Executive Summary


        We carried out this netbook selection project in order to purchase the best suitable netbook for
managers and sales executives of an international company. When we compare the netbooks, we
considered some facts such as usability, functionality of netbooks, for now and for the future, and TCO.
        To accomplish our project within a month, we considered to manage our project with a standard
methodology. We used a tailor-made methodology by combining PRINCE 2 and PMBOK standard to
systematically manage our netbook procurement project. In addition, we used a good quality management
approach which includes three main processes: planning, assurance and control for quality.
        Then, we created work break down structure and defined resources. Next, schedule management
tools such as Gantt chart and Activity Network Diagram were utilized to identify our project's milestones,
costs, responsibility of each team member, dependency between activities and duration of each activity.
        We also decided to use Spread Sheet Model which is the easiest and most efficient technique to
compare the products. So, we could define the important factors and criteria which will best suit with our
business requirements. After comparing the scores got by each netbook model for all factors, we
recommended Toshiba because it can provide abundant storage capacity, excellent customer services,
efficient performance and usability. Moreover, it has high durability and its price is also reasonable.
Consequently, we do believe that our managers and sales executives will surely be happy with our
recommended Toshiba netbook.




                                                                                                           2
3
Report for Netbook Procurement Project (Word Count - 999)


        We could successfully accomplish our Netbook Procurement Project by managing with many
systematic ways. So, we want to present to the Project Steering Committee about how we made sure the
successful rollout of our project. In this report, we will describe about our selected project management
methodology together with the reasons of choosing it, our approach of managing project quality and our
recommended netbook model.


        Every project needs a project management methodology to achieve the goals for which the
project is being carried out. Therefore, we analyzed which methodology is best to manage our project and
found that "Projects In Controlled Environments (PRINCE 2)" can assist our project in many ways.
        By applying PRINCE 2, we can easily set up our project team and define their accountability
precisely because standard role descriptions suitable for all sorts of projects are described in it. Another
important fact of choosing it is most people across our organization are familiar with PRINCE 2. As our
company is an international company, standardization is essential in managing our projects. Since
PRINCE 2 can provide a standard approach and it is easy to use and learn even for the project team
members with limited experiences, we have been using it to manage all types of our projects. So, we
planned to use it for this netbook procurement project too. Another reason also created the potential to
choose this methodology. This is PRINCE 2 can reduce risks by providing many excellent quality control
techniques. Since our project must be completed within one month, we needed to consider these aspects
to make sure of delivering our project with low risks and good quality.
        Although we decided to use PRINCE 2 for above reasons, procurement management is not
covered in PRINCE 2. As our project is netbook procurement project, we realized to use another
framework in conjunction with PRINCE 2. Then, we observed that there is a best standard which can give
guidelines to manage procurement processes and contract administration. This is "Project Management
Body of Knowledge (PMBOK)" which can more fully describe the ways to handle the procurement flow
rather than other methodologies. By these ways, we could manage our project successfully by using a
tailor-made methodology formed by combining PRINCE 2 and PBMOK.




                                                                                                               4
As we have presented above, we must accomplish our project with good quality so that we can
assure the successful roll-out of our project and use of our selected netbooks. So, we want to clarify the
quality management approach that we had utilized for our project to satisfy the implied or stated needs
of our company and staff. We used the approach of integrating quality management throughout our
project life cycle. Our project quality management contains three key processes: (1) quality planning, (2)
quality assurance and (3) quality control. (Schwalbe, 2007)
        At the start of the project, we performed the quality planning process. Firstly, we defined the
quality standard or metrics (functionalities, usability, reliability, etc.) our desired netbook should have.
So, we made market research on the netbook models and listed evaluation factors and criteria to compare
the quality of each model. Project quality management plan was also created based on vendor
management plan and budget because project cannot finish on time if vendor does not perform in
accordance with contract. Likewise, if project costs exceed the available budget, we cannot say that our
project is good in quality. So, selected vendor's actions and budget must be monitored so that we can
produce a good quality project.
        Next, we made assure our project quality by testing selected netbook models and using product
selection method such as WSM. At the end of project execution stage, we applied a quality assurance tool
such as a quality audit to review the particular quality management activities. Finally, we controlled the
quality with post implementation evaluations. We made survey on user's satisfactory level about selected
netbook model and our procurement management. Apart from this, since we reselected the one among
four netbook models which are the most suitable with our business requirements, we also believed that
quality has already been controlled.


        After justifying our selected methodology and quality management approach, we want to
recommend a netbook model to meet the needs of our company and staff. We defined 31 criteria under
six factors to compare four netbook models: Samsung, HP, Sony and Toshiba. These main factors are
technical considerations, netbook ergonomic features, business considerations, long-term prospects, TCO
and build quality. We gave the weighted scores to each netbook model for all criteria and then, calculated
the average weighted scores got by each netbook. Finally, we have seen that Toshiba got the first place
with 63.59% followed by HP with 55.975, Samsung with 54.49% and Sony with 53.19%.
        Consequently, we want to recommend Toshiba for our netbook procurement project after
calculating and comparing the percentage of scores got by each netbook model. The most prominent
reasons why we chose Toshiba are because of its specialized security features, abundant storage capacity,
efficient performance and usability such as large keyboard layout, smart design. Moreover, as it is a
second most reliable netbook brand in the netbook market, it is high durable, has good brand reputation

                                                                                                               5
and achieved 4 stars consumer ratings. Apart from this, Toshiba provides excellent customer services and
international warranty. So, we can get long-term prospects. In terms of costs, we noticed that Toshiba
netbook price is reasonable and its warranty extension charges are inexpensive. The last thing what made
us recommend Toshiba is that it is best suitable with business travellers like our sales executives because
of its good battery life, performance and extra light weight.


         To conclude, more value could be added to our project because of our tailor-made methodology.
Moreover, we could perform quality management processes by dedicating two aspects: conformance to
requirements and fitness for use with the help of our quality management approach. So, we do hope that
the investment for our recommended Toshiba netbooks costing about $314,544 can satisfy the needs of
our staff.




                                                                                                          6
References




       Web References

       Report for Netbook Procurement Project
       URL    :
       http://www.aipm.com.au/resource/A%20comparison%20of%20Prince%202%20vs%20PM
       BOK.pdf
       http://www.goalgroup.com.au/SiteFiles/goalgroupcomau/C007_ComparingPMBoKAndPRI
       NCE2In2009.pdf
       http://www.logro.sk/na_stiahnutie/project_management_-
       _comparing_prince2_with_pmbok.pdf
       Access Date    : 14th October, 2012


       Information of Netbooks
       URL    : http://www.gogodigital.co.uk/toshiba-nb500-12x-black-10-1-atom-n455-netbook-
       1gb-320gb-windows-7.html
       http://www.reghardware.com/2012/08/28/product_round_up_ten_netbooks/page3.html
       http://reviews.cnet.co.uk/netbooks/samsung-nc110-review-50004178/
       http://www.expertreviews.co.uk/laptops/277054/sony-vaio-m-series-m11m1e




       Access Date    : 14th October, 2012


                                                                                               7
Bibliography


Schwalbe, K. (2007). Information Technology Project Management (5th ed.). (M. P.Martin, Ed.) Boston:
GEX Publishing Services.




                                                                                                   8
Appendices

Appendix A (The Spread Sheet Model)

1. Selected Factors and Criteria for Spread Sheet Model

           Firstly, we will have to define some business related factors and criteria to create a spreadsheet-
based 2-level WSM. So, we analyzed the needs of our staff and found that functionality and usability are
highly requested by them. Apart from this, the company also wanted us to consider for business prospects
for future. Moreover, we usually notice about the tangible costs such as netbook purchasing costs and
project development costs and we do not aware the hidden costs. So, if we do not carefully plan for TCO,
costs can be too high. As company also wanted us to evaluate TCO, we took it into consideration as a
factor. Consequently, we picked up the following factors and criteria for our netbook procurement
project.




                                              Figure – 1.1




                                                                                                                 9
Figure – 1.2




               10
2. Descriptions of Weighted Score Range


        We gave the weighted scores to all these factors and criteria according to our predefined weighted
score standard. We defined the range of scores between 0 and 10 and the following table is the
descriptions of the range of scores.




                                              Figure – 1.3




                                                                                                      11
3. Calculation Methods of WSM and TCO

(i)   Calculation Methods of WSM

          We will demonstrate how we calculated weighted scores for comparing netbook models by
giving HP netbook model as an example.




                                                     Figure - 3.1

1.    For Factors and Criteria, we assigned their weight and calculate their maximum score.
      E.g. Netbook Ergonomic Features Factor (8 out of 10)
         Usability and Design       (8 out of 10)       Max Score     8 * 10 = 80
         Portability or Mobility    (7 out of 10)       Max Score     7 * 10 = 70
         Screen Size                (5 out of 10)       Max Score     5 * 10 = 50


2.    For each netbook model, we gave score for each criterion to show how much a netbook can
      satisfy each criterion and calculate total score of each criterion.
      E.g. For HP 210-4125sa
         Usability and Design      (5 out of 10)       Total Score    5 * 8 = 40
         Portability or Mobility (5 out of 10)         Total Score    5 * 7 = 35
         Screen Size               (6 out of 10)        Total Score   6 * 5 = 30


3.    To calculate the percentage got by each netbook for each factor, total scores must be divided
      by maximum scores and then multiply with 100.
      E.g. For HP 210-4125sa
      Percentage got by HP for Netbook Ergonomic Features Factor = (105/200) * 100
                                                                       = 52.50%




                                                                                                  12
Figure - 3.2




               13
(ii) Calculation Methods of TCO


        TCO is also an important factor to consider while planning a spread sheet model because it is
more vital than netbook purchase price according to head office. So, we calculated TCO in a separate
excel sheet.
        Firstly, we will calculate TCO for each netbook. We divided two categories of costs in
calculating TCO. First category is one-off costs and second one is recurring costs. One-off costs are the
costs that we have to pay only once for the procurement of netbooks and they include netbook purchasing
costs, project development costs, licensing costs, consultant fees and training fees. Recurring costs are the
costs that we will have to pay throughout the product life cycle and warranty extension charges, monthly
operational and overhead costs and service fees for 2 years are included under this category. But, we can
get 35% return if we sell an old netbook after two years. So, we will firstly add one-off costs and
recurring costs and then subtract the money got from selling an old netbook to calculate TCO for each
netbook. The formula is as follows:




                                                Figure – 3.3

                                                                                                         14
How Spread Sheet Model can assist us for our netbook procurement project?


        To summarize, Spread Sheet Model is the easiest and most efficient technique to compare the
products. We could define the important factors and criteria which will best suit with our business
requirements with the help of spread sheet model. Based on our defined factors and criteria, we could
compare the four netbook models by assigning scores to them for each criterion. As we can see clearly the
percentage of scores got by each netbook model, it is very convenient for us to choose the most suitable
one for our staff. Moreover, we could evaluate each netbook model's TCO which can have a great impact
on business benefits. As a result, we could reduce the business risks because hidden costs of each netbook
model could be considered. By analyzing all these facts, what we can conclude is that implementing
spread sheet model can give us many advantages by creating more possibilities to meet the requirements
of our sales executives.




                                                                                                        15
4. Test Plan


         After implementing the spread sheet model, it will be necessary to test that our spread sheet
system to ensure that it is robust and flexible. Therefore, we arranged a test plan to carry out testing of
some functions used in our spread sheet model. When we drew a project plan for our netbook selection
project, we put a task in our project to select suppliers for our netbooks. The name of this task is "Source
Selection by Using WSM and TCO" which will be carried out on 16th October to 19th October. So, we
will perform our testing during these days after creating spread sheet model to select the potential netbook
model.



                   Date                Tasks

                   17th October        Cell Validation

                   17th October        Cell Formatting

                   17th October        Cell Calculation

                   18th October        Automatic Graphs

                   18th October        Cell Protection with Sheet Password

                   18th October        Comments




                                                                                                              16
5. Test Log

5.1 Cell Validation


Test Log ID      Tested Cell No     Test Data              Expected Result    Outcome (see figure)

5.1.1            F14                -1                     Error Message      Figure – 5.1.1a
                                                                              Figure – 5.1.1b
5.1.2            F14                11                     Error Message      Figure – 5.1.2a
                                                                              Figure – 5.1.2b
5.1.3            F14                abcde                  Error Message      Figure – 5.1.3a
                                                                              Figure – 5.1.3b
5.1.4            F14                8                      Input Acceptance   Figure – 5.1.4a
                                                                              Figure – 5.1.4b


Test Log 5.1.1

Before




                                         Figure – 5.1.1a


After




                  Figure – 5.1.1b




                                                                                                 17
Test Log 5.1.2

Before




                                   Figure – 5.1.2a
After




                 Figure – 5.1.2b




Test Log 5.1.3

Before




                                   Figure – 5.1.3a
After




                 Figure – 5.1.3b


                                                     18
Test Log 5.1.4

Before




                 Figure – 5.1.4a

After




                 Figure – 5.1.4b




                                   19
5.2 Cell Formatting

Test Log ID      Tested Cell No   Test Data           Excepted Result           Outcome (see figure)

5.2.1            O11              Decimal value and   Decimal value must be     Figure – 5.2.1a
                                  percentage is not   in the percentage         Figure – 5.2.1b
                                  calculated.         format and it must have
                                                      two decimal place.



Test Log 5.2.1

   Before                                                After




              Figure – 5.2.1a                                       Figure – 5.2.1b




                                                                                                  20
5.3 Cell Calculation


Test Log    Tested Cell   Applied Formula    Test Data              Excepted     Outcome
ID          No                                                      Result       (see figure)

5.3.1       N4            Multiplication *   =F4*M4                 48           Figure - 5.3.1a
                                                                                 Figure - 5.3.1b

5.3.2       N5, N6, N7, Copying Formula      Plus sign will         N5 = 64      Figure - 5.3.2a
            N8, N9,     of N4                appear while           N6 = 56      Figure - 5.3.2b
            N10                              putting mouse          N7 = 7
                                             pointer bottom         N8 = 36
                                             right corner of cell   N9 = 30
                                             N4. Drag it            N10 = 28
                                             downward until it
                                             reaches cell N10
                                             and releases it.
5.3.3       N11           Addition           =SUM(N4:N10)           269          Figure - 5.3.3a
                          SUM (Number1,                                          Figure - 5.3.3b
                          Number2,…)
5.3.4       O11           Division           =N11/G11               59.78% in    Figure - 5.3.4a
                          Number1/Number2                           percentage   Figure - 5.3.4b
                                                                    format or
                                                                    0.59777778




                                                                                          21
Test Log 5.3.1

Before




                 Figure - 5.3.1a

After




                 Figure - 5.3.1b




                                   22
Test Log 5.3.2

Before




                 Figure - 5.3.2a

After




                 Figure - 5.3.2b




                                   23
Test Log 5.3.3

Before




                 Figure - 5.3.3a

After




                 Figure - 5.3.3b




                                   24
Test Log 5.3.4

Before




                 Figure - 5.3.4a

After




                 Figure - 5.3.4b




                                   25
5.4 Automatic Graphs

Test Log ID      Tested Cell No    Test Procedure                    Expected Result     Outcome (see figure)
5.4.1            A2, A3, B2,       Select all tested cell no and     Automatic Graph     Figure - 5.4.1a
                 B3, C2, C3,       choose Column Chart from Insert                       Figure - 5.4.1b
                 D2, D3            Menu.                                                 Figure - 5.4.1c


Test Log 5.4.1

Before




                                              Figure - 5.4.1a


After

Original Graph                                              After Modifying the Design




                 Figure - 5.4.1b                                       Figure - 5.4.1c




                                                                                                   26
Test Log ID      Tested    Password   Test Data            Expected Result          Outcome
                 Cell No                                                            (See Figure)

5.5.1            M20       -          Click on the cell    Message box describing   Figure – 5.5.1a
                                      M20                  the sheet is protected   Figure – 5.5.1b
                                                           will be displayed.

5.5.2            M20       Q          Click on the cell    Modification will be     Figure – 5.5.2a
                                      M20                  allowed.                 Figure – 5.5.2b




Test Log 5.5.1

Before




                                           Figure – 5.5.1a

After




                                         Figure – 5.5.1b




                                                                                               27
Test Log 5.5.2

Before




                                       Figure – 5.5.2a


Choosing unprotect sheet from Review Menu                Entering Password Q




                                                               Figure – 5.5.2c




            Figure – 5.5.2b


After




                                            Figure – 5.5.2d




                                                                                 28
5.6 Comments

Test Log ID      Tested Cell No   Test Data                Expected Result        Outcome (See figure)

5.6.1            D15              Adding new comment       Display comment when   Figure - 5.6.1a
                                                           mouse pointer hovers   Figure - 5.6.1b
                                                           cell no D15.


Test Log 5.6.1

Before




                                              Figure - 5.6.1a
After




                                              Figure - 5.6.1b




                                                                                                    29
Appendix B (Explanations of Presentation)

             In this section, we will demonstrate our presentation slides together with some notes we used to
     make our presentation more effective. In this presentation, we will justify our chosen business related
     factors and criteria by explaining why they are important for business purposes, the reasons of giving the
     scores to each netbook and our final recommended netbook to satisfy our business needs.


Slide 1                                                                     1. This is the introduction slide
                                                                            which shows what we are going to
                                                                            present to the audience. In this
                                                                            slide, we will start our presentation
                                                                            by describing the contents of our
                                                                            presentation.




                                                                                                                30
Slide 2   2. This slide will describe our chosen
          business related factors and criteria
          and the reasons of why they are
          important in buying the netbooks for
          our staff. Factors and criteria will be
          arranged from the highest scores to the
          lowest scores. Details of three factors
          such as Technical Considerations,
          Netbook Ergonomic Features and
          Business Considerations will be
          explained.


          Netbook Ergonomic Features – this
          can add value to the netbooks by
          letting users feel comfortable while
          using a netbook.
Slide 3   3. This slide is also the same as above
          slide. In this slide, details of three
          factors: Long-term Prospects, TCO
          and Build Quality will be presented.


          Licensing Costs – Operating System
          License costs and other software
          license costs.
          TCO – Total Cost of Ownership
          Build Quality – The most prominent
          benefits that a netbook can bring or a
          netbook comes together with.
          Best Value – Best Price
          Best for Business Travelers – This
          will be decided based on functionality,
          performance, portability and battery
          life.

                                          31
Slide 4   4. In this slide, our defined weighted
          score standard will be explained. Then,
          our weighted score model which
          compared four netbook models will be
          clarified. There will also be a link to our
          excel spread sheet. If we click on
          "Descriptions of Weighted Score Range,
          WSM and TCO", our excel spread sheet
          will be opened.




Slide 5   5. We will continue presenting our
          weighted score model in this slide. If we
          click on "Descriptions of Weighted
          Score Range, WSM and TCO", our excel
          spread sheet will be opened.




                                             32
Slide 6   6. For all four netbook models, we
          will describe how we calculate their
          total weighted scores, maximum
          scores and average scores to evaluate
          which netbook got the highest scores.




Slide 7   7. This will show how we calculated
          Total Cost of Ownership.
          One-off Costs – costs that we must
          pay only once for the procurement of
          netbooks and they include netbook
          purchasing costs, project development
          costs, licensing costs, consultant fees
          and training fees
          Recurring Costs - costs that we will
          have to pay throughout the product
          life cycle and warranty extension
          charges, monthly operational and
          overhead costs and service fees for 2
          years are included under this category
          Return Costs – money that we can
          get by selling the old netbooks after
          two years period




                                         33
Slide 8   8. Finally, we will compare
          overall scores got by each
          netbook model. To see clearly, we
          will demonstrate with graph.




Slide 9   9. This slide will show the reasons
          of why each netbook got the
          scores described in above slide.
          We will justify with strengths and
          weaknesses of each netbook.




                                         34
Slide 10   10. This slide will also describe
           the strengths and weaknesses of
           Sony and Toshiba.




Slide 11   11. This is final recommendation
           and thank you slide. We will end
           our presentation by
           recommending Toshiba netbook.
           We will also explain the reasons
           of choosing it.




                                          35
Appendix C (Project Plan)


         In this section, we will explain about our implemented project plan for our netbook selection
project. We will use Microsoft Project Plan 2007 which is project management software to create a work
breakdown schedule, a network diagram and a Gantt chart together with the critical path. Moreover, we
will assign the resources and responsibilities to carry out our project from start to end. Finally, we will
calculate the total project development costs which will be included in Total Cost of Ownership. This cost
will be considered in our Weighted Score Model.
         To develop the work breakdown schedule, we will apply two approaches stated in (Schwalbe,
2007). They are –
(i)   the analogy approach – we will analyze WBS of similar projects and then create our tailor-made
      WBS based on them.
(ii) the Top-down approach – we will firstly think about high level tasks and then placed the sub tasks
      under these main tasks.




(1) Work Breakdown Schedule
         We created work breakdown structure to define the overall scope of our netbook selection project
as it can act as a foundation for planning and managing our project schedules, resources and costs. There
are five main stages in our project plan and we will also describe the sub-tasks and milestones under each
main task. As monitoring processes will be integrated throughout the project life cycle, we will not show
it as a separate task.


(i)   Initiation
        Preparing charter and preliminary project scope statement
        Project Charter and Preliminary project scope statement (milestone)
(ii) Planning
        Carrying out Make-Or-Buy Analysis and Market Research
        Define evaluation factors and criteria for WSM and list qualified sellers
        Assign Resources and sign team contract
        Planning project's quality with vendor management plan and budget
        Procurement Planning
        Procurement Management Plan (milestone)
        Prepare procurement document such as RFP

                                                                                                              36
(iii) Execution
       Requesting Seller Responses
       Testing selected netbooks models
       Source Selection by using WSM and TCO
       Procurement Contract (milestone)
       Make payment for purchased netbooks
       Progressing delivery and inspecting delivered netbooks
       Training
       Delivered netbooks to 400 staff and Finish Training (milestone)
       Performing procurement audits for performance and quality
(iv) Closing
       Prepare and present lessons learnt report
       Project Roll Out
       Closed Contract (milestone)
(v) Post Implementation Evaluations
       Making survey on user's satisfactory level about netbooks and procurement management
       Produce Finalized Project Report (milestone)


Justifications of Sub-tasks


Preparing charter and preliminary project scope statement
         Firstly, a project charter will be defined to let the key stakeholders know their general roles and
responsibilities, project title, project start and finish date, project manager's name, project objectives,
budget information and the approaches to use for developing the project. Then, key stakeholders will have
to comment, agree and sign the project charter.
         An outside consultant will be hired because we need person with specialized skills to accomplish
the netbook procurement project within a month.
         Secondly, preliminary project scope statement will be developed based on project charter. In
preliminary project scope statement, required characteristics and features of netbook will be described. At
this stage, WBS will also be developed because it can demonstrate a complete picture of our project's
scope.




                                                                                                              37
Project Charter and Preliminary project scope statement (milestone)
        This is a milestone and project charter and preliminary project scope statement will be produced
as outputs.
Carrying out Make-Or-Buy Analysis and Market Research
        For planning purchases and acquisitions process, we need to make market research on the
strengths and weaknesses of netbook models in the market. Only if, we will know which netbook models
can meet our business requirements. After that, we need to carry out make-or-buy analysis to evaluate
whether company can gain more benefits from purchasing the netbooks or hiring the netbooks from an
outside organization.


Define evaluation factors and criteria for WSM and list qualified sellers
        Consultant will need to define evaluation criteria to select the best netbook which can meet the
requirements of company. Examples of these factors will include technical considerations such as
functionality, performance, reliability, connectivity, netbook ergonomic features such as usability, design,
portability, screen size, business considerations such as brand reputation, discounts, long-term prospects
such as availability in the local market, customer services, extensibility, and other criteria such as TCO
and build quality of netbooks.
        Consultant will need to analyze the result of market research to list the qualified sellers in the
market from which we can purchase the netbooks.


Assign Resources and sign team contract
        Inputs to this task are the project charter and preliminary project scope statement. Project
manager will break down the tasks, assign the responsibilities to the respective project team members and
show the project communication chart. Then, project team members will need to sign the team contract.


Planning project's quality with vendor management plan and budget
        We will plan project's quality based on vendor management plan and budget. When we applied a
quality planning technique such as design of experiments, we realize that vendor management plan and
budget have the most influence on the overall outcome for the project. This is because project will not
finish at the predefined time if vendor does not perform according to the contract. So, we will need to
monitor the actions of selected vendor and think what to do if they do not perform according to their
promises so that we can produce a good quality project. Likewise, if project costs exceed the available



                                                                                                             38
budget, we cannot say that our project is good in quality. So, we must arrange project quality management
plan based on vendor management plan and budget.
Procurement Planning
        Every project consists of some planning. We will arrange a plan to manage our netbook
procurement project. In this plan, we will document how our netbook procurement processes will be
controlled and managed, from planning purchases and acquisitions to closing the contract.


Procurement Management Plan (milestone)
        Procurement Management Plan will be produced as a milestone. It will include such things as
types of contracts to be used, standard procurement documents, make-or-buy decisions, roles and
responsibilities of members of project team, guidelines for selecting prequalified sellers and for
evaluating sellers and procurement metrics for managing contracts and seller's performance and actions.


Prepare procurement document such as RFP
        We will need to prepare a procurement document such as RFP. We will need contract type,
procurement management plan, make-or-buy decisions to produce a good RFP. RFP is required for
prospective sellers to prepare the proposals which must be presented to project team.


Requesting Seller Responses
        We will have to send our prepared RFP to potential sellers on 10 October and we will give them 2
days to prepare their proposals. On 11 October, we will collect their proposals.


Testing selected netbooks models
        We will ask potential sellers for delivering a technical presentation of their netbook models as
part of their proposals. Project team will also test all netbook models to evaluate whether they can meet
user requirements.


Source Selection by using WSM and TCO
        When we receive proposals from potential sellers, we will need to carry out source selection
which is the process of selecting the best seller for our netbook procurement project. We will plan two
level weighted score model to compare and contrast the sellers. While comparing the sellers, we will
consider functionality, usability and TCO of each netbook model. We will choose the proposal with
highest weighted scores. After that, we will make agreement with the selected seller and sign contract
with them.

                                                                                                           39
Procurement Contract (milestone)
         Procurement Contract is a mile stone that occurred on 10 October after signing the contract with
outside seller.


Make payment for purchased netbooks
         We will have to issue the invoices and transfer money from our bank account to theirs within two
days.


Progressing delivery and inspecting delivered netbooks
         Delivery process will be carried out by them and we will need to make inspections on the
delivered netbooks to check whether they have been damaged or not. If the netbooks have been damaged,
project procurement contract administrator will be responsible to contact with seller and replace the
damaged netbooks.


Training
         We will need to deliver training on how to use the selected netbook to the staff.


Delivered netbooks to 400 staff and Finish Training (milestone)
         This is a milestone and delivering netbooks and training to 400 staff must be completed at this
point.


Performing procurement audits for performance and quality
         A procurement auditor we have assigned will audit the performance and quality of our project
and he will have to produce an audit report. Then, he will have to present his findings to our project
steering committee.


Prepare and present lessons learnt report
         Project manager will need to review the audit report and other things that he have experienced
during carrying out the netbook selection project. Then, he will have to prepare lessons learnt report and
present it to project steering committee. In lessons learnt report, he will describe whether our project meet
time, quality, the main lessons he learned.




                                                                                                           40
Project Roll Out
        At this stage, project manager will confirm that netbook selection project has successfully
accomplished and then will sign off the project. Project manager and the seller will also have to close the
procurement contract.


Closed Contract (milestone)
        Closed Contract is a milestone resulted from project roll out task.


Making survey on user's satisfactory level about netbooks and procurement management
        Procurement officer will perform post implementation evaluations to make sure that our selected
netbook model meets the requirements of staff. So, procurement officer will make survey on user's
satisfactory level about netbooks and procurement management. Then, project manager will prepare to
create finalized project report based on the facts collected by procurement officer.


Produce Finalized Project Report (milestone)
        Finalized project report is a milestone which is produced after making survey on the feedback of
staff about selected netbooks.




                                        Figure – AppC1.1 (WBS)
                                                                                                        41
Figure – AppC1.2 (Important Milestones of WBS)




                                                 42
(2) Define Resource Names by Using Resource Sheet


        We will define the resource names which are the persons included in developing our netbook
selection project and assign their standard rate and overtime rate per hour by using the resource sheet of
Microsoft Project Plan. People who will involve in developing our netbook selection project are:
     Project Manager (Project Manager is the leader of our netbook selection project. He has the
        main responsibility from project initiation to roll-out.)
     Consultant (As our netbook selection project must finish within a month, we will have to hire
        outside consultant who understands about the netbooks and procurement project and processes.
        Only if, we can successfully accomplish our project within a short period of time.)
     Project Procurement Contract Administrator (The most important thing about procurement
        project is to monitor the seller's actions and performance. If seller do not do as they promised in
        the contract, project procurement contract administrator will have to contact and negotiate with
        seller.)
     Procurement Officer (Procurement Officer will be responsible for minor administration
        processes like requesting sellers' responses, training and making survey on users' feedback about
        selected netbooks.)
     Procurement Auditor (There are internal auditors employed at our company to monitor the
        quality and performance of projects and processes carried out by company. We will assign an
        auditor to measure our netbook selection project's quality and performance. As procurement
        auditor is not needed in developing the project from start to end and he/she is only needed for
        audit, we assigned his/her Max. Units 20%)
     Project Team (Project Manager, Consultant, Project Procurement Contract Administrator and
        Procurement Officer will be included in project team. Standard Rate will be calculated by adding
        standard rate of above resources. Likewise, Overtime Rate will be calculated by adding overtime
        rate of above resources.)




                                      Figure – AppC2.1 (Resources)

                                                                                                          43
(3) Schedule for Netbook Selection Project and Dependencies between Activities


        In this section, we want to justify how we arranged the project schedule for our project. Firstly,
we defined the activities for our project based on the WBS we have described above. Then, we carried out
activity sequencing which is determining the dependencies or relationships between activities. We also
planned to run some activities in parallel if these tasks are performed by different persons so that we can
complete within a month. After that, we assigned the resources to take the responsibilities of each
activity. Finally, we estimated the duration for each activity including its start date and finish date.
        Our netbook procurement project will last about 24days. Out of all tasks, we gave most of time
for planning stage and execution stage. The reason of why we assigned 6 days to planning stage is that
we have found that most projects of nowadays fail because of not having the systematic plans to manage
their projects. So, we gave enough time and efforts for planning stage. Execution stage has the longest
duration among all activities because many important milestones such as procurement contract and
delivered netbooks to 400 staff and finish training and critical tasks which can drive to the successful
roll-out of the project are included in this stage. Overall project duration and schedule can be seen in
below diagram.




                        Figure – AppC3.1 (Overall project duration and schedule)




                                                                                                           44
Figure – AppC3.2 (Detail project duration and schedule)




                                                          45
(4) Gantt Chart

        To complete our netbook selection project within a month, we will need to apply a schedule
development tool such as Gantt chart. Since Gantt chart can show project schedule information in a
calendar format, start and finish dates of activities can be easily seen (Schwalbe, 2007). Therefore, we
can manage time efficiently. With the help of Gantt chart, we can identify the critical path which includes
critical tasks and which can show the completion date of our project. Critical path can be seen in red
coloured bars in our Gantt chart. Apart from this, we also added the black diamond symbols which are
called milestones into our Gantt chart. By adding milestones, we can highlight crucial tasks and
accomplishments on projects.




Figure – AppC4.1 Gantt Chart for Our Netbook Selection Project (showing each activity with its
respective resource)
                                                                                                         46
(5) Activity Network Diagram

        We will describe our activity network diagram segment by segment. All the activities shown at
the network diagram come from the tasks of WBS. In network diagram, activities shown in red rectangle
are on the critical path and tasks described in hexagon are milestones. Following diagrams are activity
network diagram for our netbook selection project.




                                            Figure – AppC5.1




                                            Figure – AppC5.2

                                                                                                          47
Figure – AppC5.3




Figure – AppC5.4




                   48
Figure – AppC5.5




Figure – AppC5.6




                   49
(6) Calculating Costs for Netbook Selection Project

           We can calculate our netbook selection project development costs by using Microsoft Project
Plan. We can see clearly the costs of each task. After adding the costs of each task, we will cost about
$5,824 for developing our netbook procurement project.




                       Figure – AppC6.1 (Netbook Selection Project Development Costs)




                                                                                                           50

More Related Content

What's hot

User Interface Design
User Interface DesignUser Interface Design
User Interface DesignNay Lynn Aung
 
Information_Technology_Planning_comp_1647
Information_Technology_Planning_comp_1647Information_Technology_Planning_comp_1647
Information_Technology_Planning_comp_1647Aung Zay Ya
 
Accessories Shop Management System on Advance JAVA
 Accessories Shop Management System on Advance JAVA Accessories Shop Management System on Advance JAVA
Accessories Shop Management System on Advance JAVAMd. Mahbub Alam
 
Information Technology Planning (University of Greenwich BIT Coursework) by N...
Information Technology Planning (University of Greenwich BIT Coursework) by N...Information Technology Planning (University of Greenwich BIT Coursework) by N...
Information Technology Planning (University of Greenwich BIT Coursework) by N...Nay Linn Ko
 
Development Framework & Methods
Development Framework & MethodsDevelopment Framework & Methods
Development Framework & MethodsNay Lynn Aung
 
Information Technology Planning
Information Technology PlanningInformation Technology Planning
Information Technology PlanningNay Lynn Aung
 
1619_DANGANTHANH_GCS190644_AssignmentFull.docx
1619_DANGANTHANH_GCS190644_AssignmentFull.docx1619_DANGANTHANH_GCS190644_AssignmentFull.docx
1619_DANGANTHANH_GCS190644_AssignmentFull.docxkhangphanvan
 
Information System Engineering coursework by May Hnit Oo Khin
Information System Engineering coursework by May Hnit Oo KhinInformation System Engineering coursework by May Hnit Oo Khin
Information System Engineering coursework by May Hnit Oo KhinMay Hnit
 
Requirements Analysis COMP1645
Requirements Analysis COMP1645Requirements Analysis COMP1645
Requirements Analysis COMP1645Shane Min Zaw
 
Myo pyae phoo_pwint_000844592_comp1645
Myo pyae phoo_pwint_000844592_comp1645Myo pyae phoo_pwint_000844592_comp1645
Myo pyae phoo_pwint_000844592_comp1645Sofia Nolasco
 
Requirement analysis comp1645
Requirement analysis comp1645Requirement analysis comp1645
Requirement analysis comp1645Htet Htet Aung
 
Cw comp1645 171_mo233_20141113_194808_1415 (1)
Cw comp1645 171_mo233_20141113_194808_1415 (1)Cw comp1645 171_mo233_20141113_194808_1415 (1)
Cw comp1645 171_mo233_20141113_194808_1415 (1)Owen Muzi
 

What's hot (18)

User Interface Design
User Interface DesignUser Interface Design
User Interface Design
 
Information_Technology_Planning_comp_1647
Information_Technology_Planning_comp_1647Information_Technology_Planning_comp_1647
Information_Technology_Planning_comp_1647
 
Business IT Project
Business IT ProjectBusiness IT Project
Business IT Project
 
Accessories Shop Management System on Advance JAVA
 Accessories Shop Management System on Advance JAVA Accessories Shop Management System on Advance JAVA
Accessories Shop Management System on Advance JAVA
 
Information Technology Planning (University of Greenwich BIT Coursework) by N...
Information Technology Planning (University of Greenwich BIT Coursework) by N...Information Technology Planning (University of Greenwich BIT Coursework) by N...
Information Technology Planning (University of Greenwich BIT Coursework) by N...
 
Development Framework & Methods
Development Framework & MethodsDevelopment Framework & Methods
Development Framework & Methods
 
ITP BIT Coursework
ITP BIT CourseworkITP BIT Coursework
ITP BIT Coursework
 
Hein Thu Soe's RM BIT Coursework
Hein Thu Soe's RM BIT CourseworkHein Thu Soe's RM BIT Coursework
Hein Thu Soe's RM BIT Coursework
 
Information Technology Planning
Information Technology PlanningInformation Technology Planning
Information Technology Planning
 
DFM BIT Coursework
DFM BIT CourseworkDFM BIT Coursework
DFM BIT Coursework
 
MYINT OO IRA BIT COURSEWORK
MYINT OO IRA BIT COURSEWORKMYINT OO IRA BIT COURSEWORK
MYINT OO IRA BIT COURSEWORK
 
1619_DANGANTHANH_GCS190644_AssignmentFull.docx
1619_DANGANTHANH_GCS190644_AssignmentFull.docx1619_DANGANTHANH_GCS190644_AssignmentFull.docx
1619_DANGANTHANH_GCS190644_AssignmentFull.docx
 
Information System Engineering coursework by May Hnit Oo Khin
Information System Engineering coursework by May Hnit Oo KhinInformation System Engineering coursework by May Hnit Oo Khin
Information System Engineering coursework by May Hnit Oo Khin
 
Requirements Analysis COMP1645
Requirements Analysis COMP1645Requirements Analysis COMP1645
Requirements Analysis COMP1645
 
Requirements analysis
Requirements analysisRequirements analysis
Requirements analysis
 
Myo pyae phoo_pwint_000844592_comp1645
Myo pyae phoo_pwint_000844592_comp1645Myo pyae phoo_pwint_000844592_comp1645
Myo pyae phoo_pwint_000844592_comp1645
 
Requirement analysis comp1645
Requirement analysis comp1645Requirement analysis comp1645
Requirement analysis comp1645
 
Cw comp1645 171_mo233_20141113_194808_1415 (1)
Cw comp1645 171_mo233_20141113_194808_1415 (1)Cw comp1645 171_mo233_20141113_194808_1415 (1)
Cw comp1645 171_mo233_20141113_194808_1415 (1)
 

Viewers also liked

User Interface Design (University of Greenwich BIT Coursework) by Nay Linn Ko
User Interface Design (University of Greenwich BIT Coursework) by Nay Linn KoUser Interface Design (University of Greenwich BIT Coursework) by Nay Linn Ko
User Interface Design (University of Greenwich BIT Coursework) by Nay Linn KoNay Linn Ko
 
NayLinnKo_BIT_InteractionDesign
NayLinnKo_BIT_InteractionDesignNayLinnKo_BIT_InteractionDesign
NayLinnKo_BIT_InteractionDesignNay Linn Ko
 
Ecommerce by May Hnit Oo Khin
Ecommerce by May Hnit Oo KhinEcommerce by May Hnit Oo Khin
Ecommerce by May Hnit Oo KhinMay Hnit
 
Database Design and Implementation Coursework by May Hnit Oo Khin
Database Design and Implementation Coursework by May Hnit Oo KhinDatabase Design and Implementation Coursework by May Hnit Oo Khin
Database Design and Implementation Coursework by May Hnit Oo KhinMay Hnit
 
Information System Management Coursework by May Hnit Oo Khin
Information System Management Coursework by May Hnit Oo KhinInformation System Management Coursework by May Hnit Oo Khin
Information System Management Coursework by May Hnit Oo KhinMay Hnit
 
NayLinnKo Information Systems Management BIT
NayLinnKo Information Systems Management BITNayLinnKo Information Systems Management BIT
NayLinnKo Information Systems Management BITNay Linn Ko
 
Information Requirement Analysis
Information Requirement AnalysisInformation Requirement Analysis
Information Requirement AnalysisMd. Mahbub Alam
 
Advance Java course work under NCC Education June 2011
Advance Java course work  under NCC Education June 2011Advance Java course work  under NCC Education June 2011
Advance Java course work under NCC Education June 2011Md. Mahbub Alam
 
Database Design & Implementation
Database Design & ImplementationDatabase Design & Implementation
Database Design & ImplementationMd. Mahbub Alam
 
Cw comp1108 531_mo233_20150420_185837_1415
Cw comp1108 531_mo233_20150420_185837_1415Cw comp1108 531_mo233_20150420_185837_1415
Cw comp1108 531_mo233_20150420_185837_1415Owen Muzi
 
Cw comp1308 204344_mo233_20130516_121730_1213
Cw comp1308 204344_mo233_20130516_121730_1213Cw comp1308 204344_mo233_20130516_121730_1213
Cw comp1308 204344_mo233_20130516_121730_1213Owen Muzi
 
Cw comp1108 1013_mo233_000793120_20151208_172508_1516
Cw comp1108 1013_mo233_000793120_20151208_172508_1516Cw comp1108 1013_mo233_000793120_20151208_172508_1516
Cw comp1108 1013_mo233_000793120_20151208_172508_1516Owen Muzi
 
Cw comp1661 211574_mo233_20131122_234918_1314
Cw comp1661 211574_mo233_20131122_234918_1314Cw comp1661 211574_mo233_20131122_234918_1314
Cw comp1661 211574_mo233_20131122_234918_1314Owen Muzi
 
Cw comp1108 78_mo233_20141120_200330_1415
Cw comp1108 78_mo233_20141120_200330_1415Cw comp1108 78_mo233_20141120_200330_1415
Cw comp1108 78_mo233_20141120_200330_1415Owen Muzi
 

Viewers also liked (17)

User Interface Design (University of Greenwich BIT Coursework) by Nay Linn Ko
User Interface Design (University of Greenwich BIT Coursework) by Nay Linn KoUser Interface Design (University of Greenwich BIT Coursework) by Nay Linn Ko
User Interface Design (University of Greenwich BIT Coursework) by Nay Linn Ko
 
NayLinnKo_BIT_InteractionDesign
NayLinnKo_BIT_InteractionDesignNayLinnKo_BIT_InteractionDesign
NayLinnKo_BIT_InteractionDesign
 
MYINT OO ID BIT COURSEWORK
MYINT OO ID BIT COURSEWORKMYINT OO ID BIT COURSEWORK
MYINT OO ID BIT COURSEWORK
 
Ecommerce by May Hnit Oo Khin
Ecommerce by May Hnit Oo KhinEcommerce by May Hnit Oo Khin
Ecommerce by May Hnit Oo Khin
 
Database Design and Implementation Coursework by May Hnit Oo Khin
Database Design and Implementation Coursework by May Hnit Oo KhinDatabase Design and Implementation Coursework by May Hnit Oo Khin
Database Design and Implementation Coursework by May Hnit Oo Khin
 
Information System Management Coursework by May Hnit Oo Khin
Information System Management Coursework by May Hnit Oo KhinInformation System Management Coursework by May Hnit Oo Khin
Information System Management Coursework by May Hnit Oo Khin
 
Interaction Design
Interaction DesignInteraction Design
Interaction Design
 
NayLinnKo Information Systems Management BIT
NayLinnKo Information Systems Management BITNayLinnKo Information Systems Management BIT
NayLinnKo Information Systems Management BIT
 
MYINT OO ISM BIT COURSEWORK
MYINT OO ISM BIT COURSEWORKMYINT OO ISM BIT COURSEWORK
MYINT OO ISM BIT COURSEWORK
 
Information Requirement Analysis
Information Requirement AnalysisInformation Requirement Analysis
Information Requirement Analysis
 
Advance Java course work under NCC Education June 2011
Advance Java course work  under NCC Education June 2011Advance Java course work  under NCC Education June 2011
Advance Java course work under NCC Education June 2011
 
Database Design & Implementation
Database Design & ImplementationDatabase Design & Implementation
Database Design & Implementation
 
Cw comp1108 531_mo233_20150420_185837_1415
Cw comp1108 531_mo233_20150420_185837_1415Cw comp1108 531_mo233_20150420_185837_1415
Cw comp1108 531_mo233_20150420_185837_1415
 
Cw comp1308 204344_mo233_20130516_121730_1213
Cw comp1308 204344_mo233_20130516_121730_1213Cw comp1308 204344_mo233_20130516_121730_1213
Cw comp1308 204344_mo233_20130516_121730_1213
 
Cw comp1108 1013_mo233_000793120_20151208_172508_1516
Cw comp1108 1013_mo233_000793120_20151208_172508_1516Cw comp1108 1013_mo233_000793120_20151208_172508_1516
Cw comp1108 1013_mo233_000793120_20151208_172508_1516
 
Cw comp1661 211574_mo233_20131122_234918_1314
Cw comp1661 211574_mo233_20131122_234918_1314Cw comp1661 211574_mo233_20131122_234918_1314
Cw comp1661 211574_mo233_20131122_234918_1314
 
Cw comp1108 78_mo233_20141120_200330_1415
Cw comp1108 78_mo233_20141120_200330_1415Cw comp1108 78_mo233_20141120_200330_1415
Cw comp1108 78_mo233_20141120_200330_1415
 

Similar to IT Project and Quality Management Coursework 2 by May Hnit Oo Khin

Focus: Lean Delivery Workflow
Focus: Lean Delivery WorkflowFocus: Lean Delivery Workflow
Focus: Lean Delivery WorkflowRob Knight
 
PM TEMPLATE_ PRODUCT ROADMAP.pptx
 PM TEMPLATE_ PRODUCT ROADMAP.pptx PM TEMPLATE_ PRODUCT ROADMAP.pptx
PM TEMPLATE_ PRODUCT ROADMAP.pptxamitrcominc
 
RUNNING HEAD Customer Care Website Implementation1Customer .docx
RUNNING HEAD Customer Care Website Implementation1Customer .docxRUNNING HEAD Customer Care Website Implementation1Customer .docx
RUNNING HEAD Customer Care Website Implementation1Customer .docxjoellemurphey
 
Mobile App Development- Project Management Process
Mobile App Development- Project Management ProcessMobile App Development- Project Management Process
Mobile App Development- Project Management ProcessBagaria Swati
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docxScope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docxkenjordan97598
 
RajeevGautam_PeopleSoft Technology Lead_Infosys
RajeevGautam_PeopleSoft Technology Lead_InfosysRajeevGautam_PeopleSoft Technology Lead_Infosys
RajeevGautam_PeopleSoft Technology Lead_InfosysRajeev Gautam
 
Fixed Price Distributed Agile Projects
Fixed Price Distributed Agile ProjectsFixed Price Distributed Agile Projects
Fixed Price Distributed Agile ProjectsRaja Bavani
 
Webgen Technologies Pvt. Ltd.
Webgen Technologies Pvt. Ltd.Webgen Technologies Pvt. Ltd.
Webgen Technologies Pvt. Ltd.Sagar Sarkar
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentSiwawong Wuttipongprasert
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
ROI Driven Digital Development
ROI Driven Digital DevelopmentROI Driven Digital Development
ROI Driven Digital DevelopmentRobbie Burns
 
GNS: Your IT outsourcing provider
GNS: Your IT outsourcing providerGNS: Your IT outsourcing provider
GNS: Your IT outsourcing providerGNS
 
Bank Management System Desktop Application
Bank Management System Desktop Application Bank Management System Desktop Application
Bank Management System Desktop Application Ibadullah Khan
 
Senior PM with Real World Experience
Senior PM with Real World ExperienceSenior PM with Real World Experience
Senior PM with Real World ExperienceAlecia Chrin
 
SMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEMSMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEMSisubalan Selvan
 

Similar to IT Project and Quality Management Coursework 2 by May Hnit Oo Khin (20)

Focus: Lean Delivery Workflow
Focus: Lean Delivery WorkflowFocus: Lean Delivery Workflow
Focus: Lean Delivery Workflow
 
PM TEMPLATE_ PRODUCT ROADMAP.pptx
 PM TEMPLATE_ PRODUCT ROADMAP.pptx PM TEMPLATE_ PRODUCT ROADMAP.pptx
PM TEMPLATE_ PRODUCT ROADMAP.pptx
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
 
RUNNING HEAD Customer Care Website Implementation1Customer .docx
RUNNING HEAD Customer Care Website Implementation1Customer .docxRUNNING HEAD Customer Care Website Implementation1Customer .docx
RUNNING HEAD Customer Care Website Implementation1Customer .docx
 
Mobile App Development- Project Management Process
Mobile App Development- Project Management ProcessMobile App Development- Project Management Process
Mobile App Development- Project Management Process
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docxScope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
 
6 pma salehuddin - pqp & 3 core process procedures
6   pma salehuddin - pqp & 3 core process procedures6   pma salehuddin - pqp & 3 core process procedures
6 pma salehuddin - pqp & 3 core process procedures
 
RajeevGautam_PeopleSoft Technology Lead_Infosys
RajeevGautam_PeopleSoft Technology Lead_InfosysRajeevGautam_PeopleSoft Technology Lead_Infosys
RajeevGautam_PeopleSoft Technology Lead_Infosys
 
Fixed Price Distributed Agile Projects
Fixed Price Distributed Agile ProjectsFixed Price Distributed Agile Projects
Fixed Price Distributed Agile Projects
 
Webgen Technologies Pvt. Ltd.
Webgen Technologies Pvt. Ltd.Webgen Technologies Pvt. Ltd.
Webgen Technologies Pvt. Ltd.
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
PMO Daily Operations using Scrum Methodology
PMO Daily Operations using Scrum MethodologyPMO Daily Operations using Scrum Methodology
PMO Daily Operations using Scrum Methodology
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
ROI Driven Digital Development
ROI Driven Digital DevelopmentROI Driven Digital Development
ROI Driven Digital Development
 
GNS: Your IT outsourcing provider
GNS: Your IT outsourcing providerGNS: Your IT outsourcing provider
GNS: Your IT outsourcing provider
 
Bank Management System Desktop Application
Bank Management System Desktop Application Bank Management System Desktop Application
Bank Management System Desktop Application
 
Senior PM with Real World Experience
Senior PM with Real World ExperienceSenior PM with Real World Experience
Senior PM with Real World Experience
 
SMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEMSMARTPHONE PRODUCTION SYSTEM
SMARTPHONE PRODUCTION SYSTEM
 

Recently uploaded

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 

Recently uploaded (20)

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 

IT Project and Quality Management Coursework 2 by May Hnit Oo Khin

  • 1. 1
  • 2. Executive Summary We carried out this netbook selection project in order to purchase the best suitable netbook for managers and sales executives of an international company. When we compare the netbooks, we considered some facts such as usability, functionality of netbooks, for now and for the future, and TCO. To accomplish our project within a month, we considered to manage our project with a standard methodology. We used a tailor-made methodology by combining PRINCE 2 and PMBOK standard to systematically manage our netbook procurement project. In addition, we used a good quality management approach which includes three main processes: planning, assurance and control for quality. Then, we created work break down structure and defined resources. Next, schedule management tools such as Gantt chart and Activity Network Diagram were utilized to identify our project's milestones, costs, responsibility of each team member, dependency between activities and duration of each activity. We also decided to use Spread Sheet Model which is the easiest and most efficient technique to compare the products. So, we could define the important factors and criteria which will best suit with our business requirements. After comparing the scores got by each netbook model for all factors, we recommended Toshiba because it can provide abundant storage capacity, excellent customer services, efficient performance and usability. Moreover, it has high durability and its price is also reasonable. Consequently, we do believe that our managers and sales executives will surely be happy with our recommended Toshiba netbook. 2
  • 3. 3
  • 4. Report for Netbook Procurement Project (Word Count - 999) We could successfully accomplish our Netbook Procurement Project by managing with many systematic ways. So, we want to present to the Project Steering Committee about how we made sure the successful rollout of our project. In this report, we will describe about our selected project management methodology together with the reasons of choosing it, our approach of managing project quality and our recommended netbook model. Every project needs a project management methodology to achieve the goals for which the project is being carried out. Therefore, we analyzed which methodology is best to manage our project and found that "Projects In Controlled Environments (PRINCE 2)" can assist our project in many ways. By applying PRINCE 2, we can easily set up our project team and define their accountability precisely because standard role descriptions suitable for all sorts of projects are described in it. Another important fact of choosing it is most people across our organization are familiar with PRINCE 2. As our company is an international company, standardization is essential in managing our projects. Since PRINCE 2 can provide a standard approach and it is easy to use and learn even for the project team members with limited experiences, we have been using it to manage all types of our projects. So, we planned to use it for this netbook procurement project too. Another reason also created the potential to choose this methodology. This is PRINCE 2 can reduce risks by providing many excellent quality control techniques. Since our project must be completed within one month, we needed to consider these aspects to make sure of delivering our project with low risks and good quality. Although we decided to use PRINCE 2 for above reasons, procurement management is not covered in PRINCE 2. As our project is netbook procurement project, we realized to use another framework in conjunction with PRINCE 2. Then, we observed that there is a best standard which can give guidelines to manage procurement processes and contract administration. This is "Project Management Body of Knowledge (PMBOK)" which can more fully describe the ways to handle the procurement flow rather than other methodologies. By these ways, we could manage our project successfully by using a tailor-made methodology formed by combining PRINCE 2 and PBMOK. 4
  • 5. As we have presented above, we must accomplish our project with good quality so that we can assure the successful roll-out of our project and use of our selected netbooks. So, we want to clarify the quality management approach that we had utilized for our project to satisfy the implied or stated needs of our company and staff. We used the approach of integrating quality management throughout our project life cycle. Our project quality management contains three key processes: (1) quality planning, (2) quality assurance and (3) quality control. (Schwalbe, 2007) At the start of the project, we performed the quality planning process. Firstly, we defined the quality standard or metrics (functionalities, usability, reliability, etc.) our desired netbook should have. So, we made market research on the netbook models and listed evaluation factors and criteria to compare the quality of each model. Project quality management plan was also created based on vendor management plan and budget because project cannot finish on time if vendor does not perform in accordance with contract. Likewise, if project costs exceed the available budget, we cannot say that our project is good in quality. So, selected vendor's actions and budget must be monitored so that we can produce a good quality project. Next, we made assure our project quality by testing selected netbook models and using product selection method such as WSM. At the end of project execution stage, we applied a quality assurance tool such as a quality audit to review the particular quality management activities. Finally, we controlled the quality with post implementation evaluations. We made survey on user's satisfactory level about selected netbook model and our procurement management. Apart from this, since we reselected the one among four netbook models which are the most suitable with our business requirements, we also believed that quality has already been controlled. After justifying our selected methodology and quality management approach, we want to recommend a netbook model to meet the needs of our company and staff. We defined 31 criteria under six factors to compare four netbook models: Samsung, HP, Sony and Toshiba. These main factors are technical considerations, netbook ergonomic features, business considerations, long-term prospects, TCO and build quality. We gave the weighted scores to each netbook model for all criteria and then, calculated the average weighted scores got by each netbook. Finally, we have seen that Toshiba got the first place with 63.59% followed by HP with 55.975, Samsung with 54.49% and Sony with 53.19%. Consequently, we want to recommend Toshiba for our netbook procurement project after calculating and comparing the percentage of scores got by each netbook model. The most prominent reasons why we chose Toshiba are because of its specialized security features, abundant storage capacity, efficient performance and usability such as large keyboard layout, smart design. Moreover, as it is a second most reliable netbook brand in the netbook market, it is high durable, has good brand reputation 5
  • 6. and achieved 4 stars consumer ratings. Apart from this, Toshiba provides excellent customer services and international warranty. So, we can get long-term prospects. In terms of costs, we noticed that Toshiba netbook price is reasonable and its warranty extension charges are inexpensive. The last thing what made us recommend Toshiba is that it is best suitable with business travellers like our sales executives because of its good battery life, performance and extra light weight. To conclude, more value could be added to our project because of our tailor-made methodology. Moreover, we could perform quality management processes by dedicating two aspects: conformance to requirements and fitness for use with the help of our quality management approach. So, we do hope that the investment for our recommended Toshiba netbooks costing about $314,544 can satisfy the needs of our staff. 6
  • 7. References Web References Report for Netbook Procurement Project URL : http://www.aipm.com.au/resource/A%20comparison%20of%20Prince%202%20vs%20PM BOK.pdf http://www.goalgroup.com.au/SiteFiles/goalgroupcomau/C007_ComparingPMBoKAndPRI NCE2In2009.pdf http://www.logro.sk/na_stiahnutie/project_management_- _comparing_prince2_with_pmbok.pdf Access Date : 14th October, 2012 Information of Netbooks URL : http://www.gogodigital.co.uk/toshiba-nb500-12x-black-10-1-atom-n455-netbook- 1gb-320gb-windows-7.html http://www.reghardware.com/2012/08/28/product_round_up_ten_netbooks/page3.html http://reviews.cnet.co.uk/netbooks/samsung-nc110-review-50004178/ http://www.expertreviews.co.uk/laptops/277054/sony-vaio-m-series-m11m1e Access Date : 14th October, 2012 7
  • 8. Bibliography Schwalbe, K. (2007). Information Technology Project Management (5th ed.). (M. P.Martin, Ed.) Boston: GEX Publishing Services. 8
  • 9. Appendices Appendix A (The Spread Sheet Model) 1. Selected Factors and Criteria for Spread Sheet Model Firstly, we will have to define some business related factors and criteria to create a spreadsheet- based 2-level WSM. So, we analyzed the needs of our staff and found that functionality and usability are highly requested by them. Apart from this, the company also wanted us to consider for business prospects for future. Moreover, we usually notice about the tangible costs such as netbook purchasing costs and project development costs and we do not aware the hidden costs. So, if we do not carefully plan for TCO, costs can be too high. As company also wanted us to evaluate TCO, we took it into consideration as a factor. Consequently, we picked up the following factors and criteria for our netbook procurement project. Figure – 1.1 9
  • 11. 2. Descriptions of Weighted Score Range We gave the weighted scores to all these factors and criteria according to our predefined weighted score standard. We defined the range of scores between 0 and 10 and the following table is the descriptions of the range of scores. Figure – 1.3 11
  • 12. 3. Calculation Methods of WSM and TCO (i) Calculation Methods of WSM We will demonstrate how we calculated weighted scores for comparing netbook models by giving HP netbook model as an example. Figure - 3.1 1. For Factors and Criteria, we assigned their weight and calculate their maximum score. E.g. Netbook Ergonomic Features Factor (8 out of 10)  Usability and Design (8 out of 10) Max Score 8 * 10 = 80  Portability or Mobility (7 out of 10) Max Score 7 * 10 = 70  Screen Size (5 out of 10) Max Score 5 * 10 = 50 2. For each netbook model, we gave score for each criterion to show how much a netbook can satisfy each criterion and calculate total score of each criterion. E.g. For HP 210-4125sa  Usability and Design (5 out of 10) Total Score 5 * 8 = 40  Portability or Mobility (5 out of 10) Total Score 5 * 7 = 35  Screen Size (6 out of 10) Total Score 6 * 5 = 30 3. To calculate the percentage got by each netbook for each factor, total scores must be divided by maximum scores and then multiply with 100. E.g. For HP 210-4125sa Percentage got by HP for Netbook Ergonomic Features Factor = (105/200) * 100 = 52.50% 12
  • 14. (ii) Calculation Methods of TCO TCO is also an important factor to consider while planning a spread sheet model because it is more vital than netbook purchase price according to head office. So, we calculated TCO in a separate excel sheet. Firstly, we will calculate TCO for each netbook. We divided two categories of costs in calculating TCO. First category is one-off costs and second one is recurring costs. One-off costs are the costs that we have to pay only once for the procurement of netbooks and they include netbook purchasing costs, project development costs, licensing costs, consultant fees and training fees. Recurring costs are the costs that we will have to pay throughout the product life cycle and warranty extension charges, monthly operational and overhead costs and service fees for 2 years are included under this category. But, we can get 35% return if we sell an old netbook after two years. So, we will firstly add one-off costs and recurring costs and then subtract the money got from selling an old netbook to calculate TCO for each netbook. The formula is as follows: Figure – 3.3 14
  • 15. How Spread Sheet Model can assist us for our netbook procurement project? To summarize, Spread Sheet Model is the easiest and most efficient technique to compare the products. We could define the important factors and criteria which will best suit with our business requirements with the help of spread sheet model. Based on our defined factors and criteria, we could compare the four netbook models by assigning scores to them for each criterion. As we can see clearly the percentage of scores got by each netbook model, it is very convenient for us to choose the most suitable one for our staff. Moreover, we could evaluate each netbook model's TCO which can have a great impact on business benefits. As a result, we could reduce the business risks because hidden costs of each netbook model could be considered. By analyzing all these facts, what we can conclude is that implementing spread sheet model can give us many advantages by creating more possibilities to meet the requirements of our sales executives. 15
  • 16. 4. Test Plan After implementing the spread sheet model, it will be necessary to test that our spread sheet system to ensure that it is robust and flexible. Therefore, we arranged a test plan to carry out testing of some functions used in our spread sheet model. When we drew a project plan for our netbook selection project, we put a task in our project to select suppliers for our netbooks. The name of this task is "Source Selection by Using WSM and TCO" which will be carried out on 16th October to 19th October. So, we will perform our testing during these days after creating spread sheet model to select the potential netbook model. Date Tasks 17th October Cell Validation 17th October Cell Formatting 17th October Cell Calculation 18th October Automatic Graphs 18th October Cell Protection with Sheet Password 18th October Comments 16
  • 17. 5. Test Log 5.1 Cell Validation Test Log ID Tested Cell No Test Data Expected Result Outcome (see figure) 5.1.1 F14 -1 Error Message Figure – 5.1.1a Figure – 5.1.1b 5.1.2 F14 11 Error Message Figure – 5.1.2a Figure – 5.1.2b 5.1.3 F14 abcde Error Message Figure – 5.1.3a Figure – 5.1.3b 5.1.4 F14 8 Input Acceptance Figure – 5.1.4a Figure – 5.1.4b Test Log 5.1.1 Before Figure – 5.1.1a After Figure – 5.1.1b 17
  • 18. Test Log 5.1.2 Before Figure – 5.1.2a After Figure – 5.1.2b Test Log 5.1.3 Before Figure – 5.1.3a After Figure – 5.1.3b 18
  • 19. Test Log 5.1.4 Before Figure – 5.1.4a After Figure – 5.1.4b 19
  • 20. 5.2 Cell Formatting Test Log ID Tested Cell No Test Data Excepted Result Outcome (see figure) 5.2.1 O11 Decimal value and Decimal value must be Figure – 5.2.1a percentage is not in the percentage Figure – 5.2.1b calculated. format and it must have two decimal place. Test Log 5.2.1 Before After Figure – 5.2.1a Figure – 5.2.1b 20
  • 21. 5.3 Cell Calculation Test Log Tested Cell Applied Formula Test Data Excepted Outcome ID No Result (see figure) 5.3.1 N4 Multiplication * =F4*M4 48 Figure - 5.3.1a Figure - 5.3.1b 5.3.2 N5, N6, N7, Copying Formula Plus sign will N5 = 64 Figure - 5.3.2a N8, N9, of N4 appear while N6 = 56 Figure - 5.3.2b N10 putting mouse N7 = 7 pointer bottom N8 = 36 right corner of cell N9 = 30 N4. Drag it N10 = 28 downward until it reaches cell N10 and releases it. 5.3.3 N11 Addition =SUM(N4:N10) 269 Figure - 5.3.3a SUM (Number1, Figure - 5.3.3b Number2,…) 5.3.4 O11 Division =N11/G11 59.78% in Figure - 5.3.4a Number1/Number2 percentage Figure - 5.3.4b format or 0.59777778 21
  • 22. Test Log 5.3.1 Before Figure - 5.3.1a After Figure - 5.3.1b 22
  • 23. Test Log 5.3.2 Before Figure - 5.3.2a After Figure - 5.3.2b 23
  • 24. Test Log 5.3.3 Before Figure - 5.3.3a After Figure - 5.3.3b 24
  • 25. Test Log 5.3.4 Before Figure - 5.3.4a After Figure - 5.3.4b 25
  • 26. 5.4 Automatic Graphs Test Log ID Tested Cell No Test Procedure Expected Result Outcome (see figure) 5.4.1 A2, A3, B2, Select all tested cell no and Automatic Graph Figure - 5.4.1a B3, C2, C3, choose Column Chart from Insert Figure - 5.4.1b D2, D3 Menu. Figure - 5.4.1c Test Log 5.4.1 Before Figure - 5.4.1a After Original Graph After Modifying the Design Figure - 5.4.1b Figure - 5.4.1c 26
  • 27. Test Log ID Tested Password Test Data Expected Result Outcome Cell No (See Figure) 5.5.1 M20 - Click on the cell Message box describing Figure – 5.5.1a M20 the sheet is protected Figure – 5.5.1b will be displayed. 5.5.2 M20 Q Click on the cell Modification will be Figure – 5.5.2a M20 allowed. Figure – 5.5.2b Test Log 5.5.1 Before Figure – 5.5.1a After Figure – 5.5.1b 27
  • 28. Test Log 5.5.2 Before Figure – 5.5.2a Choosing unprotect sheet from Review Menu Entering Password Q Figure – 5.5.2c Figure – 5.5.2b After Figure – 5.5.2d 28
  • 29. 5.6 Comments Test Log ID Tested Cell No Test Data Expected Result Outcome (See figure) 5.6.1 D15 Adding new comment Display comment when Figure - 5.6.1a mouse pointer hovers Figure - 5.6.1b cell no D15. Test Log 5.6.1 Before Figure - 5.6.1a After Figure - 5.6.1b 29
  • 30. Appendix B (Explanations of Presentation) In this section, we will demonstrate our presentation slides together with some notes we used to make our presentation more effective. In this presentation, we will justify our chosen business related factors and criteria by explaining why they are important for business purposes, the reasons of giving the scores to each netbook and our final recommended netbook to satisfy our business needs. Slide 1 1. This is the introduction slide which shows what we are going to present to the audience. In this slide, we will start our presentation by describing the contents of our presentation. 30
  • 31. Slide 2 2. This slide will describe our chosen business related factors and criteria and the reasons of why they are important in buying the netbooks for our staff. Factors and criteria will be arranged from the highest scores to the lowest scores. Details of three factors such as Technical Considerations, Netbook Ergonomic Features and Business Considerations will be explained. Netbook Ergonomic Features – this can add value to the netbooks by letting users feel comfortable while using a netbook. Slide 3 3. This slide is also the same as above slide. In this slide, details of three factors: Long-term Prospects, TCO and Build Quality will be presented. Licensing Costs – Operating System License costs and other software license costs. TCO – Total Cost of Ownership Build Quality – The most prominent benefits that a netbook can bring or a netbook comes together with. Best Value – Best Price Best for Business Travelers – This will be decided based on functionality, performance, portability and battery life. 31
  • 32. Slide 4 4. In this slide, our defined weighted score standard will be explained. Then, our weighted score model which compared four netbook models will be clarified. There will also be a link to our excel spread sheet. If we click on "Descriptions of Weighted Score Range, WSM and TCO", our excel spread sheet will be opened. Slide 5 5. We will continue presenting our weighted score model in this slide. If we click on "Descriptions of Weighted Score Range, WSM and TCO", our excel spread sheet will be opened. 32
  • 33. Slide 6 6. For all four netbook models, we will describe how we calculate their total weighted scores, maximum scores and average scores to evaluate which netbook got the highest scores. Slide 7 7. This will show how we calculated Total Cost of Ownership. One-off Costs – costs that we must pay only once for the procurement of netbooks and they include netbook purchasing costs, project development costs, licensing costs, consultant fees and training fees Recurring Costs - costs that we will have to pay throughout the product life cycle and warranty extension charges, monthly operational and overhead costs and service fees for 2 years are included under this category Return Costs – money that we can get by selling the old netbooks after two years period 33
  • 34. Slide 8 8. Finally, we will compare overall scores got by each netbook model. To see clearly, we will demonstrate with graph. Slide 9 9. This slide will show the reasons of why each netbook got the scores described in above slide. We will justify with strengths and weaknesses of each netbook. 34
  • 35. Slide 10 10. This slide will also describe the strengths and weaknesses of Sony and Toshiba. Slide 11 11. This is final recommendation and thank you slide. We will end our presentation by recommending Toshiba netbook. We will also explain the reasons of choosing it. 35
  • 36. Appendix C (Project Plan) In this section, we will explain about our implemented project plan for our netbook selection project. We will use Microsoft Project Plan 2007 which is project management software to create a work breakdown schedule, a network diagram and a Gantt chart together with the critical path. Moreover, we will assign the resources and responsibilities to carry out our project from start to end. Finally, we will calculate the total project development costs which will be included in Total Cost of Ownership. This cost will be considered in our Weighted Score Model. To develop the work breakdown schedule, we will apply two approaches stated in (Schwalbe, 2007). They are – (i) the analogy approach – we will analyze WBS of similar projects and then create our tailor-made WBS based on them. (ii) the Top-down approach – we will firstly think about high level tasks and then placed the sub tasks under these main tasks. (1) Work Breakdown Schedule We created work breakdown structure to define the overall scope of our netbook selection project as it can act as a foundation for planning and managing our project schedules, resources and costs. There are five main stages in our project plan and we will also describe the sub-tasks and milestones under each main task. As monitoring processes will be integrated throughout the project life cycle, we will not show it as a separate task. (i) Initiation  Preparing charter and preliminary project scope statement  Project Charter and Preliminary project scope statement (milestone) (ii) Planning  Carrying out Make-Or-Buy Analysis and Market Research  Define evaluation factors and criteria for WSM and list qualified sellers  Assign Resources and sign team contract  Planning project's quality with vendor management plan and budget  Procurement Planning  Procurement Management Plan (milestone)  Prepare procurement document such as RFP 36
  • 37. (iii) Execution  Requesting Seller Responses  Testing selected netbooks models  Source Selection by using WSM and TCO  Procurement Contract (milestone)  Make payment for purchased netbooks  Progressing delivery and inspecting delivered netbooks  Training  Delivered netbooks to 400 staff and Finish Training (milestone)  Performing procurement audits for performance and quality (iv) Closing  Prepare and present lessons learnt report  Project Roll Out  Closed Contract (milestone) (v) Post Implementation Evaluations  Making survey on user's satisfactory level about netbooks and procurement management  Produce Finalized Project Report (milestone) Justifications of Sub-tasks Preparing charter and preliminary project scope statement Firstly, a project charter will be defined to let the key stakeholders know their general roles and responsibilities, project title, project start and finish date, project manager's name, project objectives, budget information and the approaches to use for developing the project. Then, key stakeholders will have to comment, agree and sign the project charter. An outside consultant will be hired because we need person with specialized skills to accomplish the netbook procurement project within a month. Secondly, preliminary project scope statement will be developed based on project charter. In preliminary project scope statement, required characteristics and features of netbook will be described. At this stage, WBS will also be developed because it can demonstrate a complete picture of our project's scope. 37
  • 38. Project Charter and Preliminary project scope statement (milestone) This is a milestone and project charter and preliminary project scope statement will be produced as outputs. Carrying out Make-Or-Buy Analysis and Market Research For planning purchases and acquisitions process, we need to make market research on the strengths and weaknesses of netbook models in the market. Only if, we will know which netbook models can meet our business requirements. After that, we need to carry out make-or-buy analysis to evaluate whether company can gain more benefits from purchasing the netbooks or hiring the netbooks from an outside organization. Define evaluation factors and criteria for WSM and list qualified sellers Consultant will need to define evaluation criteria to select the best netbook which can meet the requirements of company. Examples of these factors will include technical considerations such as functionality, performance, reliability, connectivity, netbook ergonomic features such as usability, design, portability, screen size, business considerations such as brand reputation, discounts, long-term prospects such as availability in the local market, customer services, extensibility, and other criteria such as TCO and build quality of netbooks. Consultant will need to analyze the result of market research to list the qualified sellers in the market from which we can purchase the netbooks. Assign Resources and sign team contract Inputs to this task are the project charter and preliminary project scope statement. Project manager will break down the tasks, assign the responsibilities to the respective project team members and show the project communication chart. Then, project team members will need to sign the team contract. Planning project's quality with vendor management plan and budget We will plan project's quality based on vendor management plan and budget. When we applied a quality planning technique such as design of experiments, we realize that vendor management plan and budget have the most influence on the overall outcome for the project. This is because project will not finish at the predefined time if vendor does not perform according to the contract. So, we will need to monitor the actions of selected vendor and think what to do if they do not perform according to their promises so that we can produce a good quality project. Likewise, if project costs exceed the available 38
  • 39. budget, we cannot say that our project is good in quality. So, we must arrange project quality management plan based on vendor management plan and budget. Procurement Planning Every project consists of some planning. We will arrange a plan to manage our netbook procurement project. In this plan, we will document how our netbook procurement processes will be controlled and managed, from planning purchases and acquisitions to closing the contract. Procurement Management Plan (milestone) Procurement Management Plan will be produced as a milestone. It will include such things as types of contracts to be used, standard procurement documents, make-or-buy decisions, roles and responsibilities of members of project team, guidelines for selecting prequalified sellers and for evaluating sellers and procurement metrics for managing contracts and seller's performance and actions. Prepare procurement document such as RFP We will need to prepare a procurement document such as RFP. We will need contract type, procurement management plan, make-or-buy decisions to produce a good RFP. RFP is required for prospective sellers to prepare the proposals which must be presented to project team. Requesting Seller Responses We will have to send our prepared RFP to potential sellers on 10 October and we will give them 2 days to prepare their proposals. On 11 October, we will collect their proposals. Testing selected netbooks models We will ask potential sellers for delivering a technical presentation of their netbook models as part of their proposals. Project team will also test all netbook models to evaluate whether they can meet user requirements. Source Selection by using WSM and TCO When we receive proposals from potential sellers, we will need to carry out source selection which is the process of selecting the best seller for our netbook procurement project. We will plan two level weighted score model to compare and contrast the sellers. While comparing the sellers, we will consider functionality, usability and TCO of each netbook model. We will choose the proposal with highest weighted scores. After that, we will make agreement with the selected seller and sign contract with them. 39
  • 40. Procurement Contract (milestone) Procurement Contract is a mile stone that occurred on 10 October after signing the contract with outside seller. Make payment for purchased netbooks We will have to issue the invoices and transfer money from our bank account to theirs within two days. Progressing delivery and inspecting delivered netbooks Delivery process will be carried out by them and we will need to make inspections on the delivered netbooks to check whether they have been damaged or not. If the netbooks have been damaged, project procurement contract administrator will be responsible to contact with seller and replace the damaged netbooks. Training We will need to deliver training on how to use the selected netbook to the staff. Delivered netbooks to 400 staff and Finish Training (milestone) This is a milestone and delivering netbooks and training to 400 staff must be completed at this point. Performing procurement audits for performance and quality A procurement auditor we have assigned will audit the performance and quality of our project and he will have to produce an audit report. Then, he will have to present his findings to our project steering committee. Prepare and present lessons learnt report Project manager will need to review the audit report and other things that he have experienced during carrying out the netbook selection project. Then, he will have to prepare lessons learnt report and present it to project steering committee. In lessons learnt report, he will describe whether our project meet time, quality, the main lessons he learned. 40
  • 41. Project Roll Out At this stage, project manager will confirm that netbook selection project has successfully accomplished and then will sign off the project. Project manager and the seller will also have to close the procurement contract. Closed Contract (milestone) Closed Contract is a milestone resulted from project roll out task. Making survey on user's satisfactory level about netbooks and procurement management Procurement officer will perform post implementation evaluations to make sure that our selected netbook model meets the requirements of staff. So, procurement officer will make survey on user's satisfactory level about netbooks and procurement management. Then, project manager will prepare to create finalized project report based on the facts collected by procurement officer. Produce Finalized Project Report (milestone) Finalized project report is a milestone which is produced after making survey on the feedback of staff about selected netbooks. Figure – AppC1.1 (WBS) 41
  • 42. Figure – AppC1.2 (Important Milestones of WBS) 42
  • 43. (2) Define Resource Names by Using Resource Sheet We will define the resource names which are the persons included in developing our netbook selection project and assign their standard rate and overtime rate per hour by using the resource sheet of Microsoft Project Plan. People who will involve in developing our netbook selection project are:  Project Manager (Project Manager is the leader of our netbook selection project. He has the main responsibility from project initiation to roll-out.)  Consultant (As our netbook selection project must finish within a month, we will have to hire outside consultant who understands about the netbooks and procurement project and processes. Only if, we can successfully accomplish our project within a short period of time.)  Project Procurement Contract Administrator (The most important thing about procurement project is to monitor the seller's actions and performance. If seller do not do as they promised in the contract, project procurement contract administrator will have to contact and negotiate with seller.)  Procurement Officer (Procurement Officer will be responsible for minor administration processes like requesting sellers' responses, training and making survey on users' feedback about selected netbooks.)  Procurement Auditor (There are internal auditors employed at our company to monitor the quality and performance of projects and processes carried out by company. We will assign an auditor to measure our netbook selection project's quality and performance. As procurement auditor is not needed in developing the project from start to end and he/she is only needed for audit, we assigned his/her Max. Units 20%)  Project Team (Project Manager, Consultant, Project Procurement Contract Administrator and Procurement Officer will be included in project team. Standard Rate will be calculated by adding standard rate of above resources. Likewise, Overtime Rate will be calculated by adding overtime rate of above resources.) Figure – AppC2.1 (Resources) 43
  • 44. (3) Schedule for Netbook Selection Project and Dependencies between Activities In this section, we want to justify how we arranged the project schedule for our project. Firstly, we defined the activities for our project based on the WBS we have described above. Then, we carried out activity sequencing which is determining the dependencies or relationships between activities. We also planned to run some activities in parallel if these tasks are performed by different persons so that we can complete within a month. After that, we assigned the resources to take the responsibilities of each activity. Finally, we estimated the duration for each activity including its start date and finish date. Our netbook procurement project will last about 24days. Out of all tasks, we gave most of time for planning stage and execution stage. The reason of why we assigned 6 days to planning stage is that we have found that most projects of nowadays fail because of not having the systematic plans to manage their projects. So, we gave enough time and efforts for planning stage. Execution stage has the longest duration among all activities because many important milestones such as procurement contract and delivered netbooks to 400 staff and finish training and critical tasks which can drive to the successful roll-out of the project are included in this stage. Overall project duration and schedule can be seen in below diagram. Figure – AppC3.1 (Overall project duration and schedule) 44
  • 45. Figure – AppC3.2 (Detail project duration and schedule) 45
  • 46. (4) Gantt Chart To complete our netbook selection project within a month, we will need to apply a schedule development tool such as Gantt chart. Since Gantt chart can show project schedule information in a calendar format, start and finish dates of activities can be easily seen (Schwalbe, 2007). Therefore, we can manage time efficiently. With the help of Gantt chart, we can identify the critical path which includes critical tasks and which can show the completion date of our project. Critical path can be seen in red coloured bars in our Gantt chart. Apart from this, we also added the black diamond symbols which are called milestones into our Gantt chart. By adding milestones, we can highlight crucial tasks and accomplishments on projects. Figure – AppC4.1 Gantt Chart for Our Netbook Selection Project (showing each activity with its respective resource) 46
  • 47. (5) Activity Network Diagram We will describe our activity network diagram segment by segment. All the activities shown at the network diagram come from the tasks of WBS. In network diagram, activities shown in red rectangle are on the critical path and tasks described in hexagon are milestones. Following diagrams are activity network diagram for our netbook selection project. Figure – AppC5.1 Figure – AppC5.2 47
  • 48. Figure – AppC5.3 Figure – AppC5.4 48
  • 49. Figure – AppC5.5 Figure – AppC5.6 49
  • 50. (6) Calculating Costs for Netbook Selection Project We can calculate our netbook selection project development costs by using Microsoft Project Plan. We can see clearly the costs of each task. After adding the costs of each task, we will cost about $5,824 for developing our netbook procurement project. Figure – AppC6.1 (Netbook Selection Project Development Costs) 50