learning from the national improveme...
 
Nearly the Holy Grail – Clinical Portals for Faster, Better and Borderless Care
Nearly the Holy Grail – Clinical Portals for Faster, Better and Borderless CareNearly the Holy Grail – Clinical Portals for Faster, Better and Borderless Care
Nearly the Holy Grail – Clinical Portals for Faster, Better and Borderless Care
 
Stephen Shortt: GP commissioning and public engagement
Stephen Shortt: GP commissioning and public engagementStephen Shortt: GP commissioning and public engagement
Stephen Shortt: GP commissioning and public engagement
 
Implementing_Edoscopy Timed_OG_Pathway.pptx
Implementing_Edoscopy Timed_OG_Pathway.pptxImplementing_Edoscopy Timed_OG_Pathway.pptx
Implementing_Edoscopy Timed_OG_Pathway.pptx
 
A guide to commissioning cardiac surgical services
A guide to commissioning cardiac surgical servicesA guide to commissioning cardiac surgical services
A guide to commissioning cardiac surgical services
 
Improving post hospital and long term care: case studies from the Stroke Impr...
Improving post hospital and long term care: case studies from the Stroke Impr...Improving post hospital and long term care: case studies from the Stroke Impr...
Improving post hospital and long term care: case studies from the Stroke Impr...
 
Managing COPD as a long term condition: emerging learning from the national i...
Managing COPD as a long term condition: emerging learning from the national i...Managing COPD as a long term condition: emerging learning from the national i...
Managing COPD as a long term condition: emerging learning from the national i...
 

Mais de NHS Improvement

PEN Awards Webinar Series 3 of 6
PEN Awards Webinar Series 3 of 6PEN Awards Webinar Series 3 of 6
PEN Awards Webinar Series 3 of 6NHS Improvement
 
Directory of Diagnostic Services for Commissioning Organisations
Directory of Diagnostic Services for Commissioning Organisations Directory of Diagnostic Services for Commissioning Organisations
Directory of Diagnostic Services for Commissioning Organisations NHS Improvement
 
Top tips to overcome the challenge of commissioning diagnostic services
Top tips to overcome the challenge of commissioning diagnostic services Top tips to overcome the challenge of commissioning diagnostic services
Top tips to overcome the challenge of commissioning diagnostic services NHS Improvement
 
Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...
Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...
Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...NHS Improvement
 
Managing multi-morbidity in practice… what lessons can be learnt from the car...
Managing multi-morbidity in practice… what lessons can be learnt from the car...Managing multi-morbidity in practice… what lessons can be learnt from the car...
Managing multi-morbidity in practice… what lessons can be learnt from the car...NHS Improvement
 
Improving the quality and safety of home oxygen services: The case for spread
Improving the quality and safety of home oxygen services: The case for spread Improving the quality and safety of home oxygen services: The case for spread
Improving the quality and safety of home oxygen services: The case for spread NHS Improvement
 
Making the case for cardiac rehabilitation: modelling potential impact on re...
Making the case for cardiac rehabilitation:  modelling potential impact on re...Making the case for cardiac rehabilitation:  modelling potential impact on re...
Making the case for cardiac rehabilitation: modelling potential impact on re...NHS Improvement
 
Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...
Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...
Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...NHS Improvement
 
Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...
Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...
Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...NHS Improvement
 
Breakout 4.3 Building a caring future - Liz Norman
Breakout 4.3 Building a caring future - Liz NormanBreakout 4.3 Building a caring future - Liz Norman
Breakout 4.3 Building a caring future - Liz NormanNHS Improvement
 
Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...
Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...
Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...NHS Improvement
 
Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...
Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...
Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...NHS Improvement
 
Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...
Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...
Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...NHS Improvement
 
Breakout 4.1 Finding the missing millions - David Halpin
Breakout 4.1 Finding the missing millions - David HalpinBreakout 4.1 Finding the missing millions - David Halpin
Breakout 4.1 Finding the missing millions - David HalpinNHS Improvement
 
Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...
Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...
Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...NHS Improvement
 
Breakout 3.4 Asthma and psychological problems - Mike Thomas
Breakout 3.4 Asthma and psychological problems - Mike ThomasBreakout 3.4 Asthma and psychological problems - Mike Thomas
Breakout 3.4 Asthma and psychological problems - Mike ThomasNHS Improvement
 
Breakout 3.4 How to support the psychological needs of patients with COPD - K...
Breakout 3.4 How to support the psychological needs of patients with COPD - K...Breakout 3.4 How to support the psychological needs of patients with COPD - K...
Breakout 3.4 How to support the psychological needs of patients with COPD - K...NHS Improvement
 
Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...
Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...
Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...NHS Improvement
 
Breakout 3.3 Pro-active management - Stephen Gaduzo
Breakout 3.3 Pro-active management - Stephen GaduzoBreakout 3.3 Pro-active management - Stephen Gaduzo
Breakout 3.3 Pro-active management - Stephen GaduzoNHS Improvement
 
Breakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-Jones
Breakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-JonesBreakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-Jones
Breakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-JonesNHS Improvement
 

Mais de NHS Improvement (20)

PEN Awards Webinar Series 3 of 6
PEN Awards Webinar Series 3 of 6PEN Awards Webinar Series 3 of 6
PEN Awards Webinar Series 3 of 6
 
Directory of Diagnostic Services for Commissioning Organisations
Directory of Diagnostic Services for Commissioning Organisations Directory of Diagnostic Services for Commissioning Organisations
Directory of Diagnostic Services for Commissioning Organisations
 
Top tips to overcome the challenge of commissioning diagnostic services
Top tips to overcome the challenge of commissioning diagnostic services Top tips to overcome the challenge of commissioning diagnostic services
Top tips to overcome the challenge of commissioning diagnostic services
 
Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...
Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...
Managing exacerbations in chronic obstructive pulmonary disease (COPD): A sec...
 
Managing multi-morbidity in practice… what lessons can be learnt from the car...
Managing multi-morbidity in practice… what lessons can be learnt from the car...Managing multi-morbidity in practice… what lessons can be learnt from the car...
Managing multi-morbidity in practice… what lessons can be learnt from the car...
 
Improving the quality and safety of home oxygen services: The case for spread
Improving the quality and safety of home oxygen services: The case for spread Improving the quality and safety of home oxygen services: The case for spread
Improving the quality and safety of home oxygen services: The case for spread
 
Making the case for cardiac rehabilitation: modelling potential impact on re...
Making the case for cardiac rehabilitation:  modelling potential impact on re...Making the case for cardiac rehabilitation:  modelling potential impact on re...
Making the case for cardiac rehabilitation: modelling potential impact on re...
 
Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...
Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...
Breakout 4.5 Preventing Oxygen Toxicity: a whole system approach - Prof Tony ...
 
Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...
Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...
Breakout 4.4 End of Life Care in Respiratory Disease ~ What we did in Solihul...
 
Breakout 4.3 Building a caring future - Liz Norman
Breakout 4.3 Building a caring future - Liz NormanBreakout 4.3 Building a caring future - Liz Norman
Breakout 4.3 Building a caring future - Liz Norman
 
Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...
Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...
Breakout 4.3 How to manage… exacerbations of COPD, asthma and… in hospital - ...
 
Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...
Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...
Breakout 4.2 Optimise not maximise for better value COPD and asthma care - No...
 
Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...
Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...
Breakout 4. 2 Benefits of implementing medicines optimisation in a COPD and a...
 
Breakout 4.1 Finding the missing millions - David Halpin
Breakout 4.1 Finding the missing millions - David HalpinBreakout 4.1 Finding the missing millions - David Halpin
Breakout 4.1 Finding the missing millions - David Halpin
 
Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...
Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...
Breakout 3.5 ‘Dying for a fag’ The hypoxic patient actively smoking – case st...
 
Breakout 3.4 Asthma and psychological problems - Mike Thomas
Breakout 3.4 Asthma and psychological problems - Mike ThomasBreakout 3.4 Asthma and psychological problems - Mike Thomas
Breakout 3.4 Asthma and psychological problems - Mike Thomas
 
Breakout 3.4 How to support the psychological needs of patients with COPD - K...
Breakout 3.4 How to support the psychological needs of patients with COPD - K...Breakout 3.4 How to support the psychological needs of patients with COPD - K...
Breakout 3.4 How to support the psychological needs of patients with COPD - K...
 
Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...
Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...
Breakout 3.3 Achieving Excellence Across Primary & Secondary Care - Sarah Kea...
 
Breakout 3.3 Pro-active management - Stephen Gaduzo
Breakout 3.3 Pro-active management - Stephen GaduzoBreakout 3.3 Pro-active management - Stephen Gaduzo
Breakout 3.3 Pro-active management - Stephen Gaduzo
 
Breakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-Jones
Breakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-JonesBreakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-Jones
Breakout 3.2 Managing Multimorbidity in Practice - Dr Kevin Gruffydd-Jones
 

Último

(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...
(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...
(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...parulsinha
 
Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...
Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...
Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...tanya dube
 
Call Girls Raipur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Raipur Just Call 9630942363 Top Class Call Girl Service AvailableCall Girls Raipur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Raipur Just Call 9630942363 Top Class Call Girl Service AvailableGENUINE ESCORT AGENCY
 
8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad
8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad
8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In AhmedabadGENUINE ESCORT AGENCY
 
Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...
Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...
Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...Sheetaleventcompany
 
Call Girls Hosur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Hosur Just Call 9630942363 Top Class Call Girl Service AvailableCall Girls Hosur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Hosur Just Call 9630942363 Top Class Call Girl Service AvailableGENUINE ESCORT AGENCY
 
Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...
Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...
Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...GENUINE ESCORT AGENCY
 
Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...
Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...
Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...parulsinha
 
Call Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service AvailableCall Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...
Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...
Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...parulsinha
 
Call Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service AvailableCall Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service Availableperfect solution
 
Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...
Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...
Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...Namrata Singh
 
Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...
Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...
Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...BhumiSaxena1
 
Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...
Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...
Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...khalifaescort01
 
Top Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any Time
Top Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any TimeTop Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any Time
Top Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any TimeCall Girls Delhi
 
Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...
Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...
Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...GENUINE ESCORT AGENCY
 
Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...
Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...
Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...hotbabesbook
 
Russian Call Girls Service Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...
Russian Call Girls Service  Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...Russian Call Girls Service  Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...
Russian Call Girls Service Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...parulsinha
 
All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...
All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...
All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...Arohi Goyal
 

Último (20)

(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...
(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...
(Low Rate RASHMI ) Rate Of Call Girls Jaipur ❣ 8445551418 ❣ Elite Models & Ce...
 
Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...
Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...
Premium Bangalore Call Girls Jigani Dail 6378878445 Escort Service For Hot Ma...
 
Call Girls Raipur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Raipur Just Call 9630942363 Top Class Call Girl Service AvailableCall Girls Raipur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Raipur Just Call 9630942363 Top Class Call Girl Service Available
 
8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad
8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad
8980367676 Call Girls In Ahmedabad Escort Service Available 24×7 In Ahmedabad
 
Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...
Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...
Call Girls Service Jaipur {9521753030} ❤️VVIP RIDDHI Call Girl in Jaipur Raja...
 
Call Girls Hosur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Hosur Just Call 9630942363 Top Class Call Girl Service AvailableCall Girls Hosur Just Call 9630942363 Top Class Call Girl Service Available
Call Girls Hosur Just Call 9630942363 Top Class Call Girl Service Available
 
Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...
Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...
Models Call Girls In Hyderabad 9630942363 Hyderabad Call Girl & Hyderabad Esc...
 
Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...
Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...
Independent Call Girls In Jaipur { 8445551418 } ✔ ANIKA MEHTA ✔ Get High Prof...
 
Call Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service AvailableCall Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 8250077686 Top Class Call Girl Service Available
 
Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...
Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...
Call Girls Service Jaipur {8445551418} ❤️VVIP BHAWNA Call Girl in Jaipur Raja...
 
Call Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service AvailableCall Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service Available
Call Girls Rishikesh Just Call 9667172968 Top Class Call Girl Service Available
 
Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...
Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...
Call Girls Kolkata Kalikapur 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl Se...
 
🌹Attapur⬅️ Vip Call Girls Hyderabad 📱9352852248 Book Well Trand Call Girls In...
🌹Attapur⬅️ Vip Call Girls Hyderabad 📱9352852248 Book Well Trand Call Girls In...🌹Attapur⬅️ Vip Call Girls Hyderabad 📱9352852248 Book Well Trand Call Girls In...
🌹Attapur⬅️ Vip Call Girls Hyderabad 📱9352852248 Book Well Trand Call Girls In...
 
Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...
Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...
Saket * Call Girls in Delhi - Phone 9711199012 Escorts Service at 6k to 50k a...
 
Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...
Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...
Call Girls Service Jaipur {9521753030 } ❤️VVIP BHAWNA Call Girl in Jaipur Raj...
 
Top Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any Time
Top Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any TimeTop Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any Time
Top Quality Call Girl Service Kalyanpur 6378878445 Available Call Girls Any Time
 
Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...
Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...
Pondicherry Call Girls Book Now 9630942363 Top Class Pondicherry Escort Servi...
 
Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...
Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...
Night 7k to 12k Chennai City Center Call Girls 👉👉 7427069034⭐⭐ 100% Genuine E...
 
Russian Call Girls Service Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...
Russian Call Girls Service  Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...Russian Call Girls Service  Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...
Russian Call Girls Service Jaipur {8445551418} ❤️PALLAVI VIP Jaipur Call Gir...
 
All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...
All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...
All Time Service Available Call Girls Marine Drive 📳 9820252231 For 18+ VIP C...
 

18 Weeks Whole Pathways Project - National Priority Projects 07/08 Summary Document

  • 1. NHS NHS Improvement CANCER DIAGNOSTICS Heart Improvement HEART 18 Weeks STROKE Whole Pathways National Priority Project
  • 2. Delivering 18 weeks in cardiology was always going to ? be one of the most challenging areas in the 18 week pathway because it is a many headed beast. You have a number of investigations and diagnostics to perform as well as definitive treatment so it’s always going to be difficult. If you can deliver it in cardiology you can deliver it anywhere. Dr Guy Lloyd, ? Consultant Cardiologist, Eastbourne District General Hospital
  • 3. 18 Weeks Whole Pathways 3 Contents Introduction 4 Key Findings 6 Project Summaries 10 Lancashire & South Cumbria Cardiac Network – Redesigning the 11 Whole Patient Pathway for Cardiology Patients Trent Cardiac Network – Angiography Rapid Redesign Project 12 Leicestershire, Northamptonshire and Rutland Cardiac Network – 14 18 Week Whole Pathway Project Sussex Heart Network – 18 Week Whole Pathway Project 17 South West London Cardiac Network – Cardiac Surgery: Referral to 18 Treatment in 12 Weeks (average) project Trent Cardiac Network – Derby Hospitals Angioplasty Pathway Project 20 Trent Cardiac Network – Tertiary Referrals Pilot Project for Cardiac Services 22 Trent Cardiac Network – Reducing Waits for Cardiac Diagnostics 24 Trent Cardiac Network – Partial Booking of Follow Ups Project 26 Anglia Cardiac Network – Achieving 18 week Referral to 29 Treatment pathways by March 2008 Anglia Cardiac Network – 18 Weeks Whole Patient Pathway 32 Data Capture Resources and Project Team Membership 35 www.improvement.nhs.uk/heart
  • 4. 4 18 Weeks Whole Pathways Introduction To ensure that by 2008 ? The scope of the project covers the main ? no one waits more than 18 weeks from GP referral to hospital treatment. Operating framework 07/08: 18 week bottlenecks/constraints including: • • • • Outpatients (OPD) Diagnostics Secondary to tertiary care interface Some sites taking a whole pathway Priority 111: Access to services: PSA13 approach. This project has reviewed, identified and supported the practical implementation of I think that consultant buy-in is ? ways to reduce the waiting time from GP referral to definitive treatment, exploring in absolutely crucial to the success detail what really works. The specific project of the 18 week project but not aims and objectives have been to: surprisingly consultants vary in • Work with identified demonstration sites their views of the importance of within cardiac networks to capture this project. Were not going to learning get ten more consultants and • Implement a peer support action learning there is no new money so we’ll group drawn from members across the demonstration sites to facilitate the just have to think of ways to do sharing of ideas and solutions in order to this better, quicker, slicker and reduce duplication and to accelerate look to how we are actually improvement doing our jobs. • Develop a range of practical resources including demonstration site case studies to assist the wider health communities to achieve required sustainable improvements • Provide input and advice to the Department of Health (DH) 18 week Programme ? Dr Gordon Murray, Consultant Cardiologist and National Clinical Lead, NHS Heart Improvement In addition, a number of projects have looked at specific sub process issues team based on demonstration site particularly in relation to patient data, progress regarding issues, challenges and tracking and the Interprovider solutions with implementing 18 weeks. Administrative Minimum Data Set (IPTAMDS). The demonstration sites involve seven cardiac networks and some 25 NHS Trusts (including foundation trusts). www.improvement.nhs.uk/heart
  • 5. 18 Weeks Whole Pathways 5 Being part of a national priority project has been good in that its ? helped people in the organisation feel really motivated. When they achieve something like bringing waiting times down they get a real sense of achievement. now beginning to demonstrate: ? Julie Juden, Service Development Manager, Frimley Park Hospital NHS Foundation Trust With the project into its 8th month sites are • Improved audit, monitoring and internal reporting processes • Shared learning of the practical • A significant release of slots and beds implications/ramifications of the into the system improvement initiative as a resource for • Reduced whole pathway waiting accelerating change. times (with certain sites showing significant reductions in referral to In conjunction with the demonstration treatment times (RTT times) sites NHS Improvement (which now • Streamlined clinical and incorporates the Heart Improvement administrative pathways Programme) has developed a range of • Improved communication between products and resources including: healthcare staff and patients • The development and testing of • Pocket clock start/stop cardiac pathway information systems to support the scenarios complete with RTT status code collection of IPTAMDS for RTT (including a indicators demonstrator site for web based tracking • An updated online interactive 18 weeks system) resource and • More efficient use of OPD and diagnostic • An interactive cardiac data dashboard clinic slots with corresponding falls in capturing the national data returns for DNAs and clinic cancellations RTT and diagnostic data. • Reduction in angiography and PCI waiting times with increased catheter lab In addition, products produced across the efficiency demonstration sites are being collated and • Improved patient experience catalogued as a resource for sharing with • Streamlined pre assessment and post the wider health community. These products procedure protocols complement the established demand and • Improved, more responsive patient capacity, statistical process control, and centred booking processes patient pathway analyser tools available via (diagnostics) the national team. A list of these resources • Efficiencies created via the introduction together with a brief summary and the of one stop/single assessment clinics relevant link(s) is available towards the end and rapid follow up slots processes. of this document. • Better informed patients particularly with regard to surgery The current projects are phased for • Reductions in bed usage with protocols completion from March 2008 onwards with allowing surgical patients to be work continuing with demonstration sites to admitted on day of procedure ensure delivery solutions are implemented • Improved equity in terms of waiting and that sustainability is in place. times with the removal of urgent, soon Consequently, the summaries that follow and routine classifications. only capture a proportion of the work to • Creative approaches to staffing and date. The resulting case studies and workforce issues associated resources (process maps, policies, • Potential for reductions in surgical examples of questionnaires etc) will be cancellations through improved multi available on the NHS Improvement website disciplinary team (MDT) working and as the projects are validated. consent processes. www.improvement.nhs.uk/heart
  • 6. 6 18 Weeks Whole Pathways Key Findings www.improvement.nhs.uk/heart
  • 7. 18 Weeks Whole Pathways 7 Our biggest challenges - one was accessing data, our PAS ? systems across the trust are quite old and we weren’t able to put our hands on good 18 week data. Anonymous Key findings During December 2008 cardiac networks took part in a voluntary audit to survey the national picture of 18 weeks - a cardiac stock take. The aim of the stock take was to raise awareness, ? In this environment many projects or initiatives simply ground to a halt in the face of the myriad of competing pressures, priorities and agenda’s with local teams struggling with the size, demonstrate progress and inform national complexity and time needed to address the tasks strategy with regard to implementation of the presented. Again this echo’s the experiences of 18 week initiative. 87% of cardiac networks the cancer waiting time initiatives and the completed the survey, the results of which pivotal nature of a comprehensive strategy. acknowledge how complex and challenging 18 weeks is as it seeks to deliver improved patient Its interesting to note that where gains have experiences and outcomes across diverse been made that the initial strategic catalyst pathways, healthcare providers, and emanated from a variety of sources whether it organisational environments. be SHA, commissioner, provider or network (top down, bottom up and everything in between). Summarising the learning itself becomes a Again this is evidenced from information challenge as the subject matter is equally diverse obtained through the network 18 week stock so for the purpose of this document only the take; 16% of approaches measured were headlines have been articulated. The 18 week attributed to network initiatives, 13% to whole online resource, developed by the NHS Heart health economy, 18% to provider with the Improvement Programme, provides top tips and remaining 7% being attributed to ‘other’. more detailed approaches in an interactive resource that runs to over 150 pages so please It’s clear that truly inclusive health economy follow the link at the end of this document. strategies, together with complementary operational plans delivered in time for Experiences gained from within the NHS Heart sustainability to be addressed will remain a Improvement Programme, across the challenge for the country as a whole. demonstration sites and findings from the stock take have summarised critical success factors as Buy in, understanding, inclusivity being: and communication 18 weeks is such a wide ranging challenge that • Comprehensive shared strategy and plans for all staff need to understand what it represents to implementation the organisation, to patients, to customers and • Buy-in, understanding, inclusivity and of course to themselves. communication • Robust project management Successful initiatives have an overall vision to • IT system architecture and data collection work to and have worked though strategies for within 18 weeks creating the required understanding. Detailed communication plans are key to this – with Comprehensive shared strategy and plans specific methods of communication being for implementation as a whole developed to mitigate risks (across the full It became evident in the early stages of the spectrum, individual, team, organisational and overall priority project that the development of stakeholder) and which are threaded into the local 18 week strategy hadn’t been addressed in organisations strategic plan. any meaningful way. This is demonstrated by the fact that the priority project membership Robust project management reduced by 40% over the six months to This requires highly visible leaders, a can do December 2007 with the root cause for this attitude and a willingness to challenge existing drop off being the lack of an appropriate norms. mandated local strategy and implementation plan. www.improvement.nhs.uk/heart
  • 8. 8 18 Weeks Whole Pathways Involvement with the project has helped us get the DGH and ? the tertiary centre to understand what’s important for each organisation, and get the clinicians together to decide and agree what should be done at each part of the pathway. Julie Juden, Service Development Manager, Frimley Park Hospital NHS Foundation Trust. Develop robust project management routines – ensure senior clinical/management involvement and ensure that projects become the business of the board. Ensure that the problem and scope of the project have been well described with data patient waits. While a great deal of data exists within organisations, this data can be fragmented, un-validated, activity focused and contained on separate, supplemental databases (such as PRISM, TOMCAT) often managed by ? (ditto the goal) and ensure that the ‘work before different departments. the work’ has been completed to assess the do ability of the project. A review of all existing data collection systems and databases with an aim to moving towards a Develop affective: strategy that enables these systems to add • Project teams ensuring appropriate team greater value by integrating with existing members with the requisite information to systems should be contemplated as a driver for allow them to buy in and commit to the change. Consideration should be given to who project. Commissioner involvement/ manages these separate data sources; use of a communication and finance involvement has common; user-friendly language across systems; become a prerequisite (particularly with regard linking and tracking patient episode data across to tariff, contract or organisational budget (and within) organisations using unique changes). Patient and carer involvement identifiers (NHS or HES identifier); linking to within the project to capture experience diagnostic data sources. encouraging patient led redesign • Communication and project risk mitigation PAS system developers should be involved at an plans early stage to consider additional field • Measurement and data collection plans and requirements or reusing of redundant PAS understand process performance (SPC) and screens. However, some of the initial and Demand and Capacity measures. Set baselines. ongoing data collection will require manual Process map and collect Voice of the customer intervention and will need to be resourced data. appropriately. The work will be intensive and • Ensure that solutions have been subject to require input from all staff groups within and pilot testing and have been subject to some across sites related to the specific pathway of form of Failure Mode Effects Analysis1 care. • Introduce process control routines/ dashboards and appoint a process owner It is important to understand the ‘real’ demand whose role it is to ensure that new processes and capacity (as opposed to just the activity) of a remain in control and that corrective action is service to enable improved service planning taken as appropriate. through modelling and gap identification. • Maintain project visibility – publish learning and successes no matter how small. Note that significant progress has now been made in the development and roll out of Examples of these are available on the processes and protocols that support NHS Improvement System at information that follows the patient through www.improvement.nhs.uk/improvementsystem their pathway. This includes solutions to the Inter Provider Transfer Administrative Minimum Data IT system architecture and data set together with the transfer of clinical data collection within 18 weeks and diagnostic imaging. Case studies describing One of the key success factors of any 18 week these initiatives are currently being worked up piece of work has been to establish good data and will shortly become available on the collection to accurately measure the reality of Improvement system. 1 Failure Mode Effects Analysis ensures that processes have been subject to stringent failure and risk mitigation tests www.improvement.nhs.uk/heart
  • 9. 18 Weeks Whole Pathways 9 Moving forward Sustaining 18 week cardiac pathways Collaborative working between NHS 2008/09 and beyond Improvement (Heart Improvement Programme) The 18 week stock take2 conducted across all and the DH 18 week team together with other cardiac networks together with experiences key stakeholders will continue to progress the gained from the 18 week priority projects (and development of practical sustainability cancer 31/62 day waits ) has identified resources that will complement the existing suite sustainability as a major issue in holding 18 of resources found on the NHS Improvement. weeks post December 2008. website. The reasons behind this are complex but for the purpose of this document can be summarised as: The peer support meetings have • Lack of cohesive local implementation plans and strategy for 18 weeks • Lack of any real redesign and a reliance of doing ‘more of the same’ rather than focussing on redesign across the whole pathway ? been extremely valuable for all sorts of reasons. I’ve been able to help them to a certain extent with my clinical input but equally I have learnt an • Increased operational and/or organisational pressures, especially in light of numerous ‘vital enormous amount from the signs’ identified in the Operational projects themselves they have Framework really been excellent and I’ve • Clinical engagement • Hugely variable IT system, data and patient been able to take home lots of tracking capability the ideas and implement them • Contingent capacity where process efficiency has been optimised. locally and that’s been very helpful for me personally and In response to the factors outlined above the my directorate in moving current 18 Week Whole Pathway Priority Project will extend its focus to the approaches required towards delivery of the 18 to deliver sustainable cardiac pathways post week project. December 2008. The developing initiative will ? be supplemented with a spotlight on cardiac Dr Gordon Murray, Consultant Cardiologist and surgery (elective and non elective). National Clinical Lead, NHS Heart Improvement Programme The intention will be that experienced members of the 2007/08 Diagnostics Priority Project will join this revised project in order to fully capitalise on the experience and expertise developed through the existing demonstrator sites. Additionally it is anticipated that there will be a requirement to develop a number of new demonstrator sites as existing projects draw to an end. 2 Cardiac Network 18 week stock take December 07 – a comprehensive strategic and operational assessment of approaches to the target covering both current and planned activities within 26 Network health economies. For more information follow the link on the NHS Improvement System. www.improvement.nhs.uk/heart
  • 10. 10 18 Weeks Whole Pathways Project Summaries www.improvement.nhs.uk/heart
  • 11. 18 Weeks Whole Pathways 11 Redesigning the Whole Patient Pathway for Cardiology Patients Lancashire Teaching Hospitals NHS Foundation Trust (Royal Preston Hospital and Chorley District General) Lancashire & South Cumbria Cardiac Network Issues to address After mapping the various pathways for angiography, cardioversion and pacemaker implantation it was clear that complete redesign of cardiology pathways were needed. Without this patients would not be able to be treated within 18 weeks, particularly for those who were referred on for tertiary care. Baseline position • 12 week waits for first cardiology outpatients (OPD) • Separate waiting list for cardiac diagnostics often commenced after first OPD • Frequent cancellations of elective cardioversions if no available coronary care Key results/outcomes unit (CCU) bed or available anaesthetist • Referral to treatment times down to eight • No waiting list for cardioversion existed weeks • Frequent cancellations on pacemaker lists as all • All patients seen in one-stop cardiology clinics patients required beds on Friday • Dedicated sessions created for cardioversion • Considerable administrative delays for letters with managed waiting list and referrals. • Utilisation of catheter laboratory up 30% • Diagnostics pre selected by clinical Actions taken physiologists to ensure results available for • Established one-stop clinics for all four first OPD cardiologists • Treatment plan given and catheter lab • Redesigned diagnostic pathway booked at first OPD. • Located regular venue and anaesthetic sessions for cardioversion Contact information • Changed pacemaker booking from single list Kathy Blacker to end of angiography list to reduce Kathy.blacker@lsccn.nhs.uk cancellations due to lack of available beds • Trained clinical physiologists and receptionists to access Choose and Book and • Gained agreement from cardiologists for clinical physiologists to pre select diagnostics • Changed booking system for catheter lab procedures. www.improvement.nhs.uk/heart
  • 12. 12 18 Weeks Whole Pathways Angiography ‘Fast Works’ Rapid Redesign Project King’s Mill Hospital Trent Cardiac Network Issues to address Waiting times for diagnostic angiography were found to be too long, with the waiting times between cardiologists showing high levels of variation. Additionally, the productivity of the catheter lab was not optimal with significant list size variation between consultants; unused slots during angiography sessions; under-utilised nursing capacity allocated to the catheter lab. Without improved productivity/increased activity in the catheter lab, the wait time would not reach the trust target figure. Baseline position available via the Improvement system website. Waiting time for a diagnostic angiography took A process map of the existing pathway was on average five weeks, with a range of 0 weeks developed and agreed and a large amount of to 18 weeks (data for five months March to July data analysis was carried out, presenting 2007). evidence of where there was some room for possible service improvements. Productivity of the catheter lab evidenced 75% utilisation over 12 months (May 2006 to May A patient survey was also conducted to gather a 2007). baseline of the existing angiography service The list size of each session showed a variation provided at King’s Mill Hospital from a patient ranging between one to six angiography perspective. A total of 50 patient names were procedures per list, with a mean of four. selected at random to be included in the survey, all of who had undergone angiography at King’s Based on a target minimum of four patients per Mill Hospital within the previous six months. session, there were found to be 244 unused The survey received an 86% response rate and a slots over 12 months to May 2007 and 44 lost detailed report produced outlining the findings lists over 12 months due to under-utilised is available via the Improvement website. nursing capacity allocated to the catheter lab. The throughput of the Lab in May 2007 was on Following the work of the time-limited project average 12 patients per week, based on four group, a two-day event was held inviting angiography lists per week. colleagues working within the trust, who had involvement in some way with patients requiring Actions taken angiography. Problems identified by the fast A ‘Fast Works’ rapid redesign project group was works project group were considered and established, comprising representation from recommendations/solutions agreed by attendees clinical and non-clinical staff working within, at the event. At the end of the two days, these or supporting the running of, the catheter lab. recommendations and related actions were An independent fast works facilitator and a presented for approval to a panel, comprising of member of the NHS Heart Improvement the Trust Chief Executive, Director of Nursing, Programme led the project group, supported by Consultant Cardiologist, Cardiology Manager, the Trent Cardiac Network. Nine (two hour) and the Divisional Manager. A number of weekly meetings of the group were held, during recommendations were approved by the panel, which 'problems' with the existing part of this which have subsequently led to a number of patient pathway were identified. A Project service improvements. Charter was developed by the group which outlines the project in more detail and is www.improvement.nhs.uk/heart
  • 13. 18 Weeks Whole Pathways 13 Key results/outcomes • Pre-assessment, including gaining of patient Several service improvements have been consent, is now carried out during the implemented since completion of this project, patients’ OP clinic appointment, meaning which have led to a reduction in waiting times patients are available to fill slots at short notice for angiography to a maximum of six weeks as (e.g. cancellations or additional clinics), which at February 2008. Productivity and activity has led to minimised lost slots within the catheter lab has also increased, • Improved and standardised referral process, resulting in a minimum of four patients now with enhanced referral forms. Proposal for all being booked per list, often having a fifth or referrals for angiographies to be centrally sixth patient booked in as emergencies. Finally, coordinated by the Central Waiting List Office the number of lost angiography lists has • Development of new patient information significantly decreased due to the introduction leaflet of ‘flexible rotas’. Over a recent six week period, • Introduction of a ‘catheter lab coordinator’ nine out of 12 lists were covered, which would role to ensure communication is optimised previously have been ‘lost slots’. This equates to within the lab, allocate daily responsibilities, an additional 36 routine angiography procedures ensure things run to time etc being scheduled during this time period, which • Increased turnaround times within the prior to the project would not have been carried catheter lab due to new pre-assessment out. process, flexible working patterns of staff, improved communication within the lab, A summary of the changes that have resulted in improved audit systems these developments so far are: • Introduction of ‘flexible rotas’, resulting in catheter lab slots being utilised to maximum • All angiographies are now fully booked from capacity, with on-calls and leave covered by OP clinic appointment consultant colleagues wherever possible • Introduction of ‘partial pooled lists’ for • Development and introduction of a written angiographies, which has reduced patient competency based training package for waiting times and decreased the variation in cardiac nurses has increased the skill mix of waiting times between cardiologists (NB To nursing staff within the catheter lab, enabling ensure continuity of care, the treatment plan cross-cover and increasing utilisation of remains under the patient’s main consultant, it nursing capacity within the lab. is purely the angiography procedure that is pooled) Further examples detailing the ‘Fast Works’ • An enhanced post angiography process means approach to rapid redesign project involving that, wherever possible, all results are Thames Valley Cardiac Network angiography discussed with the patient on the same day as and booking waits, and Leicestershire, the angiography (with their main consultant) Northamptonshire and Rutland Cardiac Network and next steps agreed reductions in unnecessary follow ups project can be found via the Improvement System. Contact information Jo Evans Joanne.evans@sfh-tr.nhs.uk www.improvement.nhs.uk/heart
  • 14. 14 18 Weeks Whole Pathways Leicester Northamptonshire and Rutland Cardiac Network and University Hospitals Leicester 18 Week Whole Pathway Project University Hospitals of Leicester (3 sites) Leicester Northamptonshire and Rutland Cardiac Network Issues to address The time taken between original GP referral to date of procedure in cardiac surgery exceeded a year, for patients being treated within cardiology by PCI the journey time was around 28 weeks. This extensive wait was similar whether the patient had their entire journey within the tertiary centre or if the patient was initially investigated at a secondary centre and then referred onwards. Baseline position A retrospective baseline audit took place in June 2006 looking at 50 sets of patient notes including all treatment options and referral sources and repeated in October 2007. The Actions taken common bottle necks were identified as: The project was launched by raising awareness of the current bottlenecks and demonstrating • The administration time between actions, the current actual referral to treatment times which progress the patients pathway took an (RTT), in comparison with the target. In addition average of four weeks. For example, awaiting raising awareness of 18 week wait measurement typing and acceptance of referral letters or and associated rules. This was implemented receiving diagnostic reports. through posters, meetings and contact with • A 12 week wait for clinic with only a key staff culminating in a well attended proportion of diagnostics being pre ordered. multidisciplinary event on 28 September 2006 Poor co-ordination of diagnostic being where members agreed how to progress completed before the first outpatient towards an 18 week wait. appointment and results being made available on time. Process mapping took place along with demand • Diagnostics wait of 17 weeks (max) which and capacity calculations for each individual area didn’t always include the reporting time. of delivery along all of the cardio respiratory • A high percentage of patients were going patient’s pathways. This information quantified around the outpatient and diagnostics loop which bottlenecks would have the highest two to three times before the correct impact on delivering 18 weeks and indicated the information was assembled for clinical staff to order in which 18 week wait changes should be make a diagnosis and progress to treating the addressed. patient. This translated in some cases to a delay of as much as three to six months from The work was then divided into manageable original referral to initial diagnosis and a stages and staff assigned to working groups, treatment plan being agreed. with clinical, service improvement and a • The capacity to admit patients for treatment managerial lead. These groups looked at the: was stretched in addition initiatives were used to meet reductions of waiting time targets. • Primary care interface • Outpatients and diagnostics • Chest pain and valve treatment • Arrhythmia treatment • Paediatric and congenital • Respiratory • Thoracic pathways. www.improvement.nhs.uk/heart
  • 15. 18 Weeks Whole Pathways 15 To ensure continuity and cohesive working Initially the changes would be implemented in between the groups a steering group formed to adult cardiology because of the large patient oversee progress chaired by the directorate base and then tailored where necessary and general manager. rolled out to other specialties and sites. Each group set specific goals, the example Key results/outcomes described in more detail here is the highest The clinical annual and study leave policy was impact area, identified as the outpatient and updated and re established with clear processes diagnostics portion of the patient pathway. The and monitoring. This meant that delivery areas aim was to deliver - referral to decision to treat were able to plan and protect capacity for the (or other outcome), inclusive of the outpatient next four weeks without change and the appointment and basic cardiac diagnostic testing associated delays or rescheduling. in less than four weeks. The waiting time for diagnostics has been This deliverable was further quantified as: reduced to six weeks through waiting list initiatives, validation, demand management and • Wait for an outpatient appointment of less recruitment drives. The reduction is continuing than four weeks down to two weeks, supported by ongoing • Deliver the majority of same day diagnostic demand and capacity work. The network has testing with a maximum wait of two weeks trained operational staff to calculate demand • Electronic diagnostic test management and and capacity within their own areas. Tests are shared cross site waiting lists booked upon request reducing the • Single assessment clinics administrative workload and providing patients • Reduce the number of follow-up patients to with a planned date. release outpatient capacity • Partially book follow-up patients to reduce A partial booking of follow-ups system has outpatient wastage been developed using the example of the • Protected capacity for a minimum of four Sherwood Forest Hospital pilot (outlined on weeks through a clinical annual leave policy page 22 - Partial Bookings of Follow-ups. • Deliver preadmission in clinic on day of Implementation was delayed due to trust wide decision to treat including fully booking the 18 week wait planning but will be delivered in admission date. May 2008. It is expected to reduce the number of wasted appointments which will release capacity for the single assessment clinics. For the network as a whole A change to the diagnostics IT system is under ? the different trusts are now ? looking at pre planning tests as much as they possibly can. way; this will enable more staff to access diagnostics information about appointments and results. It will deliver better co-ordination between tests and outpatient appointments but also allow the diagnostics waiting lists to be shared across the three delivery sites. This reduces the waiting times and improves equity of access. Elaine Kemp, Cardiac Service Development Manager, Leics, Northants & Rutland Cardiac Network www.improvement.nhs.uk/heart
  • 16. 16 18 Weeks Whole Pathways Preadmission services have been redesigned to The changes at Leicester are being supported deliver medical preadmission on the day of the through the cardiac network by sharing learning patient’s outpatient appointment. With the from trusts such as Kettering, who have option of further psychological support and implemented outpatient and diagnostics information either on the same day or later changes, Sherwood Forest with their successful before admission. This means patients are partial booking and in turn the learning at prepared earlier for admission reducing Leicester will help support the Northampton cancellations. It is planned to fully book team in developing their single assessment pilot. admissions once the preadmission changes have been embedded. Contact information Elaine Kemp Single assessment clinics have been trialed over Elaine.Kemp@northants.nhs.uk 17 clinical sessions with 84 new and 230 follow- up patients. Most tests were pre planned however on the day 54 patients were put forward for an additional 63 diagnostics; echo, ETT and Tapes. All patients were given the opportunity to stay and have tests on the day or return at a later date, only one patient declined. 40 out of the 63 diagnostics were completed on the day; those not done were due to the timing of the diagnostics working day compared to clinic appointments which can be resolved. 16 out of the 54 patients using the single assessment clinic were discharged and five patients were given a decision to treat of admission. Single assessment clinics will deliver a reduced waiting time for patients, less visits to the hospital and additional capacity in clinic. Implementation of all the above changes will deliver the aim of a four week wait, the project unfortunately has overrun due to operational pressures and several changes in the trust management team. It is projected that single assessment clinics, preadmission changes and partial booking will be implemented before June 2008. The less quantifiable change which will help deliver 18 weeks is the move from a culture in diagnostics and other delivery areas, of using waiting lists to flex the amount of work delivered to match the capacity which is available. Now the capacity is being flexed to match the amount of work required to deliver the waiting time on a shorter pathway. www.improvement.nhs.uk/heart
  • 17. 18 Weeks Whole Pathways 17 18 Weeks Whole Pathway - Sussex Eastbourne District General Hospital, Royal Sussex County Hospital (part of Brighton and Sussex University Hospitals NHS Trust), Hailsham Practice Based Commissioning (PBC) Cluster Sussex Cardiac Network Issues to address • Need to achieve 18 week target for cardiology and cardiac surgery patients from the Eastbourne area. Delays and bottlenecks were contributing to the target not being met. • Need to demand manage referrals from primary care to sustain 18 week target when achieved. • Waiting times had hidden elements in them as GP to acceptance on waiting list was not being recorded. Baseline position At July 2007: • Maximum wait for new outpatient appointment was 11 weeks Key results/outcomes • Maximum wait for diagnostic echo was 26 • At EDGH 85% of all patients are being weeks referred and treated within 18 weeks • Maximum wait for angiogram was 19 weeks. • New referral pathway has been rolled out to other referring DGH’s. Actions taken • Extra activity to address backlog Cardiac surgery waits are reducing and they now • Following an assessment of demand and include the hidden waits. capacity extra investment was made into equipment for 24 hour testing Contact information • Development of a triage clinic in secondary Lisa Fairclough care to triage referrals from primary care. Aim Lisa.fairclough@bsuh.nhs.uk is to reduce unnecessary consultant outpatient appointment, facilitate direct access to diagnostic investigations e.g. angiography and refer patients back to GP with a management plan if no intervention required • Develop a proposal for a community cardiology service in one area of Eastbourne. Service to be run by a GP with an interest in cardiology and clinical governance arrangements support from secondary care. Aim is to for all cardiac referrals to be sent to the service and following assessment, the GP will either refer on to secondary care immediately or undertake some diagnostics tests in community and then refer back to original GP with a management plan or refer onto secondary care. • Process mapped the referral pathway for cardiac surgery. A new pathway was developed. All referrals are now faxed or emailed the same day as the diagnostic investigation. Referral is actioned on receipt by the waiting list office and an OPA made within 48 hours and occurring within two weeks. www.improvement.nhs.uk/heart
  • 18. 18 18 Weeks Whole Pathways Cardiac Surgery: Referral To Treatment in 12 Weeks (Average) Frimley Park Hospital St George’s Hospital South West London Cardiac Network Issues to address According to an 18 week pilot study conducted at St George's Hospital in 2006 by the South West London Cardiac Network, patients (n=5) referred from Frimley Park Hospital waited up to 54 weeks from initial referral (18 week clock start) until treatment at St George's Hospital (clock stop). Data collected since the project started indicated that average referral to treatment (RTT) times was about 30 weeks on average (n=24). In addition, anecdotal reports of poor communication between the two organisations, one indication of which was the poor performance in terms of sending discharge A comprehensive cardiology redesign workshop summaries to the secondary centre after patients was held at Frimley Park Hospital in June 2007. had completed their course of treatment at the As a result the following changes were made: tertiary centre. Also, there were problems in terms of administrative process delays (with (1) Direct booking for angiography and pre- patients sometimes being ‘lost’ in the system), assessment from outpatient clinics was and moving patients to the next stage of instigated treatment. (2) Rapid follow-up slots and more one-stop clinics were introduced Actions taken (3) The trust admissions team was made The project started officially on the 20 March responsible for booking all diagnostic tests 2007 at the first steering group meeting and is and procedures (treatments) in the catheter due to end on the 31 March 2008. Below is a laboratory selection of improvements made to date. (4) An induction to cardiology was introduced for junior doctors at each rotation From March 2007 demand and capacity analyses (5) Diagnostic waiting times are monitored on a were undertaken at Frimley Park Hospital and weekly basis strategies were identified to reduce the backlog (6) The multidisciplinary team (MDT) meeting of patients waiting for diagnostic tests, was redesigned so that all necessary outpatient appointments and inpatient diagnostic tests are performed before the admissions. Work was also done to ensure cross- patient is seen jointly by the cardiologist and cover by staff at critical steps in the pathway, surgeon. Test results and treatment options and to identify the flow of patients and time are discussed and a treatment plan agreed requirements for each component of the with the patient. A dedicated administrator pathway. is responsible for ensuring the efficient coordination of the joint cardiac clinic and At the first steering group meeting an elective handling onward referrals to the tertiary cardiac referral form was devised and agreed. centre. Frimley Park Hospital started using the form in May 2007 and it has since been through several Mapping of clinical and administrative processes modifications, most recently to reflect the has taken place at St George’s Hospital over the publication of DSCN 44/2007 in December lifetime of the project, and systems put in place 2007. to facilitate the reliable transfer of referral data and early booking of patient appointments. www.improvement.nhs.uk/heart
  • 19. 18 Weeks Whole Pathways 19 The cardiac network decided to do a joint project between two main ? hospitals to look at the cardiac surgery pathway. We started off from a baseline of 32 weeks on average, that’s the time from when the patient is referred by the GP until they actually have their surgery in a tertiary hospital. Adrianne van Heerden, Service Improvement Manager, South West London Cardiac and Stroke Network ? Plans have been initiated to pre-assess all cardiac trust to admit patients on the day of their surgery patients so that they can be admitted on procedure, rather than the day before, thereby the day of surgery rather than the day before. saving valuable bed days. An 18 weeks training workshop was held for cardiac secretaries at St George’s Hospital, and a St George's Hospital performs around 1,150 cardiac process will be trialled where they will email surgery procedures per year, and could therefore discharge summaries and 18 week referral forms potentially save this number of bed days per year. (with clock stop dates, where appropriate) back As patients are better worked up at the secondary to the referring organisations. centre in advance of transfer for surgery, we expect the number of surgery cancellations to decline, as Key results/outcomes patients unfit for surgery will not be transferred. Patients are having their initial contact with a consultant much sooner than before the project Since tertiary care clinicians can access diagnostic started (now within four weeks), and the images at the secondary centre directly via NHS diagnostic tests required are now sometimes done extranet, extra slots for echos, angiograms and on the same day, or at most within a few weeks of dopplers will become available at the tertiary centre request. (The internal target set is two weeks for as the need for repeat diagnostic tests are reduced diagnostic tests. This is being achieved in most in number. instances, and plans are being put in place to ensure these waiting times can be sustained.) This Both Frimley Park Hospital and St George’s Hospital allows the clinician to make a diagnosis much are aiming to complete their part of the cardiac sooner and develop a treatment plan with the surgery pathway in an average of six weeks, giving a patient. Patients are better informed about the total journey time of 12 weeks (on average). Data surgery pathway and the number of visits they analysis to date suggests that the average referral to need to make to St George’s Hospital has been treatment (RTT) time has reduced from 32 weeks (on reduced by redesigning the multidisciplinary team average) to 9.4 weeks (on average) since the project meeting at Frimley Park Hospital. We believe this has started. This has had a positive effect on staff resulted in a better patient experience and we will morale, as they can see the results of their hard give patients the opportunity to feed back by means work and experience the satisfaction of providing an of a patient questionnaire in the near future. improved patient experience. The redesign work has also benefited the NHS Contact information organisations involved. St George's Hospital is Adriaan van Heerden moving to a position where all cardiac surgery adriaan.vanheerden@stgeorges.nhs.uk patients attend pre-assessment. This will enable the www.improvement.nhs.uk/heart
  • 20. 20 18 Weeks Whole Pathways Derby Hospitals Angioplasty Pathway Project Derby Hospitals NHS Foundation Trust Trent Cardiac Network Actions taken A planning workshop, followed by two further workshops, was held with attendance from cardiologists, cardiac clinicians and other clinical and non-clinical colleagues working in or alongside the catheter lab. The workshops were led by the Trent Cardiac Network and resulted in the development of a robust action plan, which was taken forward and implemented by all relevant members of the cardiology team working in the trust. To support the progress of implementing the action plan, ad hoc meetings were held as necessary to focus on moving specific issues forward. This included meetings with IT, cardiology secretaries, cardiology managers, attending the cardiologists’ monthly meeting etc. The cardiac network maintained a regular record of progress against the action plan throughout the project period. Issues to address In addition, at the start of the project nine sets The trust 18 week steering group collected data of patient notes were scrutinised to map actual to determine the high priority areas to focus on patient pathways. Findings from this work with regards to ensuring compliance with the 18 reflected the issues raised during the process weeks initiative. The angioplasty pathway was mapping exercise, highlighting key areas for identified as one of these key areas, having a improvement. A further 12 sets of patient notes comparatively low achievement rate in respect of were again scrutinised at the end of the project the 18 week target. to provide a robust comparison of where service improvements to the patient pathway had been After initially process mapping the patient made. pathway, it was identified that activity relating to referrals to or from the catheter lab was one of Key results/outcomes the key areas for concern. • Several service improvements have been implemented since completion of this project, Baseline position which have led to a reduction in waiting times Catheter lab waits peaked at a maximum during for angiography and PCI procedures, early August 2007, around the beginning of the consequently reducing the overall length of project, with patients waiting up to 17 weeks pathway for this set of patients for angiography and up to a further 15 weeks • As at the beginning of March 2008, the for their angioplasty procedure. maximum wait time for angiography from date of listing had reduced to six weeks, with As at January 2007, 44% of angioplasty (PCI) five weeks being the maximum for PCI. The patients were recorded as receiving treatment percentage of patients being treated by PCI within 18 weeks of initial referral*. This within 18 weeks of initial referral increased instigated the establishment of this project. to 65% * Using most accurate data available at the time, acknowledging limitations of existing IT systems in recording and reporting 18 week clock statuses. www.improvement.nhs.uk/heart
  • 21. 18 Weeks Whole Pathways 21 • The changes that supported and influenced • Introduction of outcome forms in the the improvement of the angioplasty pathway catheter lab, recognising that clocks could at Derby include: potentially start, stop or keep ticking at • Clinical and non-clinical engagement from point of angiography. This supports more the outset, including consultant accurate recording of RTT data cardiologists, managers, nurses and admin/ • Robust audit, monitoring and internal clerical staff. All members took ownership reporting processes re waiting lists. of relevant issues / actions which strongly supported the success of the project. Contact information • Equity for patients requiring angiography Jo Evans (removed inappropriate use of ‘urgent’ from Joanne.evans@sfh-tr.nhs.uk RACPC and individual consultants, which resulted in more appointments becoming available for the 'routine' referrals and, therefore, these could be seen more quickly) • Admin delays removed for ‘discussion patients’ wherever possible when interventionalist on site. Most cases are now discussed and treatment plans agreed directly with the interventionalist working on that particular day, rather than awaiting a monthly meeting or writing to a specific consultant for opinion • Improved post angio process – patient letter template developed for those patients whose treatment plan cannot be agreed on day of angiography. Removes the need to bring the patient back for follow-up outpatient appointment just to inform them of the outcome (reduces length of patient pathway and frees up follow-up outpatient appointments) • Raising registrars’ awareness of 18 weeks has led to improved efficiency in reviewing of diagnostic results process - now checked a minimum of twice a week as opposed to previously checking once a month • Retraining of staff (both internal and external to the trust) to ensure that new referrals for OP and/or diagnostics are correctly addressed and delivered, consequently reducing administrative delays • Exercise tolerance test (ETT) request forms updated – enable direct referral for angio following positive ETT (removes the need for patients to attend outpatient appointment, again reducing the length of patient pathway and freeing up outpatient appointments) www.improvement.nhs.uk/heart
  • 22. 22 18 Weeks Whole Pathways Tertiary Referrals Pilot Project for Cardiac Services King’s Mill Hospital Nottingham University Hospitals Trent Cardiac Network Issues to address The national Inter Provider Transfer Admin Minimum Data Set (IPTAMDS) was developed to support the efficient management of patients whose pathways involved an inter-provider transfer, in particular facilitating the transfer of the necessary data to enable receiving providers to meet their mandatory Referral to Treatment (RTT) reporting requirements. Trusts were advised that implementation of the MDS would be mandatory from 1 January 2008. Locally, it was recognised that preliminary work needed to take place in order to ensure sufficient and accurate collection, recording and ‘accurate as possible’ information using the data transfer of the MDS information. Work needed available on the existing PAS electronic database to take place to identify: or manually looking through patient notes. • Where the relevant RTT data could be found Actions taken • The ease of this data collection A specific time-limited project group was • Who would be best placed to complete the established, with representation from Sherwood MDS forms/receive completed MDS forms Forest Hospitals NHS Foundation Trust (SFHFT), • How they would be best transferred across Nottingham University Hospitals (NUH) and Trent sites, for example, electronically, by post, fax Cardiac Network. Members of the group agreed etc. project aims and objectives including how the MDS data would be collected transferred and by The trusts would also need to move away from whom, along with the key outcomes to be focusing on the previous ‘stages of treatment’ monitored and reported on at the end of the and individual hospital responsibilities, working project. Data monitoring commenced on 1 together to provide one smooth patient focused October 2007 for two months, with a final pathway of care. review process in December 2007. Regular communication was maintained and project Baseline position group meetings continued throughout the Prior to the publication of the MDS, there was project period. no standard referral information specified for inter-provider referrals between these hospital The project focused solely on those patients sites, particularly with regards to data relating to being referred from King’s Mill Hospital (KMH) the 18 week whole patient journey. The (acute trust) for tertiary cardiac care at individual trusts and hospital sites worked Nottingham University Hospitals (NUH) (Tertiary towards their specific targets for their individual Centre). All referrals were captured via the stage(s) of treatment and did not provide any catheter lab at KMH following angiography and related waiting time or complete pathway included only those being referred on for referral data when transferring to another selected treatment, namely angioplasty (PCI) or provider. surgery (CABG). Patients referred to the tertiary centre for diagnostics were not included in this Because the above data was not being provided project. across sites, specific 18 week pathway information could not be monitored for this set The pilot focused on the specific stage within of patients. Also, existing IT systems did not the patient pathway, when the patient’s care provide the facility to enable such information to was transferred from the secondary to tertiary be recorded accurately. Trusts were capturing as care centre. It was agreed that any issues www.improvement.nhs.uk/heart
  • 23. 18 Weeks Whole Pathways 23 Example of an 18 week pathway identified at either side of this should be transfer of the MDS and clinical referral addressed locally by the relevant trust outside information, method of collection of robust RTT the project group. data, dealing with referrals for diagnostics, and ‘roll-out’ to other specialties or trusts. In addition, members of the project group acknowledged the local commissioning targets The actual lengths of patient pathways, from that were hoping to be achieved by March 2008 referral to treatment, were accurately captured and, with this in mind, the information collected by manually scrutinising patient notes. This throughout the project was used to trace and enabled key areas for any breaches to the 18 manually plot care pathways for all patients week target to be identified and reasons for included within the pilot project, identifying time these delays to be addressed. Using the actual taken between each stage of treatment and any patient journeys that were mapped, example related delays. pathways could be developed to help provide clarification around clock starts and stops. Throughout the two-month project period, 27 patient pathways were monitored, with A full report detailing the project approach, respective MDS forms completed and issues, findings, recommendations and ‘roll out’ electronically transferred from KMH to NUH. have been produced following this project and shared across Trent Cardiac Network. Example Key results/outcomes pathways, developed as a result of plotting real This project enabled data completeness of the patient journeys, have also been shared across MDS forms to be monitored, highlighting which the network. data requirements were difficult, or even not available at the time of the project, for collection As a result of the work carried out within this (e.g. due to awaiting implementation of PAS project, both trusts are able to use the findings v20). A list of concerns / problems was recorded to support implementation of the MDS across all and all issues were fed back to the relevant trust specialties. The project outcome also identifies for them to locally agree next steps and action key areas for further service development work points, in order to address the problems and within cardiac services, both locally and working ensure pathways were reduced to the shortest across provider sites, in order to achieve the 18 clinically appropriate. week initiative. Other trusts within the network are also now using the project report to support A series of recommendations was also produced, their implementation of the MDS. learning from any difficulties encountered as part of the project. These mainly related to Contact information ensuring efficient and effective preparation and Jo Evans communication prior to implementation of the Joanne.evans@sfh-tr.nhs.uk MDS, selecting the most appropriate method of www.improvement.nhs.uk/heart
  • 24. 24 18 Weeks Whole Pathways Reducing Waits for Cardiac Diagnostics Sherwood Forest Hospitals NHS Foundation Trust Trent Cardiac Network many patients waiting up to two months or more from referral, particularly for echo. A workshop was held with all available members of the cardio respiratory team, using this data as a baseline. During the workshop a process map, reflecting the current referral to diagnostic process, was produced, following which problem areas were identified and suggestions for improvement made. As a result of the workshop an action plan was developed. In addition, the cardio respiratory manager worked closely with the Information Services Department to ensure relevant referral and waiting time data was received on a weekly basis. This enabled the department to move to Issues to address a more 'demand led' service, which historically The maximum waiting time for some of the high had been more 'staff led'. volume cardiac diagnostics was found to be too long. In order to improve patient experience, Significant work was carried out during and for patients to realistically achieve an 18 December 2007 to clear any backlog within the week care pathway, these waiting times needed system. All staff training for that month was to be reduced in line with Trust targets, which cancelled and clinical time maximised across the aimed for a maximum wait of four weeks for department. Use of all diagnostic slots was any diagnostic test by March 2008. maximised, with the administration team ensuring that all efforts were made to fill Baseline position cancellations as soon as they became apparent. In September 2007, echocardiography waits Any available slots in one service that had a were at around nine weeks, with doctor led ETT minimal waiting list would be converted to maximising at 10 weeks and other high volume accommodate another e.g. additional echo slots cardiac diagnostics not far behind. if trained staff available. NB. Dobutamine Stress Echo’s (DSEs) were Key results/outcomes recognised to be of comparatively low volume in The maximum wait time for any cardiac relation to the number of referrals received for diagnostic (excluding DSEs) as at the beginning other diagnostics and, although waits for this of February 2008 had reduced to three weeks, test were also too long, it was agreed that this which was actually less than the Trust target of area would be picked up as a separate project four weeks. (currently making significant progress). Due to the changes made within the Actions taken department, and the cardio respiratory manager Data was collected from within the cardio and team adapting to a new way of working, it respiratory department for the five high volume is anticipated that this short wait time will diagnostics (i.e. those receiving the most continue to be sustainable for the future. The referrals), which were 24hr BP, 24hr ECG, event new systems will ensure that clinical time recorders, echo and exercise tolerance testing continues to be maximised and that the (ETT). This data demonstrated that an average department continues to run as a 'demand led' of around four weeks wait for patients was service. Information Services now provide data actually being achieved for many of these on a weekly basis, which enables the diagnostics, but evidenced a huge variation with department to continue to be 'demand led'. www.improvement.nhs.uk/heart
  • 25. 18 Weeks Whole Pathways 25 More flexible working within the department and smarter working patterns enables capacity to be maximised, with all team members now being aware of waiting times and targets. Cancellations continue to be filled wherever possible by the administration staff and compressed hours of some of the clinical staff are worked to advantage the department, by providing additional slots at the beginning and end of the day for additional patients, or for analysis and reporting work to be carried out. In addition, the two trainee staff have very recently qualified which has enabled capacity to be extended. The more senior staff, who would previously have worked to support the trainees, are able to see patients separately whilst the newly qualified staff can work without supervision. The cardio respiratory assistant role has also been expanded to provide additional capacity within the department. Patients are now seen much quicker following referral for cardiac diagnostics. This means patients, and their carers, have less time to become anxious and are able to reach a diagnosis much sooner than before. This improvement has increased efficiency within the cardio respiratory department and has led to significantly reduced waiting times supporting the trust's achievement of the 18 week initiative. These reduced waits at King’s Mill Hospital have also provided the opportunity and additional resource to progress towards achieving similar results in relation to cardiac diagnostic waits at the Newark Hospital site. Contact information Jo Evans Joanne.evans@sfh-tr.nhs.uk www.improvement.nhs.uk/heart
  • 26. 26 18 Weeks Whole Pathways Partial Booking of Follow Ups Sherwood Forest Hospitals NHS Foundation Trust Trent Cardiac Network Issues to address There were found to be 1081 DNAs over the Trent Project ‘Cardiac Service Improvement’ same period, from 1 December 2004 and 30 (‘CSI’) was established as an initial response to November 2005, with 82% of all DNAs the 18 week wait target, which brought occurring from follow ups. together team members from Sherwood Forest Hospitals NHS Trust, the Trent Cardiac Network Planned clinic capacity was running at 64% and the National Heart Improvement utilisation prior to the project. Programme. The project aimed to deliver improvements that would make a contribution Actions taken towards achieving the target within cardiology An analysis was undertaken of the reasons for and one of the key problem areas identified was cancellations occurring more than six weeks the system for booking follow up outpatient before the appointment date. Most were due to appointments. the unavailability of medical staff due to annual leave, study leave or on-call commitments. A The booking process for follow up patients was new trust leave policy was consequently found to be inefficient, with patients being introduced, stating that a minimum of six weeks “fully” booked too far in advance (3, 6 or 12 notice was required. In line with this, clinic rotas months). This led to high DNA and cancellation and on call rotas were scheduled only six weeks rates, as well as to lots of rescheduling every in advance, rather than for several months, time an outpatient clinic was cancelled or enabling capacity to be more flexibly planned to reduced. The service was driven by the demand ensure clinics were always covered and, for new patient appointments, leading to follow therefore, removing the need for cancellation or up patient capacity being ‘squeezed’. This could rescheduling of clinics. result in patients being seen long after their ideal review date, often further delayed by A ‘go live’ date was set and publicity campaign having appointments moved forward due to launched via local hospitals and media. Initially, clinics cancelled or patients forgetting their almost 3000 appointments were cancelled, advance appointment and therefore not which had been scheduled for patients in attending. advance of six weeks. Each patient was sent a letter explaining why their appointment had As a consequence, consultants were unable to been cancelled and informing them of the follow up patients in a timely fashion according process via which their next appointment would to clinical need. The management of these be booked. A leaflet explaining and follow-up patients was not optimal and the highlighting the benefits of the new partial follow up to new ratio did not use resources to booking process was included. This process the maximum efficiency. resulted in less than 10 patient complaints. Baseline position The partial booking system worked by patients Between 1 December 2004 and 30 November requiring follow up more than six weeks in the 2005 there were 5397 cancellation events within future being partially booked and given a Partial the cardiology outpatient service. 4092 of these Booking Information leaflet. These patients cancellation events occurred more than six were added to a review list on PAS and allocated weeks before the appointment date. 1305 of a review date. Six to eight weeks before the these cancellations occurred less than six weeks review date a letter was sent to the patient, before the appointment date. inviting them to telephone to arrange an appointment. Non-responders were telephoned The follow up ratio was at 1 new to 2.57 and if no contact was made the case was (including RACPC) follow ups, with a range of referred back to the consultant for them to between 1:2.7 and 1:5.75. decide whether to discharge the patient or refer them back to their GP. www.improvement.nhs.uk/heart
  • 27. 18 Weeks Whole Pathways 27 Multidisciplinary slot management meetings • By January 2007, waiting times fell despite were held every two weeks, which contributed increased referrals, indicating more efficient significantly to monitoring and improving the use of clinic capacity efficiency of the booking process. Related • There was the potential risk that follow-up policies and procedures were reviewed and ratios would increase with easier access, but updated accordingly throughout the pilot period. this was not the case An electronic outpatient request form was also • Although the percentage utilisation of clinic introduced. slots had not changed by the end of the project (remaining at 64% utilisation), the Key results/outcomes underpinning organisation of clinics was Demand management for clinic appointments is improved with over bookings no longer now driven by the total demand in the system, occurring, a reduction in DNAs evident and not just new patients. Those requiring a follow fewer patients having appointments up appointment within six weeks are generally rearranged. The clinic volumes are more the first call on resources, with the second call predictable and so run more smoothly. being for follow ups coming up to review date (agreed boundaries are in place on what is an The project anticipated a further positive result acceptable variance to review date, + or –). in that all follow up patients would be able to Finally, the remaining capacity is pooled on be seen when clinically appropriate and in broad choose and book as new patient slots, with a chronological order by the end of the project, conversion ratio of two follow up equivalent which would then be sustainable. slots to one new patient. This system of slot Unfortunately, due to numbers of patients management now avoids under booking of exceeding the existing maximum overall clinic clinics due to unfilled new slots, as could have capacity and the pressures for new patients to happened with the previous system. be seen without delay, there is currently insufficient space in clinics to ensure that this is The key results and outcomes from this always the case and, therefore, the number of project include: follow ups outstanding is higher than desired as at March 2008. However, the way that these • A dramatic reduction in cancelled follow ups are being monitored and managed appointments (hospital and patient driven) – has dramatically improved as a result of the no follow up events cancelled more than 6 project, enabling this issue to be highlighted as a weeks before appointment as this is no longer priority area and providing evidence for a possible. Cancellation rates also reduced for solution to be identified and implemented by new appointments, from 13% in November the trust as a matter of relevant urgency. 2005 to 2% in September 2006. • An increase in patient choice with regards to To date, the project has brought many benefits time / date of appointment to both patients and staff working within the • A 50% improvement in DNA rates was trust. Patients have an improved experience demonstrated by the end of the project, with no cancellation of appointments and thought to be directly attributed to partial improved choice of follow up date, making booking for follow-ups them feel more involved and less likely to forget • The ability to flexibly plan capacity, with follow about their appointment. Better use of up demand being the driver resources means patients should no longer have • Improved cost efficiency, with the reduction in to wait as long as before. The clinical volume of staff resource required to cancel / management of patients with follow up has change clinics - the introduction of an improved, with many of them now being seen electronic outpatient request form reduced at a clinically appropriate time (although phone calls by 80 per month recognising the current issue outlined above). www.improvement.nhs.uk/heart
  • 28. 28 18 Weeks Whole Pathways Every six weeks the service has a ‘clean sheet’ in terms of clinic bookings and flexible use of capacity enables the service to be more responsive to the demands and be less bound by previous clinic booking rules. Decisions are made about how to allocate resources in a more realistic time frame. Reduced DNAs has led to increased capacity in the service. Partial booking means that the majority of patients, who would previously DNA, do not respond to partial booking, hence no longer take up an appointment slot and consequently leave this available for another patient to occupy. This also leads to reduced overall waiting times. Since completion of this project, partial booking has been introduced for many more specialties across the hospital trust, benefiting significantly more patients and supporting the trust with its work to achieve the 18 week target. Contact information Sue Brewin Sue.brewin@sfh-tr.nhs.uk www.improvement.nhs.uk/heart
  • 29. 18 Weeks Whole Pathways 29 Achieving 18 Week Referral To Treatment Pathways by March 2008 James Paget University Hospital NHS Foundation Trust (JPUH), Papworth Hospital NHS Foundation Trust, Norfolk and Norwich University Hospital NHS Trust (NNUH), Great Yarmouth and Waveney Primary Care Trust, Anglia Cardiac Network We set an admissions target for ? the team, achieving two week, one stop-clinics. We will spread this practice across our other specialties. ? Adrian Pennington, Chief Executive, James Paget University Hospital NHS Foundation Trust Issues to address The JPUH is a small district general hospital situated on the East Norfolk coast. It has a population catchment area of 220,000 and there are high levels of deprivation. The NNUH, a neighbouring DGH offers an Reducing the outpatient wait was a major angiography and pacemaker service to the JPUH aspect of this project and a demand and and percutaneous coronary intervention (PCI) to a capacity study at the beginning of the project specific group of patients. The majority of patients revealed the size of what lay ahead. however have to travel to Papworth, a cardiac tertiary provider which is a 190 mile round trip. Each consultant had: • Different start and finish times Cardiologists: • Saw a varying number of patients There is one full time cardiologist, one part-time • Where middle grades were present they often cardiologist (outpatient work only), one locum only saw a couple of patients and one vacancy. There is insufficient outpatient • New slots were frequently closed to capacity with the staffing levels as they are to accommodate follow ups reduce the outpatient wait to anything less than • There was so much wasted capacity both from two to three weeks. poor utilisation of appointments and high DNA rates that it was clear a more efficient The JPUH has a non-invasive cardiac diagnostic service was required urgently. department which means that the following diagnostics are available: ambulatory monitoring, A follow up audit undertaken to find out the echo, exercise tests, TOEs, Tilts etc. This reasons why patients were being booked to department has been very dynamic over the last return to clinic for a follow up appointment few years in that the manager has applied for revealed: funding from the SHA to take on a student every year for the last six years, she has • Inappropriate follow up practice implemented an in house echo training • Incorrect booking of patients who should have programme and with additional service redesign been new not a follow up has sustained all diagnostic waiting times at <2 • A high number of patients were being asked weeks for over eighteen months. Our challenge to return to discuss results of tests and then of implementing one stop diagnostics was discharged requiring no further intervention or therefore not reducing diagnostic waits but medical treatment. This was adding a reducing outpatient waits. The Trust could not considerable delay in the pathway (i.e. you afford to waste diagnostic capacity so we were can’t stop the clock until the result is shared unable to implement one stop diagnostics until with the patient and the outcome agreed). the outpatient wait almost matched the diagnostic wait. www.improvement.nhs.uk/heart