2. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS
Project start-up and initial presentation
Consideration of various standards and specifications
AutoCAD drafting
Loading calculations
Structural analysis in STAAD-Pro v8i
Design of transmission line tower
Project completion documentation
3. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – START-UP & INITIAL PRESENTATION
Reviewed chronological and working procedure for analysis and design of transmission
line towers using angle (L-sections) sections of steel.
Performed literature review for use of hollow circular sections (HSS) in tower design.
Prepared chronological procedure for design of transmission line towers.
Prepared dataset of required standards and specifications for design of tower using angular
and hollow circular section.
Initial presentation on topic proposal was given to project committee.
4. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Standards And Speficifactions
IS – 802 “CODE OF PRACTICE FOR USE OF STRUCTURAL STEEL IN OVERHEAD
TRANSMISSION LINE TOWERS”
IS – 806 “CODE OF PRACTICE FOR USE OF STEEL TUBES IN GENERAL BUILDING
CONSTRUCTION”
IS – 5613 “CODE OF PRACTICE FOR DESIGN, INSTALLATION AND MAINTENANCE OF
OVERHEAD POWER LINES”
IS – 2062 “CODE OF SPECIFICATIONS FOR HOT ROLLED MEDIUM AND HIGH TENSILE
STRUCTURAL STEEL”
IS – 1161 “STEEL TUBES FOR STRUCTURAL PURPOSES – SPECIFICATIONS”
TRANSMISSION LINE MANUAL by Central Board of Irrigation and Power (CBIP), Govt. Of India.
‘BLUE BOOK’ By TATA Steel Inc.
CIDECT Design Guide 7
5. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – AutoCAD Drafting
Prepared drawing layout of different parts
of transmission towers to understand their
functions
Detailing of different parts of transmission
towers
Followed specification from CBIP manual
to understand specification for calculation
of electric clearance to finalize length of
cantilever tower arm
VUE 2-2
VUE 1-1
VUE 3-3
690075007500TRONCON-IPIEDS
FACE TRANSVRSALE
PIED -2 POUR
COUPE 7-7 COUPE 8-8COUPE 9-9
TRONCON-IITRONCON-IIITRONCON-IVTRONCON-VBASE+12
BASE -8
BASE -4
BASE ±0
-2.0
-1.0
±0.0
+1.0
+2.0
+3.0
BASE +4
BASE +8
BASES -8, -4, ±0
PIED -1 POUR
BASES -8, -4, ±0
PIED ±0 POUR
BASES -8, -4, ±0
PIED +1 POUR
BASES -8, -4, ±0
PIED +2 POUR
BASES -8, -4, ±0
PIED +3 POUR
BASES -8, -4, ±0
PIED +3 POUR
BASES +4, +8, +12
PIED +2 POUR
BASES +4, +8, +12
PIED +1 POUR
BASES +4, +8, +12
PIED -1 POUR
BASES +4, +8, +12
PIED ±0 POUR
BASES +4, +8, +12
FACE LONGITUDINALE
-2.0
-1.0
±0.0
+1.0
+2.0
+3.0
6. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Loading Calculation (Load Cases)
Finalized possible load cases to perform
analysis of transmission towers
Followed criteria from IS – 5613 and IS –
802 in finalizing maximum possible load
cases
Considered three basic criteria such as
reliability, security and safety
Considered different loading conditions
such as broken wire condition, narrow front
wind load condition, temporary loads
during construction etc.
7. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Loading calculation (SAG-TENSION)
Performed SAG-TENSION calculation as
per IS - 5613 to obtain maximum Sag of
different type of conductors
Considered temperature effect in Sag-
Tension calculation for different type of
conductors as per IS-802 and CBIP manual
Considered material properties to quantify
behavior of conductor
Considered wind load effect on SAG-
TENSION.
8. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Loading calculation (Wire load)
Performed wire load calculation
under different conditions.
Each load case was considered
separately while calculating wire
load.
Each of Three criteria ( reliability,
security and safety) was considered
in wire load calculation
Load calculation was performed for
both conductor and earth wire.
9. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Loading calculation (wind load on members)
Calculated total wind load on each of
the tower truss members.
Exposed area of each member was
considered in wind load calculations.
Quantified total wind load on each of
the two faces of tower ( Longitudinal
and transverse face)
10. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Structural Analysis
3D model of tower was generated in STAAD-Pro
Initial member sections were used and analysis
was performed
Necessary iterations were performed to calibrate
design calculations.
Process of analysis and design with required
iterations was followed using Angle (L-sections)
and Hollow circular steel (HCS) sections.
11. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Structural Analysis
Member forces in
STAAD-Pro model
12. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Structural Analysis (3D rendering of model)
Rendering of 3D model of tower in
STAAD-Pro.
Members were aligned with respect
to global axis using beta angle
function in STAAD-Pro.
13. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Design of Transmission Line Towers
Excel sheets were generated
to perform design
calculations for each
members in the tower.
Stresses in each member
were obtained from
STAAD-Pro analysis for
design of member section.
Each design was calibrated
by iterating analysis and
design process.
14. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Design of Transmission Line Towers
Total weight of finalized sections
was performed using both sections
for the same tower.
Cost analysis for use of each member
section in tower was performed.
Cost comparison was performed at
last to find more economic solution.
15. COST COMPARISON FOR TRANSMISSION LINE TOWERS USING
DIFFERENT MEMBER SECTIONS – Project completion documentation
Final document of project report was submitted to Kalpataru Power Transmission Limited
(KPTL)
Project based thesis report was submitted to department of Civil Engineering at
Gandhinagar Institute of Technology, Gujarat Technological University (GTU),
Gandhinagar, Gujarat, India
Project was presented at Gujarat State Technical Project Fair and was awarded position of
2nd runner up.