Mobilink Project On Site Swap SOPMobilink Project On Site Swap SOP
© ZTE Corporation. All rights reserved
2
Internal use only▲
Red Lines
All the rules must be follow otherwise will get punishment !
Prohibit entering site besides receiving war room approval .
Top 1 Work must with safety helmet, hat torch and safety belt.
Top 2 Prohibit touch any unconcerned existing equipment.
Top 3 Prohibit phone power off, must have the another SIM card of other operator.
Top 4 Prohibit leaving site besides receiving war room approval .
Top 5 Pre swap preparation and data collection of all existing system with snaps.
Top 6 ZTE unused material must picked from site through MMAF submission after swap.
Top 7 E/// dismantled equipment MMAF must be submitted along with equipment pictures.
Top 8 BSS engineer will leave the site after confirmation by RF of successful site DT .
Top 9 BSS engineer will leave the site after site alarm verification from PMCL OAN hotline.
© ZTE Corporation. All rights reserved
3
Internal use only▲
11 steps lead swap to be successfully
Notice
Any access issue please contact War room:
03107606611/03106356611
Any technical issues (RF/Optical fiber)can not solved please contact site
engineer to support on site immediately.
Any material issues can not solved please contact site engineer to
support on site immediately.
Team leader must report to Mobilink NOC while enter and leaving site.
© ZTE Corporation. All rights reserved
4
Internal use only▲
1. Documents
BBU and RRU connection scenario Provider: Yu Guang Hui/War Room:03155104495/0310760661
– 《 SDR Commissioning solution 》 Provider: Yu Guang Hui/War Room:03155104495/0310760661
– 《 Label standard 》 Provider: Atif: 03459889898
《 BOM & DO 》 Provider: Saqib: 03458577070,Asim: 0315-7117708
《 Communication Matrix 》 Provider: Swap Team Lead
2.Material ( Each site )
– On site Material Box check to ensure all the required material is available on site and if not then
Escalate to respective Team Leader.
– Spares requirement must be calculated and in hand with site engineer for on spot
Rectification if any equipment got faulty.
1. Swap preparation
Notice : Follow preparation must be ready before go to the site.
3.Work order from Customer:
Call NOC and Back office team to proceed further
Communication
Plan
© ZTE Corporation. All rights reserved
5
Internal use only▲
Cable stripping tool
Cable Cutter
RJ45 crimping tool
Hex/Allen Key Sets
Crone (LSA)
Level Ruler
(water pass)
Ethernet Cable Tester
(Kabel LAN Tester)
Cross & Slotted
screwdriver
(Obeng Lengkap)
Safety helmet
Drill & Drill Bits
(Alat Bor & Mata Bor)
Safety Belt
Multifunctional
Crimping tools
Adjustable spanners
(Kunci Inggris)
Dust Cleaner/vacuum
cleaner
Safety GlovesHat torch
(Lampu Kepala)
4. Tools ( Also include heat Gun)
LAN cable Laptop
Camera
© ZTE Corporation. All rights reserved
6
Internal use only▲
2. Site access
3. Environment double checking
Night Swap Arrival must before 21:00
Day Swap Arrival must before 6:00
Notice : Any access issue please contact War room, Tel: 03107606611/03106356611
SN Check point
1 If label of the MCB of existing Ericsson 2G,3G and DCS system are correctly
2 If the DC power cable for DCPD7 connected correctly
3 If DC power cable for RRU connected correctly
4 If optical fiber connected correctly ( There should not any cross with power and fiber).
5 If all board quantity are correct including Dummy
6 If alarm cable has been laid to existing DDF correctly with Labels
7 If CAT6 cable connected correctly with Labels
8 If labels of jumpers, fibers and power cable have been finished
9 Check transmission power ,IF,LAN cable connections
10 Check BLVD connections for transmission
11 Electrical and Mechnical tilt of installed Anteena.
Check the follow points and make sure all the points must be ready before swap.
Send message in Line to inform enter the site.
© ZTE Corporation. All rights reserved
7
Internal use only▲
3.1. Anteena Audit
• Check Physically the condition of anteena on site.
• Record electrical and Mechanical tilt.
• If E-tilt and M-Tilts are faulty inform responsible manager.
• Check the Anteena port condition if faulty inform the responsible manager.
© ZTE Corporation. All rights reserved
8
Internal use only▲
4. RRU Relations
4.1 Ready for swap
 Report to war room after everything are ready for swap.
 Team leader start swap receive war room order of starting swap.
Not More then 6 sectors:
•GSM 900 R8881/R8863 in order of cells (lower at first) takes 0, 1, and 2
•DCS1800 R8881/R8863 in order of cells (lower at first) takes 3, 4, and 5
© ZTE Corporation. All rights reserved
9
Internal use only▲
5. RRU Connectivity diagram
Before Antenna Swapping-
Trace the BTS and do the labeling on existing antenna for every sector.
1.Trace the RF cables from BTS to Antenna for each sector and identify the correct antenna and
sector.
Standard labeling to be done at Existing Antenna and its cables-
Color Labeling Standard for RF cable a (Feeder /Jumper near Antenna port)
A. 1st Sec GSM, For Jumper 900 (for Tx/Rx 1 string-Red and for Rx 2 String-Red)
1st Sec GSM, For Jumper 1800 (for Tx/Rx 3 string-Red and for Rx 4 String-Red)
B. 2nd Sec GSM, For Jumper 900 (for Tx/Rx 1 string-Yellow and for Rx 2 String-Yellow)
2nd Sec GSM, For Jumper 1800 (for Tx/Rx 3 string-Yellow and for Rx 4 String-Yellow)
C. 3rd Sec GSM, For Jumper 900 (for Tx/Rx 1 string-Blue and for Rx 2 string-Blue)
3rd Sec GSM, For Jumper 1800 (for Tx/Rx 3 string-Blue and for Rx 4 string-Blue)
Sector Identification Color Scheme
Sector 1
Sector 2
Sector 3
Before Installation of RRU and its power/optical cables/RF Jumpers
Do the Color Labeling before installation/Mounting RRU and its cables
For RRU 8863
1. 1st Sec RRU Power cable / OFC - 2 string -Red
2. 2nd Sec RRU Power cable / OFC - 2 string -Yellow
3. 3rd Sec RRU Power cable / OFC -2 string -Blue
For RRU 8881
1. 1st Sec RRU Power cable / OFC - 1 string -Red
2. 2nd Sec RRU Power cable / OFC- 1 string -Yellow
3. 3rd Sec RRU Power cable / OFC - 1 string -Blue
© ZTE Corporation. All rights reserved
12
Internal use only▲
Swap Solution Summary:
1. Reuse the existing antennas;
2. Reuse the existing AC power system
3. IDUs will be installed in the ZTE BC8910 cabinet
6. Swap Solution: Outdoor to Outdoor Swap
Notice : Any issues happen can not solve please contact site engineer to support on site.
© ZTE Corporation. All rights reserved
13
Internal use only▲
Swap Solution Summary:
1. Pre-install new rectifier and ZTE BTS(BC cabinet and RRUs) in the proposed location.
2. IDUs will remain in the shelter.
3. New Power system (ATS, DB and New Rectifier) should be installed before swap.
6.1. Indoor Scenario: Indoor Macro site swap to outdoor distributed site.
Notice : Any issues happen can not solve please contact site engineer to support on site.
© ZTE Corporation. All rights reserved
14
Internal use only▲
Swap Solution Summary:
For this scenario, we will use the BS8906+RRU to swap the original Micro BTS.
6.2. Indoor Micro site swap to Indoor distributed site
Notice : Any issues happen can not solve please contact site engineer to support on site.
© ZTE Corporation. All rights reserved
15
Internal use only▲
7. Connect external alarm cable
SN
Cable
Sequence
Definition DB25 Definition Color
1 SA-1 Door Open DB25_1/DB25_14 White-Blue
2 SA-2 Over Heat DB25_2/DB25_15
White-
Orange
3 SA-3 AC Power Fail DB25_3/DB25_16 White-Green
4 SA-4 Low Battery DB25_4/DB25_17 White-Brown
5 SA-5 DC Rectifier Fail DB25_5/DB25_18 Red-Blue
6 SA-6
Generator
Running
DB25_6/DB25_19 Red-Orange
7 SA-7 Generator Failed DB25_7/DB25_20 Red-Green
8 SA-8 Low Fuel DB25_8/DB25_21 Red-Brown
1. Disconnect existing Ericsson external alarm cable and make labelling.
2. Connect ZTE external alarm cable according to the follow definition.
3. Report to war room confirm the status.
© ZTE Corporation. All rights reserved
16
Internal use only▲
8. Site clearance
9. Cross feeder and VSWR alarm clearance
11. Leave Site
1. Make water proof for all connected jumpers & feeders, power cable.
2. Seal the disconnected feeder ,jumper connectors and fix.
3. Proper routing of Fiber jumpers power cable
4. Clean the site and check the complete labeling before leaving
 After the completion of the above work and received the leave approval from war room can leave site.
 Send message in Line to inform leaving site.
Wait for cross feeder, Sector / Partial Swapping and VSWR confirmation from war room and confirmation from DT team.
 If the site have issues, swap team do rectification immediately until all issues solved.
 If the site have no issues, swap team can leave site.
10. Swap document
Team leader record all site information for ATP.
Thank you

Mais conteúdo relacionado

Mais procurados

Zte macro bts introduction
Zte macro bts  introductionZte macro bts  introduction
Zte macro bts introductionRamanuj Kumar
 
Huaweigsmgrfuintroduction 141128151840-conversion-gate02
Huaweigsmgrfuintroduction 141128151840-conversion-gate02Huaweigsmgrfuintroduction 141128151840-conversion-gate02
Huaweigsmgrfuintroduction 141128151840-conversion-gate02moussaCoulibaly22
 
Comparison between bts 312, 3012 and 3900 by usman zulfqar
Comparison between bts 312, 3012 and 3900 by usman zulfqarComparison between bts 312, 3012 and 3900 by usman zulfqar
Comparison between bts 312, 3012 and 3900 by usman zulfqarusman zulfqar
 
Ericsson TN Cards in Details
Ericsson TN Cards in DetailsEricsson TN Cards in Details
Ericsson TN Cards in Detailsibrahimnabil17
 
Huawei GSM Principles
Huawei GSM PrinciplesHuawei GSM Principles
Huawei GSM PrinciplesAchmad Fauzi
 
Microwave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware StructureMicrowave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware Structureibrahimnabil17
 
Ericsson Mini-link 6600 Nodes
Ericsson Mini-link 6600 NodesEricsson Mini-link 6600 Nodes
Ericsson Mini-link 6600 Nodesibrahimnabil17
 
Debashish Bhattacharya
Debashish  BhattacharyaDebashish  Bhattacharya
Debashish BhattacharyaVarun Chandra
 
Huaweiumtsnodebconfigurationprinciple 161222082051
Huaweiumtsnodebconfigurationprinciple 161222082051Huaweiumtsnodebconfigurationprinciple 161222082051
Huaweiumtsnodebconfigurationprinciple 161222082051moussaCoulibaly22
 
A glance over cellular Communication systems and BSS network equipment
A glance over cellular Communication systems and BSS network equipmentA glance over cellular Communication systems and BSS network equipment
A glance over cellular Communication systems and BSS network equipmentAhmed Nabeeh
 
Unicorn Wireless BTS/NodeB Installation Services
Unicorn Wireless BTS/NodeB Installation ServicesUnicorn Wireless BTS/NodeB Installation Services
Unicorn Wireless BTS/NodeB Installation Servicesdrottmayer
 
Huawei XPIC Hardware Connection
Huawei XPIC Hardware ConnectionHuawei XPIC Hardware Connection
Huawei XPIC Hardware Connectionibrahimnabil17
 
Ultrasite technical for 4op
Ultrasite technical for 4opUltrasite technical for 4op
Ultrasite technical for 4opTempus Telcosys
 
Nokia engineer basic_training_session_v1
Nokia engineer basic_training_session_v1Nokia engineer basic_training_session_v1
Nokia engineer basic_training_session_v1mohameddawood35
 
2.omd101010 bsc6000 hardware structure issue1.0
2.omd101010 bsc6000 hardware structure issue1.02.omd101010 bsc6000 hardware structure issue1.0
2.omd101010 bsc6000 hardware structure issue1.0moussaCoulibaly22
 
240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-trainingShelton Siziba
 
Presentation of NSN training
Presentation of NSN trainingPresentation of NSN training
Presentation of NSN trainingBhavin_Halani
 

Mais procurados (20)

Zte macro bts introduction
Zte macro bts  introductionZte macro bts  introduction
Zte macro bts introduction
 
Huaweigsmgrfuintroduction 141128151840-conversion-gate02
Huaweigsmgrfuintroduction 141128151840-conversion-gate02Huaweigsmgrfuintroduction 141128151840-conversion-gate02
Huaweigsmgrfuintroduction 141128151840-conversion-gate02
 
Comparison between bts 312, 3012 and 3900 by usman zulfqar
Comparison between bts 312, 3012 and 3900 by usman zulfqarComparison between bts 312, 3012 and 3900 by usman zulfqar
Comparison between bts 312, 3012 and 3900 by usman zulfqar
 
Ericsson TN Cards in Details
Ericsson TN Cards in DetailsEricsson TN Cards in Details
Ericsson TN Cards in Details
 
Huawei GSM Principles
Huawei GSM PrinciplesHuawei GSM Principles
Huawei GSM Principles
 
Microwave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware StructureMicrowave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware Structure
 
Ericsson Mini-link 6600 Nodes
Ericsson Mini-link 6600 NodesEricsson Mini-link 6600 Nodes
Ericsson Mini-link 6600 Nodes
 
Debashish Bhattacharya
Debashish  BhattacharyaDebashish  Bhattacharya
Debashish Bhattacharya
 
Huaweiumtsnodebconfigurationprinciple 161222082051
Huaweiumtsnodebconfigurationprinciple 161222082051Huaweiumtsnodebconfigurationprinciple 161222082051
Huaweiumtsnodebconfigurationprinciple 161222082051
 
A glance over cellular Communication systems and BSS network equipment
A glance over cellular Communication systems and BSS network equipmentA glance over cellular Communication systems and BSS network equipment
A glance over cellular Communication systems and BSS network equipment
 
Ericsson RBS 6000
Ericsson RBS 6000Ericsson RBS 6000
Ericsson RBS 6000
 
Unicorn Wireless BTS/NodeB Installation Services
Unicorn Wireless BTS/NodeB Installation ServicesUnicorn Wireless BTS/NodeB Installation Services
Unicorn Wireless BTS/NodeB Installation Services
 
Huawei XPIC Hardware Connection
Huawei XPIC Hardware ConnectionHuawei XPIC Hardware Connection
Huawei XPIC Hardware Connection
 
3G Product Summary
3G Product Summary3G Product Summary
3G Product Summary
 
Ultrasite technical for 4op
Ultrasite technical for 4opUltrasite technical for 4op
Ultrasite technical for 4op
 
Nokia engineer basic_training_session_v1
Nokia engineer basic_training_session_v1Nokia engineer basic_training_session_v1
Nokia engineer basic_training_session_v1
 
Antenna Installation Engineering.
Antenna Installation Engineering.Antenna Installation Engineering.
Antenna Installation Engineering.
 
2.omd101010 bsc6000 hardware structure issue1.0
2.omd101010 bsc6000 hardware structure issue1.02.omd101010 bsc6000 hardware structure issue1.0
2.omd101010 bsc6000 hardware structure issue1.0
 
240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training
 
Presentation of NSN training
Presentation of NSN trainingPresentation of NSN training
Presentation of NSN training
 

Semelhante a Mobilink Project On Site Swap SOP

Gsm 2 g rollout dt
Gsm 2 g rollout dtGsm 2 g rollout dt
Gsm 2 g rollout dtINAYAT ULHAQ
 
IC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex companyIC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex companyPeter Ivas
 
cisco-air-ant2535sdw-r-datasheet.pdf
cisco-air-ant2535sdw-r-datasheet.pdfcisco-air-ant2535sdw-r-datasheet.pdf
cisco-air-ant2535sdw-r-datasheet.pdfHi-Network.com
 
IBS TRAINING(new).pptx
IBS TRAINING(new).pptxIBS TRAINING(new).pptx
IBS TRAINING(new).pptxHussienEndris1
 
IRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_FinalIRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_FinalMichael Bardwell
 
SON Server Web KPI Portal 4G DT Analysis Cases Module.pptx
SON Server Web KPI Portal  4G DT Analysis Cases Module.pptxSON Server Web KPI Portal  4G DT Analysis Cases Module.pptx
SON Server Web KPI Portal 4G DT Analysis Cases Module.pptxssuser2b76bb
 
Edwards Signaling FDACT Installation Manual
Edwards Signaling FDACT Installation ManualEdwards Signaling FDACT Installation Manual
Edwards Signaling FDACT Installation ManualJMAC Supply
 
V350-35-RA22_INSTAL-GUIDE_10-08
V350-35-RA22_INSTAL-GUIDE_10-08V350-35-RA22_INSTAL-GUIDE_10-08
V350-35-RA22_INSTAL-GUIDE_10-08Cara Bereck Levy
 
eNB Introduction and I&C.tejas networkpptx
eNB Introduction and I&C.tejas networkpptxeNB Introduction and I&C.tejas networkpptx
eNB Introduction and I&C.tejas networkpptxunnikrishnanM25
 
Andrew E15Z01P13
Andrew E15Z01P13Andrew E15Z01P13
Andrew E15Z01P13savomir
 
Andrew DBXLH-9090A-R2M
Andrew DBXLH-9090A-R2MAndrew DBXLH-9090A-R2M
Andrew DBXLH-9090A-R2Msavomir
 
3 g rf_optimisation_basics
3 g rf_optimisation_basics3 g rf_optimisation_basics
3 g rf_optimisation_basicsMd.Akm Sahansha
 

Semelhante a Mobilink Project On Site Swap SOP (20)

Gsm 2 g rollout dt
Gsm 2 g rollout dtGsm 2 g rollout dt
Gsm 2 g rollout dt
 
Tk116 user mannual min gsp vehicle tracker
Tk116 user mannual min gsp vehicle trackerTk116 user mannual min gsp vehicle tracker
Tk116 user mannual min gsp vehicle tracker
 
IC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex companyIC Adapters & Interposers | Interconnect Systems ISI - a Molex company
IC Adapters & Interposers | Interconnect Systems ISI - a Molex company
 
cisco-air-ant2535sdw-r-datasheet.pdf
cisco-air-ant2535sdw-r-datasheet.pdfcisco-air-ant2535sdw-r-datasheet.pdf
cisco-air-ant2535sdw-r-datasheet.pdf
 
IBS TRAINING(new).pptx
IBS TRAINING(new).pptxIBS TRAINING(new).pptx
IBS TRAINING(new).pptx
 
IRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_FinalIRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_Final
 
Remotely cut off engine devices
Remotely cut off engine devicesRemotely cut off engine devices
Remotely cut off engine devices
 
SON Server Web KPI Portal 4G DT Analysis Cases Module.pptx
SON Server Web KPI Portal  4G DT Analysis Cases Module.pptxSON Server Web KPI Portal  4G DT Analysis Cases Module.pptx
SON Server Web KPI Portal 4G DT Analysis Cases Module.pptx
 
Vfd l m-en_20030522
Vfd l m-en_20030522Vfd l m-en_20030522
Vfd l m-en_20030522
 
Delta vfd lfrekv
Delta vfd lfrekvDelta vfd lfrekv
Delta vfd lfrekv
 
Edwards Signaling FDACT Installation Manual
Edwards Signaling FDACT Installation ManualEdwards Signaling FDACT Installation Manual
Edwards Signaling FDACT Installation Manual
 
V350-35-RA22_INSTAL-GUIDE_10-08
V350-35-RA22_INSTAL-GUIDE_10-08V350-35-RA22_INSTAL-GUIDE_10-08
V350-35-RA22_INSTAL-GUIDE_10-08
 
Nemo fsr1 scanner user manual
Nemo fsr1 scanner user manualNemo fsr1 scanner user manual
Nemo fsr1 scanner user manual
 
eNB Introduction and I&C.tejas networkpptx
eNB Introduction and I&C.tejas networkpptxeNB Introduction and I&C.tejas networkpptx
eNB Introduction and I&C.tejas networkpptx
 
Andrew E15Z01P13
Andrew E15Z01P13Andrew E15Z01P13
Andrew E15Z01P13
 
LTE 4G FDD GPS tracker TK419 -Eelink
LTE 4G FDD GPS tracker TK419 -Eelink LTE 4G FDD GPS tracker TK419 -Eelink
LTE 4G FDD GPS tracker TK419 -Eelink
 
Tx7201 zone monitor module
Tx7201 zone monitor moduleTx7201 zone monitor module
Tx7201 zone monitor module
 
Andrew DBXLH-9090A-R2M
Andrew DBXLH-9090A-R2MAndrew DBXLH-9090A-R2M
Andrew DBXLH-9090A-R2M
 
3 g rf_optimisation_basics
3 g rf_optimisation_basics3 g rf_optimisation_basics
3 g rf_optimisation_basics
 
Sony nex5manual
Sony nex5manualSony nex5manual
Sony nex5manual
 

Mobilink Project On Site Swap SOP

  • 1. Mobilink Project On Site Swap SOPMobilink Project On Site Swap SOP
  • 2. © ZTE Corporation. All rights reserved 2 Internal use only▲ Red Lines All the rules must be follow otherwise will get punishment ! Prohibit entering site besides receiving war room approval . Top 1 Work must with safety helmet, hat torch and safety belt. Top 2 Prohibit touch any unconcerned existing equipment. Top 3 Prohibit phone power off, must have the another SIM card of other operator. Top 4 Prohibit leaving site besides receiving war room approval . Top 5 Pre swap preparation and data collection of all existing system with snaps. Top 6 ZTE unused material must picked from site through MMAF submission after swap. Top 7 E/// dismantled equipment MMAF must be submitted along with equipment pictures. Top 8 BSS engineer will leave the site after confirmation by RF of successful site DT . Top 9 BSS engineer will leave the site after site alarm verification from PMCL OAN hotline.
  • 3. © ZTE Corporation. All rights reserved 3 Internal use only▲ 11 steps lead swap to be successfully Notice Any access issue please contact War room: 03107606611/03106356611 Any technical issues (RF/Optical fiber)can not solved please contact site engineer to support on site immediately. Any material issues can not solved please contact site engineer to support on site immediately. Team leader must report to Mobilink NOC while enter and leaving site.
  • 4. © ZTE Corporation. All rights reserved 4 Internal use only▲ 1. Documents BBU and RRU connection scenario Provider: Yu Guang Hui/War Room:03155104495/0310760661 – 《 SDR Commissioning solution 》 Provider: Yu Guang Hui/War Room:03155104495/0310760661 – 《 Label standard 》 Provider: Atif: 03459889898 《 BOM & DO 》 Provider: Saqib: 03458577070,Asim: 0315-7117708 《 Communication Matrix 》 Provider: Swap Team Lead 2.Material ( Each site ) – On site Material Box check to ensure all the required material is available on site and if not then Escalate to respective Team Leader. – Spares requirement must be calculated and in hand with site engineer for on spot Rectification if any equipment got faulty. 1. Swap preparation Notice : Follow preparation must be ready before go to the site. 3.Work order from Customer: Call NOC and Back office team to proceed further Communication Plan
  • 5. © ZTE Corporation. All rights reserved 5 Internal use only▲ Cable stripping tool Cable Cutter RJ45 crimping tool Hex/Allen Key Sets Crone (LSA) Level Ruler (water pass) Ethernet Cable Tester (Kabel LAN Tester) Cross & Slotted screwdriver (Obeng Lengkap) Safety helmet Drill & Drill Bits (Alat Bor & Mata Bor) Safety Belt Multifunctional Crimping tools Adjustable spanners (Kunci Inggris) Dust Cleaner/vacuum cleaner Safety GlovesHat torch (Lampu Kepala) 4. Tools ( Also include heat Gun) LAN cable Laptop Camera
  • 6. © ZTE Corporation. All rights reserved 6 Internal use only▲ 2. Site access 3. Environment double checking Night Swap Arrival must before 21:00 Day Swap Arrival must before 6:00 Notice : Any access issue please contact War room, Tel: 03107606611/03106356611 SN Check point 1 If label of the MCB of existing Ericsson 2G,3G and DCS system are correctly 2 If the DC power cable for DCPD7 connected correctly 3 If DC power cable for RRU connected correctly 4 If optical fiber connected correctly ( There should not any cross with power and fiber). 5 If all board quantity are correct including Dummy 6 If alarm cable has been laid to existing DDF correctly with Labels 7 If CAT6 cable connected correctly with Labels 8 If labels of jumpers, fibers and power cable have been finished 9 Check transmission power ,IF,LAN cable connections 10 Check BLVD connections for transmission 11 Electrical and Mechnical tilt of installed Anteena. Check the follow points and make sure all the points must be ready before swap. Send message in Line to inform enter the site.
  • 7. © ZTE Corporation. All rights reserved 7 Internal use only▲ 3.1. Anteena Audit • Check Physically the condition of anteena on site. • Record electrical and Mechanical tilt. • If E-tilt and M-Tilts are faulty inform responsible manager. • Check the Anteena port condition if faulty inform the responsible manager.
  • 8. © ZTE Corporation. All rights reserved 8 Internal use only▲ 4. RRU Relations 4.1 Ready for swap  Report to war room after everything are ready for swap.  Team leader start swap receive war room order of starting swap. Not More then 6 sectors: •GSM 900 R8881/R8863 in order of cells (lower at first) takes 0, 1, and 2 •DCS1800 R8881/R8863 in order of cells (lower at first) takes 3, 4, and 5
  • 9. © ZTE Corporation. All rights reserved 9 Internal use only▲ 5. RRU Connectivity diagram
  • 10. Before Antenna Swapping- Trace the BTS and do the labeling on existing antenna for every sector. 1.Trace the RF cables from BTS to Antenna for each sector and identify the correct antenna and sector. Standard labeling to be done at Existing Antenna and its cables- Color Labeling Standard for RF cable a (Feeder /Jumper near Antenna port) A. 1st Sec GSM, For Jumper 900 (for Tx/Rx 1 string-Red and for Rx 2 String-Red) 1st Sec GSM, For Jumper 1800 (for Tx/Rx 3 string-Red and for Rx 4 String-Red) B. 2nd Sec GSM, For Jumper 900 (for Tx/Rx 1 string-Yellow and for Rx 2 String-Yellow) 2nd Sec GSM, For Jumper 1800 (for Tx/Rx 3 string-Yellow and for Rx 4 String-Yellow) C. 3rd Sec GSM, For Jumper 900 (for Tx/Rx 1 string-Blue and for Rx 2 string-Blue) 3rd Sec GSM, For Jumper 1800 (for Tx/Rx 3 string-Blue and for Rx 4 string-Blue) Sector Identification Color Scheme Sector 1 Sector 2 Sector 3
  • 11. Before Installation of RRU and its power/optical cables/RF Jumpers Do the Color Labeling before installation/Mounting RRU and its cables For RRU 8863 1. 1st Sec RRU Power cable / OFC - 2 string -Red 2. 2nd Sec RRU Power cable / OFC - 2 string -Yellow 3. 3rd Sec RRU Power cable / OFC -2 string -Blue For RRU 8881 1. 1st Sec RRU Power cable / OFC - 1 string -Red 2. 2nd Sec RRU Power cable / OFC- 1 string -Yellow 3. 3rd Sec RRU Power cable / OFC - 1 string -Blue
  • 12. © ZTE Corporation. All rights reserved 12 Internal use only▲ Swap Solution Summary: 1. Reuse the existing antennas; 2. Reuse the existing AC power system 3. IDUs will be installed in the ZTE BC8910 cabinet 6. Swap Solution: Outdoor to Outdoor Swap Notice : Any issues happen can not solve please contact site engineer to support on site.
  • 13. © ZTE Corporation. All rights reserved 13 Internal use only▲ Swap Solution Summary: 1. Pre-install new rectifier and ZTE BTS(BC cabinet and RRUs) in the proposed location. 2. IDUs will remain in the shelter. 3. New Power system (ATS, DB and New Rectifier) should be installed before swap. 6.1. Indoor Scenario: Indoor Macro site swap to outdoor distributed site. Notice : Any issues happen can not solve please contact site engineer to support on site.
  • 14. © ZTE Corporation. All rights reserved 14 Internal use only▲ Swap Solution Summary: For this scenario, we will use the BS8906+RRU to swap the original Micro BTS. 6.2. Indoor Micro site swap to Indoor distributed site Notice : Any issues happen can not solve please contact site engineer to support on site.
  • 15. © ZTE Corporation. All rights reserved 15 Internal use only▲ 7. Connect external alarm cable SN Cable Sequence Definition DB25 Definition Color 1 SA-1 Door Open DB25_1/DB25_14 White-Blue 2 SA-2 Over Heat DB25_2/DB25_15 White- Orange 3 SA-3 AC Power Fail DB25_3/DB25_16 White-Green 4 SA-4 Low Battery DB25_4/DB25_17 White-Brown 5 SA-5 DC Rectifier Fail DB25_5/DB25_18 Red-Blue 6 SA-6 Generator Running DB25_6/DB25_19 Red-Orange 7 SA-7 Generator Failed DB25_7/DB25_20 Red-Green 8 SA-8 Low Fuel DB25_8/DB25_21 Red-Brown 1. Disconnect existing Ericsson external alarm cable and make labelling. 2. Connect ZTE external alarm cable according to the follow definition. 3. Report to war room confirm the status.
  • 16. © ZTE Corporation. All rights reserved 16 Internal use only▲ 8. Site clearance 9. Cross feeder and VSWR alarm clearance 11. Leave Site 1. Make water proof for all connected jumpers & feeders, power cable. 2. Seal the disconnected feeder ,jumper connectors and fix. 3. Proper routing of Fiber jumpers power cable 4. Clean the site and check the complete labeling before leaving  After the completion of the above work and received the leave approval from war room can leave site.  Send message in Line to inform leaving site. Wait for cross feeder, Sector / Partial Swapping and VSWR confirmation from war room and confirmation from DT team.  If the site have issues, swap team do rectification immediately until all issues solved.  If the site have no issues, swap team can leave site. 10. Swap document Team leader record all site information for ATP.