SlideShare a Scribd company logo
1 of 36
Download to read offline
Planning and Conducting an
                       Integrated Baseline Review (IBR)


                            Matthew T. Gonzales, Project Business Manager
                                       Jet Propulsion Laboratory
                                             818-354-3629




Used with Permission                                                        Pg 1
Communication




– Early
– Frequent
– Inclusive




                Pg 2
Organization




‘If you can't describe what you are doing as a process, you don't know what you're doing.’


                                                                              W. Edward Deming




                                                                                             Pg 3
IBR as a Process
  Pre-Phase A emphasizes the             Phase A emphasizes the EV                Phase B emphasizes the              Phase C emphasizes use of EVM            Phase D emphasizes use of EVM
contractors and projects readiness       Process and Initial Baseline          validity of baseline to complete          and the validity of EAC to               and the validity of EAC to
             for EVM                               Plan                                      work                             complete work                            complete work

                                           Formulation                                                                                 Implementation
        Pre-Phase A                              Phase A                               Phase B                              Phase C                           Phase D
    Project Emphasis:                    Project Emphasis:                     Project Emphasis:                     Project Emphasis:                     Project Emphasis:

      - System Definition                 - Complete System Definition         - Project Requirements                 - Complete Flight and Ground         - Integration of Flight HW
      - Identify potential contractors    - Establish Requirements             Baselined                              Designs                              and SW
      and teammates                       - Select Contractors                 - Preliminary Design                   - Conduct component and SS           - Integrate Payload and
      - Identify contractors above        - Award Contracts with EVM           Established                            CDRs                                 Launch Vehicle
      $20M                                DRDs                                 - LL Procurements Let                  - Build BB and EMs
                                                                                                                      - Initiate Acceptance Test
                                                                                                                      Program for Flight HW

    EVM Emphasis:                        EVM Emphasis:                         EVM Emphasis:                         EVM Emphasis:                         EVM Emphasis:

      - EVM implementation team           - Contractor teams develop           - EV System is mature                  - Implement EV                       - Implement EV
      defined                             initial project cost and schedule       - Reports Submitted                 - Project Office conducts IBR with   - Project Office conducts IBR with
      - Contractors develop EVM           baseline                                - Logs Established                  emphasis on Risk to Reserves         emphasis on Risk to Reserves
      plan                                - Contractors submit EV reports         - Change Control Exercised             - Does Project Plan support          - Does Project Plan support I&T
      - Progress Assessment Visit         per DRDs                             - Project Office conducts IBR with        detail design                        Program
      (PAV); Contractor presents          - Project Office conducts IBR        emphasis on Risk to Reserves              - Is EV data reliable as a           - Is EV data reliable as a predictor
      EVM plan                            with emphasis on Process                - Project Plan content                 predictor                            - Quality of VARs
      - EVM team evaluates                   - Compliance to EV Process           - Completeness of Planning             - Quality of VARs                    - Is the project using EVM data to
      - If Validation Review is              - Data Quality                       - Change control process               - Is the project using EVM data      manage
      required, EVM teams works              - CAM Knowledge                      - Basis of Estimate for Cost and       to manage                            - Test EAC process
      with local DCMA                        - Change Control                     Schedule                               - Test EAC process                   - Quality BOEs
      - Conduct follow-up PAV                - Validity of Baseline relative      - Can design be built with             - Quality BOEs                       - Can I&T be completed for
      - Support KDP A                        to Scope of Work                     planned resources                      - Can HW be built for                estimated cost
                                          - Support KDP B                         - Overall robustness of EVM            estimated cost                       - Is there sufficient schedule
                                                                                  system                                 - Is there sufficient schedule       - Are Risks known and mitigated
                                                                                  - Reconciliation to Phase A            - Are Risks known and                - Reliable reporting
                                                                                  Baseline                               mitigated                         - Support KDP E
                                                                               - Support KDP C                           - Reliable reporting
                                                                                                                      - Support KDP D


                                                                                                                                                                                        Pg 4
Key to Success




– Communication
– Organization




                  Pg 5
IBR Steps


Impetus

Planning

Conducting

Caucus and review


Out-brief

Final Report



                    Pg 6
Impetus

Impetus for an Integrated Baseline Review
    Comply with customer requirements (7120.5d)

    Significant change to system design

    New Launch Date

    ‘Grass roots’ EAC Developed

    Over Target Baseline incorporated




                                                   Pg 7
Planning



In preparing for battle I
have always found that
plans are useless, but
planning is indispensable.
Dwight D. Eisenhower



                             Pg 8
Planning Process Flow
Timeline    Events     Process

            Project    IMS restructured for       Project IMS resources     Project Plan approved
            Re-plan    new launch date and        estimated and loaded          by SMD PMC.
                         design change             into Turbo for pricing   Authorized to Proceed.



             EV           Turbo estimates         MS Project milestones       Project integrated
           Database     imported into MPM.         imported in MPM.           baseline complete.
           Complete      PMB established.          Weight applied. EV          Set ‘Over Target
 Jul ‘06                                                Plan Set                  Baseline’


               1st     Schedule updated on           Update to MPM           Generate and submit
             Month       weekly cadence.                database.             CPR Format 1 in
           EV update     Weekly metrics            ACWP and BCWP for         support of customer
             cycle        implemented.               July month end                 MMR



           Review        EV metrics               Corrective actions         Changes to S/C and
              &        analysis reveals          assigned/reviewed.           Mtl plans and EV
Aug ‘06
           Analysis       planning            Implementation approved         methods complete
                         anomalies.            by PO and implemented          prior to Aug close.

                                                                                            Pg 9
Planning Process Flow
Timeline    Events     Process
              2nd      Submit CPR Format 1.              Corrective actions       IBR date negotiated
             Month       Planning changes             closed. EV and VARs           with all affected
           EV update     incorporated. EV               reviewed at project       parties. Set for Nov.
             cycle        metrics improve.                     MMR
Sep ‘06
                           Project office                 IBR scope,
                                                                                   Contractor, HQ/DPO
            Project     generates and briefs           schedule and team
                                                                                    and project team
             CDR          IBR information                 membership
                                                                                   briefed on IBR plan
                             package.                      finalized.
 Oct ‘06

                         IBR Coordination              Day 1 -IBR In-Brief
                                                         Update to MPM           Day 2 – Data Review
                       meeting with Review              JPL database.
                                                            Project Office        Review team audits
                        Team week before              BATC EV Surveillance
                                                      ACWP and BCWP for            CAM notebooks.
            Project           review                   BATC Project end
                                                         July month Office          Team caucus.
             IBR


                         EV metrics
                        Day 3 – CAM Interviews               Day 4 – Data Review/
                       analysis reveals
                         Project Technical Lead                Informal Out-brief               Formal
Nov ‘06
                          planning
                       conducts interview. All team          Review Survey Results             Out-brief
                         anomalies.
                        members complete survey           3-4 slide contractor feedback

                                                                                                   Pg 10
Planning

Plan for your review
     Anticipated KDP

     Project Phase

     Working with contractors



Define IBR as early as possible
    Scope, Goals, Purpose

    Team membership with roles and responsibilities

    Required documents for review

    Work with contractor on logistics



Communicate
   3 briefings in preparation for review

   Need to train interviewers as well as interviewees

   Provide contractor with questions ahead of time




                                                         Pg 11
The In-Brief




  Preamble




               Pg 12
John Wooden: A Coaching Legend
UCLA's basketball program has the international reputation of being No. 1. There is a major reason
for that his name is John Robert Wooden, who announced his retirement after the 1974-75 season
(his 27th campaign) as the Bruins' head coach with the winningest record in all of the sport's
history. Wooden celebrated his 92nd birthday on Oct. 14, 2002.

Wooden concluded his 40 years as a head coach that season and his 885-203 overall career win-
loss record (a percentage of .813) is unequaled. A large part of that success was at UCLA. In 27
years as Bruin coach, his teams registered 620 wins, and only 147 losses while earning far more
national honors than any other university.

Under Wooden, UCLA won an unprecedented 10 NCAA championships, including seven
consecutive (1966-73). Included in the string is one of the most amazing win streaks in all of
sports, 38 straight NCAA tournament victories.

In addition, there is the all-time NCAA consecutive winning-streak record of 88 games over four
seasons, which included consecutive 30-0 seasons in 1971-72 and 1972-73. UCLA also won 149
of 151 games in Pauley Pavilion during his Bruin tenure.

John Wooden is the only coach to compile four undefeated seasons of 30-0 and his Bruin teams
captured 19 conference championships (the record of which Wooden is most proud).

Coach Wooden is the first person to be inducted into the National Basketball Hall of Fame as
both a player and coach

                                                                                                Pg 13
John Wooden Quotes
“It’s the little details that are vital. Little things make big things happen”

“If you don’t have time to do it right, when will you have the time to do it over”

“Winning takes talent, to repeat it takes character”

“It is what we learn after we know it all that really counts”

“Be prepared and be honest”

“Things turn out best for the people who make the best of the way things turn
out”




                                                                                     Pg 14
Use your review In-brief as a time to

               Inspire




                                        Pg 15
The In-Brief




Project Overview
Goals
Success Criteria
Process Overview
Documents
Logistics/Schedule
General Comments




                     Pg 16
Data Review - Wed, Nov. 15th 8am – 5pm
•   Control Account Managers Notebooks
     – Turbo reports                                 • Reviewing for completeness
     – Schedules , by WBS element and by IPT         and consistency in the plans.
     – Control Account Plans to Work Package level   • Is the work fully accounted for
       of detail and Earned Value Milestone Report   and plan appropriately.
     – Current WBS and WBS Dictionary                • Are all resources planned and
                                                     available when required.
     – Estimating methodology and documentation
       to enable assessment of the basis of the      • Is the time phasing of cost and
       estimates                                     schedule consistent.
     – Work Authorization Documents for authorized   • Is EV planned in a way to yield
       control accounts.                             accurate results.
     – Performance Measurement Reports (CPR          • Are analysis tools available
       Format 1)                                     and utilized.
     – Budget Change Requests (if applicable)        • Are changes tracked and
                                                     managed
     – Approved liens and KVRs and recovery plans
                                                     • Are they adhering to the BATC
•   Other Ball documentation required for the IBR:   way of planning and managing
     – Current Contract SOW                          projects.
     – BATC System Description, Kepler EVM Plan
       Supplement
                                                                                Pg 17
Conducting Interviews




                        Pg 18
Conducting Interviews
Select WBS elements for review
    Risk driven (technical and/or programmatic)
    Phase specific




Select appropriate questions
    Phase specific
    Basis of Estimate

    Discern risk

    Communicate early




Develop interview teams
    Led by technical representative
    Small teams

    Provide training on questions




Discussions/Interviews
    Conversational
    ~ 2 hours

    Document results


                                                   Pg 19
CAM Interviews – Nov. 16th 8am – 5pm
                                                                          IBR CAM Interview Schedule

 DRAFT                                               WBS       WBS Description                     Day           Interview Time
                                                     6.1.1     FS Management                       Thurs         08:00 – 10:00
                                                     5.2.6     Attitude Control                    Thurs         08:00 – 10:00
                                                     5.2.8     Communications                      Thurs         08:00 – 10:00
                                                     6.1.3     FS Mission Assurance                Thurs         10:00 – 12:00
                                                     6.3.2     FPAA                                Thurs         10:00 – 12:00
                                                     6.3.3     Electrical                          Thurs         10:00 – 12:00
                                                     6.3.4     Telescope                           Thurs         1:00 – 3:00
                                                     5.2.3     Mechanical Subsystem                Thurs         1:00 – 3:00
                                                     6.3.5     Photo Integration Test              Thurs         3:00 – 5:00
                                                     5.2.11    Spacecraft I&T                      Thurs         3:00 – 5:00
                                                     5.3       System ATLO


  IBR CAM Interview Schedule             Technical Leads                  NASA Reps              Discovery Program Office                 Support

                                  Peg      Leslie Jim     Sarah Michael Renee Pam Jack   Steve   Nate John Robert Dan        Maura Bill    Tim Cal       Joe
WBS      WBS Description          Frerking Livesay Fanson Gavit Moore Leck Marcum Graham McClard Porter Keidel Bitten Graham Fujieh Epping Clark Cambers Fischetti
6.1.1    FS Management                   1                     1                      1                                                             1
5.2.6    Attitude Control                                  1                                                 1              1         1
5.2.8    Communications                          1                                                           1              1                              1
6.1.3    FS Mission Assurance            1                                                                   1      1           1
6.3.2    FPAA                     1                            1             1        1
6.3.3    Electrical                              1                    1                                             1           1
6.3.4    Telescope                1                                          1                                                  1                   1
5.2.3    Mechanical Subsystem                    1                                           1                                        1                    1
6.3.5    Photo Integration Test   1                                   1      1               1
5.2.11   Spacecraft I&T                  1                 1   1                                       1
5.3      System ATLO




                                                                                                                                                            Pg 20
CAM Questionnaire
                                       Questions                                                  Rating      Low       Med       High
1.What is the Manager’s scope of work? Does the Manager know what scope of work is
his/her responsibility?                                                                               Cost     1    2    3    4     5

–The Manager should be able to show the team a Statement of Work (SOW) paragraph, a WBS,
PWBS, or CWBS narrative, and a Work Authorization Document that correlates to the task.           Schedule     1    2    3    4     5

Comments:
                                                                                                  Technical    1    2    3    4     5




2.How did the Manager plan the scope of work into control accounts?
                                                                                                      Cost     1    2    3    4     5

–The SOW defines the effort. The WBS, PWBS, or CWBS provides specifics, such as work
definition. The work authorization and change documentation should show information such as the   Schedule     1    2    3    4     5
dollars/hours, period of performance, and description of the scope of work and any changes.
Comments:
                                                                                                  Technical    1    2    3    4     5




3.How did the Manager ensure that all elements of the scope of work were planned?
                                                                                                      Cost     1    2    3    4     5

–The Manager should be able to show the team the work packages breaking down the scope of
work, and the budget associated with each work package. The sum of the work packages should be    Schedule     1    2    3    4     5
the control account budget. Each control account should contain a specific scope of work.
Comments:
                                                                                                  Technical    1    2    3    4     5




                                                                                                                                  Pg 21
Caucus and Review




                    Pg 22
Caucus and Review



Review survey responses
    By interview, by question
    Look for outliers and discuss.

    Opportunity to share thoughts and observations

    Normalize metrics

        Do metrics support subjective risk observations




                                                           Pg 23
Caucus and Review
   Low   Med      High
    12     36       60                                                                                    Risk Rating
WBS    CAM    Intvr      No                            Questions                                 Cost   Sched    Tech   Total
5.2.6   CS     SG        1    1.What is the Manager’s scope of work? Does the Manager
                                                                                                  1       2       3       6
                              know what scope of work is his/her responsibility?
5.2.6   CS     DG        1    1.What is the Manager’s scope of work? Does the Manager
                                                                                                  1       1       2       4
                              know what scope of work is his/her responsibility?
5.2.6   CS     RB        1    1.What is the Manager’s scope of work? Does the Manager
                                                                                                  1       1       1       3
                              know what scope of work is his/her responsibility?
5.2.6   CS     BE        1    1.What is the Manager’s scope of work? Does the Manager
                                                                                                  1       1       1       3
                              know what scope of work is his/her responsibility?
                                                                                        Totals    4       5       7      16
5.2.6   CS     DG        2    2.How did the Manager plan the scope of work into control
                                                                                                  1       1       1       3
                              accounts?
5.2.6   CS     SG        2    2.How did the Manager plan the scope of work into control
                                                                                                  1       1       1       3
                              accounts?
5.2.6   CS     RB        2    2.How did the Manager plan the scope of work into control
                                                                                                  1       1       1       3
                              accounts?
5.2.6   CS     BE        2    2.How did the Manager plan the scope of work into control
                                                                                                  1       1       1       3
                              accounts?
                                                                                        Totals    4       4       4      12
5.2.6   CS     DG        3    3.How did the Manager ensure that all elements of the scope of
                                                                                                  2       2       2       6
                              work were planned?
5.2.6   CS     SG        3    3.How did the Manager ensure that all elements of the scope of
                                                                                                  1       1       1       3
                              work were planned?
5.2.6   CS     RB        3    3.How did the Manager ensure that all elements of the scope of
                                                                                                  1       1       1       3
                              work were planned?
5.2.6   CS     BE        3    3.How did the Manager ensure that all elements of the scope of
                                                                                                  1       1       1       3
                              work were planned?
                                                                                        Totals    5       5       5      15
5.2.6   CS     BE        4    4.How did the Manager obtain the resources for assigned work?
                                                                                                  3       3       3       9
5.2.6   CS     RB        4    4.How did the Manager obtain the resources for assigned work?
                                                                                                  2       2       1       5
5.2.6   CS     DG        4    4.How did the Manager obtain the resources for assigned work?
                                                                                                  1       1       1       3
5.2.6   CS     SG        4    4.How did the Manager obtain the resources for assigned work?
                                                                                                  1       1       1       3


                                                                                                                                Pg 24
Survey Results




…and the survey says…




                        Pg 25
Cost Risk Rating

              5.00
              4.00
Risk Rating




              3.00
              2.00
              1.00
              0.00




                                                                                                                                          SPACECRAFT/ATLO
                                       FPAA
                          ASSURANCE




                                                                                                         MECHANICAL
                                                                                            ELECTRICAL
                                                          ATTITUDE




                                                                           PHOTOMETER I&T




                                                                                                                                                            COMMUNICATIONS
                                                                                                                      FLIGHT SEGMENT
                                              TELESCOPE




                                                          CONTROL
                          FS MISSION




                                                                                                                       MANAGEMENT
                                                                     Cost Risk
                WBS             No                                   Questions                                                   Cost
                6.1.3                                                           FS MISSION ASSURANCE                               2.77
                6.3.2                                                                            FPAA                              2.38
                6.3.4                                                                      TELESCOPE                               2.29
                5.2.6                                                               ATTITUDE CONTROL                               1.84
                6.3.5                                                                  PHOTOMETER I&T                              1.75
                6.3.3                                                                      ELECTRICAL                              1.56
                5.2.3                                                                     MECHANICAL                               1.52
                6.1.1                                                    FLIGHT SEGMENT MANAGEMENT                                 1.44
                5.2/5.3                                                              SPACECRAFT/ATLO                               1.39
                5.2.8                                                                 COMMUNICATIONS                               1.25


                                                                                                                                                                             Pg 26
Schedule Risk Rating

              5.00
              4.00
Risk Rating




              3.00
              2.00
              1.00
              0.00




                                                                                                      SPACECRAFT/ATLO
                          FPAA




                                               ASSURANCE




                                                                                                                        MECHANICAL
                                                                                         ELECTRICAL
                                                            ATTITUDE




                                                                        PHOTOMETER I&T




                                                                                                                                            COMMUNICATIONS




                                                                                                                                                             FLIGHT SEGMENT
                                                            CONTROL
                                  TELESCOPE




                                               FS MISSION




                                                                                                                                                              MANAGEMENT
                                                             Schedule Risks
                WBS          No                                Questions                                                     Sched
                6.3.2                                                                          FPAA                                  2.39
                6.3.4                                                                    TELESCOPE                                   2.28
                6.1.3                                                         FS MISSION ASSURANCE                                   2.06
                5.2.6                                                             ATTITUDE CONTROL                                   1.83
                6.3.5                                                                PHOTOMETER I&T                                  1.76
                6.3.3                                                                    ELECTRICAL                                  1.65
                5.2/5.3                                                            SPACECRAFT/ATLO                                   1.52
                5.2.3                                                                   MECHANICAL                                   1.52
                5.2.8                                                               COMMUNICATIONS                                   1.37
                6.1.1                                                  FLIGHT SEGMENT MANAGEMENT                                     1.36


                                                                                                                                                                              Pg 27
Technical Risk Rating

              5.00
              4.00
Risk Rating




              3.00
              2.00
              1.00
              0.00




                                                                                          SPACECRAFT/ATLO
                          FPAA




                                                                                                            ASSURANCE




                                                                                                                                                 MECHANICAL
                                                                             ELECTRICAL
                                                ATTITUDE




                                                           PHOTOMETER I&T




                                                                                                                         COMMUNICATIONS




                                                                                                                                                              FLIGHT SEGMENT
                                  TELESCOPE




                                                CONTROL




                                                                                                            FS MISSION




                                                                                                                                                               MANAGEMENT
                                                           Technical Risks
                WBS          No                               Questions                                                                   Tech
                6.3.2                                                                               FPAA                                  2.19
                6.3.4                                                                         TELESCOPE                                   2.16
                5.2.6                                                                  ATTITUDE CONTROL                                   1.64
                6.3.5                                                                     PHOTOMETER I&T                                  1.59
                6.3.3                                                                         ELECTRICAL                                  1.38
                5.2/5.3                                                                 SPACECRAFT/ATLO                                   1.35
                6.1.3                                                              FS MISSION ASSURANCE                                   1.29
                5.2.8                                                                    COMMUNICATIONS                                   1.24
                5.2.3                                                                        MECHANICAL                                   1.24
                6.1.1                                                       FLIGHT SEGMENT MANAGEMENT                                     1.20


                                                                                                                                                                               Pg 28
Risk Rating by WBS
                                                                                                Risk Rating
WBS     No                                 Questions                                   Cost   Sched    Tech   Total
6.1.1   1    1.What is the Manager’s scope of work? Does the Manager know what
                                                                                       1.33    1.33    1.40   3.83
             scope of work is his/her responsibility?
6.1.1   2    2.How did the Manager plan the scope of work into control accounts?
                                                                                       1.17    1.33    1.20   3.50
6.1.1   3    3.How did the Manager ensure that all elements of the scope of work
                                                                                       1.20    1.40    1.20   3.17
             were planned?
6.1.1   4    4.How did the Manager obtain the resources for assigned work?             1.33    1.33    1.00   3.33
6.1.1   5    5.Ask the Manager to describe the resource development process.           1.40    1.17    1.00   3.00
6.1.1   6    6.How did the Manager come to an agreement of the scope, hours,
                                                                                       1.50    1.33    1.00   3.50
             dollars and schedule?
6.1.1   7    7.Ask the Manager to show the team the schedule milestones used in the
             planning of the control accounts. The Manager should discuss:             1.00    1.00    1.00   2.83

6.1.1   8    8.Ask the Manager how the work was time phased to achieve the
                                                                                       1.40    1.33    1.00   3.17
             schedule.
6.1.1   9    9.Ask the Manager to identify any known risks that may affect the plan.
                                                                                       1.67    1.17    1.20   3.83
6.1.1   10   10.Are the Manager's resources adequately planned and correctly time
             phased to meet the plan? Progress of each plan should relate to earned    1.33    1.17    1.00   3.33
             value
6.1.1   11   11.Ask the Manager why he/she chose a particular type of earned value
                                                                                       1.33    1.33    1.40   3.83
             method?
6.1.1   12   12.Does the earned value method used make sense for the type of work
             being performed? Can you measure performance? Is the Manager using
             milestones to measure accomplishments? Does the Manager use the           1.20    1.00    1.00   2.50
             LOE method; and is the LOE in support of measurable

6.1.1   13   13.How does the Manager manage his/her plan?                              1.50    1.50    1.20   4.00
6.1.1   14   14.How is the baseline maintained?                                        2.00    1.80    1.80   4.67
6.1.1   15   15.What is the project’s risk management process? How is risk
                                                                                       1.50    1.50    1.50   3.00
             incorporated into the EAC?
6.1.1   16   16.What is the process for reviewing and updating EACs?                   2.00    1.75    1.50   3.50
6.1.1   17   17.How does the CAM update the schedule? How often are schedules
                                                                                       1.67    1.67    1.00   4.33
             updated?
                           FLIGHT SEGMENT MANAGEMENT Total Scores by WBS               1.44    1.36    1.20   3.49

                                                                                                                      Pg 29
Risk Rating




                                 0.00
                                        1.00
                                               2.00
                                                      3.00
                                                             4.00
                                                                    5.00
                                                                           6.00
                                                                                  7.00
                                                                                         8.00
             9.Ask the Manager
                 to identify any




        9
               known risks that
             may affect the plan.
                  15.What is the
                   project’s risk




        15
                   management
               process? How is
                   16.What is the
                    process for




        16
                   reviewing and
                 updating EACs?
             7.Ask the Manager
              to show the team




        7
                  the schedule
             milestones used in
                 4.How did the
             Manager obtain the




        4
                 resources for
              assigned work?
                         10.Are the
                         Manager's




        10
                         resources
                        adequately
                  6.How did the
               Manager come to




        6
                an agreement of
               the scope, hours,
               13.How does the
               Manager manage




        13
                  his/her plan?
             5.Ask the Manager
                to describe the



        5
                    resource
                  development
                  12.Does the
        12        earned value
             method used make
              sense for the type
                     14.How is the
                        baseline
        14




                     maintained?
             8.Ask the Manager
              how the work was
        8




                time phased to
                   achieve the
                                                                                                Risk Rating by Question




                  2.How did the
               Manager plan the
        2




              scope of work into
              control accounts?
                     11.Ask the
                   Manager why
        11




                  he/she chose a
                 particular type of
                  3.How did the
               Manager ensure
        3




             that all elements of
              the scope of work
                  1.What is the
              Manager’s scope
        1




             of work? Does the
                Manager know
Pg 30




                17.How does the
                 CAM update the
        17




                 schedule? How
                      often are
Risk Rating by Question

                                                                                                               Risk Rating
No                                             Questions                                              Cost   Sched    Tech    Total
 9   9.Ask the Manager to identify any known risks that may affect the plan.                          2.44    2.40    2.24     6.86
15   15.What is the project’s risk management process? How is risk incorporated into the EAC?         2.43    2.45    2.24     6.69
16   16.What is the process for reviewing and updating EACs?                                          2.20    2.07    1.75     5.78
 7   7.Ask the Manager to show the team the schedule milestones used in the planning of the control
                                                                                                      1.82    1.99    1.43     5.15
     accounts. The Manager should discuss:
 4   4.How did the Manager obtain the resources for assigned work?                                    1.83    1.90    1.43     5.10
10   10.Are the Manager's resources adequately planned and correctly time phased to meet the plan?
                                                                                                      1.87    1.72    1.49     4.96
     Progress of each plan should relate to earned value
 6   6.How did the Manager come to an agreement of the scope, hours, dollars and schedule?            1.85    1.72    1.55     4.88
13   13.How does the Manager manage his/her plan?                                                     1.68    1.61    1.50     4.78
 5   5.Ask the Manager to describe the resource development process.                                  1.72    1.66    1.42     4.59
12   12.Does the earned value method used make sense for the type of work being performed? Can you
     measure performance? Is the Manager using milestones to measure accomplishments? Does the
                                                                                                      1.76    1.61    1.30     4.58
     Manager use the LOE method; and is the LOE in support of measurable

14   14.How is the baseline maintained?                                                               1.84    1.70    1.50     4.58
 8   8.Ask the Manager how the work was time phased to achieve the schedule.                          1.64    1.70    1.44     4.52
 2   2.How did the Manager plan the scope of work into control accounts?                              1.60    1.52    1.37     4.48
11   11.Ask the Manager why he/she chose a particular type of earned value method?                    1.64    1.54    1.30     4.44
 3   3.How did the Manager ensure that all elements of the scope of work were planned?                1.57    1.59    1.38     4.42
 1   1.What is the Manager’s scope of work? Does the Manager know what scope of work is his/her
                                                                                                      1.45    1.38    1.30     4.08
     responsibility?
17   17.How does the CAM update the schedule? How often are schedules updated?                        1.58    1.58    1.31     4.06




                                                                                                                             Pg 31
The Out-Brief



Goals
Success Criteria
Observations
Survey Results
Concerns
Request for Actions (RFAs)
Improvements
General Comments




                             Pg 32
The Final Report



Author and submit
report to Program
Office, Project Office
and appropriate line
management




                                      Pg 33
Final Report




               Pg 34
Final Report




               Pg 35
Walk - off




             Pg 36

More Related Content

What's hot

D brown gbezos_shirshorn
D brown gbezos_shirshornD brown gbezos_shirshorn
D brown gbezos_shirshornNASAPMC
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.johnNASAPMC
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristenNASAPMC
 
Graham dave
Graham daveGraham dave
Graham daveNASAPMC
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseNASAPMC
 
Competentia Presentation
Competentia PresentationCompetentia Presentation
Competentia Presentationkingk99
 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
 
Doug.sander
Doug.sanderDoug.sander
Doug.sanderNASAPMC
 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycuttNASAPMC
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1NASAPMC
 
Dittemore.gary
Dittemore.garyDittemore.gary
Dittemore.garyNASAPMC
 
Dumbacher2012 pmchallenge
Dumbacher2012 pmchallengeDumbacher2012 pmchallenge
Dumbacher2012 pmchallengeNASAPMC
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmermanNASAPMC
 
Davis.howard
Davis.howardDavis.howard
Davis.howardNASAPMC
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardoNASAPMC
 
Armstrong
ArmstrongArmstrong
ArmstrongNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Smith.marshall.bryant
Smith.marshall.bryantSmith.marshall.bryant
Smith.marshall.bryantNASAPMC
 

What's hot (19)

D brown gbezos_shirshorn
D brown gbezos_shirshornD brown gbezos_shirshorn
D brown gbezos_shirshorn
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
 
Graham dave
Graham daveGraham dave
Graham dave
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
 
Competentia Presentation
Competentia PresentationCompetentia Presentation
Competentia Presentation
 
Ed.mango
Ed.mangoEd.mango
Ed.mango
 
Doug.sander
Doug.sanderDoug.sander
Doug.sander
 
Tim.honeycutt
Tim.honeycuttTim.honeycutt
Tim.honeycutt
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1
 
Dittemore.gary
Dittemore.garyDittemore.gary
Dittemore.gary
 
Dumbacher2012 pmchallenge
Dumbacher2012 pmchallengeDumbacher2012 pmchallenge
Dumbacher2012 pmchallenge
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmerman
 
Davis.howard
Davis.howardDavis.howard
Davis.howard
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardo
 
Armstrong
ArmstrongArmstrong
Armstrong
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Smith.marshall.bryant
Smith.marshall.bryantSmith.marshall.bryant
Smith.marshall.bryant
 

Viewers also liked

Backup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventorsBackup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventorsNASAPMC
 
Taylor.ron
Taylor.ronTaylor.ron
Taylor.ronNASAPMC
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.jNASAPMC
 
Kerby.jerald
Kerby.jeraldKerby.jerald
Kerby.jeraldNASAPMC
 
Ronnie goodin.ronnie contracts
Ronnie goodin.ronnie contractsRonnie goodin.ronnie contracts
Ronnie goodin.ronnie contractsNASAPMC
 
Terry.cooke davies
Terry.cooke daviesTerry.cooke davies
Terry.cooke daviesNASAPMC
 
Ann over
Ann overAnn over
Ann overNASAPMC
 
Gill.paul
Gill.paulGill.paul
Gill.paulNASAPMC
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngbloodNASAPMC
 
Krasa.lee
Krasa.leeKrasa.lee
Krasa.leeNASAPMC
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012NASAPMC
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbieNASAPMC
 
Derleth.james
Derleth.jamesDerleth.james
Derleth.jamesNASAPMC
 
Juli.thomas
Juli.thomasJuli.thomas
Juli.thomasNASAPMC
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegemanNASAPMC
 
Kelly.michael
Kelly.michaelKelly.michael
Kelly.michaelNASAPMC
 
Carol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalCarol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalNASAPMC
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robertNASAPMC
 

Viewers also liked (20)

Backup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventorsBackup ronniegoodinchampionsinventors
Backup ronniegoodinchampionsinventors
 
Taylor.ron
Taylor.ronTaylor.ron
Taylor.ron
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.j
 
Kerby.jerald
Kerby.jeraldKerby.jerald
Kerby.jerald
 
Ronnie goodin.ronnie contracts
Ronnie goodin.ronnie contractsRonnie goodin.ronnie contracts
Ronnie goodin.ronnie contracts
 
Terry.cooke davies
Terry.cooke daviesTerry.cooke davies
Terry.cooke davies
 
Ann over
Ann overAnn over
Ann over
 
Gill.paul
Gill.paulGill.paul
Gill.paul
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngblood
 
Krasa.lee
Krasa.leeKrasa.lee
Krasa.lee
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbie
 
Derleth.james
Derleth.jamesDerleth.james
Derleth.james
 
Juli.thomas
Juli.thomasJuli.thomas
Juli.thomas
 
Grieman
GriemanGrieman
Grieman
 
Ray hines stegeman
Ray hines stegemanRay hines stegeman
Ray hines stegeman
 
Kelly.michael
Kelly.michaelKelly.michael
Kelly.michael
 
Carol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalCarol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinal
 
Symons
SymonsSymons
Symons
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robert
 

Similar to Gonzalez.matthew

Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
David.graham
David.grahamDavid.graham
David.grahamNASAPMC
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerbyNASAPMC
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project ManagementMartin Mehalchin
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porterNASAPMC
 
R simpson elee
R simpson eleeR simpson elee
R simpson eleeNASAPMC
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
Lean product development implementation
Lean product development implementationLean product development implementation
Lean product development implementationITZHAK123
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Walley.tina
Walley.tinaWalley.tina
Walley.tinaNASAPMC
 
How to choose and implement wms
How to choose and implement wmsHow to choose and implement wms
How to choose and implement wmsSubhan Novianda
 
Project management - kickoff - opensource erp
Project management - kickoff - opensource erpProject management - kickoff - opensource erp
Project management - kickoff - opensource erpThanh Nguyen
 
Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02guest2aa104
 
Project Governance Model
Project Governance ModelProject Governance Model
Project Governance ModelConstient
 
at ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systemsat ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained SystemsBrent Barton
 
Martt.anne
Martt.anneMartt.anne
Martt.anneNASAPMC
 

Similar to Gonzalez.matthew (20)

Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
David.graham
David.grahamDavid.graham
David.graham
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerby
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project Management
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
 
R simpson elee
R simpson eleeR simpson elee
R simpson elee
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
Lean product development implementation
Lean product development implementationLean product development implementation
Lean product development implementation
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Walley.tina
Walley.tinaWalley.tina
Walley.tina
 
How to choose and implement wms
How to choose and implement wmsHow to choose and implement wms
How to choose and implement wms
 
Integrated Operations io-PMO
Integrated Operations io-PMOIntegrated Operations io-PMO
Integrated Operations io-PMO
 
Project management - kickoff - opensource erp
Project management - kickoff - opensource erpProject management - kickoff - opensource erp
Project management - kickoff - opensource erp
 
Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02
 
Project Governance Model
Project Governance ModelProject Governance Model
Project Governance Model
 
at ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systemsat ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systems
 
Martt.anne
Martt.anneMartt.anne
Martt.anne
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 

Recently uploaded (20)

New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 

Gonzalez.matthew

  • 1. Planning and Conducting an Integrated Baseline Review (IBR) Matthew T. Gonzales, Project Business Manager Jet Propulsion Laboratory 818-354-3629 Used with Permission Pg 1
  • 3. Organization ‘If you can't describe what you are doing as a process, you don't know what you're doing.’ W. Edward Deming Pg 3
  • 4. IBR as a Process Pre-Phase A emphasizes the Phase A emphasizes the EV Phase B emphasizes the Phase C emphasizes use of EVM Phase D emphasizes use of EVM contractors and projects readiness Process and Initial Baseline validity of baseline to complete and the validity of EAC to and the validity of EAC to for EVM Plan work complete work complete work Formulation Implementation Pre-Phase A Phase A Phase B Phase C Phase D Project Emphasis: Project Emphasis: Project Emphasis: Project Emphasis: Project Emphasis: - System Definition - Complete System Definition - Project Requirements - Complete Flight and Ground - Integration of Flight HW - Identify potential contractors - Establish Requirements Baselined Designs and SW and teammates - Select Contractors - Preliminary Design - Conduct component and SS - Integrate Payload and - Identify contractors above - Award Contracts with EVM Established CDRs Launch Vehicle $20M DRDs - LL Procurements Let - Build BB and EMs - Initiate Acceptance Test Program for Flight HW EVM Emphasis: EVM Emphasis: EVM Emphasis: EVM Emphasis: EVM Emphasis: - EVM implementation team - Contractor teams develop - EV System is mature - Implement EV - Implement EV defined initial project cost and schedule - Reports Submitted - Project Office conducts IBR with - Project Office conducts IBR with - Contractors develop EVM baseline - Logs Established emphasis on Risk to Reserves emphasis on Risk to Reserves plan - Contractors submit EV reports - Change Control Exercised - Does Project Plan support - Does Project Plan support I&T - Progress Assessment Visit per DRDs - Project Office conducts IBR with detail design Program (PAV); Contractor presents - Project Office conducts IBR emphasis on Risk to Reserves - Is EV data reliable as a - Is EV data reliable as a predictor EVM plan with emphasis on Process - Project Plan content predictor - Quality of VARs - EVM team evaluates - Compliance to EV Process - Completeness of Planning - Quality of VARs - Is the project using EVM data to - If Validation Review is - Data Quality - Change control process - Is the project using EVM data manage required, EVM teams works - CAM Knowledge - Basis of Estimate for Cost and to manage - Test EAC process with local DCMA - Change Control Schedule - Test EAC process - Quality BOEs - Conduct follow-up PAV - Validity of Baseline relative - Can design be built with - Quality BOEs - Can I&T be completed for - Support KDP A to Scope of Work planned resources - Can HW be built for estimated cost - Support KDP B - Overall robustness of EVM estimated cost - Is there sufficient schedule system - Is there sufficient schedule - Are Risks known and mitigated - Reconciliation to Phase A - Are Risks known and - Reliable reporting Baseline mitigated - Support KDP E - Support KDP C - Reliable reporting - Support KDP D Pg 4
  • 5. Key to Success – Communication – Organization Pg 5
  • 6. IBR Steps Impetus Planning Conducting Caucus and review Out-brief Final Report Pg 6
  • 7. Impetus Impetus for an Integrated Baseline Review  Comply with customer requirements (7120.5d)  Significant change to system design  New Launch Date  ‘Grass roots’ EAC Developed  Over Target Baseline incorporated Pg 7
  • 8. Planning In preparing for battle I have always found that plans are useless, but planning is indispensable. Dwight D. Eisenhower Pg 8
  • 9. Planning Process Flow Timeline Events Process Project IMS restructured for Project IMS resources Project Plan approved Re-plan new launch date and estimated and loaded by SMD PMC. design change into Turbo for pricing Authorized to Proceed. EV Turbo estimates MS Project milestones Project integrated Database imported into MPM. imported in MPM. baseline complete. Complete PMB established. Weight applied. EV Set ‘Over Target Jul ‘06 Plan Set Baseline’ 1st Schedule updated on Update to MPM Generate and submit Month weekly cadence. database. CPR Format 1 in EV update Weekly metrics ACWP and BCWP for support of customer cycle implemented. July month end MMR Review EV metrics Corrective actions Changes to S/C and & analysis reveals assigned/reviewed. Mtl plans and EV Aug ‘06 Analysis planning Implementation approved methods complete anomalies. by PO and implemented prior to Aug close. Pg 9
  • 10. Planning Process Flow Timeline Events Process 2nd Submit CPR Format 1. Corrective actions IBR date negotiated Month Planning changes closed. EV and VARs with all affected EV update incorporated. EV reviewed at project parties. Set for Nov. cycle metrics improve. MMR Sep ‘06 Project office IBR scope, Contractor, HQ/DPO Project generates and briefs schedule and team and project team CDR IBR information membership briefed on IBR plan package. finalized. Oct ‘06 IBR Coordination Day 1 -IBR In-Brief Update to MPM Day 2 – Data Review meeting with Review JPL database. Project Office Review team audits Team week before BATC EV Surveillance ACWP and BCWP for CAM notebooks. Project review BATC Project end July month Office Team caucus. IBR EV metrics Day 3 – CAM Interviews Day 4 – Data Review/ analysis reveals Project Technical Lead Informal Out-brief Formal Nov ‘06 planning conducts interview. All team Review Survey Results Out-brief anomalies. members complete survey 3-4 slide contractor feedback Pg 10
  • 11. Planning Plan for your review  Anticipated KDP  Project Phase  Working with contractors Define IBR as early as possible  Scope, Goals, Purpose  Team membership with roles and responsibilities  Required documents for review  Work with contractor on logistics Communicate  3 briefings in preparation for review  Need to train interviewers as well as interviewees  Provide contractor with questions ahead of time Pg 11
  • 12. The In-Brief Preamble Pg 12
  • 13. John Wooden: A Coaching Legend UCLA's basketball program has the international reputation of being No. 1. There is a major reason for that his name is John Robert Wooden, who announced his retirement after the 1974-75 season (his 27th campaign) as the Bruins' head coach with the winningest record in all of the sport's history. Wooden celebrated his 92nd birthday on Oct. 14, 2002. Wooden concluded his 40 years as a head coach that season and his 885-203 overall career win- loss record (a percentage of .813) is unequaled. A large part of that success was at UCLA. In 27 years as Bruin coach, his teams registered 620 wins, and only 147 losses while earning far more national honors than any other university. Under Wooden, UCLA won an unprecedented 10 NCAA championships, including seven consecutive (1966-73). Included in the string is one of the most amazing win streaks in all of sports, 38 straight NCAA tournament victories. In addition, there is the all-time NCAA consecutive winning-streak record of 88 games over four seasons, which included consecutive 30-0 seasons in 1971-72 and 1972-73. UCLA also won 149 of 151 games in Pauley Pavilion during his Bruin tenure. John Wooden is the only coach to compile four undefeated seasons of 30-0 and his Bruin teams captured 19 conference championships (the record of which Wooden is most proud). Coach Wooden is the first person to be inducted into the National Basketball Hall of Fame as both a player and coach Pg 13
  • 14. John Wooden Quotes “It’s the little details that are vital. Little things make big things happen” “If you don’t have time to do it right, when will you have the time to do it over” “Winning takes talent, to repeat it takes character” “It is what we learn after we know it all that really counts” “Be prepared and be honest” “Things turn out best for the people who make the best of the way things turn out” Pg 14
  • 15. Use your review In-brief as a time to Inspire Pg 15
  • 16. The In-Brief Project Overview Goals Success Criteria Process Overview Documents Logistics/Schedule General Comments Pg 16
  • 17. Data Review - Wed, Nov. 15th 8am – 5pm • Control Account Managers Notebooks – Turbo reports • Reviewing for completeness – Schedules , by WBS element and by IPT and consistency in the plans. – Control Account Plans to Work Package level • Is the work fully accounted for of detail and Earned Value Milestone Report and plan appropriately. – Current WBS and WBS Dictionary • Are all resources planned and available when required. – Estimating methodology and documentation to enable assessment of the basis of the • Is the time phasing of cost and estimates schedule consistent. – Work Authorization Documents for authorized • Is EV planned in a way to yield control accounts. accurate results. – Performance Measurement Reports (CPR • Are analysis tools available Format 1) and utilized. – Budget Change Requests (if applicable) • Are changes tracked and managed – Approved liens and KVRs and recovery plans • Are they adhering to the BATC • Other Ball documentation required for the IBR: way of planning and managing – Current Contract SOW projects. – BATC System Description, Kepler EVM Plan Supplement Pg 17
  • 19. Conducting Interviews Select WBS elements for review  Risk driven (technical and/or programmatic)  Phase specific Select appropriate questions  Phase specific  Basis of Estimate  Discern risk  Communicate early Develop interview teams  Led by technical representative  Small teams  Provide training on questions Discussions/Interviews  Conversational  ~ 2 hours  Document results Pg 19
  • 20. CAM Interviews – Nov. 16th 8am – 5pm IBR CAM Interview Schedule DRAFT WBS WBS Description Day Interview Time 6.1.1 FS Management Thurs 08:00 – 10:00 5.2.6 Attitude Control Thurs 08:00 – 10:00 5.2.8 Communications Thurs 08:00 – 10:00 6.1.3 FS Mission Assurance Thurs 10:00 – 12:00 6.3.2 FPAA Thurs 10:00 – 12:00 6.3.3 Electrical Thurs 10:00 – 12:00 6.3.4 Telescope Thurs 1:00 – 3:00 5.2.3 Mechanical Subsystem Thurs 1:00 – 3:00 6.3.5 Photo Integration Test Thurs 3:00 – 5:00 5.2.11 Spacecraft I&T Thurs 3:00 – 5:00 5.3 System ATLO IBR CAM Interview Schedule Technical Leads NASA Reps Discovery Program Office Support Peg Leslie Jim Sarah Michael Renee Pam Jack Steve Nate John Robert Dan Maura Bill Tim Cal Joe WBS WBS Description Frerking Livesay Fanson Gavit Moore Leck Marcum Graham McClard Porter Keidel Bitten Graham Fujieh Epping Clark Cambers Fischetti 6.1.1 FS Management 1 1 1 1 5.2.6 Attitude Control 1 1 1 1 5.2.8 Communications 1 1 1 1 6.1.3 FS Mission Assurance 1 1 1 1 6.3.2 FPAA 1 1 1 1 6.3.3 Electrical 1 1 1 1 6.3.4 Telescope 1 1 1 1 5.2.3 Mechanical Subsystem 1 1 1 1 6.3.5 Photo Integration Test 1 1 1 1 5.2.11 Spacecraft I&T 1 1 1 1 5.3 System ATLO Pg 20
  • 21. CAM Questionnaire Questions Rating Low Med High 1.What is the Manager’s scope of work? Does the Manager know what scope of work is his/her responsibility? Cost 1 2 3 4 5 –The Manager should be able to show the team a Statement of Work (SOW) paragraph, a WBS, PWBS, or CWBS narrative, and a Work Authorization Document that correlates to the task. Schedule 1 2 3 4 5 Comments: Technical 1 2 3 4 5 2.How did the Manager plan the scope of work into control accounts? Cost 1 2 3 4 5 –The SOW defines the effort. The WBS, PWBS, or CWBS provides specifics, such as work definition. The work authorization and change documentation should show information such as the Schedule 1 2 3 4 5 dollars/hours, period of performance, and description of the scope of work and any changes. Comments: Technical 1 2 3 4 5 3.How did the Manager ensure that all elements of the scope of work were planned? Cost 1 2 3 4 5 –The Manager should be able to show the team the work packages breaking down the scope of work, and the budget associated with each work package. The sum of the work packages should be Schedule 1 2 3 4 5 the control account budget. Each control account should contain a specific scope of work. Comments: Technical 1 2 3 4 5 Pg 21
  • 23. Caucus and Review Review survey responses  By interview, by question  Look for outliers and discuss.  Opportunity to share thoughts and observations  Normalize metrics  Do metrics support subjective risk observations Pg 23
  • 24. Caucus and Review Low Med High 12 36 60 Risk Rating WBS CAM Intvr No Questions Cost Sched Tech Total 5.2.6 CS SG 1 1.What is the Manager’s scope of work? Does the Manager 1 2 3 6 know what scope of work is his/her responsibility? 5.2.6 CS DG 1 1.What is the Manager’s scope of work? Does the Manager 1 1 2 4 know what scope of work is his/her responsibility? 5.2.6 CS RB 1 1.What is the Manager’s scope of work? Does the Manager 1 1 1 3 know what scope of work is his/her responsibility? 5.2.6 CS BE 1 1.What is the Manager’s scope of work? Does the Manager 1 1 1 3 know what scope of work is his/her responsibility? Totals 4 5 7 16 5.2.6 CS DG 2 2.How did the Manager plan the scope of work into control 1 1 1 3 accounts? 5.2.6 CS SG 2 2.How did the Manager plan the scope of work into control 1 1 1 3 accounts? 5.2.6 CS RB 2 2.How did the Manager plan the scope of work into control 1 1 1 3 accounts? 5.2.6 CS BE 2 2.How did the Manager plan the scope of work into control 1 1 1 3 accounts? Totals 4 4 4 12 5.2.6 CS DG 3 3.How did the Manager ensure that all elements of the scope of 2 2 2 6 work were planned? 5.2.6 CS SG 3 3.How did the Manager ensure that all elements of the scope of 1 1 1 3 work were planned? 5.2.6 CS RB 3 3.How did the Manager ensure that all elements of the scope of 1 1 1 3 work were planned? 5.2.6 CS BE 3 3.How did the Manager ensure that all elements of the scope of 1 1 1 3 work were planned? Totals 5 5 5 15 5.2.6 CS BE 4 4.How did the Manager obtain the resources for assigned work? 3 3 3 9 5.2.6 CS RB 4 4.How did the Manager obtain the resources for assigned work? 2 2 1 5 5.2.6 CS DG 4 4.How did the Manager obtain the resources for assigned work? 1 1 1 3 5.2.6 CS SG 4 4.How did the Manager obtain the resources for assigned work? 1 1 1 3 Pg 24
  • 25. Survey Results …and the survey says… Pg 25
  • 26. Cost Risk Rating 5.00 4.00 Risk Rating 3.00 2.00 1.00 0.00 SPACECRAFT/ATLO FPAA ASSURANCE MECHANICAL ELECTRICAL ATTITUDE PHOTOMETER I&T COMMUNICATIONS FLIGHT SEGMENT TELESCOPE CONTROL FS MISSION MANAGEMENT Cost Risk WBS No Questions Cost 6.1.3 FS MISSION ASSURANCE 2.77 6.3.2 FPAA 2.38 6.3.4 TELESCOPE 2.29 5.2.6 ATTITUDE CONTROL 1.84 6.3.5 PHOTOMETER I&T 1.75 6.3.3 ELECTRICAL 1.56 5.2.3 MECHANICAL 1.52 6.1.1 FLIGHT SEGMENT MANAGEMENT 1.44 5.2/5.3 SPACECRAFT/ATLO 1.39 5.2.8 COMMUNICATIONS 1.25 Pg 26
  • 27. Schedule Risk Rating 5.00 4.00 Risk Rating 3.00 2.00 1.00 0.00 SPACECRAFT/ATLO FPAA ASSURANCE MECHANICAL ELECTRICAL ATTITUDE PHOTOMETER I&T COMMUNICATIONS FLIGHT SEGMENT CONTROL TELESCOPE FS MISSION MANAGEMENT Schedule Risks WBS No Questions Sched 6.3.2 FPAA 2.39 6.3.4 TELESCOPE 2.28 6.1.3 FS MISSION ASSURANCE 2.06 5.2.6 ATTITUDE CONTROL 1.83 6.3.5 PHOTOMETER I&T 1.76 6.3.3 ELECTRICAL 1.65 5.2/5.3 SPACECRAFT/ATLO 1.52 5.2.3 MECHANICAL 1.52 5.2.8 COMMUNICATIONS 1.37 6.1.1 FLIGHT SEGMENT MANAGEMENT 1.36 Pg 27
  • 28. Technical Risk Rating 5.00 4.00 Risk Rating 3.00 2.00 1.00 0.00 SPACECRAFT/ATLO FPAA ASSURANCE MECHANICAL ELECTRICAL ATTITUDE PHOTOMETER I&T COMMUNICATIONS FLIGHT SEGMENT TELESCOPE CONTROL FS MISSION MANAGEMENT Technical Risks WBS No Questions Tech 6.3.2 FPAA 2.19 6.3.4 TELESCOPE 2.16 5.2.6 ATTITUDE CONTROL 1.64 6.3.5 PHOTOMETER I&T 1.59 6.3.3 ELECTRICAL 1.38 5.2/5.3 SPACECRAFT/ATLO 1.35 6.1.3 FS MISSION ASSURANCE 1.29 5.2.8 COMMUNICATIONS 1.24 5.2.3 MECHANICAL 1.24 6.1.1 FLIGHT SEGMENT MANAGEMENT 1.20 Pg 28
  • 29. Risk Rating by WBS Risk Rating WBS No Questions Cost Sched Tech Total 6.1.1 1 1.What is the Manager’s scope of work? Does the Manager know what 1.33 1.33 1.40 3.83 scope of work is his/her responsibility? 6.1.1 2 2.How did the Manager plan the scope of work into control accounts? 1.17 1.33 1.20 3.50 6.1.1 3 3.How did the Manager ensure that all elements of the scope of work 1.20 1.40 1.20 3.17 were planned? 6.1.1 4 4.How did the Manager obtain the resources for assigned work? 1.33 1.33 1.00 3.33 6.1.1 5 5.Ask the Manager to describe the resource development process. 1.40 1.17 1.00 3.00 6.1.1 6 6.How did the Manager come to an agreement of the scope, hours, 1.50 1.33 1.00 3.50 dollars and schedule? 6.1.1 7 7.Ask the Manager to show the team the schedule milestones used in the planning of the control accounts. The Manager should discuss: 1.00 1.00 1.00 2.83 6.1.1 8 8.Ask the Manager how the work was time phased to achieve the 1.40 1.33 1.00 3.17 schedule. 6.1.1 9 9.Ask the Manager to identify any known risks that may affect the plan. 1.67 1.17 1.20 3.83 6.1.1 10 10.Are the Manager's resources adequately planned and correctly time phased to meet the plan? Progress of each plan should relate to earned 1.33 1.17 1.00 3.33 value 6.1.1 11 11.Ask the Manager why he/she chose a particular type of earned value 1.33 1.33 1.40 3.83 method? 6.1.1 12 12.Does the earned value method used make sense for the type of work being performed? Can you measure performance? Is the Manager using milestones to measure accomplishments? Does the Manager use the 1.20 1.00 1.00 2.50 LOE method; and is the LOE in support of measurable 6.1.1 13 13.How does the Manager manage his/her plan? 1.50 1.50 1.20 4.00 6.1.1 14 14.How is the baseline maintained? 2.00 1.80 1.80 4.67 6.1.1 15 15.What is the project’s risk management process? How is risk 1.50 1.50 1.50 3.00 incorporated into the EAC? 6.1.1 16 16.What is the process for reviewing and updating EACs? 2.00 1.75 1.50 3.50 6.1.1 17 17.How does the CAM update the schedule? How often are schedules 1.67 1.67 1.00 4.33 updated? FLIGHT SEGMENT MANAGEMENT Total Scores by WBS 1.44 1.36 1.20 3.49 Pg 29
  • 30. Risk Rating 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.Ask the Manager to identify any 9 known risks that may affect the plan. 15.What is the project’s risk 15 management process? How is 16.What is the process for 16 reviewing and updating EACs? 7.Ask the Manager to show the team 7 the schedule milestones used in 4.How did the Manager obtain the 4 resources for assigned work? 10.Are the Manager's 10 resources adequately 6.How did the Manager come to 6 an agreement of the scope, hours, 13.How does the Manager manage 13 his/her plan? 5.Ask the Manager to describe the 5 resource development 12.Does the 12 earned value method used make sense for the type 14.How is the baseline 14 maintained? 8.Ask the Manager how the work was 8 time phased to achieve the Risk Rating by Question 2.How did the Manager plan the 2 scope of work into control accounts? 11.Ask the Manager why 11 he/she chose a particular type of 3.How did the Manager ensure 3 that all elements of the scope of work 1.What is the Manager’s scope 1 of work? Does the Manager know Pg 30 17.How does the CAM update the 17 schedule? How often are
  • 31. Risk Rating by Question Risk Rating No Questions Cost Sched Tech Total 9 9.Ask the Manager to identify any known risks that may affect the plan. 2.44 2.40 2.24 6.86 15 15.What is the project’s risk management process? How is risk incorporated into the EAC? 2.43 2.45 2.24 6.69 16 16.What is the process for reviewing and updating EACs? 2.20 2.07 1.75 5.78 7 7.Ask the Manager to show the team the schedule milestones used in the planning of the control 1.82 1.99 1.43 5.15 accounts. The Manager should discuss: 4 4.How did the Manager obtain the resources for assigned work? 1.83 1.90 1.43 5.10 10 10.Are the Manager's resources adequately planned and correctly time phased to meet the plan? 1.87 1.72 1.49 4.96 Progress of each plan should relate to earned value 6 6.How did the Manager come to an agreement of the scope, hours, dollars and schedule? 1.85 1.72 1.55 4.88 13 13.How does the Manager manage his/her plan? 1.68 1.61 1.50 4.78 5 5.Ask the Manager to describe the resource development process. 1.72 1.66 1.42 4.59 12 12.Does the earned value method used make sense for the type of work being performed? Can you measure performance? Is the Manager using milestones to measure accomplishments? Does the 1.76 1.61 1.30 4.58 Manager use the LOE method; and is the LOE in support of measurable 14 14.How is the baseline maintained? 1.84 1.70 1.50 4.58 8 8.Ask the Manager how the work was time phased to achieve the schedule. 1.64 1.70 1.44 4.52 2 2.How did the Manager plan the scope of work into control accounts? 1.60 1.52 1.37 4.48 11 11.Ask the Manager why he/she chose a particular type of earned value method? 1.64 1.54 1.30 4.44 3 3.How did the Manager ensure that all elements of the scope of work were planned? 1.57 1.59 1.38 4.42 1 1.What is the Manager’s scope of work? Does the Manager know what scope of work is his/her 1.45 1.38 1.30 4.08 responsibility? 17 17.How does the CAM update the schedule? How often are schedules updated? 1.58 1.58 1.31 4.06 Pg 31
  • 32. The Out-Brief Goals Success Criteria Observations Survey Results Concerns Request for Actions (RFAs) Improvements General Comments Pg 32
  • 33. The Final Report Author and submit report to Program Office, Project Office and appropriate line management Pg 33
  • 34. Final Report Pg 34
  • 35. Final Report Pg 35
  • 36. Walk - off Pg 36