1. Orbiting Carbon Observatory - 2: Recovering from Mission Loss Eric Ianson Program Executive Science Mission Directorate
2. Introduction – Launch of the Orbiting Carbon Observatory (OCO) February 24, 2009 1:59 AM PST Approximately 17 minutes later
3.
4.
5.
6.
7.
8. OCO-2 Schedule Activities conducted during this 8-month Tailored Formulation Period are described in the following slides 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 01 02 03 04 FY2016 FY2017 FY2012 FY2013 FY2014 FY2015 FY2009 FY2010 FY2011 Proposed OCO-2 Schedule Conventional Project Life-Cycle Pre-A (6 mo) Phase A (9 mo) Phase B (12 mo) Phase C (24 mo) Phase D (12 mo) Phase E (24 mo) 21 mo MCR MDR (PNAR) PDR (NAR) CDR SIR ORR LRD PLAR Pre-A (6 mo) TFP (8 mo) Phase C (16.5 mo) Phase D (11.5 mo) Phase E (24 mo) CDR (NAR) SIR ORR LRD PLAR 36 mo SRR 8 mo 28 mo Tailored Formulation Period (8 mo) CDR (NAR) Peer Reviews (w/SRB Participation)
9.
10. OCO-2 will complete all NPR 7120.5 Formulation Gate Products Prior to KDP-C NPR 7120.5 OCO2 Products Pre-A Phase A § Phase B KDP A KDP B KDP C HQ and Program Products 1. FAD Approved 2. Program Requirements on the Project Draft Baseline Update 3. ASM minutes Baseline 4. NEPA Compliance Documentation EA 5. Inter-Agency & International Agrmts Baseline 6. Mishap Control Plan Project Technical Products 1. Mission Concept Report Preliminary Baseline 2. System Level Requirements Preliminary Baseline 3. Preliminary Design Report Baseline 4. Missions Operations Concept Preliminary Baseline 5. Tech Readiness Assessment Rept Baseline 6. Missile Sys Pre-Launch Safety Pkg Preliminary 7. Detailed Design Report 8. As-built H/W & S/W Documentation 9. Verification and Validation Report 10. Operations Handbook 11. Orbital Debris Assessment Initial Preliminary 12. End of Mission Plan Initial Preliminary 13. Mission Report Proj. Planning, Cost, & Schedule Prod. 1. Work Agreements for Next Phase Baseline** Baseline 2. Management Baseline Draft Preliminary Baseline 3. Project Plan Preliminary Baseline 4. CADRe Preliminary Baseline 5. Planetary Protection Plan PPC Baseline 6. Nuclear Safety Launch Approval Plan Baseline 7. Bus. Case Analysis for Infrastructure Preliminary Baseline 8. Range Safety Risk Management Plan Preliminary 9. Sys Decommissioning/Disposal Plan KDP Readiness Products 1. SRB Report Final Final Final 2. Project Manager Recommendation Final Final Final 3. CMC Recommendation Final Final Final 4. Program Manager Recommendation Final Final Final 5. MD-PMC Recommendation Final Final Final 6. Governing PMC Recommendation Final Final Final Products Pre-A TFP Kickoff KDP C HQ and Program Products 1. FAD Approved 2. Program Requirements on the Project Draft Baseline 3. ASM minutes Baseline 4. NEPA Compliance Documentation EA 5. Inter-Agency & International Agrmts Baseline 6. Mishap Control Plan Project Technical Products 1. Mission Concept Report Baseline 2. System Level Requirements Baseline 3. Preliminary Design Report Baseline 4. Missions Operations Concept Baseline 5. Tech Readiness Assessment Rept Baseline 6. Missile Sys Pre-Launch Safety Pkg Preliminary 7. Detailed Design Report 8. As-built H/W & S/W Documentation 9. Verification and Validation Report 10. Operations Handbook 11. Orbital Debris Assessment Preliminary 12. End of Mission Plan Preliminary 13. Mission Report Proj. Planning, Cost, & Schedule Prod. 1. Work Agreements for Next Phase Baseline 2. Management Baseline Baseline 3. Project Plan Baseline 4. CADRe Baseline 5. Planetary Protection Plan N/A 6. Nuclear Safety Launch Approval Plan N/A 7. Bus. Case Analysis for Infrastructure Baseline 8. Range Safety Risk Management Plan Preliminary 9. Sys Decommissioning/Disposal Plan KDP Readiness Products 1. SRB Report Final 2. Project Manager Recommendation Final 3. CMC Recommendation Final 4. Program Manager Recommendation Final 5. MD-PMC Recommendation Final Final 6. Governing PMC Recommendation Final Final
11. OCO-2 will complete all NPR 7120.5 Formulation Project Control Plans Prior to KDP-C NPR 7120.5 OCO-2 Project Plan – Control Plans Pre-Phase A Phase A Phase B KDP A KDP B KDP C 1. Technical, Schedule, and Cost Control Plan Preliminary Baseline 2. Safety and Mission Assurance Plan Preliminary Baseline 3. Risk Management Plan Preliminary Baseline 4. Acquisition Plan Preliminary Baseline 5. Technology Development Plan Baseline 6. Systems Engineering Management Plan Baseline 7. Software Management Plan Preliminary Baseline 8. Review Plan Preliminary Baseline 9. Missions Operations Plan Preliminary 10. Environmental Management Plan Baseline 11. Logistics Plan Preliminary 12. Science Data Management Plan Preliminary 13. Information and Configuration Management Plan Preliminary Baseline 14. Security Plan Preliminary Baseline 15. Export Control Plan Preliminary Baseline Project Plan – Control Plans Pre-Phase A TFP Kickoff KDP C 1. Technical, Schedule, and Cost Control Plan Baseline 2. Safety and Mission Assurance Plan Baseline 3. Risk Management Plan Baseline 4. Acquisition Plan Baseline 5. Technology Development Plan Baseline 6. Systems Engineering Management Plan Baseline 7. Software Management Plan Baseline 8. Review Plan Baseline 9. Missions Operations Plan Preliminary 10. Environmental Management Plan Baseline 11. Logistics Plan Preliminary 12. Science Data Management Plan Preliminary 13. Information and Configuration Management Plan Baseline 14. Security Plan Baseline 15. Export Control Plan Baseline