SlideShare a Scribd company logo
1 of 8
Download to read offline
8. Project Risk Management
As per PMBOK - "The whole point of undertaking a project is to achieve or establish something
new, to venture, to take chances, to risk. Risk may have positive effects or negative effects on
the project “Schedule” and/or “Cost”. Positive risks are Opportunities and negative risks are
losses or threats; remember both risks are uncertain “percentage of occurrence less than 80%”.
Risk Management purpose is to manage (Plan and implement) these uncertainties.
Following are processes defined in Risk Management Knowledge Area:
5 Process
Groups

Processes

-

Initiation

Planning
8.1. Plan Risk
Management.
8.2. Identify Risks.
8.3. Perform Qualitative
Risk Analysis
8.4. Perform Quantitative
Risk Analysis
8.5. Plan Risk Response

Execution

M&C

Closing

8.6. Monitor
and Control
Risk

We can decide which risks are acceptable and take actions to “Mitigate” or “Avoid”
those risks. If our project risk assessment determines that some risks are excessive,
we may want to consider restructuring the project to within acceptable levels of risk.

-

Deliverables which have uncertainty to be completed successfully can be considered
as risk. For example: after finishing the Project planning you still feel that the scope
might change then it is a Risk. Or even if scope is not well defined then it is a Risk.
Known technical difficulty or complexity will increase project risk. Ambitious goals
always result in risk. Unfamiliarity with the process, or inexperienced personnel,
constitutes project risks. Exterior interfaces cause risks because they can change
and, even if they don’t change, their descriptions or specifications may be
inaccurate. Exterior organizational dependencies create project risks. Incomplete
planning or optimistic cost or schedule goals create risk. If the customer is involved
in schedule dependencies for document review and approval or for delivering
process information, this creates project risks.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
-

Any area over which the project manager does not have control can be project risks.
Anything that is not well understood, anything that is not well documented, and
anything that can change, these all create project risks. Things that haven’t been
tested are always at risk.

-

Three steps approach is very important for all your Projects;
 Identify all Project Risks through “Risk Identification Sessions”
 Analyze that Risk
a. qualitatively – Probability of occurrence
b. quantitatively – Impact if it occurs
 Prepare your responses to those identified and analyzed Risks.

-

Remember you need not evaluate all identified risks or you need not to take actions
on all responded risks either. For example, you identified airplane hitting in to your
building as a project Risk because your office is next to Airport. Probability of
occurrence is .0001. For such kind of risk you need not to find a Response strategy or
need not implement a solution.

8.1 Plan Risk Management
- It is the process of defining how to conduct risk management activities on your
project.
Inputs
-

Enterprise Environmental
Factors
Organizational Process
Assets
Project Scope Statement
Project Management Plan

Tools
-

Planning Meetings and
Analysis

Outputs
-

Risk Management
Plan

Important Contents of “Risk Management Plan”


Methodology: Describes the approaches, tools, and data sources to be used
when doing risk management.



Roles and responsibilities: Defines the team of people responsible for managing
the identified risks and responses and outlines their roles. People outside of the
project team may be named, to keep the risk analysis unbiased.



Budgeting: Defines the budget for risk management for the project. This is
included in the cost baseline.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD


Timing: Defines when and how often the risk management process will be
performed. This process should begin early in the project life cycle and be
revisited throughout project execution.



Risk categories: A good way of providing the structure necessary to identify risks
consistently is to outline the categories of risks in a RBS (Risk Breakdown
Structure.



Definitions of risk probability and impact: Outlines the scales that will be used
during qualitative risk analysis to assess the probability and impact of the risks
that have been identified for a particular project. Scales could be qualitative,
from "very low" to "very high," or quantitative, like a scale from 1 to 5.



Probability and impact matrix: The combination of each risk's probability and
impact will lead to an overall risk rating, which allows the risks to be prioritized.
Revised stakeholder tolerances: Stakeholder tolerances will be defined and
revised as necessary as they pertain to the specific project.



Reporting formats: This component defines the risk register and other risk
reports. Outlines how they will be created and distributed.



Tracking: This component defines how risk will be recorded for the benefit of
this project and future projects, as well as if and how the risk processes will be
audited.

8.2 Identify Risks
- It is the process of determining each risk that may affect the project and then
analyze and document those risks.
Inputs
-

Activity Cost Estimates
Activity Duration Estimates
Risk Management Plan
Scope Baseline
Stakeholder Register
Enterprise Environmental
Factors
Organizational Process
Assets
Project Management Plan

Tools
-

Expert Judgment
Documentation Reviews
Information Gathering
Techniques
Checklist Analysis
Assumptions Analysis
Diagramming Techniques
SWOT analysis

Outputs
-

Risk Register

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
8.3 Perform Qualitative Risk Analysis
- This is the process of prioritizing risks by working out their probability as well as
impact. The result here will be qualitative like “this risk is high, medium, or low
impact risk.”
Inputs
-

Tools

Organizational Process Assets
Project Scope Statement
Risk Management Plan
Risk Register

-

Outputs

Risk Probability and
Impact Assessment
Probability and Impact
Matrix
Risk Data Quality
Assessment
Risk Categorization
Risk Urgency Assessment

-

Risk Register (updates)

8.4 Perform Quantitative Risk Analysis
- That is the process of numerically analyzing the effect of these identified risks on the
overall project objectives.
Inputs
-

Tools

Risk Register
Risk Management Plan
Cost Management Plan
Schedule Management Plan
Organizational Process
Assets

-

-

Outputs

Expert Judgment
Data Gathering and
Representation
Techniques
Quantitative Risk
Analysis and Modeling
Techniques

-

Risk Register (updates)

8.5 Plan Risk Response
- It is the process of developing actions or defines how to respond to enhance positive
risks and/or to reduce negative risks.
Inputs
-

Risk Management Plan
Risk Register

Tools
-

Expert Judgment
Strategies for Negative
Risks
Strategies for Positive
Risks
Contingent Response
Strategy

Outputs
-

Risk Related Contract
Decisions
Risk Register (updates)
Project Management Plan
(updates)
Project Document updates

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
8.6 Risk Monitoring and Control
- It is the process of implementing all those risks plans, tracking the identified risks,
insuring risk management effectiveness through the project life, and monitoring and
identifying new / residual risks.
Inputs

Project Management
Plan (Risk Management Plan)
Risk Register
Work Performance
Information
Performance Reports

-

Tools
-

Risk Reassessment
Risk Audits
Variance and Trend
Analysis
Technical Performance
Information
Reserve Analysis
Status Meetings

Outputs
-

Risk Register (updates)
Change Requests
Organizational Process
Assets (updates)
Project Management Plan
(updates)
Project Document (Updates)

Very Important Concepts:
1. Difference between “Issue” and “Risk”;
-

Issue; a point or matter in question or in dispute, or a matter that is not settled and
under discussion or over which there are opposing views or disagreements.
Risk; an uncertain event or condition that if it occurs, has a positive or negative
effect on a project’s objectives.
Simply, we can say that a “Risk is something that could happen in the future”, while
an “Issue is that risk has became a reality”.
2. Difference between “Threats” and “Opportunities”;

-

Risks are not necessarily “Negative” and they can be simply “Positive”.

-

Threats; are simply the “Negative” risks, while Opportunities are the “Positive” risks.

3. Difference between “Contingency” and “Workaround”;
-

Contingency; a provision in the project management plan to mitigate cost risk
and/or schedule risk. It is simply “an allowance to deal with a problem”, you decide
today “what your contingency will be if a risk occurs”, this can be budget or schedule
oriented.

-

Workaround; it is a response to a negative risk that has occurred and that response
was not planned in advance of the occurrence of the risk event.

-

Generally, when contingency is taken into consideration, this refers to a proactive
PM who is following risk management processes to enhance project success.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
4. Risk Attitudes (Human Factors)
-

There are four types of risk attitudes which are;
I.

Risk Averse Person; such person always uncomfortable with
uncertainty. Such person prefers a more certain outcome and
demands a premium to accept projects of high risk.

II.

Risk Neutral Person; such person always embraces risks for future
payoffs; he looks to risks as opportunity or way to gain additional
payoffs.

III.

Risk Seeker Person; always looks at risks as challenge.

IV.

Risk Tolerant Person; such person doesn’t worry too much about
risks. If a risk actually occurs, he acts all surprised.

5. Utility Theory Basics
-

An appropriate method for describing risk tolerance based on the various
stakeholders' tolerances for risk. This method is depicted using three structures
where the x-axis denotes the money at stake and the y-axis denotes utility, or
the amount of satisfaction the person obtains from the payoff.

-

For “Risk Averse” stakeholder; such person usually requires a premium utility to
accept a high risk.
U

Risk payoffs

-

$

For “Risk Neutral” stakeholder; such person is more concerned about the
expected return on his investment, not on thr risk he maybe taking on.
U

$

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
-

For “Risk Seeker” stakeholder; he prefers uncertain outcomes and is willing to
take the risk; the more the money is that stake, the greater the utility he gets out
of it.
U

$
Example:
-

If there is a chance of 50% to gain 100$ and another chance of 100% to gain 50$, risk
averse person will accept the 2nd choice, while the risk seeker person will prefer the
1st choice and finally, the risk neutral person has no preferences between them
Notes:
-

A person can be both risk averse and risk seeking at different times.

-

Risk attitudes of individuals in a company shape the risk attitude of the company.

-

On an individual level, it is important to know the risk attitudes of the
stakeholders to be able to deal with them properly when talking about “Risk
list”.

6. Project risk management is an iterative process
-

PM has to monitor the risks constantly, watches out for triggers and then,
responds to any risk that already happens and turns to an issue.

-

During the life of the project, factors that define and affect risks will change; you
may have scope changes, environment changes, or even changes in the project
team...etc.

-

Changes open up possible new risks and required new round of planning and
that is why “Risk Management Process is an Iterative process”.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
7. Prioritizing risks is done through two steps
-

“Qualitative Prioritization”
1. Prioritize risks according to their potential effect, i.e. probability and
impact, on the project.
2. Assign each risk a quality like high (H), Medium (M), or low (L).
3. Focus on risks with high priorities to shorten the risks list

-

“Quantitative Prioritization”
1. Numerically defines probability of each risk, from the short risk list that
comes from qualitative prioritization and its consequences on the project
objective.
2. Calculate risk rating = probability * Impact [ex; 70% * 2000$]
3. Narrow down the risks list to the most important ones.

Important notes regarding the “Project Risk Management”;
-

Young dynamic startup companies are usually risk seekers, while established
companies are usually risk averse.

-

“Risk Management Plan” components are very important for the PMP Exam.

-

“Identifying Risks” is an “Iterative Process”

-

The “Check List” tool in “Identify Risk” process is not a chick list with expected
risks, but a check list that helps to identify risks based on the RBS.

-

Risks types are “Business Risks” & “Pure Risks”

-

Tools like Sensitivity Analysis – ex. Tornado Diagram & What-If scenarios -,
Expected Monetary Value (EMV) and Decision Tree are important tools regarding
“Quantitative Risk Analysis”.

-

Probability of events occurring in sequence must be multiplied to calculate the
accumulative probability of occurring of all the events together.

-

Transfer Risk = Deflection of Risk.

-

Mitigation Strategy results in Contingent Response Strategy.

-

The main goal of “Reserve Analysis” as a tool in “Monitor & Control Risks” is to
determine any “Potential Risk”

-

“Project Risk management” is considered to be an item in every “Status
Meeting”.

-

In case of occurrence of surprising unexpected risk, “Workaround” is only
suitable response which always taken directly even before issuing the change
request needed.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD

More Related Content

What's hot

Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsseethaveera
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & templateAllie Gentry
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMauro Jasse
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks ReviewDavid Tennant
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and applicationMarco De Santis, PMP, CFPP
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOKGeoDiga
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementKaustubh Gupta
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementNandi Sudheer
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Managementguest90bddb
 
Stephen Ward: Performance uncertainty management is a more effective approach...
Stephen Ward: Performance uncertainty management is a more effective approach...Stephen Ward: Performance uncertainty management is a more effective approach...
Stephen Ward: Performance uncertainty management is a more effective approach...Association for Project Management
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managmentMalan Bothma
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Risk Management
Risk ManagementRisk Management
Risk ManagementSaqib Raza
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Risk response planning
Risk response planningRisk response planning
Risk response planningRaj Sampat
 

What's hot (20)

Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-concepts
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks Review
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and application
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOK
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Stephen Ward: Performance uncertainty management is a more effective approach...
Stephen Ward: Performance uncertainty management is a more effective approach...Stephen Ward: Performance uncertainty management is a more effective approach...
Stephen Ward: Performance uncertainty management is a more effective approach...
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managment
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Risk response planning
Risk response planningRisk response planning
Risk response planning
 

Viewers also liked

Introduction To Risk Aversion
Introduction To Risk AversionIntroduction To Risk Aversion
Introduction To Risk Aversiontxslr
 
Shannon Park Redevelopment Plan Remodeling with Esri CityEngine
Shannon Park Redevelopment Plan Remodeling with Esri CityEngineShannon Park Redevelopment Plan Remodeling with Esri CityEngine
Shannon Park Redevelopment Plan Remodeling with Esri CityEngineCOGS Presentations
 
Mutual funds in pakistan(final)
Mutual funds in pakistan(final)Mutual funds in pakistan(final)
Mutual funds in pakistan(final)Uswah Nasir
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAgatha Maia Duarte de Assis
 
Risk Management Sir A. S. Chaubal
Risk Management Sir A. S. ChaubalRisk Management Sir A. S. Chaubal
Risk Management Sir A. S. Chaubalsameersanghani
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMarkos Mulat G
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Editionpankajsh10
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 

Viewers also liked (19)

Risk Analysis
Risk AnalysisRisk Analysis
Risk Analysis
 
Risk
RiskRisk
Risk
 
Introduction To Risk Aversion
Introduction To Risk AversionIntroduction To Risk Aversion
Introduction To Risk Aversion
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
 
Shannon Park Redevelopment Plan Remodeling with Esri CityEngine
Shannon Park Redevelopment Plan Remodeling with Esri CityEngineShannon Park Redevelopment Plan Remodeling with Esri CityEngine
Shannon Park Redevelopment Plan Remodeling with Esri CityEngine
 
Mutual funds in pakistan(final)
Mutual funds in pakistan(final)Mutual funds in pakistan(final)
Mutual funds in pakistan(final)
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan Sample
 
Risk Management Sir A. S. Chaubal
Risk Management Sir A. S. ChaubalRisk Management Sir A. S. Chaubal
Risk Management Sir A. S. Chaubal
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Utility theory
Utility theoryUtility theory
Utility theory
 
Ch 12
Ch 12Ch 12
Ch 12
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
Risk And Return
Risk And ReturnRisk And Return
Risk And Return
 
Portfolio theory
Portfolio theoryPortfolio theory
Portfolio theory
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 

Similar to 8. project risk management

Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual EssayPrince Bertrand
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdfNmnKmr2
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docxalinainglis
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as OpportunityGlen Alleman
 
Sameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk managementSameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk managementSameer Mitter
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaGlobalSkillup
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Managementabhinayverma
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship AliAbbas390458
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxGeorgeKabongah2
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptBetshaTizazu2
 
Project risk management: Techniques and strategies
Project risk management: Techniques and strategiesProject risk management: Techniques and strategies
Project risk management: Techniques and strategiesDebashishDas49
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 

Similar to 8. project risk management (20)

Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual Essay
 
Project/Program Risk management
Project/Program Risk managementProject/Program Risk management
Project/Program Risk management
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdf
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
Ch_1_PRM.pdf
Ch_1_PRM.pdfCh_1_PRM.pdf
Ch_1_PRM.pdf
 
Risk guideline
Risk guidelineRisk guideline
Risk guideline
 
Sameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk managementSameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk management
 
11 risk management
11 risk management11 risk management
11 risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Management
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
Li Rmp Prep
Li Rmp PrepLi Rmp Prep
Li Rmp Prep
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
 
Project risk management: Techniques and strategies
Project risk management: Techniques and strategiesProject risk management: Techniques and strategies
Project risk management: Techniques and strategies
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 

More from Mohamed Salah Eldien Mohamed Ali (9)

Series_Certificate
Series_CertificateSeries_Certificate
Series_Certificate
 
Business Management Cert.
Business Management Cert.Business Management Cert.
Business Management Cert.
 
Business Management Cert.
Business Management Cert.Business Management Cert.
Business Management Cert.
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
5. project quality management
5. project quality management5. project quality management
5. project quality management
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
3. project time management
3. project time management3. project time management
3. project time management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
0. project management framework (fundamentals)
0. project management framework (fundamentals)0. project management framework (fundamentals)
0. project management framework (fundamentals)
 

Recently uploaded

Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 

Recently uploaded (20)

Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 

8. project risk management

  • 1. 8. Project Risk Management As per PMBOK - "The whole point of undertaking a project is to achieve or establish something new, to venture, to take chances, to risk. Risk may have positive effects or negative effects on the project “Schedule” and/or “Cost”. Positive risks are Opportunities and negative risks are losses or threats; remember both risks are uncertain “percentage of occurrence less than 80%”. Risk Management purpose is to manage (Plan and implement) these uncertainties. Following are processes defined in Risk Management Knowledge Area: 5 Process Groups Processes - Initiation Planning 8.1. Plan Risk Management. 8.2. Identify Risks. 8.3. Perform Qualitative Risk Analysis 8.4. Perform Quantitative Risk Analysis 8.5. Plan Risk Response Execution M&C Closing 8.6. Monitor and Control Risk We can decide which risks are acceptable and take actions to “Mitigate” or “Avoid” those risks. If our project risk assessment determines that some risks are excessive, we may want to consider restructuring the project to within acceptable levels of risk. - Deliverables which have uncertainty to be completed successfully can be considered as risk. For example: after finishing the Project planning you still feel that the scope might change then it is a Risk. Or even if scope is not well defined then it is a Risk. Known technical difficulty or complexity will increase project risk. Ambitious goals always result in risk. Unfamiliarity with the process, or inexperienced personnel, constitutes project risks. Exterior interfaces cause risks because they can change and, even if they don’t change, their descriptions or specifications may be inaccurate. Exterior organizational dependencies create project risks. Incomplete planning or optimistic cost or schedule goals create risk. If the customer is involved in schedule dependencies for document review and approval or for delivering process information, this creates project risks. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 2. - Any area over which the project manager does not have control can be project risks. Anything that is not well understood, anything that is not well documented, and anything that can change, these all create project risks. Things that haven’t been tested are always at risk. - Three steps approach is very important for all your Projects;  Identify all Project Risks through “Risk Identification Sessions”  Analyze that Risk a. qualitatively – Probability of occurrence b. quantitatively – Impact if it occurs  Prepare your responses to those identified and analyzed Risks. - Remember you need not evaluate all identified risks or you need not to take actions on all responded risks either. For example, you identified airplane hitting in to your building as a project Risk because your office is next to Airport. Probability of occurrence is .0001. For such kind of risk you need not to find a Response strategy or need not implement a solution. 8.1 Plan Risk Management - It is the process of defining how to conduct risk management activities on your project. Inputs - Enterprise Environmental Factors Organizational Process Assets Project Scope Statement Project Management Plan Tools - Planning Meetings and Analysis Outputs - Risk Management Plan Important Contents of “Risk Management Plan”  Methodology: Describes the approaches, tools, and data sources to be used when doing risk management.  Roles and responsibilities: Defines the team of people responsible for managing the identified risks and responses and outlines their roles. People outside of the project team may be named, to keep the risk analysis unbiased.  Budgeting: Defines the budget for risk management for the project. This is included in the cost baseline. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 3.  Timing: Defines when and how often the risk management process will be performed. This process should begin early in the project life cycle and be revisited throughout project execution.  Risk categories: A good way of providing the structure necessary to identify risks consistently is to outline the categories of risks in a RBS (Risk Breakdown Structure.  Definitions of risk probability and impact: Outlines the scales that will be used during qualitative risk analysis to assess the probability and impact of the risks that have been identified for a particular project. Scales could be qualitative, from "very low" to "very high," or quantitative, like a scale from 1 to 5.  Probability and impact matrix: The combination of each risk's probability and impact will lead to an overall risk rating, which allows the risks to be prioritized. Revised stakeholder tolerances: Stakeholder tolerances will be defined and revised as necessary as they pertain to the specific project.  Reporting formats: This component defines the risk register and other risk reports. Outlines how they will be created and distributed.  Tracking: This component defines how risk will be recorded for the benefit of this project and future projects, as well as if and how the risk processes will be audited. 8.2 Identify Risks - It is the process of determining each risk that may affect the project and then analyze and document those risks. Inputs - Activity Cost Estimates Activity Duration Estimates Risk Management Plan Scope Baseline Stakeholder Register Enterprise Environmental Factors Organizational Process Assets Project Management Plan Tools - Expert Judgment Documentation Reviews Information Gathering Techniques Checklist Analysis Assumptions Analysis Diagramming Techniques SWOT analysis Outputs - Risk Register By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 4. 8.3 Perform Qualitative Risk Analysis - This is the process of prioritizing risks by working out their probability as well as impact. The result here will be qualitative like “this risk is high, medium, or low impact risk.” Inputs - Tools Organizational Process Assets Project Scope Statement Risk Management Plan Risk Register - Outputs Risk Probability and Impact Assessment Probability and Impact Matrix Risk Data Quality Assessment Risk Categorization Risk Urgency Assessment - Risk Register (updates) 8.4 Perform Quantitative Risk Analysis - That is the process of numerically analyzing the effect of these identified risks on the overall project objectives. Inputs - Tools Risk Register Risk Management Plan Cost Management Plan Schedule Management Plan Organizational Process Assets - - Outputs Expert Judgment Data Gathering and Representation Techniques Quantitative Risk Analysis and Modeling Techniques - Risk Register (updates) 8.5 Plan Risk Response - It is the process of developing actions or defines how to respond to enhance positive risks and/or to reduce negative risks. Inputs - Risk Management Plan Risk Register Tools - Expert Judgment Strategies for Negative Risks Strategies for Positive Risks Contingent Response Strategy Outputs - Risk Related Contract Decisions Risk Register (updates) Project Management Plan (updates) Project Document updates By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 5. 8.6 Risk Monitoring and Control - It is the process of implementing all those risks plans, tracking the identified risks, insuring risk management effectiveness through the project life, and monitoring and identifying new / residual risks. Inputs Project Management Plan (Risk Management Plan) Risk Register Work Performance Information Performance Reports - Tools - Risk Reassessment Risk Audits Variance and Trend Analysis Technical Performance Information Reserve Analysis Status Meetings Outputs - Risk Register (updates) Change Requests Organizational Process Assets (updates) Project Management Plan (updates) Project Document (Updates) Very Important Concepts: 1. Difference between “Issue” and “Risk”; - Issue; a point or matter in question or in dispute, or a matter that is not settled and under discussion or over which there are opposing views or disagreements. Risk; an uncertain event or condition that if it occurs, has a positive or negative effect on a project’s objectives. Simply, we can say that a “Risk is something that could happen in the future”, while an “Issue is that risk has became a reality”. 2. Difference between “Threats” and “Opportunities”; - Risks are not necessarily “Negative” and they can be simply “Positive”. - Threats; are simply the “Negative” risks, while Opportunities are the “Positive” risks. 3. Difference between “Contingency” and “Workaround”; - Contingency; a provision in the project management plan to mitigate cost risk and/or schedule risk. It is simply “an allowance to deal with a problem”, you decide today “what your contingency will be if a risk occurs”, this can be budget or schedule oriented. - Workaround; it is a response to a negative risk that has occurred and that response was not planned in advance of the occurrence of the risk event. - Generally, when contingency is taken into consideration, this refers to a proactive PM who is following risk management processes to enhance project success. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 6. 4. Risk Attitudes (Human Factors) - There are four types of risk attitudes which are; I. Risk Averse Person; such person always uncomfortable with uncertainty. Such person prefers a more certain outcome and demands a premium to accept projects of high risk. II. Risk Neutral Person; such person always embraces risks for future payoffs; he looks to risks as opportunity or way to gain additional payoffs. III. Risk Seeker Person; always looks at risks as challenge. IV. Risk Tolerant Person; such person doesn’t worry too much about risks. If a risk actually occurs, he acts all surprised. 5. Utility Theory Basics - An appropriate method for describing risk tolerance based on the various stakeholders' tolerances for risk. This method is depicted using three structures where the x-axis denotes the money at stake and the y-axis denotes utility, or the amount of satisfaction the person obtains from the payoff. - For “Risk Averse” stakeholder; such person usually requires a premium utility to accept a high risk. U Risk payoffs - $ For “Risk Neutral” stakeholder; such person is more concerned about the expected return on his investment, not on thr risk he maybe taking on. U $ By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 7. - For “Risk Seeker” stakeholder; he prefers uncertain outcomes and is willing to take the risk; the more the money is that stake, the greater the utility he gets out of it. U $ Example: - If there is a chance of 50% to gain 100$ and another chance of 100% to gain 50$, risk averse person will accept the 2nd choice, while the risk seeker person will prefer the 1st choice and finally, the risk neutral person has no preferences between them Notes: - A person can be both risk averse and risk seeking at different times. - Risk attitudes of individuals in a company shape the risk attitude of the company. - On an individual level, it is important to know the risk attitudes of the stakeholders to be able to deal with them properly when talking about “Risk list”. 6. Project risk management is an iterative process - PM has to monitor the risks constantly, watches out for triggers and then, responds to any risk that already happens and turns to an issue. - During the life of the project, factors that define and affect risks will change; you may have scope changes, environment changes, or even changes in the project team...etc. - Changes open up possible new risks and required new round of planning and that is why “Risk Management Process is an Iterative process”. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 8. 7. Prioritizing risks is done through two steps - “Qualitative Prioritization” 1. Prioritize risks according to their potential effect, i.e. probability and impact, on the project. 2. Assign each risk a quality like high (H), Medium (M), or low (L). 3. Focus on risks with high priorities to shorten the risks list - “Quantitative Prioritization” 1. Numerically defines probability of each risk, from the short risk list that comes from qualitative prioritization and its consequences on the project objective. 2. Calculate risk rating = probability * Impact [ex; 70% * 2000$] 3. Narrow down the risks list to the most important ones. Important notes regarding the “Project Risk Management”; - Young dynamic startup companies are usually risk seekers, while established companies are usually risk averse. - “Risk Management Plan” components are very important for the PMP Exam. - “Identifying Risks” is an “Iterative Process” - The “Check List” tool in “Identify Risk” process is not a chick list with expected risks, but a check list that helps to identify risks based on the RBS. - Risks types are “Business Risks” & “Pure Risks” - Tools like Sensitivity Analysis – ex. Tornado Diagram & What-If scenarios -, Expected Monetary Value (EMV) and Decision Tree are important tools regarding “Quantitative Risk Analysis”. - Probability of events occurring in sequence must be multiplied to calculate the accumulative probability of occurring of all the events together. - Transfer Risk = Deflection of Risk. - Mitigation Strategy results in Contingent Response Strategy. - The main goal of “Reserve Analysis” as a tool in “Monitor & Control Risks” is to determine any “Potential Risk” - “Project Risk management” is considered to be an item in every “Status Meeting”. - In case of occurrence of surprising unexpected risk, “Workaround” is only suitable response which always taken directly even before issuing the change request needed. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD